Wall construction method and wall
The method addresses the challenge of fixing facing materials to studs near pillars by forming aligned holes and using specialized tools to insert screws from the back side, enhancing ease and efficiency of construction.
Patent Information
- Application Number
- JP2023056884
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing wall construction methods face difficulties in fixing facing materials to studs when pillars are nearby, as pillars obstruct the insertion of fixing members, increasing construction time and effort.
A wall construction method involving hole formation steps and the use of specialized tools to fix facing materials between the pillar and stud, allowing insertion and fixation from the back side, utilizing drill drivers and preparation screws to create aligned holes for easy screw insertion.
Facilitates easy fixation of facing materials to studs near pillars, reducing construction effort and ensuring efficient installation without obstruction, maintaining fire resistance and structural integrity.
Smart Images

Figure 2024143928000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a wall construction method and wall technology for fastening facings to studs. [Background technology]
[0002] Conventionally, techniques for wall construction methods for fixing facings to studs have been publicly known, as described in Patent Document 1, for example.
[0003] The construction method described in Patent Document 1 is for constructing a fire-resistant partition wall comprising a stud, a wall member, and a fixing member. The wall member is disposed adjacent to the stud. Hereinafter, the side of the wall member facing the stud is referred to as the back side, and the opposite side is referred to as the front side. The fixing member is composed of a tapping screw, a bolt, or the like. The fixing member is inserted from the front side of the wall member to the back side, thereby fixing the wall member to the stud.
[0004] However, with the construction method of Patent Document 1, if a building pillar is placed near the stud, the pillar may get in the way when inserting the fixing member, making it difficult to fix the wall member. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2018-91123 A Summary of the Invention [Problem to be solved by the invention]
[0006] The present invention has been made in consideration of the above-mentioned circumstances, and the problem it aims to solve is to provide a wall construction method and a wall that can easily fix a panel even when a stud is placed near a pillar. [Means for solving the problem]
[0007] The problem to be solved by the present invention has been described above, and the means for solving this problem will now be described.
[0008] That is, claim 1 is a wall construction method for fixing a panel to a stud arranged near a pillar of a building, the panel including a first panel arranged between the pillar and the stud, the construction method comprising: a first hole forming step of forming a first hole on the side of the stud opposite the first panel; a second hole forming step of forming a second hole on the side of the stud facing the first panel; a third hole forming step of forming a third hole in the first panel so as to communicate with the second hole; a setting step of setting a fastener for fixing the first panel to the stud through the third hole; and a first panel fixing step of inserting the fastener into the second hole and the third hole by using the first hole to pull the fastener from the second hole to fix the first panel.
[0009] In claim 2, in the first panel fixing step, the fixing tool is pulled in using a tool inserted into the first hole portion.
[0010] In claim 3, the tool is a drill equipped with a chuck device, and in the first face material fixing process, the chuck device is inserted into the first hole portion, and the fixing device is attracted by operating the drill while the fixing device is gripped by the chuck device.
[0011] In claim 4, the fastener has a shaft portion that can be inserted into the second hole portion and the third hole portion, and the third hole portion forming process forms the third hole portion by inserting a preparation member having a shaft portion having an outer diameter smaller than that of the fastener shaft portion from the stud side of the first panel and removing the preparation member from the first panel.
[0012] In claim 5, in the third hole forming step, the preparation member is inserted using a tool inserted into the first hole member, and the preparation member is removed from the first surface material.
[0013] In claim 6, the panel further includes a second panel arranged on the opposite side of the stud from the first panel, and the construction method further includes a second panel fixing step of fixing the second panel to the stud, and the first panel fixing step is performed prior to the second panel fixing step.
[0014] In claim 7, at least one stud is arranged near a column of the building; The structure comprises a panel that is placed between the stud and the pillar, and a fastener that is inserted into the stud and the panel to fix the panel to the stud, and a hole is formed in the stud at a position corresponding to the first fastener on the opposite side to the first panel. Effect of the Invention
[0015] The present invention has the following advantages.
[0016] In claim 1, even when the stud is disposed near the pillar, the panel can be easily fixed by utilizing the first hole portion.
[0017] In claim 2, the fixing device can be easily pulled by using a tool.
