Existing gas purification methods using porous materials as adsorbents face issues with deterioration of adsorption performance due to high-temperature regeneration, leading to increased energy costs and material degradation.
A method involving intermittent passage of a gaseous substance through a gas adsorption column filled with an adsorbent, allowing for efficient maintenance of adsorption performance by alternating gas flow intervals.
This approach maintains adsorption performance effectively, increasing the amount of processed gas below the impurity concentration limit and enhancing the adsorbed mass on the adsorbent, while reducing material deterioration and energy consumption.
Smart Images

Figure 2024133809000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a gas purification method, and more particularly to a gas purification method in which a gaseous substance is intermittently passed through a gas adsorption column packed with an adsorbent to remove a component to be removed (adsorbate) contained in the substance. [Background technology]
[0002] Gas purification methods using adsorbents have long been used in the chemical, food and petroleum industries. In such purification methods, known adsorbents used for gas adsorption include porous materials such as activated carbon, zeolite, silica gel, activated alumina, etc. These porous materials have a large specific surface area and numerous pores, and are known to enable gas purification through physical adsorption due to van der Waals forces and the molecular sieve effect of the pores.
[0003] The adsorption performance of these porous materials decreases with use, and in order to restore the adsorption performance, it is necessary to carry out a regeneration operation, that is, desorption of the adsorbate from the porous material. A commonly known method for regenerating the porous material is to heat it to a high temperature to desorb the adsorbate, but this method deteriorates the porous material and increases the energy cost. Therefore, there is a need to develop a method for preventing the deterioration of the adsorption performance of the porous material and efficiently maintaining the adsorption performance. As such a technique, Patent Document 1 describes a method in which the porous material is cooled during gas adsorption by a cooling means such as an air-cooling mechanism consisting of cooling fins and a cooling fan or a water-cooling mechanism. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2020-89833 A Summary of the Invention [Problem to be solved by the invention]
[0005] However, the method described in the above document requires cooling equipment, and therefore there is a need to develop a simpler method for preventing the deterioration of the adsorption performance of the porous material and efficiently maintaining that adsorption performance. [Means for solving the problem]
[0006] Under these circumstances, the inventors conducted intensive research and discovered that by intermittently passing a gaseous substance containing an adsorbate through a gas adsorption column packed with a porous material as an adsorbent, the adsorption performance of the adsorbent can be efficiently maintained, which led to the present invention. That is, the present invention relates to the inventions described in the following items.
[0007] 1. A gas purification method in which a gaseous substance is passed through a gas adsorption column filled with an adsorbent and having a gas inlet and a gas outlet arranged on either side of the adsorbent, thereby removing components to be removed that are contained in the gaseous substance, characterized in that the passage of the gaseous substance is performed intermittently.
[0008] 2. The gas purification method according to item 1, wherein the passage of the gaseous substance is carried out intermittently at intervals of 0.5 hours or more.
[0009] 3. The gas purification method according to item 1, wherein the gaseous substance is a corrosive gas.
[0010] 4. The gas purification method according to Item 1, wherein the adsorbent is one selected from the group consisting of high-silica zeolite, activated alumina, and silica-alumina gel.
[0011] 5. A gas purification device having a gas adsorption column filled with an adsorbent and having a gas inlet and a gas outlet arranged on either side of the adsorbent, and in which a gaseous substance is passed through the gas adsorption column to remove components to be removed that are contained in the gaseous substance, the gas purification device being configured to allow the passage of the gaseous substance to be performed intermittently.
[0012] 6. A gas purification method in which a gaseous substance is passed through a gas purification apparatus comprising a plurality of gas adsorption columns filled with an adsorbent and each column has a gas inlet and a gas outlet disposed between the adsorbent, and a target component to be removed contained in the gaseous substance is removed, characterized in that the gaseous substance is only partially passed through the gas adsorption columns.
