Underpass construction method and underpass building
The method allows efficient installation of piping and wiring alongside the box structure by using hollow pipe members and solidifying material, addressing the challenges of space reduction and cost in existing underpass construction.
Patent Information
- Application Number
- JP2023056472
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-30
- Publication Date
- 2024-10-11
AI Technical Summary
Existing underpass construction methods require separate and costly through-hole drilling for installing piping and wiring below existing structures, reducing the effective space and aesthetic appeal of underground passages.
A method where piping and wiring are installed alongside the box structure by using hollow pipe members with a rectangular cross-section, guided through the side surfaces of the box structure, and filled with a solidifying material to secure them in place, allowing efficient installation without occupying internal space.
Piping and wiring are easily and efficiently installed around the box structure, maintaining space and aesthetic integrity, while being protected from damage and corrosion.
Smart Images

Figure 2024143684000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an underpass construction method and an underground passage structure, and in particular to an underpass construction method in which a box-shaped structure is thrust-installed to replace a previously installed box-shaped roof, thereby forming an underground space using a box-shaped structure, and an underground passage structure constructed by the underpass construction method. [Background technology]
[0002] For example, underpass construction methods such as the R&C method (registered trademark) (see, for example, Patent Document 1) and the SFT method (registered trademark) (see, for example, Patent Document 2) are known as methods for constructing underground passages that cross existing railways, roads, etc., in the ground below the existing structure where the underground space is to be formed, for example, by installing a plurality of hollow pipe members having a rectangular hollow cross-sectional shape in series in the circumferential direction of the planned formation location in the ground below the existing structure where the underground space is to be formed, forming a box-shaped roof including a top pipe row that supports the existing structure from below and a pair of side pipe rows on both sides, and then replacing the formed box-shaped roof with, for example, a box structure having a rectangular cross-sectional shape made of precast concrete, which is advanced into the ground where the underground space is to be formed, thereby forming an underground space by the replaced box structure.
[0003] That is, in the underpass construction method, for example, in the R&C construction method, as shown in Figs. 4(a) to (d), a plurality of hollow pipe members 21 having a hollow cross-sectional shape, preferably a rectangular shape (including a square shape), are installed in advance along the outer peripheral shape of a box structure 20 to be installed at a location where an underground space is to be formed, and a box-shaped roof 22 is formed by pipe rows arranged in a U-shaped cross-sectional shape, preferably consisting of a top pipe row 22a and a pair of side pipe rows 22b on both sides. 4(a) and (b)), and then the front end surface of the concrete box structure 20 is abutted against the rear end surface of the box-shaped roof 22 via a center jack 24a (see FIG. 4(c)), and the box structure 20 is advanced by a main jack 24b (see FIG. 4(d)), thereby replacing the box structure 20 with a box-shaped roof 22 having a U-shaped cross-section made of multiple hollow pipe members 21, and the box structure 20 is installed underground (see FIG. 4(e)). This is a well-known construction method. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A Summary of the Invention [Problem to be solved by the invention]
[0005] On the other hand, in the ground below an existing structure where an underground space is formed by a box structure using the underpass method, it may be necessary to lay, for example, pipes for water supply and sewerage, and wiring such as electric wires and cables across the ground below. If such pipes and wiring are laid inside the underground space formed by the box structure, it will reduce the effective area of the underground space and also impair the aesthetic appearance of the underground space. Therefore, in the past, through holes were formed in the ground around the box structure by a work separate from the underpass method to enable the installation of these pipes and wiring across the ground below the existing structure, and these pipes and wiring were laid in the through holes formed. However, since it requires considerable cost and effort to precisely excavate and form such through holes at the specified positions by a separate work, there is a need to develop a technology that allows these pipes and wiring to be laid easily and efficiently around the box structure by crossing below the existing structure.
[0006] The present invention aims to provide an underpass construction method that can easily and efficiently lay piping and wiring around a box structure by crossing the ground below an existing structure, and an underground passage structure constructed by the underpass construction method. [Means for solving the problem]
[0007] The present invention relates to an underpass construction method for forming an underground space by a box structure by propelling and installing a box structure having a rectangular cross section from a starting base to the ground directly below an existing structure, replacing a box roof including a top pipe row and a pair of side pipe rows on both sides that have been installed in advance on the ground below the existing structure. In the process of forming the box roof by driving a plurality of hollow pipe members having a rectangular hollow cross section into the ground below the existing structure, The above-mentioned object has been achieved by providing an underpass construction method which includes a step of guiding a piping / wiring pipe member, which has the same rectangular hollow cross-sectional shape as the hollow pipe member, through a joint portion onto the side portion of the hollow pipe member, and propelling and installing the box structure into the ground directly below the existing structure by replacing the box-shaped roof, in which the box structure is propelled while the piping / wiring pipe member is left in the ground, and a step of installing piping / wiring in the piping / wiring pipe member that has been left behind.
