Construction plan preparation support system, construction plan preparation system, construction method, construction plan preparation support method, and construction plan preparation method
The construction plan creation support system optimizes block stacking in coke ovens by determining delivery flow lines and correcting block shapes and orders, addressing the challenges of heavy blocks and safety concerns in precast methods, thereby reducing construction time and risks.
Patent Information
- Application Number
- JP2023075716
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-01
- Publication Date
- 2024-11-14
AI Technical Summary
The precast large block construction method for coke ovens requires heavy blocks that cannot be handled manually, leading to high workloads and safety concerns due to interference and the need for precise stacking order planning, which complicates the construction process.
A construction plan creation support system that determines optimal delivery flow lines for stacking large refractory blocks using a parts database, construction database, and design system to minimize interference and ensure safety, incorporating a digital mockup for evaluation and correction of block shapes and stacking orders.
This system allows for efficient planning of block stacking, reducing construction time and minimizing safety risks by optimizing block delivery and worker movement, thus enhancing the construction efficiency of coke ovens.
Smart Images

Figure 2024160572000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction plan creation support system, a construction plan creation system, a construction method, a construction plan creation support method, and a construction plan creation method, and in particular to a construction plan creation support system, a construction plan creation system, a construction method, a construction plan creation support method, and a construction plan creation method for stacking large blocks in the construction of a coke oven. [Background technology]
[0002] In a chamber-type coke oven that produces coke for pig iron production, the carbonization chambers and the combustion chambers are arranged alternately in the furnace length direction (furnace width direction), and the furnace top is arranged above the carbonization chamber and the combustion chamber, and the heat regenerator is arranged below. The part between the combustion chamber and the heat regenerator is also called the bellows. The sole flue is arranged below the heat regenerator. Usually, the dimensions of the carbonization chamber are about 4 to 7.5 m high, 350 to 550 mm wide, and 13 to 17 m long. The combustion chamber consists of a row of combustion chamber flues arranged in the furnace length direction. The partitions between the carbonization chamber and the combustion chamber, the partitions between the combustion chamber flues, the furnace top, the bellows, the heat regenerator, and the sole flue are all formed of a brickwork structure of refractory bricks. For example, a chamber-type coke oven (hereinafter simply referred to as a "coke oven") with 64 carbonization chambers is constructed using a total of 2 million of the above-mentioned refractory bricks.
[0003] Currently, existing coke ovens nationwide have been in operation for 20 to 30 years and are showing signs of aging, and the need to build new coke ovens is becoming urgent.
[0004] Traditionally, coke ovens have been constructed by kiln builders stacking refractory bricks by hand. Hand-laid construction requires repeated application of mortar with a trowel to each refractory brick and then stacking them. Furthermore, the refractory bricks used in coke ovens weigh over 10 kg each, making stacking them extremely hard work.
[0005] In addition, coke ovens require the complex assembly of many different types of refractory bricks of various shapes and sizes, and installation accuracy must be within ±2 mm. This requires a large number of skilled oven builders, but these workers are aging, making it difficult to secure a large number of them.
[0006] In view of these circumstances, a prefabricated construction method is known, in which a large block is made by stacking a number of refractory bricks to a predetermined size in a large, easy-to-work area away from the construction site and integrating them with mortar, and then assembling the large block at the construction site to stack the coke oven, with the aim of reducing the number of oven builders required by shortening the construction period. As a system and method for forming blocks using a prefabricated construction method, Patent Document 1 discloses a system and method for stacking standard refractory materials on a stacking base to create blocks.
[0007] Also known is a precast method (also called a large precast block method) in which, instead of piling up refractory bricks to form blocks as in the prefabricated method, a granular refractory composition is mixed with water, poured into a formwork, and dried to form a large refractory block (Patent Document 2).
[0008] The prefabricated or precast construction method is said to improve work efficiency and shorten the construction period because the number of blocks to be stacked at the furnace construction site is reduced and the work space required at the narrow furnace construction site is shortened by using large refractory blocks per block. In particular, the precast construction method has good work efficiency because the number of blocks to be stacked is reduced.
[0009] In typical coke oven construction, a certain amount of bricks of the same shape are packed (about 1 ton) on a pallet, which is then transported to the construction site, where they are unpacked (by hand), arranged (by hand), and constructed (by hand). Because the bricks handled are lighter than large blocks, any problems that occur on site (cracked bricks, incorrect arrangement, etc.) can be dealt with by hand in a short time.
[0010] On the other hand, in the precast large block construction method, unlike the lightweight bricks used in general coke oven construction that can be stacked by hand, the precast large blocks (large refractory blocks) are heavy objects weighing up to 1 ton or more, and are impossible to handle by humans, so they require transportation such as cranes and special equipment for furnace construction. These precast large blocks are also handled one by one on mats called pallets.
