AI Technical Summary
【0013】 本発明によれば、アクチュエータの飛び出しと遅延とを防ぐことができる。
Smart Images

Figure 2024143084000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a control valve and a construction machine. [Background technology]
[0002] 2. Description of the Related Art Among construction machines, there are those equipped with a bucket on an arm, and which perform excavation work or the like with the bucket by operating the arm with an actuator (see, for example, Patent Document 1). In this type of construction machine, for example, when the bucket is lowered from a position above the ground by its own weight, the following method is known to smooth the operation of the bucket (i.e., the arm). That is, a method is known in which the pressure of the hydraulic oil pushed out from the actuator is controlled by changing the meter-out throttle area. By controlling the pressure of the hydraulic oil pushed out from the actuator and returned to the tank, it is possible to smoothly adjust the operation of the actuator. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2019-31989 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, for example, if the weight of the bucket attached to the arm is heavy, the pressure of the hydraulic oil returning to the tank becomes high, and the flow rate of hydraulic oil flowing through the meter-out throttle increases. This can cause the actuator to suddenly move out of the machine. One possible solution to this problem is to reduce the meter-out throttle area. However, if the meter-out throttle area is reduced, it takes time for the pressure of the hydraulic oil returning to the tank to decrease when it is high. This can cause a delay in the operation of the actuator when the operating lever for the arm is operated.
[0005] The present invention provides a control valve and a construction machine that can prevent actuator popping out and delay. [Means for solving the problem]
[0006] A control valve according to one embodiment of the present invention is connected to a first flow path and a second flow path, and controls the working fluid discharged from the pump to be supplied to an actuator via the first flow path as a spool moves, and to return the working fluid pushed out of the actuator to a tank via the second flow path.The control valve is provided with a regeneration valve that returns all of the working fluid pushed out of the actuator to the first flow path when the pressure of the working fluid discharged from the pump is a first pressure and the pressure of the working fluid pushed out of the actuator is a second pressure, and when the first pressure is lower than the second pressure.
[0007] For example, when an attachment is lowered from a position above the ground using its own weight, the spool of the control valve is positioned in an intermediate range just before the full stroke range. When the spool is positioned in the intermediate range, if the weight of the actuator is heavy, the second pressure of the working fluid pushed out from the actuator is kept relatively high. Meanwhile, the first pressure of the working fluid discharged from the pump is kept relatively low. As a result, the pressure difference between the first pressure and the second pressure is kept relatively small.
[0008] In this state, when the first pressure is lower than the second pressure, all of the working fluid pushed out of the actuator can be returned to the first flow path by the regeneration valve. The pressure difference between the second pressure and the first pressure is kept relatively small. This makes it possible to appropriately control the amount of working fluid pushed out of the actuator and returned to the first flow path (i.e., the regeneration amount). Therefore, it is possible to appropriately maintain the pressure difference between the second pressure and the first pressure, and it is possible to prevent the actuator from popping out (i.e., sudden actuation).
[0009] By returning (regenerating) an appropriate amount of the working fluid pushed out from the actuator to the first flow path, the second pressure of the working fluid pushed out from the actuator can be appropriately reduced. Therefore, the second pressure can be quickly reduced in response to the operation of the control lever. Therefore, a delay in the actuator in response to the operation of the control lever can be prevented.
[0010] In the above configuration, the regeneration valve may be positioned in a position to return the working fluid pushed out of the actuator to the first flow path and the second flow path when the spool is in a full stroke state in which it has moved to its maximum extent in a predetermined direction.
[0011] A construction machine according to another aspect of the present invention comprises a vehicle body, a pump provided on the vehicle body and discharging a working fluid, an actuator provided on the vehicle body and driven by the working fluid, a first flow path connecting the pump and the actuator, a second flow path connecting a tank and the actuator, and a control valve provided midway between the first flow path and the second flow path, wherein the control valve controls the working fluid to supply the working fluid discharged from the pump to the actuator via the first flow path as a spool moves, and to return the working fluid pushed out of the actuator to the tank via the second flow path, and the control valve comprises a regeneration valve that returns all of the working fluid pushed out of the actuator to the first flow path when the pressure of the working fluid discharged from the pump is defined as a first pressure and the pressure of the working fluid pushed out of the actuator is defined as a second pressure and the first pressure is lower than the second pressure.
