Test circuits, test devices and test systems
By using a two-level collaborative addressing test circuit, the control commands are split into coarse and fine adjustment signals, which solves the problem of insufficient control chip ports in traditional test systems and achieves efficient and low-cost test management.
Patent Information
- Application Number
- CN202522403126.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-12
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-11-12
AI Technical Summary
Traditional testing systems suffer from high testing costs and long testing times because the limited input/output ports of the control chip cannot efficiently adapt to a large number of testing channels.
A test circuit is adopted, which uses a two-level collaborative addressing mechanism of the main controller to split the control command into a first control signal and a second control signal. The first control signal is used for coarse addressing in the first-level control terminal, and the second control signal is used for fine addressing in the second-level control terminal, so as to manage test channels that are far more numerous than the number of physical input and output ports.
While ensuring testing speed, the requirements for input/output port resources of the main controller and hardware costs have been reduced, thereby improving testing efficiency and resource utilization.
Smart Images

Figure CN224985528U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of electronic testing technology, and in particular to a test circuit, test device, and test system. Background Technology
[0002] In the field of modern electronic testing, as the functions of devices under test become increasingly complex, the number of test channels required is growing explosively. This trend is particularly evident in highly integrated components such as automotive displays, where the increase in screen size and resolution has directly led to a surge in test channels for backlighting, touch, power supply, and data signals.
[0003] Traditional testing systems employ a direct control mode where the main controller's input / output ports correspond one-to-one with the test channels. This results in a linear correlation between the number of input / output pins required by the main controller and the number of test channels. To drive a massive number of test channels, engineers are forced to choose high-end main controller chips with larger packages and more abundant input / output port resources, which directly leads to a sharp increase in hardware costs.
[0004] In addition, while chips that use expanded input / output ports can alleviate the pressure of the corresponding number of pins, the serial communication protocol they rely on introduces significant timing delays, making it difficult to meet the strict requirements for test time in high-efficiency test scenarios, thus reducing test speed and affecting test efficiency. Summary of the Invention
[0005] One of the purposes of this application is to provide a test circuit to solve the technical problem in the prior art that the limited input and output ports of the control chip cannot efficiently adapt to a large number of channels under test, resulting in high test costs and long test times.
[0006] One objective of this application is to provide a test circuit, comprising: a main controller having M first control lines and N second control lines, where M is an integer greater than or equal to 1 and N is an integer greater than 1; multiple signal channel units, the multiple signal channel units being divided into N channel groups; and N selection switches, the N selection switches being respectively connected to the output terminals of the N channel groups, and the control terminals of the N selection switches being respectively connected to the N second control lines; wherein, the M first control lines are connected in parallel with the signal channel units within the N channel groups, and are used to select a corresponding signal channel unit from each channel group according to a first control signal output by the main controller; the N selection switches are used to select the selection switch corresponding to a target channel group according to a second control signal output by the main controller, so as to route the signal output from the target channel group to the test terminal.
[0007] As a further improvement of one embodiment of this application, the sum of the number of the first control lines M and the number of the second control lines N is less than the total number of the signal channel units.
[0008] As a further improvement of one embodiment of this application, the number of signal channel units in each channel group is K, where K satisfies 1 < K ≤ 2^M.
[0009] As a further improvement of one embodiment of this application, each of the M first control lines is configured to be connected to multiple designated signal channel units from different channel groups according to a predefined mapping relationship, and to uniformly control the group of units to receive the address signals constituted therefrom.
[0010] As a further improvement of one embodiment of this application, the maximum total number of signal channel units is P, where P satisfies P=N×2^M.
[0011] As a further improvement to one embodiment of this application, the main controller is a CPLD chip or an ARM chip.
[0012] As a further improvement of one embodiment of this application, a signal processing unit is provided between the output terminal of each channel group and the corresponding selection switch, for summarizing the output signals of the signal channel units within the channel group.
[0013] As a further improvement of one embodiment of this application, the signal processing unit is a GRU, and the gating switch is a GRU switch.
[0014] To achieve one of the above-mentioned objectives, one embodiment of this application provides a testing device, which includes the testing circuit described in any one of the claims.
[0015] To achieve one of the above-mentioned objectives, one embodiment of this application provides a testing system, which includes the testing circuit described in any one of the claims.
