Repair work management device, repair work management method, and repair work management program
The repair work management device generates repair processes from survey data, enhancing the management of construction processes by integrating inspection and repair work data for efficient repair execution.
Patent Information
- Application Number
- JP2023054263
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-29
- Publication Date
- 2024-10-10
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing technologies fail to generate a repair work process based on survey results, leading to a lack of centralized management of construction processes from inspection to repair work.
A repair work management device that acquires design data, inputs repair point position and work type data, and generates process data for repair work based on inspection results, using a mobile terminal to specify deterioration types and locations, and automatically extracts repair processes.
Enables the generation of a repair work process and accurate management of progress status, allowing efficient coordination between survey and repair work data.
Smart Images

Figure 2024142202000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a repair work management device, a repair work management method, and a repair work management program. [Background technology]
[0002] In the above technical fields, Patent Document 1 discloses a technique for displaying information including at least one of the inspection results and repair details of a selected part of a concrete structure on a screen in association with the selected part (claim 1, etc.). Patent Document 2 discloses a technique for scanning the surface of a building to create a tile layout diagram, inputting abnormal parts of tiles, and displaying repaired tiles and unrepaired tiles in a differentiated manner (claims 5, 7, etc.). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2020-154465 A [Patent Document 2] Patent Publication No. 2022-109415 Summary of the Invention [Problem to be solved by the invention]
[0004] However, the technologies described in Patent Documents 1 and 2 only display the details of concrete repairs and unrepaired tiles on a screen, and are not capable of generating a repair work schedule based on the survey results. [Means for solving the problem]
[0005] In order to achieve the above object, a repair work management device according to the present invention comprises: A design data acquisition unit that acquires design data of a building that is a target for repair and inspection; an input receiving unit that receives repair location position data indicating the location of the repair location and work type data regarding the work type as the name of the repair work at the repair location, as a result of the repair inspection of the building, which are input on a display screen that displays the acquired design data; A process generation unit that extracts process data related to the process of the work type linked to the work type based on the received input result and generates a process of the work type; Equipped with:
[0006] In order to achieve the above object, a repair work management method according to the present invention includes: A design data acquisition step of acquiring design data of a building to be inspected for repair; An input reception step of receiving, on a display screen displaying the acquired design data, input of repair location position data indicating the location of the repair location as a result of the repair inspection of the building, and work type data relating to the work type as the name of the repair work at the repair location; A process generation step of extracting process data related to the process of the work type linked to the work type based on the received input result and generating a process of the work type; Includes.
[0007] Furthermore, in order to achieve the above object, the repair work management program according to the present invention comprises: A design data acquisition step of acquiring design data of a building to be inspected for repair; An input reception step of receiving, on a display screen displaying the acquired design data, input of repair location position data indicating the location of the repair location as a result of the repair inspection of the building, and work type data relating to the work type as the name of the repair work at the repair location; A process generation step of extracting process data related to the process of the work type linked to the work type based on the received input result and generating a process of the work type; to be executed by the computer. Effect of the Invention
[0008] According to the present invention, a repair work schedule can be generated based on the survey results, and the progress of the repair work can be accurately managed. [Brief description of the drawings]
[0009] [Figure 1A] 1 is a diagram for explaining an overview of a repair work management device according to a first embodiment of the present invention; [Figure 1B] FIG. 2 is a diagram for explaining input of a type of deterioration and a repair location in the repair work management device according to the first embodiment of the present invention. [Diagram 2] 1 is a block diagram for explaining a configuration of a repair work management device according to a first embodiment of the present invention. [Diagram 3] 2 is a diagram for explaining an example of a process table included in the repair work management device according to the first embodiment of the present invention; FIG. [Figure 4] 1 is a diagram for explaining a hardware configuration of a repair work management device according to a first embodiment of the present invention. [Diagram 5] 4 is a flowchart for explaining a processing procedure of the repair work management device according to the first embodiment of the present invention. [Figure 6] FIG. 5 is a block diagram for explaining the configuration of a repair work management device according to a second embodiment of the present invention. [Figure 7] FIG. 11 is a diagram for explaining a hardware configuration of a repair work management device according to a second embodiment of the present invention. [Figure 8] 10 is a flowchart for explaining a processing procedure of a repair work management device according to a second embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] Hereinafter, the embodiments of the present invention will be described in detail with reference to the drawings. However, the configurations, numerical values, process flows, functional elements, etc. described in the following embodiments are merely examples, and are free to be modified or changed, and are not intended to limit the technical scope of the present invention to the following description.
