Cutting device and cutting method

The cutting device with integrated dust collection through pulleys and suction nozzles effectively contains dust during concrete cutting, addressing the issue of scattering and improving environmental cleanliness.

JP2024160594APending Publication Date: 2024-11-14SHIMIZU CORP +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023075765
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-01
Publication Date
2024-11-14

AI Technical Summary

Technical Problem

Existing cutting devices for concrete members using wire saws fail to effectively collect and contain dust generated during the cutting process, leading to scattering in the surrounding area.

Method used

A cutting device equipped with a cutting section and a dust collection section, featuring pulleys and a suction nozzle connected to a dust collector, which collects dust through a core hole formed in the concrete member during cutting.

Benefits of technology

Prevents dust generated during cutting from scattering by collecting it within the core hole and slit structures, ensuring a cleaner cutting process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024160594000001_ABST
    Figure 2024160594000001_ABST
Patent Text Reader

Abstract

To provide a cutting device and a cutting method capable of preventing spreading of powder dust formed when cutting a concrete member.SOLUTION: A wire saw 5 is configured to cut a concrete floor slab 22 by being passed through an inside of a core hole 222 formed in the concrete floor slab 22 (concrete member). A dust collection section 4 has: a suction nozzle 43 installed inside the core hole 222; and a dust collecting machine 41 connected with the suction nozzle 43 and suctioning powder dust inside the core hole 222 via the suction nozzle 43.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a cutting device and a cutting method. [Background technology]

[0002] In a composite girder in which the steel girder and the concrete deck are joined together with a slip stopper, the concrete deck cannot be removed by peeling it off from the steel girder by jacking up when replacing the concrete deck. For this reason, when removing the concrete deck of an existing composite girder, the part of the concrete deck directly above the steel girder (the deck above the girder) is cut with a cutting device equipped with a loop-shaped wire saw (for example, see Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2019-31868 A Summary of the Invention [Problem to be solved by the invention]

[0004] When cutting concrete components such as concrete floor slabs with a wire saw, the generated dust must be collected and disposed of to prevent it from scattering into the surrounding area.

[0005] Therefore, an object of the present invention is to provide a cutting device and a cutting method that can prevent dust generated when cutting a concrete member with a wire saw from scattering into the surrounding area. [Means for solving the problem]

[0006] In order to achieve the above-mentioned object, the cutting device of the present invention has a cutting unit that cuts concrete members and a dust collection unit that collects dust generated during cutting, the cutting unit having a plurality of pulleys and a wire saw that is wound around the plurality of pulleys and rotates in a circular motion, the wire saw being configured to cut the concrete member by passing through the inside of a core hole formed in the concrete member, and the dust collection unit having a suction nozzle installed inside the core hole and a dust collector connected to the suction nozzle and sucking up dust inside the core hole via the suction nozzle.

[0007] In order to achieve the above-mentioned object, the cutting method of the present invention comprises a cutting process of cutting the concrete member with a wire saw that passes inside a core hole formed in the concrete member, and a dust collection process of collecting dust inside the core hole with a dust collection device, the dust collection device having a suction nozzle installed inside the core hole and a dust collector connected to the suction nozzle and sucking up dust inside the core hole through the suction nozzle, and the cutting process is performed while the dust collection process is being performed.

[0008] In the present invention, the concrete component can be cut with the wire saw while sucking in and collecting dust inside the core hole through which the wire saw passes, thereby preventing dust generated when cutting the concrete component from leaking out of the core hole and scattering around.

[0009] Moreover, the cutting device according to the present invention may have a lid portion that closes an open end of the core hole, and the suction nozzle may be disposed inside the core hole, penetrating the lid portion.

[0010] In the cutting method according to the present invention, in the dust collecting step, an open end of the core hole may be closed with a lid, and the suction nozzle may be disposed inside the core hole by penetrating the lid.

[0011] With this configuration, it is possible to more reliably prevent dust generated when cutting the concrete member from leaking out of the core hole and scattering into the surrounding area.