[0013] 7. A gas purification device having a plurality of gas adsorption columns filled with an adsorbent, with a gas inlet and a gas outlet arranged on either side of the adsorbent, and in which a gaseous substance is passed through the gas adsorption columns to remove components to be removed that are contained in the gaseous substance, the gas purification device being configured so as to be able to partially pass the gaseous substance through the gas adsorption columns. Effect of the Invention
[0014] According to the present invention, the adsorption performance of the adsorbent can be more simply and efficiently maintained. [Brief description of the drawings]
[0015] [Figure 1] 1 is a schematic diagram of a gas purification apparatus according to the present invention, in which 1 denotes a gas adsorption column, 2 denotes an inlet control valve for the gas to be treated, 3 denotes an outlet control valve for the gas to be treated, 4 denotes a gas inlet, and 5 denotes a gas outlet. [Diagram 2] FIG. 2 is a graph showing the relationship between the interruption time of the gas purification operation and the amount of gas (treated gas) obtained in which the adsorbate (moisture) concentration is reduced to the upper control limit concentration (8 volppm) or less in Examples 1 to 3 and Comparative Example 1. [Diagram 3] FIG. 2 is a graph showing the relationship between the adsorbate (moisture) concentration at the outlet of a gas adsorption column and the total amount of gas treated by the adsorbent of the gas adsorption column in Examples 1 to 3 and Comparative Example 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] As shown in FIG. 1, a gas purification apparatus 100 according to the present invention comprises a gas adsorption column 1, an inlet control valve 2 for introducing a gas to be treated into the gas adsorption column, and a discharge control valve 3 for discharging the treated gas. The gas purification method according to the present invention includes a step of introducing a gas to be treated into a gas adsorption column 1, which is filled with a porous material as an adsorbent and has a gas inlet 4 and a gas outlet 5 arranged with the adsorbent sandwiched between them, from the gas inlet 4, and discharging the treated gas (treated gas) from the gas outlet 5. After this step, the inlet control valve 2 and the discharge control valve 3 are closed and maintained for a predetermined time (interruption of the gas purification operation), and then the control valves 2 and 3 are opened to resume the introduction of the gas from the inlet 4, and this operation is repeated as necessary.
[0017] Furthermore, the gas purification apparatus of the present invention can also be configured as a multi-tower type having two or more of the above-mentioned gas adsorption columns in parallel. In this case, the above-mentioned gas inflow, purification (treatment), and gas discharge are performed in at least one gas adsorption column (hereinafter referred to as the previous column), and in the other gas adsorption columns, the inlet control valve 2 for the gas to be treated and the discharge control valve 3 for the treated gas are closed, and after the gas purification in the previous column is interrupted, the above-mentioned gas inflow, purification (treatment), and gas discharge are performed in the other columns instead. This makes it possible to perform purification continuously without stopping the gas purification operation in the entire multi-tower apparatus, while performing the gas purification operation and interrupting it in each gas adsorption column.
[0018] (Adsorbent) In the present embodiment, the adsorbent packed in the gas adsorption column 1 may be any porous material having adsorption properties for the components to be removed, and may be inorganic porous materials such as zeolites such as high silica zeolites, activated alumina, silica gel, silica alumina gel, or carbon-based porous materials such as activated carbon. These porous materials may be used alone, or two or more types of porous materials may be used in combination.
[0019] From the viewpoint of adsorption efficiency, the porous material is preferably at least one selected from the group consisting of high-silica zeolite, activated alumina, and silica-alumina gel. Also, a portion of the gas adsorption column 1 may be filled with a porous material, and the remaining portion may be filled with packing materials such as Raschig rings, Berl saddles, and alumina balls.
