Distributer

The distributor system addresses the excessive manual labor of relocating fixing members by using a suspension device to lift and move these components, reducing the worker's burden during relocation.

JP2024138966AActive Publication Date: 2024-10-09KYOKUTO KAIHATSU IND
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2023049705
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-27
Publication Date
2024-10-09
Estimated Expiration
2043-03-27

AI Technical Summary

Technical Problem

The burden on workers is excessive when manually carrying multiple fixing members and separate parts during the relocation of a ready-mixed concrete distributor between construction floors.

Method used

A distributor system with a suspension means that allows fixing members and separate parts to be lifted and moved to the next upper floor using a crane, minimizing manual labor by incorporating a suspension device that can suspend and move these components.

Benefits of technology

Reduces the labor required for relocating the distributor by enabling the lifting and transport of fixing members and other parts to upper floors, thereby alleviating the worker's burden.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024138966000001_ABST
    Figure 2024138966000001_ABST
Patent Text Reader

Abstract

To provide a distributor that supplies ready mixed concrete to a desired location (a pouring site) and is capable of reducing the burden on workers when replacing the distributor.SOLUTION: A distributor 1 comprises a base device 10, a mast device 20 supported by the base device 10, and a boom device 30 arranged on an upper end of the mast device 20, and supplies ready-mixed concrete to a desired location via a transport pipe 32 provided on the boom device 30. The base device 10 has a base body 11, at least one outrigger 12 provided to be horizontally deployable from the peripheral edge of the base body 11, and fixing members 13 which fix the base device 10 to a floor surface F by clamping the outriggers 12 between the fixing members 13 and the floor surface F, the number of the fixing members 13 being equal to the number of outriggers 12. The distributor 1 further comprises a suspension device 6 capable of suspending the fixing members 13.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a distributor that supplies ready-mixed concrete to a desired location (a pouring site). [Background technology]

[0002] Conventionally, there has been known a distributor that comprises a base portion fixed to a floor surface, a mast portion supported in an upright position on the base portion, and a bendable and swingable boom portion positioned at the upper end of the mast portion, and that supplies ready-mixed concrete to a desired location (pouring site) via a transport pipe installed along the boom portion (see, for example, Patent Document 1). In the above-mentioned distributor, various methods are known for fixing the base part to the floor surface. One example is a method in which multiple fixing members extending in one direction are prepared in advance as separate parts, and the fixing members are each placed in a crossed state on the upper surfaces of multiple outriggers deployed from the base part, and then both ends of each fixing member are fixed to the floor surface using anchor bolts, etc., so that the outriggers are clamped between the fixing members and the floor surface.

[0003] Here, for example, when a distributor is used to supply ready-mix concrete (pouring work) at a construction site of a building or the like, typically, concrete is poured onto the floor surface (floor slab) of a specified level (e.g., the first level) to construct a reinforced concrete floor slab, and then a crane or the like is used to transfer the distributor to the floor surface (floor slab) of the next upper level (e.g., the second level) (hereinafter referred to as "reloading"). Then, while repeating the above-mentioned replacement, the distributor pours concrete onto the floor surface (floor slab) of each story in sequence, thereby constructing the reinforced concrete floor slabs on each story in sequence. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent Publication No. 2022-92129 Summary of the Invention [Problem to be solved by the invention]

[0005] When replacing a distributor, the multiple fixing members that fixed the base to the floor surface of a specified floor are removed, and then the distributor body is lifted by a crane or the like and moved to the floor surface of the next higher floor. However, the multiple fixing members that were removed must be manually carried up to the next higher floor by workers, which places an excessive burden on the workers.

[0006] The present invention has been made in consideration of the current problems described above, and has an objective of providing a distributor that supplies ready-mixed concrete to a desired location (pouring site) and that can reduce the burden on workers when replacing the distributor. [Means for solving the problem]

[0007] The problem to be solved by the present invention has been described above, and the means for solving this problem will now be described.

[0008] That is, the distributor of aspect 1 of the present invention comprises a base portion, a mast portion supported in an upright state on the base portion, and a boom portion arranged on the upper end of the mast portion, and the boom portion has a boom row consisting of a plurality of boom sections connected in series and capable of bending and swinging relative to each other, a transport pipe arranged along the boom row, and a support base that supports the base of the boom row in a manner that allows it to be raised and lowered, and supplies ready-mixed concrete to a desired location via the transport pipe, and the base portion has a main body portion, at least one or more outriggers that are arranged to be horizontally deployable from the periphery of the main body portion, and at least the same number of fixing members as the outriggers that fix the base portion to the floor surface by clamping each of the outriggers between the base portion and the floor surface, and the distributor further comprises a suspension means capable of suspending the fixing members. With this configuration, when the distributor is replaced, the distributor body can be hoisted and moved to the next higher floor by a crane or the like, and then the hoisting means can be used to hoist and move the removed fixing members and other parts such as the extension piping connected to the transport pipe of the boom section to the next higher floor. Therefore, the labor required for the worker to manually carry the fixing members and the other parts to the upper floors can be minimized, and the burden on the worker when replacing the distributor can be reduced.

[0009] Furthermore, the distributor of aspect 2 of the present invention is characterized in that, in the above-mentioned aspect 1, the base portion is fixed to the floor surface of the first level, and the suspension means is provided above the floor surface of the second level, which is the next level above the first level. With this configuration, for example, additional fixing members can be prepared in advance on the floor surface of the second level, and when the distributor is to be rearranged, the distributor body can be moved from the first level to the second level, and the base part can be fixed on the floor surface of the second level using these added fixing members. After that, the fixing members used on the floor surface of the first level can be hoisted and carried by the suspending means, skipping a level to the third level, which is the next level above the second level.

