Signal system
The signal system automatically deploys and retracts safety devices to address platform-vehicle gaps and height differences, enhancing safety by coordinating door operations and eliminating the need for manual intervention.
Patent Information
- Application Number
- JP2023070288
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-21
- Publication Date
- 2024-10-31
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing systems fail to automatically install slope devices to address gaps and height differences between platforms and vehicles, relying on station staff or crew members for deployment.
A signal system integrating a traffic control device, on-board device, and equipment control device to automatically deploy and retract fall prevention safety devices like ramps, coordinating door openings and closings to manage these differences.
Enables safe and automatic installation of slope devices without manual intervention, preventing accidents by ensuring proper deployment and retraction of safety measures.
Smart Images

Figure 2024155511000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to signaling systems. [Background technology]
[0002] Conventionally, when a train enters a platform, stops, and passengers board and disembark, there is a gap or difference in height between the platform and the train. In such cases, the gap or difference in height can cause accidents due to passengers tripping, or wheelchair users have difficulty boarding and disembarking. For this reason, ramps are installed between the platform and the train so that passengers can move around safely even if there is a gap or difference in elevation between the platform and the train.
[0003] For example, Patent Document 1 discloses a technology in which "a railway vehicle entrance / exit crossing plate device 1 is provided on the lower outside of the boarding / exit sliding door 3 of the car body 2, and spans a slope plate 5 between the boarding / exit 2a and the platform PH, and is equipped with a slope plate 5 rotatably attached to a hoisting shaft 4, a hoisting rack 6 connected to the lower part of the boarding / exit sliding door 3, and an interlocking gear mechanism 7 which has a passive pinion 11 that screws into the hoisting rack 6 and can lower the slope plate 5 via the hoisting shaft 4."
[0004] Furthermore, Patent Document 2 discloses a technology in which "a wheelchair ramp device 2 for railway vehicles that enables boarding and disembarking of wheelchairs comprises a boarding plate 10 that enables wheelchairs to travel, an in-vehicle / out-of-vehicle moving support mechanism 20 that supports the boarding plate 10 so that it can be moved between an extended position extending across the station platform 3 and the vehicle floor 4 and an intermediate position where it is retracted onto the vehicle floor 4, and an in-vehicle moving support mechanism 30 that supports the boarding plate 10 so that it can be moved between this intermediate position and a storage position provided to the side of the boarding and disembarking entrance 1."
[0005] Furthermore, Patent Document 3 discloses a technology in which "a vertical axis rotating frame 5 that rotates around a vertical axis Y is provided on a wall surface 3 inside the vehicle cabin near the side entrance 2. A rotation drive means 31 for the vertical axis rotating frame 5 is provided. A horizontal pin 10 rotatably connects the lower part of the vertical axis rotating frame 5 to the base of one of the side frames of the step 9, so that the step 9 can be raised, lowered and turned around the horizontal pin 10. The vertical axis rotating frame 5 is provided with a tipping prevention mechanism B that holds the step 9 in an upright position or releases this, and a drive means 32 that drives the tipping prevention mechanism B. On the opposite side of the vertical axis rotating frame 5 across the side entrance 2, a step raising / lowering mechanism E is provided that engages with the other side frame of the step 9 and raises, lowers and turns the step 9 by the drive means, and that releases this engagement by the drive means." [Prior art documents] [Patent documents]
[0006] [Patent Document 1] JP 2014-156239 A [Patent Document 2] JP 2005-319886 A [Patent Document 3] JP 2002-255029 A Summary of the Invention [Problem to be solved by the invention]
[0007] However, while the inventions described in Patent Documents 1 to 3 can eliminate problems caused by gaps and differences in elevation between the platform and the vehicle, they are based on the premise that the slope device for filling the gaps and differences in elevation between the platform and the vehicle will be deployed and stored by station staff or crew members. For this reason, no consideration has been given to automatically setting up a slope device at an appropriate time.