[0012] With this configuration, the pressure difference between the second pressure and the first pressure can be appropriately maintained by the control valve provided on the vehicle body, thereby providing a construction machine that can prevent the actuator from jumping out. Furthermore, the second pressure can be quickly reduced in response to the operation of the control lever, making it possible to provide a construction machine that is capable of preventing delays in the actuator in response to the operation of the control lever. Effect of the Invention
[0013] According to the present invention, it is possible to prevent actuator popping out and delay. [Brief description of the drawings]
[0014] [Figure 1] 1 is a schematic configuration diagram of a construction machine according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a hydraulic circuit diagram of a drive device according to an embodiment of the present invention. [Diagram 3] FIG. 4 is a circuit diagram showing a state in which a bucket is lowered from a position above the ground in the arm cylinder circuit according to the embodiment of the present invention. [Figure 4] FIG. 4 is a circuit diagram showing a state in which an excavation operation or the like is performed with a bucket in the arm cylinder circuit according to the embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0015] Next, a control valve and a construction machine according to an embodiment of the present invention will be described with reference to the drawings.
[0016] <Construction machinery> FIG. 1 is a schematic configuration diagram of a construction machine according to an embodiment. As shown in Fig. 1, the construction machine 100 is, for example, a hydraulic excavator. The construction machine 100 includes a revolving body (an example of a vehicle body in the claims) 101, a running body (an example of a vehicle body in the claims) 102 provided below the revolving body 101, and a drive unit 1 for driving the revolving body 101 and the running body 102. The drive unit 1 is provided on the revolving body 101, for example.
[0017] The rotating body 101 rotates relative to the traveling body 102. The rotating body 101 includes a cab 103, a boom 104 having one end connected to the cab 103, an arm 105 having one end connected to the other end of the boom 104, and a bucket 106 connected to the other end of the arm 105. The cab 103 supports an operator who rides on the rotating body 101. The boom 104 swings relative to the main body of the rotating body 101. The arm 105 swings relative to the boom 104. The bucket 106 swings relative to the arm 105. That is, the boom 104, the arm 105, and the bucket 106 constitute a working device of the construction machine 100.
[0018] <Drive unit> FIG. 2 is a hydraulic circuit diagram of the drive device 1 in the embodiment. As shown in Figures 1 and 2, the drive device 1 includes actuators 21-26 for driving the rotating body 101 and the running body 102, a hydraulic pump 5 that discharges hydraulic oil (an example of a working fluid in the claims) that serves as a driving source for each of the actuators 21-26, a supply flow path (an example of a first flow path in the claims) 7 that connects each of the actuators 21-26 to the hydraulic pump 5, a tank flow path (an example of a second flow path in the claims) 8 that connects each of the actuators 21-26 to a tank 9, and a hydraulic control valve (an example of a control valve in the claims) 2 provided midway between the supply flow path 7 and the tank flow path 8.
[0019] The hydraulic control valve 2 includes, for example, spools 11 and 12 for traveling, a spool 13 for swinging, a spool 14 for a boom, a spool 15 for an arm, and a spool 16 for a bucket. In the drive unit 1, hydraulic oil discharged from the hydraulic pump 5 is supplied to the ports of the actuators 21 to 26 via the supply passage 7 and the spools 11 to 16. The hydraulic control valve 2 controls the hydraulic oil by the spools 11 and 12 for traveling, the spool 13 for swinging, the spool 16 for the boom, the spool 15 for the arm, and the spool 16 for the bucket.
