Construction work estimate preparation system using unmanned aircraft, construction work estimate preparation method using unmanned aircraft, and construction work estimate preparation program using unmanned aircraft
The construction work estimate system using UAVs integrates building material costs into the estimate process, enhancing workability and accuracy by calculating material needs and costs, addressing the limitations of existing systems.
Patent Information
- Application Number
- JP2024078113
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-05-18
- Filing Date
- 2024-05-13
- Publication Date
- 2024-11-28
- Estimated Expiration
- 2044-05-13
AI Technical Summary
Existing construction work estimate systems using unmanned aerial vehicles (UAVs) do not adequately address the integration of building material costs, leading to incomplete estimates and reduced workability in assessing building repairs.
A construction work estimate system using an UAV that includes a construction scope acquisition unit, a building material information acquisition unit, a building material parts calculation unit, and a database linking building material identification information with unit prices to calculate the required materials and costs for construction work.
The system improves workability and accuracy of construction estimates by integrating building material costs into the estimate process, allowing for reliable confirmation of repair needs and efficient calculation of construction costs based on external appearance information.
Smart Images

Figure 2024166121000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction work estimate preparation system using an unmanned aerial vehicle, which is used particularly when estimating and carrying out repairs (including repairs and renovations) on buildings at high altitudes, a construction work estimate preparation method using an unmanned aerial vehicle, and a construction work estimate preparation program using an unmanned aerial vehicle. [Background technology]
[0002] In the past, construction workers had to work at heights to determine whether or not repairs were necessary on the roof or walls of a building. In recent years, the use of unmanned aerial vehicles (drones) has made it possible to photograph the exterior of roofs and walls, eliminating the need for manual work at heights, and dramatically improving safety and workability when estimating and carrying out repairs.
[0003] Patent Document 1 discloses a system for taking an image of a roof of a building in order to prepare an estimate for painting or waterproofing work on the roof. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2018-55351 A Summary of the Invention [Problem to be solved by the invention]
[0005] According to the system disclosed in Patent Document 1, it is possible to create an accurate and inexpensive estimate for roof painting or waterproofing work. However, the system disclosed in Patent Document 1 does not particularly disclose the cost of construction of building materials, and there is a problem that the workability of estimating building repairs, etc. cannot be improved because the construction cost must be considered separately.
[0006] The present invention has been devised in consideration of the above-mentioned problems, and its object is to provide a construction work estimate preparation system using an unmanned aerial vehicle, a construction work estimate preparation method using an unmanned aerial vehicle, and a construction work estimate preparation program using an unmanned aerial vehicle that can improve workability in estimating building repairs, etc. [Means for solving the problem]
[0007] A construction work estimate creation system using an unmanned aerial vehicle according to a first invention is a construction work estimate creation system using an unmanned aerial vehicle that creates an estimate for new construction work on an existing building using an unmanned aerial vehicle, the system comprising: a construction scope acquisition unit that acquires a construction scope of the construction work specified from appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle; a building material information acquisition unit that acquires identification information of building materials to be used in the construction work specified by a user; the construction scope acquired by the construction scope acquisition unit; and the identification information of the building materials acquired by the building material information acquisition unit. a unit price acquisition unit that refers to a database in which identification information of building materials is linked in advance to the unit price of the building material and the unit price of construction, and acquires from the database the unit price of the building material and the unit price of construction corresponding to the identification information of the building material acquired by the building material information acquisition unit; and a construction work amount output unit that outputs a construction work amount corresponding to the number of pieces of the building material calculated by the building material number calculation unit and the unit price of the building material and the unit price of the construction acquired by the unit price acquisition unit.
[0008] The second invention is a construction work estimate creation system using an unmanned aerial vehicle, which is characterized in that in the first invention, the building material information acquisition unit acquires the characteristics of the building materials to be used in the construction work specified by the user, and refers to a database in which the characteristics of the building materials are pre-linked to identification information of the building materials, and then acquires identification information of the building materials corresponding to the acquired characteristics of the building materials from the database.
[0009] The construction work estimate creation system using an unmanned aerial vehicle in the third invention is characterized in that, in the second invention, the construction scope acquisition unit further acquires the construction area of the construction work specified by the user, and the building material information acquisition unit refers to a database in which the characteristics and construction area of building materials are pre-linked to identification information of the building materials, and acquires from the database the identification information of the building materials corresponding to the characteristics and construction area of the building materials acquired by the construction scope acquisition unit.
[0010] The construction work estimate creation system using an unmanned aerial vehicle in the fourth invention is characterized in that, in the first invention, the construction scope acquisition unit further acquires the construction area of the construction work specified by the user, and the unit price acquisition unit refers to a database in which identification information of building materials and the construction area are pre-linked to the unit price of construction, and acquires from the database the unit price of the construction corresponding to the identification information of the building materials acquired by the building material information acquisition unit and the construction area acquired by the construction scope acquisition unit.
[0011] The construction work estimate creation system using an unmanned aerial vehicle in the fifth invention is any one of the first to fourth inventions, further comprising: an unmanned aerial vehicle; a shooting range acquisition unit that acquires a planar shooting range of the unmanned aerial vehicle; a flight path generation unit that generates a horizontal flight path of the unmanned aerial vehicle based on the shooting range acquired by the shooting range acquisition unit; a shooting condition acquisition unit that acquires the shooting altitude and the number of shots in the shooting range acquired by the shooting range acquisition unit; a shooting operation identification unit that identifies the shooting operation on the flight path based on the number of shots acquired by the shooting condition acquisition unit; and an operation control unit that controls the flight operation of the unmanned aerial vehicle based on the flight path generated by the flight path generation unit and the shooting altitude acquired by the shooting condition acquisition unit, and controls the shooting operation of the unmanned aerial vehicle based on the shooting operation identified by the shooting operation identification unit, and is characterized in that the construction range acquisition unit acquires the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle controlled by the operation control unit.
[0012] The construction work estimate creation system using an unmanned aerial vehicle in the 6th invention is characterized in that, in the 5th invention, the shooting range acquisition unit acquires the shooting range in a polygonal shape, and the flight path generation unit generates the flight path including a direction approximately perpendicular to the longest side of each side of the polygonal shooting range acquired by the shooting range acquisition unit.
[0013] The construction work estimate creation system using an unmanned aerial vehicle in the 7th invention is characterized in that, in the 5th invention, the operation control unit controls the operation of the unmanned aerial vehicle so that when the remaining charge of the battery installed in the unmanned aerial vehicle on the flight path generated by the flight path generation unit falls below a predetermined lower limit value, the unmanned aerial vehicle automatically retreats to the takeoff point, and then when the remaining charge of the battery reaches or exceeds a predetermined value, the unmanned aerial vehicle resumes photographing from the point on the flight path where the retreat began.
[0014] The construction work estimate creation system using an unmanned aerial vehicle in the 8th invention is characterized in that in the 5th invention, it further includes a server which can be controlled independently of the shooting range acquisition unit, the flight path generation unit, the shooting condition acquisition unit, the shooting operation identification unit, and the operation control unit, receives two-dimensional appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle via a wireless communication network, and acquires a three-dimensional modeling image showing the existing building based on the received two-dimensional appearance information.
[0015] The construction work estimate creation system using an unmanned aerial vehicle in the 9th invention is characterized in that in the 5th invention, it further comprises a server that receives exterior information showing the appearance of the existing building photographed by the unmanned aerial vehicle via a wireless communication network, and a transmission control unit that controls the transmission of the exterior information to the server.
[0016] The construction work estimate creation system using an unmanned aerial vehicle of the 10th invention is characterized in that, in the 5th invention, it further includes an authentication unit that certifies that the approval information corresponding to the unmanned aerial vehicle is valid by referring to a database that links unmanned aerial vehicle identification information that identifies the unmanned aerial vehicle with approval information indicating flight permission for the unmanned aerial vehicle in DIPS (Drone / UAS Information Platform System) or FISS (Flight Information Sharing System), and the operation control unit controls the operation of the unmanned aerial vehicle after the authentication unit certifies that the approval information is valid.
[0017] The construction work estimate creation system using an unmanned aerial vehicle in the 11th invention is characterized in that, in the 5th invention, it further includes a calculation unit that calculates the number of photographs based on the photographing altitude or the photographing altitude based on the number of photographs, and the photographing condition acquisition unit first acquires either the number of photographs or the photographing altitude, and then acquires the other one calculated by the calculation unit.
[0018] The construction work estimate creation system using an unmanned aerial vehicle in the 12th invention is characterized in that in the 5th invention, it further includes a calculation unit that calculates the shooting altitude based on the shooting interval of the unmanned aerial vehicle and a set overlap width that is preset as the overlap width at which the angles of view of the unmanned aerial vehicle at two adjacent points separated by the shooting interval overlap each other, and the shooting condition acquisition unit acquires the shooting interval and then acquires the shooting altitude calculated by the calculation unit.
[0019] A construction work estimate preparation method using an unmanned aerial vehicle in a thirteenth invention is a construction work estimate preparation method using an unmanned aerial vehicle for preparing an estimate for construction work on an existing building using an unmanned aerial vehicle, the method comprising: a construction scope acquisition step for acquiring a construction scope of the construction work specified from appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle; a building material information acquisition step for acquiring identification information of building materials to be used in the construction work specified by a user; the construction scope acquired by the construction scope acquisition step; and the identification information of the building materials acquired by the building material information acquisition step. a unit price acquisition step of acquiring the unit price of the building material and the unit price of construction work corresponding to the identification information of the building material acquired in the building material information acquisition step by referring to a database in which identification information of the building material, the unit price of the building material, and the unit price of construction work are linked in advance; and a construction work amount output step of outputting an amount of construction work corresponding to the number of pieces of the building material calculated in the building material number calculation step and the unit price of the building material and the unit price of construction work acquired in the unit price acquisition step.
[0020] A construction work estimate creation program using an unmanned aerial vehicle in a fourteenth invention is a construction work estimate creation program using an unmanned aerial vehicle for creating an estimate for construction work on an existing building using an unmanned aerial vehicle, the program comprising: a construction scope acquisition step for acquiring a construction scope of the construction work specified from appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle; a building material information acquisition step for acquiring identification information of building materials to be used in the construction work specified by a user; and a construction scope acquisition step for acquiring an estimate for the construction work from the construction scope acquired by the construction scope acquisition step and the identification information of the building materials acquired by the building material information acquisition step. The method is characterized in that the computer is caused to execute the following steps: a building material quantity calculation step for calculating the number of units of building materials to be used in the construction work; a unit price acquisition step for acquiring the unit price of the building material and the unit price of construction work corresponding to the identification information of the building material acquired in the building material information acquisition step by referring to a database in which identification information of the building material, the unit price of the building material, and the unit price of construction work are previously linked; and a construction work amount output step for outputting the construction work amount corresponding to the number of units of the building material calculated in the building material quantity calculation step, and the unit price of the building material and the unit price of construction work acquired in the unit price acquisition step. Effect of the Invention
[0021] According to the first to twelfth inventions, the construction work estimate creation system includes a construction material quantity calculation unit that calculates the number of pieces of building materials from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle and the identification information of the building materials specified by the user, and a construction work cost output unit that outputs the construction work cost according to the calculated number of pieces of building materials, the acquired unit price of the building materials, and the unit price of construction. Therefore, the construction work cost based on the exterior information showing the exterior of the existing building can be easily output. This can improve the workability of estimating repairs and the like of existing buildings.
[0022] According to the first to twelfth inventions, the construction area acquisition unit acquires the construction area of the building work from the exterior information photographed by the unmanned aerial vehicle. Therefore, compared to the case where a drawing or the like is used, the area and the situation where repairs are required can be confirmed more reliably. This improves the accuracy of estimates for repairs of existing buildings.
[0023] In particular, according to the second aspect of the present invention, the building material information acquisition unit acquires the characteristics of the building materials to be used in the construction work specified by the user, and acquires the identification information of the building materials from the database according to the acquired characteristics of the building materials. Therefore, by identifying the characteristics of the building materials, it is not necessary to take the time to grasp the identification information of the building materials. This can further improve the workability of estimating repairs and other work for existing buildings.
[0024] In particular, according to the third invention, the construction area acquisition unit further acquires the construction area of the construction work specified by the user, and the building material information acquisition unit acquires the identification information of the building material according to the acquired characteristics of the building material and the construction area from the database. Therefore, it is possible to easily output the construction work cost taking into account the circumstances of the building material caused by the construction area, such as regional characteristics. This further improves the workability of estimating the repairs of existing buildings.
[0025] In particular, according to the fourth aspect of the present invention, the construction area acquisition unit further acquires the construction area of the construction work specified by the user, and the unit price acquisition unit acquires the construction unit price corresponding to the acquired building material identification information and construction area from the database. Therefore, it is possible to easily output the construction cost taking into account the construction circumstances caused by the construction area, such as regional characteristics. This further improves the workability of estimating repairs to existing buildings.
[0026] In particular, according to the fifth aspect of the present invention, the construction work estimate creation system includes an operation control unit that controls the flight operation of the unmanned aerial vehicle based on the flight path generated based on the acquired shooting range and the acquired shooting altitude, and controls the shooting operation of the unmanned aerial vehicle based on the shooting operation specified based on the acquired number of shots. Therefore, by setting the shooting range to match the existing building, the entire existing building can be automatically photographed according to the generated flight path. This improves the workability of estimating repairs and other work for the existing building.
[0027] In particular, according to the sixth aspect of the present invention, the flight path generating unit generates a flight path including a direction substantially perpendicular to the longest side of the captured polygonal imaging range. This simplifies the process compared to flight path calculations based on a side other than the longest side, and allows the flight path to be generated efficiently. This improves the efficiency of estimates for repairs to existing buildings.
[0028] In particular, according to the seventh aspect of the present invention, the operation control unit automatically retreats the unmanned aerial vehicle to the takeoff point when the remaining battery charge falls below a preset lower limit on the flight path, and then resumes image capture from the point on the flight path where the retreat began when the remaining battery charge reaches a predetermined value or higher. This makes it possible to control the flight and image capture operations of the unmanned aerial vehicle for a longer period of time. This also makes it possible to improve the workability of estimating repairs, etc., even for larger existing buildings.
[0029] In particular, according to the eighth aspect of the present invention, the system further includes a server that is controllable independently of the operation control unit and receives two-dimensional appearance information photographed by the unmanned aerial vehicle and acquires a three-dimensional modeling image showing an existing building based on the received two-dimensional appearance information. In other words, the operation of the unmanned aerial vehicle can be controlled without waiting until a three-dimensional modeling image showing an existing building based on the two-dimensional appearance information is generated and acquired. Therefore, acquisition of the three-dimensional modeling image and photography of other existing buildings by the unmanned aerial vehicle can be performed in parallel. This can further improve the workability of estimating repairs and the like for existing buildings.