[0008] Therefore, the present invention aims to provide a technology that can automatically install a slope device that eliminates problems caused by gaps or differences in height between the platform and the vehicle, without the need for operation by station staff, etc., by performing mutual signal processing between the operation management device, on-board equipment, and facility control device. [Means for solving the problem]
[0009] In order to solve the above problems, one representative signaling system of the present invention is a signaling system including an operation management device, a station equipment control device, and a train's on-board equipment, the operation management device being connected to the equipment control device and the on-board equipment and transmitting information on the opening and closing of the train's on-board doors and information on the opening and closing of the station's platform doors to the on-board equipment and the equipment control device. In addition, the equipment control device is connected to the operation management device and the platform doors and controls the opening and closing of the platform doors, and the on-board device is connected to the operation management device, the on-board doors, and the fall prevention safety device and controls the deployment and storage of the fall prevention safety device and the opening and closing of the on-board doors. Furthermore, the operation management device receives train stop information (first information) of the train from the on-board equipment and then transmits it to the equipment control device, receives fall prevention safety device deployment instruction information (second information) of the fall prevention safety device from the equipment control device and then transmits it to the on-board equipment, and receives on-board door open instruction information (third information) of the on-board doors from the equipment control device and then transmits it to the on-board equipment. Then, after receiving the first information from the operations management device, the equipment control device transmits the second information to the operations management device, and after transmitting the second information, transmits the third information to the operations management device, and the on-board device transmits the first information to the operations management device, and after transmitting the first information to the operations management device, deploys the fall prevention safety device based on the second information received from the operations management device, and opens the on-board doors based on the third information received from the operations management device. Effect of the Invention
[0010] According to the present invention, it is possible to provide a technology that can automatically install a slope device that eliminates problems caused by gaps or differences in elevation between the platform and the vehicle, without the need for operation by station staff, etc., by performing mutual signal processing between the operation management device, on-board equipment, and equipment control device. Problems, configurations and effects other than those described above will become apparent from the following description of the preferred embodiment of the invention. [Brief description of the drawings]
[0011] [Figure 1] FIG. 1 is a diagram illustrating an example of the configuration of a signaling system according to an embodiment. [Diagram 2] FIG. 2 is a sequence diagram showing the transition of the control timing of the fall prevention safety device. [Diagram 3] FIG. 3 is a flowchart showing a specific example of the deployment control process of the fall prevention safety device. [Figure 4] FIG. 4 is a flowchart showing a specific example of a storage control process for a fall-prevention safety device. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. Note that the present invention is not limited to the embodiment. In addition, in the description of the drawings, the same parts are denoted by the same reference numerals. When there are multiple components having the same or similar functions, they may be described by using the same reference numerals with different subscripts, or when there is no need to distinguish between these multiple components, the subscripts may be omitted. In order to facilitate understanding of the invention, the position, size, shape, range, etc. of each component shown in the drawings may not represent the actual position, size, shape, range, etc. Therefore, the present invention is not necessarily limited to the position, size, shape, range, etc. disclosed in the drawings.
[0013] [Embodiment] First, a signaling system 1 according to an embodiment will be described with reference to FIG. FIG. 1 is a diagram showing an example of the configuration of a signaling system 1 according to an embodiment. Signaling system 1 is a system that safely deploys or stores fall prevention safety devices such as ramp devices installed between the train and the station platform in coordination with the opening and closing of the onboard doors of trains stopped at the station platform and the opening and closing of the platform doors installed on the station platform. The signaling system 1 mainly includes a traffic management device 100, an on-board device 120, and an equipment control device 140. The traffic management device 100 is connected to the on-board device 120 and the equipment control device 140 via a general-purpose LAN 110. The on-board device 120 is a device for controlling the opening and closing of on-board doors 130 installed on trains and the deployment and storage of fall prevention safety devices 190, and is connected to the traffic management device 100 via the general-purpose LAN 110. Furthermore, the equipment control device 140 can control the opening and closing of platform doors 150 installed on station platforms, and is connected to the traffic management device 100.
[0014] <Operation management device> The traffic management device 100 is a device that grasps train information and the operational status of trains running on a target line, and is generally installed in a central control room. In this embodiment, the traffic management device 100 relays telegram signals communicated between the on-board device 120 and the facility control device 140. In addition, the traffic management device 100 is connected to an on-board device 120 and a facility control device 140 located at remote locations via a general-purpose LAN 110 . In addition, the operation management device 100 communicates opening / closing information of the train's on-board doors 130 and opening / closing information of the station's platform doors 150 between the on-board equipment 120 and the equipment control device 140 using telegram signals, and controls the on-board equipment 120 and the equipment control device 140 to work together and operate appropriately.
[0015] Specifically, the traffic management device 100 receives, from the on-board device 120, first information notifying that the train has stopped, and then transmits the first information to the equipment control device 140. In addition, after receiving second information instructing the opening of the on-board doors 130 of the train from the equipment control device 140, the second information is transmitted to the on-board device 120. Furthermore, after receiving third information instructing the deployment of the fall prevention safety device 190 from the equipment control device 140, it transmits this to the on-board device 120.
[0016] <On-vehicle equipment> The on-board device 120 is mounted on the train and controls the operation of the train based on control commands from the central control room, thereby realizing functional safety. In this embodiment, the on-board device 120 is connected to the on-board door 130 and the fall prevention safety device 190, and controls the deployment and storage of the fall prevention safety device 190 and the opening and closing of the on-board door 130. The on-board equipment 120 is connected to the traffic management device 100 via the general-purpose LAN 110, and receives equipment control information transmitted by the equipment control device 140 via the traffic management device 100. In addition, the on-board equipment 120 transmits information regarding the fall prevention safety device 190 and the on-board door 130 to the equipment control device 140 via the traffic management device 100.