[0011] [First embodiment] A repair work management device according to a first embodiment of the present invention will be described with reference to Fig. 1A to Fig. 5. Fig. 1 is a diagram for explaining an outline of the operation of a repair work management device 100 according to this embodiment. The repair work management device 100 is a device that investigates deterioration and the like of a building 110 and manages the process of repair work based on the investigation.
[0012] The building 110 deteriorates due to aging of the materials used in its construction. Examples of deterioration of the building 110 that can be seen from the outside include deterioration of concrete, tiles used in the exterior walls, etc. As time passes after the construction of the building 110, for example, cracks and efflorescence occur in the concrete, and tiles become loose, peel off, or break.
[0013] In this way, when deterioration occurs in the building 110, an on-site investigation is carried out, and a repair method is considered and selected according to the investigation results. Then, a process plan is created according to the selected repair method, and construction is carried out based on the created process plan.
[0014] In this regard, the on-site investigation was carried out by, for example, noting the extent and condition of the deterioration on copies of the construction drawings that were brought with them, and attaching photographs, etc., as necessary. After that, when carrying out repair work, the matters noted on the copies of the construction drawings were transferred to a separate drawing for the target area, and the repairs were carried out according to the prepared process plan.
[0015] Recently, with the digitization of on-site management, on-site inspections are being carried out by specifying the deteriorated area on a drawing displayed on a tablet terminal, etc., and taking notes on the situation. In addition, repair work is being carried out by displaying the repair area and construction schedule on a tablet terminal, etc., and carrying out the work according to this.
[0016] In this method, when repair work is carried out, electronic data of the construction drawings is displayed on a tablet device or the like, but the extent of deterioration that is discovered later and added is saved as part of the electronic data of the original construction drawings. Therefore, there is no link between the data at the investigation stage and the data at the repair work, or between the data obtained during the investigation and the data obtained during the repair work, and it has not been possible to centrally manage the process from the investigation of deterioration to the execution of the repair work.
[0017] In this embodiment, for example, the inspector 120 investigates the deterioration of the tiles 130 on the exterior wall of the building 110, and inputs the results of the investigation, such as the type and size (range) of the deterioration, on a design drawing displayed on a mobile terminal 140 such as a tablet terminal. For example, as shown in FIG. 1B, when the inspector 120 finds peeling or cracks in the tiles 130 on the exterior wall of the building 110, he first taps a predetermined button on the display screen 141 of the mobile terminal 140. Then, a list of possible deterioration (pre-set deterioration) in the building 110 and a graphic marker for entering the position of the deterioration on the construction drawing of the building 110 are displayed as a pull-down menu 142. That is, in this embodiment, the inspector 120 does not specify the position of the deterioration and input the type of the deterioration, but first selects (declares) the type of deterioration to be input, and then inputs the position and size of the deterioration.
[0018] The graphic markers are designed to be shapes that easily recall the type of deterioration. For example, in the case of a crack, multiple linear markers are displayed according to the width of the crack. Similarly, in the case of tile peeling or peeling traces, a pentagonal marker is displayed. Then, the inspector 120 first selects a graphic marker according to the deterioration from the pull-down menu 142 to determine the type of deterioration. After the type of deterioration is determined, the inspector 120 specifies the range of deterioration. In the case of a crack, the inspector 120 uses a linear marker to specify the range of deterioration by tracing the position of the crack, and in the case of peeling, the inspector 120 uses a pentagonal marker and adjusts the size and position of the pentagon so that the peeled portion is surrounded by the pentagonal marker.
[0019] In this way, in the repair work management device 100, the type of deterioration displayed in the pull-down menu 142 is first selected, and then the location and range of the selected deterioration are specified. Here, when the inspector 120 selects a marker from the pull-down menu 142, the selected marker is linked to data of a process for repairing that deterioration, and the repair work management device 100 generates a process chart 150 for the repair work by extracting the linked process. When carrying out repair work, the repair work worker carries out the work according to the process chart 150 displayed on the mobile terminal 140.
[0020] Next, the configuration of the repair work management device 100 will be described with reference to Fig. 2. The repair work management device 100 has a design data acquisition unit 201, an input reception unit 202, a process generation unit 203, and a display control unit 204.