[0012] In addition, in the cutting device of the present invention, the multiple pulleys may include a core hole installation pulley installed inside the core hole, and the cover portion may have a through hole into which a support member supporting the core hole installation pulley is inserted.

[0013] With this configuration, even when a support member is provided, the open end of the core hole can be closed with the lid portion.

[0014] In addition, in the cutting device of the present invention, the wire saw is configured to cut the concrete member through the inside of the core hole and a groove formed in the concrete member and continuing into the inside of the core hole, and may have a sealing material that seals the open end of the groove.

[0015] In addition, in the cutting method of the present invention, in the cutting process, the concrete member is cut with a wire saw that passes through the inside of the core hole and a groove formed in the concrete member and continuous with the core hole, and in the dust collection process, the open end of the groove is blocked with a blocking material and dust inside the groove is sucked in through the inside of the core hole.

[0016] With this configuration, when a groove through which the wire saw passes is provided in the concrete member, dust inside the groove is sucked in through the core hole, preventing dust generated when cutting the concrete member from leaking out of the groove and scattering around. Effect of the Invention

[0017] According to the present invention, it is possible to prevent dust generated when cutting a concrete member from scattering around. [Brief description of the drawings]

[0018] [Figure 1] FIG. 2 is a side view of a cutting device according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a plan view of a cutting device according to an embodiment of the present invention. [Diagram 3] FIG. [Figure 4] FIG. 2 is a side view of the cutting device in a state where the wire saw is pulled toward the cutting device in the first cutting step. [Diagram 5] FIG. 2 is a plan view of the cutting device with the wire saw pulled toward it in a first cutting step. [Figure 6] FIG. 11 is a diagram illustrating a second cutting step. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0019] Hereinafter, a cutting device and a cutting method according to an embodiment of the present invention will be described with reference to Figs. The cutting device 1 according to this embodiment shown in Figures 1 and 2 is used to cut and remove the concrete floor slab 22 from a composite girder 2 in which a steel girder 21 and a concrete floor slab 22 are joined together to form an integrated structure. The concrete floor slab 22 corresponds to the "concrete member" in the claims. As shown in Fig. 3, the composite girder 2 has a concrete deck 22 joined onto multiple steel girders 21 arranged in parallel at intervals. A shear stopper 23 is joined to the upper surface of the steel girders 21 to integrate the multiple steel girders 21 and the concrete deck 22. The direction in which the composite girder 2 extends, i.e., the direction in which the steel girder 21 extends, is referred to as the girder axis direction (the direction of the arrow A in the figure). In this embodiment, the girder axis direction is a substantially horizontal direction. The horizontal direction perpendicular to the girder axis direction is referred to as the girder axis perpendicular direction (the direction of the arrow B in the figure).

[0020] The steel girders 21 are made of I-beams or the like and are provided at intervals in a direction perpendicular to the girder axis. The concrete floor slab 22 has a haunch portion 221 that protrudes downward directly above the steel girder 21. The lower surface of the haunch portion 221 is joined to the upper surface of the steel girder 21. The dimension of the haunch portion 221 in the direction perpendicular to the girder axis gradually decreases downward. The portion of the concrete floor slab 22 that is joined to the steel girder 21 directly above the steel girder 21 is referred to as a girder floor slab 24. The portion of the concrete floor slab 22 that does not overlap with the steel girder 21 in the vertical direction and is not directly joined to the steel girder 21 is referred to as an inter-girder floor slab 25. The girder floor slabs 24 and the inter-girder floor slabs 25 are arranged alternately in the direction perpendicular to the girder axis. Between the boundary with the girder deck 24 on the underside of the inter-girder deck 25 and a nearby position 221a, an inclined surface 221b of the haunch portion 221 is formed which gradually ascends upward from the boundary with the girder deck 24 toward the side away from the girder deck 24 (see Figure 6).

