Underpass construction method and underpass building

The method addresses the inefficiencies of traditional underpass construction by integrating piping and wiring alongside the box structure using hollow pipe members and solidifying materials, enhancing installation efficiency and space utilization.

JP2024143685APending Publication Date: 2024-10-11OKUMURA CORP +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2023056473
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing underpass construction methods require separate construction work to drill through-holes for installing piping and wiring, which is time-consuming and costly, and these installations reduce the effective area and aesthetic appearance of the underground space.

Method used

The method involves installing piping and wiring pipe members alongside the box structure, using hollow pipe members with a rectangular cross-section, and filling them with a solidifying material like foam mortar to efficiently integrate these elements without occupying the internal space of the box structure.

Benefits of technology

Piping and wiring can be easily and efficiently installed around the box structure, maintaining the space's functionality and aesthetics while reducing installation time and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143685000001_ABST
    Figure 2024143685000001_ABST
Patent Text Reader

Abstract

To provide an underpass construction method which can arrange piping and wiring simply and efficiently around a box body structure across a ground below an existing building.SOLUTION: An underpass construction method in this invention thrusts and places a box body structure 15 that has a rectangular-shape cross section into underground replacing a previously-installed box-shape roof, and creates an underground space 16 formed in the box body structure 15. In the procedure of forming a box-shape roof 11, pipe members 14a, 14b for pipelines and wires are placed by being thrust with joint parts as a guide on the side face of hollow pipe members 13 of side-face pipe rows 12b. In the procedures to place the box body structure 15 in the ground right below an existing building 19, the box body structure 15 is thrust while leaving the pipe members 14a, 14b for pipelines and wires underground. The retained pipe members 14a, 14b for pipelines and wires will have pipeline and wire items 17 laid in them.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an underpass construction method and an underground passage structure, and in particular to an underpass construction method in which a box-shaped structure is thrust-installed to replace a previously installed box-shaped roof, thereby forming an underground space using a box-shaped structure, and an underground passage structure constructed by the underpass construction method. [Background technology]

[0002] For example, underpass construction methods such as the R&C method (registered trademark) (see, for example, Patent Document 1) and the SFT method (registered trademark) (see, for example, Patent Document 2) are known as methods for constructing underground passages that cross existing railways, roads, etc., in the ground below the existing structure where the underground space is to be formed, for example, by installing a plurality of hollow pipe members having a rectangular hollow cross-sectional shape in series in the circumferential direction of the planned formation location in the ground below the existing structure where the underground space is to be formed, forming a box-shaped roof including a top pipe row that supports the existing structure from below and a pair of side pipe rows on both sides, and then replacing the formed box-shaped roof with, for example, a box structure having a rectangular cross-sectional shape made of precast concrete, which is advanced into the ground where the underground space is to be formed, thereby forming an underground space by the replaced box structure.

[0003] That is, as an underpass construction method, preferably an R&C construction method, for example, as shown in Figs. 4(a) to (d), a plurality of hollow pipe members 21 having a hollow cross-sectional shape, preferably a rectangular shape (including a square shape), are installed in advance along the outer circumferential shape of a box structure 20 to be installed at a location where an underground space is to be formed, to form a box-shaped roof 22 by pipe rows arranged in a U-shaped cross-sectional shape, preferably consisting of a top pipe row 22a and a pair of side pipe rows 22b on both sides. (see Figures 4(a) and (b)), and then the front end surface of the concrete box structure 20 is abutted against the rear end surface of the box-shaped roof 22 via a center jack 24a (see Figure 4(c)), and the box structure 20 is advanced by a main jack 24b (see Figure 4(d)), thereby replacing the box structure 20 with a box-shaped roof 22 having a U-shaped cross-section made of multiple hollow pipe members 21, and the box structure 20 is installed underground (see Figure 4(e)). This is a well-known construction method. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A Summary of the Invention [Problem to be solved by the invention]

[0005] On the other hand, in the ground below an existing structure where an underground space is formed by a box structure using the underpass method, it may be necessary to lay, for example, pipes for water supply and sewerage, and wiring such as electric wires and cables across the ground below. If such pipes and wiring are laid inside the underground space formed by the box structure, it will reduce the effective area of ​​the underground space and also impair the aesthetic appearance of the underground space. Therefore, in the past, through holes were formed in the ground around the box structure by a work separate from the underpass method to enable these pipes and wiring to be laid across the ground below the existing structure, and these pipes and wiring were laid in the through holes formed. However, since it requires considerable cost and effort to precisely excavate and form such through holes at a specified position by a separate work, there is a need to develop a technology that allows these pipes and wiring to be laid around the box structure easily and efficiently, crossing under the existing structure.

