Repair method for abandoned lateral connected to sewer main
The method addresses the complexity of repairing abandoned sewer pipes by using a packer device and inorganic stabilizer with a double-tube injection to seal and harden the pipe, ensuring effective soil and sewage prevention and easy removal, while maintaining corrosion resistance.
Patent Information
- Application Number
- JP2023065535
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-13
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2043-04-13
AI Technical Summary
Existing methods for repairing abandoned sewer pipes connected to a main sewer pipe are complicated by the need to temporarily close the proximal end of the pipe and may not efficiently prevent soil and sewage flow, especially under varying site conditions.
A method involving an electromagnetic survey using a television camera to identify the pipe's position and depth, followed by the installation of a packer device with expandable sections to block the pipe, filling with an inorganic suspended soil stabilizer, and applying a corrosion-resistant material to seal and harden the area, using a double-tube instant injection method for efficient sealing.
The method allows for accurate and efficient repair of abandoned sewer pipes, preventing soil and sewage flow, ensuring ground stability, and enabling easy removal of the stabilizer when needed, while maintaining corrosion resistance.
Smart Images

Figure 2024151813000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a technology for a method of repairing abandoned detached pipes connected to a sewer main pipe, which fills the internal space of the abandoned detached pipe that is buried while still connected to the sewer main pipe with a filler to prevent the ground from collapsing or soil from flowing into the sewer main pipe. [Background technology]
[0002] When existing houses are demolished and roads are widened, the connecting pipe that is pulled out through a sewage collection pit to allow sewage to flow down to the main sewer line may be left buried and behind.
[0003] FIG. 9 is an explanatory diagram showing a typical state of an installation pipe that has been left buried (referred to as an "abandoned installation pipe" in this specification). In the abandoned installation pipe 11, soil 8 has entered the internal space 14 from a poorly blocked area 13 at the tip end near the ground level of the underground 2 which was originally connected to a sewage collection basin, causing a cavity to form. This cavity has caused the ground to collapse, and when a large amount of rainwater or the like flows down the sewer main pipe 4, soil 8 inside the abandoned installation pipe 11 is taken in from the base end pipe mouth 12 and flows into the sewer main pipe 4, hindering the smooth flow of sewage.
[0004] In view of such past cases, the present inventor has already proposed a "repair method for abandoned installation pipes connected to the main sewer system" as an effective solution, as shown in Patent Document 1 below. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] Patent No. 4782757
[0006] That is, according to the technology disclosed in Patent Document 1, there are a situation grasping step of identifying the position of the abandoned attachment pipe and grasping the depth of the tip-side defective blockage portion located on the ground side of the abandoned attachment pipe, a gelling and blocking step of temporarily closing the base-end pipe opening of the abandoned attachment pipe and filling the pipe opening with a soil stabilizer to gel, a hardening waiting step of waiting for the soil stabilizer to gel, releasing the temporary closure and installing a filling formwork to wait for the soil stabilizer to harden, a filling formwork removal step of removing the filling formwork after hardening, and a cutting step of cutting the area around the base-end pipe opening and filling the soil stabilizer after removing the filling formwork. By going through a temporary finishing process in which the agent is partially removed, an injection formwork installation process in which an injection formwork is installed so as to block the pipe base end opening from the sewer main pipe side after the temporary finishing, a corrosion-resistant treatment process in which a corrosion-resistant injection material is injected through the injection formwork's injection opening and hardened, an injection formwork removal process in which the injection formwork is removed after hardening, and a finishing process in which the corrosion-resistant injection material after hardening is surface-treated, it is possible to carry out repairs that reliably prevent ground collapse and the inflow of soil and sand into the sewer main pipe side while flexibly responding to the on-site conditions of the abandoned installation pipe. Summary of the Invention [Problem to be solved by the invention]
[0007] Incidentally, the technology disclosed in Patent Document 1 can effectively repair abandoned casings, including their connection with the sewer main. However, the gelation blocking process requires the temporary closing of the base end of the abandoned casing, which is troublesome. Depending on the site conditions, it may be necessary to fill the abandoned casing with soil stabilizer from the base end of the abandoned casing, which is connected to the sewer main, while blocking the flow of sewage in the sewer main. In order to flexibly respond to such specific site conditions, there has been a demand for diversifying and enriching repair techniques by developing alternative methods that can reliably repair abandoned casings.