[0017] <Equipment control device> The equipment control device 140 is a device for controlling station equipment that is installed at each station. In this embodiment, the equipment control device 140 is connected to the platform doors 150 and controls the opening and closing of the platform doors 150. The equipment control device 140 is connected to the traffic management device 100 via the general-purpose LAN 110, and receives information on the fall prevention safety device 190 and the on-board door 130 transmitted by the on-board device 120 via the traffic management device 100. In addition, the equipment control device 140 transmits equipment control information to the on-board device 120 via the traffic management device 100.
[0018] <General-purpose LAN> The general-purpose LAN 110 is made up of a plurality of base stations, and is a network that connects the traffic management device 100, the on-board device 120, and the facility control device 140 so that they can communicate with each other. The general-purpose LAN 110 is, for example, an Ethernet, but other communication means may be used as long as they are capable of transmitting and receiving information to each other. For example, it may be a public network, or a network that communicates with a public network.
[0019] <Vehicle door> The on-board door 130 is a door for each car of the train, and is a door with a movable opening that can be opened and closed and is installed at the entrance and exit used by passengers to board and disembark the train. The on-board door 130 is connected to the on-board equipment 120 and opens and closes based on control commands from the on-board equipment 120.
[0020] <Platform doors> The platform door 150 is installed on station platforms and is a partition with a movable opening that can be opened and closed and is installed on the part facing the tracks for the purpose of preventing people from falling off the platform or being hit by trains. The platform doors 150 are connected to the equipment control device 140 and open and close based on control commands from the equipment control device 140.
[0021] <Safety device for fall prevention> The fall prevention safety device 190 eliminates the gap and height difference between the platform and the vehicle, This is a device such as a ramp that can be deployed and stored, which is installed on the outside of the vehicle, that is, on the platform side when viewed from the on-board door 130, for the purpose of allowing passengers to move around safely. For this reason, the fall prevention safety device 190 is connected to the on-board equipment 120 and is deployed and stored based on a control command from the on-board equipment 120.
[0022] <Control of fall prevention safety devices> Next, the control of the fall prevention safety device 190 will be described with reference to FIG. FIG. 2 is a sequence diagram showing the transition of the control timing of the fall prevention safety device 190. As shown in FIG. In Figure 2, time passes from left to right, and the control timing is different for each direction. In FIG. 2, only the main electronic message signals necessary for explaining the types of electronic message signals described in the embodiment are shown, and other electronic message signals are omitted.
[0023] The transition of the control timing of the fall prevention safety device 190 shown in Fig. 2 is roughly divided into three stages: the control timing before the train stops at the station platform (region 231), the control timing during the period when the train is stopped at the station platform (region 232), and the control timing after the train departs from the station platform (region 233). At the control timings shown in area 231 and area 233, the train is moving, so the on-board doors 130, platform doors 150 and fall prevention safety devices 190 are all closed and fixed in their stored positions.
[0024] Next, the three vertical regions in Fig. 2 describe the operation of each device. Region 241 shows the control timing of the process mainly performed by the traffic management device 100. Similarly, region 242 shows the control timing of the process mainly performed by the equipment control device 140, and region 243 shows the control timing of the process mainly performed by the on-board device 120.
[0025] The following describes the generation of telegram signals and the continuation of their statuses while a train is stopped at the platform (area 232). In addition, the processing in Figure 2 will be explained under the assumption that after the fall prevention safety device 190 is deployed, the platform door 150 is opened and then the on-board door 130 is opened.
[0026] (Status S201) First, the generation of telegram signals and the continuation of status during the period when a train is stopped within the platform (area 232) starts from the stage when the on-board equipment transmits train stop information. Status S201 is a status in which the on-board equipment 120 transmits “(1) train stop information (first information)” to the traffic management device 100. During the period when the train is stopped at the station platform (area 232), except in the cases of (9) platform doors closed 209 and (10) on-board doors closed, a telegram signal indicating the status is repeatedly transmitted, for example, every second to indicate the continuation of the status.
[0027] (Status S202) Status S202 is a status in which the traffic management device 100 receives “(2) Train stop information (first information)” from the on-board device 120.
[0028] (Status S203) Status S203 is a status in which the equipment control device 140 receives the first information from the traffic management device 100 and “(3) confirms that the train has stopped in the stopping area”. A stopping area is an area that occupies the platform when a train stops in line with the station's stopping position target.
[0029] (Status S204) Status S204 is a status in which the equipment control device 140 transmits to the traffic management device 100 “(4) Deployment instruction information for fall prevention safety device (second information)”.
[0030] (Status S205) Status S205 is a status in which the on-board equipment 120 receives “(5) Fall-prevention safety device deployment instruction information (second information)” from the traffic management device 100 and deploys the fall-prevention safety device 190.
[0031] (Status S206) Status S206 is a stage where the equipment control device 140 executes the opening of the platform doors 150. Note that the opening of the platform doors 150 is executed based on an instruction from the traffic management device 100, as described later.
[0032] (Status S207) Status S207 is a status in which the equipment control device 140 transmits "(7) On-board door opening instruction information (third information)" to the traffic management device 100 after opening the platform doors 150 in stage S206.