[0016] Compared with the prior art, the embodiments of this application have at least one of the following beneficial effects: This application employs a test circuit that constructs a "two-level collaborative addressing" hardware architecture. The control commands of the main controller are split into a first control signal and a second control signal. The first control signal is used for "coarse adjustment" within the first-level control terminal, addressing and activating the corresponding target signal channel unit. The second control signal is used for "fine adjustment" within the second-level control terminal, controlling the gating switch to construct the final signal path. This mechanism of decoupling and hierarchically executing control functions allows the main controller to operate far more test channels than its physical input / output ports using "address encoding," thereby reducing the input / output port resource requirements and hardware costs of the main controller while ensuring test speed. Attached Figure Description
[0017] Figure 1 This is a schematic diagram of the test circuit in one embodiment of this application.
[0018] Figure 2 This is a schematic diagram of a test circuit including a signal processing unit in one embodiment of this application.
[0019] Figure 3 This is a schematic diagram of the test circuit in a preferred embodiment of this application. Detailed Implementation
[0020] The present application will now be described in detail with reference to the specific embodiments shown in the accompanying drawings. However, these embodiments do not limit the present application, and any structural, methodological, or functional modifications made by those skilled in the art based on these embodiments are included within the scope of protection of this application.
[0021] The terms used in this document, such as “center,” “upper,” “lower,” “front,” “rear,” “left,” “right,” “vertical,” “horizontal,” “top,” “bottom,” “inner,” and “outer,” indicating spatial relative positions, are used for illustrative purposes to describe the relationship of one unit or feature relative to another unit or feature as shown in the accompanying drawings. The terms “spatial relative positions” may be intended to include different orientations of the equipment in use or operation other than those shown in the figures.
[0022] For example, if the device in the figure is flipped, a unit described as being "below" or "under" other units or features will be "above" other units or features. Therefore, the exemplary term "below" can encompass both above and below orientations. The device may be oriented in other ways (rotated 90 degrees or otherwise) and the spatially related descriptive terms used herein will be interpreted accordingly.
[0023] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0024] It should be noted that the term "comprising" or any other variation thereof is intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus. Furthermore, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance.
[0025] like Figure 1 and Figure 2 As shown, one embodiment of this application provides a test circuit 100.
[0026] Test circuit 100 is a circuit structure used for performing testing. In this application, test circuit 100 specifically refers to a dedicated circuit structure designed to achieve the goal of "managing a large number of test channels with a small number of control lines" and to resolve the contradiction between control resources (e.g., I / O ports) and test requirements (e.g., the number of channels).
[0027] The test circuit 100 includes a main controller 11, which is the core control component of the test circuit 100. The main controller 11 has M first control lines and N second control lines. It can output corresponding first control signals and second control signals, which are used to control the operation of other components in the test circuit 100, such as the gating signal channel unit 12 and the control gating switch 13.
[0028] There are M first control lines, where M is an integer greater than or equal to 1. They are connected in parallel with the signal channel units 12 in the N channel groups 15 and are used to transmit the first control signal output by the main controller 11. Their function is to select a corresponding signal channel unit 12 from each channel group 15.
[0029] There are N second control lines, where N is an integer greater than 1. The main controller 11 outputs second control signals through these N second control lines to control the selection switch 13 corresponding to the target channel group 15, and routes the signal output from the target channel group 15 to the test end.
[0030] In one embodiment, the main controller 11 can be a CPLD (Complex Programmable Logic Device) or an ARM chip.
[0031] Thus, by limiting the preferred type of the main controller 11, the rapid and accurate execution of control commands can be ensured.
[0032] In this embodiment, a CPLD is a digital integrated circuit based on programmable logic units and an interconnect matrix. Users can implement custom logic functions through software programming, providing fast (e.g., second-level) hardware parallel speeds to meet testing time requirements. An ARM chip is a processor based on a reduced instruction set architecture, providing powerful logic processing capabilities.
[0033] In one embodiment, one end of the first control line and the second control line are connected to the I / O port of the main controller 11, and the other end is connected to the signal channel unit 12.
[0034] The test circuit 100 includes multiple signal channel units 12, which are the basic units in the test circuit 100 for processing signals. The multiple signal channel units 12 are divided into N channel groups 15. Each signal channel unit 12 can receive and process signals and can be selected according to the first control signal output by the main controller 11.
