Construction method of superstructure on water

The method uses precast concrete blocks with through holes and divided members to close gaps from above the water, addressing inefficiencies and safety concerns in existing superstructure construction methods.

JP2024150201APending Publication Date: 2024-10-23TOA KENSETSU KK
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023063495
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-10
Publication Date
2024-10-23

AI Technical Summary

Technical Problem

Existing methods for constructing superstructures over water require complex underwater work, limiting construction efficiency and posing safety risks for workers.

Method used

A method involving precast concrete blocks with vertically penetrating through holes for pile insertion, using divided members to close gaps with filler concrete, allowing construction from above the water surface without underwater work.

Benefits of technology

Enables efficient and safe construction of superstructures by allowing gap closure and integration from above the water, improving efficiency and worker safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024150201000001_ABST
    Figure 2024150201000001_ABST
Patent Text Reader

Abstract

To provide a construction method of a superstructure on water that can efficiently construct a superstructure without performing a work below precast concrete blocks installed on piles erected on a water bottom ground.SOLUTION: By arranging a plurality of divided members 10 provided with an insertion hole 12 in a line in a circumferential direction of a through hole 3, each of the divided members 10 is supported by supports 14 inserted into the insertion hole 12 so as to slide and rotate along a bottom surface of a precast concrete block 2. By sliding each of the divided members 10 from above the precast concrete block 2 toward an outer peripheral surface of a pile 40, an arc-shaped front end portion 11 of each of the divided members 10 is fitted externally onto an outer peripheral surface of the pile 40. A gap S between the outer peripheral surface of the pile 40 and an inner peripheral surface at the bottom of the through hole 3 of the precast concrete block 2 is sealed by the divided members 10.SELECTED DRAWING: Figure 11
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for constructing a superstructure above water, and more specifically, to a method for constructing a superstructure above water that allows the superstructure to be constructed efficiently without performing work below precast concrete blocks installed on piles erected on the waterbed. [Background technology]

[0002] One method for constructing a superstructure on water, such as a pier supported by piles erected on the waterbed, is to place reinforcing bars on the water, set up formwork, and pour ready-mixed concrete into the formwork at the construction site and allow it to harden. This method of constructing a superstructure requires the construction of temporary scaffolding on the water, and there is a lot of cumbersome work on the water, so there is a limit to how much construction efficiency can be improved.

[0003] Therefore, as a method for constructing an overwater structure (superstructure), a construction method has been proposed in which a precast concrete slab having pile holes (through holes) through which piles are inserted is formed on the ground, the precast concrete slab is fixed to the piles with the heads of the piles loosely inserted into the pile holes of the precast concrete slab, and scaffolding is attached to the outside of the precast concrete slab (see, for example, Patent Document 1). In this construction method, the gap between the pile holes of the precast concrete slab and the outer peripheral surface of the pile is closed with a leak stopper plate provided below the precast concrete slab, and the above-mentioned gap is filled with non-shrink mortar, thereby fixing the precast concrete slab to the head of the pile. However, in the construction method proposed in Patent Document 1, the work of closing the gap between the pile holes of the precast concrete slab and the outer peripheral surface of the pile with a leak stopper plate must be performed from below the precast concrete slab installed on the pile, and workers such as divers must enter under the precast concrete slab to perform complicated work. Therefore, there is room for improvement in the construction efficiency of constructing an overwater superstructure and the safety of workers. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2021-107631 A Summary of the Invention [Problem to be solved by the invention]

[0005] The object of the present invention is to provide a method for constructing a superstructure above water that can efficiently construct the superstructure without performing work below precast concrete blocks installed on piles erected on the waterbed. [Means for solving the problem]

[0006] In order to achieve the above-mentioned object, the method for constructing a superstructure above water of the present invention comprises the steps of: an installation step of placing a precast concrete block having a through hole penetrating vertically so that a pile erected on the water bottom can be inserted into the through hole at a predetermined position with the pile loosely inserted into the through hole; a closing step of closing the gap between the outer circumferential surface of the pile and the inner circumferential surface of the lower part of the through hole with a bottom plate; and a pouring step of filling the gap between the outer circumferential surface of the pile and the inner circumferential surface of the through hole with fill concrete and solidifying it, thereby fixing a superstructure integrated with the precast concrete block and the solidified fill concrete to the top of the pile. In this method for constructing a superstructure above water, before the installation step, a plurality of divided members constituting the bottom plate are arranged in a circumferential direction of the through hole along the bottom surface of the precast concrete block. The partition members are arranged side by side, with an insertion hole provided in each partition member, and each partition member is supported so as to be able to slide and rotate along the bottom surface of the precast concrete block by supports whose upper parts are fixed to the bottom of the precast concrete block and inserted into the insertion hole.In the installation process, each partition member is positioned outward from the outer peripheral surface of the pile in a plan view, and the pile is loosely inserted into the through hole.In the blocking process, each partition member is slid toward the outer peripheral surface of the pile by working from above the precast concrete block, and the arc-shaped front end portion of each partition member is brought into contact with the outer peripheral surface of the pile, thereby blocking the gaps with the multiple partition members. Effect of the Invention

[0007] According to the present invention, before the installation step, a plurality of divided members each having an insertion hole are arranged in a line in the circumferential direction of the through hole of the precast concrete block, and each divided member is supported so as to be slidable and rotatable along the bottom surface of the precast concrete block by a support whose upper part is fixed to the bottom of the precast concrete block and inserted into the through hole of the divided member. Then, in the closing step, each divided member is slid toward the outer circumferential surface of the pile by an operation from above the precast concrete block, and the arc-shaped front end of each divided member is brought into contact with the outer circumferential surface of the pile. This makes it possible to close the gap between the outer circumferential surface of the pile and the inner circumferential surface of the lower part of the through hole with a plurality of divided members by an operation from above the precast concrete block, even if the center of the pile loosely inserted in the through hole of the precast concrete block is deviated from the center of the through hole. Therefore, the superstructure above water can be easily and efficiently constructed without performing an operation below the precast concrete block installed on the pile. [Brief description of the drawings]