[0020] (Gas to be treated) In the present invention, the gas to be treated flowing through the gas adsorption column 1 is a gaseous substance containing a main component and a component to be removed, which is an impurity component different from the main component. The main component is not particularly limited as long as it is a component that constitutes the majority of the gaseous substance, and examples of the main component include inert gases such as nitrogen, helium, and argon, hydrocarbon gases such as propane and propylene, corrosive gases such as ammonia, hydrogen sulfide, and sulfur dioxide, and oxygen-containing gases such as carbon monoxide, nitric oxide, and nitrous oxide. In particular, when the gas to be treated is a corrosive gas, the apparatus and porous materials are likely to deteriorate due to the regeneration step (heating), and therefore, the application of the method of the present invention is advantageous.
[0021] The components to be removed are not particularly limited as long as they are components that can be adsorbed in the gas adsorption column 1, and examples of such components include hydrocarbon gases such as propane and propylene, corrosive gases such as ammonia, hydrogen sulfide, and sulfur dioxide, oxygen-containing gases such as carbon monoxide, nitric oxide, and nitrous oxide, halogen-containing gases such as chlorine, bromine, fluorine, hydrogen chloride, hydrogen bromide, hydrogen fluoride, hydrogen iodide, and halogenated hydrocarbons, and water.
[0022] Specifically, the gas to be treated is, for example, a gaseous substance whose main component is sulfur dioxide containing water, which is the component to be removed; a gaseous substance whose main component is nitrogen containing water, which is the component to be removed; a gaseous substance whose main component is helium containing carbon dioxide, which is the component to be removed; etc.
[0023] (Gas purification method) The gas purification according to the present invention is carried out by intermittently passing a gas to be treated containing components to be removed, which are gaseous substances, i.e., impurity components, through a gas adsorption column 1 packed with a porous material as an adsorbent, to adsorb and remove the components to be removed contained in the gas to be treated. First, the gas to be treated is introduced into the gas adsorption column 1 with the inlet control valve 2 and the outlet control valve 3 open.
[0024] At this time, it is not always necessary to control the flow rate of the gas to be treated, but it is preferable to control the flow rate of the gas to be treated with a flow meter in order to control the purification process.
[0025] The linear velocity of the gas to be treated (=flow rate of the gas to be treated when introduced into the gas adsorption column / cross-sectional area of the gas adsorption column) is preferably 1 normal cm / sec or more and 100 normal cm / sec or less. As the linear velocity increases, the amount of gas treated per unit time increases, but the time until breakthrough becomes shorter, and the operable time of the adsorption column decreases. Therefore, from the viewpoint of process control, it is preferable to measure the gas flow rate with a flow meter and change the linear velocity according to the production amount of the gas to be treated and the time cycle of the production process.
[0026] The internal pressure of the gas adsorption column for the gas to be treated containing the impurities is preferably 0.01 MPa (gauge pressure) or more and 20 MPa (gauge pressure) or less. The higher the internal pressure of the gas adsorption column, the greater the amount of the components to be removed that are adsorbed. However, as the pressure increases, pressure-resistant equipment is required, which increases costs. Therefore, it is preferable to control the pressure by comprehensively considering the equipment conditions, production efficiency, etc. The gas to be treated is continuously introduced into the gas adsorption column 1 until the impurity concentration in the treated gas discharged from the gas outlet 5 reaches a reference concentration (here, the reference concentration refers to a predetermined impurity concentration in the treated gas to be adsorbed and removed by the gas adsorption column used, and is an arbitrary concentration within a range not exceeding the upper limit of the impurity concentration in the treated gas to be adsorbed and removed in the above gas purification operation using the gas adsorption column ("upper control limit concentration").). After the standard concentration is reached, the inlet control valve 2 and the outlet control valve 3 are closed and the condition is maintained for a predetermined period of time, that is, the gas purification operation is interrupted.
[0027] The retention time (interruption time of the gas purification operation) may be 0.5 hours or more, preferably 0.5 hours or more and 50 hours or less, and more preferably 20 hours or more and 50 hours or less.