[0035] Channel group 15 is a set formed by grouping multiple signal channel units 12. There are N channel groups 15 in the test circuit 100. Each channel group 15 contains a certain number of signal channel units 12. The main controller 11 selects the signal channel units 12 in each channel group 15 through the first control line.
[0036] For example, the first control line outputs a first control signal, which can simultaneously select the first signal channel unit CH1 in the first channel group and the first signal channel unit CH6 in the second channel group, such as... Figure 3 As shown.
[0037] In one embodiment, the sum of the number of first control lines M and the number of second control lines N is less than the total number of signal channel units 12.
[0038] It should be noted that multiple signal channel units 12 are divided into N channel groups 15, and the main controller 11 is connected in parallel to the signal channel units 12 in each channel group 15 through M first control lines. Since it is a grouped parallel control, one first control line can act on one signal channel unit 12 in N channel groups 15 at the same time (for example, the first signal channel unit, which achieves intra-group selection through specific coding or logic), instead of setting a separate control line for each signal channel unit 12. Therefore, M is much smaller than the total number of signal channel units 12.
[0039] In this way, it can accurately select specific signal channel units 12 within each channel group 15, and flexibly control the signal routing of the target channel group 15. While ensuring the functional integrity of the test circuit, it simplifies the control circuit structure, reduces hardware complexity and cost, and achieves efficient management of a large number of signal channel units 12 with fewer control lines.
[0040] For example, such as Figure 3 As shown, if there are 10 signal channel units 12, divided into two channel groups 15, then each channel group 15 has 5 signal channel units 12. The two channel groups 15 only need 5 first control lines (for example, CH1_Ctr to CH5_Ctr shown in the figure) and 2 second control lines to implement the test of 10 signal channel units 12.
[0041] In this example, the main controller 11 can control the signal testing of 10 signal channel units 12 by using 7 (5+2) I / O ports; the use of two channel groups 15 can save three I / O ports, and the number of saved I / O ports will increase as the number of signal channel units 12 increases, such as more than 10.
[0042] For example, with increasingly larger in-vehicle screens, the number of test channels (i.e., signal channel units 12) required also increases, continuing to refer to... Figure 3 As shown, we will use 140 as an example for explanation.
[0043] Five channel control lines (i.e., five first control lines) are drawn from the CPLD or ARM chip (i.e., the main controller 11). In the first-level control terminal, they are divided into 28 channel groups 15, each group containing 5 signal channel units 12. In the second-level control terminal, there are 28 GRUs (i.e., selection switches 13) corresponding to the previous channel group 15. At this point, the overall framework of the test circuit 100 is completed. A total of 33 control lines are used from the main controller 11: 5 first control lines + 28 second control lines, to control 140 channels, saving 140 - 33 = 107 control lines and improving the resource utilization of the main controller 11.
[0044] In one embodiment, the number of signal channel units 12 in each channel group 15 is K, where K satisfies 1 < K ≤ 2^M.
[0045] Thus, by leveraging the exponential nature of binary encoding, the single-group control capability is increased from linear growth to exponential growth. This design can effectively control the number of corresponding control lines, simplify circuit results, and improve resource utilization.
[0046] Specifically, if the number M of the first control lines is considered as the bit width of a binary address, then the number of unique coding combinations that these M lines can generate is exactly 2 to the power of M (2^M). Each coding combination corresponds to a specific signal channel unit 12 within channel group 15. Therefore, by simply adding one control line (i.e., increasing M by 1), the number of independently addressable signal channel units 12 within a single group can be doubled.
[0047] In addition, limiting K to be greater than 1 avoids the weakening of grouping meaning due to too few signal channel units 12 in channel group 15. At the same time, setting K to not exceed 2^M ensures that the existing M first control lines can cover the selection requirements of all signal channel units 12 in channel group 15, and there will be no insufficient coding. This ensures that the system can make full use of coding resources without address conflicts, thus laying the foundation for "managing a large number of test channels with a small number of control lines".
[0048] In one embodiment, each of the M first control lines is configured to connect to a plurality of designated signal channel units 12 from different channel groups 15 according to a predefined mapping relationship, and to uniformly control the group of units to receive the address signals constituted therefrom.
[0049] Thus, by binding each first control line to a set of signal channel units 12 consisting of units within multiple channel groups 15, physical-level control relationships are pre-configured. This structure integrates multiple units originally scattered across different channel groups 15 into a single entity driven by a single signal, simplifying the control logic of the main controller 11. When gating this set, a single control signal can simultaneously drive all bound units, not only enhancing signal driving capability but also ensuring the synchronization of these unit actions.