[0008] [Figure 1] 1 is an explanatory diagram illustrating a side view of a superstructure constructed on top of a pile using the method for constructing a superstructure above water of the present invention. FIG. [Diagram 2] FIG. 2 is an explanatory diagram illustrating a cross-sectional view of the precast concrete blocks that make up the superstructure before they are installed on the piles. [Diagram 3] 3 is an explanatory diagram illustrating an enlarged example of the support in FIG. 2, where FIG. 2(a) shows a support supporting an upper divided member, and FIG. 2(b) shows a support supporting a lower divided member. [Figure 4] This is an explanatory diagram illustrating the precast concrete blocks that make up the superstructure in a plan view from above before they are installed on the piles. [Diagram 5] 5 is an explanatory diagram illustrating a cross-sectional view of the precast concrete block of FIG. 2 and FIG. 4 installed on a pile. FIG. [Figure 6]FIG. 6 is an explanatory diagram illustrating the precast concrete block of FIG. 5 in a plan view from above. [Figure 7] 6 is an explanatory diagram illustrating the precast concrete block of FIG. 5 as viewed from below. FIG. [Figure 8] FIG. 6 is an explanatory diagram illustrating, in cross section, the situation shown in FIG. 5 in which a split member has been used to seal the gap between the outer peripheral surface of the pile and the inner peripheral surface of the lower part of the through hole provided in the precast concrete block. [Figure 9] FIG. 9 is an explanatory diagram illustrating the precast concrete block of FIG. 8 in a plan view from above. [Figure 10] 9 is an explanatory diagram illustrating the precast concrete block of FIG. 8 as viewed from below. FIG. [Figure 11] FIG. 9 is an explanatory diagram illustrating, in cross section, the state in which the through-holes provided in the precast concrete block in the state shown in FIG. 8 have been filled with filler concrete and solidified. [Figure 12] This is an explanatory diagram illustrating, in cross section, the situation in which a dividing member arranged along the bottom surface of a precast concrete block installed on a pile is moved toward the outer peripheral surface of the pile using an extension member. [Figure 13] 13 is an explanatory diagram illustrating an enlarged example of the elongate member of FIG. 12. FIG. [Figure 14] 13 is an explanatory diagram illustrating, in cross section, the situation shown in FIG. 12 in which a split member has been used to seal the gap between the outer peripheral surface of the pile and the inner peripheral surface of the lower part of the through hole in the precast concrete block. FIG. [Figure 15] This is an explanatory diagram illustrating a plan view from above of a dividing member arranged along the bottom surface of a precast concrete block installed on a pile, before it is slid toward the outer peripheral surface of the pile using a fastening band. [Figure 16] 16 is an explanatory diagram illustrating an enlarged example of the fastening band of FIG. 15. [Figure 17] 16 is an explanatory diagram illustrating, in cross section, a state in which the divided member in FIG. 15 is slid toward the outer circumferential surface of the pile by using a fastening band. FIG. [Figure 18]This is an explanatory diagram showing, in a plan view from above, the situation shown in Figure 15, in which a dividing member has been used to seal the gap between the outer surface of the pile and the inner surface of the lower part of the through hole in a precast concrete block. [Figure 19] 19 is an explanatory diagram illustrating the situation in FIG. 18 in cross section. [Figure 20] This is an explanatory diagram illustrating a plan view from above of another embodiment of a dividing member arranged along the bottom surface of a precast concrete block installed on a pile, showing the situation before it is slid toward the outer peripheral surface of the pile. [Figure 21] This is an explanatory diagram showing, in cross section, the situation in which a dividing member arranged along the bottom surface of a precast concrete block installed on a pile is slid to the outer peripheral surface of the pile using an elastic member. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, a method for constructing a superstructure above water according to the present invention will be described based on an embodiment shown in the drawings.

[0010] As illustrated in Fig. 1, the present invention is a method for constructing a superstructure 1 on water, such as a pier, which is fixed to the top of piles 40 driven into the water bottom ground WB. Examples of piles 40 include steel pipe piles and concrete piles. In this embodiment, a case where a superstructure 1 is constructed which is fixed to the top of one pile 40 is illustrated, but the present invention can also construct a superstructure 1 which is fixed to the top of two or more piles 40. In this embodiment, a case where the top of the pile 40 protrudes above the water is illustrated, but there is also a case where the top of the pile 40 does not protrude above the water.

[0011] As illustrated in Figures 2 and 4, in the present invention, a superstructure 1 is constructed using precast concrete blocks 2 that have been fabricated in advance on land or on a ship. The precast concrete blocks 2 are made of precast concrete. The precast concrete blocks 2 may be of a reinforced concrete structure in which reinforcing bars are embedded in the precast concrete, or may be of a structure in which reinforcing bars are not embedded in the precast concrete. In this embodiment, the precast concrete blocks 2 are shaped like a rectangular parallelepiped, but the shape of the precast concrete blocks 2 is not limited to a rectangular parallelepiped shape and may be of other shapes.

[0012] The precast concrete block 2 has a through hole 3 that passes vertically through and into which a pile 40 can be loosely inserted. In this embodiment, the through hole 3 is formed in one place in the center of the precast concrete block 2. The precast concrete block 2 in this embodiment is configured to include a block body 4 made of precast concrete and having the through hole 3 formed therein, a sheath pipe 5 that is fitted into the through hole 3 and extends vertically, a beam member 6 that protrudes to the inside of the through hole 3 in a plan view, and a hanging metal fitting 7.

[0013] In this embodiment, a lower hole 3b that is circular in plan view is formed in the lower part of the block body 4 as the through hole 3, and an upper hole 3a that is rectangular in plan view and wider than the lower hole 3b is formed above the lower hole 3b. The upper hole 3a and the lower hole 3b communicate vertically. In this embodiment, a sheath pipe 5 that extends vertically is fitted into the lower hole 3b. The outer circumferential surface of the sheath pipe 5 is bonded to the precast concrete that constitutes the block body 4, so that the sheath pipe 5 is integrated with the block body 4.

[0014] The sheath pipe 5 can be provided optionally in the precast concrete block 2, and it is also possible to use a precast concrete block 2 that does not have a sheath pipe 5. In the present invention, when the precast concrete block 2 has the sheath pipe 5, the inner peripheral surface of the sheath pipe 5 is the inner peripheral surface of the lower part of the through hole 3, and when the precast concrete block 2 does not have the sheath pipe 5, the inner concrete surface of the through hole 3 is the inner peripheral surface of the lower part of the through hole 3.

[0015] The inner dimension of the lower part of the through hole 3 (in this embodiment, the inner dimension of the sheath pipe 5) is set to a dimension that allows the pile 40 to be loosely inserted. The inner dimension of the lower part of the through hole 3 is set to a dimension that, when the pile 40 is inserted into the through hole 3 with the center position of the through hole 3 and the center position of the pile 40 aligned in a plan view, a gap (clearance) of, for example, 5 cm to 20 cm, more preferably 10 cm to 15 cm, is formed between the inner peripheral surface of the lower part of the through hole 3 and the outer peripheral surface of the pile 40. The shape of the upper hole 3a is not limited to a square shape, and can be formed, for example, into a circular shape or an elliptical shape in a plan view. For example, the lower hole 3b and the upper hole 3a can be formed to have the same shape and the same size.

[0016] Steel frames such as H-shaped steel and channel steel are used for the beam members 6. The beam members 6 extend horizontally and protrude into the through hole 3 (sheath pipe 5) in plan view. At least a portion of the beam members 6 extends to the outside of the through hole 3 in plan view. As illustrated in FIG. 2, in this embodiment, a pair of beam members 6, 6 are arranged in parallel with a gap between them, and each beam member 6 spans across the through hole 3.

[0017] As exemplified in Fig. 4, the beam member 6 is disposed above the sheath pipe 5 or on top of the sheath pipe 5. The beam member 6 and the sheath pipe 5 are preferably joined by welding or the like. The portion of the beam member 6 located on the inside of the through hole 3 is exposed, and the portion of the beam member 6 located on the outside of the through hole 3 is embedded in the precast concrete that constitutes the block body 4. Note that the beam member 6 can be provided arbitrarily, and a precast concrete block 2 without the beam member 6 can also be used.