[0008] In view of the above-mentioned problems encountered with the technology disclosed in Patent Document 1, the present invention aims to provide a method for repairing an abandoned lateral pipe connected to a sewer main pipe, which can smoothly and efficiently repair an abandoned lateral pipe connected to a sewer main pipe while reliably stopping the sewage flowing down the sewer main pipe when filling a soil stabilizer into the abandoned lateral pipe. [Means for solving the problem]
[0009] The present invention has been made to achieve the above-mentioned object, and includes a situation assessment step of identifying the location of an abandoned faucet connected to a sewer main pipe via a base end pipe port and buried in the ground, and electromagnetically exploring the depth of a clogged portion located at the tip end of the abandoned faucet, using a television camera sent from the sewer main pipe side; and a method of detecting a clogged portion comprising: a cylinder having an outer diameter smaller than the inner diameter of the sewer main pipe; one side expansion / contraction section and another side expansion / contraction section arranged to be expandable and contractible on one side outer peripheral surface and the other side outer peripheral surface of the cylinder, the one side being divided into two, excluding the central outer peripheral surface; a packer device installation process for installing a packer device having an air supply hose for pressurizing air to the one side expansion / contraction portion and the other side expansion / contraction portion, and a first supply hose connected to the first outlet and a second supply hose connected to the second outlet, the central outer peripheral surface being positioned on the base end side pipe opening side of the left attachment pipe, and the one side expansion / contraction portion and the other side expansion / contraction portion being expanded so as to block the inside of the sewer main pipe; a gelling and filling step in which an inorganic suspension-type soil stabilizer is pressure-fed through the first supply hose and the second supply hose to the left side of the installation pipe and mixed while filling the inside of the left installation pipe from the base end side pipe opening in a viscous state and gelling the mixture; a packer device removal step in which, after the filled inorganic suspension-type soil stabilizer has gelled, the one side expansion and contraction section and the other side expansion and contraction section are contracted to remove the packer device; and a cutting step in which the surrounding area including the base end side pipe opening after the packer device is removed is cut and the hardened inorganic suspension-type soil stabilizer near the base end side pipe opening is removed. The most important feature of this method is that it includes at least a temporary finishing process in which a mechanical suspension-type soil stabilizer is partially removed, an injection formwork installation process in which an injection formwork is installed so as to block the surrounding area including the temporarily finished base end pipe opening from the sewer main pipe side, a corrosion-resistant treatment process in which a corrosion-resistant injection material is injected through an injection formwork port provided in the installed injection formwork and hardened, an injection formwork removal process in which the injection formwork is removed after the injected corrosion-resistant injection material has hardened, and a main finishing process in which surface treatment of the hardened corrosion-resistant injection material is performed.
[0010] In this case, the filling of the inorganic suspension type soil stabilizer in the gelling filling process is preferably carried out by a double-pipe instantaneous injection method using an ultrafine cement suspension pressure-fed through the first supply hose and an inorganic hardening accelerator solution pressure-fed through the second supply hose. Effect of the Invention
[0011] According to the invention of claim 1, after accurately grasping the condition of the internal space of an abandoned attachment pipe that is connected to a sewer main pipe and buried in the ground, and the poorly blocked areas (cavities) communicating with it, a viscous inorganic suspension-type soil stabilizer is pumped from the base end pipe opening to fill the internal space including the poorly blocked areas and the cavities communicating with them, and then rapidly harden it, thereby reliably preventing soil from flowing into the attachment pipe or the soil in the attachment pipe from being taken up and washed out when a large amount of rainwater, etc. flows down the sewer main pipe, thereby making it possible to carry out repair work smoothly and quickly, thereby preventing the ground from collapsing.