[0018] In claim 3, the fastener can be easily attracted by using the chuck device.
[0019] In claim 4, the third hole can be easily formed by using the preparation member.
[0020] In claim 5, the third hole can be easily formed using a tool.
[0021] In claim 6, since the second surface material does not get in the way when fixing the first surface material, the first surface material can be easily fixed.
[0022] In claim 7, even if a stud is placed near a pillar, the panel can be easily fixed using the first hole portion, so that a wall with a simple configuration can be provided. [Brief description of the drawings]
[0023] [Figure 1] FIG. 2 illustrates a fire resistant wall according to an embodiment of the present invention. [Diagram 2] Cross section AA. [Diagram 3] B-B cross section. [Figure 4] FIG. [Diagram 5] 4 is an exploded cross-sectional perspective view showing a stud, a first plaster board, a first screw, a third plaster board, and a second screw. FIG. [Figure 6] (a) A cross-sectional view showing how holes are drilled into the studs, and (b) a plan cross-sectional view showing the first gypsum board placed near the column. [Figure 7] (a) is a plan sectional view showing how the preparation screw is inserted, and (b) is a plan sectional view showing how the preparation screw is removed. [Figure 8] 1A is an explanatory diagram showing a first drill driver, and FIG. 1B is an explanatory diagram showing a second drill driver. [Figure 9] 1A is a cross-sectional plan view showing how the first screw is set, and FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0024] In the following description, the up / down and left / right directions are defined according to the arrows shown in the drawings.
[0025] Hereinafter, a fireproof wall 1 according to one embodiment of the present invention will be described with reference to Figs. 1 to 5 .
[0026] The fireproof wall 1 shown in Figures 1 and 2 has fire resistance and is intended to form a partition wall installed in the indoor space of a building. The fireproof wall 1 includes a runner 10, a stud 20, a first plaster board 30, a first screw 40, a second plaster board 50, a third plaster board 60, a second screw 70 (see Figure 3), and a fourth plaster board 80.
[0027] The runner 10 shown in FIG. 1 is for supporting the stud 20. The runner 10 is formed in an elongated shape. In this embodiment, the runner 10 is arranged with its longitudinal direction facing the left-right direction. The runner 10 is made of a metal member. A pair of runners 10 is provided, one above the other. The upper runner 10 is fixed to the floor slab of the upper floor or to a steel frame supporting the floor slab. The lower runner 10 is fixed to the floor slab of the floor in question.
[0028] The studs 20 are vertical components in the fire-resistant wall 1 (partition wall). The studs 20 are formed in an elongated shape with their longitudinal direction facing the up-down direction. As shown in FIG. 2, the studs 20 are formed in a roughly C-shape when viewed from above. The studs 20 are made of metal. A plurality of the studs 20 are arranged at equal intervals along the left-right direction (the longitudinal direction of the runner 10).
[0029] In this embodiment, one of the multiple studs 20 (the stud 20 in the left-right center in FIG. 2) is positioned near a pillar 90 installed in the indoor space of a building. More specifically, the one stud 20 is positioned slightly away from the pillar 90 in the direction in which a first screw 40, which will be described later, is inserted (upward on the page in FIG. 2). In this embodiment, the pillar 90 has a square steel pipe 91 covered with a fire-resistant covering material 92 to improve fire resistance.
[0030] In the following, the side where the pillar 90 is located (the side of space A1 shown in FIG. 2) will be referred to as the "front side" with respect to the stud 20, and the side where the pillar 90 is not located (the side of space A2 shown in FIG. 2) will be referred to as the "back side". In the following, the direction from one of the front side and the back side to the other will be referred to as the "depth direction". In the following, the center of the stud 20 in the depth direction will be referred to as the "partition core C10". In the following, the studs 20 arranged near the pillar 90 will be referred to as the "first stud 20A", and the other studs 20 will be referred to as the "second studs 20B".
[0031] 2 and 4, the stud 20 (first stud 20A and second stud 20B) includes a web 21, a first flange 22, and a second flange 23. The web 21 is a generally plate-shaped portion whose plate surface faces in the left-right direction.
