Posture change jig and arch timbering transshipment method

The posture changing jig allows for the efficient and safe transformation of arch supports during transportation by suspending and rotating them using a winch, addressing the inefficiencies and risks of existing methods.

JP2024134810AInactive Publication Date: 2024-10-04NIPPON MAINTENANCE CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023045193
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-22
Publication Date
2024-10-04
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing methods for changing the posture of arch supports during transportation are complex, costly, and risky, requiring temporary storage and rehanging, which increases time and safety hazards.

Method used

A posture changing jig that includes a main body, first and second wires, a sheave, and a winch, allowing the posture of an arch support to be changed while suspended by rotating the main body using the winch, eliminating the need for temporary storage and rehanging.

Benefits of technology

The jig enables safe, efficient, and cost-effective posture change of arch supports without temporary storage or rehanging, reducing work time and risk of damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024134810000001_ABST
    Figure 2024134810000001_ABST
Patent Text Reader

Abstract

To provide a posture change jig for changing a posture in a state where an object such as an arch timbering is suspended with a simple structure.SOLUTION: This posture change jig interposed between a crane and an object to change a posture in a state where the object is suspended comprises at least: a body 10; a first wire 20 moored from at least two points of the body 10 to a hook of the crane; a sheave 30 provided in the body 10; a second wire 40 moored at one end to the hook and wound at the midway on the sheave 30; a winch 50 to which the other end of the second wire 40 is connected to be wound up; and a third wire 60 provided in the body 10 to be able to suspend the object. The posture of the object suspended by the third wire 60 can be changed through rotation of the body 10 based on winding-up of the second wire 40.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a position changing tool for changing the position of an object such as an arch support while it is suspended, and a method for transferring an arch support using the position changing tool. [Background technology]

[0002] Arch-shaped supports (also called "arch supports") used in tunnel construction and other work are transported to the construction site loaded sideways on the bed of a truck or other vehicle, then turned upright and transferred to the bed of another vehicle for transport into the tunnel. In the conventional method for this operation, as shown in Figure 4, the arch support was first lifted up in a horizontal position mounted on a loading platform (Figure 4(a)), then temporarily placed on the ground in this horizontal position (Figure 4(b)), and then the position was changed by changing the rigging position and re-hanging it (Figure 4(c)), before being transferred to the loading platform of another vehicle (Figure 4(d)).

[0003] Another example of a device for changing the posture of an object being lifted is the posture switching device described in Patent Document 1 below. However, when trying to apply this position changing device to, for example, arch support, the components of the position changing device (rails, steel plates, etc.) need to be processed into a shape that corresponds to the arc surface of the support, which places a limit on how much manufacturing costs can be reduced. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent No. 7102236 Summary of the Invention [Problem to be solved by the invention]

[0005] An object of the present invention is to provide a means for realizing, with a simple structure, a change in the position of an object such as an arch support while it is suspended. [Means for solving the problem]

[0006] The present invention, which has been made to solve the above-mentioned problems, is a posture change tool that is placed between a crane and an object to change the posture of the object while it is suspended, and is characterized in that it comprises at least a main body, a first wire that is moored to the hook of the crane from at least two points of the main body, a sheave provided on the main body, a second wire that has one end moored to the hook and is wound around the sheave in the middle, a winch to which the other end of the second wire is connected and capable of winding up the object, and a third wire provided on the main body and capable of suspending the object, and that the posture of the object suspended by the third wire can be changed by rotating the main body by winding up the second wire. In addition, when the target object of the present invention is an arch support, the hanging points of the third wire can be set at three locations: the top and the left and right sides of the arch support. In addition, the present invention can be configured so that the main body portion comprises a beam material made of a long member and an extension material extending in a direction perpendicular to the longitudinal direction of the beam material when viewed in a plane, the first wire is provided on the upper surface of the beam material, the sheave is provided on the upper surface of the extension material, the winch is provided on the upper surface of the beam material or on the upper surface of the extension material, and the third wire is provided on the lower surface of the beam material. The present invention also relates to a method for transferring arch supports, in which arch supports loaded horizontally are transferred in an upright position, and is characterized in that the above-mentioned position change jig is attached to a crane, the position change jig is positioned above the arch supports loaded horizontally, the arch supports are sling-hooked using the third wire, the arch supports are hoisted in their horizontal position, the winch is wound up, the arch supports are transitioned to an upright position, and then transferred at the transfer destination. Effect of the Invention

[0007] The present invention has at least one of the following effects. (1) The position of the object can be changed while it is suspended, in conjunction with the change in position of the main body. (2) There is no need to temporarily place the objects or re-rig the rigging during the transfer work, which reduces the time required for the work. (3) There is no need to re-hang the device when changing its position, which increases safety. (4) It is possible to avoid the risk of the object becoming dirty or damaged due to temporary placement in order to change its position. (5) The posture of the object can be changed by simply operating the winch, without the need for complicated operations. (6) The manufacturing of the posture-changing jig does not require complex processing such as machining the main body into an arc shape, which leads to a reduction in manufacturing costs. [Brief description of the drawings]

