Method and structure for reducing stress acting on main beam

By removably fixing connecting members to the surfaces of adjacent and temporary floor slabs, the method and structure effectively reduce stress on the main girder during bridge deck replacement, enhancing efficiency and reducing costs.

JP2024139431APending Publication Date: 2024-10-09OHBAYASHI GUMI LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
JP2023050368
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-27
Publication Date
2024-10-09

AI Technical Summary

Technical Problem

Conventional bridge deck replacement methods face challenges in reducing stress on the main girder during temporary deck installation, particularly due to non-constant gaps between slabs, uneven surfaces, and the need for multiple jacks, leading to increased costs and labor.

Method used

A method and structure that involves removably fixing a connecting member to the upper and/or lower surfaces of adjacent and temporary floor slabs to straddle the gap, using members like steel plates or angle steels, allowing axial force transmission and reducing stress on the main girder.

Benefits of technology

This approach ensures reliable stress reduction on the main girder, enabling easier and more efficient deck replacement with minimal traffic disruption and reduced construction costs, by ensuring sufficient rigidity and axial force transmission.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024139431000001_ABST
    Figure 2024139431000001_ABST
Patent Text Reader

Abstract

To provide a technology that can further easily and reliably reduce stress acting on a main girder 20 during the period when a temporary slab 12 is placed in the replacement work of the deck slab for the existing composite girder.SOLUTION: In a slab replacement method in which existing slabs 11 of a composite girder are removed and temporary slabs 12 with a strength that can be considered a rigid body against forces acting in the bridge axis direction are placed in a temporary state at the location where the existing slabs 11 have been removed, and then the temporary slabs 12 are removed and new slabs 13 are placed where the temporary slabs 12 have been removed, connecting members 30, being members with a strength that can be regarded as a rigid body against the force acting in the bridge axis direction AX, are detachably fixed to at least the upper surfaces of the adjacent slabs and the temporary slabs 12 so as to straddle the gap G, which is the space between adjacent slabs, being other slabs adjacent to the temporary slabs 12 in the bridge axis direction AX, and the temporary slabs 12.SELECTED DRAWING: Figure 8
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a method and structure for reducing stress acting on main girders, and in particular to a technology suitable for reducing stress acting on main girders during the period when a temporary deck is installed in place of an existing deck that has been removed during bridge deck replacement work. [Background technology]

[0002] In the replacement of decks of existing composite girders using conventional methods, a certain section of the existing deck is removed, a new deck is laid in that section, and the area is opened to traffic after curing such as paving (see, for example, Patent Document 1). In such conventional methods, one lane restrictions (hereinafter also referred to as "nighttime one lane restrictions") may be implemented only at night when traffic volume is low. In such cases, the traffic closure period during which continuous construction work can be carried out is limited to nighttime only, making it difficult or impossible to complete a series of construction works from removing the existing deck to laying the new deck and completing curing such as paving within one traffic closure period.

[0003] Therefore, a deck replacement method is adopted in which a temporary deck is installed in place of the existing deck that has been removed (hereinafter referred to as the "temporary state"), dividing the traffic closure period into several relatively short periods and replacing the deck. However, the temporary deck is a temporary deck that is installed to open traffic during the traffic closure period, and is not completely fixed to the main girders. In other words, in the temporary state, the deck and the main girders are not integrated, making it a non-composite girder. In a non-composite girder, the load on the bridge surface, such as the load of heavy machinery during construction and the wheel load when traffic is opened, is supported only by the main girders, so the compressive stress acting on the upper part of the main girder and the tensile stress acting on the lower part are greater than those of a composite girder.

[0004] Therefore, in conventional construction methods, it was necessary to reinforce the main girders, for example by attaching angle irons to the webs of the main girders (near the upper flanges) with bolts, or by connecting adjacent main girders with H-shaped steel beams in the horizontal direction. Such reinforcement members are installed before removing the existing deck, but the space under the girders is narrow, making it difficult to lift and install the reinforcement members.