[0021] The design data acquisition unit 201 acquires design data of the building 110 that is the target of repair and inspection. The design data is data such as design drawings and on-site photos created when the building 110 was constructed. The inspector 120 inspects the building 110 while looking at the design drawings and on-site photos of the building 110 displayed on the display screen of the mobile terminal 140 or the like.
[0022] The input receiving unit 202 receives repair location data indicating the location of the repair location and work type data regarding the type of work as the name of the repair work at the repair location, as results of the repair inspection of the building 110, input on a display screen that displays the acquired design data.
[0023] An inspector 120 inspecting the building 110 (deterioration survey, etc.) carries a mobile terminal 140 while carrying out the inspection work, and at the same time inputs the inspection results into image data such as a blueprint displayed on the display screen (display) of the mobile terminal 140. For example, when inputting data, if there is a location where a tile has fallen off, the location to be repaired can be input by encircling the target location on the blueprint on the display screen with a pentagonal marker. Furthermore, the type of work and process for the input location to be repaired are automatically extracted at the time the marker is selected.
[0024] In the pull-down menu 142, the type of marker (the type of deterioration to be repaired) is determined according to the type of building 110 to be inspected.
[0025] In this way, by directly inputting the inspection results such as damaged areas into the image data of the blueprint, the inspector 120 does not need to input complex data such as location information, but can simply select the content of the repair work and specify the areas that need repair, making it possible to efficiently input the inspection results.
[0026] The inspector 120 can input the type, location, size, etc. of the deterioration by attaching a marker to the location that is judged to be deteriorated to the extent that repair is necessary. The marker is like a figure that indicates the location to be repaired (repair range) and is not limited to a pentagon, but may be, for example, a shape that clearly shows the repair content at a glance (square, triangle, circle, straight line). The marker is displayed superimposed on image data such as a blueprint, but the image data itself is not changed, and the position information, size (area), length, etc. of the marker are recorded. The amount of repair material required can be estimated using the recorded size and length of the marker.
[0027] The pull-down menu 142 displays the types of deterioration expected in the building 110 that is the target of the repair inspection. However, for example, when an appropriate type of deterioration is not displayed or when special repair work is required, the inspector 120 may be able to add a type of deterioration that corresponds to these appropriately.
[0028] Also, for example, when the inspector 120 selects repair of broken tiles (mortar repair work, etc.) as an item from the pull-down menu 142, the repair work management device 100 may automatically calculate the number of broken tiles from the area of the part circled by the inspector 120 with a marker and the area of the tiles. For example, for tiles that have completely peeled off in the item of repair of broken tiles, the inspector 120 may check them on-site and input the number of tiles.
[0029] In this way, the repair work management device 100 may automatically calculate quantities such as the number of tiles that can be calculated automatically, and quantities that require confirmation by the inspector 120 may be manually input by the inspector 120, etc. For example, the number of peeled tiles may be automatically calculated from the difference between the color of the tile and the color of the base and the area of the base. As described above, the repair work management device 100 can be configured to use manual input and automatic input appropriately.
[0030] Based on the received input result, the process generation unit 203 extracts process data related to the process linked to the selected type of deterioration, and generates a process for the repair work. For example, if the inspector 120 selects "crack injection work" as the type of deterioration, the process generation unit 203 extracts "initial process, base preparation, sealing, injection port installation, injection, removal of sealing material" and the like as process data linked to the crack injection work. Then, the process is generated by rearranging these in the order of work. The order of the generated processes can be changed by the on-site worker or the operator of the repair work management device 100, and new processes other than the processes displayed here can be added. The process data is stored in a specified database or the like.
[0031] Next, an example of a process table 301 held by the repair work management device 100 will be described with reference to Fig. 3. The process table 301 stores a work type 312 and a process 313 related to a deterioration type in association with an ID (identifier) 311. The ID 311 is an identifier for identifying a combination of the work type 312 and the process 313. The work type 312 related to the deterioration type indicates the name of the repair work. The process 313 indicates specific work content included in the work type 312. The repair work management device 100 then generates a process using the process table 301.