[0018] The upper part of the block body 4 is provided with multiple lifting fittings 7 that are used when hoisting the precast concrete block 2 with a crane or the like. In this embodiment, a lifting fitting 7 is provided at each of the four corners of the upper part of the block body 4. The lower part of the lifting fittings 7 is embedded in the precast concrete that constitutes the block body 4, and the lifting fittings 7 are integrated into the block body 4. Although not provided in this embodiment, if accessories such as mooring posts are to be provided to the superstructure 1, the accessories such as mooring posts can also be integrated into the precast concrete block 2 (block body 4).

[0019] In the method for constructing the superstructure 1 of the present invention, an installation step is performed in which the precast concrete block 2 is placed at a predetermined position with the pile 40 loosely inserted in the through hole 3 in the construction water area where the superstructure 1 is to be constructed, as illustrated in Figs. 5 to 7. Next, a closing step is performed in which the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3 of the precast concrete block 2 is closed with a bottom plate 9, as illustrated in Figs. 8 to 10. Thereafter, a casting step is performed in which the gap between the outer circumferential surface of the pile 40 and the inner circumferential surface of the through hole 3 of the precast concrete block 2 is filled with filler concrete 8 and hardened, as illustrated in Fig. 11, thereby fixing the superstructure 1 in which the precast concrete block 2 and the hardened filler concrete 8 are integrated to the top of the pile 40.

[0020] In the present invention, before the above-mentioned installation process is performed, on land or on a ship, a plurality of dividing members 10 constituting the bottom plate 9 are arranged in a line in the circumferential direction of the through hole 3 of the precast concrete block 2 along the bottom surface of the precast concrete block 2, as exemplified in Figs. 2 to 4. The dividing members 10 are plate-shaped members and are formed of, for example, metal, resin, wood, etc. The thickness of the dividing members 10 can be appropriately determined, but is, for example, about 5 mm to 20 mm. In this embodiment, six dividing members 10 are arranged for the through hole 3 of the precast concrete block 2. The number of dividing members 10 is not particularly limited as long as it is plural, and can be, for example, six or less, or more than six.

[0021] 3, in this embodiment, adjacent divided members 10 in the circumferential direction of the through hole 3 are alternately divided into an upper divided member 10A and a lower divided member 10B disposed below the upper divided member 10A. The front end portion 11 of each divided member 10 (10A, 10B) located toward the center of the through hole 3 is formed in an arc shape so as to abut against the outer circumferential surface of the pile 40 without any gaps. It is preferable to provide the front end portion 11 of the divided member 10 with an elastic material such as rubber or resin that enhances adhesion with the outer circumferential surface of the pile 40.

[0022] In this embodiment, a divided member 10 that is fan-shaped in plan view is exemplified, but the divided member 10 can have other shapes as long as it has an arc-shaped front end portion 11. An insertion hole 12 is provided in each divided member 10. In this embodiment, as the insertion hole 12, a long hole (slit) extending toward the center of the through hole 3 is provided in each divided member 10. More specifically, in this embodiment, a single linear, elongated hole is provided in the center of each divided member 10 in plan view.

[0023] Each partition member 10 is supported by a support 14 whose upper part 14a is fixed to the bottom of the precast concrete block 2 and inserted into the insertion hole 12, allowing it to slide and rotate along the bottom surface of the precast concrete block 2.

[0024] More specifically, as illustrated in FIG. 3(a), the support 14 provided on the upper partition member 10A has an upper portion 14a fixed to the bottom of the precast concrete block 2, a shaft portion 14b inserted through the insertion hole 12, and a support portion 14c that supports the partition member 10. As illustrated in FIG. 3(b), the support 14 provided on the lower partition member 10B further has a gap forming portion 14d between the upper portion 14a and the shaft portion 14b. The shaft portion 14b and the support portion 14c of the support 14 provided on the lower partition member 10B are disposed lower than the shaft portion 14b and the support portion 14c of the support 14 provided on the upper partition member 10A by the thickness of the upper partition member 10A.

[0025] The upper portion 14a of the support 14 is, for example, a metal bolt. The upper portion 14a of the support 14 is inserted into the bottom of the precast concrete block 2 after the precast concrete block 2 is produced. In this embodiment, the outer dimensions of the shaft portion 14b are set to be approximately the same as the width dimension of the long hole that is the insertion hole 12, and the long hole and the shaft portion 14b function as a guide when sliding the divided member 10 toward the outer circumferential surface of the pile 40. The support portion 14c protrudes outward from the shaft portion 14b, and the divided member 10 is placed on the support portion 14c. The gap forming portion 14d protrudes outward from the shaft portion 14b. The thickness of the gap forming portion 14d is set to be approximately the same as the thickness of the divided member 10A in the upper stage. The shaft portion 14b, the support portion 14c, and the gap forming portion 14d are formed of, for example, metal, resin, or the like.

[0026] The top surface of the upper partition member 10A and the bottom surface of the precast concrete block 2 are close to each other, with almost no gap between them. There is a gap approximately the same as the thickness of the upper partition member 10A between the top surface of the lower partition member 10B and the bottom surface of the precast concrete block 2. It is advisable to coat the top surface of the partition members 10 (especially the upper partition member 10A) with a friction-reducing material such as fluororesin to reduce friction between the partition member 10 and the bottom surface of the precast concrete block 2.

[0027] In the present invention, each of the dividing members 10 arranged on the precast concrete block 2 is slid along the bottom surface of the precast concrete block 2 by working from above the precast concrete block 2. In this embodiment, a rod-shaped member 16 extending upward is provided at the front of each dividing member 10 as a means for sliding the dividing members 10 along the bottom surface of the precast concrete block 2. An engaging device 17 that can engage with the upper end of a pile 40 is provided at the top of the rod-shaped member 16. In this embodiment, the fixed position of the engaging device 17 relative to the rod-shaped member 16 in the vertical direction can be changed.

[0028] The specific work procedures for the construction method of the superstructure 1 of the present invention will be described below.

[0029] 2 and 4, the precast concrete block 2 and the multiple divided members 10 having the above-mentioned configuration are prepared in advance on land or on a ship according to the size of the piles 40 that will construct the superstructure 1. Before the installation process, the multiple divided members 10 are arranged in a line in the circumferential direction of the through hole 3 along the bottom surface of the precast concrete block 2 on land or on a ship, and each divided member 10 is supported by supports 14 so that it can slide and rotate along the bottom surface of the precast concrete block 2. Then, the precast concrete block 2 with the multiple divided members 10 and supports 14 arranged thereon is transported to the construction waters where the piles 40 are driven.

[0030] In the construction water area, a partition plate 30 is provided at a position at a predetermined depth from the upper end of the pile 40 to separate the inside of the pile 40 into upper and lower parts. The outer dimensions of the partition plate 30 are set to be approximately the same as the inner dimensions of the pile 40. There are no particular limitations on the method of installing the partition plate 30 inside the pile 40, but for example, the partition plate 30 is fixed inside the pile 40 by supporting the partition plate 30 with a hanging material such as a wire suspended from the upper end of the pile 40.

[0031] Next, in the installation process, wire rope hoists suspended from a crane are connected to each of the hoisting fittings 7 provided on the precast concrete block 2, and the precast concrete block 2 is hoisted above the pile 40 by the crane. In a plan view, each of the divided members 10 is positioned outside the outer circumferential surface of the pile 40. In this embodiment, each of the rod-shaped members 16 and engaging members 17 is positioned near the inner circumferential surface of the through hole 3.