[0005] In this technical field, attempts have been made to solve the above problems while reducing the stress acting on the main girder in a temporary state. For example, in the deck replacement method according to the invention disclosed in Patent Document 2, jacks are placed between the temporary deck and the deck (existing deck and new deck) adjacent to the temporary deck, so that the axial force is transmitted through the temporary deck. According to this technology, the temporary deck can function as a strut installed above the main girder, so that sufficient rigidity can be ensured even in the temporary state, and the stress acting on the main girder can be reduced.

[0006] However, the width between adjacent temporary decks (hereinafter also referred to simply as "gap") is not always constant due to, for example, errors in bridge design and / or construction, and the jack may not fit into the gap. There is also concern that the desired axial force transmission effect may not be achieved due to, for example, unevenness and / or inclination of the surfaces where adjacent decks face each other. Furthermore, depending on the length of the temporary deck in the width direction and / or the number of temporary decks to be installed, it may be necessary to prepare a large number of jacks, which may lead to increased construction costs and / or labor. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] JP 2005-282272 A [Patent Document 2] Patent Publication No. 2022-6913 Summary of the Invention [Problem to be solved by the invention]

[0008] As mentioned above, there is a demand in the field of technology for a technology that can more easily and reliably reduce the stress acting on the main girder during the period when a temporary deck is in place during deck replacement work for an existing composite girder.

[0009] The present disclosure has been made in consideration of the above-mentioned problems, and aims to provide a method and structure that are suitable for reducing the stress acting on the main girder during the period when a temporary deck is in place during deck replacement work for an existing composite girder. [Means for solving the problem]

[0010] As a result of extensive research, the inventors have discovered that the above-mentioned problems can be solved by removably fixing connecting members to the top surfaces of the adjacent slab and the temporary slab so as to span the space between the adjacent slab, which is another slab adjacent to the temporary slab, and the temporary slab during the temporary state during deck replacement work.

[0011] Specifically, the method of reducing stress acting on the main girders according to the present disclosure (hereinafter also referred to as the "presently disclosed method") is a method of reducing stress acting on the main girders in a deck replacement construction method. In the deck replacement construction method to which the presently disclosed method is applied, the existing deck of the composite girder is removed, a temporary deck is arranged in the location where the existing deck was removed, and then the temporary deck is removed and a new deck is arranged in the location where the temporary deck was removed. The temporary deck is a deck that has a strength that allows it to be considered as a rigid body against forces acting in the bridge axis direction.

[0012] The disclosed method reduces stress acting on the main girder in a temporary state in which a temporary deck is installed at the location where the existing deck was removed. Specifically, in the disclosed method, a connecting member is detachably fixed to at least the upper surface of the adjacent deck, which is another deck adjacent to the temporary deck in the bridge axis direction, and the temporary deck so as to span the gap between the adjacent deck and the temporary deck. The connecting member is a member that has a strength that allows it to be considered as a rigid body against forces acting in the bridge axis direction.

[0013] Another aspect of the disclosed method is characterized in that the connecting members are detachably fixed to the undersides of the adjacent deck and the temporary deck so as to span the gap.

[0014] Another aspect of the disclosed method is characterized in that the connecting members are detachably fixed to the adjacent deck and the temporary deck by at least one fixing method selected from the group consisting of bolting, anchor bolting, and adhesive fixing.

[0015] As mentioned at the beginning of this specification, the present disclosure relates not only to a method for reducing stress acting on a main girder, but also to a structure for reducing stress acting on a main girder.

[0016] The structure for reducing stress acting on the main girder according to the present disclosure (hereinafter also referred to as the "disclosed structure") is a structure for reducing stress acting on the main girder in a deck replacement method. In the deck replacement method to which the disclosed structure is applied, the existing deck of the composite girder is removed, a temporary deck is placed in the location where the existing deck was removed, and then the temporary deck is removed and a new deck is placed in the location where the temporary deck was removed. The temporary deck is a deck that has a strength that allows it to be considered as a rigid body against forces acting in the bridge axis direction.

[0017] The disclosed structure reduces stress acting on the main girder in a temporary state in which a temporary deck is installed at the location where the existing deck has been removed. Specifically, the disclosed structure has a connecting member detachably fixed to at least the upper surface of the adjacent deck, which is another deck adjacent to the temporary deck in the bridge axis direction, and the temporary deck so as to span the gap between the adjacent deck and the temporary deck. The connecting member is a member that has a strength that allows it to be regarded as a rigid body against forces acting in the bridge axis direction.