[0021] In this embodiment, it is assumed that the girder deck 24 is cut by the cutting device 1 at every predetermined span 26 in the girder axis direction shown in Fig. 2 and separated from the steel girder 21. Each of the two girder decks 24, 24 adjacent to each other in the direction perpendicular to the girder axis is separated from the steel girder 21 while still connected to the inter-girder deck 25 between them, and these girder decks 24, 24 and the inter-girder deck 25 between them are removed as a unit while still connected. For this reason, the inter-girder deck 25 alone is not separated and removed from the concrete deck 22 before the girder deck 24 is separated from the steel girder 21 as in the conventional method.

[0022] When separating the girder deck 24 from the steel girder 21, the girder deck 24 is cut from one side to the other in the direction perpendicular to the girder axis by the wire saw 5 of the cutting device 1 for each predetermined span 26 in the girder axial direction. The predetermined span 26 in the girder axial direction when cutting the girder deck 24 is the span in the girder axial direction that the cutting device 1 can cut at one time. To prevent the wire saw 5 cutting the girder deck 24 from damaging the steel girder 21, the girder deck 24 is cut at a cutting position 27 (see Figures 2 and 4) above the upper surface of the steel girder 21. A portion 28 of the girder deck 24 below the cutting position 27 is chipped off and removed using a water jet device or the like. The cutting position 27 is, for example, 2 cm above the upper surface of the steel girder 21. The cutting position 27 is at the height where the shear stopper 23 is provided. The cutting device 1 of this embodiment is capable of cutting the shear stopper 23 as well as the concrete deck 22.

[0023] When cutting the concrete floor slab 22 with the cutting device 1, a pair of core holes 222, 222, a pair of slits 223, 223 in the girder axis orthogonal direction, and a girder axial direction slit 224 are formed in the concrete floor slab 22. A first movable pulley 61 and a second movable pulley 62 of the cutting device 1 are installed in the pair of core holes 222, 222. A wire saw 5 of the cutting device 1 is installed in the pair of slits 223, 223 in the girder axis orthogonal direction and the girder axial direction slit 224.

[0024] As shown in Figs. 1 and 2, the pair of core holes 222, 222 are holes that penetrate the inter-girder floor slab 25 in the up-down direction. The pair of core holes 222, 222 are arranged with a gap in the girder axis direction. The pair of core holes 222, 222 are formed in the inter-girder floor slab 25 located on the other side of the area to be cut in the concrete floor slab 22 in the direction perpendicular to the girder axis. The core hole 222 is formed from above the concrete floor slab 22. The first swivel pulley 61 and the second swivel pulley 62 of the cutting device 1 are inserted into the core holes 222, 222 from above.

[0025] The pair of girder axis orthogonal slits 223, 223 are grooves extending in the girder axis orthogonal direction. The pair of girder axis orthogonal slits 223, 223 are formed over the entire girder axis orthogonal direction of the concrete floor slab 22. The portion of the pair of girder axis orthogonal slits 223, 223 formed in the inter-girder floor slab 25 penetrates the inter-girder floor slab 25 in the vertical direction. The portion of the pair of girder axis orthogonal slits 223, 223 formed in the girder floor slab 24 is a groove that does not penetrate the girder floor slab 24 in the vertical direction and opens upward. The bottom of the portion of the pair of girder axis orthogonal slits 223, 223 formed in the girder floor slab 24 is located below the cutting position 27. The core hole 222 and the girder axis orthogonal slit 223 are continuous.

[0026] The girder axial direction slit 224 is a groove portion that extends in the girder axial direction and opens downward from the lower end of the concrete floor slab 22 to the height of the cutting position 27. The girder axial direction slit 224 is located between a pair of girder axis orthogonal direction slits 223, 223 and is connected to each of the pair of girder axis orthogonal direction slits 223, 223. In this embodiment, the girder axial direction slit 224 is formed in the haunch portion 221 that is located on one side of the region to be cut in the concrete floor slab 22 in the girder axis orthogonal direction. The girder axial direction slit 224 is formed from below the concrete floor slab 22.