[0032] 5 to 7, with the through hole 3 provided in the precast concrete block 2 and the pile 40 aligned, the precast concrete block 2 is moved downward from above the pile 40, and the precast concrete block 2 is placed in a predetermined position with the pile 40 loosely inserted into the through hole 3 (sheath pipe 5). In this embodiment, the pile 40 is loosely inserted into the through hole 3 with the rod-shaped members 16 and the engaging members 17 inserted between the outer circumferential surface of the pile 40 and the inner circumferential surface of the through hole 3.

[0033] In this embodiment, the beam member 6 protruding inside the through hole 3 is placed on the upper end of the pile 40, so that the precast concrete block 2 is supported on the top of the pile 40. When the precast concrete block 2 is supported on the top of the pile 40, a worker can stand on the precast concrete block 2 and perform work.

[0034] Since the work of installing the precast concrete block 2 on the pile 40 is performed on water, it is difficult to install the precast concrete block 2 in a position where the center of the through hole 3 perfectly coincides with the center of the pile 40. Therefore, in many cases, the precast concrete block 2 is installed with the center of the pile 40 misaligned with the center of the through hole 3, as exemplified in Figures 5 to 7.

[0035] As illustrated in Figures 8 to 10, in the closing step, each divided member 10 is slid toward the outer circumferential surface of the pile 40 from above the precast concrete block 2, so that the arc-shaped front end portion 11 of each divided member 10 is brought into contact with the outer circumferential surface of the pile 40. Then, the plurality of divided members 10 closes the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3. Note that the portion of the beam member 6 located inside the through hole 3 is omitted in Figures 9 and 10.

[0036] More specifically, when the precast concrete block 2 is installed with the center of the pile 40 and the center of the through hole 3 misaligned, the arc-shaped front end 11 of each of the partition members 10 does not come into contact with the outer circumferential surface of the pile 40 without any gaps by simply moving each partition member 10 straight toward the center of the through hole 3 in the orientation in which it was arranged in the installation process. Therefore, in the present invention, each partition member 10 is supported by the support 14 so as to be slidable and rotatable along the bottom surface of the precast concrete block 2. In the present invention, when each partition member 10 is slidable toward the outer circumferential surface of the pile 40, the partition member 10 is rotated horizontally around the support 14 as the center of rotation to adjust the orientation of the partition member 10, so that the arc-shaped front end 11 of the partition member 10 can come into contact with the outer circumferential surface of the pile 40 without any gaps.

[0037] In this embodiment, a worker holds the upper part of the rod-shaped member 16 from above the precast concrete block 2 and moves the rod-shaped member 16 toward the outer circumferential surface of the pile 40, thereby sliding each of the partition members 10 toward the outer circumferential surface of the pile 40 and bringing the front end portion 11 of each partition member 10 into contact with the outer circumferential surface of the pile 40. Even if the precast concrete block 2 is installed with the center of the pile 40 and the center of the through hole 3 misaligned, the worker can operate the rod-shaped member 16 to adjust the orientation of the partition member 10, thereby bringing the arc-shaped front end portion 11 of the partition member 10 into contact with the outer circumferential surface of the pile 40 without any gaps.

[0038] Next, each of the rod-shaped members 16 is fixed to the pile 40, thereby fixing each of the divided members 10 to the pile 40. In this embodiment, the rod-shaped member 16 is fixed to the pile 40 by fixing the engaging tool 17 to the rod-shaped member 16 with the engaging tool 17 engaged with the upper end of the pile 40.

[0039] In this embodiment, when the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the through hole 3 is filled with multiple divided members 10, partial regions of adjacent divided members 10 in the circumferential direction of the through hole 3 are vertically overlapped. That is, partial regions of adjacent upper divided members 10A and lower divided members 10B are vertically overlapped.

[0040] In a state where the gap S between the outer peripheral surface of the pile 40 and the inner peripheral surface of the through hole 3 is blocked by the multiple divided members 10, the insertion holes 12 provided in each divided member 10 are positioned outside the inner peripheral surface of the through hole 3 (in this embodiment, the sheath pipe 5). In other words, the insertion holes 12 provided in each divided member 10 are formed in a range that is not positioned inside the inner peripheral surface of the through hole 3 in a state where the above-mentioned gap S is blocked by the multiple divided members 10.

[0041] Next, the gaps between the upper surface of each partition member 10 and the bottom surface of the precast concrete block 2 at the lower end of the through hole 3 are sealed with a sealant 15. The above-mentioned work can be performed from above the precast concrete block 2. If the gaps between the upper surface of each partition member 10 and the bottom surface of the precast concrete block 2 are small enough that the filling concrete 8 does not leak out, the above-mentioned work of sealing the gaps with the sealant 15 can be omitted.

[0042] Next, as illustrated in Figure 11, in the pouring process, filler concrete 8 is poured into the inside of the through hole 3 of the precast concrete block 2, so that the filler concrete 8 fills the gap S between the outer surface of the pile 40 and the inner surface of the through hole 3, the inside of the pile 40 above the partition plate 30, and the upper part of the through hole 3 (upper hole 3a).

[0043] In this embodiment, the filling concrete 8 is poured in two separate pours. In the first pour, a first filling concrete 8a is poured between the outer circumferential surface of the pile 40 and the inner circumferential surface of the through hole 3 onto the bottom plate 9 (dividable member 10) to a thickness of about 5 cm to 20 cm, and the first filling concrete 8a is allowed to solidify to form a thin concrete slab on the bottom plate 9. Thereafter, the remaining filling concrete 8 is poured so that the through hole 3 is filled. In FIG. 11, the area filled with the filling concrete 8 is indicated by hatching.

[0044] Thereafter, after a prescribed curing period has elapsed and the fill concrete 8 has solidified, the superstructure 1, consisting of the precast concrete block 2 and the solidified fill concrete 8 integrated together, is fixed to the top of the pile 40. In this embodiment, the rod-shaped members 16 and the engaging members 17 are embedded in the fill concrete 8. Each of the separate members 10 and the supports 14 may be left as part of the superstructure 1, or may be removed from the superstructure 1 after the fill concrete 8 has solidified. With this, the construction work of the superstructure 1 is completed.

[0045] In this way, in the present invention, before the installation step, a plurality of partition members 10 each having an insertion hole 12 are arranged in a line in the circumferential direction of the through hole 3 of the precast concrete block 2, and each partition member 10 is supported by the support 14 so as to be slidable and rotatable along the bottom surface of the precast concrete block 2. Then, in the closing step, each partition member 10 is slid toward the outer peripheral surface of the pile 40 by an operation from above the precast concrete block 2, and the arc-shaped front end portion 11 of each partition member 10 is brought into contact with the outer peripheral surface of the pile 40. When each partition member 10 is slid toward the outer peripheral surface of the pile 40, the support 14 is used as the center of rotation to rotate the partition member 10 to adjust the orientation of the partition member 10. Therefore, even if the center of the pile 40 loosely inserted in the through hole 3 of the precast concrete block 2 is deviated from the center of the through hole 3, the arc-shaped front end portion 11 of the partition member 10 can be brought into contact with the outer peripheral surface of the pile 40 without any gaps. Therefore, by working from above the precast concrete block 2, it is possible to seal the gap S between the outer surface of the pile 40 and the inner surface of the lower part of the through hole 3 with a plurality of separate members 10, making it possible to easily and efficiently construct the superstructure 1 above water without having to work below the precast concrete block 2 installed on the pile 40.