[0011] With the large precast block construction method, it is important to "build the specified large precast blocks in the specified locations quickly and without error," and this requires management.
[0012] Patent Document 2 discloses a method of constructing a coke oven by stacking large blocks of refractory material, in which tags recording position data for constructing each large block and shape data for the large blocks are attached to the large blocks themselves or to the pallets on which the large blocks are placed, and the records on the tags are read and sent to a high-performance crane, which transports the large blocks on the pallets based on the records and stacks them in designated locations at the construction site. [Prior art documents] [Patent documents]
[0013] [Patent Document 1] JP 2017-14448 A [Patent Document 2] JP 2019-218421 A Summary of the Invention [Problem to be solved by the invention]
[0014] In the precast large block construction method, the large precast blocks are heavy and cannot be handled by humans, so they are handled by a crane as described in Patent Document 2. In addition, the number that can be stocked on-site is limited. Therefore, if interference between large blocks when stacked or with other blocks or equipment during transport is discovered on-site, the workload is very large when correcting the shape of the large blocks on-site.
[0015] In addition, manual work such as applying mortar before and after transporting each block is required during block construction work. In addition, precast blocks are transported by crane during construction work, but for safety reasons, workers must evacuate while the blocks are being transported, so planning the order in which blocks are stacked while considering the movement of people and equipment is essential to shortening construction time.
[0016] The present invention aims to provide a construction plan creation support system, a construction plan creation system, a construction method, a construction plan creation support method, and a construction plan creation method that can determine an optimal delivery route for loading large blocks in advance so as to shorten the construction time for loading large blocks in the construction of a coke oven. [Means for solving the problem]
[0017] That is, the gist of the present invention is as follows. [1] A construction plan creation support system that supports the creation of a construction plan for stacking large refractory blocks in the construction of a coke oven, comprising: a parts database for storing one or both of the shape of each block and the shape of the block in a constructed state; A construction database that stores one or more of the following: conditions to be met for safety, the stacking order of each block, the range of movement of blocks when carrying in blocks, and the movement of materials; and A design system in which a delivery line for each block is determined based on the part database and the construction database, In the design system, when the delivery traffic line of a target block among the blocks is determined, in a state in which a block that precedes the target block in the stacking order has been constructed in accordance with the stacking order of each block stored in the construction database, the delivery traffic line of the target block is set within a range that satisfies the block traffic line movement range at the time of block delivery stored in the construction database and the safety conditions that must be met, and when each block is delivered along the set delivery traffic line of each block, the stacking construction time of the block is evaluated, and the delivery traffic line of each block that will shorten the stacking construction time is determined. This is a construction plan creation support system characterized by the above. [2] The construction database stores the conditions that must be met for safety, and further stores the movement range of workers, The construction plan creation support system described in [1] is characterized in that in the design system, the movement lines of workers are determined based on the delivery movement lines of each block, within a range that satisfies the safety conditions that must be met and the movement line movement range of workers stored in the construction database. [3] The parts database stores the shape of each block or the construction database stores the stacking order of each block, and the design system modifies one or both of the shape of each block stored in the parts database and the stacking order of each block stored in the construction database, According to the revised results, the design system again corrects the delivery flow lines of each block based on the parts database and the construction database, The construction plan creation support system described in [1] or [2] is characterized in that the loading and construction time of each block is evaluated for the revised delivery line of each block and the delivery line of each block before the revision, and the delivery line of the block that results in the shorter loading and construction time is determined.
[0018] [4] A construction plan creation system for creating a construction plan using the construction plan creation support system according to [1] to [3], The construction plan includes one or more of the following: the delivery line of each block, the position of each block, the shape of each block, the stacking order of each block, and the flow line of workers; Construction planning system.
[0019] [5] A construction method for stacking large refractory blocks in the construction of a coke oven, comprising the steps of: [1]-[3] The delivery route of each block, the position data of each block, and the shape of each block determined by the construction plan creation support system described in the above are recorded in the tag, The tag is attached to each of the blocks themselves or to a pallet on which each of the blocks is placed. Construction method.