[0010] In addition, the distributor of aspect 3 of the present invention is characterized in that, in the above-mentioned aspect 1, the suspension means is provided at a position of a predetermined height relative to the floor surface to which the base portion is fixed, so as to be able to suspend the fixed member at least up to above the outrigger. With this configuration, when replacing the distributor, the fixing member can be removed while it is suspended by the hanging means, and the fixing member can be used to clamp the outriggers and fix the base part to the floor surface, making it easy to remove, attach, and fix the base part. Furthermore, by suspending them by the suspending means, the fixed members and the separate parts can be easily moved on the floor surface.

[0011] Furthermore, a distributor according to aspect 4 of the present invention is characterized in that, in any of aspects 1 to 3 above, the mast portion has a hook portion protruding from the side, and the suspension means is provided on the hook portion. Here, a number of hook portions that can be connected to a wire or the like are provided in advance on the side of the mast section, and, for example, when the mast section is transported to a specified site, the mast section is lifted in a reclining position by a crane or the like via the wires connected to the hook portions. In addition, once the distributor starts supplying ready-mixed concrete (pouring work), the hook portion is not used until the pouring work is completed, including when the distributor is replaced. According to the distributor of aspect 4 of the present invention, since the suspension means is provided using, for example, the above-mentioned hook portion, there is no need to provide a separate mounting structure for mounting to the mast portion, and the number of parts constituting the suspension means can be reduced.

[0012] Furthermore, a distributor according to aspect 5 of the present invention is characterized in that, in any of aspects 1 to 3 above, the suspension means has an arm member extending horizontally from the side of the mast section, a winch capable of suspending the fixed member in an upward and downward direction, and a connecting member for connecting the winch at one end of the arm member in the extending direction, and in a planar view, the end face of the arm member in the extending direction is located closer to the axis of the mast section than the outer edge of the main body of the base section. With this configuration, when a distributor is rearranged, the arm member of the suspension means can be prevented from interfering with the floor surface of the next upper floor when the distributor is lifted by a crane or the like through an opening provided on each floor and moved to the next upper floor. Effect of the Invention

[0013] The present invention has the following advantages. That is, the distributor according to the present invention can reduce the burden on the worker when changing the distributor. [Brief description of the drawings]

[0014] [Figure 1] 1 is a side view showing an overall configuration of a distributor according to an embodiment of the present invention; [Diagram 2] 2(a) and 2(b) are diagrams showing the configuration of a base device, in which (a) is a side view and (b) is a plan view seen in the direction of an arrow X2 in FIG. 2(a). [Diagram 3] 1A and 1B are diagrams showing the configuration of a mast assembly, in which FIG. 1A is a side view and FIG. [Figure 4] FIG. 2 is a side view showing the configuration of the boom device. [Diagram 5] FIG. 4 is a diagram showing the configuration of the suspension device, and is an enlarged front view of the range indicated by region X1 in FIG. [Figure 6] 6 is an enlarged side view taken in the direction of the arrow X3 in FIG. 5, showing the configuration of the suspension device. FIG. [Figure 7] FIG. 11 is a diagram for explaining the work procedure when changing the number of fixing parts when there is one set, where (a) is a side view showing the state immediately before the distributor is moved to the upper floor, and (b) is a side view showing the state immediately after the distributor has been moved to the upper floor. [Figure 8] FIG. 11 is a diagram for explaining the work procedure when changing the number of fixing parts being two sets, where (a) is a side view showing the state immediately before the distributor is moved to the upper floor, and (b) is a side view showing the state immediately after the distributor has been moved to the upper floor. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] Next, one embodiment of the present invention will be described with reference to FIGS. For the sake of convenience, in the following description, the side on which the suspension device 6 is provided is referred to as the front side, and the front-rear, left-right, and up-down directions of the distributor 1 are defined by the directions of the arrows shown in Figures 1 to 8.

[0016] [Overall configuration of Distributor 1] First, the overall configuration of a distributor 1 embodying the present invention will be described with reference to FIGS. 1 to 4. FIG.

[0017] The distributor 1 in this embodiment is a device that receives ready-mixed concrete for constructing the framework of a structure (e.g., floor slabs, walls, etc.) from a concrete pump (not shown) located on the ground at a construction site such as a building, and supplies the ready-mixed concrete to various locations at a pouring site located at an elevated position. As shown in FIG. 1, the distributor 1 mainly includes a base device 10, a mast device 20, and a boom device 30, which are arranged in this order from bottom to top.

[0018] The base device 10 is an example of a base portion according to the present invention, and is a device for fixing the distributor 1 to a desired floor surface F. The base device 10 has a base body 11, an outrigger 12, and a fixing member 13.

[0019] The base main body 11 is an example of a main body portion according to the present invention, and serves as a base for the base device 10. As shown in Figures 2(a) and (b), the base body 11 has a square tube portion 11a consisting of a hollow square tube member having a rectangular cross-section, an upper frame 11b and a lower frame 11c consisting of a rectangular frame-shaped member, and a vertical wall portion 11d that supports the upper frame 11b and the lower frame 11c from the square tube portion 11a. The rectangular tube portion 11a is made of a material substantially equivalent to a mast member piece 21a, which will be described later.

[0020] The rectangular tube portion 11a is arranged in an upright state, and an upper frame 11b and a lower frame 11c are arranged on the periphery thereof coaxially with the rectangular tube portion 11a and parallel to each other in the up-down direction. In addition, when viewed in a plan view, the vertical wall portions 11d-11d-11d-11d are each arranged to extend radially from multiple (in this embodiment, four) corners of the angular tube portion 11a, and the ends of the extending direction of each vertical wall portion 11d are each connected to multiple (in this embodiment, four each) corners of the upper frame 11b and the lower frame 11c.

[0021] An upper bearing portion 11e is provided at each corner of the upper frame 11b (that is, the connection portion with the vertical wall portion 11d). Furthermore, lower bearing portions 11f are provided at each corner of the lower frame 11c (that is, the connection portions with the vertical wall portion 11d).