[0030] In particular, according to the ninth aspect of the present invention, the unmanned aerial vehicle further includes a server that receives the appearance information photographed by the unmanned aerial vehicle, and a transmission control unit that controls the transmission of the appearance information to the server. That is, the appearance information can be re-photographed and then transmitted, or multiple pieces of appearance information relating to multiple existing buildings can be transmitted collectively. Therefore, it is not necessary to wait to re-photograph the appearance information or to photograph other existing buildings until the transmission of the appearance information is completed due to line congestion caused by the transmission of large amounts of data. This can further improve the operability of estimating repairs, etc. of existing buildings. In addition, the number of data transmissions can be reduced by re-photographing the appearance information or transmitting multiple pieces of appearance information collectively. Furthermore, the waiting time until the transmission of the appearance information is completed can be shortened by moving within the range of short-distance wireless communication and transmitting data. This can further improve the operability of estimating repairs, etc. of existing buildings.
[0031] In particular, according to the tenth aspect of the present invention, the operation control unit controls the photographing operation of the unmanned aerial vehicle after the authentication unit authenticates that the approval information is valid. This makes it possible to easily and reliably check whether or not a flight permit for the unmanned aerial vehicle has been forgotten or has expired, and to avoid or prevent illegal acts by the user. This improves the accuracy of compliance with laws and regulations regarding the operation of unmanned aerial vehicles used to estimate repairs and other work on existing buildings.
[0032] In particular, according to the eleventh aspect of the present invention, the operation control unit controls the photographing operation of the unmanned aerial vehicle after either the number of photographs based on the acquired photographing altitude or the photographing altitude based on the acquired number of photographs is calculated. This automatically optimizes the number of photographs, reducing the system's communication capacity, storage capacity, and the effort required to check the photographed content. This further improves the workability of estimating repairs to existing buildings, etc.
[0033] In particular, according to the twelfth aspect of the invention, the unmanned aerial vehicle further includes a calculation unit that calculates the shooting altitude based on the shooting interval of the unmanned aerial vehicle and a preset overlap width, and the shooting condition acquisition unit acquires the shooting interval and then acquires the shooting altitude calculated by the calculation unit. That is, the shooting altitude is automatically calculated according to the preset overlap width (overlap value) by acquiring the shooting interval. Therefore, for a large existing building, it is possible to complete acquisition of appearance information with a minimum number of shootings (number of shots) while satisfying a predetermined overlap value, and since the data volume of the appearance information is reduced, the waiting time until the transmission of the appearance information is completed can be shortened. This can further improve the workability of estimating repairs and the like for existing buildings.
[0034] According to the thirteenth aspect of the present invention, the method for creating an estimate for construction work includes a step of calculating the number of pieces of building materials from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle and the identification information of the building materials specified by the user, and a step of outputting the construction work cost according to the calculated number of pieces of building materials, the acquired unit price of the building materials, and the unit price of construction. Therefore, the construction work cost based on the exterior information showing the exterior of the existing building can be easily output. This can improve the workability of estimating the repairs of the existing building.
[0035] According to the fourteenth aspect of the present invention, the construction work estimate creation program causes a computer to execute a construction material quantity calculation step of calculating the number of pieces of construction material from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle and the identification information of the construction material specified by the user, and a construction work cost output step of outputting the construction work cost according to the calculated number of pieces of construction material, the acquired unit price of the construction material, and the unit price of construction. Therefore, the construction work cost based on the exterior information showing the exterior of the existing building can be easily output. This can improve the workability of estimating the repairs of the existing building. [Brief description of the drawings]
[0036] [Figure 1]FIG. 1 is a schematic diagram showing an example of a construction work estimate creating system in the first embodiment. [Diagram 2] Figure 2(a) is a schematic diagram showing an example of the configuration of a control device that constitutes the construction work estimate preparation system in the first embodiment, and Figure 2(b) is a schematic diagram showing an example of the configuration of an unmanned aerial vehicle that constitutes the construction work estimate preparation system in the first embodiment. [Diagram 3] FIG. 3 is a schematic diagram showing an example of the detailed configuration of the control device and the unmanned aerial vehicle that constitute the construction work estimate creation system in the first embodiment. [Figure 4] FIG. 4 is a flowchart showing an example of an operation method of the construction work estimate preparation system in the first embodiment. [Diagram 5] FIG. 5 is a schematic diagram showing an example of information handled by the construction work estimate making system in the first embodiment. [Figure 6] FIG. 6 is a schematic diagram showing an example of a database used in the operation method of the construction work estimate creation system in the first embodiment. [Figure 7] 7(a) and 7(b) are schematic diagrams showing an example of details of a database used in the operation method of the construction work estimate making system in the first embodiment. [Figure 8] 8(a) and 8(b) are schematic diagrams showing an example of details of a database used in the operation method of the construction work estimate making system in the first embodiment. [Figure 9] 9(a) and 9(b) are schematic diagrams showing an example of details of a database used in the operation method of the construction work estimate making system in the first embodiment. [Figure 10] FIG. 10 is a schematic diagram showing an example of a method for acquiring construction information included in the operation method of the construction work estimate creation system in the first embodiment. [Figure 11] FIG. 11 is a schematic diagram showing an example of a construction work cost output method included in the operation method of the construction work estimate creation system in the first embodiment. [Figure 12]FIG. 12 is a schematic diagram showing an example of a construction work estimate making system in the second embodiment. [Figure 13] FIG. 13 is a flowchart showing an example of an operation method of the construction work estimate preparation system in the second embodiment. [Figure 14] FIG. 14 is a schematic diagram showing an example of information handled by the construction work estimate making system in the second embodiment. [Figure 15] Figure 15(a) is a schematic diagram showing an example of flight and photographing operations of the construction work estimate creation system in the second embodiment, and Figure 15(b) is a schematic diagram showing an example of appearance information obtained by the photographing operation. [Figure 16] FIG. 16 is a schematic diagram showing an example of a database used in the operation method of the construction work estimate creation system in the second embodiment. [Figure 17] 17(a) and 17(b) are schematic diagrams showing an example of details of a database used in the operation method of the construction work estimate making system in the second embodiment. [Figure 18] FIG. 18 is a sequence diagram showing an example of an operation method of the construction work estimate preparation system in the second embodiment. [Figure 19] 19(a) to (e) are schematic diagrams showing an example of an operation method of the construction work estimate making system in the second embodiment. [Figure 20] FIG. 20(a) is a schematic diagram showing an example of an operation method of the construction work estimate making system in the second embodiment, and FIG. 20(b) is a schematic diagram showing the RR cross section of FIG. 20(a). [Figure 21] FIG. 21 is a schematic diagram showing a modified example of the operation method of the construction work estimate making system in the second embodiment. [Figure 22] FIG. 22 is a schematic diagram showing a modified example of the operation method of the construction work estimate making system in the second embodiment. [Figure 23] 23(a) and 23(b) are schematic diagrams showing a modified example of the operation method of the construction work estimate making system in the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0037] Hereinafter, an example of a construction work estimate preparation system 100, a construction work estimate preparation method, and a construction work estimate preparation program as an embodiment of the present invention will be described in detail with reference to the drawings. Note that the components in each drawing are shown diagrammatically for the purpose of explanation, and for example, the size of each component and the size comparison between each component may differ from those shown in the drawings.
[0038] (First embodiment: Construction work estimate creation system 100) An example of a construction work estimate preparation system 100 according to the present embodiment will be described with reference to FIGS. 1 to 3. FIG.
[0039] 1, the construction work estimate creation system 100 includes a control device 1, an unmanned aerial vehicle 2, and a wireless communication network 9. The construction work estimate creation system 100 captures an image of the exterior of an existing building 200 via the unmanned aerial vehicle 2 wirelessly connected via the wireless communication network 9 in response to information input by a user U who operates the control device 1.
[0040] The construction work estimate creation system 100 may include a server 3 that can be wirelessly connected to the control device 1 and the unmanned aerial vehicle 2, for example, via a wireless communication network 9. The construction work estimate creation system 100 may cooperate with an external system or a device in which a database is stored, connected, for example, via the wireless communication network 9 or other known communication methods, and may send and receive information to and from the device.
[0041] <Control device 1> The control device 1 is a device for controlling the operation of the unmanned aerial vehicle 2. The control device 1 is, for example, a terminal operated by a user U, and has portability. In addition to the terminal operated by the user U, the control device 1 may include a relay device that relays the transmission and reception of information between the terminal and the server 3.
[0042] 2(a), the control device 1 includes a housing 10, a CPU (Central Processing Unit) 101, a ROM (Read Only Memory) 102, a RAM (Random Access Memory) 103, a storage unit 104, and I / Fs 105 to 107. The components 101 to 107 are connected by an internal bus 110. As the control device 1, for example, a portable electronic device such as a tablet terminal or a smartphone is used.
[0043] The CPU 101 controls the entire control device 1. The ROM 102 stores operation codes for the CPU 101. The RAM 103 is a working area used when the CPU 101 operates. The storage unit 104 stores various information such as backups of data stored in the ROM, databases, and learning target data. As the storage unit 104, for example, a data storage device such as an HDD (Hard Disk Drive) or an SSD (Solid State Drive) is used. For example, the control device 1 may have a GPU (Graphics Processing Unit) (not shown).
[0044] The I / F 105 is an interface for transmitting and receiving various information to and from the unmanned aerial vehicle 2 and the server 3 as necessary via the wireless communication network 9. The I / F 106 is an interface for transmitting and receiving information to and from the input unit 108. As the input unit 108, for example, a keyboard or a mouse is used, and the user U inputs various information via the input unit 108. The I / F 107 is an interface for transmitting and receiving various information to and from the display unit 109. The display unit 109 displays various information stored in the storage unit 104, evaluation results, etc. A display is used as the display unit 109, and in the case of a touch panel type, for example, it is provided integrally with the input unit 108.
[0045] 3, the control device 1 has a wireless communication unit 11, a storage unit 12, a work area acquisition unit 13, a building material information acquisition unit 14, a building material quantity calculation unit 15, a unit price acquisition unit 16, and a construction work cost output unit 17. Each component of the control device 1 is realized by a CPU 101 using a RAM 103 as a working area to execute a program stored in a ROM 102 or a storage unit 104. In this embodiment, an example in which the control device 1 has each of the units 61 to 65 will be described, but at least a part of the units 61 to 65 may be provided in the server 3.
[0046] <Wireless Communication Unit 11> The wireless communication unit 11 transmits information to the unmanned aerial vehicle 2 or the server 3. The wireless communication unit 11 transmits information acquired, generated or stored by each component of the control device 1, for example, to the unmanned aerial vehicle 2 or the server 3 via the wireless communication network 9. The wireless communication unit 11 receives information acquired, generated or stored by the unmanned aerial vehicle 2, for example, via the wireless communication network 9. The wireless communication unit 11 receives information stored in the server 3, for example.
[0047] <Storage section 12> The storage unit 12 stores, for example, information acquired or generated by each component of the control device 1 in a database stored in the storage unit 104 as necessary. The storage unit 12 retrieves, for example, various pieces of information stored in the database stored in the storage unit 104 as necessary.
[0048] <Construction Scope Acquisition Section 13> The construction area acquisition unit 13 acquires the construction area of the construction work specified from the appearance information. The construction area acquisition unit 13 acquires the construction area of the construction work specified from the appearance information showing the appearance of the existing building 200 photographed by the unmanned aerial vehicle 2, for example.
[0049] The construction scope acquisition unit 13 acquires the construction scope of the designated construction work, for example, by a method of receiving input via the input unit 108 from a user U who has viewed the appearance information displayed on the display unit 109. The construction scope acquisition unit 13 may acquire the construction scope of the designated construction work, for example, by a method of automatically recognizing specific parts of the existing building 200, such as the roof or walls, from the appearance information via a known image recognition system.
[0050] <Building material information acquisition department 14> The building material information acquisition unit 14 acquires the identification information of the building materials used in the construction work. The building material information acquisition unit 14 acquires the identification information of the building materials, for example, by a method of accepting input from the user U via the input unit 108. The building material information acquisition unit 14 may acquire the identification information of the building materials by a method such as referring to a database in which identification information of the building materials is linked in advance for each specific part according to a specific part of the existing building 200 acquired from the exterior information via a known image recognition system, for example.
[0051] <Building Material Quantity Calculation Section 15> The building material quantity calculation unit 15 calculates the number of pieces of building materials to be used in the construction work from the construction work scope and the identification information of the building materials. The building material quantity calculation unit 15 calculates the number of pieces of building materials to be used in the construction work from the construction work scope acquired by the construction work scope acquisition unit 13 and the identification information of the building materials acquired by the building material information acquisition unit 14, for example.
[0052] The building material number calculation unit 15 calculates, for example, by dividing the area of the construction range acquired by the construction range acquisition unit 13 by the area per building material, or by integrating the amount used per unit area. The building material number calculation unit 15 calculates the area of the construction range for each part acquired by the construction range acquisition unit 13, for example, the area of the construction range acquired for each part such as horizontal roofing, vertical roofing, gables, and walls, by the area per building material corresponding to each part, or by integrating the amount used per unit area corresponding to each part. The building material number calculation unit 15 may use the result of automatically calculating the number of parts for the roof and exterior wall using known exterior roof allocation estimating software such as "Tsubo-Hibiki (registered trademark)" as the calculation result.
[0053] <Unit Price Acquisition Section 16> The unit price acquisition unit 16 refers to a database in which the identification information of a building material and the unit price of the building material are linked in advance, and acquires the unit price of the building material corresponding to the identification information of the building material from the database. The unit price acquisition unit 16 acquires the unit price of the building material corresponding to the identification information of the building material acquired by the building material information acquisition unit 14, for example.
[0054] <Construction work cost output section 17> The construction work cost output unit 17 outputs the construction work cost according to the number of pieces of the building material and the unit price of the building material. The construction work cost output unit 17 outputs the construction work cost according to, for example, the number of pieces of the building material calculated by the building material number calculation unit 15 and the unit price of the building material acquired by the unit price acquisition unit 16.
[0055] <Unmanned aircraft 2> The unmanned aerial vehicle 2 is a so-called small drone (multicopter) or unmanned helicopter capable of unmanned flight. The unmanned aerial vehicle 2 may include an unmanned aerial vehicle weighing 200g or more as defined by the Aviation Act, as well as a so-called small unmanned aircraft weighing less than 200g as defined by the same act. The unmanned aerial vehicle 2 may be, for example, a quadcopter having four rotors (propellers), and may be embodied as a helicopter with one rotor, a tricopter with three rotors, a hexacopter with six rotors, or an octocopter with eight rotors, depending on the required flight performance, reliability against failures, allowable costs, and the like.