[0012] In addition, after being filled and hardened, the inorganic suspension-type soil stabilizer retains a relatively weak hardness, so it can be easily scraped out when it becomes necessary to remove it from the abandoned installation pipe.
[0013] In addition, by going through the packer device installation process inside the main sewer pipe, the sewage attempting to flow down can be stopped reliably, making it possible to smoothly and reliably repair abandoned attachment pipes connected to the main sewer pipe.
[0014] Furthermore, according to the invention of claim 2, the filling of the inorganic suspension-type soil stabilizer into the left-standing installation pipe can be carried out by a double-pipe instantaneous injection method using an ultrafine cement suspension pressure-fed through a first supply hose and an inorganic hardening accelerator solution pressure-fed through a second supply hose, making it possible to carry out the filling work more smoothly and reliably. [Brief description of the drawings]
[0015] [Figure 1]FIG. 4 is an explanatory diagram illustrating an example of a situation grasping process according to the present invention. [Diagram 2] FIG. 2 is an explanatory diagram showing a schematic diagram of an example of a packer device installation process according to the present invention. [Diagram 3] FIG. 1 is an explanatory diagram showing a specific example of the configuration of a packer device according to the present invention, in which (a) shows an example of the state before installation in a sewer main pipe, and (b) shows an example of the state after installation in a sewer main pipe. [Figure 4] FIG. 1 is an explanatory diagram showing a schematic example of the arrangement between an abandoned faucet pipe and a sewer main pipe after a packer device is installed. [Diagram 5] 1A and 1B are explanatory diagrams showing a schematic example of a provisional finishing step in the present invention, in which FIG. 1A shows an example of a state during provisional finishing, and FIG. 1B shows an example of a state after provisional finishing. [Figure 6] FIG. 1 is an explanatory diagram showing a schematic example of a corrosion-resistant treatment process in the present invention, in which (a) shows an example of the state during the corrosion-resistant treatment performed after the injection formwork installation process, and (b) shows an example of the state after the corrosion-resistant treatment. [Figure 7] FIG. 2 is an explanatory diagram showing a schematic example of a final finishing step in the present invention, in which (a) shows an example of a state during final finishing, and (b) shows an example of a state after final finishing. [Figure 8] FIG. 2 is an explanatory diagram showing an example of the state of an abandoned installation pipe after repair according to the present invention. [Figure 9] FIG. 1 is a schematic diagram showing an example of a conventional state of an installation pipe left buried DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] Figures 1 to 7 are explanatory diagrams showing schematic examples of main steps in each step of the present invention, and the whole process is made up of at least the situation assessment step shown in Figure 1, the packer device installation step shown in Figure 2, the gelling filling step shown in Figure 4, the temporary finishing step shown in Figure 5 which is carried out after the packer device is removed, the corrosion-resistant treatment step shown in Figure 6 which is carried out after the injection formwork is installed, and the main finishing step shown in Figure 7 which is carried out after the injection formwork is removed.
[0017] Of these steps, the situation assessment step shown in Figure 1 is carried out to identify the location of the abandoned installation pipe 11 that is still connected to the sewer main pipe 4 and buried in the ground 2, and to assess the situation inside the pipe, including the defective blockage area 13.
[0018] The situation grasping process will be described in detail here. First, as shown in FIG. 1, a first mobile robot 31 is sent from the ground 1 through a first manhole 3 into a sewer main pipe 4. The first mobile robot 31 is guided by a worker W in a first work vehicle 41 on the ground 1 for processing a TV camera. 1 The robot can move within the sewer main pipe 4 under travel control by the robot controller.
[0019] Worker W 1 The location of the installation pipes 5 which connect the sewer main pipe 5 and the manhole 6 and are currently in use or no longer in use, and the abandoned installation pipes 11 which have been left buried, is grasped by taking side-view photographs using the parent television camera 32 equipped with a light provided on the first mobile robot 31, and furthermore, a child television camera 33 equipped with a light is sent into the interior to grasp the internal situation in more detail, and at the same time, the situation is recorded on a recording medium such as a video tape in the first work vehicle 41.
