A type of miscellaneous fill soil support structure

By designing a return component on the self-drilling anchor and utilizing the reinforcing fluid in the static pressure compaction hole, the problems of cement slurry waste and poor support effect in the construction of miscellaneous fill soil were solved, achieving efficient use of materials and structural stability, and avoiding pit wall collapse.

CN224982200UActive Publication Date: 2026-11-17NORTHWEST RES INST OF ENG INVESTIGATIONS & DESIGN
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522758302.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-26
Publication Date
2026-11-17
Estimated Expiration
2035-12-26

AI Technical Summary

Technical Problem

Traditional support structures suffer from problems such as difficulty in drilling holes, poor support effect, low construction efficiency, and waste of cement slurry in the construction of miscellaneous fill soil.

Method used

A miscellaneous fill support structure is designed. By adding a return component to the self-drilling anchor, the cement grout overflowing during the grouting process is used to reinforce the anchor. The static pressure compaction hole and the reinforcement liquid are used to form a reinforcement panel to jointly resist the lateral pressure of the foundation pit.

Benefits of technology

This approach enabled the effective use of cement grout, enhanced the stability of the support structure, reduced material waste, improved construction efficiency, and prevented pit wall collapse through the combination of reinforcing liquid and static pressure compaction holes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982200U_ABST
    Figure CN224982200U_ABST
Patent Text Reader

Abstract

This utility model relates to the field of foundation pit support, specifically to a support structure for miscellaneous fill soil. The self-drilling anchor bolt includes a baffle plate, within which a return assembly for the secondary use of cement slurry is provided. The return assembly includes a first chamber, with a second chamber fixedly connected to the top wall of the first chamber. The top wall of the first chamber has a through hole communicating with the second chamber. An inlet is connected to the inner wall of the first chamber on the side closest to the miscellaneous fill soil pit. A warning block is slidably connected to the inner wall of the first chamber, and a warning opening corresponding to the warning block is located on the side of the first chamber away from the inlet. This utility model, by incorporating the return assembly, utilizes the cement slurry flowing out during grouting, achieving both a warning effect and allowing excess cement slurry to be used to reinforce the anchor bolt, thus increasing the practicality of the support structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of foundation pit support, specifically to a miscellaneous fill soil support structure. Background Technology

[0002] With urban development, readily available natural flat sites are decreasing, and many projects need to be carried out on "filled land plots." The fill in these plots is mostly formed by historical accumulation or artificial landfill. Miscellaneous fill is not a natural soil layer, but a mixture of various wastes generated by human activities and soil. Due to the complex composition and dispersed structure of miscellaneous fill, without proper support, it is extremely prone to collapse, settlement, and other accidents during construction, directly threatening project safety and the surrounding environment.

[0003] Miscellaneous fill soil is characterized by its complex composition, uneven particle size, poor stability, and tendency to collapse. Traditional support structures often face problems such as difficulty in drilling, poor support effect, and low construction efficiency when dealing with this type of stratum. However, self-drilling anchor support, through its integrated design of "drilling-grouting-anchoring," specifically solves the core pain points of miscellaneous fill soil support.

[0004] Existing products, such as Hengnuo Anchoring R25 self-drilling anchors, require construction workers to connect the drilling rig to the anchor, align the rig with the preset hole, start the rig to drive the anchor deep into the fill soil, and then use a grouting machine to inject grout into the anchor. The cement grout flows out with the drill bit to fill the fill soil until it flows out through the baffle, at which point the grouting stops. When using this product to fill fill soil, excess cement grout flows out with the baffle, resulting in waste. Therefore, this utility model proposes a fill soil support structure to solve the above problems. Utility Model Content

[0005] To address the aforementioned problems, this utility model provides a miscellaneous fill soil support structure that utilizes a return component to reinforce anchor bolts by reusing the cement slurry flowing out during the grouting process.

[0006] To achieve the above objectives, the technical solution of this utility model is as follows: a miscellaneous fill soil support structure, including a miscellaneous fill soil pit, a plurality of static pressure compaction holes perpendicular to the miscellaneous fill soil pit are provided in the miscellaneous fill soil pit, each static pressure compaction hole is filled with reinforcing liquid, and each static pressure compaction hole is provided with a reinforcing steel pipe, the reinforcing steel pipes are combined to form a reinforcing panel, and a plurality of grouting holes penetrating the static pressure compaction holes are provided in the miscellaneous fill soil pit, each grouting hole is installed with a self-drilling anchor rod; The self-drilling anchor bolt includes a hollow anchor bolt and a baffle. The baffle is installed on the hollow anchor bolt and has a return assembly for secondary use of cement slurry inside. The return assembly includes a first chamber, and a second chamber is fixedly connected to the top wall of the first chamber. The top wall of the first chamber has a through hole communicating with the second chamber. The inner wall of the first chamber near the fill pit has a flow inlet. The first chamber has a prompt block that is slidably connected to the inner wall of the first chamber. The side of the first chamber away from the flow inlet has a prompt port corresponding to the prompt block. The inner wall of the second chamber near the fill pit has a one-way valve.