[0027] As shown in Figures 1 and 2, the cutting device 1 has a cutting unit 3 and a dust collection unit 4 (dust collection device). The cutting unit 3 cuts the concrete floor slab 22. The dust collection unit 4 collects dust generated when the cutting unit 3 cuts the concrete floor slab 22. In Figure 2, only the upper cover unit 44 of the dust collection unit 4 is shown.

[0028] The cutting unit 3 has a loop-shaped wire saw 5, a plurality of pulleys 6 around which the wire saw 5 is wound, a pulley support unit 31 that supports the plurality of pulleys 6, and a drive unit 32 that rotates the pulleys 6 to drive the wire saw 5. The cutting device 1 is capable of pulling the rotating wire saw 5 in the horizontal direction to cut the concrete floor slab 22 horizontally, and is also capable of cutting the concrete floor slab 22 by moving it from above to below. The horizontal direction in which the wire saw 5 is pulled when the cutting device 1 cuts the concrete floor slab 22 is referred to as the front-rear direction. The horizontal direction perpendicular to the front-rear direction is referred to as the width direction. In this embodiment, the cutting device 1 cuts the concrete floor slab 22 in an orientation in which the width direction is the girder axis direction (the direction of arrow A in the figure) and the front-rear direction is the direction perpendicular to the girder axis (the direction of arrow B in the figure).

[0029] The pulley support 31 is installed on the concrete floor slab 22. The pulleys 6 include a pair of swivel pulleys 61, 62 (core hole installed pulleys), a drive pulley 63, a lift pulley, and a plurality of auxiliary pulleys. The tension pulley and the auxiliary pulleys are not shown. The drive pulley 63, the lift pulley and the multiple auxiliary pulleys are arranged in the same vertical plane facing in the front-rear direction, with their respective rotation axes extending in the front-rear direction. The drive pulley 63 is connected to the drive unit 32. The drive pulley 63 rotates by the power of the drive unit 32, and rotates the wire saw 5 in a circular motion. The lifting pulley is supported by the pulley support unit 31 so as to be movable in the vertical direction. The lifting pulley moves the cutting portion 51 of the wire saw 5 by moving in the vertical direction. The cutting portion 51 will be described later. The multiple auxiliary pulleys are appropriately positioned on the trajectory of the circular rotation of the wire saw 5.

[0030] The pair of movable pulleys 61, 62 are provided below both widthwise ends 311, 312 of the pulley support part 31. In this embodiment, a pair of movable pulley support members 33, 34 (support members) that support the movable pulleys 61, 62 are provided at both widthwise ends 311, 312 of the pulley support part 31. The pair of movable pulley support members 33, 34 are rod-shaped members. The pair of movable pulley support members 33, 34 are installed in a position in which axes 331, 341 extend in the vertical direction. The first and second movable pulley support members 33 and 34 are disposed at an interval in the width direction. The drive pulley 63 and the multiple auxiliary pulleys are provided in a widthwise intermediate portion 313 of the pulley support part 31, which is an area between the pair of movable pulley support members 33, 34. Of the pair of movable pulley support members 33, 34, one provided at an end portion 311 on one side in the width direction of the pulley support part 31 is referred to as the first movable pulley support member 33, and the other provided at an end portion 312 on the other side in the width direction of the pulley support part 31 is referred to as the second movable pulley support member 34.

[0031] The first swivel pulley 61, which is one of the pair of swivel pulleys 61, 62, is attached to the lower end of the first swivel pulley support member 33 so as to be rotatable around the axis 331 of the first swivel pulley support member 33. The rotation axis 65 of the first swivel pulley 61 extends in the horizontal direction. The rotation axis 65 of the first swivel pulley 61 and the axis 331 of the first swivel pulley support member 33 do not intersect. The second swivel pulley 62, which is the other of the pair of swivel pulleys 61, 62, is attached to the lower end of the second swivel pulley support member 34 so as to be rotatable around the axis 341 of the second swivel pulley support member 34. The rotation axis 65 of the second swivel pulley 62 extends in the horizontal direction. The rotation axis 65 of the second swivel pulley 62 and the axis 341 of the second swivel pulley support member 34 do not intersect. The first swivel pulley 61 and the second swivel pulley 62 are disposed at the same height. The first swivel pulley 61 and the second swivel pulley 62 are disposed below the drive pulley 63, the lift pulley, and the auxiliary pulley. As described above, the first swivel pulley 61 and the second swivel pulley 62 are each installed in the core hole 222.