[0006] The present invention aims to provide an underpass construction method that can easily and efficiently lay piping and wiring around a box structure by crossing the ground below an existing structure, and an underground passage structure constructed by the underpass construction method. [Means for solving the problem]

[0007] The present invention relates to an underpass construction method for forming an underground space by a box structure by propelling and installing a box structure having a rectangular cross section from a starting base to the ground immediately below an existing structure, replacing a box roof including a top pipe row and a pair of side pipe rows on both sides that have been installed in advance on the ground below the existing structure. In the process of forming the box roof by excavating a plurality of hollow pipe members having a rectangular hollow cross section into the ground below the existing structure, one or more of the central pipe members constituting the side pipe rows are The above-mentioned object has been achieved by providing an underpass construction method which includes a step of guiding a pipe member for piping and wiring through a joint portion at the side of an empty pipe member, driving and installing the pipe member for piping and wiring, and then replacing the box structure with the box-shaped roof and driving the box structure into the ground directly below the existing structure, while leaving the pipe member for piping and wiring in the ground.

[0008] In the underpass construction method of the present invention, it is preferable that the piping / wiring pipe member has a rectangular hollow cross-sectional shape similar to the hollow pipe member constituting the box-shaped roof.

[0009] Furthermore, the underpass construction method of the present invention preferably includes a step of filling a filling and solidifying material such as foamed mortar inside the piping / wiring pipe member in which the piping / wiring is arranged.

[0010] Furthermore, the present invention achieves the above-mentioned object by providing an underground passage structure constructed by the underpass construction method, in which one or more of the piping and wiring pipe members are arranged adjacent to the outside of at least one side portion of the jack-up installed box structure and are installed extending along the entire length of the side portion of the underground passage structure, and the wiring and piping arranged across the ground below the existing structure are not arranged in the internal space of the box structure but are inserted through the piping and wiring pipe members.

[0011] In the underground passage structure of the present invention, it is preferable that the inside of the piping / wiring pipe member in which the wiring / piping is arranged is filled with a filling and solidifying material such as foamed mortar and solidified. Effect of the Invention

[0012] According to the underpass construction method or underground passage construction of the present invention, piping and wiring can be easily and efficiently laid around the box structure, crossing the ground below the existing structure. [Brief description of the drawings]

[0013] [Figure 1] FIG. 1 is a schematic vertical sectional view illustrating an underpass construction method according to a preferred embodiment of the present invention. [Diagram 2] FIG. 2 is a schematic cross-sectional view taken along the line AA in FIG. 1, illustrating an underpass construction method according to a preferred embodiment of the present invention. [Diagram 3] FIG. 2 is a schematic cross-sectional view illustrating an underground passage structure formed by the underpass construction method. [Figure 4] 1(a) to 1(e) are schematic vertical sectional views and schematic horizontal sectional views illustrating an R&C construction method, which is an underpass construction method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] The underpass construction method according to a preferred embodiment of the present invention shown in Figures 1 and 2 is a method similar to the R&C construction method (registered trademark) shown in Figures 4(a) to (e), for example, in which an underground space 16 (see Figure 3) made of a box structure 15 that becomes the underground passage structure 10 is formed by crossing the ground directly below an existing structure, such as a railway track 19.By utilizing the hollow pipe members 13 that constitute the box roof 11 that are installed in advance, the piping and wiring 17 (see Figure 3) that are arranged to cross the ground below the existing structure 19 can be easily and efficiently arranged around the box structure 15 without being installed inside the underground space 16, thereby making it possible to construct the underground passage structure 10.

[0015] As shown in Figs. 1 and 2, the underpass construction method of this embodiment replaces the box-shaped roof 11 including the top pipe row 12a and a pair of side pipe rows 12b on both sides that were previously installed on the ground below the railroad tracks 19, which is an existing structure, by propelling and installing a box-shaped structure 15 having a rectangular cross-sectional shape from a starting base 23 to the ground directly below the existing structure 19, thereby forming an underground space 16 by the box-shaped structure 15. In this R&C construction method, a plurality of hollow pipe members 13 having a rectangular hollow cross-sectional shape are excavated into the ground below the existing structure to form the box-shaped roof 11. In the step of installing the box-shaped roof 11, the piping and wiring pipe members 14a, 14b are driven and installed by guiding them via joints (not shown) to the side portions of one or more hollow pipe members 13 constituting the side pipe row 12b, and in the step of installing the box-shaped roof 11, the box-shaped structure 15 is driven and installed on the ground directly below the existing structure 19, in which the box-shaped roof 11 is replaced by the box-shaped roof 11, and the step of installing the box-shaped roof 11 and the box-shaped roof 11 is replaced by the box-shaped roof 11.

[0016] In addition, in this embodiment, the underpass construction method preferably includes a step of filling a filling and solidifying material 18 such as foamed mortar inside the piping and wiring pipe members 14a, 14b in which the piping and wiring 17 are arranged.

