A hoisting mechanism for BGL insulation board construction
By combining the lifting cable winches and stabilizing cable winches at both ends of the shaft, the problem of panel swaying during BGL insulation board construction was solved, achieving stability and convenient alignment adjustment during the hoisting process.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- ZHONG TIE CHENG JIAN JI TUAN HUA DONG JIAN SHE YOU XIAN GONG SI
- Filing Date
- 2025-08-06
- Publication Date
- 2026-05-26
AI Technical Summary
During the installation of BGL insulation boards, the boards are prone to swaying when lifted, which can cause the connection between the slings and the boards to detach, potentially causing the boards to fall off or collide with the wall, and making it difficult to reposition them.
The design employs a combination of lifting cable winches and stabilizing cable winches at both ends of the shaft. The lifting cable winch lifts the sheet material to the installation position, and the stabilizing cable winch straightens the taut lifting cable, allowing the sliding sleeve to slide along the stabilizing cable, thus ensuring the stability of the sheet material.
It effectively prevents the panels from shaking, ensuring stability and ease of alignment during hoisting, and avoiding panel detachment and impact.
Smart Images

Figure CN224279615U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of construction hoisting technology, and in particular relates to a hoisting mechanism for BGL insulation board construction. Background Technology
[0002] When installing BGL insulation boards, a crane is needed to lift the boards to the wall where they are to be installed. The position and angle of the boards are then adjusted to align them with the desired location before installation by construction workers. During the lifting process, the boards are prone to swaying, which can cause the connection between the slings and the boards to detach, resulting in the boards falling off. The swaying can also cause the boards to collide with the wall, damaging either the boards or the wall. Furthermore, the swaying makes it difficult to align the boards properly, complicating the installation process.
[0003] To address these issues, we provide a hoisting mechanism for BGL insulation board construction. Utility Model Content
[0004] The purpose of this utility model is to provide a hoisting mechanism for BGL insulation board construction. A lifting cable winch is fixedly installed on the outer sides of both ends of a shaft. The upper end of the shaft adapter sleeve, which is rotatably connected to both ends of the shaft, is slidably mounted on a horizontal slide rail. The horizontal slide rail is set on the wall or roof where the BGL insulation board needs to be installed. The lifting cable in the lifting cable winch is connected to the BGL insulation board. Rotating the shaft causes the lifting cable winch to wind up the lifting cable, raising the board to the desired installation position. The shaft is then slid laterally to slide the BGL insulation board, hoisted by the lifting cable, horizontally to the desired installation position. Two stabilizing cable winches are rotatably installed on the upper end of a trolley. The stabilizing cables in the two stabilizing cable winches are fixedly connected to the sides of the two lifting cable winches. One side of the sliding sleeve, which is fixedly connected to the lower end of the lifting cable, is slidably fitted onto the outside of the stabilizing cable. Rotating the stabilizing cable winch straightens and tightens the stabilizing cable, allowing the lower sliding sleeve of the lifting cable to slide along the stabilizing cable when the board is hoisted, preventing the board from swaying.
[0005] To solve the above-mentioned technical problems, this utility model is achieved through the following technical solution:
[0006] This utility model relates to a hoisting mechanism for BGL insulation board construction, comprising a trolley, a horizontal slide rail, and a shaft. A shaft adapter sleeve is rotatably sleeved on the outer sides of both ends of the shaft. The upper end of the shaft adapter sleeve is sleeved on the horizontal slide rail. A lifting cable winch is fixedly installed at each end of the shaft, with a lifting cable wound on the winch. A sliding sleeve is fixedly sleeved at the end of the lifting cable. Stabilizing cable winches are rotatably installed on both sides of the upper end face of the trolley, with stabilizing cables wound inside the stabilizing cable winches. The upper ends of the stabilizing cables in the two stabilizing cable winches are fixedly connected to the sides of the two lifting cable winches, and one side of each sliding sleeve is slidably sleeved on the outer side of the two stabilizing cables.
[0007] A further feature of this invention is that a lifting hook is fixedly provided on the lower end face of the sliding sleeve.