[0020] In this case, the sub television camera 33, which is sent into the internal space 14 from the base end pipe port 12 of the abandoned attachment pipe 11, displays the obstruction defect portion 13 located at the tip end side as an image on the display 42 in the first work vehicle 41, thereby notifying the worker W of its existence. 1 The internal data obtained in this way as analog or digital data will be used as reference data for determining the amount and type of materials to be used, including inorganic suspension-type soil stabilizer28, and will also be used as preparation data for various required equipment.
[0021] At that time, worker W 1 The operator W on the ground 1 transmits electromagnetic waves E from the slave television camera 33 located at the blockage defect site 13 in the abandoned installation pipe 11 underground 2 toward the ground 1. 2uses a receiver 43 to receive the electromagnetic waves E emitted from the slave television camera unit 33 side, and identifies the position and depth of the obstruction defective portion 13 of the abandoned attachment pipe 11.
[0022] After the situation assessment process has been completed and the location of the abandoned attachment pipe 11 and the condition inside the pipe, including the defective blockage area 13, have been identified, and the first mobile robot 31 has been removed to the ground 1, the process proceeds to the packer device installation process shown in Figure 2.
[0023] As is clear from Figure 3(a), the packer device 21 used in the packer device installation process comprises a cylindrical body 22 of appropriate length with an outer diameter smaller than the inner diameter of the sewer main pipe 4 that is the subject of the current work, and one side expansion / contraction section 23 and other side expansion / contraction section 24 which are freely arranged to expand and contract using an elastic material such as rubber on one side outer peripheral surface 22b and the other side outer peripheral surface 22c which are divided in half excluding the central outer peripheral surface 22a of the cylindrical body 22, giving it an airtight structure, and wheels 21a are attached to two places on each the front and rear of the cylindrical body 22 to form the entire device.
[0024] In addition, an air supply hose 45 is connected to the one-side air supply port 23a of the one-side expansion / contraction section 23 and the other-side air supply port 24a of the other-side expansion / contraction section 24 as shown in FIG. 3, the air supply hose 45 being drawn from a second work vehicle 44 arranged on the ground 1 and performing necessary pressure-feeding plant processing and passing through a second manhole 7 as shown in FIG. 2. 3 In accordance with the above operation, compressed air can be supplied to the one-side expansion / contraction section 23 and the other-side expansion / contraction section 24.
[0025] Furthermore, a first outlet 25 and a second outlet 26 are provided on the central outer surface 22a of the cylinder 22 as shown in Figure 3, and the first outlet 25 is connected to the tip of a first supply hose 47 that is pulled out from the second work vehicle 44 side and passed through the second manhole 7 as shown in Figure 2, and the second outlet 26 is connected to the tip of a second supply hose 47 that is pulled out in a similar manner.
[0026] The packer device installation process, which is carried out using a packer device 21 having such a structure, involves sending the packer device 21, which has been deflated to shrink the one-side expansion / contraction section 23 and the other-side expansion / contraction section 24, into the second manhole 7 side, and then changing direction while being guided by the wheels 21a, so that it is sent into the sewer main pipe 4.
[0027] The packer device 21 sent into the sewer main pipe 4 is a worker W who guides the second mobile robot 34 sent into the sewer main pipe 4 from the third work vehicle 48 that performs appropriate TV camera processing via the first manhole 3 as shown in FIG. 4 By operating the fourth work vehicle 49 in FIG. 2, the fourth work vehicle 49 is used to perform the necessary high-pressure washing process.
[0028] After the packer device 21 in the sewer main pipe 4 is positioned as shown in Fig. 3(a), air is pumped through the air supply hose 45 to the one-side expansion / contraction section 23 and the other-side expansion / contraction section 24 to expand as shown in Fig. 3(b), and the packer device installation process is completed by bringing the packer device 21 into close contact with the inner circumferential surface 4a of the sewer main pipe 4 as shown in Fig. 4. In other words, the packer device 21 is installed with a space secured between its central outer circumferential surface 22c and the inner circumferential surface 4a of the sewer main pipe 4, and in communication only with the base end pipe opening 12 side of the abandoned attachment pipe 11.