[0032] The first flange 22 is a generally plate-shaped portion extending rightward from the end of the front side of the web 21. A lip portion 22a extending to the rear side (partition core C10) is formed at the tip (right end) of the first flange 22. The second flange 23 is a generally plate-shaped portion formed at the end of the rear side of the web 21. The second flange 23 is formed symmetrically to the first flange 22 in the depth direction with respect to the partition core C10. The second flange 23 is formed with a lip portion 23a.
[0033] The first gypsum board 30 and the second gypsum board 50 are members (surface materials) that form a wall surface on the front side of the stud 20. The first gypsum board 30 and the second gypsum board 50 are arranged with their board surfaces facing the depth direction. The first gypsum board 30 is arranged adjacent to the front side of the stud 20. The second gypsum board 50 is arranged adjacent to the front side of the first gypsum board 30 and is fixed to the first gypsum board 30 by staples (not shown). Note that in FIG. 1, a portion (left side) of the first gypsum board 30 and the second gypsum board 50 are omitted.
[0034] As shown in Figs. 3 and 5, the first gypsum board 30 is fixed to the stud 20 by the first screw 40. The first screw 40 has a head 41 and a shaft 42. The shaft 42 is formed so as to extend from the head 41 toward the back side. A male thread is formed on the outer periphery of the shaft 42 (not shown). The tip (end on the back side) of the shaft 42 is formed in a sharp shape. Note that the drawings attached to this specification show the first screw 40 in which the entire shaft 42 is formed in a sharp shape, but in reality, the part of the first screw 40 other than the tip is formed in a substantially cylindrical shape.
[0035] The first screw 40 is inserted into the first plaster board 30 until the head 41 sinks into the front surface of the first plaster board 30. Since the overall length (depth width) of the first screw 40 in this embodiment is longer than the combined thickness of the first plaster board 30 and the first flange 22, the first screw 40 penetrates the first plaster board 30 and the first flange 22. In this manner, the first screw 40 can fix the first plaster board 30 to the stud 20.
[0036] The first screws 40 are inserted into the first stud 20A and the second stud 20B, respectively (see FIG. 2). A plurality of first screws 40 are inserted into each stud 20 in the vertical direction. The number of first screws 40 inserted into each stud 20 is appropriately determined according to the vertical width of the fire-resistant wall 1, and is set to about ten in this embodiment.
[0037] 2 and 4, the third gypsum board 60 and the fourth gypsum board 80 are members (surface materials) that form the wall surface on the back side of the studs 20. The third gypsum board 60 and the fourth gypsum board 80 are configured symmetrically in the depth direction with the first gypsum board 30 and the second gypsum board 50, with the partition core C10 as the base.
[0038] 3 and 5, the third gypsum board 60 is disposed with its board surface facing the depth direction and is fixed to the second flange 23 of the stud 20 by the second screw 70. The fourth gypsum board 80 is disposed with its board surface facing the depth direction and is fixed to the third gypsum board 60 by a staple (not shown). The second screw 70 in this embodiment is inserted into the third gypsum board 60 so that its height position is different from that of the first screw 40.
[0039] 2 and 3, the first stud 20A is located near the pillar 90, and so when attempting to insert the first screw 40 into the first plaster board 30 from the front side, the pillar 90 gets in the way, raising concerns that this will increase the amount of work required. For example, if there is only a gap between the first plaster board 30 and the pillar 90 large enough for a worker to fit his or her hand through (e.g., a gap of about 70 mm, see symbol C in FIG. 2), it will be difficult to insert a tool such as a screwdriver into the gap, making it difficult to insert the first screw 40 from the front side.
[0040] In this case, for example, the portion of the first gypsum board 30 that interferes with the pillar 90 is cut out, and a board cut to an appropriate width is erected from the end (cutout portion) perpendicular to the surface of the fire-resistant covering material 92 of the pillar 90. If the first screws 40 are not inserted into the first gypsum board 30 in this way, construction work will increase.
[0041] In this regard, by using the wall construction method of this embodiment, the first screw 40 can be easily inserted into the first stud 20A arranged near the pillar 90. This construction method is used when there is a gap between the first gypsum board 30 and the pillar 90 that is large enough for a worker to reach, but not large enough for a tool to be inserted to insert the first screw 40. This construction method will be described below with reference to Figs. 3 to 9.