[0020] The actuators 21-26 are a collective term for the various parts for driving the revolving body 101 and the traveling body 102. That is, the actuators 21-26 are each composed of a hydraulic motor 21, 22 for traveling, a hydraulic motor 23 for revolving, a hydraulic cylinder 24 for the boom, a hydraulic cylinder 25 for the arm (an example of the actuator in the claims), and a hydraulic cylinder 26 for the bucket.
[0021] The traveling spools 11, 12 are provided midway between the hydraulic pump 5 and the traveling hydraulic motors 21, 22. The traveling of the traveling body 102 is controlled by operating the traveling spools 11, 12. The turning spool 13 is provided midway between the hydraulic pump 5 and the turning hydraulic motor 23. The turning of the turning body 101 is controlled by operating the turning spool 13.
[0022] The boom spool 14 is provided midway between the hydraulic pump 5 and the boom hydraulic cylinder 24. The boom spool 14 is operated to control the swing of the boom 104. The arm spool 15 is provided midway between the hydraulic pump 5 and the arm hydraulic cylinder (an example of an actuator in the claims) 25. The arm spool 15 is operated to control the swing of the arm 105. The bucket spool 16 is provided midway between the hydraulic pump 5 and the bucket hydraulic cylinder 26. The bucket spool 16 is operated to control the swing of the bucket 106.
[0023] Next, the circuit 3 that controls the arm spool 15 and the arm hydraulic cylinder 25 will be described. Hereinafter, the circuit 3 that controls the arm spool 15 and the arm hydraulic cylinder 25 may be referred to as the "arm cylinder circuit 3." The arm spool 15 may be referred to as the "arm spool 15," and the arm hydraulic cylinder 25 may be referred to as the "arm cylinder 25." Of the arm cylinder 25, the port Po1 on the cylinder head side may be referred to as the "head port Po1," and the port Po2 on the cylinder rod side may be referred to as the "rod port Po2."
[0024] <Arm cylinder circuit> The arm cylinder circuit 3 includes an arm spool 15 and an arm cylinder 25 connected to the arm spool 15 via a supply passage 7 and a tank passage 8. The arm spool 15 is provided inside a valve body (not shown) so as to be movable in the axial direction. The arm spool 15 includes a neutral region P1, an ascending region P2, and a descending region P3. By disposing the arm spool 15 in the neutral region P1, the hydraulic oil discharged from the hydraulic pump 5 is returned to the tank 9 via the arm spool 15. The head port Po1 and the rod port Po2 of the arm cylinder 25 are closed by the arm spool 15. Therefore, the arm 105 is kept stationary.
[0025] By disposing the arm spool 15 in the ascending region P2, the hydraulic oil discharged from the hydraulic pump 5 is supplied to the rod port Po2 of the arm cylinder 25 via the arm spool 15. In addition, the hydraulic oil pushed out from the head port Po1 of the arm cylinder 25 is returned to the tank 9 via the arm spool 15. As a result, the arm cylinder 25 contracts and the arm 105 ascends.
[0026] By arranging the arm spool 15 in the descending region P3, the hydraulic oil discharged from the hydraulic pump 5 is supplied to the head port Po1 of the arm cylinder 25 via the supply flow path 7 and the arm spool 15, etc. Also, the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 is returned to the tank 9 via the arm spool 15 and the tank flow path (an example of the second flow path in the claims) 8, etc. As a result, the arm cylinder 25 extends and the arm 105 descends.
[0027] Here, a regeneration valve 30 is built into the arm spool 15 in order to smoothly control the descent of the bucket 106 and the excavation work by the bucket 106. The arm spool 15 and the regeneration valve 30 will be described in detail below with reference to Figs. 1, 3 and 4. FIG. 3 is a circuit diagram showing a state in which the bucket 106 is lowered from a position above the ground in the arm cylinder circuit 3 of the embodiment.