[0017] In this embodiment, in an underpass construction method, preferably an R&C construction method, similarly to the conventional R&C construction method, a plurality of hollow pipe members 13 having a rectangular (including square) hollow cross-sectional shape are installed in advance along the outer peripheral shape of a box structure 15 to be installed at a planned location for forming an underground space 16, and a box-shaped roof 11 is formed by pipe rows arranged in a U-shaped cross-sectional shape, which is composed of a top surface pipe row 12a and a pair of side surface pipe rows 12b on both sides. Thereafter, the end face of the concrete box structure 15 is abutted against the rear end face of the box roof 11 via a center push jack 24a, and the box structure 15 is advanced by a front push jack 24b, so that the box structure 15 is replaced with the box roof 11 having a U-shaped cross-sectional shape made of a plurality of hollow pipe members 13, and is then installed underground.

[0018] In this embodiment, as described above, in the process of forming the box-shaped roof 11 by digging a plurality of hollow pipe members 13 into the ground below the existing structure 19, the piping / wiring pipe members 14a, 14b are driven and installed adjacent to the sides of one or more hollow pipe members 13 constituting the side pipe row 12b. In this embodiment, the piping / wiring pipe member 14a provided adjacent to the hollow pipe member 13 of the right side pipe row 12b in FIG. 2 is a pipe member having a hollow cross-sectional shape that is preferably rectangular similar to the hollow pipe member 13 constituting the box-shaped roof 11. The piping / wiring pipe member 14b provided adjacent to the hollow pipe member 13 of the left side pipe row 12b in FIG. 2 is a pipe member having a hollow cross-sectional shape that is larger than that of the hollow pipe member 13 constituting the box-shaped roof 11, preferably a circular hollow cross-sectional shape, and a joint portion (not shown) on the side portion that can be joined to the joint portion of the hollow pipe member 13.

[0019] In this way, the size and shape of the piping / wiring pipe members 14a, 14b can be designed as appropriate according to the type and number of piping / wiring 17 arranged inside, the required gradient, etc. Also, one or more hollow pipe members 13 in the side pipe row 12b that guide the jacking of the piping / wiring pipe members 14a, 14b via joints (not shown) in the side sections that can be joined to the joints of the piping / wiring pipe members 14a, 14b can be selected as appropriate according to the height position at which the piping / wiring 17 is arranged, the number of the piping / wiring 17, etc.

[0020] These piping / wiring pipe members 14 can be installed by the same construction method as for each hollow pipe member 13, using the same propulsion equipment as that used to propel the hollow pipe members 13 constituting the box-shaped roof 11. That is, the piping / wiring pipe members 14 can be easily and accurately installed at predetermined positions adjacent to the side of a selected hollow pipe member 13 while being guided by the previously installed hollow pipe member 13, for example, via a known joint portion (not shown) extending axially between the side portion of the hollow pipe member 13 in the side portion pipe row 12b.

[0021] Furthermore, in this embodiment, in the process of installing the box-shaped structure 15 in place of the box-shaped roof 11 and driving it into the ground directly below the existing structure 19, the box-shaped structure 15 is driven while the piping and wiring pipe members 14a, 14b are left in the ground.

[0022] That is, as with the conventional R&C construction method, the box structure 15 is propelled from the starting base 23 toward the reaching base 25 while excavating the ground inside the box-shaped roof 11 and pushing out the box-shaped roof 11 using the center push jack 24a and the base push jack 24b, and the piping and wiring pipe members 14a, 14b are buried adjacent to the sides of the hollow pipe members 13 of the side pipe row 12b, in the outer area outside the area where the underground space is planned to be formed by the box structure 15. Therefore, when the tip of the box structure 15 is abutted against the end of the box-shaped roof 11 on the starting base 23 side and propelled forward, it is possible to leave the piping and wiring pipe members 14a, 14b in the ground. As a result, when the box structure 15 is installed across the ground directly below the railway track 19, which is an existing structure, as shown in Figure 3, the piping and wiring pipe members 14a, 14b are installed adjacent to the outside of the side portion 15a of the box structure 15, which has a rectangular cross-sectional shape, and extend along the side portion 15a over the entire length of the box structure 15, crossing the ground directly below the railway track 19.

[0023] Furthermore, this embodiment includes a step of installing piping and wiring 17 in the remaining piping and wiring pipe members 14a, 14b. That is, in the step of installing piping and wiring 17, for example, pipes for water supply and sewerage and wiring such as electric wires and cables are inserted through the ground directly below the railroad tracks 19 and into the hollow interiors of the piping and wiring pipe members 14a, 14b installed along the box structure 15, so that the piping and wiring 17 can be easily installed across the ground below the railroad tracks 19, which are existing structures.

