Gas analysis system
The gas analysis system simplifies gas component detection by using a single detection device and timing control to synchronize component introduction, reducing the need for multiple detection devices and minimizing peak overlap.
Patent Information
- Application Number
- JP2023053039
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-29
- Publication Date
- 2024-10-10
AI Technical Summary
Conventional gas analysis systems require multiple detection devices for analyzing gas components separated by multiple columns, which increases cost and complexity, necessitating complex adjustments to synchronize the introduction of gas components into a common detection device.
A gas analysis system that uses a single detection device by incorporating a control device to manage the timing of gas component introduction through a switching valve, allowing delayed introduction of components from one column relative to another, thereby reducing the need for multiple detection devices.
This system enables efficient detection of gas components from multiple columns using fewer detection devices, simplifying adjustments and reducing costs without peak overlap, while maintaining separation performance.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a gas analysis system using gas chromatography (gas chromatograph system). [Background technology]
[0002] Gas chromatography is an analytical technique that detects components in a gas by separating them using a separation column. Since the components that can be analyzed by gas chromatography are diverse, a huge variety of columns have been developed.
[0003] For example, among conventional gas analysis systems, there are gas analysis systems that are configured to switch the connection pattern between a detection device that detects gas components and multiple separation columns using a multi-port switching valve (see Non-Patent Document 1). [Prior art documents] [Patent documents]
[0004] [Non-Patent Document 1] Agilent Technologies, Inc. Application "GC Analysis of Refinery Gas (RGA)" 5989-7439EN Summary of the Invention [Problem to be solved by the invention]
[0005] In a gas analysis system, it is desirable to detect gas components separated in multiple columns using a common detector, taking into consideration low cost, compactness, and design freedom. In order to detect gas components separated in multiple columns using a common detector, adjustment is required to introduce the gas components separated in the multiple columns into the detector at different times. There is a need to easily perform this adjustment.
[0006] The present disclosure has been made to solve the above problems, and an object of the present disclosure is to provide a gas analysis system that can detect gas components separated in multiple columns using a detection device that is fewer than the number of columns. [Means for solving the problem]
[0007] The gas analysis system according to the present disclosure includes a first column that separates gas components contained in a sample gas, a second column that separates gas components contained in the sample gas, a detection device that detects gas components introduced from the first column and the second column, a valve that switches the gas introduction from the first column to the detection device, and a control device that performs a delay process by switching the open / closed state of the valve to delay the timing at which the introduction of the gas components separated in the first column into the detection device begins from the timing at which the introduction of the gas components separated in the second column into the detection device is completed. Effect of the Invention
[0008] According to the present disclosure, gas components separated in a plurality of columns can be easily detected by a detection device whose number is less than the number of the columns. [Brief description of the drawings]
[0009] [Figure 1] 1 is a diagram illustrating an example of an overall configuration of a gas analysis system. [Diagram 2] FIG. 2 is a cross-sectional view of the microvalve when the microvalve is in an open state. [Diagram 3] FIG. 2 is a cross-sectional view of the microvalve when the microvalve is in a closed state. [Figure 4] 6A to 6C are diagrams illustrating the state of a switching valve and the flows of each gas in a first operation pattern. [Diagram 5] 11A to 11C are diagrams illustrating the state of the switching valve and the flows of each gas during a second operation pattern. [Figure 6] 13A to 13C are diagrams illustrating the state of the switching valve and the flows of each gas in a third operation pattern. [Figure 7]13A to 13C are diagrams illustrating the state of the switching valve and the flows of each gas in a fourth operation pattern. [Figure 8] FIG. 13 is a diagram showing the state of the switching valve and the flows of each gas in a fifth operation pattern. [Figure 9] FIG. 13 is a diagram showing the state of the switching valve and the flows of each gas in a sixth operation pattern. [Figure 10] FIG. 13 is a diagram showing the state of the switching valve and the flows of each gas in a seventh operation pattern. [Figure 11] FIG. 13 is a diagram illustrating a schematic state of a component S3 during delay processing. [Figure 12] FIG. 13 is a diagram showing the state of the switching valve and the flows of each gas in an eighth operation pattern. [Figure 13] 13 is a diagram showing a schematic state of a component S3 after the delay process is released. FIG. [Figure 14] FIG. 4 is a diagram showing an example of an analysis result obtained by the gas analysis system. [Figure 15] FIG. 1 is a diagram showing an example of a diffusion image when a sample component is sealed in a packed column. [Figure 16] FIG. 1 is a diagram showing an example of a diffusion image when a sample component is sealed in a capillary column. [Figure 17] FIG. 2 is a diagram illustrating a first modified example of a flow path configuration of the gas analysis system. [Figure 18] FIG. 13 is a diagram illustrating a second modified example of the flow path configuration of the gas analysis system. [Figure 19] FIG. 13 is a diagram illustrating a third modified example of the flow path configuration of the gas analysis system. [Figure 20] FIG. 13 is a diagram illustrating a fourth modified example of the flow path configuration of the gas analysis system. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] Hereinafter, the present embodiment will be described in detail with reference to the drawings. In the following, the same or corresponding parts in the drawings are designated by the same reference characters and their description will not be repeated.
[0011] [Overall system configuration] FIG. 1 is a diagram showing a schematic diagram of an example of the overall configuration of a gas analysis system 1 according to the present embodiment.
[0012] The gas analysis system 1 includes carrier gas supply devices 11-13, a sample tank 20, a pump 21, a vent 23, a sampler module M1, a switching module M2, columns 41-44, a detection device 50, an input device 60, a display device 70, a drive device 80, and a control device 100.