[0020] [7] A method for supporting construction planning for stacking large refractory blocks in the construction of a coke oven, comprising: a parts database for storing one or both of the shape of each block and the shape of the block in a constructed state; A construction database that stores one or more of the following: conditions to be met for safety, the stacking order of each block, the range of movement of blocks when carrying in blocks, and the movement of materials; and A design system that determines the delivery line of each block based on the component database and the construction database. In the design system, when the delivery traffic line of a target block among the blocks is determined, in a state in which a block that precedes the target block in the stacking order according to the stacking order of each block stored in the construction database has been constructed, the delivery traffic line of the target block is set within a range that satisfies the block traffic line movement range at the time of block delivery stored in the construction database and the safety conditions that must be met, and when each block is delivered along the set delivery traffic line of each block, the stacking construction time of the block is evaluated, and the delivery traffic line of each block that will shorten the stacking construction time is determined. This is a construction plan creation support method characterized by the above. [8] The construction database stores the conditions that must be met for safety, and further stores the movement range of workers; The construction plan creation support method described in [7] is characterized in that in the design system, the movement lines of workers are determined based on the delivery movement lines of each block, within a range that satisfies the safety conditions that must be met and the movement line movable range of workers, which are stored in the construction database. [9] A construction plan creation support method as described in [7] or [8], characterized in that the parts database stores the shape of each block or the construction database stores the stacking order of each block, the design system modifies one or both of the shape of each block stored in the parts database and the stacking order of each block stored in the construction database, and based on the results of the modifications, the design system again modifies the delivery route of each block based on the parts database and the construction database, evaluates the stacking and construction time of the blocks for the modified delivery route of each block and the delivery route of each block before the modifications, and determines the delivery route of the blocks that will have the shorter stacking and construction time.
[0021]
[10] A construction plan creation method for creating a construction plan using the construction plan creation support method according to any one of [7] to [9], The construction plan includes one or more of the following: the delivery line of each block, the position of each block, the shape of each block, the stacking order of each block, and the flow line of workers; How to create a construction plan.
[0022]
[11] A construction method for stacking large refractory blocks in the construction of a coke oven, comprising the steps of: [7] to [9], one or more of the delivery traffic flow of each block, the position data of each block, and the shape of each block determined by the construction plan creation support method described in any one of [7] to [9] are recorded in a tag; The tag is attached to each of the blocks themselves or to a pallet on which each of the blocks is placed. Construction method. Effect of the Invention
[0023] The present invention provides a construction plan creation support system, a construction plan creation system, a construction method, a construction plan creation support method, and a construction plan creation method that can determine an optimal delivery route for loading large blocks in advance so as to shorten the construction time for loading large blocks in the construction of a coke oven. [Brief description of the drawings]
[0024] [Figure 1] 1 is a diagram showing a system configuration of a construction plan creation support system according to an embodiment of the present invention. [Diagram 2] 1A is a plan view, FIG. 1B is a side cross-sectional view, and FIG. 1C is a front view, comparing the crane loading traffic flow of an example of the present invention with that of a comparative example. [Diagram 3] FIG. 2 is a side view showing the intermediate stage of block laying for a coke oven battery. [Figure 4] This is a plan view showing the intermediate stage of block laying for a coke oven battery. [Diagram 5] This is a plan view showing the intermediate stage of block laying for a coke oven battery. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0025] 1, the construction plan creation support system according to this embodiment includes a parts database 1, a construction database 2, and a design system 3 that determines the block delivery traffic line based on the parts database 1 and the construction database 2. More preferably, the system includes an input / output terminal 4 for man-machine interface.
[0026] Hereinafter, a method for optimizing the delivery flow line of each block will be described with reference to FIG. 2 which explains the delivery flow line 21 of the crane.
[0027] The parts database 1 stores the shape of each block 11 and the shape of the blocks 11 when constructed. The shape of each block is designed in advance in 3D, and the shape of each designed block when constructed is constructed and stored in the parts database 1. In addition, the parts database 1 stores shape data of metal fittings, protective plates, backstays, etc., which are structures other than the coke oven blocks, as necessary. The shape of the blocks 11 when constructed is set in advance so that there is no interference between the blocks.
[0028] The construction database 2 stores the order in which the blocks 11 are laid, the range of movement 23 of the blocks when the blocks are brought in, and the conditions that must be met for safety. The construction database 2 also stores the material delivery flow, etc., as necessary.
[0029] The construction database 2 stores the order in which blocks are stacked. The order in which blocks are stacked can be determined based on the stored order of stacking the blocks 11 and the shape of the blocks in their constructed state (stored in the parts database 1) for the state in which a block that precedes the block 11A for which the block delivery traffic line 21 is to be determined. There are multiple possible orders for stacking the blocks. The multiple stacking orders will be described later with reference to Figs. 3 to 5.
[0030] The construction database 2 stores a block movement line movable range 23 when the block is carried in. The block movement line movable range 23 when the block is carried in is a range that can be set as a movement line for moving the target block 11A to a loading position when the block is carried in the building. In the case of FIG. 2, the block 11 is placed in a storage area 15 outside the coke oven building 13, and a crane 12 is used to move the block 11 from the storage area 15 to a loading position 14 in the coke oven building 13. Since the loading entrance 16 for carrying the block from the storage area 15 into the building is limited, the block movement line movable range 23 when the block is carried in is determined based on the position of the storage area 15 of the block 11, the arrangement of the coke oven building 13, the arrangement of the loading entrance 16 of the block 11 into the building 13, and the like, and is stored in the construction database 2. An example of the block movement line movable range 23 is shown by a two-dot chain line in FIG. 2(B).