[0018] Another aspect of the disclosed structure is characterized in that connecting members are detachably fixed to the undersides of the adjacent deck and the temporary deck so as to span the gap.

[0019] Another aspect of the disclosed structure is characterized in that the connecting members are removably fixed to the adjacent deck slabs and the temporary deck slab by at least one fixing method selected from the group consisting of bolting, anchor bolting, and fixing with an adhesive. Effect of the Invention

[0020] According to the method and structure disclosed herein, the stress acting on the main girder during the period when a temporary deck is in place during deck replacement work for an existing composite girder can be more easily and reliably reduced. [Brief description of the drawings]

[0021] [Figure 1] 1 is a flowchart showing the flow of each construction process in a deck replacement method to which a method for reducing stress acting on a main girder according to the present disclosure (the method disclosed herein) is applied. [Diagram 2] FIG. 13 is a schematic diagram illustrating the construction procedures for deck replacement work during the first nighttime one-lane restriction period. [Diagram 3] FIG. 13 is a schematic diagram illustrating the construction procedures for deck replacement work during the second nighttime one-lane restriction period. [Figure 4] This is a schematic diagram comparing deck replacement work with two-way traffic restrictions using conventional construction methods with deck replacement work with one-lane restrictions at night. [Diagram 5] FIG. 2 is a schematic perspective view showing an example of the configuration of a temporary deck used in the disclosed method. [Figure 6] FIG. 1 is a schematic diagram illustrating the difference in the magnitude of stress acting on the main girder in a composite girder and a non-composite girder. [Figure 7] FIG. 1 is a schematic diagram showing an example of installation of a temporary deck in a temporary state to which the method disclosed herein is applied. [Figure 8] 1 is a schematic diagram showing an example of the configuration of a portion where a temporary deck and an adjacent deck are connected by a connecting member. FIG. [Figure 9] 1 is a schematic cross-sectional view illustrating the difference in stress acting on the main girder depending on whether or not there is a connection between the adjacent deck and the temporary deck via a connecting member in a temporary state. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0022] Hereinafter, a method (the disclosed method) and a structure (the disclosed structure) for reducing stress acting on a main girder according to the present disclosure will be described with reference to the drawings.

[0023] <composition> The disclosed method and structure (hereinafter also referred to as the "disclosed technology") provide a technology for reducing stress acting on main girders, for example, in a deck replacement method for bridges and the like. In a deck replacement method to which the disclosed technology is applied, the existing deck of a composite girder is removed, a temporary deck is installed in the location where the existing deck was removed, and then the temporary deck is removed and a new deck is installed in the location where the temporary deck was removed. The temporary deck is a deck that has a strength that allows it to be considered as a rigid body against forces acting in the bridge axis direction.

[0024] FIG. 1 is a flowchart showing the flow of each construction process in the deck replacement method to which the technology disclosed herein is applied. As illustrated in FIG. 1, in the first nighttime one-lane restriction period R01, a first process (step S01) of removing the existing deck of the composite girder, a second process (step S02) of installing a temporary deck at the location where the existing deck was removed, and a third process (step S03) of temporarily paving the location where the temporary deck is installed are executed. In the second nighttime one-lane restriction period R02, a fourth process (step S04) of removing the temporary deck, a fifth process (step S05) of installing a new deck at the location where the temporary deck was removed, and a sixth process (step S06) of permanently paving the location where the new deck is installed are executed. Depending on the length of the period during which lane restrictions are permitted and / or the work content in each construction process, the first night-time one-lane restriction period R01 may be repeated multiple times before moving on to a second night-time one-lane restriction period R02.

[0025] Fig. 2 is a schematic diagram illustrating a first step (step S01), a second step (step S02), and a third step (step S03) executed in a first nighttime one-lane regulation period R01. Fig. 3 is a schematic diagram illustrating a fourth step (step S04), a fifth step (step S05), and a sixth step (step S06) executed in a second nighttime one-lane regulation period R02.