[0013] Each of the carrier gas supply devices 11 to 13 adjusts a mobile phase called a carrier gas to a predetermined pressure and outputs it. For example, helium gas is used as the carrier gas. The pressure of the carrier gas is adjusted by an electronic automatic pressure controller (APC: Automatic Pressure Controller) not shown.
[0014] The sample tank 20 is a device for storing a sample gas to be analyzed. The sample tank 20 is connected to a connector C1 of the sampler module M1. A user can change the sample gas to be analyzed by the gas analysis system 1 by replacing the sample tank 20 connected to the connector C1 of the sampler module M1.
[0015] The pump 21 is a suction pump for sucking air from the flow passage of the sampler module M1 to create a negative pressure in the flow passage of the sampler module M1. Note that the negative pressure here refers to a pressure lower than atmospheric pressure, with atmospheric pressure being used as the reference.
[0016] The vent 23 connects the flow path of the sampler module M1 to the outside, and discharges gas within the flow path of the sampler module M1 to the outside.
[0017] The sampler module M1 and the switching module M2 are provided on a flow path that is fluidly connected to the sample tank 20, the columns 41-44, and the detection device 50. Note that the term "fluid connection" used here means that the modules are connected by a fluid directly without passing through other components, or indirectly via other components.
[0018] Each of the sampler module M1 and the switching module M2 is formed by mounting a plurality of switching valves on a flow path plate (flow path member) on which a flow path pattern is formed.
[0019] Each of the modules M1 and M2 is provided with a plurality of connectors (interfaces) for connecting external devices. The flow paths formed in each of the modules M1 and M2 are connected to the external devices via these connectors. Specifically, the sampler module M1 is provided with connectors C1 to C6. The sample tank 20, the pump 21, and the vent 23 are connected to the connectors C1 to C3, respectively. The carrier gas supply device 11 and the column 43 are connected to the connector C4. The carrier gas supply device 12 is connected to the connector C5. The column 41 is connected to the connector C6. The switching module M2 is provided with connectors C7 to C10. The columns 41 to 44 are connected to the connectors C7 to C10, respectively.
[0020] The sampler module M1 is a device for supplying a constant amount of sample gas to the column 41. The sampler module M1 includes connectors C1-C6, a constant-volume sample loop PL, switching valves V1-V6, and a plurality of flow paths connecting these. As described above, the connectors C1-C6 of the sampler module M1 are connected to the sample tank 20, the pump 21, the vent 23, the carrier gas supply device 11, the carrier gas supply device 12, and the column 41, respectively.
[0021] The switching valves V1 and V4 are disposed in this order in the flow path from the connector C1 to the connector C4. The switching valves V3, V5, and V6 are disposed in this order in the flow path from the connector C2 to the connector C5. The switching valve V2 is disposed in the flow path connecting the flow path between the switching valves V5 and V6 and the connector C3.
[0022] The sample loop PL is disposed in a flow path that connects the flow path between the switching valves V1 and V4 and the flow path between the switching valves V3 and V5. The sample loop PL has a function of temporarily holding the sample gas introduced from the sample tank 20 in order to supply it to the column 41. The connection destination of the sample loop PL is appropriately switched by controlling the switching valves V1 to V6, so that the sampler module M1 temporarily fills the sample loop PL with the sample gas supplied from the sample tank 20, and then supplies the sample gas filled in the sample loop PL to the column 41.
[0023] The switching module M2 includes connectors C7-C10, switching valves V7-V10, and a plurality of flow paths connecting these. As described above, the columns 41-44 are connected to the connectors C7-C10 of the switching module M2, respectively.
[0024] The switching valve V9 is disposed in the flow path between the connector C7 and the connector C8. The switching valve V8 is disposed in the flow path between the connector C9 and the connector C10.
[0025] The switching valve V7 is disposed in a flow path connecting the flow path between the connector C9 and the switching valve V8 and the flow path between the connector C8 and the switching valve V9. The switching valve V10 is disposed in a flow path connecting the flow path between the connector C7 and the switching valve V9 and the flow path between the connector C10 and the switching valve V8.
[0026] The switching valves V1 to V10 are switched between an open state and a closed state by a drive device 80. The drive device 80 switches the states of the switching valves V1 to V10 in response to a command from the control device 100. In other words, the states of the switching valves V1 to V10 are controlled by the control device 100.
[0027] The columns 43 and 44 are resistance tubes for adjusting pressure and have no ability to separate various components of the sample gas.
[0028] Columns 41 and 42 separate various components in the supplied sample gas. Specifically, columns 41 and 42 separate and output various components contained in the supplied sample gas in the time direction while the supplied sample gas passes through each column with the flow of carrier gas. In this embodiment, column 41 is a column for primary separation. Column 42 is a column for secondary separation that further separates various components of the sample gas primarily separated by column 41.
[0029] The outlet of column 42 is connected to the junction 30. The outlet of column 41 is connected to the junction 30 via the switching module M2 and a resistance tube (column 44). The switching module M2 is in a "series state" in which columns 41 and 42 are connected in series to the junction 30 in this order by opening the switching valves V8 and V9 and closing the switching valves V7 and V10 (see FIG. 4 described later). On the other hand, the switching module M2 is in a "parallel state" in which columns 41 and 42 are connected in parallel to the junction 30 by opening the switching valves V7 and V10 and closing the switching valves V8 and V9 (see FIG. 9 described later).
[0030] In this embodiment, the columns 41 and 42 are not packed columns (columns filled with an absorbent) but rather capillary columns having an inner diameter smaller than that of a packed column.