[0008] A further feature of this invention is that a drive motor is fixedly mounted on the end face of one of the shaft adapter sleeves away from the lifting cable winch, and the output shaft of the drive motor is connected to the end face of the shaft for transmission.
[0009] A further feature of this invention is that the upper end plate of the shaft adapter sleeve has a through-hole for a slide rail, and the horizontal slide rail is slidably sleeved within the slide rail notch of the two shaft adapter sleeves.
[0010] A further feature of this invention is that vertical side plates are fixedly provided on both sides of the slide rail notch, and a pulley is rotatably installed between the two vertical side plates, with the lower end of the pulley rollingly sleeved in the upper end groove of the horizontal slide rail.
[0011] A further feature of this invention is that a connecting lug is fixedly provided at the upper end of the shaft adapter sleeve, and a connecting rod is fixedly connected between the connecting lugs at the upper ends of the two shaft adapter sleeves.
[0012] A further feature of this invention is that vertical rods are fixedly provided on the upper surfaces of both ends of the horizontal slide rail, and a suspension plate is fixedly provided on the upper ends of the vertical rods at both ends.
[0013] This utility model has the following beneficial effects:
[0014] 1. This utility model involves fixing a lifting cable winch to the outer sides of both ends of a shaft. The upper end of the shaft adapter sleeve, which is rotatably connected to both ends of the shaft, is slidably mounted on a horizontal slide rail. The horizontal slide rail is set on the wall or roof where BGL insulation boards need to be installed. The lifting cable in the lifting cable winch is connected to the BGL insulation board. Rotating the shaft causes the lifting cable winch to wind up the lifting cable, raising the board to the required installation position. The shaft is then slid laterally to slide the BGL insulation board, which is hoisted by the lifting cable, horizontally to the required installation position.
[0015] 2. This utility model involves rotating and installing two stabilizing cable winches on the upper end of the trolley, fixing the stabilizing cables of the two stabilizing cable winches to the sides of the two lifting cable winches respectively, and sliding one side of the sliding sleeve fixedly sleeved at the lower end of the lifting cable onto the outside of the stabilizing cable. Rotating the stabilizing cable winches straightens and tightens the stabilizing cable, so that when the lifting cable lifts the plate, the sliding sleeve at the lower end slides along the stabilizing cable, preventing the plate from shaking. Attached Figure Description
[0016] To more clearly illustrate the technical solutions of the embodiments of this utility model, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0017] Figure 1 This is a structural schematic diagram of a hoisting mechanism for BGL insulation board construction.
[0018] Figure 2 This is a schematic diagram of the drive motor and the shaft adapter sleeve.
[0019] Figure 3 This is a schematic diagram of the structure of the shaft adapter sleeve and pulley.
[0020] Figure 4 This is a schematic diagram of the structure of the shaft adapter sleeve and the horizontal slide rail.
[0021] Figure 5 This is a schematic diagram of the structure of the horizontal slide rail and the suspension plate.
[0022] The attached diagram lists the components represented by each number as follows:
[0023] 1-Trolley, 101-Stabilizing cable winch, 101a-Stabilizing cable, 2-Horizontal slide rail, 201-Vertical rod, 201a-Suspension plate, 3-Shaft rod, 301-Shaft rod adapter sleeve, 301a-Drive motor, 301b-Slide rail notch, 301b-1-Vertical side plate, 301b-2-Pulley, 301c-Connecting ear, 301c-1-Connecting rod, 302-Lifting cable winch, 302a-Lifting cable, 302b-Sliding sleeve, 302b-1-Lifting hook. Detailed Implementation
[0024] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present utility model.