[0032] The hardware configuration of the repair work management device 100 will be described with reference to FIG. 4. The CPU (Central Processing Unit) 410 is a processor for arithmetic control, and executes a program to realize each functional configuration of the repair work management device 100 in FIG. 2. The CPU 410 may have multiple processors and execute different programs, modules, tasks, threads, etc. in parallel. The ROM (Read Only Memory) 420 stores fixed data such as initial data and programs, and other programs. The network interface 430 communicates with other devices via a network. The CPU 410 is not limited to one, and may be multiple CPUs or may include a GPU (Graphics Processing Unit) for image processing. The network interface 430 preferably has a CPU independent of the CPU 410 and writes or reads transmitted / received data in an area of the RAM (Random Access Memory) 440. It is also preferable to provide a DMAC (Direct Memory Access Controller) for transferring data between the RAM 440 and the storage 450 (not shown). Furthermore, the CPU 410 processes the data upon recognizing that the data has been received or transferred to the RAM 440. The CPU 410 also prepares the processing results in the RAM 440, and leaves the subsequent transmission or transfer up to the network interface 430 or DMAC.
[0033] The RAM 440 is a random access memory used by the CPU 410 as a work area for temporary storage. A storage area for storing data necessary for implementing this embodiment is secured in the RAM 440. The design data 441 is data at the time of designing the building 110 that is the subject of repair inspection. The repair location position data 442 is data indicating the location of the repair location on the design data. The work type data 443 related to the deterioration type is data indicating the name of the repair work at the repair location selected on the display screen by the inspector 120. The process data 444 is data regarding the process included in the work type related to the deterioration type selected on the display screen.
[0034] The transmitted / received data 445 is data that is transmitted and received via the network interface 430. The RAM 440 also has an application execution area 446 for executing various application modules.
[0035] The storage 450 stores a database, various parameters, or the following data or programs required to realize this embodiment. The storage 450 stores a process table 301. The process table 301 is a table that manages the relationship between the work type 312 and the process 313, etc., shown in FIG.
[0036] The storage 450 further stores a design data acquisition module 451, an input reception module 452, and a process generation module 453. The design data acquisition module 451 is a module that acquires design data of a building that is a target for repair and inspection. The input reception module 452 is a module that receives repair location position data and work type data related to a deterioration type that are input on a display screen that displays the design data. The process generation module 453 is a module that extracts process data related to a process linked to a work type related to a deterioration type based on the received input result, and generates a process. These modules 451 to 453 are read into the application execution area 446 of the RAM 440 by the CPU 410 and executed. The control program 454 is a program for controlling the entire repair work management device 100.
[0037] The input / output interface 460 interfaces input / output data with input / output devices. A display unit 461 and an operation unit 462 are connected to the input / output interface 460. A storage medium 464 may be further connected to the input / output interface 460. A speaker 463 serving as an audio output unit, a microphone (not shown) serving as an audio input unit, or a GPS position determination unit may be further connected. Note that the RAM 440 and storage 450 shown in FIG. 4 do not show programs and data relating to the general-purpose functions of the repair work management device 100 or other feasible functions.
[0038] Next, a processing procedure of the repair work management device 100 will be described with reference to the flowchart shown in Fig. 5. This flowchart is executed by the CPU 410 in Fig. 4 using the RAM 440, and realizes each functional configuration of the repair work management device 100 in Fig. 2.
[0039] In step S501, the design data acquisition unit 201 acquires design data of the building 110 that is the target of repair and inspection. In step S503, the input reception unit 202 receives input of the position of the repair area. The input of the position of the repair area is performed, for example, by the inspector 120 using a predetermined marker. When the input of the position of the repair area is completed, the process proceeds to step S507.
[0040] In step S505, the process generation unit 203 extracts process data linked to the marker indicating the selected deterioration content. In step S507, the process generation unit 203 uses the extracted process data to generate a repair work process for the repair location. When the process generation is completed, in step S509, the repair work management device 100 determines whether or not input of all repair location positions has been completed. If it is determined that input of all repair location positions has not been completed (NO in step S509), the repair work management device 100 returns to step S503. If it is determined that input of all repair location positions has been completed (YES in step S509), the repair work management device 100 ends the process.
[0041] According to this embodiment, simply by inputting the location of the area to be repaired on the design drawing and selecting the type of deterioration of the area to be inspected during the repair inspection, the process required for the repair work on the area to be repaired is generated, allowing for centralized management of everything from the inspection of the area to the repair work.
[0042] [Second embodiment] Next, a repair work management device according to a second embodiment of the present invention will be described with reference to Figs. 6 to 8. Fig. 6 is a block diagram for explaining the configuration of a repair work management device 600 according to this embodiment. The repair work management device 600 according to this embodiment is a device capable of managing the progress of a generated process, and is different from the first embodiment in that it has a process completion input receiving unit, an update recording unit, a process completion recording unit, and a display control unit. Since the other configurations and operations are the same as those of the first embodiment, the same configurations and operations are assigned the same reference numerals and detailed descriptions thereof are omitted. The repair work management device 600 has a process completion input receiving unit 601, a process completion recording unit 602, an update recording unit 603, and a display control unit 604.