[0022] An upper bearing member 11e1 made of a bushing, a bearing, or the like is fitted into each upper bearing portion 11e with the axial direction being the up-down direction. Similarly, a lower bearing member 11f1 made of a bushing, bearing, or the like is fitted into each lower bearing portion 11f with its axial direction extending vertically. The upper bearing member 11e1 and the lower bearing member 11f1 are arranged coaxially with each other.

[0023] A plurality of (eight in this embodiment) joining blocks 5·5··· (more specifically, convex joining blocks 51·51··, which will be described later) are provided on the upper end of the rectangular tube portion 11a. The multiple convex joint blocks 51 are arranged at predetermined intervals on each side surface at the upper end of the rectangular tube portion 11a in a state where they protrude upward. Furthermore, these multiple convex side connecting blocks 51·51··· are configured to be able to fit into multiple concave side connecting blocks 52·52··· provided at the lower end of the lowest mast member piece 21a, as described below.

[0024] Further, a plurality of support legs 11c1·11c··· that can be grounded are provided on the lower surface of the lower frame 11c so as to protrude downward.

[0025] The outriggers 12 are used when fixing the base device 11 to a desired floor surface F. The outrigger 12 has, for example, an outrigger main body portion 12a made of a rectangular parallelepiped member extending in one direction, and a housing portion 12b made of a substantially hollow cylindrical member.

[0026] The housing portion 12b is provided at one end in the longitudinal direction of the outrigger main body portion 12a, and is formed integrally with the outrigger main body portion 12a with the axial direction being the width direction (in this embodiment, the up-down direction) which is perpendicular to the longitudinal direction.

[0027] At least one outrigger 12 is provided for the base body 11. For example, in this embodiment, the outriggers 12 are provided in the same number (four) as the corners of the upper frame 11b (or the lower frame 11c). Further, each outrigger 12 is coaxially disposed between an upper bearing portion 11e of the upper frame 11b and a lower bearing portion 11f of the lower frame 11c via a housing portion 12b. Furthermore, each outrigger 12 is connected to an upper bearing member 11e1 of the upper bearing portion 11e and a lower bearing member 11f1 of the lower bearing portion 11e via a rotating shaft 14, and is configured to be rotatable around the rotating shaft 14.

[0028] The outrigger 12 is configured to be displaceable between a stored position P1, in which it fits within the space between the upper frame 11b and the lower frame 11c, by rotating about the pivot axis 14, and a maximum deployed position P2, in which it extends horizontally toward the outside of the base body 11 along one side of the upper frame 11b (or the lower frame 11c). In other words, the outrigger 12 is provided so as to be able to be deployed in the horizontal direction from the periphery of the base body 11 (more specifically, from the upper bearing portion 11e or the lower bearing portion 11f).

[0029] The fixing member 13 fixes the base device 10 to a desired floor surface F via the outriggers 12. The fixing member 13 is, for example, a member having a rectangular parallelepiped shape extending in one direction, and through holes 13a, 13a are provided at both ends in the longitudinal direction, penetrating in a direction perpendicular to the longitudinal direction. Furthermore, the fixing member 13 is provided at both end surfaces in the longitudinal direction with hook portions 13b, 13b which can be connected to a wire or the like.

[0030] The fixing members 13 are provided in a number at least equal to the number of the outriggers 12 (four in this embodiment).

[0031] Each fixing member 13 is placed on the upper surface of each outrigger 13 deployed from the peripheral edge of the base body 11 in a state in which it crosses the outrigger 13 in a plan view. Furthermore, while the fixing member 13 is placed on the upper surface of the outrigger 13, it is fixed to the floor surface F by a pair of fastening members 15, 15 made of anchor bolts or the like via the through holes 13a, 13a. As a result, the outriggers 13 are firmly clamped between the fixing members 13 and the floor surface F, and the base device 11 is fixed to the desired floor surface F by the fixing members 13.

[0032] The mast device 20 is an example of a mast section according to the present invention, and is a device that supports the boom device 30 directly above the base device 10. As shown in FIGS. 3(a) and 3(b), the mast assembly 20 includes a mast member 21, a ladder 22, a work platform 23 (see FIG. 1), and a mast side connecting pipe 24.

[0033] The mast member 21 forms the base of the mast assembly 20 . The mast member 21 is made of a hollow square tubular member having a rectangular cross section, and has a divided structure in which it is divided into predetermined lengths along the longitudinal direction. In other words, the mast member 21 is composed of multiple mast member pieces 21a (two in this embodiment) connected in series to each other toward one side, and by increasing the number of mast member pieces 21a, the overall length (or overall height) of the mast assembly 20 can be made longer (or higher), and by reducing the number of mast member pieces 21a, the overall length (or overall height) of the mast assembly 20 can be made shorter (or lower). The mast member piece 21a is made of substantially the same material as the square tube portion 11a of the base body 11 described above.

[0034] A plurality of (eight in this embodiment) connecting blocks 5·5··· are provided on both longitudinal ends of each mast member piece 21a. Here, each joint block 5 is composed of a convex joint block 51 having a protrusion 51a, and a concave joint block 52 having a recess 52a into which the protrusion 51a can be fitted. The convex joint block 51 and the concave joint block 52 are provided with a plurality of through holes (not shown) that pass through each other coaxially when they are fitted together.

[0035] In each mast member piece 21a, on each side surface at one end in the longitudinal direction, a plurality of convex side connecting blocks 51·51··· are arranged at a predetermined interval with their protrusions 51a·51a··· protruding. In addition, in each mast member piece 21a, on each side surface at the other end in the longitudinal direction, a plurality of concave side connecting blocks 52·52··· are arranged at a predetermined interval, with the recesses 52a·52a··· positioned at the points protruding from the other end of the mast member piece 21a.