[0028] 1 and 3, the arm spool 15 is housed inside a valve body (not shown) so as to be movable in the axial direction. The arm spool 15 is moved to a lowering region P3 where the arm 105 is lowered by an operator operating an operating lever (not shown). The descent region P3 of the arm 105 has an intermediate region P3a and a full stroke region P3b. The intermediate region P3a is located between the neutral region P1 and the full stroke region P3b. The intermediate region P3a is a region in which the arm spool 15 is located when, for example, the bucket 106 is lowered from a position above the ground by using its own weight.
[0029] In Fig. 3, the arm spool 15 is positioned in an intermediate region P3a by operating the operating lever. The full stroke region P3b is a region in which the arm spool 15 moves to the maximum and is positioned when, for example, an excavation operation is performed with the bucket 106. Hereinafter, the state in which the arm spool 15 is positioned in the full stroke region P3b may be referred to as the "full stroke state."
[0030] A regeneration valve 30 is housed inside the arm spool 15 so as to be movable in the axial direction. The regeneration valve 30 is movable in the axial direction by a first pressure (an example of the first pressure in the claims) of the hydraulic oil discharged from the hydraulic pump 5, a second pressure (an example of the second pressure in the claims) of the hydraulic oil pushed out from the arm cylinder 25, and the pressing force of a spring 32.
[0031] The first pressure is the pressure of the hydraulic oil discharged from the hydraulic pump 5 and flowing through the supply passage 7. The second pressure is the pressure of the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25. In FIG. 3, when the arm spool 15 is positioned in the intermediate region P3a, the regeneration valve 30 is positioned in the first regeneration position P4 by the second pressure of the hydraulic oil pushed out from the rod port Po2.
[0032] FIG. 4 is a circuit diagram showing a state in which an excavation operation or the like is performed with a bucket 106 in the arm cylinder circuit 3 of the embodiment. 1 and 4, the arm spool 15 is placed in a full stroke region P3b by an operator operating an operation lever (not shown). When the arm spool 15 is placed in the full stroke region P3b, the regeneration valve 30 is placed in a second regeneration position P5 by the first pressure of the hydraulic oil flowing through the supply passage 7 and the pressing force of the spring 32.
[0033] <Arm cylinder circuit operation> Next, the operation of lowering the bucket 106 and the operation of performing excavation work or the like with the bucket 106 will be described with reference to Figs. First, the operation of lowering the bucket 106 from a position above the ground by using its own weight will be described with reference to Figs. As shown in Figures 1 and 3, an operating lever (not shown) is operated to place the arm spool 15 in the intermediate region P3a of the descending region P3. Hydraulic oil discharged from the hydraulic pump 5 passes through the arm spool 15 and is supplied to the inside of the arm cylinder 25 from the head port Po1 of the arm cylinder 25. As the piston 25a of the arm cylinder 25 moves, hydraulic oil is pushed out from the rod port Po2 of the arm cylinder 25, and the arm cylinder 25 extends.
[0034] Here, a heavy bucket 106 is connected to the other end of the arm 105. Therefore, when the arm spool 15 is moved to the intermediate region P3a, the second pressure of the hydraulic oil pushed out from the head port Po1 becomes higher than the first pressure of the hydraulic oil discharged from the hydraulic pump 5. Furthermore, the pressure difference between the second pressure and the first pressure becomes higher by a certain value or more. In this state, the second pressure causes the regeneration valve 30 to be located at the first regeneration position P4.
[0035] By disposing the regeneration valve 30 in the first regeneration position P4, the hydraulic oil pushed out from the head port Po1 returns (regenerates) to the supply flow path 7 via the arm spool 15 and the regeneration valve 30. In this state, the bucket 106 connected to the other end of the arm 105 can be lowered together with the arm 105 by using its own weight from a position above the ground.