[0043] The process completion input receiving unit 601 receives a process completion input for a completed process in which repair work is performed according to the process of the type of work related to the deterioration content generated by the process generation unit 203. First, when performing repair work, for example, a worker can check the unstarted repair parts from the display color of the marker (repair marker) attached to each repair part displayed on the display screen. Then, the worker selects the process of the unstarted repair part on the display screen, checks the process and quantity, etc., and starts the work. When the work of each process is completed, the worker performs an operation to indicate that the work of the process is completed, and inputs the process completion. The process completion receiving unit 601 receives the input of the process completion. The input operation of the process completion by the worker may be performed for each repair work, or may be performed for several repair works together. Similarly, the input operation of the process completion by the worker may be performed for each process, or may be performed for all processes together.
[0044] The process completion recording unit 602 records the completion of the process in the process data related to the received process completion input. As described above, the process completion recording unit 602 records the received process completion input so that the progress of each process can be managed.
[0045] When the process completion input receiving unit 601 receives a change input for the process content related to the repair work together with the process completion input, the update recording unit 603 updates and records the content of the process data with the change input content. For example, if the repair range input at the time of repair inspection is found to be small when the repair work is actually carried out, in order to record that the repair range was small, the size of the repair range at the time of repair inspection is updated to the repair range at the time of repair work. In this way, when changes occur in the repair location or repair range between the time of repair inspection and the time of repair work, or in the generated process, data and information are updated in a timely manner so that the latest information can be recorded.
[0046] The display control unit 604 displays the repair locations in an identifiable manner on the display screen in accordance with the progress of the process. The display control unit 604 displays the repair locations in an identifiable manner on the display screen by reflecting the process completion input and the change input. The display control unit 604 displays, for example, repair locations where repair work has been completed and repair locations where part of the process of the remunerated work has been completed in a manner that makes them distinguishable from other repair locations and locations that do not require repair on the display screen.
[0047] The display control unit 604 also displays quantity data on at least one of the repair location, the process, and the time series on the display screen. The display control unit 604 displays, for example, the size (area) of the repair location, the number of days for the process, or the schedule of the work, the status (quantity data) of the repair location at a certain time in the past or the status (quantity data) of the repair location at a certain time in the future. By displaying the past and future status in this way, it becomes possible to compare the planned and actual quantities. Furthermore, the display control unit 604 may also display quantities such as the above-mentioned quantities input by automatic input (e.g., the number of damaged tiles) and the manually input quantities (e.g., the number of tiles that have completely peeled off), making it easier to grasp the progress of the work.
[0048] The hardware configuration of the repair work management device 600 will be described with reference to Fig. 7. The RAM 740 is a random access memory used by the CPU 410 as a work area for temporary storage. A storage area for storing data required to realize this embodiment is secured in the RAM 740. The process completion data 741 is data related to a completed process, and is data input by a worker of the repair work using the mobile terminal 140 or the like. The update data 742 is data for correcting and updating the data input at the time of the repair inspection when a situation different from that at the time of the repair inspection occurs during the repair work.
[0049] The storage 750 stores a database, various parameters, or the following data or programs required to realize this embodiment. The storage 750 stores a process completion input reception module 751, a process completion record module 752, an update record module 753, and a display control module 754. The process completion input reception module 751 is a module that receives a process completion input for a process in which repair work has been carried out and completed. The process completion record module 752 is a module that records the completion of a process in the process data related to the received process completion input. The update record module 753 is a module that updates and records the contents of the process data with the contents of the change input when a change input related to the contents of the type of work related to the deterioration content is received. The display control module 754 is a module that displays the repair parts in an identifiable manner on the display screen according to the progress of the process. The display control module 754 is also a module that reflects the process completion input and the change input on the display screen to display the repair parts in an identifiable manner. These modules 751 to 754 are read by the CPU 410 into the application execution area 446 of the RAM 740 and executed.
[0050] Next, a processing procedure of the repair work management device 600 will be described with reference to the flowchart shown in Fig. 8. This flowchart is executed by the CPU 410 in Fig. 7 using the RAM 740, and realizes each functional configuration of the repair work management device 600 in Fig. 6.