[0007] The technical principle of the above scheme is as follows: During the grouting process, cement slurry flows out from the grouting hole at the drill bit to fill the miscellaneous fill soil. After the cement slurry is filled, the excess cement slurry will flow into the first chamber through the inlet. The cement slurry entering the first chamber pushes the indicator block in the first chamber to extend along the indicator port to the outside of the device, indicating to the construction personnel that the grouting is completed. The remaining cement slurry flows into the second chamber through the through hole between the first chamber and the second chamber. The excess cement slurry flows out from the one-way valve in the second chamber and is used to reinforce the anchor rod.

[0008] The above approach has the following beneficial effects: 1. This solution utilizes the overflow cement slurry during grouting to reinforce the self-drilling anchor rod by adding a return component. This makes the support structure more stable without wasting any cement slurry. At the same time, the overflow cement slurry can be used to directly trigger the movement of the indicator block, which can promptly and fully indicate the filling status of the cement slurry.

[0009] 2. In this scheme, the static pressure compaction holes formed by static pressure compaction reduce the porosity of the fill soil, the reinforcement liquid and the reinforcement steel pipe form a rigid support, and the grout fills the intermediate stratum. The three work together to resist the lateral pressure of the foundation pit excavation and avoid the collapse of the pit wall.

[0010] Furthermore, the hollow anchor rod is connected in sequence along its axial direction to a grouting port, nut, washer, centering device, connecting sleeve and drill bit. A grouting hole is provided on one side of the drill bit, and a baffle is located between the washer and the centering device.

[0011] Beneficial effects: The self-drilling anchor rod body is drilled into the grouting hole between adjacent static pressure compaction holes by rotating the drill bit. The centering device ensures that the hollow anchor rod is centered in the grouting hole, and the connecting sleeve firmly connects the hollow anchor rod and the drill bit. Cement grout is delivered to the grouting hole on one side of the drill bit through the internal channel of the hollow anchor rod. The cement grout diffuses outward to the surrounding strata through the grouting hole. During the grouting process, the centering device ensures that the cement grout evenly coats the anchor rod.

[0012] Furthermore, the hollow anchor rod has an anti-corrosion sleeve on its outer wall, which is located between the centering device and the connecting sleeve.

[0013] Beneficial effects: Miscellaneous fill soil often contains corrosive media, and anti-corrosion sleeves can prevent the hollow anchor rods from rusting, thus extending the service life of the support.

[0014] Furthermore, the reinforcing fluid is composed of cement, clay, and water.

[0015] Beneficial effects: After the reinforcement liquid and grout solidify, they fill the pores and bind the mixed filler particles, which can enhance the integrity of the stratum. In addition, the reinforcement liquid uses a low-cost ratio of cement, clay and water, which reduces material consumption.

[0016] Furthermore, it is indicated that several springs are fixedly connected to the bottom wall of the block, and the top of each spring is fixedly connected to the inner wall of the first chamber near the inlet.

[0017] Beneficial effect: It limits the position of the indicator block when grouting is not in place, preventing the indicator block from accidentally sliding out.

[0018] Furthermore, the reinforcing steel pipe is either an H-beam or a round steel pipe.

[0019] Beneficial effects: The steel pipe is an H-beam or round steel pipe with a smooth surface, which reduces the resistance during extraction and facilitates separation.

[0020] Furthermore, a reflective marking block is provided at the end of the indicator block away from the spring.

[0021] Beneficial effect: The design of reflective marking blocks can increase the visibility of the marking blocks, thereby reducing accidents.

[0022] Furthermore, the side of the baffle away from the fill pit is equipped with an anti-slip coating.

[0023] Beneficial effect: It increases the friction of the baffle, thereby increasing the stability of the connection between the gasket and the baffle.

[0024] Furthermore, drainage channels are provided on the bottom wall of the fill pit.