[0028] In addition, the internal pressure of the gas adsorption column during interruption of the gas purification operation may be 0.01 MPa (gauge pressure) or more and 20 MPa (gauge pressure) or less. If the pressure is lower than that during gas passage, the adsorbed components to be removed may desorb from the adsorbent, and the effect may not be obtained, so it is preferable to maintain the pressure at or above the pressure during gas passage.
[0029] The standard concentration may be less than 100% of the upper limit concentration, but is preferably 95% or less, more preferably 80% or less. If it exceeds 100%, there is a risk of breakthrough of the adsorbent, and the effect may not be obtained.
[0030] After the retention time has elapsed, the inlet control valve 2 and the outlet control valve 3 are opened to reintroduce the gas to be treated into the adsorption column 1, and adsorption and removal of the impurity components is resumed. According to the gas purification method of the present invention, which includes a step of stopping the introduction of the gas to be treated into the gas adsorption column for a predetermined period of time, i.e., by intermittently passing the gaseous substance, the time until the concentration of impurities, which are the components to be removed in the gas to be treated, reaches the upper control limit concentration is increased compared to a case in which the gas to be treated is introduced into and passed through the gas adsorption column continuously for a long period of time, and as a result, the amount of treated gas obtained whose impurity concentration is below the upper control limit concentration and the adsorbed mass adsorbed onto the adsorbent are increased.
[0031] In this manner, according to the gas purification method of the present invention, the adsorption performance of the adsorbent can be efficiently maintained.
[0032] The concentration of the components to be removed in the treated gas discharged from the gas outlet 5 of the gas adsorption column is measured by an appropriate analyzer for each adsorbate. For example, when the component to be removed is water, the moisture concentration is measured using a moisture meter. As the moisture meter, a capacitance dew point meter, a phosphorus pentoxide dew point meter, a chilled mirror dew point meter, a cavity ring down spectroscopy (CRDS), etc. can be used, and it is preferable to use the cavity ring down spectroscopy (CRDS) for the analysis of low moisture concentrations. When the component to be removed is other than moisture such as carbon dioxide, quantitative analysis by gas chromatography is preferable. As a detector in gas chromatography, a PDD (Pulsed Discharge Detector) that is selected according to the type and concentration of the component to be removed and capable of high sensitivity analysis is preferable for the measurement.
[0033] As described above, the gas purification method according to the present invention can also be implemented using two or more gas adsorption columns arranged in parallel. In this case, by carrying out the above-mentioned gas inflow, purification (treatment), and gas discharge in at least one gas adsorption column (hereinafter referred to as the previous column), it is possible to carry out the gas purification operation and interruption in each gas adsorption column, while carrying out the purification operation continuously across the multiple columns without stopping the gas purification operation.
[0034] The present invention will be described in more detail below with reference to examples, although the present invention is not limited to these examples.
[0035] Example 1 A SUS column with an inner diameter of 1.0 cm and a length of 30 cm, equipped with a SUS protective tube with an outer diameter of 3 mm for measuring the column inner temperature, was filled with high silica zeolite (HSZ-640HOD1A, manufactured by Tosoh Corporation) as an adsorbent to a length of 3 cm, and alumina balls (diameter 3 mm) as packing materials to a length of 13.5 cm above and below the zeolite. Nitrogen gas was passed through the column at a flow rate of 60 normal ml / min while heating the column from the outside with a heater so that the temperature outside the column was 150°C. After 16 hours, the temperature outside the column was cooled to room temperature (about 25°C), and gas adsorption column 1 was prepared.
[0036] Next, with the discharge control valve 3 connected to the gas outlet 5 of the gas adsorption column 1 closed, sulfur dioxide was introduced from the gas inlet 4 of the gas adsorption column 1 until the pressure inside the column reached 0.1 MPa (gauge pressure). At this time, heat was generated inside the column, so the column was left to cool until the temperature inside the column decreased to room temperature (about 25°C).