[0031] The construction database 2 also stores conditions that must be met for safety when carrying in the target block. The conditions that must be met for safety include the allowable lifting range 22 of the block lifted by the crane and the height limit within the allowable lifting range 22. The allowable lifting range 22 of the block lifted by the crane is exemplified by the range that must be secured as the distance from the surface of the stacked blocks in the current state of stacking the blocks in the coke oven (constructed block structure 17). More specifically, for example, the range that must be secured as the height from the top surface of the stacked blocks is exemplified. For an area where the blocks have not yet been placed and the floor surface is exposed, the range that must be secured as the height from the exposed floor surface is determined. The lower limit of the height of the allowable lifting range 22 of the block lifted by the crane is determined, for example, so that the bottom end of the target block 11A is 1 m above the top end of the object installed in the oven, taking into account the misalignment of the gripping position of the block and the misconception of the object installed in the oven. By taking into consideration the allowable lifting range 22 of the target blocks, it is possible to prevent blocks from coming into contact with each other or with other equipment during stacking. In addition, the upper limit of the allowable lifting range 22 of the blocks lifted by the crane can be set to a height that does not cause the blocks to come into contact with the building, for example. On the other hand, the height of the traffic line for bringing in the blocks should be set as low as possible within the allowable lifting range 22. This is to minimize damage in the event of an accident in which the load falls from the crane, since workers are performing work on top of the stacked blocks and on the exposed floor surfaces. An example of the lower limit of the allowable lifting range 22 is shown by the two-dot chain line in Figure 2(B).
[0032] It is preferable that the construction database 2 further stores the moving range of the worker's movement line. The determination of the moving range of the worker's movement line using the carry-in movement line 21 of each block will be described separately later.
[0033] In the design system 3, a block delivery traffic line 21 is determined based on the parts database 1 and the construction database 2. This will be described in detail below.
[0034] In the design system 3, when the delivery traffic line 21 of the target block 11A among each block 11 is determined, the state in which a block that precedes the target block 11A in the stacking order according to the block stacking order stored in the construction database 2 has been constructed is clearly indicated as a completed block structure 17. In the completed block structure 17, the delivery traffic line 21 of the target block is set within a range that satisfies the block traffic line movable range 23 at the time of block delivery stored in the construction database 2 and the conditions that must be met for safety. At this time, if multiple block delivery traffic lines 21 are possible, multiple block delivery traffic lines 21 are set. In addition, the presence or absence of interference between the block and equipment when the block 11A is delivered along the set block delivery traffic line 21 is evaluated, and the construction time required for stacking each block is calculated.
[0035] A digital mockup (DMU) can be preferably used as an element of the design system 3. For example, Fujitsu Limited's "COLMINA Digital Production Preparation VPS" can be used as the DMU. The DMU represents parts and mechanisms in a three-dimensional virtual space, and can evaluate the relationship between the target block and adjacent blocks, the relationship between the target block and the coke oven building structure and the already-constructed block structure, whether there is interference when the target block is moved by a crane, and whether there is interference when the target block is installed at the target position. In addition, the construction time required for transporting and stacking the target block can be determined and evaluated.
[0036] FIG. 2 shows the carrying-in traffic line 21 along which the target block 11A is moved by the crane 12 from the storage area 15 outside the coke oven to the loading position 14 inside the oven. The target block 11A is sling-loaded to the crane 12 at the storage area 15 and transported to the loading position 14 via the carrying-in entrance 16. In FIG. 2(B), the movable range 23 of the block traffic line when the block is carried in is shown by a two-dot chain line, and the lower limit of the lifting allowable range 22 of the block lifted by the crane is also shown by a two-dot chain line and hatched as a condition to be met for safety. In FIG. 2(B), the lifting allowable range 22 of the block is based on the lower end position of the block, while the carrying-in traffic line 21 is based on the upper end position of the block.
[0037] In Fig. 2, the carry-in traffic line 21X in the comparative example to which the present invention is not applied is shown by a thick dashed line. The material moves in a straight line from the storage area 15 to the carry-in entrance 16 in the shortest possible distance, and after entering the furnace from the carry-in entrance 16, the material also moves in a straight line in the shortest possible distance to directly above the loading position 14.
[0038] The construction database 2 of the construction plan creation support system of the present invention stores the lower limit position of the lifting allowable range 22 as a condition to be met for safety. The lower limit position is set at a height of 1.0 m from the top surface of the already constructed block structure 17. Workers are working on the top surface of the already constructed block structure 17, and if the lower limit height is set at a height of 1.0 m from the top surface, the work of the workers will not be impeded. In addition, as a condition to be met for safety, it is set that the height should be as low as possible within the lifting allowable range 22. Therefore, as a result of applying this embodiment to determine the delivery line of the target block 11A, as shown in FIG. 2, the delivery line of the block 21A is determined within the range that satisfies the block flow line movable range at the time of block delivery and the conditions to be met for safety (thick solid line (hidden part is thick chain line)).