[0036] A number of mast member pieces 21a·21a having this configuration are arranged in series with the convex connecting block 51 provided on one mast member piece 21a and the concave connecting block 52 provided on the other mast member piece 21a fitted together, and are fastened together by fastening members such as bolts through the multiple through holes. In this way, the mast member 21 is constructed from the multiple mast member pieces 21a.

[0037] The constructed mast member 21 is then stood up with the multiple convex side connecting blocks 51·51··· facing upward and the multiple concave side connecting blocks 52·52··· facing downward, and is placed on the upper end of the angular tube portion 11a of the base device 10. As described above, a plurality of convex side connecting blocks 51·51··· are provided at the upper end of the angular tube portion 11a, and the mast member 21 is fixed to the angular tube portion 11a by fastening the convex side connecting blocks 51·51··· and the plurality of concave side connecting blocks 52·52··· provided at the lower end of the lowest mast member piece 21a with each other engaged with the convex side connecting blocks 51·51··· and fastening them to each other with fastening members through the plurality of through holes. As a result, the mast device 20 is supported in an upright position relative to the base device 10.

[0038] The ladder 22 is used when an operator ascends and descends along the mast device 20 in the distributor 1 fixed to a floor surface F (see FIG. 1). The ladder 22 is set to a length approximately equal to the longitudinal dimension of the mast member piece 21a, and is fixed along one side surface 21a1 of each mast member piece 21a (for example, the front side surface 21a1 in this embodiment).

[0039] The workbench 23 is a stand on which an operator performs various tasks, and is fixed to the upper end of the mast device 20 (more specifically, to the upper end of the uppermost mast member piece 21a) in the distributor 1 which is fixed to the floor surface F, as shown in FIG. The various types of work performed on the work platform 23 include, for example, connecting the mast device 20 and the boom device 30 when transporting them to a specified site, connecting various pipes, inspecting and servicing the boom support base 33, and maintenance work such as refueling.

[0040] The mast side connecting pipe 24 guides the ready mixed concrete supplied from the concrete pump to a boom side connecting pipe 33c of the boom device 30 described later. The mast side connection piping 24 has a plurality of piping members 24a arranged in series, and a plurality of joint members 24b that connect adjacent piping members 24a in a liquid-tight manner.

[0041] Here, in this embodiment, the length of each piping member 24a is set to approximately half the longitudinal dimension of each mast member piece 21a, and for example, for a mast member piece 21a with a total length of 4 m, the length of each piping member 24a is set to approximately 2 m.

[0042] As shown in Figures 3(a) and (b), two piping members 24a·24a connected in series are pre-supported on the front side surface 21a1 of each mast member piece 21a via a number of support members 25·25··. When connecting multiple (two) mast member pieces 21a·21a to construct the mast member 21, the opposing ends of the piping members 24a·24a supported by one mast member piece 21a and the piping members 24a·24a supported by the other mast member piece 21a are newly connected by joint member 24b to construct the mast side connection piping 24.

[0043] As described later, the upper end of the piping member 24a supported by the uppermost mast member piece 21a is connected to a boom side connection pipe 33c of the boom device 30. In addition, when the distributor 1 is performing the operation of supplying ready-mixed concrete (pouring operation), the lower end of the piping member 24a supported by the lowest mast member piece 21a is connected to a concrete pressure pipe (not shown) extending from the concrete pump.

[0044] In the mast assembly 20, one side of each mast member piece 21a (for example, the front side surface 21a1 in this embodiment) is provided with a plurality of hook portions 21a2-21a2 (two in this embodiment) protruding from the front side surface 21a1. The hook portion 21a2 is a part used when suspending each mast component piece 21a in a lying position by a crane or the like, for example, when transporting the mast assembly 20 to a specified site, and is configured to be connectable to a wire, etc.

[0045] In this embodiment, when the distributor 1 is replaced, a suspension device 6 is provided for suspending the removed multiple fixing members 13·13··· (see Figure 2), and the suspension device 6 is attached to each mast member piece 21a via the hook portion 21a2. The configuration of the suspension device 6 will be described in detail later.

[0046] The boom device 30 is an example of a boom section according to the present invention, and is a device that guides the ready-mixed concrete supplied from the concrete pump to a desired location (a pouring site). As shown in FIG. 4, the boom device 30 has a boom row 31, a transport pipe 32, and a boom support base 33.

[0047] The boom array 31 supports a transport pipe 32 . The boom array 31 comprises a plurality of boom pieces consisting of a first boom piece 31a, a second boom piece 31b, a third boom piece 31c, and a fourth boom piece 31d, which are arranged in series in order and connected to each other using a connecting member or the like not shown so that they can bend and swing, and a first actuator 31e, a second actuator 31f, a third actuator 31g, and a fourth actuator 31h, which are composed of, for example, hydraulic cylinders, and which move the plurality of boom pieces.

[0048] The multiple boom sections are connected at the base end of the first boom section 31a (more specifically, the end opposite the second boom section 31b) via a pivot shaft 34 to the upper end of the boom support base 33 (more specifically, the swivel base 33b described later) so as to be rotatable in the vertical direction. Furthermore, via the above-mentioned connecting member, the second boom piece 31b is capable of rotating relative to the first boom piece 31a in the vertical direction, the third boom piece 31c is capable of rotating relative to the second boom piece 31b in the vertical direction, and the fourth boom piece 31d is capable of rotating relative to the third boom piece 31c in the vertical direction.

[0049] The first actuator 31e is positioned between the boom support base 33 (more specifically, the swivel base 33b) and the first boom section 31a, the second actuator 31f is positioned between the first boom section 31a and the second boom section 31b, the third actuator 31g is positioned between the second boom section 31b and the third boom section 31c, and the fourth actuator 31h is positioned between the third boom section 31c and the fourth boom section 31d.