[0042] This construction method mainly involves the stud hole drilling process shown in Fig. 6(a), the board hole drilling process shown in Fig. 7, the setting process shown in Fig. 9(a), and the first, second and third fixing processes shown in Fig. 9(b). Each process will be explained in order below.
[0043] The stud hole drilling process shown in FIG. 6(a) is a process of drilling holes in the first stud 20A. In the stud hole drilling process, the worker drills a hole penetrating in the depth direction in the second flange 23 (the side opposite the first plaster board 30) of the first stud 20A. At this time, the worker drills a hole at the same height as the part where the first screw 40 is inserted. The worker also drills a hole penetrating in the depth direction in the first flange 22 (the side of the first plaster board 30) of the first stud 20A at the same height as the second flange 23. Hereinafter, the hole drilled in the first flange 22 is referred to as the "front side through hole 22b" and the hole drilled in the second flange 23 is referred to as the "rear side through hole 23b."
[0044] The front side through hole 22b and the back side through hole 23b are formed by penetrating the first flange 22 and the second flange 23 with, for example, a drill. The front side through hole 22b and the back side through hole 23b are formed in a substantially circular shape when viewed in the depth direction (see FIG. 5).
[0045] The inner diameter of the front side through hole 22b is smaller than the outer diameter of the shaft portion 42 of the first screw 40. The inner diameter of the back side through hole 23b is larger than the inner diameter of the front side through hole 22b and the outer diameter of the shaft portion 42. The inner diameter of the back side through hole 23b is also larger than the outer diameter of a bit D13 of a first drill driver D10 and a chuck device D22 of a second drill driver D20, which will be described later. Note that the order in which the front side through hole 22b and the back side through hole 23b are formed in the stud hole drilling process is not particularly limited.
[0046] As shown in Fig. 6(b), in this construction method, after the stud drilling step, the first gypsum board 30 is pressed against the first stud 20A. Then, the board drilling step shown in Fig. 7 is performed. Note that the first gypsum board 30 may be pressed against the first stud 20A after the first gypsum board 30 is fixed to the stud 20B.
[0047] The board hole drilling step is a step of drilling holes in the first plaster board 30. As shown in Fig. 7(a), in the board hole drilling step, a preparatory screw B10 is inserted into the first plaster board 30 by a first drill driver D10.
[0048] The preparatory screw B10 is for drilling a hole in the first plaster board 30. The preparatory screw B10 has a head B11 and a shaft B12. The outer diameter of the shaft B12 is smaller than that of the shaft 42 of the first screw 40. The length (axial width) of the shaft B12 is longer than that of the shaft 42 of the first screw 40. The preparatory screw B10 is positioned on the back side of the first plaster board 30 when being inserted into the first plaster board 30.
[0049] The first drill driver D10 shown in Fig. 8(a) is an electric tool for screwing, drilling, etc. The first drill driver D10 includes a main body D11, a chuck device D12, and a bit D13.
[0050] The main body D11 has a built-in motor. The chuck device D12 is attached to the tip of the main body D11 and is for gripping the bit D13. The chuck device D12 has a plurality of claws (not shown) and can grip the bit D13 with the claws. The bit D13 is an attachment (tip tool) of the first drill driver D10. The bit D13 of this embodiment is formed in an elongated shape and is formed so as to be able to screw into the head B11 of the preparation screw B10. The first drill driver D10 can rotate the bit D13 by driving the motor.
[0051] As shown in FIG. 7(a), in the board drilling step, the bit D13 of the first drill driver D10 is inserted from the back side into the back side through hole 23b of the second flange 23. The bit D13 is screwed into the head B11 of the preparatory screw B10. In this state, the motor of the first drill driver D10 is driven to rotate the bit D13. This rotation causes the shaft B12 of the preparatory screw B10 to be inserted from the back side (first stud 20A side) into the first gypsum board 30 through the front side through hole 22b of the first stud 20A. In this construction method, the preparatory screw B10 is inserted until the shaft B12 penetrates the first gypsum board 30.