[0032] The wire saw 5 is sent out by the rotation of the drive pulley 63, passes through the first swivel pulley 61 and the second swivel pulley 62 in this order, and performs a circular rotation returning to the drive pulley 63. The lifting pulley and the auxiliary pulley are appropriately provided between the drive pulley 63 and the first swivel pulley 61, and between the second swivel pulley 62 and the drive pulley 63. The wire saw 5 cuts the concrete floor slab 22 between the first swivel pulley 61 and the second swivel pulley 62. The portion of the wire saw 5 that rotates circulatingly between the first swivel pulley 61 and the second swivel pulley 62 is referred to as a cutting portion 51.

[0033] The wire saw 5 has the cutting portion 51 pulled out forward of the first swivel pulley 61 and the second swivel pulley 62 and wrapped around the portion of the concrete floor slab 22 to be cut. As the wire saw 5 rotates in a circular motion, the lifting pulley is raised and lowered to pull the cutting portion 51 rearward, moving the cutting portion 51 from the front side to the rear side, and the concrete floor slab 22 is cut. 2, the cutting portion 51 has a C-shape that opens rearward when viewed from the top-bottom direction. The cutting portion 51 extends forward from each of the first swivel pulley 61 and the second swivel pulley 62, and extends in the width direction forward of the first swivel pulley 61 and the second swivel pulley 62. The portion of the cutting portion 51 that extends in the width direction forward of the first swivel pulley 61 and the second swivel pulley 62 mainly cuts the concrete floor slab 22.

[0034] As shown in Figures 1 and 2, when the cut portion 51 extends forward of the first swivel pulley 61 and the second swivel pulley 62, the first swivel pulley 61 and the second swivel pulley 62 are in a position in which the rotating shaft 65 extends in the width direction forward of the axes 331, 341 of the first swivel pulley support member 33 and the second swivel pulley support member 34. As shown in Figures 4 and 5, when the cutting portion 51 moves rearward and is located between the first and second swivel pulleys 61 and 62, the first and second swivel pulleys 61 and 62 rotate about the axes 331 and 341 of the first and second swivel pulley support members 33 and 34, respectively, and their front ends approach each other and move rearward. Since the first and second swivel pulleys 61 and 62 are rotatable about the axes 331 and 341 of the first and second swivel pulley support members 33 and 34, the cutting portion 51 can be pulled further rearward. In Figure 4, the portion cut by the wire saw 5 is indicated by reference numeral 225.

[0035] The first swivel pulley 61 and the second swivel pulley 62 can each be raised and lowered relative to the pulley support portion 31. The first swivel pulley support member 33 and the second swivel pulley support member 34 are raised and lowered relative to the pulley support portion 31, thereby causing the first swivel pulley 61 and the second swivel pulley 62 to be raised and lowered relative to the pulley support portion 31. Therefore, the concrete floor slab 22 can be lowered by lowering the first swivel pulley 61 and the second swivel pulley 62.

[0036] A method for cutting the concrete slab 22 will now be described. First, a core hole forming process is performed to form a pair of core holes 222, 222 in the concrete floor slab 22, a girder axis perpendicular direction slit forming process is performed to form a pair of girder axis perpendicular direction slits 223, 223, and a girder axis direction slit forming process is performed to form a girder axis direction slit 224. In this embodiment, before or after these steps, a confirmation hole forming step is performed in which a confirmation hole 29 is formed in the boundary between the upper girder deck 24 and the inter-girder deck 25 in the concrete deck 22, extending in the vertical direction from the upper surface of the concrete deck 22 to the cutting position 27. The confirmation hole 29 is, for example, a round hole with a diameter of about 25 mm to 50 mm. The confirmation hole 29 is formed in a position where the flange end of the steel girder 21 can be confirmed near the center in the girder axial direction of the area to be cut. Note that multiple confirmation holes 29 may be formed at intervals in the girder axial direction.