[0056] As shown in FIG. 1, the unmanned aerial vehicle 2 has a control unit 20, a camera 21, a battery 22, and a rotor motor 23.
[0057] The unmanned aerial vehicle 2 may have arms extending from the control unit 20 in different directions, with rotor motors 23 provided at the tips of the arms. In particular, when configured as a quadcopter having four rotors, the arms of the unmanned aerial vehicle 2 are extended so that they are spaced at intervals of about 90° from each other in a plan view. Each arm of the unmanned aerial vehicle 2 may be configured as a tube made of, for example, metal, resin, carbon, or other material. In this case, a cable for supplying power from a battery 22 connected to the control unit 20 may be inserted into the tube of the arm.
[0058] As shown in FIG. 2(b), for example, the unmanned aerial vehicle 2 has a CPU 201, a ROM 202, and a RAM 203. The unmanned aerial vehicle 2 may have a storage unit 204 for storing data other than the control program that controls the operation of the unmanned aerial vehicle 2. The unmanned aerial vehicle 2 may have an I / F 205 for connecting to the wireless communication network 9. The components 201 to 205 are connected by an internal bus 210. In the unmanned aerial vehicle 2, for example, the CPU 201, the ROM 202, and the RAM 203 are integrated into a control unit 20. This control unit 20 may be, for example, a microcontroller.
[0059] The CPU 201 controls the entire unmanned aerial vehicle 2. The ROM 202 stores programs for controlling the hardware resources of the entire unmanned aerial vehicle 2, information for controlling the operation of the unmanned aerial vehicle 2, and the like. The RAM 203 is used as a working area for data accumulation, expansion, and the like, and temporarily stores various commands for controlling the hardware resources of the entire unmanned aerial vehicle 2. The storage unit 204 stores various information such as backups of the information stored in the ROM 202 and a database in which the information is integrated. As the storage unit 204, for example, a data storage device such as an HDD or an SSD is used. The unmanned aerial vehicle 2 may have, for example, a GPU (Graphics Processing Unit) not shown.
[0060] The CPU 201 is a so-called central processing unit for controlling all the components. The CPU 201 reads out programs stored in the ROM 202 or the storage unit 204, etc., and notifies each component of commands for performing various operations. For example, if the program stored in the ROM 202 is related to the generation of a flight path, flight operations, or photographing operations of the unmanned aerial vehicle 2, the CPU 201 generates various commands for generating a flight path, flying operations, or photographing operations based on the program, and transmits them to each component.
[0061] The CPU 201 also generates various commands based on information related to flight path generation, flight operations, or photographing operations and other information sent via the wireless communication network 9, and transmits them to each component. The CPU 201 also controls each component based on data sent from a group of sensors for controlling the unmanned aerial vehicle 2 and position information of the unmanned aerial vehicle 2 sent from the GNSS receiver.
[0062] <Control unit 20> The control unit 20 is configured with a housing for accommodating integrated circuits and devices required for various controls. The housing is made of, for example, metal or resin, and is configured, for example, in a box shape. The housing is provided in advance with screw holes (not shown) necessary for attaching components including, for example, an arm for attaching a rotor and legs for the unmanned aerial vehicle 2 to land. Various components accommodated in the control unit 20 or various components connected to the control unit 20 are fixed to screw holes provided in the housing of the control unit 20 via screws.
[0063] The control unit 20 includes a flight controller 50, a wireless communication unit 51, and an ESC (Electronic Speed Controller) 52, for example, as shown in FIG.
[0064] <Flight Controller 50> The flight controller 50 is a device for controlling the attitude of the unmanned aerial vehicle 2 and movement such as autonomous flight. The flight controller 50 controls the rotor motor 23 via the ESC 54, and controls the movement of the unmanned aerial vehicle 2. The flight controller 50 may control the movement of the unmanned aerial vehicle 2 based on information received by the wireless communication unit 51 via the wireless communication network 9, for example.
[0065] The flight controller 50 includes a sensor information acquisition unit 501 and an operation control unit 502. Each unit included in the flight controller 50 is realized by the CPU 201 executing a program stored in the ROM 202 or the like, using the RAM 203 as a working area.
[0066] <Sensor information acquisition unit 501> The sensor information acquisition unit 501 sequentially acquires, in a chronological order, information for controlling the movement of the unmanned aerial vehicle 2. The sensor information acquisition unit 501 includes, for example, a flight control sensor group and a GNSS receiving unit.
[0067] The flight control sensor group may be composed of various sensors including, for example, an acceleration sensor, an angular velocity sensor, an air pressure sensor (altitude sensor), a geomagnetic sensor (orientation sensor), as well as an altimeter for detecting flight altitude, an anemometer for detecting wind speed and direction, an acceleration sensor for detecting the inclination angle and inclination direction of the aircraft, a gyro sensor, etc. The flight control sensor group acquires, for example, information indicating the movement speed of the unmanned aerial vehicle 2 as three-dimensional information including a component in the forward / backward direction X, a component in the left / right direction Y, and a component in the height direction Z. The flight control sensor group acquires, for example, information indicating the movement direction of the unmanned aerial vehicle 2.
[0068] The GNSS receiver unit acquires position information indicating the position of the unmanned aerial vehicle 2 in real time based on satellite positioning signals transmitted from artificial satellites while the unmanned aerial vehicle 2 is moving. The GNSS receiver unit acquires the position information of the unmanned aerial vehicle 2, for example, as three-dimensional information including latitude, longitude, and altitude.
[0069] <Operation control unit 502> The operation control unit 502 controls the flight operation and image capturing operation of the unmanned aerial vehicle 2. The operation control unit 502 controls the flight operation and image capturing operation of the unmanned aerial vehicle 2 based on information received by the wireless communication unit 51, for example.
[0070] The operation control unit 502 controls the flight operation of the unmanned aerial vehicle 2, for example, by controlling the number of rotations and rotation speed of the rotor motor 23 via the connected ESC 53. The operation control unit 502 controls the shooting operation of the unmanned aerial vehicle 2, for example, via the connected camera 21. The operation control unit 502 is composed of, for example, a PWM (Pulse Width Modulation) controller.
[0071] <Wireless communication unit 51> The wireless communication unit 51 performs wireless communication with the control device 1 via the wireless communication network 9. The wireless communication unit 51 performs frequency conversion and other various conversion processes required for wireless communication with the control device 1, and also includes an antenna that converts an electric signal into a radio wave, or converts a radio wave into an electric signal. The wireless communication unit 51 may convert control information superimposed on a radio wave transmitted from the control device 1 or a device other than the control device 1 for controlling the operation of the unmanned aerial vehicle 2 into an electric signal, and then output the electric signal to the flight controller 50. As a result, the construction work estimate creation system 100 can realize the control of the unmanned aerial vehicle 2 via the flight controller 50.
[0072] The wireless communication unit 51 may convert data received from the flight controller 50 or the camera 21 into radio waves and transmit the data to the wireless communication network 9, or may transmit the data to the control device 1 or the server 3 via the wireless communication network 9. The wireless communication unit 51 may acquire various information from the wireless communication network 9 and transmit the information to the flight controller 50. However, in this embodiment, it is not necessary to control the operation of the unmanned aerial vehicle 2 based on control information received from an external source other than the construction work estimate creation system 100.
[0073] <Storage section 52> The memory unit 52 stores, as necessary, information acquired or generated by, for example, each component of the unmanned aerial vehicle 2 in a database stored in the storage unit 204. The memory unit 52 retrieves, as necessary, various pieces of information stored in, for example, the database stored in the storage unit 204.
[0074] <esc53> The ESC 53 controls the number of rotations, the rotation speed, etc. of the rotor motor 23 under the control of the operation control unit 502. The ESC 53 controls the rotor motor 23, thereby being able to control the movement speed and movement direction of the unmanned aerial vehicle 2.
[0075] <Camera 21> The camera 21 is mounted on, for example, the unmanned aerial vehicle 2. The camera 21 is attached, for example, to the lower part of the control unit 20, and captures an image below the unmanned aerial vehicle 2. The camera 21 may be a known camera capable of acquiring appearance information including images or videos.
[0076] <Battery 22> The battery 22 is a battery for supplying the power necessary to drive the control unit 20 and the camera 21. The battery 22 may be built into the unmanned aerial vehicle 2, for example, or may be mounted on the surface of the body of the unmanned aerial vehicle 2. The battery 22 may be configured, for example, to be detachable from the unmanned aerial vehicle 2. The battery 22 may be designed to be rechargeable.
[0077] <Rotor motor 23> The rotor motor 23 is electrically connected to the control unit 20, and rotates the rotors mounted on the unmanned aerial vehicle 2. A rotor motor 23 is provided for each rotor, and rotates based on power supplied from the battery 22 via the control unit 20. The rotor motor 23 is not limited as long as it has the above-mentioned functions, and any commercially available motor can be used.
[0078] Rotating the rotor motor 23 rotates the rotor, and the unmanned aerial vehicle 2 can instantly ascend or descend in a vertical direction, or can be stopped in place. When moving the unmanned aerial vehicle 2 forward, backward, left, or right, the rotation speed of the rotor motor 23 in the direction of travel is reduced, and the rotation speed of the rotor motor 23 on the opposite side to the direction of travel is increased. This causes the unmanned aerial vehicle 2 to lean forward in the direction of travel, allowing it to move in the direction of travel. Adjusting the output of the rotor motor 23 according to the direction of rotation also makes it possible to rotate the unmanned aerial vehicle 2 itself. The rotation speed of these rotor motors 23 is controlled via the control unit 20.
[0079] <200 existing buildings> The existing building 200 is a structure that is to be photographed by the unmanned aerial vehicle 2. The existing building 200 includes buildings classified into uses such as residences, apartment buildings, offices, factories, and hotels, and the improvement in workability by using the unmanned aerial vehicle 2 becomes more noticeable, especially as the building portion becomes taller or horizontally wider.
[0080] <Server 3> The server 3 stores information acquired and generated by, for example, the control device 1 or the unmanned aerial vehicle 2. The server 3 may be equipped with a CPU, ROM, and RAM, similar to the control device 1, and the CPU may read out a program stored in the ROM and control the operation of each component of the server 3 using the RAM as a working area. The server 3 may be connected to the control device 1 or the unmanned aerial vehicle 2 via, for example, a wireless communication network 9, and may transmit and receive any data to and from the control device 1 or the unmanned aerial vehicle 2. The server 3 may store information indicating the position and dimensions of, for example, the existing building 200 in advance, and transmit the stored information on the existing building 200 in response to a request from the control device 1 or the unmanned aerial vehicle 2.
[0081] <Wireless Communication Network 9> The wireless communication network 9 is, for example, an Internet network to which the control device 1, the unmanned aerial vehicle 2, and the server 3 are connected via a communication circuit. The wireless communication network 9 may be realized by a known communication technology such as a wireless communication network including LTE (Long Term Evolution). Note that in the construction work estimate creation system 100, the control device 1 and the unmanned aerial vehicle 2 may be connected by a known short-range wireless communication such as "Wi-Fi (registered trademark)" instead of the wireless communication network 9, or may be connected by a long-distance transmission technology unique to the unmanned aerial vehicle such as "OcuSync (registered trademark) 2.0" or "OcuSync (registered trademark) 3.0".
[0082] (First embodiment: an example of the operation of the construction work estimate creation system 100) Next, an example of the operation of the construction work estimate creation system 100 in this embodiment will be described with reference to Figures 4 to 11. The construction work estimate creation system 100 is executed via, for example, the control device 1, the unmanned aerial vehicle 2, and an unmanned aerial vehicle photography program installed in the server 3.
[0083] The operation of the construction work estimate creation system 100 further includes, as shown in FIG. 4, a construction scope acquisition step S11, a building material information acquisition step S12, a building material quantity calculation step S13, a unit price acquisition step S14, and a construction work amount output step S15.
[0084] First, various types of information associated with the operation of the construction work estimate preparation system 100 in this embodiment will be described.
[0085] <Construction Information D11> The construction information D11 is information related to the building construction of the existing building 200. The construction information D11 includes construction scope information D111, for example, as shown in Fig. 5. The construction information D11 may include construction site information D112, and may be stored in association with the construction scope information D111. The construction information D11 may include construction area information D113, and may be stored in association with the construction scope information D111. The construction information D11 is acquired, for example, by the input unit 108 of the control device 1 accepting an input from the user U.
[0086] The construction scope information D111 is information that specifies the scope of construction work on the existing building 200. The construction scope information D111 specifies a planar construction scope. The construction scope information D111 specifies, for example, a polygonal construction scope. The construction scope information D111 includes, for example, the dimensions of each side of the polygonal shape and the area of the planar construction scope for the specified construction scope. The construction scope information D111 may specify, for example, multiple construction scopes that are spaced apart from each other.
[0087] The construction area information D111 is formed, for example, along the outer peripheral shape from the appearance information of the existing building 200. At this time, a part or all of the roof of the existing building 200 included in the appearance information may be specified as the construction area, or a part or all of the wall may be specified as the construction area.
[0088] Here, the appearance information refers to visual information such as images and videos captured by the unmanned aerial vehicle 2. The appearance information includes, for example, visual information showing a partial appearance of the existing building 200, visual information showing the overall appearance of the existing building 200, and visual information generated by processing this information.
[0089] The construction site information D112 is information for identifying the sites that constitute the exterior of the existing building 200. The construction site information D112 includes information for identifying sites such as the "roof" and the "wall", for example.
[0090] The construction area information D113 is information indicating the area in which the existing building 200 where construction work is to be carried out is located. The construction area information D113 includes, for example, information identifying each region of Japan or each division of a local government.
[0091] <Building material information D12> The building material information D12 is information related to building materials used in construction work of the existing building 200. The building material information D12 includes, for example, building material characteristic information D121, building material identification information D122, and building material number information D123. The construction information D11 may include only one of the building material characteristic information D121 and the building material identification information D122, or may include both and store them linked to each other. The building material information D12 is acquired, for example, by the input unit 108 of the control device 1 accepting an input from the user U.
[0092] The building material characteristic information D121 is information indicating the characteristics of the building materials used in the construction work of the existing building 200. The building material characteristic information D121 includes, for example, information indicating the category of the building material, such as "horizontal roofing," "vertical roofing," and "ridgepole," and information indicating the quality of the building material, such as "steel" and "aluminum."
[0093] The building material identification information D122 is information for identifying building materials used in the construction work of the existing building 200. The building material characteristic information D121 includes information for identifying building materials, such as the product name and product model number of the building material, for example.