[0029] After the packer device installation process, the process moves to the gelling filling process shown in Figure 4, in which an inorganic suspension-type soil stabilizer 28 having a specific gravity lighter than water (for example, Pacific Allofix MC-2, manufactured by Pacific Materials Co., Ltd.) is pressurized and sprayed simultaneously from the first nozzle 25 and the second nozzle 26 to the central outer surface 22a side of the packer device 21 via the first supply hose 46 and the second supply hose 47, thereby mixing and filling the abandoned attachment pipe 11 in a viscous state from the base end pipe mouth 12 of the abandoned attachment pipe 11 and gelling it.
[0030] That is, in the gelling and filling step, for example, an ultrafine cement suspension (for example, Pacific Materials Corporation's product name "Pacific Allofix MC") supplied from the first supply hose 46 and a solution of an inorganic hardening accelerator (for example, Pacific Materials Corporation's product name "Pacific Allofix SS") supplied from the second supply hose 47 are mixed and filled into the left attachment pipe 11 using, for example, a double-pipe instantaneous hardening injection method in which an outer pipe and an inner pipe of different diameters are concentrically combined to instantly gel and inject the mixture. Whether the inorganic suspension-type soil stabilizer 28 has been completely filled into the left attachment pipe 11 can be determined by a worker W in the second work vehicle 44 on the ground 1. 3 This can be confirmed reliably by checking the pressure state during filling.
[0031] After the inorganic suspension-type soil stabilizer 28 filled through the gelling filling process has been gelled, the process moves on to a packer device removal process (not shown) in which the one-side expansion / contraction section 23 and the other-side expansion / contraction section 24 are contracted by following the processing steps in the packer device installation process in reverse, and then the packer device 21 is removed from the second manhole 7.
[0032] After the packer device removal process, the process moves to the temporary finishing process shown in Figure 5, in which the surrounding area including the base-end pipe port 12 is cut and the hardened inorganic suspension-type soil stabilizer 28 near the base-end pipe port 12 is partially removed.
[0033] In the temporary finishing process, after the second traveling robot 34 has been withdrawn, a third traveling robot 35 as shown in Figure 5(a), which is also capable of being freely controlled to travel from the ground 1 side, is sent from the first manhole 3 to the sewer main pipe 4 side, and the cutting and polishing device 35a equipped on the third traveling robot 35 is operated to perform the necessary temporary finishing, including cutting the area around the base end pipe opening 12 and partially removing the inorganic suspension-type soil stabilizer 28 after gelling and filling near the base end pipe opening 12, and then the third traveling robot 35 is withdrawn, whereby the area around the base end pipe opening 12 can be prepared as shown in Figure 5(b) and the process can be completed.
[0034] After the temporary finishing process, the process proceeds to an injection form installation process in which an injection form 37 is installed so as to block the surrounding area including the base end pipe opening 12 from the sewer main pipe 4 side.
[0035] In the injection form installation process, the fourth traveling robot 36 shown in Figure 6(a) is made to hold the injection form 37 and the fixing band 38 and is sent in from the sewer main pipe 4 side, and the injection form 37 is pressed against the base end pipe mouth 12 side of the abandoned attachment pipe 11 by the fixing band 38 via the fourth traveling robot 36, thereby completing the process.
[0036] After the injection mold setting step, the process proceeds to a corrosion-resistant treatment step shown in FIG. 6 in which a corrosion-resistant injection material 39 is injected through an injection port 37a of the injection mold 37 and hardened.
[0037] In the corrosion-resistant treatment step, as shown in Fig. 6(a), an injection nozzle 36a of a fourth traveling robot 36 is inserted into an injection port 37a of an injection form 37 to inject a corrosion-resistant injection material 39, and the treatment is completed in the state shown in Fig. 6(b). In this case, an epoxy resin having excellent corrosion resistance and chemical resistance can be suitably used as the corrosion-resistant injection material 39.