[0046] In this embodiment, by providing a beam member 6 that protrudes inward into the through hole 3 of the precast concrete block 2, the precast concrete block 2 can be easily and stably installed on the top of the pile 40 by placing the beam member 6 on the upper end of the pile 40, which is advantageous for improving construction efficiency.

[0047] As in this embodiment, when a long hole extending toward the center of the through hole 3 is provided as the insertion hole 12 in each divided member 10, the long hole functions as a guide when the divided member 10 is slid toward the outer circumferential surface of the pile 40, so that the trajectory along which the divided member 10 moves is stabilized. Therefore, the work of bringing the front end portion 11 of the divided member 10 into contact with the outer circumferential surface of the pile 40 can be performed more smoothly. Furthermore, when the width dimension of the long hole and the outer dimension of the shaft portion 14b of the support 14 are set to be substantially the same, the trajectory along which the divided member 10 moves is more stable, so that the work of bringing the front end portion 11 of the divided member 10 into contact with the outer circumferential surface of the pile 40 can be performed more easily.

[0048] Furthermore, as in this embodiment, by providing each partition 10 with a pair of long holes (insertion holes 12) and supports 14 and supporting the partition 10 so that it can rotate around the supports 14, it is possible to smoothly slide and rotate the partition 10 along the bottom surface of the precast concrete block 2, despite the extremely simple configuration. Also, since the partition 10 can be moved along one long hole and rotated around one support 14 as its center of rotation, the trajectory along which the partition 10 is moved and the center of rotation when the partition 10 is rotated are stable, making it even easier to bring the front end 11 of the partition 10 into contact with the outer circumferential surface of the pile 40.

[0049] In addition, the shape, size, and number of the insertion holes 12 provided in each partition member 10, and the shape and size of the supports 14 provided in each insertion hole 12, can be configured in various other ways as long as the partition members 10 can be supported in a state where they can slide and rotate along the bottom surface of the precast concrete block 2.

[0050] As in this embodiment, if the rod-shaped members 16 extending upward are provided at the front of each of the divided members 10 before the installation step, the rod-shaped members 16 are moved from above the precast concrete block 2 toward the outer circumferential surface of the pile 40 in the closing step, so that the work of sliding each of the divided members 10 toward the outer circumferential surface of the pile 40 can be performed very easily. Since the divided members 10 can be moved by the rod-shaped members 16 while visually checking the relative positional relationship between the outer circumferential surface of the pile 40 and the front end 11 of each of the divided members 10 from above the precast concrete block 2, the work of bringing the front end 11 of each of the divided members 10 into contact with the outer circumferential surface of the pile 40 can be performed very easily. Furthermore, by fixing each of the rod-shaped members 16 to the pile 40, each of the divided members 10 can be stably fixed to the pile 40. Furthermore, the load of the filling concrete 8 applied to the front of the divided members 10 can be stably supported by the rod-shaped members 16.

[0051] As in this embodiment, by providing the engaging device 17 that engages with the upper end of the pile 40 on the upper part of the rod-shaped member 16, the rod-shaped member 16 can be easily fixed to the pile 40 with few man-hours, which is advantageous for improving construction efficiency. In this embodiment, the engaging device 17 is configured so that the fixed position in the vertical direction with respect to the rod-shaped member 16 can be changed, but the engaging device 17 can have various other configurations as long as it is configured so that the rod-shaped member 16 can be fixed to the pile 40. For example, a rotatable engaging device 17 can be provided on the upper part of the rod-shaped member 16.

[0052] The rod-shaped member 16 can be fixed to the pile 40 by other methods, not limited to using the engaging device 17. For example, a magnet can be provided on the upper part of the rod-shaped member 16 and the magnet can be attached to the pile 40 to fix the rod-shaped member 16 to the pile 40. In addition, the rod-shaped member 16 can be fixed to the pile 40 by, for example, joining the outer circumferential surface of the rod-shaped member 16 to the pile 40 with an adhesive or welding, or by bending the upper part of the rod-shaped member 16 into a hook shape and hooking the hook-shaped part onto the upper part of the pile 40.

[0053] As in this embodiment, by alternately dividing the circumferentially adjacent divided members 10 into upper divided members 10A and lower divided members 10B, and using multiple divided members 10 to fill the gap S between the outer peripheral surface of the pile 40 and the inner peripheral surface of the lower part of the through hole 3, and by making partial areas of adjacent divided members 10A, 10B circumferentially of the through hole 3 overlap each other vertically, it is possible to more reliably prevent gaps from occurring between adjacent divided members 10.

[0054] In the present invention, for example, adjacent divided members 10 in the circumferential direction can be arranged at the same height, and the multiple divided members 10 can be used to fill the gap S between the outer peripheral surface of the pile 40 and the inner peripheral surface of the lower part of the through hole 3, while the side surfaces of adjacent divided members 10 in the circumferential direction of the through hole 3 are in tight contact with each other.

[0055] When pouring the filler concrete 8, the load of the filler concrete 8 is applied to the bottom plate 9 (dividing member 10). However, if the filler concrete 8 is poured in multiple steps as in this embodiment, and a thin concrete slab of about 5 cm to 20 cm is formed on the bottom plate 9 in the first pour, the thin concrete slab functions together with the bottom plate 9 as a bottom plate that supports the load of the filler concrete 8 poured thereafter. Therefore, the load on the bottom plate 9 can be reduced compared to when all the filler concrete 8 is poured in one pour. Accordingly, the dividing member 10 and the support 14 can be made lighter and more simple.

[0056] The work of bringing the front end 11 of each partition member 10 into contact with the outer peripheral surface of the pile 40 from above the precast concrete block 2 can also be performed, for example, by a method such as that shown in Figures 11 and 12.

[0057] As illustrated in Figures 12 to 14, in this embodiment, an elongated member 18 and a rotating member 19 are used instead of the rod-shaped member 16 and the engaging member 17 of the previous embodiment illustrated in Figures 1 to 11. The other configurations are the same as those of the previous embodiment illustrated in Figures 1 to 11.

[0058] As illustrated in FIG. 12 and FIG. 13, in this embodiment, for each partition member 10, an extension member 18 that can extend from the inner peripheral surface of the through hole 3 toward the center of the through hole 3 in a plan view is interposed between the inner peripheral surface of the through hole 3 and the engagement portion 13 at the front of the partition member 10. In this embodiment, the partition member 10 has an engagement portion 13 that protrudes upward at the front, and the front end portion 18a of the extension member 18 is pressed against the rear surface of the engagement portion 13, and the rear end portion 18b of the extension member 18 is pressed against the inner peripheral surface of the through hole 3. The extension member 18 is configured to be able to change its orientation in the lateral direction along the bottom surface of the precast concrete block 2. In this embodiment, the front end portion 18a and the rear end portion 18b of the extension member 18 are each made of an elastic material (e.g., rubber, resin, etc.), and the front end portion 18a and the rear end portion 18b of the extension member 18 are deformed, so that the extension member 18 can change its orientation in the lateral direction.