[0052] As shown in Fig. 7(b), after the preparatory screw B10 is inserted, in the board drilling step, the motor of the first drill driver D10 is driven and the bit D13 is rotated in the reverse direction. This causes the preparatory screw B10 to be pulled out of the first gypsum board 30 and removed from the fireproof wall 1. In this manner, in this embodiment, a through hole 31 communicating with the front-side through hole 22b is formed in the first gypsum board 30. The inner diameter of the through hole 31 is approximately the same as the outer diameter of the shaft B12 of the preparatory screw B10, and is therefore smaller than the outer diameter of the shaft 42 of the first screw 40.
[0053] In this construction method, the setting process shown in Fig. 9(a) is carried out after the board drilling process. The setting process is a process for setting the first screw 40. In the setting process, a worker inserts his / her hand into the gap C between the first gypsum board 30 and the pillar 90, and sets the first screw 40 from the front side of the first gypsum board 30.
[0054] At this time, the worker manually pushes the shank 42 of the first screw 40 from the front side to the back side of the through hole 31 of the first gypsum board 30. This causes the shank 42 of the first screw 40 to protrude a predetermined distance from the front side through hole 22b of the first stud 20A to the back side. In this manner, the first screw 40 is set. The predetermined distance is a length that allows the shank 42 of the first screw 40 to be grasped by the second drill driver D20. Specifically, the length is about 15 mm.
[0055] In this construction method, the first fixing step shown in Fig. 9(b) is performed after the setting step. The first fixing step is a step of fixing the first gypsum board 30 to the first stud 20A. In the first fixing step, a second drill driver D20 is inserted into the back side through hole 23b of the first stud 20A.
[0056] 8(b) is an electric tool for pulling the first screw 40 set in the first plaster board 30 from the front side to the back side. The second drill driver D20 is configured so that the tip of the second drill driver D20 can grip the shaft 42 (rod-shaped member) of the first screw 40 with strong force.
[0057] The second drill driver D20 of this embodiment is configured to grip the shank 42 of the first screw 40 by utilizing the structure of the chuck device D12 of the first drill driver D10 described above. In other words, the second drill driver D20 is like the first drill driver D10 (see FIG. 8(a)) from which the bit D13 has been removed. The second drill driver D20 can grip the shank 42 of the first screw 40 by the claw portion D23 of the chuck device D22.
[0058] 9(b), in the first fixing step, the chuck device D22 of the second drill driver D20 is inserted from the back side into the back-side through-hole 23b of the second flange 23. In this way, the second drill driver D20 is positioned on the back side of the first gypsum board 30 in the first fixing step.
[0059] The chuck device D22 inserted into the rear through-hole 23b of the second flange 23 grips the shaft portion 42 of the first screw 40 with the claw portion D23. In this state, a motor built into the main body portion D21 of the second drill driver D20 is driven. This causes the second drill driver D20 to reversely rotate the first screw 40. Note that reverse rotation means that the chuck device D22 of the second drill driver D20 is rotated in the opposite direction (the direction in which the first screw 40 is loosened when fixing the facing material (first gypsum board 30) to the second stud 20B) to the direction opposite to the direction in which the first screw 40 is inserted from the front side.
[0060] The first screw 40 is pulled from the front side to the back side by being rotated in the reverse direction, and inserted into the through hole 31 of the first gypsum board 30 and the front side through hole 22b of the first stud 20A. In this manner, in this construction method, the first gypsum board 30 is fixed to the first stud 20A by working on the back side of the first gypsum board 30.
[0061] In this construction method, the second fixing step is performed after the first fixing step. The second fixing step is a step of fixing the first plaster board 30 to the second stud 20B shown in Fig. 2. When fixing the second stud 20B, the pillar 90 is unlikely to get in the way when inserting the first screw 40. For this reason, in the second fixing step, the first screw 40 is inserted into the second stud 20B and the first plaster board 30 from the front side (by working on the front side of the first plaster board 30).
[0062] In this construction method, the third fixing step is performed after the second fixing step. The third fixing step is a step of fixing gypsum boards other than the first gypsum board 30 to the studs 20. In the third fixing step, the second gypsum board 50 is fixed to the first gypsum board 30. Basically, staples are driven into the second gypsum board 50 from the front side, but since the space between the second gypsum board 50 and the pillar 90 is narrow, staples are driven into the relevant location from the back side of the first gypsum board 30.