[0051] In step S801, the process completion input receiving unit 601 receives a process completion input for a completed process in which repair work has been performed according to the generated repair work process. In step S803, the process completion recording unit 602 records the completion of the process in the process data related to the received process completion input. In step S805, when the update recording unit 603 receives a change input related to the content of the process together with the completion of the process, it updates the content of the process data with the content of the change input and records it. In step S807, the display control unit 604 displays the repair location in an identifiable manner according to the progress of the process. Furthermore, the display control unit 604 reflects the process completion input and the change input and displays the repair location in an identifiable manner. Furthermore, the display control unit 604 displays quantitative data related to the repair location, process, time series, etc.
[0052] According to this embodiment, progress management and process management of repair work can be reliably performed. In addition, even during repair work, information that could not be found during repair inspection can be linked to the information of the repair inspection, and the information can be managed as a whole. Furthermore, even during repair work, the repair location and repair range can be changed, and the results of the change can be displayed on the display screen.
[0053] Although the present invention has been described above with reference to the embodiments, the present invention is not limited to the above-described embodiments and can be modified as appropriate. Various modifications that can be understood by those skilled in the art can be made to the configuration and details of the present invention within the scope of the present invention. In addition, systems or devices that combine separate features included in each embodiment in any way are also included in the scope of the present invention.
[0054] The present invention may be applied to a system consisting of multiple devices, or to a single device. Furthermore, the present invention may be applied to a case where an information processing program for implementing the functions of the embodiment is supplied to a system or device and executed by a built-in processor. Therefore, the technical scope of the present invention includes a program installed on a computer to implement the functions of the present invention with a computer, a medium storing the program, a WWW (World Wide Web) server that downloads the program, and a processor that executes the program. In particular, at least a non-transitory computer readable medium storing a program that causes a computer to execute the processing steps included in the above-mentioned embodiment is included in the technical scope of the present invention.
[0055] Also, for example, the repair work management device 100 may determine whether or not the input of all repair location positions has been completed at the time when the input of repair location positions for a specified position has been completed, and if it determines that the input of all repair location positions has not been completed, it may return to the input of repair location positions, and only after determining that the input of all repair location positions has been completed, may it proceed to extracting process data and creating the process.
Claims
1. A design data acquisition unit that acquires design data of a building that is a target for repair and inspection; an input receiving unit that receives data on the type of deterioration and repair location position data indicating the location of the repair location as a result of the repair inspection of the building, the data being input on a display screen that displays the acquired design data; a process generation unit that extracts process data related to the process of the repair work associated with the type of deterioration based on the received input result and generates a process of the repair work; A repair work management device equipped with the above.
2. a process completion input receiving unit that receives a process completion input for a completed process in which repair work is carried out according to the process of the repair work generated by the process generation unit; a process completion recording unit that records the completion of the process in the process data related to the received process completion input; an update record unit that updates and records the content of the process data with the content of the change input when the process completion input receiving unit receives a change input regarding the content of the repair work together with the process completion input; A display control unit that displays the repair location in an identifiable manner according to the progress of the repair work on the display screen; Further equipped with The repair work management device according to claim 1 , wherein the display control unit displays the repair location on the display screen in an identifiable manner, reflecting the process completion input and the change input.
3. The repair work management device according to claim 2 , wherein the display control unit causes quantity data relating to at least one of the repair locations, the processes, and a time series to be displayed on the display screen.
4. A design data acquisition step of acquiring design data of a building to be inspected for repair; an input receiving step of receiving, on a display screen that displays the acquired design data, an input of a type of deterioration and repair location data indicating the location of the repair location as a result of the repair inspection of the building; A process generation step of extracting process data related to the process of the repair work associated with the type of deterioration based on the received input result and generating the process of the repair work; A method for managing repair work, including:
5. A design data acquisition step of acquiring design data of a building to be inspected for repair; an input receiving step of receiving, on a display screen that displays the acquired design data, an input of a type of deterioration and repair location data indicating the location of the repair location as a result of the repair inspection of the building; A process generation step of extracting process data related to the process of the repair work associated with the type of deterioration based on the received input result and generating the process of the repair work; A repair work management program that causes a computer to execute the above.
Citation Information
Patent Citations
Process management system, management terminal, and method for managing process
JP2016184427A
Structure inspection support system
JP2019057192A
Tile wall surface repair management system and repair management method for the same
JP2022109415A
Management support system and management support method
JP2022153909A
Concrete structure management device, information processing system, concrete structure management method, and program
JP2020154465A