[0033] (Status S208: Car door 130 opens) Status S208 is a status in which the on-board device 120 receives “(8) Open instruction information for the on-board door 130 (third information)” from the traffic management device 100 and opens the on-board door 130. At this time, the on-board device 120 opens the on-board door 130 based on the third information received from the equipment control device 140 via the operation management device 100, so that the on-board device 120 and the equipment control device 140 can work together to open the on-board door 130.
[0034] (Status S209: Platform door 150 closed) Status S209 is a status in which the equipment control device 140 closes the platform doors 150 based on the information transmitted by the on-board device 120 in status S209.
[0035] (Status S210: vehicle door 130 closed) Status S210 is a status in which the on-board device 120 stores the fall prevention safety device 190, closes the on-board door 130, and transmits this information to the traffic management device 100.
[0036] (Fall prevention safety device 190 deployment abnormality) In addition, if the fall prevention safety device 190 does not deploy normally in status S205, the on-board device 120 transmits fall prevention safety device deployment abnormality information (fourth information (not shown)) to the operation management device 100, and then transmits it from the operation management device 100 to the equipment control device 140. Next, the on-board device 120 re-deploys the fall prevention safety device 190. If the fall prevention safety device 190 is normally deployed, normal processing continues.
[0037] If the fall prevention safety device 190 does not deploy normally again, the on-board device 120 transmits fifth information (not shown) to the operation management device 100 indicating that the fall prevention safety device 190 did not deploy normally again and an abnormality has occurred, and then opens the on-board door 130 without deploying the fall prevention safety device 190. In addition, the operation management device 100 issues a fault alarm to the fall prevention safety device 190, which transmits fall prevention safety device re-deployment abnormality information (fifth information) to the equipment control device 140, indicating that the fall prevention safety device 190 has not been deployed normally again and an abnormality has occurred. Note that control commands such as the fault alarm will be described later. If the above-mentioned fault alarm is output normally, the equipment control device 140 opens the platform doors 150. As a result, even if there is an abnormality in the fall prevention safety device 190, a fault alarm is issued and passengers can board and disembark by opening the on-board doors 130 and the platform doors 150.
[0038] The failure alarm of the fall prevention safety device 190 may be transmitted to the traffic management device 100, or a visual lamp may be provided to indicate that an abnormality has occurred in the fall prevention safety device 190, and the status of the lamp may be indicated. This makes it possible to inform passengers that the fall prevention safety device 190 is not working and to draw their attention.
[0039] <Anomaly in storage of fall prevention safety device 190> If the fall prevention safety device 190 is not stored normally, the on-board device 120 transmits sixth information (not shown) indicating that an abnormality has occurred in the storage of the fall prevention safety device 190 to the operation management device 100, and then the operation management device 100 transmits it to the equipment control device 140. Next, the traffic management device 100 transmits to the on-board device 120 information on a re-storage instruction to instruct the fall prevention safety device 190 to be stored again.
[0040] When the on-board device 120 receives the storage instruction information again, it activates an alarm means for notifying that an abnormality has occurred in the fall prevention safety device 190, and attempts to store the fall prevention safety device 190 again. This causes a message to be sent to those around that an abnormality has occurred in the fall prevention safety device 190, and an attempt is made to retract the fall prevention safety device 190.
[0041] Similarly, as a means for notifying an abnormality in the fall prevention safety device 190, information on the abnormality may be transmitted to the operation management device 100, or a visual lamp may be provided to indicate that an abnormality has occurred in the fall prevention safety device 190, and the state of the lamp may be indicated. This makes it possible to inform passengers that the fall prevention safety device 190 is not working, and to draw their attention.
[0042] <Deployment control process for fall prevention safety device> Next, a specific example of the deployment control process of the fall prevention safety device 190 will be described with reference to FIG. FIG. 3 is a flowchart of the deployment control process of the fall prevention safety device 190 by the traffic management device 100. The process in FIG. 3 shows the process after the train has stopped at the station platform and the equipment control device 140 has confirmed that the train has stopped in the stopping area.
[0043] (Step S301) Step S301 is a step in which the on-board device 120 determines whether the fall prevention safety device 190 has been normally deployed. If the fall prevention safety device 190 has not been normally deployed, the process proceeds to step S302, and if the fall prevention safety device 190 has been normally deployed, the process proceeds to step S305.
[0044] (Step S302) Step S302 is a step in which, if the fall prevention safety device 190 is not deployed normally, the operation management device 100 transmits information to the on-board device 120 instructing it to deploy the fall prevention safety device 190 again, and attempts to deploy the fall prevention safety device 190 again.