[0063] 3 is fixed to the studs 20, and a fourth plaster board 80 is fixed to the third plaster board 60. The second screws 70 for fixing the third plaster board 60 are inserted at a different height from the rear through holes 23b (first screws 40) so as not to be inserted through the rear through holes 23b of the first studs 20A. The fourth plaster board 80 is fixed to the third plaster board 60 by driving staples into it from the rear side.
[0064] In this manner, the fire resistant wall 1 is constructed by this construction method. In the fire resistant wall 1, of the studs 20, only the first stud 20A that is disposed near the column 90 is formed with a back side through hole 23b. The back side through hole 23b is formed at a height position corresponding to the first screw 40. For example, the back side through hole 23b is formed concentrically with the first screw 40.
[0065] Note that a heat insulating material, a sound absorbing material, or the like may be filled between the first gypsum board 30 and the third gypsum board 60 as necessary. Also, the rear through hole 23b does not necessarily need to be formed concentrically with the first screw 40, as long as the first screw 40 can be pulled by the second drill driver D20. However, in consideration of the workability using the second drill driver D20, it is desirable that the axis of the rear through hole 23b is located close to the axis of the first screw 40 so that it can be considered to be concentric with the first screw 40.
[0066] In this manner, with this construction method, the first screws 40 can be inserted from the back side of the first gypsum board 30 (by working on the side where there is no pillar 90). This makes it easier to fasten the first gypsum board 30 to the first stud 20A without the pillar 90 getting in the way, reducing the amount of work required for construction.
[0067] As described above, the first studs 20A and the second studs 20B are arranged at equal intervals in the left-right direction. With this construction method, the first screws 40 can be driven into all of the studs 20, even if a pillar 90 is present. This makes it possible to insert the first screws 40 into all of the studs 20 at equal intervals in the left-right direction without skipping the insertion of the first screws 40 into the studs 20 (first studs 20A) arranged near the pillar 90. This ensures a predetermined fire resistance.
[0068] In this embodiment, the through holes 31 are formed in the first plaster board 30 using the preparatory screws B10 (see FIG. 7). This makes it possible to easily form the through holes 31.
[0069] Specifically, the inner diameter of the through hole 31 in the first plaster board 30 is smaller than the shaft 42 of the first screw 40. If a commercially available drill is used to form a hole with such a small inner diameter, the size will not fit, and a custom-made drill will be required. In contrast, in this embodiment, by inserting a preparatory screw B10, which is smaller than the first screw 40, into the first plaster board 30, the through hole 31 can be easily formed without using a custom-made drill.
[0070] As described above, the wall construction method according to this embodiment is a wall construction method for fixing a facing material (first gypsum board 30 to fourth gypsum board 80) to a first stud 20A (stud 20) arranged near a pillar 90 of a building, the facing material including a first gypsum board 30 (first facing material) arranged between the pillar 90 and the first stud 20A, and the construction method includes a first hole forming process (a stud hole drilling process shown in FIG. 6( a )) for forming a back-side through hole 23 b (first hole portion) on the back side of the first stud 20A (the side opposite to the first gypsum board 30), and a second hole forming process (a stud hole drilling process shown in FIG. 6( a )) for forming a front-side through hole 22 b (second hole portion) on the front side of the first stud 20A (the side facing the first gypsum board 30). 6(a)), a third hole forming process (board hole drilling process shown in FIG. 7) of forming a through hole 31 (third hole portion) in the first gypsum board 30 so as to communicate with the front-side through hole 22b, a setting process (see FIG. 9(a)) of setting a first screw 40 (fixing device) for fixing the first gypsum board 30 to the first stud 20A through the through hole 31, and a first surface material fixing process (first fixing process shown in FIG. 9(b)) of pulling the first screw 40 from the front-side through hole 22b by utilizing the back-side through hole 23b, thereby inserting the first screw 40 into the front-side through hole 22b and the through hole 31 to fix the first gypsum board 30.
[0071] With this configuration, even when the first stud 20A is disposed near the pillar 90, the first gypsum board 30 can be easily fixed from the back side.