[0050] In the boom row 31 configured as described above, the first actuator 31e, the second actuator 31f, the third actuator 31g, and the fourth actuator 31h each move independently in extension and contraction, causing the multiple boom pieces (the first boom piece 31a, the second boom piece 31b, the third boom piece 31c, and the fourth boom piece 31d) to bend and swing independently of each other.

[0051] The transport pipe 32 transports the ready-mixed concrete and discharges the ready-mixed concrete to a desired location (a pouring site). The transport pipe 32 has a first transport pipe 32a provided along the first boom section 31a, a second transport pipe 32b provided along the second boom section 31b, a third transport pipe 32c provided along the third boom section 31c, and a fourth transport pipe 32d provided along the fourth boom section 31d.

[0052] An end of the first transport pipe 32a and an end of the second transport pipe 32b are liquid-tightly connected to each other via a joint member (not shown) so as to be capable of rotating relative to each other. Similarly, an end of the second transport pipe 32b and an end of the third transport pipe 32c are liquid-tightly connected to each other via a joint member (not shown) so as to be capable of rotating relative to each other. Furthermore, an end of the third transport pipe 32c and an end of the fourth transport pipe 32d are similarly connected in a liquid-tight manner via a joint member (not shown) so as to be capable of relative rotation.

[0053] As described later, the end of the first transport pipe 32a on the boom support base 33 side is connected to a boom side connecting pipe 33c provided on the boom support base 33.

[0054] The boom support base 33 is an example of a support base according to the present invention, and serves as a base for the boom device 30. The boom support base 33 has a fixed base 33a fixed to the upper end of the uppermost mast member piece 21a, a swivel base 33b connected to the upper end of the fixed base 33a so as to be rotatable horizontally, and a boom side connection piping 33c provided along the fixed base 33a and the swivel base 33b.

[0055] The fixed base 33a has a main body frame 33a1 made of a generally hollow square tubular member having a rectangular cross section, and a housing portion 33a2 made of a hollow cylindrical member. The housing portion 33a2 is provided at one end in the longitudinal direction of the main body frame 33a1, and is provided integrally with the main body frame 33a1 with the axial direction being the longitudinal direction. The main body frame 33a1 is made of substantially the same material as the mast member piece 21a described above.

[0056] Furthermore, a plurality of (eight in this embodiment) connecting blocks 5... (more specifically, concave side connecting blocks 52...) are provided on the other end of the main body frame 33a1 in the longitudinal direction. These multiple concave side joining blocks 52·52··· are arranged at a predetermined interval on each side surface at the other end of the main frame 33a1, with the recesses 52a·52a··· positioned at points protruding from the other end.

[0057] The main body frame 33a1 is disposed on the upper end of the mast member 21 (more specifically, the uppermost mast member piece 21a) with the multiple concave side connecting blocks 52 facing downward. As described above, a plurality of convex side connecting blocks 51·51··· are provided on the upper end of the mast member 21, and the main frame 33a1 is fixed to the mast member 21 by fastening the convex side connecting blocks 51·51··· and the plurality of concave side connecting blocks 52·52··· provided on the main frame 33a1 to each other with the convex side connecting blocks 51·51··· fitted into each other and fastening them to each other using fastening members through the plurality of through holes. As a result, the boom assembly 30 is disposed at the upper end of the mast assembly 20.

[0058] The swivel base 33b is made of a generally plate-like member bent into a U-shape, and is disposed on the upper surface of the fixed base 33a with its opening facing upward. The swivel base 33b is connected to the fixed base 33a via a circular ring member (not shown) fitted inside the housing portion 33b1 so as to be rotatable in the horizontal direction.

[0059] The upper end of the swivel base 33b is connected via a rotary shaft 34 to the base end of the first boom section 31a. Moreover, one side end of the swivel base 33b is connected to one end of the first actuator 31e (the end opposite to the first boom section 31a side). In other words, the boom support base 33 axially supports the base of the boom row 31 (more specifically, the base end portion of the first boom section 31a) via the rotating shaft 34 so that the boom can be raised or lowered.

[0060] The boom side connection pipe 33c guides the ready-mixed concrete supplied from the concrete pump to the transport pipe 32. The boom side connection pipe 33c is formed by pipe members connected in a substantially S-shape, and is disposed along the fixed base 33a and the swivel base 33b.

[0061] Specifically, the boom side connection pipe 33c first extends upward along one side of the main frame 33a1 on the fixed base 33a, then bends horizontally to enter the inside of the main frame 33a1, and then bends vertically again to extend upward, passing through the inside of the housing portion 33b1 (more specifically, the above-mentioned circular member) and entering the inside of the swivel base 33b, and then bends horizontally at the upper end of the swivel base 33b and is arranged to protrude outside the swivel base 33b. The boom side connection pipe 33c is divided into two parts at a location located inside the housing portion 33b1, and the two parts are rotatably and liquid-tightly connected via a joint member (not shown).

[0062] The boom side connecting pipe 33c is rotatably and liquid-tightly connected to the end of the transport pipe 32 (more specifically, the first transport pipe 32a) at its end located on the upper end side of the swivel base 33b via a joint member not shown. In addition, the boom side connecting piping 33c, at its end located on the lower end side of the main frame 33a1, is liquid-tightly connected to the upper end of the piping member 24a supported on the uppermost mast member piece 21a via the joint member 24b, as described above.

[0063] [Configuration of suspension device 6] Next, the configuration of the suspension device 6 will be described in detail with reference to FIGS. 2(b), 3(a), 5 and 6. FIG.

[0064] The suspension device 6 is an example of the suspension means according to the present invention, and as described above, is a device that suspends a plurality of removed fixing members 13·13··· (see Figure 2) together, for example when replacing the distributor 1, and hoists and moves these multiple fixing members 13·13··· to an upper floor.