[0059] The extension member 18 in this embodiment is configured to have a cylindrical member with a telescopic structure. The extension member 18 may have any structure as long as it can extend its length in the longitudinal direction, and may have various other structures without being limited to a telescopic structure. In this embodiment, a fitting part that can rotate laterally is provided on the upper part of the extension member 18 as an extension mechanism 18c for extending the extension member 18. As illustrated in Figs. 12 and 13, a rod-shaped rotating tool 19 is inserted into the through hole 3 from above the precast concrete block 2, and the lower end of the rotating tool 19 is fitted into the fitting part described above. When the fitting part is rotated laterally by rotating the rotating tool 19 about its axis, the extension member 18 is extended toward the center of the through hole 3.

[0060] As illustrated in Figures 12 and 13, in the installation process, each extension member 18 (extension mechanism 18c) is shortened so that the front end portion 11 of each partition member 10 is positioned outside the outer peripheral surface of the pile 40, and the pile 40 is loosely inserted into the through hole 3 of the precast concrete block 2.

[0061] As illustrated in FIG. 14, in the closing step, each extension member 18 is extended to slide each divided member 10 toward the outer circumferential surface of the pile 40, and the front end portion 11 of each divided member 10 is brought into contact with the outer circumferential surface of the pile 40, thereby closing the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3 with the divided members 10. Then, each extension member 18 is stretched between the inner circumferential surface of the through hole 3 and the engagement portion 13 of the divided member 10, and the front end portion 11 of each divided member 10 is pressed against the outer circumferential surface of the pile 40, thereby fixing each divided member 10 to the pile 40. The subsequent steps are the same as those of the previous embodiment illustrated in FIG. 1 to FIG. 11.

[0062] To explain in more detail, in this embodiment, the extension member 18 is extended toward the outer peripheral surface of the pile 40, and until a portion of the front end portion 11 of the split member 10 contacts the outer peripheral surface of the pile 40, the split member 10 and the extension member 18 slide toward the outer peripheral surface of the pile 40 with little change in orientation from the orientation in which they were arranged during the installation process.

[0063] When the extension member 18 is further extended after a part of the front end 11 of the divided member 10 hits the outer peripheral surface of the pile 40, the divided member 10 and the extension member 18 naturally rotate laterally around the support 14 as the center of rotation so that the part of the front end 11 of the divided member 10 that is not in contact with the outer peripheral surface of the pile 40 fits into the outer peripheral surface of the pile 40, and the orientation of the divided member 10 and the extension member 18 naturally changes to the orientation in which the front end 11 of the divided member 10 abuts against the outer peripheral surface of the pile 40. Then, the part of the front end 11 of the divided member 10 that is not in contact with the outer peripheral surface of the pile 40 approaches further to the outer peripheral surface of the pile 40, and the front end 11 of the divided member 10 abuts against the outer peripheral surface of the pile 40. In this embodiment, the front end 18a and the rear end 18b of the extension member 18 formed of an elastic member are deformed, and the orientation of the extension member 18 changes according to the movement of the divided member 10.

[0064] When the extension members 18 are used as in this embodiment, in the closing step, the front end portions 11 of the respective segment members 10 can be brought into contact with the outer circumferential surface of the pile 40 simply by extending each extension member 18. Furthermore, the segment members 10 can be fixed to the pile 40 simply by tensioning the extension members 18 between the inner circumferential surface of the through hole 3 and the engagement portion 13. Therefore, the closing step can be completed with an extremely small number of work steps, which is advantageous for improving construction efficiency.

[0065] The method of extending the extension member 18 and the structure of the extension member 18 are not limited to the method using the rotating tool 19 of this embodiment, and various other configurations are possible. For example, a configuration in which a switch is provided on the upper part of the extension member 18 as the extension mechanism 18c, and the extension member 18 extends when a worker presses the switch using a rod-shaped member or the like from above the precast concrete block 2. Also, for example, a configuration in which the extension member 18 is extended by a remote control device is also possible.

[0066] In this embodiment, the front end 18a and the rear end 18b of the extension member 18 are respectively made of elastic members, but various other configurations can be used to change the orientation of the extension member 18 as long as the orientation of the extension member 18 can be changed in accordance with the movement of the divided member 10. For example, the front end 18a of the extension member 18 can be connected to the engagement portion 13 so as to be rotatable laterally, and the rear end 18b of the extension member 18 can be connected to the inner circumferential surface of the through hole 3 so as to be rotatable laterally.

[0067] The work of bringing the front end 11 of each separate member 10 into contact with the outer peripheral surface of the pile 40 from above the precast concrete block 2 can also be performed, for example, by a method such as that illustrated in Figures 15 to 19.

[0068] As illustrated in Figures 15 to 17, in this embodiment, a fastening band 20 and a rotating tool 19 are used instead of the rod-shaped member 16 and the engaging tool 17 of the previous embodiment illustrated in Figures 1 to 11. Also, in this embodiment, a divided member 10 having a different shape in a plan view from the divided member 10 of the embodiment illustrated in Figures 1 to 11 is used. The other configurations are the same as those of the previous embodiment illustrated in Figures 1 to 11.

[0069] As illustrated in Fig. 15, the split member 10 of this embodiment has a front portion that fills the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3 and a rear portion in which the insertion hole 12 is provided and a narrow portion that is relatively narrower than the front portion (wide portion). More specifically, the front portion of the split member 10 of this embodiment is formed in a fan shape in a plan view, and the rear portion is formed in a rectangular shape narrower than the front portion in a plan view. The width of the split member 10 here refers to the dimension in the direction perpendicular to the direction in which the split member 10 slides toward the center of the through hole 3 in a plan view (in other words, the extension direction of the insertion hole 12).

[0070] As in this embodiment, by forming the rear part of the partition member 10, where the insertion hole 12 is provided, as a narrow part that is relatively narrower than the front part that closes the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3, the weight of the partition member 10 can be reduced while maintaining its functionality. By reducing the weight of the partition member 10, the weight and simplification of the support 14 that supports the partition member 10 can also be achieved. In particular, by setting the width dimension of the narrow part of the partition member 10 to, for example, 2 to 30 times, more preferably 2.5 to 20 times, and even more preferably 3 to 7 times, the width dimension of the insertion hole 12, the weight of the partition member 10 can be reduced in a balanced manner while stably ensuring the strength of the rear part of the partition member 10 supported by the support 14.

[0071] As shown in FIG. 20, the divided member 10 having a narrow rear portion can also be, for example, a diamond-shaped divided member 10 having a fan-shaped front portion and a triangular rear portion tapering toward the rear.

[0072] 15 to 17, the fastening band 20 is configured to have a string-like or belt-like band portion 20a, and a fastening fitting 20b that fixes one end of the band portion 20a, which is annular in plan view, and a middle portion of the band portion 20a to maintain the band portion 20a in an annular shape. In this embodiment, the annular fastening band 20 extending in the circumferential direction of the through hole 3 is wound around the outside of the engaging portion 13 at the front of each divided member 10. In this embodiment, the engaging portion 13, which is arc-shaped in plan view and protrudes upward, is provided at the front of each divided member 10, and the fastening band 20 (band portion 20a) is wound around the arc-shaped outer circumferential surface of the engaging portion 13.