[0072] In the first face material fixing step, the first screw 40 is pulled in using a second drill driver D20 (tool) inserted into the rear through-hole 23b (see FIG. 9(b)).
[0073] With this configuration, the first screw 40 can be easily pulled in using the second drill driver D20.
[0074] In addition, the second drill driver D20 is a drill equipped with a chuck device D22, and in the first face material fixing process, the chuck device D22 is inserted into the rear through hole 23b, and the first screw 40 is pulled in by operating the drill while being gripped by the chuck device D22 (see Figure 9 (b)).
[0075] With this configuration, the first screw 40 can be easily attracted by using the chuck device D22.
[0076] In addition, the first screw 40 has a shaft portion 42 that can be inserted into the front side through hole 22b and the through hole 31, and the third hole formation process involves inserting a preparatory screw B10 (preparatory member) having a shaft portion B12 having an outer diameter smaller than that of the shaft portion 42 of the first screw 40 into the first gypsum board 30 from the back side of the first gypsum board 30 (the first stud 20A side of the first gypsum board 30) and removing the preparatory screw B10 from the first gypsum board 30 to form the through hole 31 (see Figure 7).
[0077] With this configuration, the through holes 31 can be easily formed using the preparatory screws B10.
[0078] In addition, in the third hole forming process, a first drill driver D10 is inserted into the rear through hole 23b to insert the preparation screw B10 and remove the preparation screw B10 from the first gypsum board 30 (see Figure 7).
[0079] With this configuration, the through hole 31 can be easily formed using the first drill driver D10. The chuck device D12 of the first drill driver D10 may be formed so as to be insertable into the back side through hole 23b. With this configuration, the first screw 40 can be pulled in using the first drill driver D10 from which the bit D13 has been removed. This allows the tools (the first drill driver D10 and the second drill driver D20) used in this construction method to be standardized.
[0080] In addition, the face material further includes a third gypsum board 60 and a fourth gypsum board 80 (second face material) that are arranged on the back side of the first stud 20A (the opposite side to the first face material), and the construction method further includes a second face material fixing step (the third fixing step described above) of fixing the third gypsum board 60 and the fourth gypsum board 80 to the first stud 20A, and the first face material fixing step is performed before the second face material fixing step.
[0081] With this configuration, the third gypsum board 60 and the fourth gypsum board 80 do not get in the way when the first gypsum board 30 is fixed, so that the first gypsum board 30 can be easily fixed.
[0082] As described above, the fire-resistant wall 1 of this embodiment comprises at least one first stud 20A (stud) arranged near a pillar 90 of a building, a first plaster board 30 (face material) arranged between the first stud 20A and the pillar 90, and a first screw 40 (fixing device) inserted into the first stud 20A and the first plaster board 30 to secure the first plaster board 30 to the first stud 20A, and a back side through hole 23b (hole portion) is formed in the first stud 20A at a position corresponding to the first screw 40 on the back side (the opposite side to the first plaster board 30).
[0083] By configuring in this manner, even if the first stud 20A is placed near the column 90, the first gypsum board 30 can be easily fixed from the back side, thereby providing a fire-resistant wall 1 with a simple configuration.
[0084] The first stud 20A according to this embodiment is one embodiment of the stud 20 according to the present invention. Moreover, the first gypsum board 30 to the fourth gypsum board 80 according to this embodiment are one embodiment of the facing material according to the present invention. Moreover, the first gypsum board 30 according to this embodiment is one embodiment of the first facing material according to the present invention. Moreover, the back side through hole 23b according to this embodiment is one embodiment of a first hole portion according to the present invention. Moreover, the front side through hole 22b according to this embodiment is one embodiment of the second hole portion according to the present invention. Moreover, the through hole 31 according to this embodiment is one embodiment of a third hole portion according to the present invention. Moreover, the first screw 40 according to this embodiment is one embodiment of a fastener according to the present invention. Moreover, the preparation screw B10 according to this embodiment is one embodiment of a preparation member according to the present invention. Moreover, the third gypsum board 60 and the fourth gypsum board 80 according to this embodiment are one embodiment of the second facing material according to the present invention.