[0037] Next, the cutting device 1 is installed on the concrete deck 22. A first movable pulley 61 and a second movable pulley 62 are installed in the pair of core holes 222, 222. The wire saw 5 of the cutting device 1 is installed in the pair of girder axis orthogonal direction slits 223, 223 and the girder axial direction slit 224. After installing the wire saw 5, a filler material such as wood may be installed in the girder axial direction slit 224 to prevent the wire saw 5 from being unable to maintain the correct position due to sagging or the like. Next, a first cutting step is performed in which the girder deck 24 is cut horizontally by the cutting section 3, and then a second cutting step is performed in which the girder deck 24 is continuously cut down.

[0038] In the first cutting step, the drive pulley 63 is driven and the lifting pulley is raised and lowered to draw the cutting portion 51 of the wire saw 5 toward the pulley support portion 31. As a result, the cutting portion 51 moves from one side to the other side in the direction perpendicular to the girder axis, and the girder upper deck 24 of the concrete deck 22 is cut into the upper and lower parts. When the inside of the confirmation hole 29 is checked from above and it is confirmed that the cutting portion 51 of the wire saw 5 has crossed the confirmation hole 29, it can be confirmed that the wire saw 5 has moved from the girder deck 24 to the inter-girder deck 25. Immediately after crossing the confirmation hole 29, the cutting portion 51 of the wire saw 5 is located above the inclined surface 221b of the haunch portion 221 in the inter-girder deck 25. The wire saw 5 checks the inside of the confirmation hole 29, and once it is confirmed that it has moved from the girder deck 24 to the inter-girder deck 25, the second cutting process is started.

[0039] In the second cutting step, the first swivel pulley 61 and the second swivel pulley 62 are moved downward. As a result, the cutting portion 51 of the wire saw 5 gradually moves downward in a diagonal direction toward the other side in the direction perpendicular to the girder axis. By further moving the first swivel pulley 61 and the second swivel pulley 62 downward, the cutting portion 51 of the wire saw 5 moves below the inter-girder floor slab 25 so as to cut the inclined surface 221b of the haunch portion 221, and cuts (cuts down) the concrete floor slab 22. As a result, the concrete floor slab 22 is separated from the steel girder 21.

[0040] 1 sucks up dust generated when cutting the concrete floor slab 22 through each of a pair of core holes 222. The dust collecting unit 4 is attached to each of the pair of core holes 222. The dust collecting unit 4 sucks up dust inside the core holes 222. The dust collector 4 has a dust collector 41 having a suction function, a hose 42 connected to the dust collector 41, a suction nozzle 43 provided at the tip of the hose 42, an upper cover 44 that closes the upper opening end 222a of the core hole 222, a lower cover 45 that closes the lower opening end 222b of the core hole 222, and a closing material 46 that closes the upper end portions (opening ends 223a) of each of the pair of girder axis orthogonal direction slits 223, 223. In this embodiment, two sets of the dust collector 41, the hose 42, and the suction nozzle 43 are provided for one core hole 222.

[0041] The upper cover 44 and the lower cover 45 are each formed with nozzle insertion holes 441, 451 that penetrate in the vertical direction and allow the suction nozzle 43 to be inserted. The tip of the suction nozzle 43 inserted into the nozzle insertion hole 441 of the upper cover 44 and the tip of the suction nozzle 43 inserted into the nozzle insertion hole 451 of the lower cover 45 are each disposed inside the core hole 222. The upper cover 44 is formed with a support member insertion hole 442 (through hole) into which the first swivel pulley support member 33 or the second swivel pulley support member 34 is inserted. The first swivel pulley 61 and the second swivel pulley 62 are disposed below the upper cover 44. An upper cover portion 44 is provided above the core hole 222, and a lower cover portion 45 is provided below the core hole 222, thereby preventing dust inside the core hole 222 from leaking out above and below the core hole 222. The upper cover 44 and the lower cover 45 may be composed of a plurality of divided plate members divided at the portions where the nozzle insertion holes 441, 451 and the support member insertion holes 442 are formed. In this way, by placing the divided plate members of the upper cover 44 and the lower cover 45 from both sides so as to sandwich the suction nozzle 43 and the movable pulley support members 33, 34, the suction nozzle 43 and the movable pulley support members 33, 34 can be made to pass through the nozzle insertion holes 441, 451 and the support member insertion holes 442.