[0026] In the first nighttime one-lane restriction period R01, as illustrated in FIG. 2, construction is carried out from (a) removal of the existing deck 11 to (b) installation of the temporary deck 12 and (c) laying of the temporary pavement 50, and traffic is opened during the day the next day. As illustrated in FIG. 2(c), a connection member 30 (see FIG. 7 and FIG. 8) disclosed in the present specification, the details of which will be described later, is applied to the installation of the temporary deck 12 (b). Then, in the second nighttime one-lane restriction period R02, construction is carried out from (a) removal of the temporary deck 12 to (b) installation of the new deck 13 and pouring of filler concrete (not shown) into the gaps between the new decks 13 and (c) laying of the permanent pavement 60, as illustrated in FIG. 3. The gaps between the new decks 13 into which concrete has been poured are also called "filling sections". The connection member 30 is removed when the temporary deck 12 in (a) is removed, and is preferably reused.

[0027] Figure 4 is a schematic diagram comparing deck replacement work with two-way traffic control in the conventional construction method and one-lane control at night. As shown in (a) of Figure 4, in the conventional construction method for replacing decks of existing composite girders, a certain section of the existing deck is removed, a new deck is laid in that section, and curing such as paving is performed in one go. In this case, two-way traffic control is required throughout the day and night, which may lead to problems such as traffic congestion.

[0028] On the other hand, in the case of deck replacement work that goes through a temporary state to which the technology disclosed herein is applied, it is possible to divide the deck replacement work into processes that can be completed at night. That is, as shown in (b) of Figure 4, by restricting traffic to one lane only at night when traffic volume is low (one lane restriction at night), the traffic closure period can be minimized, and problems such as the occurrence of traffic congestion can be reduced.

[0029] The number of the existing deck 11 to be removed in the first step (step S01) and the temporary deck 12 to be arranged in the second step (step S02) is not particularly limited as long as the first to third steps can be completed within the first one-lane nighttime regulation period R01. That is, the number of the existing deck 11 to be removed in the first step and the temporary deck 12 to be arranged in the second step may be one or more. Similarly, the number of the temporary deck 12 to be removed in the fourth step (step S04) and the new deck 13 to be arranged in the fifth step (step S05) is not particularly limited as long as the fourth step and the fifth step can be completed within the second one-lane nighttime regulation period R02. That is, the number of the temporary deck 12 to be removed in the fourth step and the new deck 13 to be arranged in the fifth step may be one or more.

[0030] FIG. 5 is a schematic perspective view showing an example of the configuration of the temporary deck 12 used in the disclosed method. The configuration of the temporary deck 12 is not particularly limited as long as it has a strength that can be regarded as a rigid body against a force acting in the bridge axis direction and can support a traffic load in a temporary state in which the temporary deck 12 is arranged at a location where the existing deck 11 is removed. For example, the temporary deck 12 illustrated in FIG. 5 includes a covering plate 12a and an asphalt pavement 12b provided on the covering plate 12a, and a steel balustrade 12c is provided as a substitute for the wall balustrade of the new deck 13. The main girder 20 on which the temporary deck 12 is arranged is a so-called "H-shaped steel" having a pair of flanges 20a and 20b and a web 20c. In FIG. 5, the cross-sectional shape is drawn by a broken line in order to show that the main girder 20 is an H-shaped steel, but the cross section does not mean the end face of the main girder 20. In the following description, the flange 20a on which the temporary deck 12 is disposed is referred to as the "upper flange."

[0031] The covering plate 12a is, for example, an H-shaped steel material and a steel plate integrated by welding, and has a strength that allows it to be regarded as a rigid body against forces acting in the bridge axis direction at least on the upper flange 20a of the main girder 20. A precast plate may be used as the covering plate 12a.

[0032] As shown in FIG. 3(b), the main girder 20 and the new deck 13 are fixed by inserting the dowels 20d provided at a predetermined pitch on the upper flange 20a of the main girder 20 into the dowel holes 13a formed in the new deck 13 and pouring a filler such as mortar into the dowel holes 13a. Therefore, depending on the progress of the deck replacement work, the temporary deck 12 may be placed on the main girder 20 with the dowels 20d provided on the upper flange 20a. Therefore, it is preferable to configure the shape (e.g., recessed hole, etc.) of the lower surface of the covering plate 12a so as not to interfere with the dowels 20d provided on the upper flange 20a of the main girder 20. In this case, regardless of the progress of the deck replacement work, the temporary deck 12 can be placed on the main girder 20 to open the traffic.