[0073] As illustrated in Figure 15, in this embodiment, in the installation process, the inner diameter of the fastening band 20 in a plan view is made larger than the outer diameter of the pile 40, and the front end portion 11 of each partition member 10 is positioned outside the outer peripheral surface of the pile 40, and the pile 40 is loosely inserted into the through hole 3 of the precast concrete block 2.

[0074] As illustrated in Figs. 17 to 19, in the closing step, the fastening band 20 (band portion 20a) is reduced in diameter toward the center of the pile 40, so that each divided member 10 is slid toward the outer circumferential surface of the pile 40, and the front end portion 11 of each divided member 10 is brought into contact with the outer circumferential surface of the pile 40, thereby closing the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower portion of the through-hole 3 with the divided members 10. Then, the engaging portion 13 of each divided member 10 is tightened to the outer circumferential surface of the pile 40 by the fastening band 20, so that each divided member 10 is fixed to the pile 40. The subsequent steps are the same as those of the previous embodiment illustrated in Figs. 1 to 11.

[0075] As illustrated in Figure 17, in this embodiment, a fitting portion that can rotate laterally is provided on the upper part of the fastening fitting 20b, and a rod-shaped rotating tool 19 is inserted into the through hole 3 from above the precast concrete block 2, and the lower end of the rotating tool 19 is fitted into the aforementioned fitting portion. When the rotating tool 19 is rotated around its axis to rotate the fitting portion, the position of the middle part of the band portion 20a fixed by the fastening fitting 20b moves, and the inner diameter of the annular fastening band 20 (band portion 20a) is reduced.

[0076] More specifically, in this embodiment, the fastening band 20 is contracted, and the divided member 10 slides toward the outer circumferential surface of the pile 40 without changing its orientation from the orientation in which it was arranged in the installation process, until a part of the front end 11 of the divided member 10 abuts on the outer circumferential surface of the pile 40. If the fastening band 20 is further contracted after a part of the front end 11 of the divided member 10 abuts on the outer circumferential surface of the pile 40, the divided member 10 naturally rotates laterally with the support 14 as the center of rotation so that the arc-shaped front end 11 of the divided member 10 fits into the outer circumferential surface of the pile 40, and the orientation of the divided member 10 naturally changes to a direction in which the front end 11 abuts on the outer circumferential surface of the pile 40. Then, the part of the front end 11 of the divided member 10 that is not in contact with the outer circumferential surface of the pile 40 approaches the outer circumferential surface of the pile 40 further, and the front end 11 of the divided member 10 abuts on the outer circumferential surface of the pile 40.

[0077] When the fastening band 20 is used as in this embodiment, in the closing step, the front end 11 of each divided member 10 can be brought into contact with the outer circumferential surface of the pile 40 simply by reducing the diameter of the fastening band 20. Since there is no need to move each divided member 10 individually, the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through-hole 3 can be closed with a very small number of work steps, which is very advantageous in improving construction efficiency.

[0078] The method of reducing the diameter of the fastening band 20 and the structure of the fastening fitting 20b are not limited to the method using the rotating tool 19 of this embodiment, and various other configurations are possible. For example, a switch may be provided on the upper part of the fastening fitting 20b, and when a worker uses a rod-shaped member or the like to press the switch from above the precast concrete block 2, the fastening band 20 (band portion 20a) is reduced in diameter. Also, for example, the fastening band 20 may be reduced in diameter by a remote control device.

[0079] The work of bringing the front end 11 of each partition member 10 into contact with the outer peripheral surface of the pile 40 from above the precast concrete block 2 can also be performed, for example, by a method as shown in Figure 21.

[0080] As shown in Fig. 21, in this embodiment, an elastic member 21 is used instead of the rod-shaped member 16 and the engaging device 17 of the previous embodiment shown in Figs. 1 to 11. Also, in this embodiment, a mount 22 that is installed on a pile 40 is used. The other configurations are the same as those of the previous embodiment shown in Figs. 1 to 11. Note that, although this embodiment shows an example in which the elastic member 21 and the mount 22 are used together, it is also possible to use only one of them.

[0081] The elastic member 21 is composed of a rod-like member or a plate-like member having elasticity formed of metal or resin. As illustrated in Fig. 21, in this embodiment, the tip of the elastic member 21 extending upward is pressed against the engagement portion 13 at the front end portion 11 of each divided member 10. In this embodiment, the front portion of each divided member 10 has the engagement portion 13 protruding upward, and the tip of the elastic member 21 is pressed against the outer peripheral surface of the engagement portion 13. The stand 22 extends outward from the outer peripheral surface of the pile 40 in a plan view, and is configured to be fixed to the pile 40.

[0082] When using the mount 22 as in this embodiment, the mount 22 is installed at a predetermined height on the pile 40 before the installation process is performed. The mount 22 is installed at a height such that the height position of the lower surface of the divided member 10 and the height position of the upper surface of the mount 22 coincide when the precast concrete block 2 is installed on the pile 40 in the installation process.

[0083] In the installation process, each elastic member 21 provided for each divided member 10 is inserted between the outer surface of the pile 40 and the inner surface of the through hole 3 of the precast concrete block 2, and the pile 40 is loosely inserted into the through hole 3.

[0084] In the closing step, the rear parts of the elastic members 21 are pushed downward from above the precast concrete block 2 to bring the middle parts of the elastic members 21 into contact with the inner circumferential surface of the through hole 3, and the lower parts of the elastic members 21 are curved from the inner circumferential surface of the through hole 3 toward the engagement parts 13 of the partition members 10, and each partition member 10 is slid toward the outer circumferential surface of the pile 40. Then, the front end parts 11 of each partition member 10 are brought into contact with the outer circumferential surface of the pile 40, and the gaps S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3 are closed by the multiple partition members 10. When the stand 22 is used as in this embodiment, the front parts of each partition member 10 are supported by the stand 22. Then, each elastic member 21 is fixed to the precast concrete block 2, thereby fixing each partition member 10 to the pile 40. The subsequent steps are the same as those of the previous embodiment illustrated in Figs. 1 to 11.

[0085] More specifically, in this embodiment, the rear part of the elastic member 21 is pushed downward, and the divided member 10 slides toward the outer circumferential surface of the pile 40 without changing its orientation from the orientation in which it is arranged in the installation process, until a part of the front end 11 of the divided member 10 comes into contact with the outer circumferential surface of the pile 40. When the rear end of the elastic member 21 is further pushed downward after a part of the front end 11 of the divided member 10 comes into contact with the outer circumferential surface of the pile 40, the divided member 10 naturally rotates horizontally with the support 14 as the rotation center so that the part of the front end 11 of the divided member 10 that is not in contact with the outer circumferential surface of the pile 40 fits into the outer circumferential surface of the pile 40, and the orientation of the divided member 10 naturally changes to a direction in which the front end 11 of the divided member 10 abuts against the outer circumferential surface of the pile 40. Then, the part of the front end 11 that is not in contact with the outer circumferential surface of the pile 40 approaches further closer to the outer circumferential surface of the pile 40, and the front end 11 of the divided member 10 abuts against the outer circumferential surface of the pile 40.