[0031] The detector 50 is connected to the junction 30 and detects various gas components introduced from the junction 30. As the detector 50, for example, an absorptiometry detector (PDA (Photo Diode Array) detector), a fluorescence detector, a differential refractive index detector, a conductivity detector, or a mass spectrometer is used. Data indicating the detection results by the detector 50 is stored in the memory unit 120 in the control device 100 and is displayed on the display device 70 at the request of the user.
[0032] The input device 60 is, for example, a keyboard or a pointing device such as a mouse, and receives requests or commands from a user. The requests or commands from the user input to the input device 60 are sent to the control device 100.
[0033] The display device 70 is configured, for example, with a liquid crystal display (LCD) panel, and displays information to the user. When a touch panel is used as the user interface, the input device 60 and the display device 70 are integrally formed.
[0034] The control device 100 includes a calculation unit 110, a storage unit 120, an input / output interface, etc. The control device 100 comprehensively controls the entire gas analysis system 1 including the carrier gas supply devices 11-13, the pump 21, the switching valves V1-V10 (drive device 80), etc. The control device 100 is connected to an input device 60 and a display device 70, which are user interfaces, by wire or wirelessly.
[0035] The calculation unit 110 has a calculation device (Central Processing Unit) and generates control signals for controlling each of the switching valves V1 to V10 using information stored in the memory unit 120, and outputs the generated control signals to the switching valves V1 to V10 (drive device 80) via an output interface.
[0036] [Configuration of switching valves V1 to V10] An example of the configuration of the switching valves V1 to V10 according to this embodiment will be described with reference to Fig. 2 and Fig. 3. Since the switching valves V1 to V10 have the same basic configuration, the switching valves V1 to V10 will be described as a microvalve 200 without distinction in Fig. 2 and Fig. 3.
[0037] Figure 2 is a cross-sectional view of the microvalve 200 when the microvalve 200 is in an open state. Figure 3 is a cross-sectional view of the microvalve 200 when the microvalve 200 is in a closed state.
[0038] The microvalve 200 has a laminated structure including a base layer 220, a diaphragm layer 230, and a cover layer 240, which are laminated in this order. Each of the base layer 220, the diaphragm layer 230, and the cover layer 240 is made of, for example, silicon, and is microfabricated using MEMS (Micro Electric Mechanical Systems) technology to achieve the desired strength and flexibility.
[0039] The thickness (dimension in the stacking direction) of the microvalve 200 is about 1 to 2 mm. For convenience, in the following description, the direction from the base layer 220 toward the cover layer 240 may be referred to as the upward direction, and the direction from the cover layer 240 toward the base layer 220 may be referred to as the downward direction.
[0040] The base layer 220 is disposed at the bottom layer of the microvalve 200. The base layer 220 is formed with a recess 221 and openings 222-224 penetrating the base layer 220. The recess 221 has a substantially circular shape when the base layer 220 is viewed in a plan view from above, and is formed approximately near the center of the base layer 220. The recess 221 is recessed from the upper surface side to the lower surface side of the base layer 220. The thickness of the base layer 220 is approximately 150 μm. The depth of the recess 221 is 5-20 μm, and preferably approximately 10 μm.
[0041] The openings 223 and 224 are formed in a bottom 225 of the recess 221. As described below, the openings 223 and 224 form an inlet and an outlet for the sample gas, respectively. The opening 222 is formed on the outer edge of the periphery of the recess 221 of the base layer 220, spaced apart from the recess 221. The opening 222 forms a supply port for a control fluid (pneumatic fluid) of the microvalve 200.
[0042] Diaphragm layer 230 is disposed on the upper surface side of base layer 220, facing base layer 220. Diaphragm layer 230 has an opening 232 penetrating diaphragm layer 230, a rigid portion 234, and a flexible portion 233 provided around rigid portion 234. Flexible portion 233 is thinner than rigid portion 234 and has flexibility. Elastic deformation of flexible portion 233 causes rigid portion 234 to be displaced in the vertical direction.
[0043] The opening 232 is formed apart from the flexible portion 233 and the rigid portion 234. The opening 232 is formed at a position overlapping with the opening 222 of the base layer 220 when viewed in a plan view from above, and forms a supply port for the pneumatic fluid together with the opening 222.
[0044] The microvalve 200 is connected to a flow path member (flow path plate) 250 when in use. The flow path member 250 has openings 252-254 formed at positions corresponding to the openings 222-224 of the base layer 220, respectively. The opening 252 of the flow path member 250, the opening 222 of the base layer 220, and the opening 232 of the diaphragm layer 230 communicate with each other to form a supply port 262 for the pneumatic fluid. The pneumatic fluid is supplied to the recess 241 of the cover layer 240 through the supply port 262.
[0045] An opening 253 of the flow path member 250 communicates with an opening 223 of the base layer 220, and forms an inlet 263 for the sample gas. An opening 254 of the flow path member 250 communicates with an opening 224 of the base layer 220, and forms an outlet 264 for the sample gas.
[0046] The microvalve 200 is a so-called normally open type valve that is open in the initial state (normal state) when no pneumatic fluid is supplied to the supply port 262 of the flow path member 250, and is closed when pneumatic fluid is supplied to the supply port 262 of the flow path member 250.
[0047] When pneumatic fluid is not supplied to the supply port 262 of the flow path member 250, the rigid portion 234 is held away from the bottom 225 of the recess 221 in the base layer 220, as shown in FIG. 2, so that the inlet 263 and outlet 264 of the sample gas are in an open state in which they are connected to each other.