[0008] In addition, in the underpass construction method of the present invention, it is preferable that the piping / wiring pipe members, which are installed adjacent to the side portions of the end hollow pipe members at both ends of the top panel pipe row, function as a safety roof pipe that supports loads from above together with the top panel pipe row.
[0009] Furthermore, it is preferable that the box-shaped roof pipe for the underpass construction method of the present invention includes a step of filling a filling and solidifying material such as foamed mortar inside the piping and wiring pipe member in which the piping and wiring are arranged.
[0010] The present invention also achieves the above-mentioned object by providing an underground passage structure constructed by the underpass construction method, in which the piping and wiring pipe member is installed adjacent to the side of at least one upper corner portion of the jack-up installed box structure, with its top end positioned at the same height as the top surface of the box structure, and extended along the entire length of the underground passage structure, and the wiring and piping arranged across the ground below the existing structure are not arranged in the internal space of the box structure, but are inserted through the piping and wiring pipe member.
[0011] In the underground passage structure of the present invention, it is preferable that the inside of the piping / wiring pipe member in which the wiring / piping is arranged is filled with a filling and solidifying material such as foamed mortar and solidified. Effect of the Invention
[0012] According to the underpass construction method or underground passage construction of the present invention, piping and wiring can be easily and efficiently laid around the box structure, crossing the ground below the existing structure. [Brief description of the drawings]
[0013] [Figure 1] FIG. 1 is a schematic vertical sectional view illustrating an underpass construction method according to a preferred embodiment of the present invention. [Diagram 2] FIG. 2 is a schematic cross-sectional view taken along the line AA in FIG. 1, illustrating an underpass construction method according to a preferred embodiment of the present invention. [Diagram 3] FIG. 2 is a schematic cross-sectional view illustrating an underground passage structure formed by the underpass construction method. [Figure 4] 1(a) to 1(e) are schematic vertical sectional views and schematic horizontal sectional views illustrating an R&C construction method, which is an underpass construction method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] The underpass construction method according to a preferred embodiment of the present invention shown in Figures 1 and 2 is a method similar to the R&C construction method (registered trademark) shown in Figures 4(a) to (e), for example, in which an underground space 16 (see Figure 3) made of a box structure 15 that becomes the underground passage structure 10 is formed by crossing the ground directly below an existing structure, such as a railway track 19.By utilizing the hollow pipe members 13 that constitute the box-shaped roof 11 that are installed in advance, the piping and wiring 17 (see Figure 3) that are arranged to cross the ground below the existing structure 19 can be easily and efficiently arranged around the box structure 15 without being installed inside the underground space 16, thereby making it possible to construct the underground passage structure 10.
[0015] As shown in Figs. 1 and 2, the underpass construction method of this embodiment is an R&C construction method in which a box-shaped roof 11 including a top pipe row 12a and a pair of side pipe rows 12b on both sides, which have been installed in advance on the ground below a railroad track 19, which is an existing structure, is replaced by a box-shaped structure 15 having a rectangular cross-sectional shape, which is installed from a starting base 23 on the ground directly below the existing structure 19, thereby forming an underground space 16 by the box-shaped structure 15. In the R&C construction method, in the process of forming the box-shaped roof 11 by excavating a plurality of hollow pipe members 13 having a rectangular hollow cross-sectional shape into the ground below the existing structure, the top pipe row 12a The process of propelling and installing a piping / wiring pipe member 14 having a rectangular hollow cross-sectional shape similar to that of the hollow pipe member 13 by guiding it via a joint portion (not shown) to the side portion of the end hollow pipe member 13a located at the corners of both ends of the end member and the side pipe rows 12b, and then propelling and installing the box structure 15 on the ground directly below the existing structure 19, replacing the box-shaped roof 11, involves propelling the box structure 15 while leaving the piping / wiring pipe member 14 in the ground, and also includes a step of installing piping / wiring 17 in the piping / wiring pipe member 14 that has been left behind (see Figure 3).