[0094] <Database 7> The database 7 is stored in advance in any of the components of the construction work estimate creation system 100. In this embodiment, an example in which the database 7 is stored in advance in the server 3 will be described, but the database 7 may be stored in advance in each of the storage units 104, 204, etc. instead of the server 3 or together with the server 3, for example.
[0095] As shown in Fig. 6, the database 7 includes an unmanned aerial vehicle information table 71, an exterior information table 72, a construction work information table 73, and a building material application information table 74. The information stored in each of the tables 72 to 74 is preferably linked to information having identifiability, for example, linked to the information stored in the unmanned aerial vehicle information table 71. The information stored in each table is received or directly input, for example, in the server 3. The information stored in each table is saved in association with identification information, such as a library number issued by the construction work estimate creation system 100 or reference unmanned aerial vehicle identification information D71. The information stored in each of the tables 71 to 74 may be information input in advance by the user U.
[0096] <Unmanned Aerial Vehicle Information Table 71> The unmanned aerial vehicle information table 71 stores reference unmanned aerial vehicle identification information D71, for example, as shown in FIG. 7(a).
[0097] <Reference unmanned aircraft identification information D71> The reference unmanned aerial vehicle identification information D71 is information for identifying one or more unmanned aerial vehicles. The reference unmanned aerial vehicle identification information D71 includes information such as the "pilot name", "unmanned aerial vehicle name", "serial number", "wireless aircraft registration number", and "insurance maturity date".
[0098] The reference unmanned aircraft identification information D71 may include, for example, information corresponding to the unmanned aircraft identification information D14 that identifies the unmanned aircraft 2. "Pilot name" may include, for example, information corresponding to the pilot name D141 that identifies the user U. "Unmanned aircraft body name" may include, for example, information that identifies the unmanned aircraft 2. "Serial number," "wireless aircraft registration number," and "insurance expiry date" may include information corresponding to the serial number, registration number, and insurance expiry date of the unmanned aircraft 2, respectively.
[0099] <Appearance information table 72> The appearance information table 72 stores reference appearance information D72, for example, as shown in FIG.
[0100] <Reference Appearance Information D72> The reference appearance information D72 includes appearance information captured for each of one or more unmanned aerial vehicles. The reference appearance information D72 includes, for example, information such as a "building partial image," a "building overall image," and a "three-dimensional modeling image."
[0101] The reference appearance information D72 may include, for example, information corresponding to the appearance information captured by the unmanned aerial vehicle 2. The "partial building image" may include, for example, visual information corresponding to partial appearance information of the existing building 200 captured by the unmanned aerial vehicle 2. The "full building image" may include, for example, visual information corresponding to the overall appearance information of the existing building 200 captured by the unmanned aerial vehicle 2, and visual information generated by processing this information. The "three-dimensional modeling image" may include, for example, information generated by processing based on the visual information captured by the unmanned aerial vehicle 2.
[0102] <Construction work information table 73> The construction work information table 73 stores reference construction work identification information D73, for example, as shown in FIG. 8(b).
[0103] <Reference Construction Work Identification Information D73> The reference construction work identification information D73 is information for identifying construction work of one or more existing buildings. The reference construction work identification information D73 includes information such as "building construction name", "construction contractor name", "construction work property name", and "construction area", for example.
[0104] The reference construction work identification information D73 may include, for example, information corresponding to construction work information indicating the details of the construction work of the existing building 200. The "building work name" may include, for example, information corresponding to the name of the construction work of the existing building 200. The "construction contractor name" may include, for example, information corresponding to the name of the contractor carrying out the construction work of the existing building 200. The "construction work object name" may include, for example, information corresponding to a name identifying the existing building 200. The "construction area" may include, for example, information corresponding to a name identifying the area in which the existing building 200 is located. The "construction area" may include, for example, information corresponding to the construction area information D113 included in the construction information D11 of the construction work of the existing building 200.
[0105] <Construction work information table 73> The construction work information table 73 stores reference construction work identification information D73 for identifying construction work of one or more existing buildings and reference building material information D75 in a linked manner, as shown in Fig. 8(b) for example. The construction work information table 73 may further store reference construction work identification information D73 for identifying construction work of one or more existing buildings in a linked manner, reference exterior information D72, and reference construction information D74, etc. Note that the reference building material information D75 is, for example, a copy of the information stored in the building material construction information table 74.
[0106] <Reference Construction Information D74> The reference construction information D74 is information indicating the details of construction work for one or more existing buildings. The reference construction information D74 includes information such as "building material installation area" indicating the installation area of building materials used in the construction work.
[0107] The reference construction information D74 may include, for example, information corresponding to the construction construction information indicating the contents of the construction construction of the existing building 200. The "building material installation area" may include, for example, information corresponding to the construction scope information D111 included in the construction information D11 of the construction construction of the existing building 200.
[0108] <Building material construction information table 74> The building material application information table 74 stores reference building material information D75, for example, as shown in Fig. 9(a). The building material application information table 74 may store reference building material information D75 and reference application information D76 in association with each other, for example, as shown in Fig. 9(b).
[0109] <Reference building material information D75> The reference building material information D75 is information showing details of building materials used in the construction work of one or more existing buildings. The reference building material information D75 includes information such as the "building material name", "building material unit price", "building material dealer name", "building material material", "building material characteristics", "auxiliary material name", and "building material quantity" of the building materials used in the construction work.
[0110] The reference building material information D75 may include, for example, information corresponding to the building material identification information D122. The reference building material information D75 may include, for example, information corresponding to the building material characteristic information D121. The "building material name" may include, for example, information indicating the name of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "building material unit price" may include, for example, information indicating the unit price of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "building material dealer name" may include, for example, information indicating the name of the dealer of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "building material material" may include, for example, information indicating the material of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "auxiliary material name" may include, for example, information indicating a jig or the like required for mounting the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "number of building materials" may include, for example, information indicating the number of units of a building material corresponding to the building material number information D123 included in the building material information D12.
[0111] <Reference construction information D76> The reference construction information D76 is information showing details of construction of building materials used in construction work of one or more existing buildings. The reference construction information D76 includes information such as "construction name", "contractor name", "construction content", "construction unit price", and "construction man-hours" related to the construction of building materials used in construction work.
[0112] The reference construction information D76 may include, for example, one or more pieces of construction information corresponding to the building material identification information D122. The reference construction information D76 may include, for example, one or more pieces of construction information corresponding to the building material characteristic information D121. Here, the one or more pieces of construction information may be a plurality of pieces of information with different construction processes, or may be time-series information or alternative information included in the same construction process. The "construction name" may include, for example, information indicating the construction name related to the construction of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "contractor name" may include, for example, information indicating the construction contractor related to the construction of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "construction content" may include, for example, information indicating the construction content related to the construction of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. The "construction unit price" may include, for example, information indicating the construction unit price related to the construction of the building material corresponding to the building material characteristic information D121 or the building material identification information D122. "Construction man-hours" may include, for example, information indicating the number of construction man-hours involved in constructing the building material corresponding to the building material characteristic information D121 or the building material identification information D122.
[0113] Next, the flow of operations of the construction work estimate preparation system 100 in this embodiment will be described.
[0114] <Construction scope acquisition step S11> In the construction scope acquisition step S11, the construction scope acquisition unit 13 acquires the construction scope of the building construction specified from the reference appearance information D72 as construction scope information D111, for example, as shown in Fig. 10. In this embodiment, an example in which a three-dimensional modeling image of the existing building 200 is used as the reference appearance information D72 will be described, but one or more images may be used, or a video may be used.
[0115] The construction area acquisition unit 13 receives a designation of the construction area from the user U who visually recognizes the reference appearance information D72, such as a three-dimensional modeling image of the existing building 200 displayed on the display unit 109, via the input unit 108. This allows the construction area information D111, including, for example, areas A, B, C, and D, to be acquired as the construction information D11. In addition, the construction area acquisition unit 13 receives input of the construction area information D111 and the construction site information D112 from the user U, and thereby allows the construction area information D111, including, for example, a roof A of area A, a roof B of area B, a roof C of area C, and a roof D of area D, to be acquired as the construction information D11.
[0116] In the example of FIG. 10, the user U operates to select the perimeter of each roof in the 3D modeling image A displayed on the display unit 109, thereby acquiring the range of roofs A to C and the dimensions of each side. After that, the user U operates to rotate the 3D modeling image A and specify the perimeter of the remaining roof in the 3D modeling image B displayed on the display unit 109, thereby acquiring the range of roof D and the dimensions of each side. After that, in order to simplify the calculation of the number of building materials, a planar development diagram of each roof A to D is acquired as the construction range information D111 by a generation process based on the acquired dimensions of each roof A to D, or a method of receiving input from the user U regarding the acquired dimensions of each roof A to D.
[0117] <Building material information acquisition step S12> In the building material information acquisition step S12, the building material information acquisition unit 14 acquires the building material identification information D122 designated by the user U. The building material information acquisition unit 14 acquires the building material identification information D122 by accepting an input of a designated building material from the user U who visually recognizes a list of one or more pieces of reference building material information D75 displayed on the display unit 109, for example.
[0118] Here, all of the reference building material information D75 may be displayed on the display unit 109, or only information related to the construction information D11 acquired by the construction scope acquisition unit 13 may be displayed on the display unit 109. In the example of Fig. 10, when the construction scope acquisition unit 13 acquires the construction information D11 including the construction part information D112 indicating the "roof" part, the display unit 109 may display only the reference building material information D75 corresponding to the roof material.
[0119] <Building material quantity calculation step S13> In the building material quantity calculation step S13, the building material quantity calculation unit 15 calculates building material quantity information D123 from the construction scope information D111 acquired by the construction scope acquisition unit 13 in the construction scope acquisition step S11 and the building material identification information D122 acquired by the building material information acquisition unit 14 in the building material information acquisition step S12. In the example of Fig. 10, in addition to calculating the total number of each building material as the construction information D11, the number of "used pieces (real pieces)" used as a single material and the number of "cut pieces" to be used by hand after being shaped to match the shape of the roof or exterior wall may also be calculated.
[0120] <Unit price acquisition step S14> In unit price acquisition step S14, the unit price acquisition unit 16 refers to the database 7 in which the identification information of the building material and the unit price of the building material are linked in advance, and acquires the unit price of the building material and the unit price of construction corresponding to the building material identification information D122 acquired by the building material information acquisition unit 14 from the database 7. For example, as shown in Fig. 9, the unit price acquisition unit 16 refers to a building material construction information table 74 in which "building material name", "building material unit price", and "construction unit price" are linked, and acquires the unit price of the building material and the unit price of construction corresponding to the building material identification information D122 from the building material construction information table 74.
[0121] <Construction work cost output step S15> In the construction work cost output step S15, the construction work cost output unit 17 outputs the construction work cost D13 according to the building material quantity information D123 calculated by the building material quantity calculation unit 15 in the building material quantity calculation step S13 and the unit price of the building material and the unit price of construction acquired by the unit price acquisition unit 16 in the unit price acquisition step S14. In detail, the construction work cost output unit 17 calculates the estimated subtotal A by multiplying the "material cost" corresponding to the building material identification information D122 by the "quantity (A1)" of the building material by the "unit price (A3)" as shown in Fig. 11, for example. Similarly, the construction work cost output unit 17 calculates the estimate subtotal B by multiplying the "quantity (B1)" of the processing by the "unit price (B3)" of the "processing cost" according to the building material identification information D122 and the building material number information D123, and calculates the estimate subtotal C by multiplying the "quantity (C1)" of the construction by the "unit price (C3)" of the "construction cost" according to the building material identification information D122 and the building material number information D123. After that, the total estimate D obtained by adding up the respective estimate subtotals A to C is output as the construction work cost D13. That is, even if the user U does not have specialized knowledge and is unfamiliar with the estimation of repairs, etc. of the existing building 200, he or she can be involved in the work related to the estimate of repairs, etc. In this case, the construction work cost D13 based on the appearance information showing the appearance of the existing building 200 can be easily output. This can improve the workability of the estimate of repairs, etc. of the existing building 200.
[0122] Furthermore, according to the above-mentioned construction work cost output step S15, the contents of the construction work can be taken into consideration in the estimate for the construction work. This can improve the accuracy of estimates for repairs, etc. of the existing building 200. Furthermore, when multiple "construction unit prices" are linked to one "building material name", the user U can selectively specify the unit price of the construction work from one or more "construction unit prices". In this case, when there are multiple unit prices of the construction work corresponding to the identification information of the specified building material, the unit price of the construction work can be arbitrarily selected according to the contents of the construction work. This can improve the operability of estimates for repairs, etc. of the existing building 200.
[0123] In addition, when the unit price acquisition unit 16 refers to the building material construction information table 74 in which the "building material name" and the "building material cost" are linked, and acquires the cost of the building material corresponding to the building material identification information D122 from the building material construction information table 74, it may acquire the unit sales price calculated using the "cost (A2)" of the building material and the "gross profit rate (E)" specified by the user U, and multiply this by the "quantity (A1)" instead of the "unit price (A3)" to calculate the estimated amount.
[0124] After performing each of the above steps, the operation of the construction work estimate preparation system 100 in this embodiment ends. Note that, in the construction work estimate preparation system 100, for example, each of the above steps may be repeatedly performed. Note that, in the construction work scope acquisition step S11, the construction scope acquisition unit 13 may acquire the construction scope of the construction work specified from the building plan data prepared in advance as the reference appearance information D72, as the construction scope information D111. In this case, the construction work estimate preparation system 100 does not require the control device 1 and the unmanned aerial vehicle 2 to be wirelessly connected.
[0125] (First embodiment: Modified example of the operation of the construction work estimate creation system 100) In the building material information acquisition step S12, the building material information acquisition unit 14 acquires the building material characteristic information D121 designated by the user U. Thereafter, the building material information acquisition unit 14 refers to the building material construction information table 74 in which the characteristics of the building material (e.g., "building material characteristic") and the identification information of the building material (e.g., "building material name") are linked, as shown in FIG. 9(b), and acquires the "building material name" linked to the "building material characteristic" corresponding to the acquired building material characteristic information D121 from the building material construction information table 74 as the building material identification information D122. In this case, by identifying the characteristics of the building material, there is no need to take the time to grasp the identification information of the building material. This can further improve the workability regarding the estimate of repairs and the like of the existing building 200. In addition, when multiple "building material names" are linked to one "building material characteristic", the user U can selectively specify the building material identification information D122 from one or more "building material names". In this case, when there are multiple pieces of identification information of the building material corresponding to the characteristics of the specified building material, the identification information of the building material can be arbitrarily selected. This improves the operability of estimating repairs, etc. of the existing building 200.