[0025] Beneficial effects: If the fill soil accumulates water for a long time, it will generate lateral water pressure on the concrete surface or anchor rods, increasing the load on the support components. The drainage channel can significantly reduce this additional load by draining water and relieving pressure, avoiding surface cracking and anchor rod overload deformation, and making the support structure more stable.

[0026] Further: A sealing cap is provided on the grouting port.

[0027] Beneficial effect: After the subsequent grouting is completed, it is necessary to wait for the grout to solidify. At this time, the sealing cap can seal the grouting port and reduce the accidental leakage of grout.

[0028] Additional aspects and advantages of this invention will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. Attached Figure Description

[0029] Figure 1 This is a front sectional view of an embodiment of a miscellaneous fill soil support structure according to this utility model; Figure 2 This is a front view of a self-drilling anchor bolt according to an embodiment of a miscellaneous fill soil support structure of this utility model; Figure 3 This is a cross-sectional view of the second chamber of an embodiment of a miscellaneous fill soil support structure according to the present invention.

[0030] The reference numerals in the accompanying drawings of the instruction manual include: 1. Grouting port; 2. Hollow anchor rod; 3. Nut; 4. Washer; 5. Baffle; 6. Spring; 7. Centerer; 8. Anti-corrosion sleeve; 9. Connecting sleeve; 10. Drill bit; 11. Grout outlet; 12. Inlet; 13. First chamber; 14. Indicator block; 15. Through hole; 16. Second chamber; 17. Check valve; 18. Static pressure compaction hole; 19. Grouting hole; 20. Reinforcing steel pipe; 21. Drainage trough; 24. Indicator port. Detailed Implementation

[0031] The technical solution of this utility model will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this utility model. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this utility model.

[0032] In the description of this utility model, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the accompanying drawings and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance.

[0033] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0034] The following detailed description illustrates the specific implementation method: Example 1: As attached Figure 1 and attached Figure 3 As shown: A miscellaneous fill soil support structure includes a miscellaneous fill soil pit, with a plurality of static pressure compaction holes 18 perpendicular to the pit. The static pressure compaction holes 18 are filled with reinforcing fluid, and each static pressure compaction hole 18 is equipped with a reinforcing steel pipe 20. The reinforcing steel pipes 20 are assembled to form a reinforcing panel. The miscellaneous fill soil pit also has a plurality of grouting holes 19 penetrating the static pressure compaction holes 18, and each grouting hole 19 is equipped with a self-drilling anchor rod. The self-drilling anchor rod includes a hollow anchor rod 2 and a baffle plate 5, with the baffle plate 5 positioned on the hollow anchor rod 2. The reinforcing fluid is composed of cement, clay, and water, and the preferred ratio of cement, clay, and water is: cement 1: clay 6: water 5. The reinforcing steel pipe 20 is either an H-beam or a circular steel pipe. refer to Figure 2 The hollow anchor rod 2 shown is connected along its axial direction by a grouting port 1, a nut 3, a washer 4, a centering device 7, a connecting sleeve 9, and a drill bit 10. A grout outlet 11 is provided on one side of the drill bit 10, and a baffle 5 is located between the washer 4 and the centering device 7. The outer wall of the hollow anchor rod 2 is provided with an anti-corrosion sleeve 8, which is located between the centering device 7 and the connecting sleeve 9. In order to increase the stability of the fixation, the side of the baffle 5 away from the miscellaneous fill pit is provided with an anti-slip coating. A sealing cap is provided on the grouting port 1. The baffle 5 is equipped with a return assembly for the secondary use of cement slurry. The return assembly includes a first chamber 13, and a second chamber 16 is fixedly connected to the top wall of the first chamber 13. The top wall of the first chamber 13 is provided with a through hole 15 communicating with the second chamber 16. The inner wall of the first chamber 13 near the fill pit is connected to an inlet 12. The first chamber 13 is provided with a prompt block 14 that is slidably connected to the inner wall of the first chamber 13. The side of the first chamber 13 away from the inlet 12 is provided with a prompt port 24 corresponding to the prompt block 14. The inner wall of the second chamber 16 near the fill pit is connected to a one-way valve 17 (the one-way valve 17 restricts the cement slurry to flow out only from the second chamber 16). In order to prevent the prompt block 14 from accidentally sliding out, several springs 6 are fixedly connected to the bottom wall of the prompt block 14. The top of each spring 6 is fixedly connected to the inner wall of the first chamber 13 near the inlet 12. At the same time, a reflective marking block is provided at the end of the prompt block away from the spring.