[0008] [Figure 1] FIG. 1 is a schematic perspective view showing an example of a position changing jig according to the present invention. [Diagram 2] 10A to 10C are schematic diagrams showing the transition of attitude change of the main body and the target object due to the operation of the winch. [Diagram 3] FIG. 1 is an image diagram of a method for transferring arch supports according to the present invention. [Figure 4] An illustration of the conventional method of transferring arch supports. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, embodiments of the present invention will be described with reference to the drawings. EXAMPLES

[0010] <1> Overall configuration (Fig. 1) The position changing jig according to the present invention is a jig used for changing the position of a suspended object while it remains in a suspended state. In the present invention, the object is not particularly limited, and includes any object that requires a change in position while in a suspended state. Note that in this embodiment, an arch support is assumed as the object to be suspended. The position changing jig according to the present invention is configured to at least include a main body 10, a first wire 20, a sheave 30, a second wire 40, a winch 50, and a third wire 60. In the following description, the X-axis shown in FIG. 1 is defined as the left-right direction, the Y-axis as the front-rear direction, and the Z-axis as the up-down direction. Each component will be described in detail below.

[0011] <2> Main body (Fig. 1) The main body 10 is a member that corresponds to the main body of the position changing jig. In the present invention, the shape of the main body 10 is not particularly limited, and may be selected from a flat plate shape, a frame shape, a T-shape, and the like. In this embodiment, the shape of the main body 10 is T-shaped in a plan view, consisting of a beam 11 made of a long member with its longitudinal direction in the left-right direction, and a protruding member 12 extending from the longitudinal direction of the beam 11 in a direction perpendicular to the horizontal direction (front-to-back direction).

[0012] <2.1> Hanging part Furthermore, in the present invention, the main body 10 is provided with a suspending portion between the main body 10 and a crane, and a suspending portion between the main body 10 and an object. In the present invention, the positions at which the hanging portions are provided are not particularly limited and may be designed as appropriate. In this embodiment, two hanging points are provided on the upper surface of the beam 11 for connection to the crane, and two hanging points are provided on the lower surface of the beam 11 and one hanging point on the lower surface of the protruding member 12 for connection to the target object (arch support structure A).

[0013] <3> First Wire (Figure 1) The first wire 20 is a member for connecting the crane and the main body 10. At least two first wires 20 are provided. In this embodiment, one end of the first wire 20 is anchored to each of two hanging parts provided at an interval in the longitudinal direction of the beam material 11 constituting the main body 10. The other end of each of the first wires 20 is anchored to a hook of a crane.

[0014] <4> Sieve (Fig. 1) The sheave 30 is a member for winding the second wire 40 therearound. The sheave 30 is provided at a position displaced in the front-rear direction from an imaginary line connecting the hanging parts that anchor the first wire 20 on the upper surface of the main body 10. In this embodiment, a sheave 30 is provided on the upper surface of the extension member 12 that constitutes the main body portion 10.

[0015] <5> Second Wire (Figure 1) The second wire 40 is a member that connects the crane and the winch 50 . One end of the second wire 40 is moored to the hook of the crane, the second wire 40 is wound around the sheave 30 in the middle, and the other end of the second wire 40 is connected to the winch 50. In this embodiment, one second wire 40 is provided. Therefore, in this embodiment, the two first wires 20 and one second wire 40 suspend the main body 10 at three points.

[0016] <6> Winch (Fig. 1) The winch 50 is a member for winding and unwinding the second wire 40 . The winch 50 is configured to connect the other end of the second wire 40 that is routed through the sheave 30 . In this embodiment, a winch 50 is fixed to the upper surface of the extension member 12 constituting the main body portion 10 at a location closer to the beam member 11 side than the sheave 30 is. With this configuration, the length of the second wire 40 can be adjusted by winding and unwinding the second wire 40 with the winch 50. To explain in more detail, when the second wire 40 is wound up with the winch 50, the main body 10 changes its position so that the sheave 30 side is pulled upward, and when the second wire 40 is unwound with the winch 50, the main body 10 changes its position so that the sheave 30 side falls downward. Normally, the length of the second wire 40 is adjusted so that the beam members 11 and the overhanging members 12 that constitute the main body portion 10 are in a substantially horizontal state.

[0017] <7> Third Wire (Figure 1) The third wire 60 is a member for connecting the main body 10 and the target object. The third wire 60 is provided on the main body 10 and is configured to be able to suspend an object. In this embodiment, one end of a third wire 60 of equal length is moored to three locations: two locations spaced a predetermined distance apart on the underside of the beam material 11 and one location on the underside of the projection material 12. Each third wire 60 is lowered vertically, and the other end of each third wire 60 is moored to the top and left and right sides of the target object, the arch support structure A. With this configuration, when the main body 10 is maintained in a horizontal state, the target object (arch support A) is also suspended while maintaining a horizontal state.