[0042] The blocking material 46 is, for example, a rubber packing that is inserted into the upper end portion of the girder-axis orthogonal slit 223. The blocking material 46 is provided over the entire length direction (beam-axis orthogonal direction) of the girder-axis orthogonal slit 223. By providing a blocking material 46 at the upper end portion of the girder axis orthogonal slit 223, dust inside the girder axis orthogonal slit 223 is prevented from leaking out above the girder axis orthogonal slit 223.

[0043] In the cutting method according to the present embodiment, when the cutting unit 3 performs the first cutting step and the second cutting step for cutting the concrete floor slab 22, the dust collecting unit 4 performs the dust collecting step for collecting dust inside the core hole 222. In the dust collection process, the dust collector 41 is driven to suck in the air inside the core hole 222. By sucking in the air inside the core hole 222 with the dust collector 41, dust generated in the cutting process is also sucked into the dust collector 41. By sucking in the air inside the core hole 222 with the dust collector 41, internal dust in the girder axis orthogonal slit 223 that is continuous with the core hole 222 is also sucked into the dust collector 41 through the core hole 222.

[0044] Next, the operation and effect of the cutting device 1 and cutting method according to the present embodiment will be described. In the cutting device 1 according to this embodiment, the open ends 222a, 222b of the core hole 222 are blocked by the upper cover portion 44 and the lower cover portion 45, and the open end 223a of the girder axis orthogonal slit 223 connected to the core hole 222 is blocked by the blocking material 46. The dust in the core hole 222 and the girder axis orthogonal slit 223 can be collected by sucking the dust in the core hole 222 with the dust collector 41. By cutting the concrete floor slab 22 with the wire saw 5 while collecting the dust inside the core hole 222 and the girder axis orthogonal slit 223 through which the wire saw 5 for cutting the concrete floor slab 22 passes, it is possible to prevent the dust generated when cutting the concrete floor slab 22 from leaking out of the core hole 222 and the girder axis orthogonal slit 223 and scattering around.

[0045] Although the embodiments of the cutting device and cutting method according to the present invention have been described above, the present invention is not limited to the above-mentioned embodiments and can be modified as appropriate without departing from the spirit of the present invention. For example, in the above embodiment, the wire saw 5 of the cutting unit 3 is moved in a direction perpendicular to the girder axis to cut the concrete floor slab 22, but when the wire saw 5 of the cutting unit 3 is moved in the girder axial direction to cut the concrete floor slab 22, the dust generated by cutting may be collected by the dust collection unit 4.

[0046] In the above embodiment, the core hole 222 penetrates the concrete floor slab 22 in the vertical direction, but may be a recessed shape that opens upward without penetrating the concrete floor slab 22. In such a case, the dust collector 4 may have a configuration including a lid that covers only the upper side of the core hole 222, a suction nozzle 43 that is inserted into the core hole 222 from the lid, and a hose 42 and a dust collector 41 that are connected to the suction nozzle 43.

[0047] In the above embodiment, the open ends 222a, 222b of the core hole 222 are blocked by the upper cover 44 and the lower cover 45, but depending on the state of dust generated in the core hole 222 and the girder axis orthogonal slit 223, it is not necessary to block either the upper or lower side of the open ends 222a, 222b or both. Even in such a situation, if the dust collector 41 can sufficiently collect and suck the dust, the dust is unlikely to scatter to the surroundings, and the state of the dust collection and the state of the cut surface end of the wire saw 5 can be easily checked visually at all times. Also, the blocking material 46 at the open end 223a (upper end portion) of the girder axis orthogonal slit 223 may be omitted.