[0016] In addition, in this embodiment, the underpass construction method preferably includes a step of filling a filling and solidifying material 18 such as foamed mortar inside the piping / wiring pipe member 14 in which the piping / wiring 17 is arranged.
[0017] In this embodiment, in an underpass construction method, preferably an R&C construction method, similarly to the conventional R&C construction method, a plurality of hollow pipe members 13 having a rectangular (including square) hollow cross-sectional shape are installed in advance along the outer peripheral shape of a box structure 15 to be installed at a planned location for forming an underground space 16, and a box-shaped roof 11 is formed by pipe rows arranged in a U-shaped cross-sectional shape, which is composed of a top surface pipe row 12a and a pair of side surface pipe rows 12b on both sides. Thereafter, the end face of the concrete box structure 15 is abutted against the rear end face of the box roof 11 via a center push jack 24a, and the box structure 15 is advanced by a front push jack 24b, so that the box structure 15 is replaced with the box roof 11 having a U-shaped cross-sectional shape made of a plurality of hollow pipe members 13, and is then installed underground.
[0018] In addition, in this embodiment, as described above, in the process of forming the box-shaped roof 11 by digging a plurality of hollow pipe members 13 into the ground below the existing structure 19, piping / wiring pipe members 14, which have a rectangular hollow cross-sectional shape similar to the hollow pipe members 13 and a joint portion (not shown), are each driven and installed adjacent to the sides of the end hollow pipe members 13a located at the corners on both sides of the side pipe row 12b at both ends of the top pipe row 12a.
[0019] That is, the piping / wiring pipe member 14 is easily and accurately installed, preferably at a predetermined position adjacent to the sides of the end hollow pipe members 13a on both sides, with the top surface portion positioned at the same height as the top surface portion of the end hollow pipe member 13a, while being guided by the previously installed end hollow pipe member 13a, using a propulsion facility similar to that used when propelling the other hollow pipe members 13 constituting the box-shaped roof 11, via a known joint portion (not shown) extending in the axial direction between the end hollow pipe member 13a and the side portion of the end hollow pipe member 13a, like the other hollow pipe members 13. This also makes it possible for these piping / wiring pipe members 14 adjacent to the end hollow pipe member 13a and positioned at the same height as it to function as a safety roof pipe that supports a load from above, together with the other hollow pipe members 13 in the top surface pipe row 12a.
[0020] Furthermore, in this embodiment, in the process of replacing the box-shaped roof 11 with the box-shaped structure 15 and driving it into the ground directly below the existing structure 19, the box-shaped structure 15 is driven while the piping / wiring pipe members 14 are left in the ground.
[0021] That is, as with the conventional R&C construction method, the box structure 15 is advanced from the starting base 23 toward the reaching base 25 while excavating the ground inside the box-shaped roof 11 using the center push jack 24a and the base push jack 24b and pushing out the box-shaped roof 11, and the piping and wiring pipe members 14 are buried adjacent to the outside of the end hollow pipe members 13a at both ends of the top pipe row 12a and in the outer area thereof, outside the area where the underground space is planned to be formed by the box structure 15. Therefore, when the tip of the box structure 15 is abutted against the end of the box-shaped roof 11 on the starting base 23 side and advanced, it is possible to leave the piping and wiring pipe members 14 in the ground. As a result, when the box structure 15 is installed across the ground directly below the railway tracks 19, which are an existing structure, as shown in Figure 3, the piping and wiring pipe member 14 is installed adjacent to the outside of the corner portions of the top surface 15a of the box structure 15, which has a rectangular cross-sectional shape, and extends along the corner portions over the entire length of the box structure 15, crossing the ground directly below the railway tracks 19.
[0022] Furthermore, this embodiment includes a step of installing piping and wiring 17 in the remaining piping and wiring pipe member 14. That is, in the step of installing piping and wiring 17, for example, pipes for water supply and sewerage and wiring such as electric wires and cables are inserted through the ground directly below the railroad tracks 19 and into the hollow interior of the piping and wiring pipe member 14 installed along the box structure 15, so that the piping and wiring 17 can be easily installed across the ground below the railroad tracks 19, which are existing structures.
[0023] As a result, a piping / wiring pipe member 14 is installed adjacent to the side of at least one upper corner of the propelled and installed box structure 15, with its top end positioned at the same height as the top surface of the box structure 15, and extended along the entire length of the underground passage structure 10, and wiring / piping 17 arranged across the ground below the existing structure 19 is inserted through the piping / wiring pipe member 14 without being arranged in the internal space of the box structure 15, resulting in the formation of an underground passage structure 10 constructed by the underpass construction method of this embodiment.