[0035] The specific implementation process is as follows: When using the anchor grouting support system for the miscellaneous fill foundation pit, the first step is to pre-compact the loose and porous nature of the miscellaneous fill. During construction, the miscellaneous fill in the excavation area of ​​the foundation pit is excavated in layers of 0.8m each. Construction waste such as bricks and concrete blocks with a diameter of more than 30cm is manually broken or cleaned. Several static pressure compaction holes are constructed in the miscellaneous fill pit using static pressure equipment to form a curtain. The porosity of the miscellaneous fill around the compaction holes is reduced by static pressure, which increases the initial compaction and lays the foundation for subsequent reinforcement. Then, reinforcement liquid (a liquid mixture of cement: clay: water = 1:6:5) is injected into the static pressure compaction hole 18, and reinforcement steel pipe 20 (H-beam or round steel pipe) is inserted at the same time. The reinforcement liquid diffuses along the wall of the static pressure compaction hole 18 into the surrounding pores of the miscellaneous fill, and the reinforcement steel pipe 20 provides a vertical and lateral support skeleton. Furthermore, grouting holes 19 are constructed between adjacent static pressure compaction holes 18, and self-drilling anchor bolts are installed. The anchor bolt anchoring section needs to penetrate 2.0m into the grouting reinforcement layer to ensure pull-out resistance; the specific anchor bolt reinforcement process is as follows; Debug the hydraulic anchor drilling rig to ensure that the drilling speed, torque, and thrust meet the design requirements; check the grouting pump pressure value and mark the anchor hole positions according to the design drawings. The construction personnel move the drilling rig to the hole position, adjust the machine body to be level, and make the drill rod axis consistent with the designed drilling angle. Start the drilling rig and drive the self-drilling anchor rod to drill slowly. When the hollow anchor rod 2 reaches the predetermined depth, stop drilling, connect the grouting machine to the grouting port 1, start the grouting pump, and press the cement grout into the grout outlet 11 through the hollow channel of the rod. The cement grout fills from the depth of the drill bit 10 outward. During the filling process, the cement grout continuously squeezes out the air to ensure that there are no gaps at the bottom of the hole.

[0036] During the grouting process, once the borehole is filled with cement grout, the excess cement grout will flow in the opposite direction along the gap between the self-drilling anchor and the borehole wall, eventually flowing to the return component at baffle 5. Because the one-way valve 17 installed on the inner wall of the second chamber 16 near the fill pit only allows cement slurry to flow outward from the second chamber 16 in one direction, the cement slurry flowing in the opposite direction cannot push open the one-way valve 17 to enter the second chamber 16. It can only flow smoothly into the first chamber 13 through the inlet 12 pre-set on the inner wall of the first chamber 13 near the fill pit. The cement slurry entering the first chamber 13 squeezes and pushes the indicator block 14. The bottom wall of the indicator block 14 is connected with multiple springs 6 to prevent the indicator block 14 from accidentally sliding out to the indicator port 24 before the grouting is completed. The cement slurry squeezes and pushes the indicator block 14 so that the indicator block 14 extends along the indicator port 24 to the outside of the return device, reminding the construction personnel that the grouting is completed. The remaining cement slurry flows into the second chamber 16 through the through hole 15 between the first chamber 13 and the second chamber 16. The excess cement slurry flows out from the one-way valve 17 of the second chamber 16. After the grouting is completed, the grouting machine is removed, and the nut 3 and washer 4 are tightened with the baffle 5.

[0037] After the self-drilling anchor is installed, cement grout is injected into the compaction hole stratum through grouting hole 19 to solidify the intermediate fill soil, eliminate pores, and make the support structure form a continuous whole. After the reinforcement liquid and grout solidify, a composite support system is formed, and the foundation pit excavation operation can be carried out safely. Once the foundation pit construction is completed and backfilling is finished, and the temporary support function of the support structure is confirmed to have ended, the recovery operation of the reinforcing steel pipe 20 can be initiated. Specifically, the backfill soil at the top of the reinforcing steel pipe 20 is cleared to expose the head of the reinforcing steel pipe 20, ensuring that the extraction equipment can firmly clamp the top of the reinforcing steel pipe 20 to avoid slippage. At the same time, a special hydraulic extraction device (such as a hydraulic pile extractor) is used to clamp the top of the reinforcing steel pipe 20 and apply an upward uniform pulling force to slowly pull the reinforcing steel pipe 20 out of the static pressure compaction hole 18. Because the clay content in the reinforcing liquid ratio is high (cement:clay:water = 1:6:5), the bonding force after solidification is relatively low. In addition, the reinforcing steel pipe 20 is an H-beam or round steel pipe with a smooth surface, which reduces the resistance during extraction and facilitates separation. Therefore, if the extracted reinforcing steel pipe 20 is intact, it can be directly reused in subsequent projects; if it is slightly damaged, it can still be used after repair, realizing resource recycling.