[0048] In the above embodiment, the cutting device 1 is used to cut the concrete floor slab 22, but a concrete member other than the concrete floor slab 22 may also be cut. In the above embodiment, the shear stoppers 23 joined to the multiple steel girders 21 are cut together with the concrete floor slab 22, but the concrete floor slab 22 may be cut in a manner that avoids the shear stoppers 23.

[0049] In the above embodiment, the cutting device 1 has a function of cutting down the concrete floor slab 22, but it does not have to have such a function. In the step of cutting down the concrete floor slab 22, a device other than the cutting device 1 may be used. In the above embodiment, a confirmation hole 29 is formed at the boundary between the upper girder deck 24 and the inter-girder deck 25 in the concrete deck 22, and the second cutting step is performed after the wire saw 5 passes inside the confirmation hole 29, but it is not necessary to form such a confirmation hole 29.

[0050] In the above embodiment, the pulleys installed in the core hole 222 are free-moving pulleys 61, 62 that can rotate around the axis 35 of the free-moving pulley support members 33, 34, but they may also be pulleys that do not rotate around the axis 35 of the free-moving pulley support members 33, 34.

[0051] The Sustainable Development Goals (SDGs) are among the 17 international goals adopted at the United Nations Summit in September 2015. The cutting device according to this embodiment can contribute to achieving one of the 17 SDGs goals, for example goal 12. Responsible Consumption and Production. [Explanation of symbols]

[0052] 1 cutting device 2 Composite digits 3 Cut section 4 Dust collection section (dust collection device) 5 Wire saw 6 Pulley 21 Steel girder 22 Concrete floor slab (concrete member) 33, 34 Free pulley support member (support member) 41 Dust collector 42 Hose 43 Suction nozzle 44 Top cover 45 Lower lid part 46 Sealing material 61,62 Free pulley (core hole installation pulley) 222 Core hole 222a,222b Open end 223,223 Girder axis perpendicular slit (groove) 223a Open end 441,451 Nozzle insertion hole 442 Support member insertion hole (through hole)

Claims

1. A cutting unit that cuts the concrete member; A dust collecting section that collects dust generated during cutting, The cutting portion is A plurality of pulleys; A wire saw that is wound around the pulleys and rotates cyclically, The wire saw is configured to cut the concrete member through a core hole formed in the concrete member, The dust collection unit is a suction nozzle disposed inside the core hole; a dust collector connected to the suction nozzle for sucking dust inside the core hole through the suction nozzle.

2. a cover portion for closing an open end of the core hole; The cutting device according to claim 1 , wherein the suction nozzle penetrates the lid and is disposed inside the core hole.

3. The plurality of pulleys includes a core hole installation pulley installed inside the core hole, The cutting device according to claim 2 , wherein the cover portion has a through hole into which a support member for supporting the core hole installation pulley is inserted.

4. the wire saw is configured to cut the concrete member through an interior of the core hole and a groove portion formed in the concrete member and continuing to the interior of the core hole; The cutting device according to claim 1 , further comprising a plugging material for plugging an open end of the groove.

5. a cutting step of cutting the concrete member with a wire saw passing through an inside of a core hole formed in the concrete member; A dust collecting step of collecting dust inside the core hole with a dust collecting device, The dust collecting device includes: a suction nozzle disposed inside the core hole; a dust collector connected to the suction nozzle and configured to suck dust inside the core hole through the suction nozzle; The cutting method, wherein the cutting step is carried out while the dust collecting step is being carried out.

6. In the dust collection process, The open end of the core hole is closed with a lid portion; The cutting method according to claim 5 , wherein the suction nozzle is disposed inside the core hole by penetrating the lid portion.

7. In the cutting step, the concrete member is cut with a wire saw passing through an inside of the core hole and a groove portion formed in the concrete member and continuing to the core hole, 7. The cutting method according to claim 5, wherein in the dust collecting step, an open end of the groove is blocked with a blocking material, and dust inside the groove is sucked through the inside of the core hole.