[0126] Another example of a modified example of the operation of the construction work estimate creation system 100 is as follows. In the construction work area acquisition step S11, the construction work area acquisition unit 13 acquires the construction area information D113 designated by the user U. In addition, in the building material information acquisition step S12, the building material information acquisition unit 14 acquires the building material characteristic information D121 designated by the user U. After that, the building material information acquisition unit 14 refers to the building material construction information table 74 in which the characteristics of the building material (e.g., "building material characteristics") and the construction area are linked to the identification information of the building material (e.g., "building material name") as shown in FIG. 9(b), and acquires the "construction area" corresponding to the acquired construction area information D113 and the "building material name" linked to the "building material characteristic" corresponding to the building material characteristic information D121 as the building material identification information D122 from the building material construction information table 74. In this case, the construction work amount D13 considering the circumstances of the building material due to the construction area such as the regional characteristics can be easily output. This makes it possible to further improve the workability in estimating repairs and the like for the existing building 200.
[0127] Another example of a modified example of the operation of the construction work estimate creation system 100 is as follows. In the construction work scope acquisition step S11, the construction work scope acquisition unit 13 acquires the construction area information D113 designated by the user U. In the unit price acquisition step S14, the unit price acquisition unit 16 refers to the building material construction information table 74 in which the identification information of the building material (e.g., "building material name") and the construction area are linked to the unit price of construction (e.g., "construction unit price"), as shown in FIG. 9(b), and acquires the "construction unit price" linked to the "building material name" corresponding to the acquired building material identification information D122 and the "construction area" corresponding to the acquired construction area information D113 from the building material construction information table 74. In this case, the construction work amount D13 considering the construction circumstances caused by the construction area, such as regional characteristics, can be easily output. This can further improve the workability of estimating the repair of the existing building 200.
[0128] According to this embodiment, the construction work estimate creation system 100 includes a construction material quantity calculation unit 15 that calculates the number of pieces of construction materials from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle 2 and the identification information of the construction materials specified by the user U, and a construction work cost output unit 17 that outputs the construction work cost D13 according to the calculated number of pieces of the building materials, the acquired unit price of the building materials, and the unit price of construction. Therefore, the construction work cost D13 based on the exterior information showing the exterior of the existing building 200 can be easily output. This can improve the workability of estimating repairs and the like for the existing building 200.
[0129] According to this embodiment, the construction area acquisition unit 13 acquires the construction area of the building construction from the exterior information photographed by the unmanned aerial vehicle 2. Therefore, compared to the case where a drawing or the like is used, it is possible to more reliably confirm the area and the situation where repairs or the like are required. This makes it possible to improve the accuracy of estimates for repairs or the like of the existing building 200.
[0130] According to this embodiment, the building material information acquisition unit 14 acquires the characteristics of the building materials to be used in the construction work specified by the user U, and acquires the identification information of the building materials according to the acquired characteristics of the building materials from the database 7. Therefore, by specifying the characteristics of the building materials, it is not necessary to take the time to grasp the identification information of the building materials. This can further improve the workability of estimating repairs and the like for the existing building 200.
[0131] According to this embodiment, the construction area acquisition unit 13 further acquires the construction area of the construction work specified by the user U, and the building material information acquisition unit 14 acquires the identification information of the building material according to the acquired characteristics of the building material and the construction area from the database 7. Therefore, it is possible to easily output the construction work cost D13 taking into consideration the circumstances of the building material resulting from the construction area, such as regional characteristics. This makes it possible to further improve the workability of estimating repairs, etc. of the existing building 200.
[0132] According to this embodiment, the construction area acquisition unit 13 further acquires the construction area of the construction work specified by the user U, and the unit price acquisition unit 16 acquires the unit price of the construction work corresponding to the acquired building material identification information and the construction area from the database 7. Therefore, it is possible to easily output the construction work amount D13 that takes into account the construction circumstances caused by the construction area, such as regional characteristics. This makes it possible to further improve the workability of estimating repairs, etc. of the existing building 200.
[0133] According to this embodiment, the construction work estimate creation method includes a construction material quantity calculation step S13 for calculating the number of pieces of building materials from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle 2 and the identification information of the building materials specified by the user U, and a construction work cost output step S15 for outputting the construction work cost D13 according to the calculated number of pieces of building materials, the acquired unit price of the building materials, and the unit price of construction. Therefore, the construction work cost D13 based on the exterior information showing the exterior of the existing building 200 can be easily output. This can improve the workability of estimating repairs and the like of the existing building 200.
[0134] According to this embodiment, the construction work estimate creation program causes the computer to execute a construction material quantity calculation step S13 for calculating the number of pieces of building materials from the construction range of the construction work specified from the exterior information photographed by the unmanned aerial vehicle 2 and the identification information of the building materials specified by the user U, and a construction work cost output step S15 for outputting the construction work cost D13 according to the calculated number of pieces of building materials, the acquired unit price of the building materials, and the unit price of construction. Therefore, the construction work cost D13 based on the exterior information showing the exterior of the existing building 200 can be easily output. This can improve the workability of estimating repairs and the like of the existing building 200.
[0135] (Second embodiment: Construction work estimate creation system 100) An example of a construction work estimate creation system 100 in this embodiment will be described with reference to Fig. 12. This embodiment differs from the first embodiment in that the construction work estimate creation system 100 further includes a shooting range acquisition unit 61, a flight path generation unit 62, a shooting condition acquisition unit 63, and a shooting operation identification unit 64. Note that a description of the same configuration as that described above will be omitted.
[0136] 12, the control device 1 includes a shooting range acquisition unit 61, a flight path generation unit 62, a shooting condition acquisition unit 63, and a shooting operation identification unit 64. The control device 1 may further include, for example, an authentication unit 65 and a calculation unit 66.
[0137] <Shooting range acquisition unit 61> The shooting range acquisition unit 61 acquires a planar shooting range of the unmanned aerial vehicle 2. The shooting range acquisition unit 61 acquires the shooting range by a method of accepting an input from the user U via the input unit 108, for example.
[0138] Here, "planar" refers to a horizontal plane that is approximately perpendicular to the direction in which the earth's gravity acts. That is, a planar imaging range may include latitude and longitude information, but does not include altitude information.
[0139] <Flight Path Generation Unit 62> The flight path generating unit 62 generates a horizontal flight path of the unmanned aerial vehicle 2. The flight path generating unit 62 generates a flight path of the unmanned aerial vehicle 2 based on the shooting range acquired by the shooting range acquisition unit 61, for example.
[0140] Here, the horizontal direction refers to a direction on a horizontal plane that is approximately perpendicular to the direction in which the gravity of the earth acts, and is approximately parallel to the planar shooting range. That is, the unmanned aerial vehicle 2 in the present invention flies in the horizontal direction on the flight path generated by the flight path generating unit 62, and does not perform intentional flight operations toward the height direction Z, except for environmental factors such as bad weather and collision avoidance, switching to a power-saving mode due to battery depletion, switching to an evacuation mode that interrupts flight operations, and the like.
[0141] <Photographing condition acquisition unit 63> The photographing condition acquisition unit 63 acquires the photographing conditions of the unmanned aerial vehicle 2. The photographing condition acquisition unit 63 acquires the photographing conditions, for example, by a method of accepting input from the user U via the input unit 108. The photographing condition acquisition unit 63 may acquire information related to the photographing conditions stored in advance in any of the components of the construction work estimate creation system 100, for example. The photographing condition acquisition unit 63 acquires, for example, the photographing conditions of the unmanned aerial vehicle 2 in the photographing range acquired by the photographing range acquisition unit 61. Here, the photographing conditions include, for example, the photographing altitude of the unmanned aerial vehicle 2 and the number of photographs.
[0142] <Shooting operation identification unit 64> The photographing operation identification unit 64 identifies the photographing operation of the unmanned aerial vehicle 2. The photographing operation identification unit 64 identifies the photographing operation on the flight path generated by the flight path generation unit 62, for example, based on the number of shots among the photographing conditions acquired by the photographing condition acquisition unit 63. In this embodiment, after the photographing operation identification unit 64 identifies the photographing operation on the flight path, the unmanned aerial vehicle 2 performs the photographing operation according to the identified photographing operation.
[0143] <Authentication Section 65> The authentication unit 65 certifies that the approval information corresponding to the unmanned aerial vehicle 2 is valid. The authentication unit 65 certifies that the approval information corresponding to the unmanned aerial vehicle 2 is valid, for example, by referring to a database 7 that includes information regarding flight permission for the unmanned aerial vehicle 2 in the DIPS or FISS.
[0144] <Calculation section 66> The calculation unit 66 calculates the number of shots based on the shooting altitude of the unmanned aerial vehicle 2, or the shooting altitude based on the number of shots. The calculation unit 66 calculates the number of shots based on the shooting altitude of the unmanned aerial vehicle 2 acquired by the shooting condition acquisition unit 63, for example, or the shooting altitude based on the number of shots of the unmanned aerial vehicle 2 acquired by the shooting condition acquisition unit 63.
[0145] <Operation control unit 502> The operation control unit 502 controls the flight operation of the unmanned aerial vehicle 2 based on, for example, a flight path generated by the flight path generation unit 62 and the shooting altitude acquired by the shooting condition acquisition unit 63, and also controls the shooting operation of the unmanned aerial vehicle 2 based on the shooting operation identified by the shooting operation identification unit 64.
[0146] (Second embodiment: an example of the operation of the construction work estimate creation system 100) Next, an example of the operation of the construction work estimate making system 100 in this embodiment will be described with reference to Figs.
[0147] The operation of the construction work estimate creation system 100 includes, for example, a shooting range acquisition step S21, a flight path generation step S22, a shooting condition acquisition step S23, a shooting operation specification step S24, and an operation control step S25 before the construction range acquisition step S11 is performed, as shown in Fig. 13. The construction range acquisition step S11 uses the appearance information acquired by the operation control step S25. Note that, in this embodiment, an example in which the shooting condition acquisition step S23 is performed after the flight path generation step S22 will be described, but the shooting range acquisition step S21 or the flight path generation step S22 may be performed after the shooting condition acquisition step S23.
[0148] The operation of the construction work estimate creation system 100 may further include, for example, an appearance information storage step S27 and an authentication step S26. The appearance information storage step S27 may be performed together with the operation control step S25, or may be performed after the operation control step S25 is completed. The authentication step S26 may be performed before the operation control step S25, at least before or after the shooting range acquisition step S21, the flight path generation step S22, the shooting condition acquisition step S23, and the shooting operation identification step S24, or may be performed multiple times.
[0149] First, various information associated with the operation of the construction work estimate creation system 100 in this embodiment will be described. The various information handled by the construction work estimate creation system 100 includes unmanned aerial vehicle identification information D14, shooting range information D15, flight route information D16, shooting condition information D17, unmanned aerial vehicle flight information D18, and appearance information D19, as shown in Fig. 14. The various information handled by the construction work estimate creation system 100 is acquired by the input unit 108 of the control device 1 accepting the input of the user U, and may be acquired by acquiring information that has been saved or generated in advance in each component of the construction work estimate creation system 100, or may be acquired via a sensor mounted on the unmanned aerial vehicle 2.
[0150] <Unmanned Aerial Vehicle Identification Information D14> The unmanned aerial vehicle identification information D14 is information for identifying a user U who uses the unmanned aerial vehicle 2 or the control device 1 that controls the unmanned aerial vehicle 2. The unmanned aerial vehicle identification information D14 includes, for example, a pilot name D141, an unmanned aerial vehicle name D142, etc. The pilot name D141 and the unmanned aerial vehicle name D142 are, for example, stored in association with each other.
[0151] The pilot name D141 is information for identifying the user U. The pilot name D141 is obtained, for example, by the user U directly inputting it to the control device 1 or the server 3. The pilot name D141 is transmitted, for example, from the control device 1 to the unmanned aerial vehicle 2 or the server 3. The pilot name D141 is used, for example, when inquiring about the unmanned aerial vehicle name D142 linked to the pilot name D141, or when authenticating the user U as the user of the unmanned aerial vehicle name D142.
[0152] The unmanned aircraft aircraft name D142 is information that identifies the unmanned aircraft 2. The unmanned aircraft aircraft name D142 is stored in advance, for example, in the server 3. The unmanned aircraft aircraft name D142 is used, for example, when grouping appearance information acquired by the unmanned aircraft 2 in association with information photographed by the unmanned aircraft 2, or when inquiring about the expiration date of the flight permission of the unmanned aircraft 2.
[0153] <Shooting range information D15> The photographing range information D15 is information that specifies the photographing range of the unmanned aerial vehicle 2. The photographing range information D15 specifies a planar photographing range along the horizontal direction. The photographing range information D15 may specify a photographing range having a polygonal shape, for example, or may specify a photographing range having a circular shape or any other shape.
[0154] The shooting range information D15 is formed along the outer peripheral shape of the existing building 200 in a plan view or so as to include the outer peripheral shape. For example, as shown in Fig. 15, the shooting range information D15 specifies a quadrangular shooting range in a plan view having four vertices, namely, first position information D151, second position information D152, third position information D153, and fourth position information D154, in order to shoot the entire existing building 200 having a quadrangular shape in a plan view. Here, the various kinds of position information D151 to D154 are acquired, for example, by the input unit 108 of the control device 1 accepting an input from the user U.
[0155] <Flight route information D16> The flight path information D16 is information that specifies the flight path of the unmanned aerial vehicle 2. The flight path information D16 specifies a planar flight path along the horizontal direction. As shown in FIG. 14, for example, the flight path information D16 includes first route information D161 that is generated first based on the shooting range information D15, and second route information D162 that is generated based on the first route information D161.
[0156] <Photography condition information D17> The photographing condition information D17 is information that specifies the photographing conditions of the unmanned aerial vehicle 2. The photographing condition information D17 includes, for example, photographing altitude information D171, photographed number information D172, photographing time information D173, and photographing operation specification information D174.
[0157] The photographing altitude information D171 is information indicating the photographing altitude at which the unmanned aerial vehicle 2 performs photographing operations, and indicates the altitude at which the camera 21 mounted on the unmanned aerial vehicle 2 is located. When the camera 21 is attached to the lower part of the body of the unmanned aerial vehicle 2, an error occurs between the flight altitude of the unmanned aerial vehicle 2 and the photographing altitude according to the size of the body of the unmanned aerial vehicle 2. The unmanned aerial vehicle 2 performs horizontal flight operations based on the flight route information D16 at a flight altitude based on the photographing condition information D17.