[0024] As a result, the underpass construction method and underground passage structure 10 of this embodiment make it possible to easily and efficiently arrange the piping and wiring 17 around the box structure 15, crossing the ground below the railroad tracks 19, which are an existing structure. The piping and wiring pipe member 14 is preferably subjected to an anti-rust treatment, which makes it possible to arrange the piping and wiring 17 inside it in a stable state for a long period of time.
[0025] In addition, the underpass construction method of this embodiment preferably includes a step of filling the inside of the pipe member 14 for piping and wiring in which the piping and wiring 17 are arranged with a filling and solidifying material 18 such as foamed mortar. As a result, the inside of the pipe member 14 for piping and wiring in which the wiring and piping 17 are arranged in the underground passage structure 10 of this embodiment is filled with the filling and solidifying material 18 such as foamed mortar and solidified. Since the filling and solidifying material 18 is filled and solidified inside the pipe member 14 for piping and wiring in which the wiring and piping 17 are arranged, it is possible to hold the wiring and piping 17 in a stable state, and it is possible to effectively prevent damage due to earthquakes, traffic vibrations, etc., and corrosion and leakage due to rainwater, etc.
[0026] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the existing structure in which an underground space is formed by a box structure in the ground below does not necessarily have to be a railroad track, and may be various other existing structures such as an existing structure for roads. The present invention can also be used in the SFT method, which is an underpass construction method in which the ground and earth left inside the box roof are removed in a work shaft on the arrival side. [Explanation of symbols]
[0027] 10 Underpass structure 11 Box roof 12a Top pipe row 12b Side pipe row 13 Hollow pipe components 13a End hollow pipe member 14 Piping and wiring pipe components 15 Box structure 16 Underground space 17 Piping and wiring 18 Filling and solidification materials 19 Railway tracks (existing structures) 20 Box structure 21 Box Roof 22 Hollow pipe member 23 Launch Base 24a Center Jack 24b Push jack 25 Reach base
Claims
1. In an underpass construction method, a box-shaped roof including a top pipe row and a pair of side pipe rows on both sides, which has been installed in advance on the ground below an existing structure, is replaced by a box-shaped structure having a rectangular cross section, which is propelled from a starting base to the ground directly below the existing structure, thereby forming an underground space using the box-shaped structure, In the process of forming the box-shaped roof by digging a plurality of hollow pipe members having a rectangular hollow cross-sectional shape into the ground below the existing structure, pipe members for piping and wiring having a rectangular hollow cross-sectional shape similar to the hollow pipe members are advanced and installed by guiding the end hollow pipe members through joints to side portions of end hollow pipe members located at corners between the side pipe rows at both ends of the top pipe row, In the step of installing the box structure on the ground directly below the existing structure by replacing the box-shaped roof with the box structure, the box structure is advanced while the piping / wiring pipe members are left in the ground, The underpass construction method further includes a step of installing piping and wiring in the piping and wiring pipe members that have been left behind.
2. An underpass construction method as described in claim 1, wherein the piping / wiring pipe members installed adjacent to the side portions of the end hollow pipe members at both ends of the top panel pipe row function as safety roof pipes that support loads from above together with the top panel pipe row.
3. 3. The underpass construction method according to claim 1, further comprising the step of filling a filling and solidifying material into the inside of the piping / wiring pipe member in which the piping / wiring is arranged.
4. An underground passage structure constructed by the underpass construction method according to claim 1 or 2, the piping / wiring pipe member is installed adjacent to a side surface of at least one upper corner of the box structure that has been thrust and installed, with its top end positioned at the same height as the top surface of the box structure, and extended along the entire length of the underground passage structure; An underground passage structure constructed using the underpass construction method, in which wiring and piping that is laid across the ground below the existing structure is not laid in the internal space of the box structure, but is inserted through the piping and wiring pipe members.
5. 5. An underground passage structure according to claim 4, wherein the inside of the piping / wiring pipe member in which the wiring / piping is arranged is filled with a filling and solidifying material and solidified.
Citation Information
Patent Citations
Method for executing underground structure
JP2002357079A
Underground structure embedding method
JP2006104744A
Method for dismantling box-shaped roof pipe
JP2010229779A
Method of constructing pipe roof
JP2012215026A
Method of constructing underpass across railway and highway without affecting normal traffic thereof
US4405260A