[0039] The carry-in traffic line 21X of the comparative example moves at a height much higher than the top surface of the completed block structure 17, which increases the damage in the event of an accident in which the load falls from the crane. In contrast, the carry-in traffic line 21A of the above-mentioned example of the present invention moves at a height of just 1.0 m above the top surface of the completed block structure 17, so the work of the workers is not impeded and the workers can reliably recognize the approach of the load and take shelter, minimizing the damage in the event of an accident in which the load falls from the crane.
[0040] The delivery traffic flow 21 for each block determined in the design system 3, the evaluation results for whether or not there is interference between the block and equipment when the block is delivered along the determined delivery traffic flow for the block, and the construction time required to stack each block are stored in the construction database 2.
[0041] In this embodiment, the construction database preferably further stores the movement range of the worker. The movement range of the worker is, for example, a range with a retreat distance of 3m or more on a plane from the block being carried in. In the design system 3, based on the carrying-in movement line 21 of the target block determined as described above, the movement line of the worker is determined within a range that satisfies the safety conditions stored in the construction database 2 and the movement range of the worker. During the block stacking work, the worker works around the block, but when the next block is carried in, the worker evacuates to an area (movable range of the worker's movement line) with a retreat distance of 3m from the block being carried in. After that, after confirming that the block has stopped at the stacking position, the worker moves around the block and starts the stacking work.
[0042] After the delivery traffic lines 21 for each block are set by the design system 3, the shape of each block and / or the stacking order of the blocks can be modified to further increase the number of candidates for the delivery traffic lines 21 for the blocks.
[0043] In an embodiment of the construction plan creation support system, the design system 3 modifies one or both of the shape of each block stored in the parts database and the stacking order of the blocks stored in the construction database. The input / output terminal 4 can be used to prompt the designer to make the modifications. The designer who is prompted to make the modifications modifies one or both of the shape of each block stored in the parts database 1 and the stacking order of the blocks stored in the construction database 2, and then inputs the modified data into the design system 3 via the input / output terminal 4, and the design system 3 stores the modified data in the parts database 1 and the construction database 2. The design system 3 can also modify one or both of the shape of each block stored in the parts database and the stacking order of the blocks stored in the construction database.
[0044] In an embodiment of the construction plan creation support method, the design system 3 modifies one or both of the shape of each block stored in the parts database and the stacking order of the blocks stored in the construction database. After modifying one or both of the shape of each block stored in the parts database 1 and the stacking order of the blocks stored in the construction database 2, the designer inputs the modified data into the design system 3 via the input / output terminal 4, and the design system 3 stores the modified data in the parts database 1 and the construction database 2. The design system 3 can also modify one or both of the shape of each block stored in the parts database and the stacking order of the blocks stored in the construction database.
[0045] By modifying the block shape, the number of block types can be reduced. If the number of block types can be reduced, the number of pallets for transporting the blocks can be reduced, and the construction plan can be simplified to shorten the construction time required for stacking the blocks. In addition, by modifying the block stacking order, the time required for changing jigs can be shortened. If the time required for changing jigs can be shortened, the construction time required for stacking the blocks can be shortened. Alternatively, both the block shape and the block stacking order can be modified.
[0046] If interference occurs between the blocks and the equipment, the interference can be avoided by modifying the block shape and / or the block stacking order, or by changing both the block stacking order and the block shape.
[0047] After carrying out the above preparations, the design system 3 again sets the delivery traffic line 21 for the blocks 11 based on the parts database 1 and the construction database 2, and re-evaluates the construction time required for stacking the blocks when carrying in the blocks 11 along the set delivery traffic line 21. If the re-evaluation shows that the construction time required for stacking the blocks can be shortened, it becomes possible to create an optimal construction plan.
[0048] When multiple delivery lines 21 for the target block 11A are possible, the delivery line that will minimize the construction time is selected. The construction time can be estimated using a digital mockup. Alternatively, the delivery line that poses the fewest safety issues can be selected as the delivery line 21 for the target block 11A.
[0049] When multiple shapes of blocks 11 are possible, it is possible to select the block shape that results in the smallest number of block types, and to select the block entrance traffic line 21 that corresponds to this block shape.
[0050] The method for optimizing the delivery traffic flow of each block has been described above. In the present invention, the stacking order of blocks that can minimize the construction time for a part or all of a coke oven battery can be considered. For example, as shown in Figures 3 to 5, when arranging blocks in the sole flue section of a coke oven, the delivery traffic flow and construction time of each block can be clarified by applying the present invention in the case where the blocks are stacked in the oven length direction (see Figure 4) and the case where the blocks are stacked in the oven length direction (see Figure 5), and the total construction time required to stack the blocks in the entire sole flue section of the oven battery can be calculated, and the stacking order and delivery traffic flow that minimize the total construction time can be selected.