[0158] The number of images captured by the unmanned aerial vehicle 2 indicates the number of images captured by the unmanned aerial vehicle 2. For example, as shown in Fig. 15(a) to Fig. 15(b), when the unmanned aerial vehicle 2 performs a capturing operation while flying in the order of points P1, P2, P3, and P4 in a rectangular capturing range formed by various position information D151 to D154, the camera 21 performs a flying operation and a capturing operation while keeping the angle of view V of the camera 21 constant at a vertical width w1 and a horizontal width w2 within the angle of view by maintaining a constant capturing altitude. Note that the oblique lines in the figure indicate the diagonal lines of the angles of view V1 to V4 for distinguishing the angles of view V1 to V4. In addition, in order to obtain the exterior information of the entire existing building 200, the angles of view V1, V2, V3, and V4 at the points P1, P2, P3, and P4 require an overlapping area of an overlapping vertical width w3 and an overlapping horizontal width w4. Specifically, the feature points included in the overlapping portion of the overlapping area where two or more pieces of appearance information overlap are compared between the pieces of appearance information to determine their mutual positional relationship. Such determination of the positional relationship is realized, for example, by SfM (Structure from Motion), a well-known technology that estimates a three-dimensional scene from a two-dimensional image. Then, by setting the overlapping vertical width w3 and overlapping horizontal width w4 as constant values, the number of shots required to shoot the entire shooting range can be planned (four in the case of FIG. 15). Note that the vertical width w1 within the angle of view, the horizontal width w2 within the angle of view, the overlapping vertical width w3, and the overlapping horizontal width w4 are all widths corresponding to the actual dimensions (actual measurements) of the subject included in the angle of view V, and are different from the size of the image or video.
[0159] That is, a planned value for the number of shots when a constant shooting altitude based on the shooting altitude information D171 is maintained may be acquired as the number-of-shots information D172. Also, by setting the overlapping vertical width w3 and horizontal width w4 of the overlapping area as constant values, the vertical width w1 and horizontal width w2 within the angle of view V required to shoot the entire shooting range may be calculated based on the number-of-shots information D172, and the shooting altitude at which the angle of view V can be realized may be acquired as the shooting altitude information D171.
[0160] An example of each piece of acquired information is, for example, the vertical width w1 within the field of view V from 0 m to 100 m, and the horizontal width w2 within the field of view V from 0 m to 100 m. Also, an example of each preset setting value is, for example, the overlap vertical width w3 of the overlapping area from 0 m to 20 m, and the overlap horizontal width w4 from 0 m to 20 m.
[0161] The shooting time information D173 indicates, for example, the time until the next shooting after the unmanned aerial vehicle 2 shoots an image, and also includes the time for continuous shooting when the unmanned aerial vehicle 2 shoots a video. In this embodiment, an example is described in which the shooting operation is performed according to the position information of the unmanned aerial vehicle 2, but the unmanned aerial vehicle 2 may also perform the shooting operation according to the flight speed and flight direction of the flight operation, and the shooting time included in the shooting time information D173.
[0162] The photographing operation specification information D174 indicates the content of the photographing operation on the flight path of the unmanned aerial vehicle 2. The photographing operation specification information D174 is specified based on, for example, the photographed frame count information D172.
[0163] Examples of the contents of the photographing operation include photographing operation in which the number of photographs included in the photograph count information D172 is taken as the total number of photographs taken on the flight path, and photographing is performed at equal intervals along the entire flight path of the unmanned aerial vehicle 2. Also, photographing operation in which the photographing time included in the photographing time information D173 is taken as the total photographing time along the flight path, and photographing is performed at equal intervals along the predetermined scheduled flight time of the unmanned aerial vehicle 2.
[0164] <Unmanned aircraft flight information D18> The unmanned aerial vehicle flight information D18 is information indicating the status of the flight operation of the unmanned aerial vehicle 2. For example, as shown in Fig. 14, the unmanned aerial vehicle flight information D18 includes unmanned aerial vehicle position information D181, flight speed information D182, remaining battery level information D183, and flight date and time information D184. The unmanned aerial vehicle flight information D18 is obtained, for example, in response to a request from each component of the construction work estimate creation system 100, or automatically at predetermined intervals.
[0165] The unmanned aerial vehicle position information D181 is information (position information) indicating the position of the unmanned aerial vehicle 2. The unmanned aerial vehicle position information D181 is used, for example, when controlling the flight operation and shooting operation of the unmanned aerial vehicle 2 based on the position information, or when linking the position information to the captured exterior information. In this embodiment, the construction work estimate creation system 100 continuously or intermittently acquires the changes in altitude and coordinate information included in the unmanned aerial vehicle position information D181 in order to fly the unmanned aerial vehicle 2 horizontally while maintaining a constant altitude, and controls the flight operation of the unmanned aerial vehicle 2 to follow the flight path information D16. In addition, the construction work estimate creation system 100 continuously or intermittently acquires the altitude and coordinate information included in the unmanned aerial vehicle position information D181 in order to have the unmanned aerial vehicle 2 shoot the entire predetermined shooting range with a predetermined number of shots, and controls the shooting operation of the unmanned aerial vehicle 2 to follow the flight path information D16 and the shooting condition information D17.
[0166] The flight speed information D182 is information indicating the flight speed of the unmanned aerial vehicle 2. The flight speed information D182 is used, for example, when determining whether the unmanned aerial vehicle 2 is flying at a predetermined speed and in a flight direction following the flight path. In this embodiment, the construction work estimate creation system 100 continuously or intermittently acquires the speed included in the flight speed information D182 and controls the flight operation of the unmanned aerial vehicle 2 to follow the flight path information D16 in order to fly the unmanned aerial vehicle 2 in a horizontal direction while maintaining a constant speed.
[0167] The battery remaining amount information D183 is information that indicates the remaining battery amount of the battery 22 mounted on the unmanned aerial vehicle 2. The battery remaining amount information D183 is used, for example, when determining whether or not the remaining battery amount has fallen below a preset lower limit, or when determining whether or not the unmanned aerial vehicle 2 that is being charged with the battery 22 mounted thereon can resume image capture (for example, whether or not the remaining battery amount has reached a preset value or greater).
[0168] The flight date and time information D184 is information indicating the date and time when the unmanned aerial vehicle 2 performs a flight operation. The flight date and time information D184 is used, for example, when linking time information to exterior information photographed by the unmanned aerial vehicle 2, or when inquiring whether the flight permission for the unmanned aerial vehicle 2 is within the validity period.
[0169] <Appearance information D19> The appearance information D19 indicates visual information such as images and videos captured by the unmanned aerial vehicle 2. The appearance information D19 includes, for example, building part appearance information D191, entire building appearance information D192, and processed appearance information D193.
[0170] The building portion appearance information D191 indicates visual information showing a portion of the existing building 200 photographed by the unmanned aerial vehicle 2. The building portion appearance information D191 is visual information showing a portion of the existing building 200 included in each of the angles of view V1 to V4, as shown in Fig. 15(b), for example.
[0171] The entire building exterior information D192 indicates visual information showing the entire plan view of the existing building 200 excluding walls, etc., photographed by the unmanned aerial vehicle 2. The entire building exterior information D192 is acquired in a single photographing operation, for example, by increasing the photographing altitude and expanding the vertical width w1 and horizontal width w2 within the angle of view of the angle of view V, so that the entire existing building 200 fits within the angle of view.
[0172] The processed appearance information D193 is visual information generated by processing at least one of the building part appearance information D191 and the whole building appearance information D192 captured by the unmanned aerial vehicle 2. The processed appearance information D193 is visual information showing the whole of the existing building 200, which is generated by synthesizing a plurality of pieces of building part appearance information D191 showing parts of the existing building 200 included in each of the angles of view V1 to V4, as shown in FIG. 15(a), for example. At this time, the processed appearance information D193 is generated by synthesizing based on position information included in Exif (Exchangeable image file format) assigned to the plurality of pieces of building part appearance information D191. Here, in the present invention, since the building part appearance information D191 is captured by the unmanned aerial vehicle 2 at the same altitude, it is easy to generate the processed appearance information D193 by more accurately synthesizing the plurality of pieces of building part appearance information D191.
[0173] Note that Figure 15(a) shows an example in which the entire planar view of the existing building 200 is included in each of the viewing angles V1 to V4, but when some visual information of the entire planar view of the existing building 200 is missing, the processed appearance information D193 may be generated by complementing and synthesizing the missing visual information using a known artificial intelligence system.
[0174] The processed appearance information D193 includes, for example, a three-dimensional modeling image showing a three-dimensional appearance of the existing building 200. The three-dimensional modeling image is useful for accurately grasping, for example, the three-dimensional structure of the roof part of the existing building 200, such as the degree of the roof slope, the direction of the slope, and the structure of a lean-to roof or a sloping roof that is difficult to grasp in a planar view. The three-dimensional modeling image may be, for example, an image output by inputting a plurality of building part appearance information D191 into the well-known open source software "Open Drone Map."
[0175] <Database 7> The database 7 may further include an approval information table 75, as shown in Fig. 16. The information stored in the approval information table 75 is saved in association with identification information, such as a library number issued by the construction work estimate creation system 100 and reference unmanned aerial vehicle identification information D71.
[0176] <Approval information table 75> The approval information table 75 stores, for example, reference approval information D77 as shown in FIG.
[0177] <Reference approval information D77> The reference approval information D77 is information that indicates the contents of the flight permission for each of one or more unmanned aerial vehicles. The reference approval information D77 includes information such as the "flight permission number" and the "flight permission expiration date."
[0178] The reference approval information D77 may include information corresponding to approval information indicating the contents of flight permission for the unmanned aerial vehicle 2, which is stored in an external database such as DIPS (Drone Information Infrastructure System) or FISS (Flight Information Sharing System). The "flight permission number" may include information corresponding to the flight permission number of the unmanned aerial vehicle 2. The "flight permission expiration date" may include information corresponding to the flight permission expiration date linked to the flight permission number of the unmanned aerial vehicle 2.
[0179] After the server 3 confirms that the reference unmanned aircraft identification information D71 previously stored in the unmanned aircraft information table 71 corresponds to the unmanned aircraft identification information D14 received from the control device 1, it may receive approval information of the unmanned aircraft 2 linked to the unmanned aircraft identification information D14 and store it in the reference approval information D77.
[0180] After the server 3 confirms that the reference unmanned aircraft identification information D71 previously stored in the unmanned aircraft information table 71 corresponds to the unmanned aircraft identification information D14 received from the control device 1, it may receive appearance information D19 of the unmanned aircraft 2 linked to the unmanned aircraft identification information D14 and store it in the reference appearance information D72.
[0181] After the server 3 confirms that the reference unmanned aircraft identification information D71 previously stored in the unmanned aircraft information table 71 corresponds to the unmanned aircraft identification information D14 received from the control device 1, it may receive appearance information D19 of the unmanned aircraft 2 linked to the unmanned aircraft identification information D14, and link and store the reference construction work identification information D73 and the reference appearance information D72 via the reference unmanned aircraft identification information D71.
[0182] After confirming that the reference unmanned aircraft identification information D71 stored in advance in the unmanned aircraft information table 71 corresponds to the pilot name D141 received from the control device 1, the server 3 may receive information on the "serial number", "wireless aircraft registration number" and "insurance maturity date" of the unmanned aircraft 2 linked to the pilot name D141, and store the information in the reference unmanned aircraft identification information D71. For example, when the pilot name D141 received from the control device 1 does not correspond to the reference unmanned aircraft identification information D71 stored in advance, the server 3 may newly generate the reference unmanned aircraft identification information D71 corresponding to the pilot name D141 received by the server 3, and store the information in the database 7. These processes can be replaced with any information included in the unmanned aircraft identification information D14 that can identify the user U or the unmanned aircraft 2, and for example, the unmanned aircraft aircraft name D142 may be used instead of the pilot name D141.
[0183] Next, the flow of operations of the construction work estimate preparation system 100 in this embodiment will be described.
[0184] <Advance preparation> As a preliminary preparation for operation, the construction work estimate creation system 100 may authenticate that the user U operating the control device 1 is the pilot of the unmanned aerial vehicle 2. As an authentication method, for example, the control device 1 may transmit the pilot name D141 input by the user U to the server 3, authenticate that the pilot name is linked to the unmanned aerial vehicle name D142 corresponding to the unmanned aerial vehicle 2 pre-stored in the server 3, and activate the control of the unmanned aerial vehicle 2 by the control device 1.
[0185] <Photographing range acquisition step S21> In the shooting range acquisition step S21, the shooting range acquisition unit 61 acquires shooting range information D15 including a planar shooting range, for example, as shown in FIG. 18 (S211).
[0186] The control device 1 may transmit the shooting range information D15 including the planar shooting range R acquired by the shooting range acquisition unit 61 to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S212). The unmanned aerial vehicle 2 stores the shooting range information D15 received via the wireless communication network 9 in the storage unit 204. When the unmanned aerial vehicle 2 detects that it has left the shooting range information D15 received by an on-board sensor or the like, it may transmit a notice to that effect to the control device 1 or the server 3.
[0187] As shown in FIG. 19(a), the shooting range acquisition unit 61 acquires each piece of position information D151 to D154 by input from the user U, and then acquires shooting range information D15 including a planar shooting range R. In detail, the user U first taps four points, namely, points A, B, C, and D, which correspond to the periphery vertices of the existing building 200, in a known map application that shows the surrounding area of the existing building 200 in a planar manner displayed on the display unit 109 of the touch panel type control device 1. At this time, the shooting range acquisition unit 61 acquires coordinate information corresponding to each of the points A to D from the map application. As a result, the shooting range acquisition unit 61 acquires the point A inputted via the input unit 108 as the first position information D151, the point B as the second position information D152, the point C as the third position information D153, and the point D as the fourth position information D154, and acquires the rectangular shooting range R as the shooting range information D15 based on the coordinate information included in each piece of position information. The display unit 109 may display the acquired shooting range R. When the control device 1 acquires the current location of the unmanned aerial vehicle 2 from the unmanned aerial vehicle 2 before flight operation, the display unit 109 may display it as the takeoff point H. The shooting range acquisition unit 61 may directly acquire shooting range information D15 including the planar shooting range R in response to an input such as a range designation by the user U.
[0188] The unmanned aerial vehicle 2 receives the shooting range information D15 via the wireless communication network 9 and stores it in the storage unit 204. When the flight path generation step S22 is executed by the flight path generation unit 62 mounted on the control device 1, the unmanned aerial vehicle 2 does not need to receive the shooting range information D15.
[0189] <Flight route generation step S22> In a flight path generation step S22, the flight path generation unit 62 generates flight path information D16 including a horizontal flight path of the unmanned aerial vehicle 2 based on the shooting range R contained in the shooting range information D15 acquired by the shooting range acquisition unit 61 in the shooting range acquisition step S21, as shown in, for example, FIG. 18 (S221).