[0045] (Step S303) Step S303 is a step in which the traffic management device 100 determines whether or not it has received fall prevention safety device redeployment abnormality information (fifth information) from the on-board device 120, which indicates that an abnormality has occurred in the redeployment of the fall prevention safety device 190. If the fifth information has been received, that is, if the fall prevention safety device 190 has not been properly deployed again, the process proceeds to step S304, and if the fourth information has not been received, that is, if the fall prevention safety device 190 has been properly deployed, the process proceeds to a step in which the on-board doors 130 and the platform doors 150 are opened.
[0046] (Step S304) Step S304 is a step of issuing a failure alarm when the fall prevention safety device 190 does not deploy normally again. At this time, the traffic management device 100 outputs a failure notification to, for example, a terminal in a central control room to indicate that the fall prevention safety device 190 has failed. In addition, a control command to, for example, turn on a lamp may be sent to the fall prevention safety device 190 so that the failure can be visually confirmed.
[0047] (Step S305) Step S305 is a step for determining whether the fall prevention safety device 190 has normally issued a fault alarm. If the fall prevention safety device 190 has normally output a fault alarm, the process proceeds to step S306, where the on-board doors 130 and the platform doors 150 are opened while a warning has been issued using a notification means or the like. On the other hand, if the fall prevention safety device 190 has not normally issued a fault alarm, the process proceeds to step S413, where the platform doors 150 are not opened and abnormality response 307 is taken.
[0048] Here, the equipment control device 140 normally outputs and notifies a failure alarm for the fall prevention safety device 190 means that the equipment control device 140 transmits information to the on-board device 120 via the operation management device 100 so that the on-board device 120 can recognize that the fall prevention safety device 190 has failed. Alternatively, the equipment control device 140 displays on the platform door 150 that the fall prevention safety device 190 has failed, or the like. In either case, by properly issuing a fault alarm, passengers can be aware of any gaps or differences in height between the station platform and the train cars when boarding or disembarking, thereby preventing accidents caused by tripping over the gaps or differences in height.
[0049] That is, in the deployment control of the fall prevention safety device 190 of this embodiment, The traffic management device 100 includes: After receiving fourth information indicating that the fall prevention safety device 190 has not been deployed normally and an abnormality has occurred from the on-board device 120, the fourth information is transmitted to the equipment control device 140, Transmit information to the on-board device 120 to instruct the device 120 to deploy the fall prevention safety device 190 again, Even if the fifth information is received from the on-board device 120, indicating that the fall prevention safety device 190 has not deployed normally again and an abnormality has occurred, if the malfunction alarm is normally notified, the on-board device 120 and the facility control device 140 are each sent an instruction to open the on-board door 130 and the platform door 150, The on-board device 120 is When the fall prevention safety device 190 does not deploy normally and an abnormality occurs, the fourth information is transmitted to the traffic management device 100, and then the fall prevention safety device 190 is attempted to be deployed again, If the fall prevention safety device 190 does not deploy normally again and an abnormality occurs, fifth information is sent to the operation management device 100, and then, if an instruction to open the on-vehicle door 130 is received from the operation management device 100, the on-vehicle door 130 is opened. The equipment control device 140 is Even if the fall prevention safety device 190 does not deploy normally and an abnormality occurs, the fact that an abnormality has occurred in the fall prevention safety device 190 is reported based on the fifth information received from the operation management device 100, and then, if an instruction to open the platform doors 150 is received from the operation management device 100, the platform doors 150 will be opened.
[0050] (Modification) As a modification of this embodiment, when the fall prevention safety device 190 is connected to the equipment control device 140 instead of the on-board device 120, The operation management device is After receiving fourth information indicating that the fall prevention safety device 190 has not been deployed normally and an abnormality has occurred from the equipment control device 140, the fourth information is transmitted to the on-board device 120, Send information to the equipment control device 140 to instruct it to deploy the fall prevention safety device 190 again, Even if a fifth piece of information is received from the equipment control device 140 indicating that the fall prevention safety device 190 has not deployed normally again and an abnormality has occurred, if the fault alarm is normally announced, an instruction to open the platform doors 150 is sent to the equipment control device 140, and an instruction to open the on-board doors 130 is sent to the on-board device 120. The equipment control device includes: When the fall prevention safety device 190 does not deploy normally and an abnormality occurs, the fourth information is transmitted to the traffic management device 100, and then the fall prevention safety device is deployed again, Even if the fall prevention safety device 190 does not deploy normally again and an abnormality occurs, a fault alarm will be issued, and if an instruction to open the platform doors 150 is received from the operation management device, the platform doors 150 will be opened. The on-board device 120 is Based on the fifth information received from the operation management device 100, it notifies the user that an abnormality has occurred in the fall prevention safety device 190, and if an instruction to open the upper door 130 on the vehicle is received from the operation management device, it opens the upper door 130 on the vehicle.
[0051] <Storage control process for fall prevention safety device> Next, a specific example of the storage control process of the fall-prevention safety device 190 will be described with reference to FIG. FIG. 4 is a flowchart of the storage control process of the fall prevention safety device 190. In addition, the processing in Figure 4 shows a case where the platform door 150 is opened after the fall prevention safety device 190 is deployed, but the present disclosure is not limited to this, and the fall prevention safety device 190 may be stored after the platform door 150 is opened.