[0033] However, as mentioned above, the temporary deck 12 is a temporary deck installed to open traffic during traffic closure periods, and is not completely fixed to the main girders 20, making it a non-composite girder. Moreover, in a state where the temporary deck 12 is simply installed on the main girders 20, the transmission of axial force between the temporary deck 12 and the decks adjacent to it (other temporary decks 12, the existing deck 11, or the new deck 13) is insufficient or nonexistent.

[0034] FIG. 6 is a schematic diagram for explaining the difference in the magnitude of the stress acting on the main girder 20 in a composite girder and a non-composite girder. In FIG. 6, it is assumed that a traffic load P acts on the center of the span of the main girder 20 as shown in (a). In a composite girder, as shown in the cross-sectional view of the center of the span on the left side of FIG. 6(b), the traffic load P is supported by both the integrated deck 10 and the main girder 20, so the compressive stress acting on the upper part of the main girder 20 is small as shown in the graph on the right side (see the shorter black arrow). For this reason, there is an advantage that, for example, it is possible to reduce the thickness of the upper flange 20a of the main girder 20. On the other hand, in a non-composite girder, as shown in the cross-sectional view of the center of the span on the left side of FIG. 6(c), the traffic load P is supported only by the main girder 20, so the compressive stress acting on the upper part of the main girder 20 is larger than that of a composite girder as shown in the graph on the right side (see the black arrow).

[0035] As described above, in a non-composite girder, the load on the bridge surface, such as the load of heavy machinery during construction and the wheel load when traffic is opened, is supported only by the main girder 20, so the compressive stress acting on the upper part of the main girder 20 and the tensile stress acting on the lower part are greater than those of a composite girder.

[0036] 7 and 8, the technology disclosed herein uses a connection member 30 to reduce the stress acting on the main girder 20 in a temporary state in which the temporary deck 12 is disposed at the location from which the existing deck 11 was removed. Specifically, in the technology disclosed herein, the connection member 30 is detachably fixed to at least the upper surfaces of the adjacent deck, which is another deck adjacent to the temporary deck 12 in the bridge axis direction AX, and the temporary deck 12 so as to span the gap G between the adjacent deck and the temporary deck 12.

[0037] The details of the connection member 30 of the present disclosure will be described below with reference to Figures 7 and 8. The method of detachably fixing the connection member 30 to the adjacent deck and the temporary deck 12 is not particularly limited as long as it is capable of withstanding loads such as loads and vibrations acting in the temporary state and is capable of sufficiently transmitting axial force to the decks connected by the connection member 30 to solve the problem of reducing the stress acting on the main girder 20 in the temporary state. Typically, the method of detachably fixing the connection member 30 to the adjacent deck and the temporary deck 12 is at least one fixing method selected from the group consisting of bolt fastening, anchor bolt fastening, and fixing with an adhesive.

[0038] The connection member 30 is a member having a strength that allows it to be regarded as a rigid body against a force acting in the bridge axis direction. The configuration of the connection member 30 (e.g., shape, size, material, etc.) is also not particularly limited as long as it can withstand loads such as loads and vibrations acting in the temporary state and can sufficiently transmit axial force to the deck connected by the connection member 30 to solve the problem of reducing the stress acting on the main girder 20 in the temporary state. In addition, a connection member 30 having high strength in the bending direction may be adopted so that a part of the bending moment acting on the deck in the temporary state is borne by the connection member 30. Typically, the connection member 30 is a plate-like member such as a steel plate 31 or a member having a deformed cross section such as an angle steel 32.

[0039] As described above, the connection member 30 is fixed to at least the upper surfaces of the adjacent deck slab and the temporary deck slab 12 so as to span the gap therebetween. That is, as long as it is possible to solve the problem of reducing the stress acting on the main girder 20 in the temporary state, the connection member 30 may be fixed only to the upper surfaces of the adjacent deck slab and the temporary deck slab 12. On the other hand, there are cases where fixing the connection member 30 only to the upper surfaces of the adjacent deck slab and the temporary deck slab 12 does not sufficiently solve the problem of reducing the stress acting on the main girder 20 in the temporary state. In such cases, the connection member 30 may be fixed not only to the upper surfaces of the adjacent deck slab and the temporary deck slab 12 but also to the lower surfaces of the adjacent deck slab and the temporary deck slab 12 so as to span the gap therebetween.