[0051] The construction plan creation system of this embodiment creates a construction plan using the construction plan creation support system of this embodiment. The construction plan includes one or more of the following: the delivery traffic flow of each block, the position of each block, the shape of each block, the stacking order of each block, and the traffic flow of workers.
[0052] The construction method of this embodiment for stacking large refractory blocks 11 in the construction of a coke oven will be described. One or more of the delivery traffic line of each block, the position data of each block, and the shape of each block determined by the construction plan creation support system of this embodiment are recorded in a tag 18. The tag 18 is attached to each block 11 itself or to a pallet on which each block 11 is placed.
[0053] A crane 12 is used to carry in the block 11. In this embodiment, preferably, a high-performance crane as described in Patent Document 2 is used. The high-performance crane is a crane 12 that can freely transport the block 11 in all three directions, the furnace width direction, the furnace length direction, and the furnace height direction. The high-performance crane has an assembly position setting control function at an absolute address (predetermined coordinates), and can ensure the stacking accuracy of the blocks. In addition to using a high-performance crane as the crane 12, the data recorded in the tag 18 can be read and the block 11 can be transported exactly as it is. An IC chip or the like can be used as a method for recording on the tag 18. If the recording medium is paper, a two-dimensional code such as a QR code (registered trademark), a barcode, or the like can be used.
[0054] The construction plan creation support method and construction plan creation method of this embodiment are a construction plan creation support method and a construction plan creation method that support the creation of a construction plan for stacking large refractory blocks in the construction of a coke oven, using the same parts database and construction database as the construction plan creation support system and construction plan creation system, and a design system in which the block delivery traffic route is determined based on the parts database and construction database. EXAMPLES
[0055] 3 to 5, an example will be described in which the construction plan creation support system of this embodiment is used to determine an efficient stacking order of blocks that can minimize construction time when stacking blocks in the sole flue section of a coke oven.
[0056] The target furnace battery has blocks 11 arranged in N rows in the furnace battery length direction 42, and blocks 1 to M arranged in the furnace length direction 41. Figure 3 is a side view seen in the furnace battery length direction 42, with the furnace length direction 41 on the left and right of the paper. Figures 4 and 5 are plan views, with the furnace battery length direction 42 on the top and bottom of the paper and the furnace length direction 41 on the left and right of the paper, and three rows from row I-1 to row I+1 are shown in the furnace battery length direction 42. In Figures 4 and 5, block 11A to be positioned by a crane is shown with dot hatching.
[0057] There are two types of blocks 11 to be arranged: end blocks 31 that contact the backstays arranged at both ends in the furnace length direction 41, and intermediate blocks 32 that are arranged in the portion sandwiched between the end blocks 31 in the furnace length direction 41. When lifting and moving the blocks 11 with the crane 12, an end jig 33 is used to lift the end blocks 31, and an intermediate jig 34 is used to lift the intermediate blocks 32. When exchanging the end jig 33 and the intermediate jig 34, a required exchange time is required.
[0058] In order to prevent leakage of gas and the like, dowels 36 are provided at the joint surfaces between the blocks in the furnace length direction 41. In Fig. 3(A), the J-th intermediate block 32 in the furnace length direction 41 is the target block 11A, and dowels 36 are provided on both end surfaces in the furnace length direction 41 so that they can engage with the dowels 36 of the mating block to be joined (e.g., the J-1 intermediate block 32). Since the J-th intermediate block 32 has such dowels 36, when placing it, it is necessary to lower the target block 11A with the crane 12 and then move it horizontally in the furnace length direction 41 toward the J-1 intermediate block 32, as shown in Fig. 3(A).
[0059] However, there is not enough space for horizontal movement for all blocks from J=2 to J=M. Therefore, the method shown in Fig. 3(B)(C) is adopted. As shown in Fig. 3(B), for blocks up to M-2, dowels 36 are placed between the blocks placed before them, and horizontal movement is interwoven to join them. Next, the end block 31 of M is placed as the target block 11A (Fig. 3(B)). At this time, the interval between the middle block 32 of M-2 and the end block 31 of M is accurately adjusted. As a result, the middle block 32 of M-1 can be accurately placed next (Fig. 3(C)). However, when placing the middle block 32 of M-1 as the target block 11A, the blocks cannot be moved horizontally, so that the joint surfaces between M-1 and M-2 and between the M-1 stage and M are provided with uneven joints 37 instead of dowels, as shown in Fig. 3(C).
[0060] Next, the stacking order of blocks in the furnace length direction 41 and the furnace battery length direction 42 is considered.