[0085] Although the embodiment of the present invention has been described above, the present invention is not limited to the above configuration, and various modifications are possible within the scope of the invention described in the claims.
[0086] For example, the stud 20 is formed in a generally C-shape when viewed from above, but the shape of the stud 20 is not limited to this embodiment. For example, the stud 20 may be formed in a generally rectangular ring shape when viewed from above.
[0087] In addition, in this embodiment, two gypsum boards are provided on each of the front and back sides of the stud 20, but the number of gypsum boards can be changed as appropriate depending on the fire resistance performance required of the partition wall, etc.
[0088] Further, the wall of this embodiment is fire-resistant (fire-resistant wall 1), but the type of wall according to the present invention is not particularly limited.
[0089] In the board drilling step (see FIG. 7) of this embodiment, the preparatory screws B10 are inserted into the first gypsum board 30 using a power tool (first drill driver D10), but the method of inserting the preparatory screws B10 is not particularly limited. For example, the preparatory screws B10 may be inserted into the first gypsum board 30 by a worker manually turning a tool (driver).
[0090] In the board drilling step of this embodiment, the through holes 31 are formed in the first gypsum board 30 using the preparation screws B10, but the method of forming the through holes 31 is not particularly limited. However, since the pillars 90 are present on the front side of the first gypsum board 30, it is preferable to form the through holes 31 from the back side of the first gypsum board 30. This makes it possible to easily form the through holes 31.
[0091] In the first fixing step (see FIG. 9(b)) of this embodiment, the first screw 40 is pulled in using a power tool (second drill driver D20), but the method of pulling the first screw 40 is not limited to this embodiment as long as the first screw 40 is pulled in via the rear through-hole 23b. The first screw 40 may be pulled in by an operator manually turning a tool that is inserted into the rear through-hole 23b and grips the shaft 42 of the first screw 40. [Explanation of symbols]
[0092] 1 Fireproof wall 20 Studs 30 First gypsum board 40 1st Vis B10 Preparation Screw 22b Front-side through hole 23b Back-side through hole 31 Through hole
Claims
1. A wall construction method for fastening a facing to a stud disposed near a column of a building, comprising the steps of: The face material is a first facing disposed between the post and the stud; The construction method includes: a first hole forming step of forming a first hole on a side of the stud opposite the first face material; a second hole forming step of forming a second hole on the first face side of the stud; a third hole forming step of forming a third hole in the first surface material so as to communicate with the second hole; a setting step of setting a fastener for fastening the first panel to the stud through the third hole; a first surface material fixing process of inserting the fastener into the second hole portion and the third hole portion by drawing the fastener from the second hole portion using the first hole portion, thereby fixing the first surface material; Equipped with How to build a wall.
2. In the first surface material fixing step, Pulling the fastener with a tool inserted through the first hole; A method for constructing a wall according to claim 1.
3. The tool comprises: A drill equipped with a chuck device, In the first surface material fixing step, The chuck device is inserted into the first hole portion; The fastener is pulled in by operating the drill while the fastener is gripped by the chuck device. A method for constructing a wall according to claim 2.
4. The fixing device is a shaft portion that can be inserted into the second hole portion and the third hole portion; The third hole forming step includes: a preparation member having an axial portion having an outer diameter smaller than that of the axial portion of the fastener is inserted from the stud side of the first face material, and the preparation member is removed from the first face material to form the third hole portion; A method for constructing a wall according to any one of claims 1 to 3.
5. In the third hole forming step, inserting the preparation member using a tool inserted through the first hole portion and removing the preparation member from the first face material; A method for constructing a wall according to claim 4.
6. The face material is a second face disposed on an opposite side of the stud from the first face, The construction method includes: The method further includes a second panel fixing step of fixing the second panel to the stud, The first surface material fixing step includes: This is carried out prior to the second surface material fixing step. A method for constructing a wall according to any one of claims 1 to 3.
7. At least one stud disposed adjacent a column of the building; A facing disposed between the stud and the column; A fastener that is inserted into the stud and the face material and fastens the face material to the stud; Equipped with The studs include: A hole is formed at a position corresponding to the fastener on the opposite side of the face material. wall.