[0052] (Step S401) Step S401 is a step in which the on-board equipment 120 determines whether the fall prevention safety device 190 has been normally stored. That is, this is a step in which the traffic management device 100 determines whether or not it has received, from the on-board equipment 120, fall prevention safety device storage abnormality information (sixth information) indicating that an abnormality has occurred in the storage of the fall prevention safety device 190. If the fall prevention safety device 190 has not been normally stored, the process proceeds to step S402, and if the fall prevention safety device 190 has been normally stored, the process proceeds to step S405.
[0053] (Step S402) In step S402, if the fall prevention safety device 190 is not stored properly and the operation management device 100 receives the sixth information from the on-board device 120, the operation management device 100 then transmits information to the on-board device 120 instructing it to store the fall prevention safety device 190 again, and instructs it to attempt to store the fall prevention safety device 190 again.
[0054] (Step S403) Step S403 is a step for judging whether the fall prevention safety device 190 has been normally stored by the re-storing of the fall prevention safety device 190. That is, it is a step for judging whether the traffic management device 100 has received fall prevention safety device re-storage abnormality information (seventh information) from the on-board device 120, which indicates that an abnormality has occurred in the re-storing of the fall prevention safety device 190. If the seventh information has been received, that is, if the fall prevention safety device 190 has not been normally stored despite the re-correction instruction, the process proceeds to step S407, and if the seventh information has not been received, that is, if the fall prevention safety device 190 has been normally stored, the process proceeds to step S406 for closing the on-board doors 130 and the platform doors 150.
[0055] In step S407, the fall prevention safety equipment was not stored properly despite a second instruction to store it, so there is a clear possibility that a malfunction has occurred. For this reason, it is not possible to proceed directly to step S406, which is the step of closing the on-board doors 130 and the platform doors 150, and some kind of response to the abnormal operation is required.
[0056] That is, in the storage control of the fall prevention safety device 190 of this embodiment, The traffic management device 100 includes: After receiving sixth information indicating that the fall prevention safety device 190 has not been properly stored and an abnormality has occurred from the on-board device 120, the sixth information is transmitted to the equipment control device 140, Transmit information to the on-board device 120 to instruct the vehicle to store the fall prevention safety device 190 again, When seventh information is received from the on-board device 120, indicating that the fall prevention safety device 190 has not deployed normally again and an abnormality has occurred, measures to deal with the abnormality will be taken. The on-board device 120 is If the fall prevention safety device 190 does not deploy normally and an abnormality occurs, sixth information is transmitted to the operation management device 100, and then an attempt is made to re-store the fall prevention safety device 190, When the fall prevention safety device 190 is properly stored, the vehicle door is closed, If the fall prevention safety device 190 is not stored properly again and an abnormality occurs, seventh information is transmitted to the operation management device 100. The equipment control device 140 is Once the fall prevention safety device 190 is properly stored, the platform door 150 will be opened.
[0057] The signal system 1 according to the embodiment has been described above. The signal system 1 disclosed herein mainly comprises an operation management device 100, an on-board device 120, and an equipment control device 140, and the operation management device 100, the on-board device 120, and the equipment control device 140 work together to handle the opening of the on-board doors 130 and the deployment of the fall prevention safety device 190. Furthermore, in the signaling system 1 of the present disclosure, even if an abnormality occurs once in opening the upper doors 130, an attempt is made again to open the upper doors 130. If an abnormality occurs as a result of attempting to open the upper doors 130 again, a known notification means is implemented to notify the abnormality and alert passengers, etc., so that the train operation can proceed as scheduled. However, if the notification means does not operate normally, separate measures will be taken. This allows the system to flexibly absorb minor anomalies, while responding rigorously if there is a possibility of a major anomaly.
[0058] Although an embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and various modifications are possible without departing from the gist of the present invention. For example, in the above embodiment, it is assumed that the fall prevention safety device 190 is connected to the on-board device 120, is installed on the platform side as viewed from the on-board door 130, and can be deployed and stored regardless of the open / closed state of the on-board door, but the fall prevention safety device 190 may be installed on the inside of the vehicle as viewed from the on-board door 130, and can be deployed and stored only when the on-board door is open. In this case, the fall prevention safety device 190 is deployed and stored after it is confirmed that the on-board door is open. Furthermore, in the above embodiment, the fall prevention safety device 190 is connected to the on-board device 120 and installed on the train, but the fall prevention safety device 190 may also be connected to the equipment control device 140 and installed on the station platform. In this case, after receiving train stop information (first information) from the operation management device 100, the equipment control device 140 deploys the fall prevention safety device 190, and then transmits on-board door opening instruction information (third information) to the operation management device 100.