[0040] In addition, all of the connection members 30 fixed to the adjacent deck and the temporary deck 12 do not necessarily have to have the same configuration, and a combination of multiple types of connection members 30 having different configurations may be used. For example, when the connection members 30 are fixed to both the upper and lower surfaces of the adjacent deck and the temporary deck 12, since the space under the girder is narrow as described above, it may be difficult to fix the steel plate 31, which is large in size and weight, as the connection member 30 to the lower surface of the adjacent deck and the temporary deck 12. In such a case, the steel plate 31 may be fixed to the upper surface of the adjacent deck and the temporary deck 12 as the connection member 30, and the angle steel 32, which is smaller in size and weight than the steel plate 31, may be fixed to the lower surface of the adjacent deck and the temporary deck 12 as the connection member 30.

[0041] Furthermore, the connection member 30 is not placed in the gap between the adjacent deck and the temporary deck 12 as described above, but is fixed only to the upper surface or both the upper surface and the lower surface of the adjacent deck and the temporary deck 12. Therefore, even if the width of the gap is not necessarily constant due to, for example, bridge design and / or construction errors, or if the surfaces where the adjacent decks face each other are uneven and / or inclined, the adjacent deck and the temporary deck 12 can be easily and reliably connected by the connection member 30. In addition, for example, plate-shaped members such as the steel plate 31 or members having a deformed cross section such as the angle steel 32 can be adopted as the connection member 30 used in the disclosed method. Therefore, compared to the method using a jack, such as the deck replacement method according to the invention disclosed in the above-mentioned Patent Document 2, the construction cost and / or labor can be reduced.

[0042] For example, when steel plates 31 and / or angle steel 32 are used as the connecting members 30 and bolt fastening and / or anchor bolt fastening are used as the fixing method, it is preferable to provide a large number of bolt holes and / or bolt holes that are long in a plan view in the steel plates 31 and / or angle steel 32. With such a configuration, the connecting members 30 can be easily fixed to the adjacent deck slabs and the temporary deck slab 12 even when the gap width is not necessarily constant due to, for example, bridge design and / or construction errors and / or the connecting members 30 need to be fixed at a predetermined position to avoid interference with rebars.

[0043] FIG. 7(a) is a schematic side view when observed from a direction perpendicular to the bridge axis, and FIG. 7(b) is a schematic top view. In the example shown in FIG. 7, a steel plate 31 as a connecting member 30 is detachably fixed to the upper surface of the adjacent deck and the covering plate 12a by bolt fastening (not shown) so as to span the gap between the adjacent deck (existing deck 11, temporary deck 12, and new deck 13) which is a deck adjacent to the temporary deck 12 in the bridge axis direction and the temporary deck 12. Also, an angle steel 32 as a connecting member 30 is detachably fixed to the lower surface of the adjacent deck and the covering plate 12a by bolt fastening (not shown) so as to span the gap between the adjacent deck and the temporary deck 12. With such a configuration, an axial force can be transmitted between the existing deck 11 and the new deck 13 via the temporary deck 12. In other words, the temporary deck 12 can function as a strut installed above the main girder 20, so that sufficient rigidity can be ensured even in the temporary state, thereby reducing the stress acting on the main girder 20.

[0044] 7(b), one steel plate 31 is depicted as being fixed to one gap as the connecting member 30, but it is not necessary that one steel plate 31 is fixed to one gap as the connecting member 30. For example, a plurality of smaller steel plates 31 may be used as the connecting member 30 for the purpose of facilitating the transportation of the connecting member 30 to the construction site and / or the handling during the fixing work of the connecting member 30 to the adjacent deck slabs (the existing deck slab 11, the temporary deck slab 12, and the new deck slab 13) and the covering plate 12a at the construction site.