[0036] Next, the operation of performing excavation work or the like with the bucket 106 will be described with reference to FIGS. As shown in Figures 1 and 4, an operating lever (not shown) is operated to place the arm spool 15 in the full stroke region P3b of the descending region P3. Hydraulic oil discharged from the hydraulic pump 5 passes through the arm spool 15 and is supplied to the inside of the arm cylinder 25 from the head port Po1 of the arm cylinder 25. As the piston 25a of the arm cylinder 25 moves, hydraulic oil is pushed out from the rod port Po2 of the arm cylinder 25, and the arm cylinder 25 extends.
[0037] The bucket 106 descends together with the arm 105, and excavation work or the like is performed by the bucket 106. By performing excavation work or the like by the bucket 106, a large load is applied to the bucket 106 (i.e., the arm 105) from the part being excavated. For this reason, in a state in which the arm spool 15 is disposed in the full stroke region P3b, the first pressure of the hydraulic oil discharged from the hydraulic pump 5 becomes higher than the second pressure of the hydraulic oil pushed out from the rod port Po2. Furthermore, the pressure difference between the first pressure and the second pressure becomes higher by a certain value or more. In this state, the regeneration valve 30 is disposed in the second regeneration position P5 by the first pressure and the pressing force of the spring 32.
[0038] By disposing the regeneration valve 30 in the second regeneration position P5, the hydraulic oil pushed out from the rod port Po2 is returned (regenerated) to both the supply flow path 7 and the tank flow path 8 via the arm spool 15 and the regeneration valve 30. In this state, excavation work or the like can be performed with the bucket 106 connected to the other end of the arm 105.
[0039] As described above, the hydraulic control valve 2 in the embodiment has the arm cylinder circuit 3 equipped with the regeneration valve 30. In the arm cylinder circuit 3, as shown in Figs. 1 and 3, for example, in the case of an operation such as lowering the bucket 106 from a position above the ground by using its own weight, the arm spool 15 is disposed in the intermediate region P3a of the lowering region P3. When the arm spool 15 is disposed in the intermediate region P3a, if the weight of the bucket 106 is heavy, the second pressure of the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 is kept relatively high. On the other hand, the first pressure of the hydraulic oil discharged from the hydraulic pump 5 is kept relatively low. Therefore, the pressure difference between the first pressure and the second pressure is kept relatively small.
[0040] In this state, when the first pressure is lower than the second pressure and the pressure difference between the second pressure and the first pressure is higher than a certain value, all the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 can be returned to the supply flow path 7 by the regeneration valve 30. Also, the pressure difference between the second pressure and the first pressure is kept relatively small. This makes it possible to appropriately control the amount of hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 that is returned to the supply flow path 7 (i.e., the regeneration amount). Therefore, it becomes possible to appropriately maintain the pressure difference between the second pressure and the first pressure, and it is possible to prevent the piston rod 25b in the arm cylinder 25 from jumping out (i.e., sudden operation).
[0041] In addition, by returning (regenerating) an appropriate amount of the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 to the supply flow path 7, the second pressure of the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 can be suitably lowered. Therefore, the second pressure can be quickly lowered in response to the operation of the operation lever (not shown). This makes it possible to prevent a delay in the arm cylinder 25 in response to the operation of the operation lever.
[0042] 1 and 4, when an operation such as excavation work is performed with the bucket 106, the arm spool 15 is disposed in a full stroke region P3b of the lowering region P3 and is maintained in a full stroke state. When the arm spool 15 is disposed in the full stroke region P3b, a large load acts on the arm 105 due to excavation work or the like performed by the bucket 106. As a result, the first pressure of the hydraulic oil discharged from the hydraulic pump 5 becomes high.
[0043] In this state, the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25 can be returned to both the supply flow path 7 and the tank flow path 8 by the regeneration valve 30. This makes it possible to suitably reduce the second pressure of the hydraulic oil pushed out from the rod port Po2 of the arm cylinder 25. This makes it possible to prevent the second pressure from interfering with the operation of the arm cylinder 25. Therefore, the arm cylinder 25 can be operated smoothly.