[0025] Example 1
[0026] Please see Figures 1 to 3This utility model relates to a hoisting mechanism for BGL insulation board construction, comprising a trolley 1, a horizontal slide rail 2, and a shaft 3. A lifting cable winch 302 is fixedly installed on the outer sides of both ends of the shaft 3. The upper ends of the shaft adapter sleeves 301, which are rotatably connected to both ends of the shaft 3, are slidably mounted on the horizontal slide rail 2. The horizontal slide rail 2 is positioned on the wall or roof where the BGL insulation board needs to be installed. The lifting cable 302a in the lifting cable winch 302 is connected to the BGL insulation board. Rotating the shaft 3 causes the lifting cable winch 302 to wind up the lifting cable 302a, raising the board to the required installation position. The shaft 3 is then slid laterally to lift the board. The BGL insulation board, lifted by the lifting cable 302a, is slid horizontally to the required installation position. Two stabilizing cable winches 101 are rotated and installed on the upper end of the trailer 1. The stabilizing cables 101a of the two stabilizing cable winches 101 are fixedly connected to the sides of the two lifting cable winches 302 respectively. The sliding sleeve 302b, which is fixedly sleeved at the lower end of the lifting cable 302a, is slidably sleeved on the outside of the stabilizing cable 101a. The stabilizing cable winch 101 is rotated to straighten and tighten the stabilizing cable 101a. When the lifting cable 302a lifts the board, the sliding sleeve 302b at the lower end slides along the stabilizing cable 101a, so that the board does not shake.
[0027] Specifically, a shaft adapter sleeve 301 is rotatably sleeved on the outer side of each end of the shaft 3. The upper end of the shaft adapter sleeve 301 is sleeved on the horizontal slide rail 2. A lifting cable winch 302 is fixedly installed on each end of the shaft 3. A lifting cable 302a is wound on the lifting cable winch 302. A sliding sleeve 302b is fixedly sleeved at the end of the lifting cable 302a. A stabilizing cable winch 101 is rotatably installed on both sides of the upper end face of the trolley 1. A stabilizing cable 101a is wound inside the stabilizing cable winch 101. The upper ends of the stabilizing cables 101a in the two stabilizing cable winches 101 are fixedly connected to the sides of the two lifting cable winches 302 respectively. One side of each sliding sleeve 302b is slidably sleeved on the outer side of the two stabilizing cables 101a respectively.
[0028] Furthermore, a lifting hook 302b-1 is fixedly provided on the lower end face of the sliding sleeve 302b for hooking up the plate.
[0029] Furthermore, a drive motor 301a is fixedly installed on the end face of one of the shaft adapter sleeves 301 away from the lifting cable winch 302. The output shaft of the drive motor 301a is connected to the end face of the shaft 3 for transmission. The drive motor 301a drives the shaft 3 to drive the lifting cable winch 302 to rotate, so that the lifting cable 302a is wound up and lifted.
[0030] Furthermore, the upper end plate of the shaft adapter sleeve 301 is provided with a slide rail notch 301b, and the horizontal slide rail 2 is slidably sleeved in the slide rail notch 301b of the two shaft adapter sleeves 301.
[0031] Furthermore, vertical side plates 301b-1 are fixed on both sides of the slide rail notch 301b, and pulleys 301b-2 are rotatably installed between the two vertical side plates 301b-1. The lower end of the pulley 301b-2 is rolled and sleeved in the upper end of the horizontal slide rail 2, pushing the shaft rotating sleeve 301, so that the pulley 301b-2 slides in the upper end of the horizontal slide rail 2, thereby adjusting the horizontal position of the BGL insulation board below.
[0032] The operation process in this embodiment is as follows:
[0033] Stack the BGL insulation boards to be installed on top of the trolley 1. Hook the lifting hooks 302b-1 at the lower end of the two sliding sleeves 302b with the holes on the side of the boards. The output shaft of the drive motor 301a is connected to the end face of the shaft 3. The drive motor 301a drives the shaft 3 to rotate the lifting cable winch 302, so that the lifting cable 302a is wound up and lifted. The lifting cable 302a lifts the boards to the required installation height. During the lifting process, the sliding sleeves 302b slide vertically along the stabilizing cable 101a, so that the lifting cable 302a does not shake when lifting the boards. The horizontal sliding shaft adapter sleeve 301 allows the pulley 301b-2 to slide in the groove at the upper end of the horizontal slide rail 2, thereby adjusting the horizontal position of the BGL insulation boards below.