[0065] In addition, the object suspended by the suspension device 6 is not limited to the fixed member 13. For example, a separate part such as an extension pipe (not shown) which is provided between the mast side connection pipe 24 provided on the mast device 20 and the concrete pressure pipe (not shown) and connected to the transport pipe 32 of the boom device 30 via the mast side connection pipe 24 and the boom side connection pipe 33c (see Figure 4) can also be suspended by the suspension device 6.

[0066] As shown in FIG. 6, the suspension device 6 has an arm member 61 that is detachably attached to the mast device 20, a winch 62 supported by the arm member 61, and a connecting member 63 that connects the arm member 61 and the winch 62 to each other.

[0067] The arm member 61 has an arm main body 61a consisting of a member extending in one direction, a connecting portion 61b provided at one end of the arm main body 61a in the longitudinal direction, and an attachment portion 61c provided on the other end side of the arm main body 61a in the longitudinal direction and at one end side perpendicular to the longitudinal direction. The arm member 61 also has a first reinforcing portion 61d that connects and reinforces the arm body 61a and the attachment portion 61c, and a second reinforcing portion 61e that connects and reinforces the connection portion 61b and the attachment portion 61c.

[0068] Here, in this embodiment, for example, a pair of right-angled triangular frame members are fixed to both side surfaces of the arm main body 61a, facing each other and with their respective base portions aligned along the longitudinal direction of the arm main body 61a, and the first reinforcing portion 61d is formed by one side portion of the frame member (a portion perpendicular to the base portions), and the second reinforcing portion 61e is formed by the oblique side portion of the frame member.

[0069] As shown in FIG. 5, the connecting portion 61b has a first through hole 61b1 that simultaneously passes through the pair of frame members and the arm main body 61a in a direction perpendicular to the longitudinal direction of the arm main body 61a. The attachment portion 61c also has a pair of second through holes 61c1 and 61c2 that respectively pass through the pair of frame members in parallel with the first through hole 61b1.

[0070] As shown in Figure 6, the arm member 61 is detachably connected to the hook portion 21a2 of the mast assembly 20 (more specifically, the mast member piece 21a) using a fastening member 64 such as a bolt via the second through hole 61c1 (see Figure 5) of the mounting portion 61c. Furthermore, once the distributor 1 has started supplying ready-mixed concrete (pouring work), the hook portion 21a2 will not be used until the pouring work is completed, at least, including when the distributor 1 is replaced. As a result, the suspension device 6 is mounted on the mast assembly 20 with the arm member 61 (more specifically, the arm body 61a) extending horizontally from the side surface (front side surface 21a1) of the mast member piece 21a of the mast assembly 20.

[0071] As described above, in this embodiment, the mast member piece 21a of the mast device 20 is provided with a hook portion 21a2 protruding from the front side surface 21a1, which is used when suspending the mast in a recumbent position, and the suspension device 6 is configured to be mounted on the hook portion 21a2.

[0072] By having such a configuration, according to the suspension device 6 of this embodiment, there is no need to provide a separate mounting structure for mounting it to the mast device 20, and the number of parts that make up the suspension device 6 can be reduced.

[0073] As shown in FIG. 2(b), in plan view, a distance L1 from the axis G of the square tube portion 11a of the base body 11 (i.e., the axis G of the mast assembly 20) to an end face in the extension direction of the arm member 61 provided on the mast assembly 20 (more specifically, one end face 61a1 in the longitudinal direction of the arm body 61a (see FIG. 6)) is set to be smaller than a distance L2 from the axis G to the outer end face of the upper bearing portion 11e (or the lower bearing portion 11f) of the base body 11 (L1 <L2)。 In other words, in a plan view, the end face (one end face 61a1) in the extending direction of the arm member 61 provided on the mast device 20 is set to be located closer to the axis G of the mast device 20 than the outer edge of the base body 11 of the base device 10.

[0074] With this configuration, when the distributor 1 is rearranged, when the distributor 1 is lifted by a crane or the like through an opening provided on each floor and moved to the next upper floor, the arm member 61 of the suspension device 6 can be prevented from interfering with the floor surface of the upper floor.

[0075] As shown in FIG. 6, a cushioning member 65 made of an elastic member or the like is provided on the other end side of the arm main body 61a in the longitudinal direction, and by abutting the cushioning member 65 against the front side surface 21a1 of the mast member piece 21a, it is possible to cushion impacts, etc., when the multiple fixed members 13·13··· are suspended by the winch 62.

[0076] The winch 62 can be a commercially available electric winch that has a sufficient rated load to suspend multiple fixed members 13·13·· in both the upward and downward directions and can lift these multiple fixed members 13·13·· above the outriggers 12 on the base device 10, as described below.

[0077] The connecting member 63 may be, for example, a commercially available shackle, and is detachably connected to the arm member 61 using a fastening member 66 such as a bolt via a first through hole 61b1 (see Figure 5) of the connecting portion 61b of the arm member 61.

[0078] Then, by hanging the winch 62 on the connecting member 63, the winch 62 is connected to the arm portion 61. In other words, the connecting member 63 connects the winch 62 to one end of the arm member 61 in the extending direction (more specifically, the one end of the arm body 61a).

[0079] The suspension device 6 having the above-described configuration is provided at a predetermined height H above the floor surface F to which the base device 10 is fixed, so that, when the distributor 1 is placed on the desired floor surface F, as shown in Figure 3(a), the suspension device 6 can suspend the multiple fixed members 13·13··· collectively, at least up to above the outriggers 12.

[0080] With this configuration, when the distributor 1 is to be reloaded, the fixing member 13 can be removed while being suspended by the suspension device 6, and the fixing member 13 can be used to clamp the outriggers 12 and fix the base device 10 to the floor surface F to which it is to be moved, facilitating the removal, installation and fixing of the base device 10. Furthermore, by suspending the plurality of fixing members 13, 13, . . . and the separate parts described above, etc., using the suspension device 6, they can be easily moved above the floor surface F.