[0086] When using the elastic member 21 as in this embodiment, it is only necessary to press the tip of the elastic member 21 against the engagement portion 13 at the front of each separate member 10, which greatly reduces the number of steps and time required for preparation before carrying out the closing step. In the closing step, the front end 11 of the separate member 10 can be brought into contact with the outer circumferential surface of the pile 40 simply by pressing the rear part of the elastic member 21 downward from above the precast concrete block 2, so that the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface at the bottom of the through-hole 3 can be closed very easily.

[0087] As in this embodiment, by installing the mount 22 on the pile 40, the front part of each separate member 10 is supported by the mount 22, so that the separate members 10 can be fixed in a more stable state. In addition, since the load of the filling concrete 8 applied to the separate members 10 can be supported by the mount 22, the separate members 10 can be made lighter and simpler.

[0088] In the present invention, a method different from the embodiment exemplified above can be adopted as long as the front end 11 of each partition 10 can be brought into contact with the outer circumferential surface of the pile 40 by working from above the precast concrete block 2. Furthermore, the shape, number, arrangement, etc. of the partition members 10 are not limited to those in the embodiment exemplified above, and various other shapes can be adopted as long as the shape can close the gap S between the outer circumferential surface of the pile 40 and the inner circumferential surface of the lower part of the through hole 3 and can provide an insertion hole 12.

[0089] Furthermore, the shape and size of the superstructure 1 (precast concrete block 2) are not limited to the embodiment exemplified above, and various other configurations are possible. In this embodiment, the case where the superstructure 1 is fixed to one pile 40 is exemplified, but it is also possible to construct a superstructure 1 that extends across multiple piles 40 by, for example, producing a precast concrete block 2 having multiple through holes 3 and loosely inserting different piles 40 into each through hole 3. Also, for example, it is possible to construct a superstructure 1 that is L-shaped, polygonal, circular, or the like when viewed from above. [Explanation of symbols]

[0090] 1 Superstructure 2. Precast concrete blocks 3 Through holes 3a Upper hole 3b Lower hole 4 Block letters 5 Sheath tube 6 Beam members 7 Hanging hardware 8. Filling concrete 8a First filling concrete 9 Bottom plate 10 Partition 10A Upper division part 10B Lower division member 11 Front end 12 Insertion hole 13 Engagement part 14 Supports 14a Upper 14b Shaft 14c Support part 14d Gap forming part 15 Sealing materials 16 Rod-shaped member 17 Engagement tool 18 Extension member 18a Front end 18b Rear end 18c extension mechanism 19 Rotating Tool 20 Fastening band 20a Band section 20b Fastening hardware 21 Elastic member 22 Mounting stand 30 Partition 40 stakes S: Gap (between the outer surface of the pile and the inner surface of the bottom of the through hole) WB Underwater ground

Claims

1. A method for constructing a superstructure above water, in which a precast concrete block having a through hole penetrating vertically and into which a pile erected on the water bottom can be inserted is placed at a predetermined position with the pile loosely inserted into the through hole, a closing process for closing the gap between the outer circumferential surface of the pile and the inner circumferential surface of the lower part of the through hole with a bottom plate, and a casting process for filling the gap between the outer circumferential surface of the pile and the inner circumferential surface of the through hole and solidifying it, is carried out, Prior to carrying out the installation step, a plurality of divided members constituting the bottom plate are arranged in a line in a circumferential direction of the through hole along the bottom surface of the precast concrete block, an insertion hole is provided in each of the divided members, and each of the divided members is supported so as to be slidable and rotatable along the bottom surface of the precast concrete block by supports whose upper parts are fixed to the bottom surface of the precast concrete block and which are inserted into the insertion holes; In the installation step, the pile is loosely inserted into the through hole with each divided member being disposed outside the outer circumferential surface of the pile in a plan view, The method for constructing a superstructure above water is characterized in that in the blocking process, each of the divided members is slid toward the outer peripheral surface of the pile from above the precast concrete block, bringing the arc-shaped front end of each of the divided members into contact with the outer peripheral surface of the pile, thereby blocking the gap with a plurality of the divided members.

2. 2. A method for constructing a superstructure above water as described in claim 1, wherein each of the divided members is provided with a long hole extending toward the center of the through hole as the insertion hole.

3. A method for constructing a superstructure above water as described in claim 2, wherein each of the divided members is provided with a pair of the long hole and the support, so that the divided members are rotatably supported with the support as the center of rotation.

4. a rod-shaped member extending upward is provided at the front of each of the divided members, In the installation step, the pile is loosely inserted into the through hole with each rod-shaped member being inserted between the outer peripheral surface of the pile and the inner peripheral surface of the through hole, A method for constructing a superstructure above water as described in any of claims 1 to 3, wherein in the blocking process, each of the rod-shaped members is moved from above the precast concrete block toward the outer peripheral surface of the pile, thereby sliding each of the divided members toward the outer peripheral surface of the pile, and bringing the front end portions of each of the divided members into contact with the outer peripheral surface of the pile.

5. For each of the divided members, an extension member capable of extending from an inner peripheral surface of the through hole toward a center of the through hole in a plan view is interposed between the inner peripheral surface of the through hole and an engagement portion at a front portion of the divided member, In the installation step, the piles are loosely inserted into the through holes with the extension members contracted, A method for constructing a superstructure above water as described in any one of claims 1 to 3, wherein in the blocking process, each of the extension members is extended to slide each of the divided members toward the outer peripheral surface of the pile, thereby bringing the front end portion of each of the divided members into contact with the outer peripheral surface of the pile.

6. a ring-shaped fastening band extending in a circumferential direction of the through hole is wrapped around the outside of the engagement portion at the front of each of the divided members; In the installation process, the inner diameter of the fastening band in a plan view is made larger than the outer diameter of the pile, and the pile is loosely inserted into the through hole, A method for constructing a superstructure above water as described in any one of claims 1 to 3, wherein in the blocking process, the fastening band is reduced in diameter, thereby sliding each of the divided members toward the outer peripheral surface of the pile, and bringing the front end portion of each of the divided members into contact with the outer peripheral surface of the pile.

7. The tip end of the elastic member extending upward is pressed against the engagement portion at the front of each of the divided members, In the installation step, the elastic members are inserted between the outer peripheral surface of the pile and the inner peripheral surface of the through hole, and the pile is loosely inserted into the through hole, A method for constructing a superstructure above water as described in any of claims 1 to 3, wherein in the blocking process, the rear portions of each of the elastic members are pushed downward from above the precast concrete block to bring the middle portions of the elastic members into contact with the inner surface of the through hole, and the front portions of the elastic members are curved from the inner surface of the through hole toward the engagement portion, and each of the divided members is slid toward the outer surface of the pile to bring the front end portions of each of the divided members into contact with the outer surface of the pile.

8. The divided members adjacent to each other in the circumferential direction are alternately divided into an upper divided member and a lower divided member disposed below the upper divided member, A method for constructing a superstructure above water as described in any one of claims 1 to 3, wherein when the gaps are blocked by a plurality of the divided members, partial areas of the divided members adjacent in the circumferential direction are overlapped vertically.

9. Before performing the installation step, a stand extending outward from the outer circumferential surface of the pile in a plan view is installed at a predetermined height of the pile, A method for constructing a superstructure above water as described in any one of claims 1 to 3, in which, in the blocking process, the front end portion of each of the divided members is abutted against the outer peripheral surface of the pile, and the front portion of each of the divided members is supported on the mounting base.