[0037] After the above operation, the discharge control valve 3 was opened, sulfur dioxide with a water concentration of 37 volppm was introduced from the gas inlet 4 of the gas adsorption column 1, and the water contained in the sulfur dioxide was adsorbed and removed by the adsorbent. At this time, the supply rate of sulfur dioxide gas was 22.6 normal cm / sec, and the internal pressure of the gas adsorption column was 0.1 MPa (gauge pressure). The water concentration in the sulfur dioxide discharged from the gas outlet 5 of the gas adsorption column 1 was measured by cavity ring-down spectroscopy (CRDS). After the water concentration in the discharged gas reached 4 volppm, the introduction control valve 2 and the discharge control valve 3 were closed, and the gas purification operation was suspended for 20 hours while maintaining the internal pressure of the column at 0.1 MPa (gauge pressure). Next, the introduction control valve 2 and the discharge control valve 3 were opened, and sulfur dioxide gas with a water concentration of 37 volppm was again introduced from the gas inlet 4 of the gas adsorption column 1. Sulfur dioxide gas with a moisture concentration of 37 volppm was introduced into the gas adsorption column 1, and the amount of treated gas with the moisture concentration reduced to 8 volppm or less was 440 normal liters in total. The amount of adsorbed moisture was calculated to be 12.4 mg from the measured values of the moisture concentrations of the gas to be treated and the treated gas.
[0038] Example 2 Except for the interruption time of the gas purification operation being set to 1 hour, the gas purification operation was carried out in the same manner as in Example 1. Then, the moisture concentration in the sulfur dioxide discharged from the gas outlet 5 of the gas adsorption column was measured in the same manner as in Example 1, and the amount of treated gas obtained by introducing sulfur dioxide gas with a moisture concentration of 37 volppm into the gas adsorption column 1 and reducing the moisture concentration to 8 volppm or less was 380 normal liters in total. At this time, the amount of adsorbed moisture was calculated to be 10.5 mg.
[0039] Example 3 Except for the interruption time of the gas purification operation being 44 hours, the gas purification operation was carried out in the same manner as in Example 1. Then, the moisture concentration in the sulfur dioxide discharged from the gas outlet 5 of the gas adsorption column was measured in the same manner as in Example 1, and the amount of treated gas obtained by introducing sulfur dioxide gas with a moisture concentration of 37 volppm into the gas adsorption column 1 and reducing the moisture concentration to 8 volppm or less was 460 normal liters in total. The amount of adsorbed moisture at this time was calculated to be 12.9 mg.
[0040] Example 4 A SUS column with an inner diameter of 1.0 cm and a length of 30 cm was packed with silica alumina gel (Neo Bead SA, manufactured by Mizusawa Chemical Industry Co., Ltd.) as an adsorbent to a length of 3 cm, and alumina balls (diameter 3 mm) as a packing material to a length of 13.5 cm were packed above and below the silica alumina gel to a length of 13.5 cm. Nitrogen gas was passed through the column at a flow rate of 60 normal ml / min while heating the column from the outside with a heater so that the temperature outside the column became 250°C. After heating for 16 hours, the column was cooled to room temperature (about 25°C) to prepare gas adsorption column 1. Next, with the discharge control valve 3 connected to the gas outlet 5 of the gas adsorption column 1 closed, nitrogen was introduced from the gas inlet 4 of the gas adsorption column 1 until the internal pressure of the column reached 0.1 MPa (gauge pressure).