[0081] The number of suspension devices 6 can be set appropriately depending on the situation when changing the distributor 1, and may be provided, for example, for all hook portions 21a2·21a2··· provided on the mast device 20, or may be provided only on certain hook portions 21a2. In other words, it is sufficient that the suspension device 6 is provided on at least one hook portion 21a2.

[0082] In addition, the suspension device 6 can be attached to any hook portion 21a2 provided on the mast device 20, and as described below, when the distributor 1 is reloaded, the multiple fixed members 13·13··· can be provided in a position where they can be raised and lowered from a predetermined floor surface F to the floor surface F of the next higher floor, or they can be provided in a position where they can be raised and lowered from the predetermined floor surface F to the floor surface F of the next higher floor relative to the upper floor.

[0083] Furthermore, the configuration of the suspension device 6 is not limited to this embodiment, and may be configured, for example, without having an arm member 61, by a connecting member 63 that is directly connected to the hook portion 21a2 of the mast device 20, and a winch 62 that is hooked onto the connecting member 63.

[0084] Further, the portion where the suspension device 6 is provided is not limited to the hook portion 21a2, but may be provided separately and newly on the mast device 20 or the like. In this case, the newly installed portion may be installed at any location that can support the suspension device 6 at least at a position where the multiple fixed members 13·13··, etc. can be raised and lowered from a specified floor surface F to the floor surface F of the next higher floor when the distributor 1 is reloaded.

[0085] [Refilling procedure] Next, the procedure for changing the distributor 1 will be described with reference to FIGS.

[0086] <When the number of fixing members 13 is one set> First, a case in which the number of fixing members 13 prepared for one distributor 1 is equal to the number of outriggers 12 (four in this embodiment) will be described with reference to FIG. In the following description, the four fixing members 13·13·13·13 will be referred to as "one set" of fixing members 13·13·13·13 where appropriate.

[0087] In Figure 7(a), when the pouring operation by the distributor 1 fixed to the floor surface F1 of the first floor (for example, the sixth floor in this embodiment) is completed, the distributor 1 is suspended by a crane (not shown) via a wire or the like and temporarily held in an upright position with the boom row 31. Furthermore, the set of fixing members 13, 13, 13, 13 that have fixed the base device 10 to the floor surface F1 is removed by the worker.

[0088] Then, the removed set of fixing members 13·13·13·13 is temporarily placed on the floor surface F1, and each of the outriggers 12 is displaced to the storage position P1 (see FIG. 2(b)) and stored within the base body 11.

[0089] Once each outrigger 12 is stored within the base body 11, as shown in Figure 7(b), the distributor 1 is lifted (moved) by the crane to the second floor (for example, the seventh floor in this embodiment), which is the next floor above the first floor (sixth floor).

[0090] Thereafter, by deploying each outrigger 12 again, the distributor 1 is placed on the floor surface F2 of the second floor (seventh floor) via the outriggers 12.

[0091] On the other hand, in this embodiment, for example, a suspension device 6 is provided via the hook portion 21a2 (see Figure 3) of the lowest mast member piece 21a, and while maintaining the distributor 1 suspended by the crane on the second floor (seventh floor), a worker uses the suspension device 6 to hoist a set of fixing members 13·13·13·13 placed on the floor surface F1 up to the second floor (seventh floor).

[0092] Then, the worker uses the fixing member 13 that has been hoisted up to the second floor (seventh floor) to fix the base device 10 again to the floor surface F2 via the outriggers 13. Furthermore, the worker performs various operations such as releasing the distributor 1 from the crane and connecting the above-mentioned extension pipes (not shown) and the like. This completes the series of work procedures for changing the distributor 1. Furthermore, when the distributor 1 needs to be reloaded, the above procedure is repeated.

[0093] <When there are two sets of fixing members 13> Next, a case where two sets of fixing members 13 are prepared for one distributor 1 will be described with reference to FIG.

[0094] In Figure 8(a), when the pouring operation by the distributor 1 fixed to the floor surface F1 of the first floor (for example, the sixth floor in this embodiment) is completed, the distributor 1 is suspended by a crane (not shown) via a wire or the like and temporarily held in an upright position with the boom row 31. Furthermore, the set of fixing members 13·13·13·13 (hereinafter, appropriately referred to as "fixing members 13X") that fixed the base device 10 to the floor surface F1 is removed by the worker.

[0095] Then, the removed set of fixing members 13X·13X·13X·13X is temporarily placed on the floor surface F1, and each of the outriggers 12 is displaced to the storage position P1 (see FIG. 2(b)) and stored within the base body 11.

[0096] In this embodiment, a further set of fixing members 13·13·13·13 (hereinafter referred to as "fixing members 13Y" as appropriate) is provided separately, and this set of fixing members 13Y·13Y·13Y·13Y is placed in advance on the floor surface F2 of the second floor (for example, the seventh floor in this embodiment), which is the next higher floor than the first floor.

[0097] When each outrigger 12 is stored in the base body 11, the distributor 1 is lifted (moved) up to the second floor (seventh floor) by the crane, as shown in FIG. 8(b).

[0098] Thereafter, by deploying each outrigger 12 again, the distributor 1 is placed on the floor surface F2 of the second floor (seventh floor) via the outriggers 12, and the worker again fixes the base device 10 to the floor surface F2 using the set of fixing members 13Y·13Y·13Y·13Y. Furthermore, the worker performs the work of releasing the distributor 1 from the crane.

[0099] On the other hand, in this embodiment, a suspension device 6 is provided via, for example, a hook portion 21a2 (see FIG. 3) of the uppermost mast member piece 21a. That is, as shown in FIG. 8(a), when the base device 10 is fixed to the floor surface F1 of the first floor (sixth floor), the suspension device 6 is provided above the floor surface F2 of the second floor (seventh floor), which is the floor next higher than the first floor (sixth floor).