[0050] It should be noted that, in this embodiment, the M first control lines can be understood as a set of common address buses, connected in parallel to each signal channel unit 12 within each channel group 15; each unit integrates logic circuitry for decoding this set of common address signals. When the main controller 11 issues a first control signal, all signal channel units 12 within the group synchronously perform address resolution, but within each channel group 15, only the unique signal channel unit 12 whose internal address completely matches the address bus signal will be activated.
[0051] For example, such as Figure 3 As shown, assuming the signal of CH1 needs to be tested, the first control signal is sent through the first control line (i.e. the control line that controls CH1_Ctr in the figure). In the first-level control terminal, the signals of CH1 and CH6 will be simultaneously connected to GRU1 and GRU2 (i.e., activate CH1 in the first group and activate CH2 in the second group). Then, the GRU1 switch is controlled to be closed and the GRU2 switch is controlled to be open, so that the signal of CH1 can reach the test terminal smoothly.
[0052] In one specific embodiment, when the number K of signal channel units in channel group 15 is greater than the number M of first control lines, M signal channel units are selected from the K signal channel units and connected one by one with the M first control lines.
[0053] In one embodiment, the total number of signal channel units 12 is P, where P satisfies N = N × 2^M. This means that each address code defined by M first control lines obtains a corresponding physical channel in each channel group 15, thus saturating the utilization of control resources.
[0054] The test circuit 100 includes N selector switches 13, which are respectively connected to the output terminals of N channel groups 15. The control terminals of the N selector switches are respectively connected to N second control lines. Their function is to control whether to route the signal output of the corresponding target channel group 15 to the test terminal according to the second control signal output by the main controller 11, so as to achieve selective signal transmission.
[0055] It should be noted that the first control signal is output by the main controller 11 through M first control lines, and is used to select a corresponding signal channel unit 12 from each channel group 15, which determines which signal channel unit 12 in each signal channel group 15 is activated to process or transmit signals.
[0056] The second control signal is output by the main controller 11 through N second control lines, and is used to control the selection switch 13 corresponding to the target channel group 15 to determine which channel group 15's signal can be routed to the test end.
[0057] In the test circuit 100, activating any one of the first control lines will select one signal channel unit 12 in each channel group 15, that is, N signal channel units 12 will be selected simultaneously; then activating any one of the second control lines will select only one of the N selection switches 13 corresponding to the N signal channel units, so that the signal output of the corresponding target signal channel unit 12 is routed to the test end.
[0058] like Figure 2As shown, in one embodiment, the test circuit 100 further includes a signal processing unit 14, which is disposed between the output terminal of the channel group 15 and the corresponding selection switch 13, and is used to summarize the output signals of the signal channel unit 12 in the channel group 15.
[0059] Thus, by introducing the signal processing unit 14 as the interface between the two-level control, signal aggregation and buffering can be achieved, improving the modularity and signal integrity of the system. It regularizes the output of the channel group 15 in the first-level control terminal into a single node, providing a clear operational object for the gating of the second level and reducing the complexity of the circuit design.
[0060] In one specific embodiment, the number of signal processing units 14 is N, and a signal processing unit 14 is provided between the output terminal of each channel group 15 and the corresponding selection switch 13.
[0061] Specifically, after each signal channel unit 12 in channel group 15 completes signal acquisition or processing, its output signal is first fed into signal processing unit 14. This unit performs unified processing on all signals in the group (e.g., superposition, filtering, amplification, or encoding integration) to form a summary signal representing the overall characteristics of channel group 15. Subsequently, according to the instruction of the second control line, the selection switch 13 selects one of the summary signals processed by each channel group 15 and outputs it to the subsequent circuit.
[0062] This design avoids interference or data redundancy that may result from direct transmission of the original signal, and improves signal quality and consistency through in-group signal preprocessing. Meanwhile, the gating switch 13 only needs to route the integrated signal, reducing the complexity of switch control and signal transmission path, and achieving efficient signal management and accurate transmission.
[0063] In one specific embodiment, the signal processing unit 14 is a GRU, and the gating switch 13 is a GRU switch.