[0044] In the construction machine 100 in the embodiment, the revolving body 101 is provided with the hydraulic control valve 2. Therefore, it becomes possible to appropriately maintain the pressure difference between the second pressure and the first pressure by the hydraulic control valve 2. This makes it possible to provide a construction machine 100 that can prevent the piston rod 25b of the arm cylinder 25 from jumping out. Furthermore, the second pressure can be quickly reduced in response to the operation of the control lever (not shown). This makes it possible to provide a construction machine 100 that can prevent delays in the arm cylinder 25 in response to the operation of the control lever.
[0045] The technical scope of the present invention is not limited to the above-described embodiment, and various modifications can be made without departing from the spirit of the present invention.
[0046] For example, in the above embodiment, a hydraulic excavator equipped with working devices, that is, the boom 104, the arm 105, and the bucket 106, has been described as an example of the construction machine 100. However, the present invention is not limited to this, and the present invention may be applied to a construction machine or the like equipped with working devices other than the boom 104, the arm 105, and the bucket 106.
[0047] In the above embodiment, an example has been described in which the present invention is applied to the arm cylinder circuit 3 that controls the arm 105, and the bucket 106 serving as an attachment is operated by the arm 105. However, the present invention is not limited to this, and as another example, the present invention may be applied to a circuit that operates another attachment, for example. In the above embodiment, hydraulic oil is exemplified as the working fluid. However, the present invention is not limited to this, and may be applied to a working fluid other than hydraulic oil. The working fluid is not limited to a liquid, and may be a gas.
[0048] In addition, the components of the above-described embodiment may be replaced with well-known components without departing from the spirit of the present invention. Also, the above-described modified examples may be combined.
[0049] Among the embodiments disclosed in this specification, those that are composed of multiple objects may be integrated, and conversely, those that are composed of one object may be divided into multiple objects. Regardless of whether they are integrated or not, it is sufficient that they are configured to achieve the object of the invention. [Explanation of symbols]
[0050] 1...Drive device, 2...Hydraulic control valve (control valve), 3...Arm cylinder circuit, 5...Hydraulic pump (pump), 7...Supply flow path (first flow path), 8...Tank flow path (second flow path), 9...Tank, 15...Arm spool (spool), 25...Arm cylinder (hydraulic cylinder for arm, actuator), 30...Regeneration valve, 100...Construction machine, 101...Slewing body (vehicle body), 102...Traveling body (vehicle body)
Claims
1. a control valve connected to a first flow path and a second flow path, and configured to control a working fluid discharged from a pump in accordance with a movement of a spool so as to supply the working fluid to an actuator via the first flow path and to return the working fluid pushed out from the actuator to a tank via the second flow path, When a pressure of the working fluid discharged from the pump is a first pressure and a pressure of the working fluid pushed out from the actuator is a second pressure, a regeneration valve that returns all of the hydraulic fluid displaced from the actuator to the first flow path when the first pressure is lower than the second pressure. Control valve.
2. The regeneration valve is disposed at a position where the working fluid pushed out from the actuator is returned to the first flow path and the second flow path when the spool is in a full stroke state where the spool has moved to the maximum in a predetermined direction. The control valve of claim 1 .
3. The car body and A pump provided on the vehicle body and configured to discharge a working fluid; an actuator provided on the vehicle body and driven by the working fluid; a first flow path connecting the pump and the actuator; a second flow path connecting a tank and the actuator; a control valve provided in the first flow path and the second flow path; Equipped with the control valve controls the working fluid discharged from the pump to be supplied to the actuator via the first flow path in accordance with the movement of the spool, and controls the working fluid pushed out from the actuator to be returned to the tank via the second flow path; the control valve includes a regeneration valve that returns all of the working fluid pushed out from the actuator to the first flow path when the first pressure is lower than the second pressure, where the pressure of the working fluid discharged from the pump is a first pressure and the pressure of the working fluid pushed out from the actuator is a second pressure. Construction machinery.
Citation Information
Patent Citations
A hydraulic valve arrangement
US20160061225A1
Construction machine
JP2019031989A