[0038] After the corrosion-resistant treatment process, the process proceeds to a casting form removal process (not shown) in which the casting form 37 is removed after the injected corrosion-resistant casting material 39 has hardened.
[0039] In the injection form removal process, the fourth traveling robot 36 shown in Figure 6(a) with the injection nozzle 36a pulled out from the injection port 37a of the injection form 37 is moved to the side and the hardening is awaited, and then the fourth traveling robot 36 is used again to remove and recover the fixing band 38 and the injection form 37, thereby completing the process.
[0040] After the step of removing the injection mold, the process proceeds to a main finishing step shown in FIG. 7 in which the surface of the hardened corrosion-resistant injection material 39 is treated.
[0041] In this finishing process, after the fourth traveling robot 36 has been removed, the third traveling robot 35 is sent in again from the sewer main pipe 4 side as shown in Figure 7(a), and the cutting and polishing device 35a equipped on the third traveling robot 35 is operated to remove the injection formwork 37 and perform a surface polishing process on the hardened corrosion-resistant injection material 39 around the base-end pipe opening 12, thereby completing the process.
[0042] By completing all the steps in this manner, the abandoned attachment pipe 11 has the internal space 14 leading to the poorly plugged area 13 and the hollow portion 15 communicating with the internal space 14 filled with inorganic suspension-type soil stabilizer 28, as shown in Figure 8, and the surface around the base end pipe opening 12 (the side facing the main sewer pipe 4) is also covered with hardened corrosion-resistant grout 39, completing the repair process.
[0043] Therefore, according to the present invention, the condition of the internal space 14 of the abandoned attachment pipe 11, which is connected to the sewer main pipe 4 and buried in the soil 2, and the poorly blocked area 13 (hollow portion 15) communicating with it are accurately grasped, and then a viscous inorganic suspension-type soil stabilizer 28 is pumped from the base end pipe opening 12 to fill the internal space 14 including the poorly blocked area 13 and the hollow portion 15 communicating with it, and rapidly harden it, thereby reliably preventing soil 7 from flowing into the attachment pipe 11 as shown in Figure 9, or the soil 7 in the abandoned attachment pipe 11 from being taken up and flowed out when a large amount of rainwater, etc. flows down the sewer main pipe 4, thereby making it possible to carry out repair work smoothly and in a short time, which prevents the ground from collapsing.
[0044] In addition, since the inorganic suspension-type soil stabilizer 28 after being filled into the abandoned attachment pipe 11 and hardened retains a relatively weak hardness, when it becomes necessary to remove it from the abandoned attachment pipe 11, it can be easily scraped out.
[0045] Furthermore, since the inside of the sewer main pipe 4 can be sealed by the packer device 21 installed through the packer device installation process, the sewage attempting to flow down the sewer main pipe 4 can be reliably stopped, and repairs to the abandoned attachment pipe 11 connected to the sewer main pipe 4 can be carried out smoothly and reliably.
[0046] Furthermore, the area around the base end pipe port 12 of the abandoned attachment pipe 11 can be covered with hardened corrosion-resistant grout 39 as shown in Figure 8, so that even if a liquid with a strong acidic or alkaline component flows down through the sewer main pipe 4, the inorganic suspension-type soil stabilizer 28 around the base end pipe port 12 of the abandoned attachment pipe 11 can be reliably prevented from corroding, thereby increasing its durability.
[0047] Furthermore, when the inorganic suspension type soil stabilizer 28 is filled into the standing attachment pipe 11 by a double-pipe instantaneous injection method using an ultrafine cement suspension pressure-fed through the first supply hose 46 and an inorganic hardening accelerator solution pressure-fed through the second supply hose 47, the inorganic suspension type soil stabilizer 28 can be filled while being instantly gelled, making it possible to carry out the filling operation more smoothly and reliably.