[0034] Example 2
[0035] Please see Figures 1 to 5 Based on Embodiment 1, a connecting rod 301c-1 is fixedly connected to the upper end of the two shaft adapter sleeves 301, so that the two shaft adapter sleeves 301 can move simultaneously when sliding.
[0036] Specifically, a connecting lug 301c is fixedly provided at the upper end of the shaft adapter sleeve 301, and a connecting rod 301c-1 is fixedly connected between the connecting lugs 301c at the upper ends of the two shaft adapter sleeves 301.
[0037] Furthermore, vertical rods 201 are fixedly installed on the upper surfaces of both ends of the horizontal slide rail 2, and a suspension plate 201a is fixedly installed on the upper end of the vertical rods 201 at both ends. The suspension plate 201a is used to install on the upper part of the wall on the roof.
[0038] The operation process in this embodiment is as follows:
[0039] The suspension plate 201a is fixedly installed on the upper part of the wall on the roof. After the lifting cable 302a hoists the plate to the required installation height, the connecting rod 301c-1 is pushed to make the two shaft adapter sleeves 301 slide on the horizontal slide rail 2 at the same time, so that the plate slides horizontally to the required installation position.
[0040] In the description of this specification, references to terms such as "an embodiment," "example," "specific example," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
Claims
1. A hoisting mechanism for BGL insulation board construction, comprising a trolley (1), a horizontal slide rail (2), and a shaft (3), characterized in that: A shaft adapter sleeve (301) is rotatably sleeved on the outer side of each end of the shaft (3). The upper end of the shaft adapter sleeve (301) is sleeved on the horizontal slide rail (2). A lifting cable winch (302) is fixedly installed on each end of the shaft (3). A lifting cable (302a) is wound on the lifting cable winch (302). A sliding sleeve (302b) is fixedly sleeved at the end of the lifting cable (302a). A stabilizing cable winch (101) is rotatably installed on both sides of the upper end face of the trolley (1). A stabilizing cable (101a) is wound inside the stabilizing cable winch (101). The upper ends of the stabilizing cables (101a) in the two stabilizing cable winches (101) are fixedly connected to the sides of the two lifting cable winches (302). One side of the two sliding sleeves (302b) is slidably sleeved on the outer side of the two stabilizing cables (101a).
2. The hoisting mechanism for BGL insulation board construction according to claim 1, characterized in that: The lower end face of the sliding sleeve (302b) is fixed with a lifting hook (302b-1).
3. The hoisting mechanism for BGL insulation board construction according to claim 2, characterized in that: One of the shaft adapter sleeves (301) is fixedly equipped with a drive motor (301a) on the end face away from the lifting cable winch (302), and the output shaft of the drive motor (301a) is connected to the end face of the shaft (3) for transmission.
4. The hoisting mechanism for BGL insulation board construction according to claim 3, characterized in that: The upper end plate of the shaft adapter sleeve (301) is provided with a slide rail notch (301b), and the horizontal slide rail (2) is slidably sleeved in the slide rail notch (301b) of the two shaft adapter sleeves (301).
5. The hoisting mechanism for BGL insulation board construction according to claim 4, characterized in that: Vertical side plates (301b-1) are fixed on both sides of the slide rail notch (301b), and a pulley (301b-2) is rotatably installed between the two vertical side plates (301b-1). The lower end of the pulley (301b-2) is rolled and sleeved in the upper end groove of the horizontal slide rail (2).
6. The hoisting mechanism for BGL insulation board construction according to claim 3, characterized in that: The upper end of the shaft adapter sleeve (301) is fixedly provided with a connecting ear (301c), and a connecting rod (301c-1) is fixedly connected between the connecting ears (301c) at the upper ends of the two shaft adapter sleeves (301).
7. The hoisting mechanism for BGL insulation board construction according to claim 6, characterized in that: Vertical rods (201) are fixedly provided on the upper surfaces of both ends of the horizontal slide rail (2), and a suspension plate (201a) is fixedly provided on the upper end of the vertical rods (201) at both ends.