[0064] In this embodiment, the GRU (Gated Recurrent Unit) dynamically controls the flow of information through update gates and reset gates. The update gate is used to determine how much historical information to retain and how much to incorporate new information, while the reset gate is used to adjust the degree of influence of historical information on the current state.
[0065] When the GRU is used as signal processing unit 14, it can extract and integrate the features of the signal output from channel group 15, and adaptively filter noise and retain key information through a gating mechanism. The GRU switch controls the activation state of the GRU unit to achieve dynamic gating of signal channels. The GRU unit only processes the signal of the corresponding channel group 15 and outputs the integrated result when the GRU switch is turned on; otherwise, it blocks signal transmission.
[0066] This design combines the timing processing capabilities of the GRU with the flexible control of the switch, ensuring the quality of signal processing while reducing unnecessary calculations through the gating switch 13, thereby improving efficiency and reliability.
[0067] The various implementation methods, embodiments, or specific examples provided in this application can be combined with each other to ultimately form multiple better implementation methods.
[0068] The following is combined with Figures 1 to 3 Describe the testing process of test circuit 100.
[0069] The operation of the test circuit 100 begins with the cooperative signal output of the main controller 11. First, the main controller 11 determines the required number of control lines and the number of groups of signal channel units 12 (i.e., the number N of channel groups 15) based on the number of signal channel units 12 under test and the total number of I / O ports that can be provided (i.e., signal channel units). A specific parallel address code, i.e., the first control signal, is output through its M first control lines.
[0070] The first control signal is broadcast synchronously to N channel groups 15. Due to the specific parallel connection structure between the first control line and the signal channel unit 12 in each group, this address code will uniquely select a corresponding signal channel unit 12 in each channel group 15, so that it enters the working state.
[0071] Subsequently, to route the signal to the final test terminal, the main controller 11 simultaneously outputs a second control signal through its N second control lines. The second control signal is used to precisely control the N gating switches 13 of the second-level control terminal. At any given time, only one of the N second control lines is activated, thereby uniquely opening the gating switch 13 connected to the corresponding target channel group 15.
[0072] Finally, only the signal channel unit 12 that is selected within the group by the first control signal (first-level control) and whose selection switch 13 of its channel group 15 is opened by the second control signal can successfully pass through the two levels of control and be routed to the test terminal to complete the test action. By repeating this process, all signal channel units 12 can be tested efficiently with a very small number of control lines.
[0073] For ease of understanding, Figure 3This paper presents a schematic diagram of the test circuit described in a preferred embodiment. Assuming the main controller 11 is a CPLD / ARM, the signal channel units 12 are CH1-CH10 (divided into two access groups), each group has five signal channel units 12. These five signal channel units 12 (CH1-CH5 or CH6-CH10) are respectively connected to five control lines on the CPLD / ARM. The signal processing unit 14 is a GRU (including GRU1 and GRU2), and the selection switch 13 is a GRU switch (including GRU1 switch and GRU2 switch). The following description, in conjunction with... Figures 1 to 3 Describe the testing process for the test circuit.
[0074] At the start of the test, the first-level control terminal, composed of CPLD / ARM, as the core command component, begins operation. Based on the preset test strategy, it sends first control signals to the two channel groups 15 respectively. For the first group, the CPLD / ARM outputs instructions to CH1_Ctr to CH5_Ctr, precisely selecting one of the corresponding signal channel units 12 (i.e., CH1 to CH5), causing the selected signal channel unit 12 to start working and output a signal. Simultaneously, a similar operation is performed on the second group, selecting one of the signal channel units 12 from CH6 to CH10 through CH1_Ctr to CH5_Ctr (here, the control signal is for the corresponding signal channel unit 12 in the second group) to output a signal.
[0075] The signals output from different channel groups 15 are transmitted to the second-level control terminal. At the second-level control terminal, GRU1 and GRU2 switches become key control points for signal routing. The main controller 11 sends control commands through N second control lines to precisely control the states of GRU1 and GRU2 switches. For example, when it is necessary to detect the signal of a certain signal channel unit 12 in the first group, the main controller 11 controls the GRU1 switch to open the corresponding path, allowing the signal of the selected channel in the first group to be transmitted through the GRU1 switch; if it is necessary to detect the signal of the second group, it controls the GRU2 switch to open the corresponding path, allowing the signal of the selected channel in the second group to be transmitted through the GRU2 switch.