[0048] When a pneumatic fluid is supplied to the supply port 262 of the flow path member 250, the rigid portion 234 is pushed by the pneumatic fluid and displaced downward, so that the lower surface of the rigid portion 234 comes into close contact with the bottom 225 of the recess 221 in the base layer 220, resulting in a closed state in which the inlet 263 and the outlet 264 for the sample gas are blocked. Note that instead of driving (displacing) the rigid portion 234 with the pneumatic fluid, the rigid portion 234 may be electrically driven (displaced) using a piezoelectric element or the like.
[0049] [System operation pattern] The gas analysis system 1 detects the gas components separated in the columns 41 and 42 by a single detection device 50 by switching between the following first to eighth operation patterns in this order. In the following, the gas analysis system 1 mainly detects the gas components to be analyzed, such as H 2 and inorganic gases other than He (N 2 , O 2、 CO, CO 2 etc.), and some lower hydrocarbons (CH 4 , C 2 H 4 , C 2 H 6 , C 3 H 6 , C 3 H 8 , C 3 H 4We will explain examples where
[0050] (First operation pattern) Sample introduction Sample introduction is an operating pattern in which a fixed amount of sample gas is sampled.
[0051] Fig. 4 is a diagram showing the states of the switching valves V1 to V10 and the flow of each gas during the first operation pattern (sample introduction). In Fig. 4, the switching valves marked with an x are in a closed state, and the switching valves not marked with an x are in an open state. In Fig. 4, the solid arrows indicate the flow of the carrier gas, and the diagonal arrows indicate the flow of the sample gas (sample). The same applies to the following Figs. 5 to 10 and 12.
[0052] 4, in the first operation pattern (sample introduction), the control device 100 opens the switching valves V1, V3, V6, V8, and V9 and closes the other switching valves V2, V4, V5, V7, and V10. The control device 100 also operates the pump 21. As a result, the sample gas is filled from the sample tank 20 into the sample loop PL, as shown by the hatched arrow.
[0053] In addition, the control device 100 operates the carrier gas supply devices 11 to 13. As a result, as shown by the black arrows, the carrier gas from the carrier gas supply device 11 is supplied to the junction 30 via columns 43 and 44, the carrier gas from the carrier gas supply device 13 is supplied to the junction 30 via column 44, and the carrier gas from the carrier gas supply device 12 is supplied to the junction 30 via columns 41 and 42.
[0054] Thereafter, the operation pattern of the gas analytical system 1 is switched to the next second operation pattern (pressure balance).
[0055] (Second operation pattern) Pressure balance Fig. 5 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the second operation pattern (pressure balance). As shown in Fig. 5, in the second operation pattern (pressure balance), the controller 100 opens the switching valves V3, V6, V8, and V9 and closes the other switching valves V1, V2, V4, V5, V7, and V10. In addition, the controller 100 operates the carrier gas supply devices 11 to 13 and stops the pump 21.
[0056] As a result, the pressure in the sample loop PL reaches an equilibrium state where it is stabilized at approximately atmospheric pressure, thereby stabilizing the amount of sample gas held in the sample loop PL at a constant amount.
[0057] Thereafter, the operation pattern of the gas analysis system 1 is switched to the next third operation pattern (sample gas injection).
[0058] (Third operation pattern) Sample gas injection Fig. 6 is a diagram showing the states of the switching valves V1 to V10 and the flow of each gas in the third operation pattern (sample gas injection). As shown in Fig. 6, in the third operation pattern (sample gas injection), the controller 100 opens the switching valves V4, V5, V8, and V9 and closes the other switching valves V1 to V3, V6, V7, and V10. In addition, the controller 100 operates the carrier gas supply devices 11 and 13 and stops the carrier gas supply device 12 and the pump 21.
[0059] As a result, carrier gas from the carrier gas supply device 11 is supplied to the sample loop PL through the switching valve V4, and the sample gas filled in the sample loop PL is pushed out by the carrier gas and supplied to the column 41 through the switching valve V5.
[0060] Thereafter, the operation pattern of the gas analysis system 1 is switched to the next fourth operation pattern (primary separation).
[0061] (4th operation pattern) Primary separation Fig. 7 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the fourth operation pattern (primary separation). As shown in Fig. 7, in the fourth operation pattern (primary separation), the controller 100 opens the switching valves V6, V8, and V9 and closes the other switching valves V1 to V5, V7, and V10. In addition, the controller 100 operates the carrier gas supply devices 11 to 13 and stops the pump 21.
[0062] As a result, primary separation of the sample gas is performed in the column 41. Fig. 7 shows an example in which the sample gas supplied to the column 41 is separated by primary separation in the column 41 into a component (component group) S1 that elutes early, a component (component group) S2 that elutes slower than the component S1, and a component (component group) S3 that elutes slower than the component S2. In this embodiment, the analyte component (N 2 , O 2、 CO, CO 2 , C.H. 4 , C 2 H 4 , C 2 H 6 , C 3 H 6 , C 3 H 8 , C 3 H 4 ) of which N 2 , O 2、 CO, CH 4 is included in component S1, and CO 2 , C 2 H 4 , C 2 H 6 is included in component S2, and C 3 H 6 , C 3 H 8 , C 3 H 4 is configured to be included in component S3.
[0063] Thereafter, the operation pattern of the gas analytical system 1 is switched to the next fifth operation pattern (secondary separation).
[0064] (5th operation pattern) Secondary separation FIG. 8 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the fifth operation pattern (secondary separation). As shown in FIG. 8, in the fifth operation pattern (secondary separation), the state of the fourth operation pattern (primary separation) is continued. That is, in the fifth operation pattern (secondary separation), the controller 100 opens the switching valves V6, V8, and V9 and closes the other switching valves V1 to V5, V7, and V10. In addition, the controller 100 operates the carrier gas supply devices 11 to 13 and stops the pump 21.