[0024] As a result, one or more (in this embodiment, two locations) piping and wiring pipe members 14a, 14b are arranged adjacent to the outside of at least one (in this embodiment, both) side portions 15a of the propelled and installed box structure 15, and are installed extending along the entire length of the side portion of the underground passage structure 15, and wiring and piping 17 arranged across the ground below the existing structure 19 is arranged by being inserted through the piping and wiring pipe members 14a, 14b without being arranged in the internal space of the box structure 15, thereby forming an underground passage structure 10 constructed by the underpass construction method of this embodiment.

[0025] As a result, the underpass construction method and underground passage structure 10 of this embodiment make it possible to easily and efficiently arrange the piping and wiring 17 around the box structure 15, crossing the ground below the railroad tracks 19, which are an existing structure. The piping and wiring pipe members 14a, 14b are preferably subjected to an anti-rust treatment, which makes it possible to arrange the piping and wiring 17 inside them in a stable state for a long period of time.

[0026] In addition, the underpass construction method of this embodiment preferably includes a step of filling the inside of the pipe members 14a, 14b for piping and wiring in which the piping and wiring 17 are arranged with a filling solidification material 18 such as foamed mortar. As a result, the inside of the pipe members 14a, 14b for piping and wiring in which the wiring and piping 17 are arranged in the underground passage structure 10 of this embodiment is filled with the filling solidification material 18 such as foamed mortar and solidified. Since the filling solidification material 18 is filled and solidified inside the pipe members 14a, 14b for piping and wiring in which the wiring and piping 17 are arranged, it is possible to hold the wiring and piping 17 in a stable state, and it is possible to effectively prevent damage due to earthquakes, traffic vibrations, etc., and corrosion and leakage due to rainwater, etc.

[0027] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the existing structure in which an underground space is formed by a box structure in the ground below does not necessarily have to be a railroad track, and may be various other existing structures such as an existing road structure. The present invention can also be used in the SFT method (registered trademark), which is an underpass construction method in which the ground and earth left inside the box roof are removed in a work shaft on the arrival side. [Explanation of symbols]

[0028] 10 Underpass structure 11 Box roof 12a Top pipe row 12b Side pipe row 13a End hollow pipe member 14a, 14b Piping and wiring pipe components 15 Box structure 16 Underground space 17 Piping and wiring 18 Filling and solidification materials 19 Railway tracks (existing structures) 20 Box structure 21 Box Roof 22 Hollow pipe member 23 Launch Base 24a Center Jack 24b Push jack 25 Reach base

Claims

1. In an underpass construction method, a box-shaped roof including a top pipe row and a pair of side pipe rows on both sides, which has been installed in advance on the ground below an existing structure, is replaced by a box-shaped structure having a rectangular cross section, which is propelled from a launch base to the ground directly below the existing structure, thereby forming an underground space using the box-shaped structure. In the process of forming the box-shaped roof by digging a plurality of hollow pipe members having a rectangular hollow cross-sectional shape into the ground below the existing structure, a piping / wiring pipe member is advanced and installed by guiding the pipe member to the side portion of one or more of the hollow pipe members constituting the side portion pipe row via a joint portion; In the step of installing the box structure on the ground directly below the existing structure by replacing the box-shaped roof with the box structure, the box structure is advanced while the piping / wiring pipe members are left in the ground, The underpass construction method further includes a step of installing piping and wiring in the piping and wiring pipe members that have been left behind.

2. 2. The underpass construction method according to claim 1, wherein the piping / wiring pipe member has a hollow rectangular cross-sectional shape similar to that of the hollow pipe member constituting the box-shaped roof.

3. 3. The underpass construction method according to claim 1, further comprising the step of filling a filling and solidifying material into the inside of the piping / wiring pipe member in which the piping / wiring is arranged.

4. An underground passage structure constructed by the underpass construction method according to claim 1 or 2, One or more of the piping and wiring pipe members are arranged adjacent to the outside of at least one side surface of the box structure that has been propelled and installed, and are installed by extending along the entire length of the side surface of the underground passage structure, An underground passage structure using the underpass construction method, in which the wiring and piping that is laid across the ground below the existing structure is not laid in the internal space of the box structure, but is inserted through the piping and wiring pipe members.

5. 5. An underground passage structure according to claim 4, wherein the inside of the piping / wiring pipe member in which the wiring / piping is arranged is filled with a filling and solidifying material and solidified.

Citation Information

Patent Citations

  • Method for executing underground structure

    JP2002357079A

  • Underground structure embedding method

    JP2006104744A

  • Method for dismantling box-shaped roof pipe

    JP2010229779A

  • Method of constructing pipe roof

    JP2012215026A

  • Method of constructing underpass across railway and highway without affecting normal traffic thereof

    US4405260A