[0100] Then, after the base device 10 is fixed to the floor surface F2 as shown in FIG. 8(b), the worker uses the suspension device 6 to hoist the set of fixing members 13X·13X·13X·13X placed on the floor surface F1 up to the third floor (8th floor), which is the floor next higher than the second floor (7th floor), and places them on the floor surface F3 of the third floor. In other words, the suspension device 6 can hoist and transport the multiple fixing members 13X·13X·13X·13X used on the floor surface F1 of the first story (sixth floor) to the third story (eighth floor), which is the next higher floor after the second story (seventh floor), skipping a floor.

[0101] The worker also performs various operations such as connecting the extension pipes (not shown) and the like. This completes the series of work procedures for changing the distributor 1. Furthermore, when the distributor 1 needs to be reloaded, the above procedure is repeated.

[0102] As described above, the distributor 1 in this embodiment is a device comprising a base device (base section) 10, a mast device (mast section) 20 supported in an upright state on the base device (base section) 10, and a boom device (boom section) 30 arranged at the upper end of the mast device (mast section) 20. Here, the boom device (boom section) 30 has a boom row 31 consisting of a plurality of boom pieces (first boom piece 31a, second boom piece 31b, third boom piece 31c, and fourth boom piece 31d) connected in series and capable of bending and swinging relative to each other, a transport pipe 32 provided along the boom row 31, and a boom support base (support base) 33 that axially supports the base of the boom row 31 so that it can be raised and lowered, and the distributor 1 is a distributor 1 that supplies ready-mixed concrete to a desired location via the transport pipe 32.

[0103] The base device (base section) 10 has a base main body (main body section) 11, at least one or more (four in this embodiment) outriggers 12-12-12-12 that are horizontally deployable from the periphery of the base main body (main body section) 11, and at least the same number of fixing members 13-13-13-13 (four in this embodiment) as the outriggers 12, which fix the base device (base section) 10 to the floor surface F by clamping each of the outriggers 12-12-12-12 between the floor surface F, and the distributor 1 is further configured to be equipped with a suspension device (suspension means) 6 capable of suspending the multiple fixing members 13-13-13-13.

[0104] With this configuration, when the distributor 1 is to be replaced, the main body of the distributor 1 can be hoisted and moved to the next higher floor by a crane or the like, and then the suspension device 6 can hoist and move the removed multiple fixing members 13·13·13·13 and other parts such as the extension piping connected to the transport pipe 32 of the boom device 30 to the next higher floor. Therefore, it is possible to minimize the labor required for workers to manually carry the multiple fixing members 13·13·13·13 and the other parts mentioned above to upper floors, thereby reducing the burden on workers when replacing distributors.

[0105] Although one embodiment of the present invention has been described above, the present invention is not limited to such an embodiment, which is merely illustrative, and it is of course possible to embody the present invention in various other forms without departing from the spirit of the present invention. The scope of the present invention is indicated by the description of the claims, and further includes the equivalent meanings described in the claims, and all modifications within the scope of the claims. [Explanation of symbols]

[0106] 1 Distributor 10 Base device (base part) 11 Base body (main body) 12 Outrigger 13 Fixing member 20 Mast device (mast section) 21a1 Front side (side) 21a2 Hook part 30 Boom device (boom section) 31 Boom Row 31a First boom piece (boom piece) 31b Second boom piece (boom piece) 31c 3rd boom piece (boom piece) 31d 4th boom piece (boom piece) 32 Transport pipe 33 Boom support base (support base) 6 Suspension device (suspension means) 61 Arm parts 61a1 One end face (end face) 62 Winch 63 Connecting members F Floor surface F1 Floor of the first floor F2 Second floor floor G-axis center H Prescribed height

Claims

1. A base portion; a mast portion supported in an upright state on the base portion; a boom section disposed at an upper end of the mast section, The boom section includes: A boom train including a plurality of boom sections connected in series to each other so as to be able to bend and swing; A transport pipe provided along the boom row; a support base for pivotally supporting the base of the boom row so that the boom row can be raised and lowered; A distributor that supplies ready-mixed concrete to a desired location through the transport pipe, The base portion is A main body portion, At least one outrigger that is horizontally deployable from a periphery of the main body; and fixing members, the number of which is at least equal to the number of the outriggers, for fixing the base portion to the floor surface by clamping the outriggers between the outriggers and a floor surface, The distributor further includes a suspension means capable of suspending the fixing member. A distributor characterized by:

2. The base portion is fixed to a floor surface of the first level, The suspension means is The second floor is located above the floor surface of the second floor, which is the next higher floor than the first floor.

2. A distributor as claimed in claim 1 , characterized in that

3. The suspension means is With respect to a floor surface to which the base portion is fixed, The fixing member is provided at a position at a predetermined height so that the fixing member can be suspended at least above the outrigger.

2. A distributor as claimed in claim 1 , characterized in that

4. The mast portion has a hook portion protruding from a side surface, The suspension means is provided on the hook portion. A distributor according to any one of claims 1 to 3.

5. The suspension means is an arm member extending horizontally from a side surface of the mast section; a winch capable of suspending the fixing member in an upward and downward direction; a connecting member for connecting the winch to one end of the arm member in an extension direction, In plan view, The end surface of the arm member in the extending direction is The base portion is located closer to the axis of the mast portion than the outer edge of the main body portion of the base portion. A distributor according to any one of claims 1 to 3.

Citation Information

Patent Citations

  • Staging provided with load lifter

    JP2000145129A

  • Tower crane for construction of base isolated building and method for installation thereof

    JP2000303695A

  • Climbing crane

    JP2007131453A

  • Floor climbing-type tower crane and construction method for building

    JP2016108120A

  • Concrete supply distributor

    JP2022092129A