[0065] As a result, of the components S1 to S3 primarily separated in the column 41, the component S1 which elutes earliest is supplied to the column , where it is subjected to secondary separation.
[0066] Thereafter, the operation pattern of the gas analysis system 1 is switched to the next sixth operation pattern (S2 detection).
[0067] (6th operation pattern) S2 detection In the above-mentioned first to fifth operation patterns, the switching module M2 is controlled to the above-mentioned series state (a state in which the columns 41, 42 are connected in series to the junction portion 30).
[0068] In contrast, in the sixth operating pattern (S2 detection), in order to detect component S2 separated in column 41 before component S1 secondarily separated in column 42, the switching module M2 is switched to the above-mentioned parallel state (a state in which columns 41 and 42 are connected in parallel to the junction 30).
[0069] Fig. 9 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the sixth operation pattern (S2 detection). As shown in Fig. 9, in the sixth operation pattern (S2 detection), the controller 100 opens the switching valves V6, V7, and V10 and closes the other switching valves V1 to V5, V8, and V9. In addition, the controller 100 operates the carrier gas supply devices 11 to 13 and stops the pump 21.
[0070] As a result, the switching module M2 is in the above-mentioned parallel state, and before the component S1 is eluted from the column 42, the component S2 eluted from the column 41 is introduced into the detection device 50 through the junction 30. As a result, the component S2 is detected before the component S1.
[0071] Thereafter, the operation pattern of the gas analysis system 1 is switched to the seventh operation pattern (S1 detection).
[0072] (7th operation pattern) S1 detection In the seventh operation pattern (S1 detection), component S1 eluted from column 42 is introduced into detection device 50 in order to detect component S1.
[0073] In this case, if switching module M2 is maintained in a parallel state, component S3 will be introduced into detection device 50 from column 41 at the same time that component S1 is introduced into detection device 50 from column 42, which may result in a problem in which the peaks of components S1 and S3 overlap.
[0074] In order to avoid such peak overlap, in the seventh operation pattern (S1 detection), a "delay process" is executed to delay the timing at which the introduction of component S3 from column 41 to the detection device 50 is started from the timing at which the introduction of component S1 from column 42 to the detection device 50 is completed. The delay process may be executed based on a predetermined delay time. Specifically, in the delay process, the control device 100 closes the switching valve V10 provided on the outlet side of column 41 for the delay time, thereby temporarily containing component S3 within column 41. In this embodiment, column 41 corresponds to an example of the "first column" of the present disclosure, and column 42 corresponds to an example of the "second column" of the present disclosure.
[0075] The delay process may be performed by detecting the timing at which the introduction of the component S1 from the column 42 to the detection device 50 is completed. The detection may be performed, for example, by analyzing a chromatogram.
[0076] Fig. 10 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the seventh operation pattern (S1 detection). As shown in Fig. 10, in the seventh operation pattern (S1 detection), the controller 100 opens the switching valve V7 and closes the other switching valves V1 to V6 and V8 to V10. In addition, the controller 100 operates the carrier gas supply devices 11 and 13 and stops the carrier gas supply device 12 and the pump 21.
[0077] As a result, component S1 eluted from column 42 passes through junction 30 and is introduced into detection device 50 for detection. Furthermore, component S3 is confined within column 41 until introduction of component S1 into detection device 50 is complete.
[0078] 11 is a diagram showing a schematic state of the component S3 during the delay process. As shown in FIG. 11, during the delay process, the switching valve V10 provided on the outlet side of the column 41 is closed, so that the mobile phase (carrier gas) and the component S3 (C 3 H 6 , C 3 H 8 , C 3 H 4 ) is temporarily confined in a stationary state within column 41. This makes it possible to delay the timing at which component S3 is eluted from column 41.
[0079] In this embodiment, not only the outlet side switching valve V10 of the column 41 but also the inlet side switching valve V6 are closed during the delay process, but the inlet side switching valve V6 may be opened during the delay process. In this embodiment, the carrier gas supply device 12 is stopped during the delay process, but the carrier gas supply device 12 may be operated during the delay process. During the delay process, even if the carrier gas supply device 12 is operated and the inlet side switching valve V6 is opened, the outlet side switching valve V10 is closed, so that the mobile phase and the component S3 can be temporarily contained in the column 41.
[0080] Thereafter, the operation pattern of the gas analysis system 1 is switched to the next eighth operation pattern (S3 detection).
[0081] (8th operation pattern) S3 detection In the eighth operation pattern (S3 detection), in order to detect the component S3, the above-mentioned delay process is cancelled and the component S3 is introduced into the detection device 50.
[0082] Fig. 12 is a diagram showing the states of the switching valves V1 to V10 and the flows of each gas in the eighth operation pattern (S3 detection). As shown in Fig. 12, in the eighth operation pattern (S3 detection), the controller 100 opens the switching valves V6, V7, and V10 and closes the other switching valves V1 to V5, V8, and V9. In addition, the controller 100 operates the carrier gas supply devices 11 to 13 and stops the pump 21.
[0083] This cancels the above-mentioned delay process, and the component S3 separated in the column 41 passes through the junction 30 and is introduced into the detection device 50 for detection.
[0084] FIG. 13 is a diagram showing a schematic state of component S3 after the delay process is released. As shown in FIG. 13, after the delay process is released, the inlet side switching valve V6 and the outlet side switching valve V10 of the column 41 are opened, and the carrier gas from the carrier gas supply device 12 is supplied to the column 41. As a result, the component S3 (C 3 H 6 , C 3 H 8 , C 3 H 4 ) is pushed out by the carrier gas and introduced into the detection device 50.