[0076] Finally, the signals selected by the second-level control terminal switch are aggregated to the detection port. The detection port performs comprehensive detection and analysis on the input signals, acquiring various parameters and characteristic information of the signals, thereby determining the working status of the signal channel unit 12 and the performance of the entire test circuit 100, and completing the entire test process.
[0077] The test circuit described in this application has the following advantages: First, in terms of test time, by using direct signal routing and hardware gating mechanism, the inherent instruction overhead and delay of serial communication protocols are avoided, ensuring that the test process is efficient and rapid, and greatly guaranteeing test efficiency.
[0078] Secondly, from the perspective of resource utilization, the circuit adopts a clever combination control strategy to achieve precise control of a large number of channels with a small number of control lines, which greatly improves the utilization rate of control resources and effectively saves the I / O port resources of the core control chip. While realizing comprehensive testing functions, it also achieves efficient resource allocation and utilization, providing strong support for the miniaturization and integration of the testing system.
[0079] One embodiment of this application provides a testing device, which is a relatively independent and specific physical entity or device, and has a testing circuit encapsulated inside.
[0080] In one embodiment, the packaged test circuit can refer to the test circuit described above in this application, and the corresponding embodiments and effects will not be repeated here.
[0081] Specifically, the testing device can be exemplified as a testing instrument, whose housing integrates the testing circuit described above as the core motherboard, and is equipped with necessary power modules, heat dissipation units, and human-machine interfaces (such as touch screens, buttons, and status indicator lights). The front panel of the testing device is equipped with standardized testing interfaces (such as flexible printed circuit board connectors or probe arrays) for direct connection to the object under test (such as the ribbon cable of an automotive screen). After the user starts the testing process through the operating interface, the core motherboard automatically applies and measures signals to multiple test points on the object under test according to the working process of the testing circuit described above, and presents the results on the interactive interface, thus forming a fully functional and easy-to-use independent device.
[0082] One embodiment of this application provides a testing system, which can be understood as an automated testing production line. It not only integrates testing circuits as a lower-level controller, but also connects to a host computer scheduling server via a bus (such as Ethernet), and works in conjunction with other testing components (such as robotic arms, conveyor belts, etc.).
[0083] In one embodiment, the integrated test circuit can refer to the test circuit described above in this application, and the corresponding embodiments and effects will not be repeated here.
[0084] In this system, the host computer is responsible for issuing test task information, the robotic arm is responsible for grabbing the vehicle screen to be tested and placing it precisely on the test station, and the slave computer controls the test circuit 100 described in this application to perform the test according to its corresponding test process. Finally, the test data is transmitted to the server for judgment, storage and statistical analysis, thereby realizing fully automatic and efficient monitoring and traceability of the screen quality on the entire production line.
[0085] In summary, the test circuit, test device, and test system provided in this application utilize a two-level collaborative addressing hardware architecture. This circuit decomposes the control commands of the main controller 11 into a first control signal and a second control signal. The first control signal is used for "coarse adjustment" within the first-level control terminal, addressing and activating the corresponding target signal channel unit 12. The second control signal is used for "fine adjustment" within the second-level control terminal, controlling the gating switch 13 to construct the final signal path. This mechanism of decoupling and hierarchically executing control functions allows the main controller 11 to operate far more test channels than its physical input / output ports using "address encoding," thereby reducing the input / output port resource requirements and hardware costs of the main controller 11 while ensuring test speed.
[0086] It should be understood that although this specification describes embodiments, not every embodiment contains only one independent technical solution. This way of describing the specification is only for clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
[0087] The detailed descriptions listed above are merely specific descriptions of feasible implementation methods of this application and are not intended to limit the scope of protection of this application. All equivalent implementation methods or modifications made without departing from the spirit of the art of this application should be included within the scope of protection of this application.
Claims
1. A test circuit, characterized by The test device comprises the test circuit according to any one of claims 1-8. The test system comprises the test circuit according to any one of claims 1-8. The test device comprises the test circuit according to any one of claims 1-8. The test system comprises the test circuit according to any one of claims 1-8. 2. The test circuit of claim 1, wherein, 3. The test circuit of claim 1, wherein, 4. The test circuit of claim 1, wherein, 5. The test circuit of claim 1, wherein, 6. The test circuit of claim 1, wherein, 7. The test circuit of claim 1, wherein, 8. The test circuit of claim 7, wherein, 9. A test device, characterized by 10. A test system, characterized by