[0059] Furthermore, in the above embodiment, a case is shown in which the fall prevention safety device 190 is deployed, the platform door 150 is opened, and the on-board door 130 is opened, but the present disclosure is not limited to this, and the fall prevention safety device 190 may be deployed after the platform door 150 and the on-board door 130 are opened. Furthermore, in the above embodiment, the opening of the on-board door 130 is executed by transmitting an open command for the on-board door 130 after the platform door 150 is opened, but after the operation management device 100 checks the deployment state of the fall prevention safety device 190, it is also possible for the fall prevention safety device 190 to transmit an open command to the equipment control device 140 and the on-board device 120, respectively, so that the platform door 150 and the on-board door 130 are opened in parallel. The same applies to the closing of the platform doors 150 and the on-board doors 130.
[0060] The present disclosure also includes the following aspects. (Aspect 1) A signaling system including a traffic control device, a station equipment control device, and a train on-board device, The operation management device includes: A vehicle is connected to the facility control device and the on-board device. Transmitting information on opening and closing of on-board doors of the train and information on opening and closing of platform doors of stations to the on-board device and the facility control device; The facility control device is connected to the operation management device and the platform door and controls opening and closing of the platform door, The on-board device is connected to the traffic management device, the on-board door, and the fall prevention safety device, and controls the deployment and storage of the fall prevention safety device and the opening and closing of the on-board door. The operation management device includes: After receiving train stop information (first information) of the train from the on-board device, transmit the information to the facility control device; After receiving fall prevention safety device deployment instruction information (second information) of the fall prevention safety device from the equipment control device, transmit it to the on-board device, After receiving vehicle door opening instruction information (third information) of the vehicle door from the equipment control device, transmit the information to the on-board device, The equipment control device includes: After receiving the first information from the traffic management device, transmitting the second information to the traffic management device; After transmitting the second information, transmit the third information to the operation management device; The on-board device includes: Transmitting the first information to the traffic management device; After transmitting the first information to the operation management device, deploying the fall prevention safety device based on the second information received from the operation management device; The vehicle door is opened based on the third information received from the operation management device. Signal system. (Aspect 2) A signaling system including a traffic control device, a station equipment control device, and a train on-board device, The operation management device is connected to the equipment control device and the on-board device, and transmits opening / closing information of on-board doors of the train and opening / closing information of platform doors of stations to the on-board device and the equipment control device, The equipment control device is connected to the operation management device, the platform doors, and the fall prevention safety device, and controls the deployment and storage of the fall prevention safety device and the opening and closing of the platform doors, The on-board device is connected to the traffic management device and the on-board door, and controls opening and closing of the on-board door. The operation management device includes: After receiving train stop information (first information) of the train from the on-board device, transmit the information to the facility control device; After receiving vehicle door opening instruction information (third information) of the vehicle door from the equipment control device, transmit the information to the on-board device, The equipment control device includes: After receiving the first information from the operation management device, deploying the fall prevention safety device; After executing the deployment of the fall prevention safety device, transmitting the third information to the operation management device; The on-board device includes: Transmitting the first information to the traffic management device; After transmitting the first information to the traffic management device, the vehicle door is opened based on the third information received from the traffic management device. Signal system. (Aspect 3) In the signaling system according to embodiment 1 or 2, The operation management device includes: After receiving fourth information indicating that the fall prevention safety device has not been deployed normally and an abnormality has occurred from the on-board device, transmitting the fourth information to the equipment control device, Even if fifth information indicating that the fall prevention safety device has not deployed normally again and an abnormality has occurred is received from the on-board device, if a fault alarm is normally notified, an instruction to open the on-board door and the platform door is transmitted to the on-board device and the facility control device, respectively; The on-board device includes: When the fall prevention safety device is not deployed normally and an abnormality occurs, the fourth information is transmitted to the operation management device, and then the fall prevention safety device is deployed again; When the fall prevention safety device does not deploy normally again and an abnormality occurs, the fifth information is transmitted to the operation management device, and when an instruction to open the vehicle door is received from the operation management device, the vehicle door is opened, The equipment control device includes: Even if the fall prevention safety device does not deploy normally and an abnormality occurs, based on the fifth information received from the traffic management device, the occurrence of an abnormality in the fall prevention safety device is notified, and then, when an instruction to open the platform door is received from the traffic management device, the platform door is opened. Signal system. (Aspect 4) In a signaling system according to any one of aspects 1 to 3, The operation management device includes: After receiving sixth information indicating that the fall prevention safety device has not been properly stored and an abnormality has occurred from the on-board device, the sixth information is transmitted to the equipment control device; Transmitting information to the on-board device again instructing the vehicle to store the fall prevention safety device, When seventh information is received from the on-board device indicating that the fall prevention safety device is not deployed normally again and an abnormality has occurred, taking measures to deal with the abnormality; The on-board device includes: When the fall prevention safety device does not deploy normally and an abnormality occurs, the sixth information is transmitted to the operation management device, and then, an attempt is made to re-store the fall prevention safety device, When the fall prevention safety device is properly stored, the vehicle door is closed, If the fall prevention safety device is not properly stored again and an abnormality occurs, the seventh information is transmitted to the operation management device, The equipment control device includes: When the fall prevention safety device is properly stored, the platform door is opened. Signal system. [Explanation of symbols]