[0085] 14 is a diagram showing an example of an analysis result by the gas analysis system 1 according to the present embodiment. 2 , CO, CO 2 , C.H. 4 , C 2 H 4 , C 2 H 6 , C3 H 6 , C 3 H 8 , C 3 H 4 The results of the analysis are shown when
[0086] The upper part of Fig. 14 shows the analysis results of a comparative example for the present disclosure, where the above-mentioned delay process (process for temporarily confining component S3 in column 41) was not performed. The lower part of Fig. 14 shows the analysis results of the present disclosure, where the above-mentioned delay process was performed.
[0087] In the gas analysis system 1 according to the present embodiment, as described above, the components S2 and S3 eluted from the column 41 and the component S1 eluted from the column 42 are introduced into the detection device 50 in the order of the components S2, S1, and S3. 2 , C.H. 4 , CO, and component S2 contains CO 2 , C 2 H 4 , C 2 H 6 Component S3 contains C 3 H 6 , C 3 H 8 , C 3 H 4 Includes:
[0088] In this case, in a comparative example in which the above-mentioned delay processing is not performed, as shown in the upper part of FIG. 14, the component S1 (N 2 , C.H. 4 , CO), and the peak of CO that is eluted last among the peaks of component S3 (C 3 H 6 , C 3 H 8 , C 3 H 4 ) that is eluted first 3 H 6 The peaks overlap with those of the other two.
[0089] In contrast, in the present disclosure, the elution timing of component S3 is delayed by the above-mentioned delay process, thereby avoiding the above-mentioned peak overlap, as shown in the lower part of FIG.
[0090] In the comparative example (equivalent to the conventional method) in which the delay process is not performed, in order to avoid the above-mentioned peak overlap, a skilled worker was required to perform a long and cumbersome adjustment work. For example, in the case of a packed column, the amount of packing material inside can be finely adjusted, and in the case of a capillary column, the length of the column can be finely adjusted by cutting or replacing it, so that the elution time can be adjusted to the desired time. However, in both types of columns, the temperature and pressure need to be adjusted, and the adjustment work needs to be repeated while checking the elution time each time, which is very cumbersome. In particular, in the case of a packed column, the piping structure is very complicated, and even a skilled worker needs a very long time to disassemble and assemble the piping. Therefore, the adjustment work required a lot of time and cost.
[0091] In contrast, in the present disclosure, the elution timing of component S3 can be delayed without requiring any hardware changes, by a simple process of closing the switching valve V10 between the column 41 and the junction 30. This makes it possible to easily avoid the above-mentioned peak overlap without requiring a skilled operator to perform complicated adjustment work.
[0092] Furthermore, in this embodiment, the switching valve V10 is configured by the microvalve 200 having the structure shown in Figures 2 and 3. This makes it possible to greatly reduce the dead volume inside the switching valve V10. Therefore, when the switching valve V10 is closed, it is possible to reduce the width of diffusion of the component S3 in the column 41 in the column length direction.
[0093] Specifically, if the switching valve V10 is configured as a multi-port switching valve with a large dead volume, the component S3 in the column 41 will easily diffuse in the column length direction in the column 41 even if the switching valve V10 is closed to stop the carrier gas in the column 41, and as a result, there is a concern that the peak bandwidth due to diffusion will increase. However, in this embodiment, the switching valve V10 is a microvalve with a very small dead volume, so that the width of the component S3 in the column 41 diffusing in the column length direction when the switching valve V10 is closed can be reduced. This makes it possible to suppress the increase in the peak bandwidth due to diffusion.
[0094] Furthermore, in this embodiment, the column 41 is a capillary column having a smaller inner diameter than a packed column, and therefore, compared to the case where the column 41 is a packed column, it is possible to more appropriately suppress an increase in the peak bandwidth due to diffusion.
[0095] Specifically, a packed column has a relatively large inner diameter, and since the inner diameter of the column is large compared to the bandwidth occupied by the gas components in the column, the effect of diffusion on the increase in the peak bandwidth becomes large.
[0096] Figure 15 is a diagram showing an example of diffusion when sample components are sealed in a packed column. In the example shown in Figure 15, the inner diameter of the column is 3 mm, which is large compared to the band width of about 1 m occupied by the sample components in the column. Furthermore, in a packed column, the sample components disperse through many paths formed by the gaps in the internal packing material. Therefore, the diffusion width of the sample components tends to be large.
[0097] In contrast, a capillary column has a relatively narrow inner diameter, which is very small compared to the bandwidth occupied by the sample components in the column, so that diffusion has very little effect on the increase in peak bandwidth.
[0098] Figure 16 is a diagram showing an example of diffusion when sample components are sealed in a capillary column. In the example shown in Figure 16, the inner diameter of the column is 0.53 mm, which is very small compared to the bandwidth occupied by the sample components in the column of about 1.5 m. Therefore, the increase in peak width due to diffusion is very small compared to the entire bandwidth occupied by the sample components and can be ignored, so separation performance can be maintained without deterioration of the peak shape due to diffusion.
[0099] Therefore, by using a capillary column instead of a packed column for the column 41, the increase in the peak bandwidth due to diffusion can be more appropriately suppressed. This is also shown in the waveforms shown in FIG. 14. Specifically, in the comparative example C in which no delay processing is performed, as shown in FIG. 3 H 8 , C 3 H 4 The waveform of the present disclosure, which performs delay processing, 3 H 8 , C 3 H 4 When comparing the waveforms of the two, the peak areas and shapes of the two are almost the same, with no change. This indicates that there is no increase in the peak width due to diffusion of component S3 in column 41 when component S3 is confined in column 41 by the delay process, or no sample loss due to switching of the flow path.