[0061] FIG. 4 is an explanatory diagram of the case where blocks are stacked in the furnace length direction 41. The white arrows in FIG. 4 indicate the direction of stacking order. FIG. 4(A) shows the time when the arrangement of row I-1 in the furnace length direction 42 is completed, and the arrangement of row I up to J-1 in the furnace length direction 41 is completed, and the intermediate block 32 at J is the block 11A to be placed. An intermediate jig (not shown) is installed on the crane. FIG. 4(B) shows the arrangement of row I up to intermediate block 32 at M-2, at which point the jig is changed from intermediate jig 34 to end jig 33 (not shown), and the end block 31 at M is placed as the target block 11A. After this, it is recommended to continue placing end block 31 at 1 in row I+1. Next, the jig is replaced from the end jig 33 to a mid-way jig 34 (not shown), and the mid-way block 32 at number M-1 in row I is dropped and positioned as the target block 11A, as shown in FIG. 4(C).
[0062] FIG. 5 is an explanatory diagram of the case where blocks are stacked in the furnace battery length direction 42. The white arrows in FIG. 5 indicate the direction of stacking. First, the end block 31 in the furnace length direction 1 is arranged in the furnace battery length direction 42 in the order of 1st row, 2nd row, 3rd row, and so on, completing the arrangement up to row N. At this point, the jig is replaced, and the intermediate block 32 in the furnace length direction 2 is arranged in the same manner from row 1 to row N. At the stage of FIG. 5(A), the arrangement of rows 1 to N is completed for rows 1 to N for rows 1 to J-1 for J, and row 1 to row I-1 is completed for row 1 to row I-1 for row 1, and the intermediate block 32 in row I for row J is arranged as the target block 11A. In FIG. 5(B), the arrangement of all blocks in the furnace battery length direction up to row M-2 is completed, and after replacing the jig, the end block M is arranged from row 1 to row I-1 for row 1 to row I-1 for row 2, and row I for row M is currently being arranged as the target block 11A. After completing the arrangement of all the blocks 42 in the furnace length direction of M, the jig is replaced and the intermediate blocks M-1 in the furnace length direction are arranged in order in the furnace length direction as shown in Figure 5(C). Figure 5(C) shows that the arrangement has been completed up to row I-1 in the furnace length direction of M-1, and the intermediate block 32 in row I of M-1 is being arranged as the target block 11A. Since it cannot be moved horizontally, it is installed by dropping it in.
[0063] As for the order in which the blocks are arranged, two methods have been devised: stacking in the furnace length direction 41 as shown in Figure 4, and stacking in the furnace length direction 42 as shown in Figure 5. Next, for each method, the construction plan creation support system of the present invention is applied to calculate the total block stacking construction time, including the time required for joining the blocks, the time required for transporting the blocks, the time required for evacuating workers, and the time required for changing jigs, and the optimal stacking order is selected, assuming that the one with the shortest construction time is the most efficient stacking order.
[0064] Regarding the transport time for each block to be loaded, the optimal transport time is known when optimizing the loading traffic line using Figure 2 as described above, so that data can be used. Regarding the work time for joining blocks, it can be determined in advance based on past performance for both cases where the joining surface with the other block has dowels 36 (in which case a horizontal movement process is performed in the final stage of installation) and where there are no dowels (in which case only a vertical drop is performed). The time required to change jigs can also be given in advance.
[0065] The evacuation time for people may be determined in advance based on the measurement of actual work time, or may be calculated by applying the construction plan creation support system of the present invention.
[0066] With the above preparations complete, the construction plan creation support system of the present invention was applied to set up the delivery traffic lines for each of the methods of stacking in the furnace length direction 41 shown in Figure 4 and stacking in the furnace battery length direction 42 shown in Figure 5, and the total block stacking construction time when the blocks were brought in along these delivery traffic lines was calculated. As a result, it was found that the block stacking construction time was shorter when stacking in the furnace battery length direction 42 than when stacking in the furnace length direction 41. Based on this result, when setting up the delivery traffic lines that can shorten the block stacking construction time, it was possible to adopt construction in the furnace battery length direction 42 as the optimal stacking order. [Explanation of symbols]
[0067] 1 Parts database 2 Construction database 3. Design System 4 Input / Output Terminals 11 Blocks 11A Target Block 12 Crane 13 Building 14 Loading position 15 Storage 16 Loading entrance 17 Prefabricated Block Structures 18 Tags 21 Loading Route 21A Loading route 21X Loading traffic line 22 Lifting tolerance 23 Block movement range 31 End block 32 Midway Block 33 End jig 34 Intermediate jig 35 Backstay 36 Dowel 37 Concave / convex joint 41 Furnace length direction 42 Furnace leader direction 43 Height
Claims
1. A construction plan creation support system that supports the creation of a construction plan for stacking large refractory blocks in the construction of a coke oven, a parts database for storing one or both of the shape of each block and the shape of the block in a constructed state; A construction database that stores one or more of the following: conditions to be met for safety, the stacking order of each block, the range of movement of blocks when carrying in blocks, and the movement of materials; and A design system in which a delivery line for each block is determined based on the part database and the construction database, In the design system, when the delivery traffic line of a target block among the blocks is determined, in a state in which a block that precedes the target block in the stacking order has been constructed in accordance with the stacking order of each block stored in the construction database, the delivery traffic line of the target block is set within a range that satisfies the block traffic line movement range at the time of block delivery stored in the construction database and the safety conditions that must be met, and when each block is delivered along the set delivery traffic line of each block, the stacking construction time of the block is evaluated, and the delivery traffic line of each block that will shorten the stacking construction time is determined. This is a construction plan creation support system characterized by the above.