[0038] Example 2: As attached Figure 1 As shown, the difference from Embodiment 1 is that, in order to prevent the support from collapsing due to water accumulation, a drainage ditch 21 is provided on the bottom wall of the fill pit.

[0039] The specific implementation process is as follows: Due to the complex composition and dispersed internal structure of the fill soil, if the fill soil support does not have drainage, water will continue to accumulate in the soil, causing a chain reaction of problems such as increased pore water pressure and decreased soil strength, which may eventually lead to failure of the support structure or even slope collapse. In order to avoid this situation, several drainage outlets 23 are set in the fill soil to drain the water from the fill soil, thereby achieving water drainage.

[0040] Obviously, the above embodiments are merely illustrative examples for clear explanation and are not intended to limit the implementation. Those skilled in the art will recognize that other variations or modifications can be made based on the above description. It is neither necessary nor possible to exhaustively list all possible implementations here. However, obvious variations or modifications derived therefrom are still within the protection scope of this invention.

Claims

1. A miscellaneous fill soil support structure, comprising a miscellaneous fill soil pit, characterized in that, The fill pit is provided with several static pressure compaction holes (18) perpendicular to the fill pit. The static pressure compaction holes (18) are filled with reinforcement liquid and reinforced steel pipes (20) are provided in the static pressure compaction holes (18). The reinforced steel pipes (20) are combined to form a reinforced panel. The fill pit is provided with several grouting holes (19) penetrating the static pressure compaction holes (18). Self-drilling anchors are installed in the grouting holes (19). The self-drilling anchor includes a hollow anchor (2) and a baffle (5). The baffle (5) is set on the hollow anchor (2), and the baffle (5) is provided with a return assembly for secondary use of cement slurry. The return assembly includes a first chamber (13). The top wall of the first chamber (13) is fixedly connected to a second chamber (16). The top wall of the first chamber (13) is provided with a through hole (15) communicating with the second chamber (16). The inner wall of the first chamber (13) near the miscellaneous fill pit is connected to an inlet (12). The first chamber (13) is provided with a prompt block (14) that is slidably connected to the inner wall of the first chamber (13). The side of the first chamber (13) away from the inlet (12) is provided with a prompt port (24) corresponding to the prompt block (14). The inner wall of the second chamber (16) near the miscellaneous fill pit is connected to a one-way valve (17).

2. The miscellaneous fill soil support structure according to claim 1, characterized in that, The hollow anchor rod (2) is connected in sequence along its axis to the grouting port (1), nut (3), washer (4), centerer (7), connecting sleeve (9) and drill bit (10). The drill bit (10) has a grouting hole (19) on one side, and the baffle (5) is located between the washer (4) and the centerer (7).

3. The miscellaneous fill soil support structure according to claim 2, characterized in that, The hollow anchor rod (2) has an anti-corrosion sleeve (8) on its outer wall, which is located between the centering device (7) and the connecting sleeve (9).

4. The miscellaneous fill soil support structure according to claim 3, characterized in that, The reinforcing fluid is composed of cement, clay and water.

5. The miscellaneous fill soil support structure according to claim 4, characterized in that, The bottom wall of the prompt block (14) is fixedly connected with several springs (6), and the top of each spring (6) is fixedly connected to the inner wall of the first chamber (13) near the inlet (12).

6. The miscellaneous fill soil support structure according to claim 5, characterized in that, The reinforced steel pipe (20) is either an H-beam or a round steel pipe.

7. The miscellaneous fill soil support structure according to claim 6, characterized in that, A reflective marking block is provided at the end of the prompt block (14) away from the spring (6).

8. The miscellaneous fill soil support structure according to claim 7, characterized in that, The side of the baffle (5) away from the miscellaneous fill pit is provided with an anti-slip coating.

9. The miscellaneous fill soil support structure according to claim 8, characterized in that, The bottom wall of the miscellaneous fill pit is equipped with a drainage channel (21).

10. The miscellaneous fill soil support structure according to claim 9, characterized in that, A sealing cap is provided on the grouting port (1).