[0100] As described above, according to the gas analysis system 1 of this embodiment, the gas components separated in the column 41 and the gas components separated in the column 42 are introduced into the common detection device 50 through the junction 30. Therefore, the number of detection devices can be reduced compared to the case where the gas components separated in the column 41 and the gas components separated in the column 42 are introduced into separate detection devices.
[0101] Furthermore, in the gas analysis system 1 according to this embodiment, a switching valve V10 is disposed between the column 41 and the junction 30, and the control device 100 performs the above-mentioned "delay process", which is a simple process of switching the open / closed state of this switching valve V10, so that the timing at which introduction of the gas components separated in the column 41 into the detection device 50 begins can be delayed from the timing at which introduction of the gas components separated in the column 42 into the detection device 50 is completed. This makes it possible to easily avoid overlapping between the detection timing of the gas components separated in the column 42 and the detection timing of the gas components separated in the column 41, without the need for a skilled worker to perform complicated adjustment work.
[0102] <System Configuration Variations> The gas analysis system 1 according to the above-described embodiment has a complex flow path configuration including a sampler module M1 for supplying a constant amount of sample gas to the column 41, and a switching module M2 for switching the connection state between the columns 41, 42 and the junction 30.
[0103] However, the flow path configuration of the gas analysis system of the present disclosure only needs to include at least a first column and a second column, each of which separates gas components, a junction connected to the outlet of the first column and the outlet of the second column, and a switching valve arranged between the first column and the junction, and does not necessarily need to include a complex mechanism such as the above-mentioned sampler module M1 or switching module M2.
[0104] Fig. 17 is a diagram showing a first modified example of the flow path configuration of the gas analysis system. In the flow path configuration shown in Fig. 17, the inlets of columns 41 and 42 are connected to one sample injection port IP via a branching section 35, and the outlets of columns 41 and 42 are connected to a detection device 50 via a junction section 30. Furthermore, switching valves V21 and V23 are arranged on the inlet and outlet sides of column 41, respectively, and switching valves V22 and V24 are arranged on the inlet and outlet sides of column 42, respectively.
[0105] Fig. 18 is a diagram showing a second modified example of the flow path configuration of the gas analysis system. The flow path configuration shown in Fig. 18 is obtained by removing the switching valves V21 and V22 on the inlet side of the columns 41 and 42 from the flow path configuration shown in Fig. 17.
[0106] FIG. 19 is a diagram showing a third modified example of the flow path configuration of the gas analysis system. In the flow path configuration shown in FIG. 19, the inlets of columns 41 and 42 are connected to two sample injection ports IP1 and IP2, respectively, and the outlets of columns 41 and 42 are connected to the detection device 50 via the junction 30. Furthermore, switching valves V21 and V23 are arranged on the inlet side and outlet side of column 41, respectively, and switching valves V22 and V24 are arranged on the inlet side and outlet side of column 42, respectively. The same sample gas may be injected into the two sample injection ports IP1 and IP2, or completely different sample gases may be injected into them. In other words, the sample gas separated by column 42 may be the same sample gas as the sample gas separated by column 41, or it may be a completely different sample gas from the sample gas separated by column 41.
[0107] Fig. 20 is a diagram showing a fourth modified example of the flow path configuration of the gas analysis system. The flow path configuration shown in Fig. 20 is obtained by removing the switching valves V21 and V22 on the inlet side of the columns 41 and 42 from the flow path configuration shown in Fig. 19.
[0108] The flow path configuration of the gas analysis system of the present disclosure may be any of the flow path configurations shown in Figures 17 to 20. That is, in the flow path configurations shown in any of Figures 17 to 20, by performing the above-mentioned delay process on the switching valve V23 arranged on the outlet side of column 41, it is possible to easily avoid overlapping between the detection timing of the gas component separated in column 42 and the detection timing of the gas component separated in column 41 without requiring a skilled operator to perform complicated adjustment work.
[0109] [Aspects] It will be understood by those skilled in the art that the above-described embodiment and its modifications are specific examples of the following aspects.
[0110] (Item 1) A gas analysis system according to one embodiment includes a first column that separates gas components contained in a sample gas, a second column that separates gas components contained in the sample gas, a detection device that detects gas components introduced from the first column and the second column, a valve that switches the gas introduction from the first column to the detection device, and a control device that performs a delay process that delays the timing at which the introduction of the gas components separated in the first column into the detection device begins from the timing at which the introduction of the gas components separated in the second column into the detection device is completed by switching the open / closed state of the valve.
[0111] According to the gas analysis system described in paragraph 1, the gas components separated in the first column and the gas components separated in the second column are introduced into a common detection device. Therefore, the number of detection devices can be reduced compared to the case where the gas components separated in the first column and the gas components separated in the second column are introduced into separate detection devices.
[0112] In such a configuration, a valve for switching the introduction of gas from the first column to the detection device is provided, and the timing at which the introduction of the gas components separated in the first column to the detection device begins can be delayed from the timing at which the introduction of the gas components separated in the second column to the detection device is completed by a simple process of switching the open / closed state of this valve. This makes it possible to easily avoid overlapping between the detection timing of the gas components separated in the second column and the detection timing of the gas components separated in the first column, without the need for a skilled worker to perform complicated adjustment work.
[0113] As a result, it is possible to provide a gas analysis system that can easily detect gas components separated in a plurality of columns using a number of detection devices that is less than the number of the columns.
[0114] (Item 2) In the gas analysis system described in item 1, the control device may, in the delay process, close a valve to confine the gas components separated in the first column within the first column while the gas components separated in the second column are being introduced into the detection device.