[0061] 100 Traffic control device 110 General-purpose LAN 120 Onboard equipment 130 Car Door 140 Facility control device 150 Platform Doors
Claims
1. A signaling system including a traffic control device, a station equipment control device, and a train on-board device, The operation management device includes: A vehicle is connected to the facility control device and the on-board device. Transmitting information on opening and closing of on-board doors of the train and information on opening and closing of platform doors of stations to the on-board device and the facility control device; The facility control device is connected to the operation management device and the platform door and controls opening and closing of the platform door, The on-board device is connected to the traffic management device, the on-board door, and the fall prevention safety device, and controls the deployment and storage of the fall prevention safety device and the opening and closing of the on-board door. The operation management device includes: receiving train stop information (first information) of the train from the on-board device and then transmitting the information to the facility control device; After receiving fall prevention safety device deployment instruction information (second information) of the fall prevention safety device from the equipment control device, transmit it to the on-board device, receiving vehicle door opening instruction information (third information) from the equipment control device and then transmitting the information to the on-board device; The equipment control device includes: After receiving the first information from the traffic management device, transmitting the second information to the traffic management device; After transmitting the second information, transmit the third information to the operation management device; The on-board device includes: Transmitting the first information to the operation management device; After transmitting the first information to the operation management device, deploying the fall prevention safety device based on the second information received from the operation management device; The vehicle door is opened based on the third information received from the operation management device. Signal system.
2. A signaling system including a traffic control device, a station equipment control device, and a train on-board device, The operation management device is connected to the equipment control device and the on-board device, and transmits opening / closing information of on-board doors of the train and opening / closing information of platform doors of stations to the on-board device and the equipment control device, The facility control device is connected to the operation management device, the platform doors, and the fall prevention safety device, and controls the deployment and storage of the fall prevention safety device and the opening and closing of the platform doors, The on-board device is connected to the traffic management device and the on-board door, and controls opening and closing of the on-board door. The operation management device includes: receiving train stop information (first information) of the train from the on-board device and then transmitting the information to the facility control device; receiving vehicle door opening instruction information (third information) from the equipment control device and then transmitting the information to the on-board device; The equipment control device includes: After receiving the first information from the operation management device, deploying the fall prevention safety device; After executing the deployment of the fall prevention safety device, transmitting the third information to the operation management device; The on-board device includes: Transmitting the first information to the operation management device; After transmitting the first information to the traffic management device, the vehicle door is opened based on the third information received from the traffic management device. Signal system.
3. 2. The signaling system according to claim 1, The operation management device includes: receiving, from the on-board device, fourth information indicating that the fall prevention safety device has not been deployed normally and an abnormality has occurred, the fourth information being transmitted to the equipment control device; Even if fifth information indicating that the fall prevention safety device has not deployed normally again and an abnormality has occurred is received from the on-board device, if a fault alarm is normally issued, an instruction to open the on-board door and the platform door is transmitted to the on-board device and the facility control device, respectively; The on-board device includes: When the fall prevention safety device is not deployed normally and an abnormality occurs, the fourth information is transmitted to the operation management device, and then the fall prevention safety device is deployed again; When the fall prevention safety device does not deploy normally again and an abnormality occurs, the fifth information is transmitted to the operation management device, and when an instruction to open the vehicle door is received from the operation management device, the vehicle door is opened, The equipment control device includes: Even if the fall prevention safety device does not deploy normally and an abnormality occurs, the system notifies the user that an abnormality has occurred in the fall prevention safety device based on the fifth information received from the traffic management device, and then opens the platform doors when an instruction to open the platform doors is received from the traffic management device. Signal system.
4. 2. The signaling system according to claim 1, The operation management device includes: After receiving sixth information indicating that the fall prevention safety device has not been properly stored and an abnormality has occurred from the on-board device, the sixth information is transmitted to the equipment control device; Transmitting information to the on-board device again instructing the device to store the fall prevention safety device, When seventh information is received from the on-board device indicating that the fall prevention safety device is not deployed normally again and an abnormality has occurred, taking measures to deal with the abnormality, The on-board device includes: When the fall prevention safety device does not deploy normally and an abnormality occurs, the sixth information is transmitted to the operation management device, and then, an attempt is made to re-store the fall prevention safety device; When the fall prevention safety device is properly stored, the vehicle door is closed, If the fall prevention safety device is not stored normally again and an abnormality occurs, the seventh information is transmitted to the operation management device, The equipment control device includes: When the fall prevention safety device is properly stored, the platform door is opened. Signal system.
Citation Information
Patent Citations
Step device for vehicle
JP2002255029A
Wheel chair slope device for railroad vehicle
JP2005319886A
Entrance access plate device for railway vehicle
JP2014156239A