2. The construction database stores conditions that must be met for safety, and further stores the movement range of workers, The construction plan creation support system described in claim 1, characterized in that in the design system, the movement lines of workers are determined based on the delivery movement lines of each block, within a range that satisfies the safety conditions that must be met and the movement line movable range of workers, which are stored in the construction database.
3. The part database stores the shape of each block, or the construction database stores the stacking order of each block, The design system modifies one or both of the shape of each block stored in the part database and the stacking order of each block stored in the construction database, According to the revised results, the design system again corrects the delivery lines of each block based on the parts database and the construction database; The construction plan creation support system according to claim 1 or claim 2, characterized in that the loading and construction time of each block is evaluated for the revised delivery line of each block and the delivery line of each block before the revision, and the delivery line of the block which results in the shorter loading and construction time is determined.
4. A construction plan creation system for creating a construction plan using the construction plan creation support system according to claim 1 or 2, The construction plan includes one or more of the following: the delivery line of each block, the position of each block, the shape of each block, the stacking order of each block, and the flow line of workers; Construction planning system.
5. A construction method for stacking large refractory blocks in the construction of a coke oven, comprising the steps of: One or more of the delivery line of each block, the position data of each block, and the shape of each block determined by the construction plan creation support system according to claim 1 or 2 are recorded in the tag, The tag is attached to each of the blocks themselves or to a pallet on which each of the blocks is placed. Construction method.
6. A construction method for stacking large refractory blocks in the construction of a coke oven, comprising the steps of: One or more of the delivery line of each block, the position data of each block, and the shape of each block determined by the construction plan creation support system according to claim 3 are recorded in a tag, The tag is attached to each of the blocks themselves or to a pallet on which each of the blocks is placed. Construction method.
7. A method for supporting construction planning for stacking large refractory blocks in the construction of a coke oven, comprising: a parts database for storing one or both of the shape of each block and the shape of the block in a constructed state; A construction database that stores one or more of the following: conditions to be met for safety, the stacking order of each block, the range of movement of blocks when carrying in blocks, and the movement of materials; and A design system that determines the delivery line of each block based on the component database and the construction database. In the design system, when the delivery traffic line of a target block among the blocks is determined, in a state in which a block that precedes the target block in the stacking order has been constructed in accordance with the stacking order of each block stored in the construction database, the delivery traffic line of the target block is set within a range that satisfies the block traffic line movement range at the time of block delivery stored in the construction database and the safety conditions that must be met, and when each block is delivered along the set delivery traffic line of each block, the stacking construction time of the block is evaluated, and the delivery traffic line of each block that will shorten the stacking construction time is determined. This is a construction plan creation support method characterized by the above.
8. The construction database stores conditions that must be met for safety, and further stores the movement range of workers, The construction plan creation support method according to claim 7, characterized in that in the design system, the movement lines of workers are determined within a range that satisfies the safety conditions stored in the construction database and the movement range of workers, based on the delivery movement lines of each block.
9. The part database stores the shape of each block, or the construction database stores the stacking order of each block, The construction plan creation support method according to claim 7 or 8, characterized in that the design system modifies one or both of the shape of each block stored in the parts database and the stacking order of each block stored in the construction database, and based on the results of the modifications, the design system again modifies the delivery flow of each block based on the parts database and the construction database, evaluates the loading and construction time of the blocks for the modified delivery flow of each block and the delivery flow of each block before the modifications, and determines the delivery flow of the blocks that will have the shorter loading and construction time.
10. A construction plan creation method for creating a construction plan using the construction plan creation support method according to claim 7 or 8, The construction plan includes one or more of the following: the delivery line of each block, the position of each block, the shape of each block, the stacking order of each block, and the flow line of workers; How to create a construction plan.
Citation Information
Patent Citations
Coke oven vertical flame path partition wall integral repairing ceramic part and vertical flame path partition wall structure
CN213446966U
System and method for stacking regular-shaped refractories of coke oven
JP2017014448A
In-pile import method of module block
JP2017137446A
Method of constructing coke oven
JP2019218421A
Furnace construction method
JP2022012554A