[0018] <8> Posture change image (Figure 2) Next, the change in posture of the main body 10 and the target arch support A caused by the operation of the winch 50 will be described.

[0019] <8.1> Horizontal (Fig. 2(a)) When the length of the second wire 40 is adjusted so as to keep the main body 10 approximately horizontal, the arch support A suspended from the main body 10 is also kept approximately horizontal.

[0020] <8.2> When winding (Fig. 2(b)) When the second wire 40 is started to be wound up with the winch 50 from a horizontal position, the sheave 30 side of the projection 12 that constitutes the main body 10 is pulled upward, and the main body 10 and the arch support A suspended from the main body 10 gradually rotate counterclockwise on the page in Figure 2.

[0021] <8.3> When hoisting is completed (Figure 2(c)) When the second wire 40 is further wound up, the main body 10 and the arch support A rotate about 90 degrees from the horizontal state and become substantially upright.

[0022] <8.4> When unwinding Furthermore, it goes without saying that if the second wire 40 is paid out by the winch 50 from the state <8.3>, the state will return sequentially to the state <8.2> and then to the state <8.1>.

[0023] <9> Example of use (Fig. 3) Next, the procedure for the method of transferring arch supports using the posture changing jig according to this embodiment will be described. In the present invention, the location from which the arch support is transferred and the location to which it is transferred are not particularly limited, and the invention can be applied to vehicle loading platforms, temporary storage yards, slide centers, etc. In this embodiment, it is assumed that the arch support A, which is loaded horizontally on the loading platform of a vehicle C1 outside the tunnel, is raised up in the air to an upright position and then transferred to the loading platform of another vehicle C2.

[0024] <9.1> Installation of posture change jig (Fig. 3(a)) First, the position changing jig according to this embodiment is attached to the hook of the crane B. At this time, the third wire 60 may be anchored to the main body 10 in advance, or may be anchored to the main body 10 after the position changing jig is positioned above the arch support A described below. In addition, the winch 50 is operated to adjust the length of the second wire 40 so that the main body 10 is maintained in a horizontal state.

[0025] <9.2> Lifting of arch support (Fig. 3(a)) Next, the crane B is operated to position the posture changing jig above the arch support A loaded on the vehicle C1. Thereafter, a third wire 60 is used to sling the arch support A, and the arch support A is hoisted by crane B while maintaining its horizontal position.

[0026] <9.3> Winching (Fig. 3(b)) After the lifted arch support A is moved onto the loading platform of another vehicle C2, which is the transfer destination, the second wire 40 is wound up with a winch 50, and the arch support A is rotated to bring it closer to a vertical position. In addition, in the present invention, immediately after being hoisted from the vehicle C1, the posture of the arch support may be changed and then it may be moved to another vehicle C2.

[0027] <9.4> Unpacking work (Fig. 3(c)) When the arch support A is in an upright position to the extent that it does not interfere with unpacking, the arch support A is lowered onto the vehicle C2 by the crane B, and the slinging by the third wire 60 is removed to carry out the unpacking work. [Explanation of symbols]

[0028] 10: Main body 11: Beam material 12: Overhang material 20: First wire 30: Sheaves 40: Second Wire 50: Winch 60: Third Wire A: Arch support B: Crane C1, C2: Vehicle

Claims

1. A posture change tool that is interposed between a crane and an object to change the posture of the object while it is suspended, A main body portion, a first wire that is anchored from at least two points of the body to a hook of the crane; A sheave provided in the main body; a second wire, one end of which is anchored to the hook and the other end of which is wound around the sheave; a winch capable of winding up the other end of the second wire; a third wire provided on the main body and capable of suspending the object; At least The posture of the object suspended by the third wire can be changed by rotating the main body by winding up the second wire. Posture change jig.

2. The object is an arch support, The third wire is hung at three points on the top and left and right sides of the arch support. The position changing jig according to claim 1 .

3. The main body portion is A beam material made of a long member; A protruding member extending in a direction perpendicular to the longitudinal direction of the beam member in a plan view; The first wire is provided on an upper surface of the beam material; The sheave is provided on an upper surface of the protruding member, The winch is provided on an upper surface of the beam material or an upper surface of the protruding material, The third wire is provided on the lower surface of the beam material. The position changing jig according to claim 1 .

4. A method for transferring arch supports, in which arch supports loaded sideways are transferred in an upright position, The posture changing jig according to any one of claims 1 to 3 is attached to a crane, The posture changing jig is positioned above the arch support that is loaded sideways, and the third wire is used to sling the arch support, and the arch support is lifted up while it is lying sideways. The winch is hoisted up, the arch support is raised, and then the load is transferred to the transfer destination. How to transfer arch supports.

Citation Information

Patent Citations

  • Posture switching device

    JP7102236B2