[0045] Fig. 8 is a schematic diagram showing an example of the configuration of a portion where the temporary deck 12 and the adjacent deck are connected by a connecting member 30. As shown in Fig. 8(a), a plurality of rectangular steel plates 31 are fixed to the upper surfaces of the temporary deck 12 and the new deck 13 by bolts 31b so as to span the gap G. The plurality of steel plates 31 are disposed adjacent to each other in a direction perpendicular to the bridge axis direction, and the connecting member 30 as a whole has a rectangular plate shape extending in a direction perpendicular to the bridge axis direction AX.

[0046] 8(b), a plurality of angle steels 32 are fixed to the underside of the covering plate 12a and the new deck 13 by bolts 32b in positions that do not interfere with the main girder 20, with their longitudinal directions parallel to the bridge axis direction AX and spanning the gap G. As mentioned above, the method of detachably fixing the connecting members 30 to the adjacent deck and the temporary deck 12 is not limited to the above-mentioned bolt fastening, and other fastening methods such as anchor bolt fastening and / or adhesive fastening can also be used.

[0047] Fig. 9 is a schematic cross-sectional view illustrating the difference in stress acting on the main girder 20 depending on whether or not the adjacent deck slab and the temporary deck slab 12 are connected via the connection member 30 in the temporary state. Fig. 9(a) illustrates a temporary state in the conventional construction method in which the temporary deck slab 12 is disposed on the main girder 20 but is not connected to the adjacent deck slab and the temporary deck slab 12. On the other hand, Fig. 9(b) illustrates a temporary state according to the present disclosure in which the connection members 30 are fixed to both the upper and lower surfaces of the adjacent deck slab and the temporary deck slab 12 by the presently disclosed method and structure as illustrated in Figs. 7 and 8, and the adjacent deck slab and the temporary deck slab 12 are connected.

[0048] As illustrated in (a) of Figure 9, in the temporary state where adjacent decks (existing deck 11, temporary deck 12, and new deck 13) are not connected to the temporary deck 12, not only are the temporary deck 12 and the main girder 20 not integrated but also an uncomposite girder is formed, and axial force (see black arrows) is not transmitted between adjacent decks. As a result, as described above with reference to Figure 6, the traffic load P is supported only by the main girder 20, so that the compressive stress acting on the upper part of the main girder 20 (see the arrows hatched with diagonal lines) and the tensile stress acting on the lower part (see the open arrows) are large.

[0049] On the other hand, as illustrated in (b) of FIG. 9, in a temporary state in which the adjacent deck slab and the temporary deck slab 12 are connected by fixing the connection members 30 (steel plate 31 and angle steel 32) to both the upper and lower surfaces of the adjacent deck slab and the temporary deck slab 12 by the disclosed method and structure, the temporary deck slab 12 and the main girder 20 are not integrated into one, which is the same as in (a) above, but the axial force (see black arrows) is transmitted between the adjacent decks, and the temporary deck slab 12 can function as a strut installed above the main girder 20. As a result, sufficient rigidity can be ensured even in the temporary state, and the stress acting on the main girder 20, i.e., the compressive stress acting on the upper part of the main girder 20 (see the arrows hatched with diagonal lines) and the tensile stress acting on the lower part (see the open arrows) can be reduced. Therefore, traffic can be opened without carrying out reinforcement work, and the traffic closure period can be minimized.

[0050] <effect> As described above, in the disclosed method and structure, in a temporary state in which the temporary deck 12 is disposed at the location where the existing deck 11 is removed, the connection member 30 is detachably fixed to at least the upper surface of the adjacent deck 12 and the temporary deck 12 so as to span the gap, which is the space between the adjacent deck 12 and the temporary deck 12. Therefore, since the axial force is transmitted between the adjacent decks, the temporary deck 12 can function as a strut installed above the main girder 20. As a result, according to the disclosed method and structure, sufficient rigidity can be ensured even in the temporary state, and the stress acting on the main girder 20 can be reduced.

[0051] Furthermore, as described above, the connection member 30 according to the presently disclosed method and structure is not accommodated in the gap between the adjacent deck and the temporary deck 12, but is fixed only to the upper surface or both the upper surface and the lower surface of the adjacent deck and the temporary deck 12. Therefore, even if the width of the gap G is not necessarily constant due to, for example, bridge design and / or construction errors, or if there are irregularities and / or inclinations on the opposing surfaces of the adjacent decks, the adjacent deck and the temporary deck 12 can be easily and reliably connected by the connection member 30.