[0048] The above has been explained using an example in which the method of the present invention is carried out using the first running robot 31, the second running robot 34, the third running robot 35 and the fourth running robot 36, but it can also be carried out manually instead of using these running robots. [Explanation of symbols]
[0049] 1 above ground 2 In the soil 3. No. 1 Manhole 4 Sewer Main 5. Installation pipe in use 6 Squares 7. Second Manhole 8. Soil 11 Abandoned installation pipe 12 Base end pipe port 13 Poorly occluded area 14 Interior Space 15 Cavity 21 Packer equipment 21a wheels 22 Cylinder 22a Center outer circumferential surface 22b One side outer circumferential surface 22c Other side outer circumferential surface 23 One-sided expansion and contraction section 23a One side air supply port 24 Other side expansion / contraction part 24a Other side air supply port 25 1st spout 26 2nd spout 28 Non-suspension type soil stabilizer 31 First Running Robot 32 Parent Camera 33 Child Camera 34 Second Running Robot 35 Third Running Robot 35a Cutting and polishing equipment 36 4th Running Robot 36a Injection nozzle 37 Injection formwork 37a Inlet 38 Fixing band 39 Corrosion-resistant injection material 41 First work vehicle 42 Display 43 Receiver 44 No. 2 Work Vehicle 45 Air supply hose 46 First supply hose 47 Second supply hose 48 Third Work Vehicle 49 No. 4 Work Vehicle E electromagnetic waves W 1 ,W 2 ,W 3 ,W 4 Operator
Claims
1. a situation assessment step in which the location of the abandoned tubular pipe buried in the ground while connected to the sewer main pipe via a base end pipe port is identified and an electromagnetic survey is performed to determine the depth of the clogged portion located at the tip end of the abandoned tubular pipe using a television camera sent from the sewer main pipe side; a packer device installation process for installing a packer device comprising a cylinder having an outer diameter smaller than the inner diameter of the sewer main pipe, one-side expansion / contraction portion and other-side expansion / contraction portion arranged to be expandable and contractible on one side outer surface and the other side outer surface of the cylinder, the one side outer surface being divided into two halves except for the central outer surface, an air supply hose for pressurizing air to the one-side expansion / contraction portion and the other side expansion / contraction portion, and a first supply hose connected to the first outlet and a second supply hose connected to the second outlet, the central outer surface being positioned on the base end pipe opening side of the left attachment pipe, and the one-side expansion / contraction portion and the other side expansion / contraction portion being expanded so as to block the inside of the sewer main pipe; a gelling and filling process in which an inorganic suspension-type soil stabilizer is pressure-fed to the central outer peripheral surface side of the packer device after installation via the first supply hose and the second supply hose, and mixed while filling the abandoned attachment pipe in a viscous state from the base end pipe port of the abandoned attachment pipe to gel it; A packer device removal process in which the one-side expansion / contraction section and the other-side expansion / contraction section are contracted after the filled inorganic suspension-type soil stabilizer has gelled, and the packer device is removed; A temporary finishing process for cutting the surrounding area including the base end pipe mouth after removing the packer device and partially removing the hardened inorganic suspension-type soil stabilizer near the base end pipe mouth; an injection form installation process in which an injection form is installed so as to close a peripheral area including the provisionally finished base end side pipe opening from the sewer main pipe side; A corrosion-resistant treatment process in which a corrosion-resistant injection material is injected through an injection port provided in the installed injection form and hardened; a step of removing the injection mold after the injected corrosion-resistant injection material has hardened; a final finishing step of performing a surface treatment on the hardened corrosion-resistant injection material; A method for repairing an abandoned lateral pipe connected to a sewer pipe, comprising at least the steps of:
2. 2. A method for repairing an abandoned installation pipe connected to a sewer pipe as described in claim 1, wherein the filling of the inorganic suspension-type soil stabilizer in the gelling filling process is carried out by a double-pipe instantaneous injection technique using an ultrafine cement suspension pressure-fed through the first supply hose and an inorganic hardening accelerator solution pressure-fed through the second supply hose.