[0041] After the above operation, the discharge control valve 3 was opened, nitrogen with a moisture concentration of 39 volppm was introduced from the gas inlet 4 of the gas adsorption column 1, and the moisture contained in the nitrogen was adsorbed and removed by the adsorbent. At this time, the nitrogen gas supply rate was 20.4 normal cm / sec, and the gas adsorption column internal pressure was 0.1 MPa (gauge pressure). The moisture concentration in the nitrogen discharged from the gas outlet 5 of the gas adsorption column 1 was measured by cavity ring-down spectroscopy (CRDS). After the moisture concentration in the gas discharged from the outlet 5 of the gas adsorption column reached 8 volppm, the introduction control valve 2 and the discharge control valve 3 were closed, and the gas purification operation was suspended for 20 hours while maintaining the column internal pressure at 0.1 MPa (gauge pressure). Next, the introduction control valve 2 and the discharge control valve 3 were opened, and nitrogen gas with a moisture concentration of 38 volppm was again introduced from the gas inlet 4 of the gas adsorption column 1. Nitrogen gas with a moisture concentration of 39 volppm was introduced into the gas adsorption column 1, and the amount of treated gas with the moisture concentration reduced to 12 volppm or less was 380 normal liters in total. The amount of adsorbed moisture was calculated to be 10.6 mg.
[0042] Comparative Example 1 Except for the fact that gas adsorption was carried out continuously without interrupting the gas purification operation, gas purification was carried out in the same manner as in Example 1. Then, the moisture concentration in the sulfur dioxide discharged from the outlet of the gas adsorption column 1 was measured in the same manner as in Example 1, and the amount of treated gas obtained by introducing sulfur dioxide with a moisture concentration of 36 volppm into the gas adsorption column 1 and reducing the moisture concentration to 8 volppm or less was 340 normal liters. At this time, the amount of adsorbed moisture was calculated to be 9.1 mg.
[0043] Comparative Example 2 Gas purification was performed in the same manner as in Example 4, except that gas adsorption was performed continuously without interrupting the gas purification operation. The moisture concentration in the nitrogen discharged from the outlet of the gas adsorption column 1 was measured in the same manner as in Example 4, and nitrogen gas with a moisture concentration of 39 volppm was introduced into the gas adsorption column 1, and the amount of treated gas in which the moisture concentration was reduced to 12 volppm or less was 310 normal liters. The amount of adsorbed moisture was calculated to be 8.5 mg.
[0044] [Table 1] [Explanation of symbols]
[0045] 100 Gas purification equipment 1 Gas adsorption column 2. Control valve for introducing gas to be treated 3. Treated gas discharge control valve 4 Gas inlet 5 Gas outlet
Claims
1. 1. A gas purification method for removing a component to be removed that is contained in a gaseous substance by passing a gaseous substance through a gas adsorption column filled with an adsorbent and having a gas inlet and a gas outlet disposed on either side of the adsorbent, the method being characterized in that the passage of the gaseous substance is performed intermittently.
2. 2. The gas purification method according to claim 1, wherein the gaseous substance is passed intermittently at intervals of 0.5 hours or more.
3. 2. The gas purification method according to claim 1, wherein the gaseous substance is a corrosive gas.
4. 2. The gas purification method according to claim 1, wherein the adsorbent is one selected from the group consisting of high-silica zeolite, activated alumina and silica-alumina gel.
5. A gas purification device having a gas adsorption column filled with an adsorbent and having a gas inlet and a gas outlet disposed on either side of the adsorbent, the gas adsorption column being configured to allow the passage of the gaseous substance intermittently to remove a component to be removed that is contained in the gaseous substance.
6. 1. A gas purification method for removing components to be removed that are contained in a gaseous substance by passing the gaseous substance through a gas purification apparatus including a plurality of gas adsorption columns, each of which is filled with an adsorbent and has a gas inlet and a gas outlet disposed between the adsorbent, the method comprising the steps of: partially passing the gaseous substance through the gas adsorption columns.
7. A gas purification apparatus having a plurality of gas adsorption columns filled with an adsorbent, each having a gas inlet and a gas outlet disposed on either side of the adsorbent, and configured to allow a gaseous substance to pass through the gas adsorption columns to remove a component to be removed contained in the gaseous substance, the gas purification apparatus being configured so as to be able to partially pass the gaseous substance through the gas adsorption columns.