[0190] The control device 1 may transmit flight path information D16, including the horizontal flight path generated by the flight path generation unit 62, to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S222). The unmanned aerial vehicle 2 stores the flight path information D16 received via the wireless communication network 9 in the storage unit 204. When the unmanned aerial vehicle 2 detects that it has departed from the received flight path information D16 using an on-board sensor or the like, it may transmit a notification to that effect to the control device 1 or the server 3.
[0191] 19(b), the flight path generating unit 62 first calculates the length of each side constituting a rectangular shooting range R based on the coordinate information of two corresponding points, and specifies the longest side AB of the range width W1. Then, based on a preset turning-back width W2, point A, which is closer to the takeoff point H out of points A and B, is set as the shooting start point, and turning-back points E1 to E4 are specified on the longest side AB from point A to point B. Note that the number of turning-back points is not limited to four, and a number according to the range width W1 of the longest side AB and the turning-back width W2 may be specified.
[0192] In addition, when the photographing altitude information D171 is acquired in a step described later, the folding width W2 may be updated based on the vertical width w1 and horizontal width w2 of the field of view V calculated based on the photographing altitude information D171 and the overlapping vertical width w3 and overlapping horizontal width w4 of the overlapping area between the building part exterior information D191 that is set in advance. For example, when the photographing altitude included in the photographing altitude information D171 indicates a height of 7 m from the existing building 200, the field of view V of the camera 21 is a regular square pyramid shape of 90° in a plan view, the vertical width w1 of the field of view = the horizontal width w2 of the field of view = 14 m, and the initial value of the folding width W2 is set to 5 m, the overlapping horizontal width w4 of the overlapping area is calculated as, for example, w4 = w2 × 1 / 2 + w2 × 1 / 2 - W2 = 9 m (see points P2 and P3 in FIG. 15). Here, when the overlap width w4 of the overlapping area is 5m and sufficient useful appearance information D19 is obtained, the folding width W2 may be updated to an enlarged value, such as folding width W2=w2×1 / 2+w2×1 / 2-w4=9m, which is calculated by back-calculating from the overlap width w4. The overlap height w3 of the overlapping area may be calculated in the same manner as the overlap width w4. In this case, the entire shooting range R can be automatically photographed with fewer shots and shorter flight time. This can improve the efficiency of work related to estimates for repairs, etc. of the existing building 200.
[0193] Thereafter, the flight path generating unit 62 generates the first path information D161 including paths L1a-L1d that pass through turn-back points E1-E4 and are substantially perpendicular to the longest side AB. At this time, the intersections of the paths L1a-L1d and each side other than the longest side AB are respectively set as turn-back points F1-F4. Here, for example, as shown in FIG. 19(e), when generating a path substantially perpendicular to a side BC other than the longest side AB, an extra step is generated in which a line segment BC' is generated by extending the side BC, a path substantially perpendicular to the line segment BC' is generated, and then an intersection point (E7' in FIG. 19(e)) between the path and the shooting range R is calculated. However, by selecting the longest side AB, it is easy to suppress the occurrence of this step. In this case, the processing is simplified compared to the case where the flight path L is calculated based on a side other than the longest side AB, and the flight path L can be generated efficiently. This can improve the efficiency of estimating repairs and the like for the existing building 200. In addition, the routes L1a to L1d are not limited to being approximately perpendicular to the longest side AB. For example, the first route information D161 may be generated so that all of the routes include routes that are approximately parallel to the side AD adjacent to the longest side AB, or the first route information D161 may be generated so that all of the routes include routes that are approximately parallel to the side BC adjacent to the longest side AB.
[0194] After generating the first route information D161, the flight route generating unit 62 generates second route information D162 including a route connecting each path of the first route information D161, as shown in Fig. 19(c) for example. At this time, the second route information D162 indicates a route that realizes the unmanned aerial vehicle 2 to fly in directions that alternate in the order of routes L1a, L1b, L1c, and L1d. In detail, the line segment AE1 connecting point A, which is the start point of shooting, and point E1, which is the start point of path L1a, is defined as path L2a, the line segment F1F2 connecting point F1, which is the end point of path L1a, and point F2, which is the start point of path L1b, is defined as path L2b, the line segment E2E3 connecting point E2, which is the end point of path L1b, and point E3, which is the start point of path L1c, is defined as path L2c, the line segment F3F4 connecting point F3, which is the end point of path L2b, and point F4, which is the start point of path L1d, is defined as path L2d, and the line segment E4B connecting point E4, which is the end point of path L1d, and point B, which is the end point of shooting, is defined as path L2e, and a second path information D162 is generated that includes these paths L2a to L2e.
[0195] Through the above-mentioned procedure, the flight path generating unit 62 generates flight path information D16 including a flight path L consisting of the first path information D161 and the second path information D162. Note that the flight path L is not limited to the above-mentioned example, and may be a flight path L consisting of the first path information D161 and the second path information D162, for example, in which the line segment AF1 is the path L2a, the line segment E1E2 is the path L2b, the line segment F2F3 is the path L2c, the line segment E3E4 is the path L2d, and the line segment F4B is the path L2e. The unmanned aerial vehicle 2 receives the flight path information D16 via the wireless communication network 9 and stores it in the storage unit 204.
[0196] <Photographing condition acquisition step S23> In the shooting condition acquisition step S23, the shooting condition acquisition unit 63 acquires shooting condition information D17 including at least shooting altitude information D171 and number of shots information D172 of the unmanned aerial vehicle 2 based on the shooting range R included in the shooting range information D15 acquired by the shooting range acquisition unit 61 in the shooting range acquisition step S21, as shown in, for example, FIG. 18 (S231).
[0197] The control device 1 transmits the photographing condition information D17 acquired by the photographing condition acquisition unit 63 to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S232). The photographing condition information D17 transmitted by the control device 1 needs to include at least the photographing altitude information D171, and does not necessarily need to transmit the number of photographs information D172 and the photographing time information D173 by transmitting the photographing operation specification information D174 specified by the photographing operation specification unit 64 in a step described later. The unmanned aerial vehicle 2 receives the photographing condition information D17 via the wireless communication network 9 and stores it in the storage unit 204.
[0198] The photographing condition acquisition unit 63 may acquire either the photographing altitude information D171 or the photographing number information D172 first, and then acquire the other calculated by the calculation unit 66. In this case, the number of photographs can be automatically optimized to reduce the communication capacity, storage capacity, and the effort required to check the photographed content of the system. This can further improve the workability of estimating repairs, etc. of the existing building 200. Note that, when the number of photographs indicated by the acquired photographing number information D172 falls outside the threshold, the photographing condition acquisition unit 63 may reacquire at least one of the photographing altitude information D171 and the photographing number information D172 in order to optimize the number of photographs. For example, when the shooting interval (interval vertical width W3 or interval horizontal width W4 described later) of the angle of view V based on the previously acquired shooting altitude information D171 is set to 3 m and the shooting number information D172 indicating the number of shots being 30 or less is calculated, the shooting condition acquisition unit 63 may set the shooting interval to 1 m and recalculate the shooting number information D172 indicating the number of shots being more than 30. Also, when the previously acquired shooting number information D172 is more than 300, the shooting condition acquisition unit 63 may extend the shooting interval to calculate the shooting number information D172 indicating the number of shots being 300 or less. Also, when the overlap vertical width w3 and overlap horizontal width w4 of the overlapping area are greater than 0 and the maximum shooting interval is set, the shooting number information D172 indicating the number of shots being more than 300 is calculated, the existing building 200 or the shooting range R may be determined to be wider than expected and an error may be returned.
[0199] <Photographing Operation Identification Step S24> In the photographing action identification step S24, the photographing action identification unit 64 identifies the photographing action as photographing action identification information D174 on the flight path L based on the photographing number information D172 acquired by the photographing condition acquisition unit 63 in the photographing condition acquisition step S23 (S241). After that, the control device 1 transmits the photographing action identification information D174 identified by the photographing action identification unit 64 to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S242).
[0200] The photographing operation specifying unit 64 specifies the points s1 to s20 where photographing is performed according to the interval vertical width W3 and interval horizontal width W4 of the acquired photographing interval, as shown in Fig. 19(d), for example. The photographing operation specifying unit 64 determines the number of photographing positions according to the photographing number information D172 acquired by the photographing condition acquiring unit 63 (the number of photographs is 20 in the case of Fig. 19).
[0201] Note that the turn-around width W2, the interval vertical width W3, and the interval horizontal width W4 may use values set in advance without relying on the photographing altitude information D171. The interval horizontal width W4 of the photographing interval may be the same value as the turn-around width W2 of the flight path L. The interval vertical width W3 of the photographing interval may be set based on the ratio (aspect ratio) of the vertical width w1 and the horizontal width w2 of the angle of view V. That is, the interval vertical width W3 of the photographing interval may be acquired as the vertical width w1 of the angle of view × the horizontal width W4 of the angle of view / the horizontal width w2 of the angle of view, where the interval vertical width W3: the interval horizontal width W4 = the vertical width w1 of the angle of view: the horizontal width w2 of the angle of view.
[0202] In the example shown in Figure 19(d), the points corresponding to points A, E1, E2, E3, E4, and B on the flight path L and on the longest side AB are obtained as photographing points s1, s2, s10, s11, s19, and s20, and the points corresponding to points F1, F2, F3, and F4 on the flight path L and on either side AD, DC, or CB are obtained as photographing points s5, s6, s15, and s16. Also, points on route L1a that are separated from point s2 by the vertical width W3 of the shooting interval are acquired as s3 and s4, points on route L1b that are separated from point s10 by the vertical width W3 of the shooting interval are acquired as s9, s8, and s7, points on route L1c that are separated from point s11 by the vertical width W3 of the shooting interval are acquired as s12, s13, and s14, and points on route L1d that are separated from point s19 by the vertical width W3 of the shooting interval are acquired as s18 and s17. Note that when making an adjustment to reduce the number of shots, point s14 may be excluded from the shooting points because the visual information obtained by shooting at point s15 is almost the same.
[0203] Based on the above-mentioned concept, the shooting operation identification unit 64 identifies shooting operation identification information D174 including a shooting position identified based on, for example, the shooting altitude information D171 and the number of shooting information D172 acquired by the shooting condition acquisition unit 63 through input from the user U, the interval width W4 of the shooting interval similar to the turn-around width W2 of the flight path L updated using the shooting altitude information D171, and the interval vertical width W3 of the shooting interval corresponding to the interval width W4, the vertical width w1 within the angle of view, and the horizontal width w2 within the angle of view.
[0204] <Operation control step S25> In the operation control step S25, after the photographing operation specification step S24 is completed, the control device 1 generates a control signal for the unmanned aerial vehicle 2 to start photographing, and transmits it to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S251). After receiving the control signal for starting photographing from the control device 1, the operation control unit 502 controls the horizontal flight operation of the unmanned aerial vehicle 2 based on the flight path L included in the flight path information D16 generated by the flight path generation unit 62 in the flight path generation step S22 and the photographing altitude included in the photographing altitude information D171 acquired by the photographing condition acquisition unit 63 in the photographing condition acquisition step S23, and starts controlling the photographing operation of the unmanned aerial vehicle 2 based on the photographing operation included in the photographing operation specification information D174 specified by the photographing operation specification unit 64 in the photographing operation specification step S24 (S252). In other words, since the unmanned aerial vehicle 2 is automatically controlled by the operation control unit 502, the user U can be involved in work related to estimates for repairs, etc., even if he or she is unfamiliar with operating the unmanned aerial vehicle 2. Furthermore, the user U can obtain the appearance information D19 required for estimating repairs and the like without climbing onto the existing building 200 to check the dimensions and the condition of the roof, so that the work related to the estimate of repairs and the like can be performed safely and the work time can be shortened. In this case, by setting the shooting range R according to the existing building 200, the entire existing building 200 can be automatically photographed according to the generated flight path L. This can improve the workability related to the estimate of repairs and the like for the existing building 200.
[0205] 19(c)-(d), for example, the operation control unit 502 controls the flight operation of the unmanned aerial vehicle 2 to fly along flight path L, while controlling the photographing operation to photograph the existing building 200 at each of points s1-s20. This allows the construction work estimate creation system 100 to photograph substantially the entire photographing range R, and as a result, visual information on the appearance of the existing building 200 in plan view (for example, the roof, skylights, objects installed on the roof, etc.) can be obtained.
[0206] 19(c), that is, from point A to point B, in the order of the second route L2a, the first route L1a, the second route L2b, the first route L1b, the second route L2c, the first route L1c, the second route L2d, the first route L1d, and the second route L2e. At this time, the operation control unit 502 may fly at a constant speed on each route (L1a to L1d, L2a to L2e), may decelerate or accelerate midway along each route, or may decelerate or accelerate when each route switches.
[0207] The operation control unit 502 may control the photographing operation of the unmanned aerial vehicle 2, for example, without changing the flight speed at each of the points s1 to s20 shown in Figure 19 (d), or may control deceleration or acceleration so as to control the photographing operation while stationary in the air at each of the points s1 to s20.
[0208] The operation control unit 502 may control the flight operation of the unmanned aerial vehicle 2, for example, to fly at a preset flight speed or acceleration. The operation control unit 502 may control the flight operation of the unmanned aerial vehicle 2, for example, to change the flight speed or acceleration at a point corresponding to preset coordinates or at an interval corresponding to a preset distance, or to stop in the air. The operation control unit 502 may control the speed or acceleration on each route, the speed or acceleration at each point, the stop time at each point, etc., of the unmanned aerial vehicle 2, for example, to complete the flight operation and the photographing operation within a preset flight time.
[0209] The unmanned aerial vehicle 2 may appropriately transmit unmanned aerial vehicle flight information D18 acquired, for example, during a photographing operation, to the control device 1 via the wireless communication unit 11 and the wireless communication network 9 (S253).
[0210] The unmanned aerial vehicle 2 may transmit appearance information D19 acquired, for example, during a photographing operation, to the control device 1 via the wireless communication unit 11 and the wireless communication network 9 as appropriate (S254). Note that the unmanned aerial vehicle 2 may automatically transmit the appearance information D19 to the control device 1 immediately after acquiring it, or may transmit it to the control device 1 in response to a request from the control device 1.
[0211] For example, during photographing operation, the unmanned aerial vehicle 2 may calculate an evacuation route along the flight path L or depart from the flight path L and return to the takeoff position, and then appropriately transmit information regarding the calculated evacuation route to the control device 1 via the wireless communication unit 11 and the wireless communication network 9 (S255).
[0212] After completing the photographing operation, the unmanned aerial vehicle 2 returns to the takeoff position (S256). The unmanned aerial vehicle 2 may be controlled by the control device 1 to land at a position different from the takeoff position.