[0115] According to the gas analysis system described in paragraph 2, the timing at which the gas components in the first column elute from the first column can be delayed by the simple process of temporarily containing the gas components in the first column within the first column by closing the valve that switches the gas introduction from the first column to the detection device.
[0116] (Item 3) In the gas analysis system according to item 2, the control device opens the valve after executing the delay process to introduce the gas components separated in the first column into the detection device.
[0117] According to the gas analysis system described in paragraph 3, the gas components temporarily contained in the first column can be introduced into the detection device and detected by the simple process of opening the valve after performing a delay process.
[0118] (Item 4) In the gas analysis system described in any one of Items 1 to 3, the valve comprises a base portion having an inlet for introducing gas into the valve and an outlet for discharging the gas introduced from the inlet to the outside, and a diaphragm portion disposed opposite the base portion and elastically deforming to switch between allowing and blocking the flow of gas from the inlet to the outlet.
[0119] According to the gas analysis system described in paragraph 4, the dead volume inside the valve can be made extremely small. Therefore, when the valve is closed, the width of the diffusion of the gas components in the first column in the column length direction can be made as small as possible. This makes it possible to suppress an increase in the peak bandwidth due to diffusion.
[0120] (Item 5) In the gas analysis system according to item 4, the first column may be a capillary column.
[0121] According to the gas analysis system described in paragraph 5, by using a capillary column as the first column, it is possible to more appropriately suppress an increase in peak bandwidth due to diffusion compared to when the first column is a packed column.
[0122] Specifically, a packed column has a relatively large inner diameter, which is large compared to the bandwidth occupied by the gas components in the column, and therefore diffusion has a large effect on the increase in peak bandwidth. In contrast, a capillary column has a relatively small inner diameter, which is very small compared to the bandwidth occupied by the gas components in the column, and therefore diffusion has a very small effect on the increase in peak bandwidth. Therefore, by using a capillary column instead of a packed column as the first column, the increase in peak bandwidth caused by diffusion can be more appropriately suppressed.
[0123] (Item 6) In the gas analysis system according to any one of items 1 to 3, the first column may be a column for primary separation, and the second column may be a column for secondary separation for further separating gas components primarily separated by the first column. The gas analysis system may further include a switching module disposed between the first column and the second column and configured to be switchable between a series state in which the first column and the second column are connected in series to the detection device in this order, and a parallel state in which the first column and the second column are connected in parallel to the detection device. The control device may execute a delay process when the switching module is in the parallel state.
[0124] According to the gas analysis system described in paragraph 6, in a configuration in which gas components primarily separated in the first column and gas components secondarily separated in the second column are introduced into a common detection device, overlap between the detection timing of the gas components secondarily separated in the second column and the detection timing of the gas components primarily separated in the first column can be easily avoided by a simple process of switching the open / closed state of a valve that switches the gas introduction from the first column to the detection device.
[0125] (Item 7) The gas analysis system described in item 1 may further include a junction connected to an outlet of the first column and an outlet of the second column, and the detection device may detect the gas components introduced from the junction.
[0126] The embodiments disclosed herein should be considered to be illustrative and not restrictive in all respects. The scope of the present invention is defined by the claims, not by the description of the embodiments described above, and is intended to include all modifications within the meaning and scope of the claims. [Explanation of symbols]
[0127] 1 Gas analysis system, 11-13 Carrier gas supply device, 20 Sample tank, 21 Pump, 23 Vent, 30 Junction, 35 Branch, 41-44 Column, 50 Detection device, 60 Input device, 70 Display device, 80 Drive device, 100 Control device, 110 Calculation unit, 120 Memory unit, 200 Microvalve, 220 Base layer, 221, 241 Recess, 222, 223, 224, 232, 252, 253, 254 Opening, 225 Bottom, 230 Diaphragm layer, 233 Flexible part, 234 Rigid part, 240 Cover layer, 250 Path member, 262 Supply port, 263 Inlet, 264 Outlet, C1-C10 Connector, IP, IP1, IP2 Sample injection port, M1 Sampler module, PL sample loop, V1~V10, V21~V24 switching valves.
Claims
1. a first column for separating gas components contained in the sample gas; a second column for separating gas components contained in the sample gas; a detection device for detecting gas components introduced from the first column and the second column; a valve for switching the introduction of gas from the first column to the detection device; a control device that executes a delay process to delay the timing at which the introduction of the gas components separated in the first column into the detection device is started from the timing at which the introduction of the gas components separated in the second column into the detection device is completed by switching the open / closed state of the valve.
2. 2. The gas analysis system of claim 1, wherein the control device closes the valve to contain the gas components separated in the first column within the first column while the gas components separated in the second column are being introduced into the detection device during the delay process.
3. 3. The gas analysis system according to claim 2, wherein the control device opens the valve to introduce the gas component separated in the first column into the detection device after the delay process is performed.
4. The valve is a base portion having an inlet for introducing a gas into the inside and an outlet for discharging the gas introduced from the inlet to the outside; 4. The gas analysis system according to claim 1, further comprising a diaphragm portion disposed opposite the base portion and configured to elastically deform to switch between flow and blocking of gas flow from the inlet to the outlet.
5. 5. The gas analytical system of claim 4, wherein the first column is a capillary column.
6. The first column is a column for primary separation, the second column is a column for secondary separation for further separating the gas components primarily separated in the first column, a switching module disposed between the first column and the second column and configured to be switchable between a series state in which the first column and the second column are connected in series to the detection device in this order and a parallel state in which the first column and the second column are connected in parallel to the detection device; 4. The gas analysis system according to claim 1, wherein the control device executes the delay process when the switching module is in a parallel state.