[0052] In addition, easily available and inexpensive members, such as plate-like members such as steel plates 31 or members having irregular cross sections such as angle steel 32, can be used as the connection members 30 used in the method disclosed herein. Therefore, compared to the method using jacks, such as the deck replacement method according to the invention disclosed in the above-mentioned Patent Document 2, the construction costs and / or labor can be reduced.

[0053] In other words, according to the disclosed method and structure, the stress acting on the main girder 20 during the period when the temporary deck 12 is in place during deck replacement work for an existing composite girder can be more easily and reliably reduced.

[0054] For the purpose of explaining the contents of the present disclosure, a number of embodiments having specific configurations have been described above, sometimes with reference to the accompanying drawings. However, the scope of the present disclosure should not be construed as being limited to these exemplary embodiments, and it goes without saying that appropriate modifications can be made within the scope of the claims and the matters described in the specification. [Explanation of symbols]

[0055] 10... Deck, 11... Existing deck, 12... Temporary deck, 12a... Covering plate, 12b... Pavement, 12c... Steel railing, 13... New deck, 13a... Dowel hole, 20... Main girder, 20a... Upper flange, 20b... (Lower) flange, 20c... Web, 20d... Dowel, 30... Connection member, 31... Steel plate, 31b... Bolt, 32... Angle steel, 32b... Bolt, 50... Temporary pavement, 60... Permanent pavement, AX... Bridge axis direction, G... Gap

Claims

1. In a deck replacement method in which an existing deck of a composite girder is removed, a temporary deck, which is a deck having a strength that can be regarded as a rigid body against forces acting in the bridge axis direction, is placed in a temporary state in the location where the existing deck was removed, and then the temporary deck is removed and a new deck is placed in the location where the temporary deck was removed, a connecting member, which is a member having a strength that can be regarded as a rigid body against forces acting in the bridge axis direction, is detachably fixed to at least the upper surfaces of the adjacent deck and the temporary deck so as to span the gap, which is the space between the adjacent deck, which is another deck adjacent to the temporary deck in the bridge axis direction, and the temporary deck. A method for reducing stress acting on a main girder, comprising:

2. A method for reducing stress acting on a main beam as described in claim 1, comprising: The connecting member is detachably fixed to the underside of the adjacent floor slab and the temporary floor slab so as to span the gap. A method for reducing stress acting on a main girder, comprising:

3. A method for reducing stress acting on a main girder according to claim 1 or 2, comprising: The connecting member is detachably fixed to the adjacent deck and the temporary deck by at least one fixing method selected from the group consisting of bolt fixing, anchor bolt fixing, and adhesive fixing. A method for reducing stress acting on a main girder, comprising:

4. In a deck replacement method in which an existing deck of a composite girder is removed, a temporary deck having a strength that can be regarded as a rigid body against forces acting in the bridge axis direction is placed in the location where the existing deck was removed, and then the temporary deck is removed and a new deck is placed in the location where the temporary deck was removed, a connecting member which is a member having a strength that can be regarded as a rigid body against forces acting in the bridge axis direction is detachably fixed to at least the upper surfaces of the adjacent deck and the temporary deck so as to span the gap, which is the space between the temporary deck and an adjacent deck, which is another deck adjacent to the temporary deck in the bridge axis direction. A structure that reduces stress acting on the main girder, characterized by:

5. A structure for reducing stress acting on the main girder according to claim 4, The connecting member is detachably fixed to the underside of the adjacent floor slab and the temporary floor slab so as to span the gap. A structure that reduces stress acting on the main girder, characterized by:

6. A structure for reducing stress acting on the main girder according to claim 4 or claim 5, The connecting member is detachably fixed to the adjacent deck and the temporary deck by at least one fixing method selected from the group consisting of bolt fixing, anchor bolt fixing, and adhesive fixing. A structure that reduces stress acting on the main girder, characterized by:

Citation Information

Patent Citations

  • Construction method for replacing floor slab of composite girder, and device for transferring axial force between floor slabs

    JP2005282272A

  • Floor slab replacing method

    JP2022006913A