[0213] <Appearance information storage step S27> In the appearance information storage step S27, the unmanned aerial vehicle 2 links the appearance information D19 acquired by the operation control unit 502 in the operation control step S25, for example, with the unmanned aerial vehicle identification information D14 stored in the storage unit 204, and transmits them to the server 3. The server 3 then generates reference appearance information D72 corresponding to the received appearance information D19, or copies it as the reference appearance information D72, links it with the reference unmanned aerial vehicle identification information D71 corresponding to the received unmanned aerial vehicle identification information D14, and stores it as an appearance information table 72. In this case, it is possible to expand the scenes in which the construction work estimate creation system 100 can be applied, such as acquiring visual information of one existing building 200 using multiple unmanned aerial vehicles, or managing visual information of multiple existing buildings in one server 3. Note that some or all of the functions of the server 3 in the appearance information storage step S27 can be replaced by the functions of the control device 1.
[0214] <Authentication step S26> In the authentication step S26, the authentication unit 65 refers to the database 7 including the approval information table 75 in which the reference unmanned aerial vehicle identification information D71 and the reference approval information D77 are linked, and then certifies that the approval information corresponding to the unmanned aerial vehicle 2 is valid. After it is certified that the approval information of the unmanned aerial vehicle 2 is valid in the authentication step S26, in the operation control step S25, the operation control unit 502 controls the photographing operation of the unmanned aerial vehicle 2. In this case, it is possible to easily and reliably check whether the flight permission of the unmanned aerial vehicle 2 has been forgotten to be obtained or has expired, and to avoid or prevent illegal acts by the user U. This can improve the accuracy of compliance with laws and regulations regarding the operation of the unmanned aerial vehicle 2 used for estimating repairs and the like of the existing building 200.
[0215] When the construction work estimate creation system 100 cooperates with an external system such as DIPS or FISS, it may apply for approval of flight permission to the external system via the control device 1 or server 3, and store the status information of the application received as appropriate (pending, reapplication required, approved) and the approval information of the unmanned aircraft 2 as a result of the received approval application in the reference approval information D77. In this case, it is possible to centrally manage confirmation of the presence or absence of flight permission for the unmanned aircraft 2, application for flight permission, and acquisition of approval information. This can improve the workability until preparation for flight of the unmanned aircraft 2.
[0216] (Second embodiment: First modified example of the operation of the construction work estimate creation system 100) The operation control unit 502 may control the unmanned aerial vehicle 2 to automatically retreat to the takeoff point when the remaining charge of the battery 22 mounted on the unmanned aerial vehicle 2 falls below a preset lower limit on the flight path L generated by the flight path generation unit 62, and then to resume shooting from the point on the flight path L where the retreat began when the remaining charge of the battery 22 becomes equal to or greater than a predetermined value. Note that the remaining charge of the battery 22 may be identified, for example, by a known battery charge detector (not shown) mounted on the unmanned aerial vehicle 2 and compared with a preset lower limit, and the comparison result may be evaluated.
[0217] Specifically, for example, when the remaining charge of the battery 22 at point s10 falls below a preset lower limit (e.g., 10%) with point H shown in FIG. 19(d) as the takeoff point, the unmanned aerial vehicle 2 is caused to fly horizontally from point s10 to the sky above point H, and then landed at point H, and a request is made to exchange or charge the battery 22. Thereafter, when the remaining charge of the battery 22 reaches a predetermined value (e.g., 80%) or more, the unmanned aerial vehicle 2 may be controlled so that it takes off vertically to the ground surface at point H, lands in the sky above point H, flies horizontally to point s10 on the flight path L where the evacuation started, and resumes shooting from point s10. In this case, automatic control is possible even when shooting the exterior of an existing building 200 with larger dimensions. This can improve the workability of estimating repairs and the like regardless of the dimensions of the existing building 200.
[0218] (Second embodiment: second modified example of the operation of the construction work estimate creation system 100) When the shooting range acquisition unit 61 acquires a rectangular shooting range R in the shooting range acquisition step S21, in the operation control step S25, the operation control unit 502 may, for example, after completing the shooting operation and flight operation based on the flight path L generated by the flight path generation unit 62 in the flight path generation step S22, photograph the exterior of the existing building 200 at coordinates corresponding to the center of the longer of the diagonals of the rectangular shooting range R and at an altitude where the entire existing building 200 falls within the angle of view V.
[0219] Specifically, the operation control unit 502 controls the flight operation of the unmanned aerial vehicle 2 that has completed the flight operation and the photographing operation so that, when the photographing range R is a rectangle ABCD along the outer periphery of the existing building 200 in a plan view as shown in FIG. 20(a), for example, the operation control unit 502 controls the flight operation of the unmanned aerial vehicle 2 so that the unmanned aerial vehicle 2 flies horizontally to above a point G corresponding to the center of a diagonal line BD longer than the diagonal line AC. After that, as shown in FIG. 20(b), for example, the unmanned aerial vehicle 2 controls the photographing operation of the unmanned aerial vehicle 2 so that the unmanned aerial vehicle 2 rises to a photographing altitude at which the angle of view V of the photographing angle θ (for example, about 90°) fits the building width W5 of the diagonal line BD, and then photographs the exterior of the existing building 200. In this case, the appearance information D19 that includes the entire existing building 200 in the angle of view V at the same time as the appearance information D19 photographed on the flight path L can be easily obtained, and it is easy to prevent omissions in the photographing range R by using it instead of, for example, a roof plan. This makes it possible to improve the accuracy of estimates for repairs and the like for the existing building 200.
[0220] The shooting altitude at which the angle of view V of the shooting angle θ falls within the diagonal line BD is the sum of the height h1 connecting point G on the roof of existing building 200 and point G' in the sky above point G where camera 21 is located in Fig. 20(b), and the height h2 of existing building 200. The flight altitude of unmanned aerial vehicle 2 from the ground is height h0, which is calculated as the sum of height h1, height h2, and height h3 of unmanned aerial vehicle 2. Height h1 may be calculated by the following formula using building width W5 of diagonal line BD and shooting angle θ.
[0221]
number
[0222] (Second embodiment: Third modified example of the operation of the construction work estimate creation system 100) The construction work estimate creation system 100 may further include a determination unit (not shown) that determines the usefulness of the photographed appearance information D19, and only the appearance information D19 that the determination unit determines to be useful among the acquired appearance information D19 may be stored in the storage unit 104 or 204. In this case, the communication capacity and storage capacity of the system, as well as the effort required to check the photographed content, can be reduced by a process of discarding appearance information that is out of focus or otherwise unuseful. This can further improve the workability of estimating repairs, etc. of the existing building 200.
[0223] The judgment of usefulness by the judgment unit (not shown) can be performed in the following manner by using a publicly known image processing library such as "OpenCV (registered trademark)". For example, the "overexposure" of the appearance information D19 can be judged based on whether the HSV (hue, saturation, and brightness) of the image of the appearance information D19 is within a pre-specified threshold using an InRange function or the like. In addition, the "out-of-focus" of the appearance information D19 can be judged based on whether parameters such as Laplacian Variance, Tenengrad, Image Entropy, and Blurriness Index of the image of the appearance information D19 are obtained and whether each parameter is within a pre-specified threshold. For example, according to "Analysis of focus measure operators for shape-from-focus (2013)", there is a method of calculating the Laplace variance of the appearance information D19 and regarding the appearance information D19 as "out-of-focus" when the high-frequency components of the appearance information D19 are less than a predetermined value. In addition, the image entropy is an index indicating the disorder of the image. Since an in-focus image has more information and is more disordered than an out-of-focus image, an in-focus image has a higher image entropy. For example, there is a method in which appearance information D19' is generated by blurring the original appearance information D19, and then the image entropy is calculated for each of the appearance information D19 and the appearance information D19', and the larger the difference between the two, the more in-focus the original appearance information D19 is considered to be.
[0224] (Second embodiment: Fourth modified example of the operation of the construction work estimate creation system 100) The construction work estimate creation system 100 may further include a server 3 that receives two-dimensional appearance information showing the appearance of an existing building 200 photographed by an unmanned aerial vehicle 2, as shown in Fig. 21 for example. Here, the two-dimensional appearance information is visual information including building part appearance information D191, whole building appearance information D192, and processed appearance information D193 of two-dimensional images or two-dimensional videos among the appearance information D19, and does not include three-dimensional modeling images.
[0225] The server 3 receives the two-dimensional appearance information photographed by the unmanned aerial vehicle 2 via, for example, the wireless communication network 9, and acquires a three-dimensional modeling image showing the existing building 200 based on the received two-dimensional appearance information. Here, the server 3 is, for example, controllable independently of the control device 1 and the unmanned aerial vehicle 2, and specifically, is controllable independently of the photographing range acquisition unit 61, the flight path generation unit 62, the photographing condition acquisition unit 63, the photographing operation specification unit 64 constituting the control device 1, and the operation control unit 502 constituting the unmanned aerial vehicle 2. That is, the construction work estimate creation system 100 can control the operation of the unmanned aerial vehicle 2 without waiting until the three-dimensional modeling image showing the existing building 200 based on the two-dimensional appearance information showing the appearance of the existing building 200 is generated and acquired. In this case, the acquisition of the three-dimensional modeling image and the photographing of other existing buildings by the unmanned aerial vehicle 2 can be performed in parallel. This can further improve the workability of estimating repairs and the like for the existing building 200.
[0226] Next, an example of the operation of the construction work estimate preparation system 100 will be described.
[0227] The unmanned aerial vehicle 2 transmits two-dimensional appearance information acquired during, for example, a photographing operation to the server 3 or the control device 1 via the wireless communication unit 11 and the wireless communication network 9 (S254).
[0228] During the operation control step S25, the server 3 receives the two-dimensional appearance information directly from the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 during the photographing operation by the unmanned aerial vehicle 2 or after the photographing is completed (S25a). The server 3 may also receive the two-dimensional appearance information from the unmanned aerial vehicle 2 via the control device 1 (S25b).
[0229] Thereafter, the server 3 acquires a three-dimensional modeling image showing the existing building 200 based on the received appearance information. At this time, the server 3 may input the two-dimensional appearance information into known three-dimensional modeling image generation software stored in advance in a ROM or the like mounted on the server 3 to generate the three-dimensional modeling image showing the existing building 200 by itself and acquire the image, or may input the two-dimensional appearance information into known three-dimensional modeling image generation software stored in advance in another terminal with which the server 3 can communicate, generate the three-dimensional modeling image showing the existing building 200, and then receive the image.
[0230] (Second embodiment: Fifth modified example of the operation of the construction work estimate creation system 100) The construction work estimate creation system 100 may further include a server 3 that receives appearance information D19 indicating the appearance of an existing building 200 photographed by the unmanned aerial vehicle 2, for example, as shown in FIG.
[0231] The control device 1 may further include a transmission control unit (not shown) that controls the transmission of the appearance information D19 to the server 3, for example. That is, the control device 1 can retake the appearance information D19 and transmit it to the server 3, or transmit a plurality of pieces of appearance information D19 related to a plurality of existing buildings 200 at once. In this case, it is not necessary to wait to retake the appearance information D19 or to take pictures of other existing buildings until the transmission of the appearance information D19 is completed due to line congestion caused by the transmission of a large amount of data. This can further improve the workability of estimating the repair or the like of the existing building 200. In addition, the number of data transmissions can be reduced by retaking the appearance information D19 or transmitting a plurality of pieces of appearance information D19 at once. Furthermore, the waiting time until the transmission of the appearance information D19 is completed can be shortened by moving to a short-distance wireless communication range or the like and transmitting data. This can further improve the workability of estimating the repair or the like of the existing building 200.
[0232] Next, an example of the operation of the construction work estimate preparation system 100 will be described.
[0233] The unmanned aerial vehicle 2 transmits appearance information D19 acquired during, for example, a photographing operation to the control device 1 via the wireless communication unit 11 and the wireless communication network 9 (S254). Thereafter, the control device 1 performs steps similar to steps S21-24 for other existing buildings without transmitting the appearance information D19 received from the unmanned aerial vehicle 2 to the server 3, and then performs an operation control step S25' for photographing other appearance information showing the appearances of the other existing buildings. Note that the operation control step S25' has the same content as the above-mentioned operation control step S25 for the existing building 200. Furthermore, the other appearance information indicates information similar to the appearance information D19.
[0234] In detail, in the operation control step S25', the control device 1 generates a control signal for the unmanned aerial vehicle 2 to start photographing another existing building, and transmits the control signal to the unmanned aerial vehicle 2 via the wireless communication unit 11 and the wireless communication network 9 (S251'). After that, the unmanned aerial vehicle 2 starts photographing another existing building (S252'), transmits the unmanned aerial vehicle flight information D18 acquired during the photographing operation to the control device 1 as appropriate (S253'), and may transmit other appearance information acquired during the photographing operation to the control device 1 as appropriate (S254'). After that, the control device 1 may transmit the appearance information D19 received from the unmanned aerial vehicle 2 in the operation control step S25 and the other appearance information received from the unmanned aerial vehicle 2 in the operation control step S25' to the server 3 in a lump (S25d). Also, the server 3 may receive the appearance information D19 and the other appearance information transmitted from the control device 1 in a lump (S25e). This photographing method reduces the number of times data is transmitted, and the workability of estimating repairs, etc. for the existing building 200 can be further improved.
[0235] When retaking the appearance information D19, the control device 1 may perform an operation control step S25' of retaking the appearance information D19 for the same existing building 200, omitting the same steps as steps S21 to S24, without transmitting the appearance information D19 received from the unmanned aerial vehicle 2 in the operation control step S25 to the server 3. Thereafter, the control device 1 may transmit the retaken appearance information D19 received from the unmanned aerial vehicle 2 in the operation control step S25' to the server 3, and discard the appearance information D19 before the retake received from the unmanned aerial vehicle 2 in the operation control step S25 without transmitting it to the server 3. This photographing method reduces the number of data transmissions, and can further improve the workability of estimating repairs and the like for the existing building 200.
[0236] The unmanned aerial vehicle 2 may further include a transmission control unit (not shown) that controls the transmission of the appearance information D19 to the control device 1. That is, the unmanned aerial vehicle 2 can retake the appearance information D19 and then transmit it to the control device 1, or transmit a plurality of pieces of appearance information D19 relating to a plurality of existing buildings 200 at once. In this case as well, there is no need to wait to retake the appearance information D19 or to photograph other existing buildings 200 until the transmission of the appearance information D19 is complete, and the number of data transmissions can be reduced. Furthermore, by moving within a short-range wireless communication range or the like to transmit data, the waiting time can be shortened, and therefore the workability of estimating repairs, etc. for the existing building 200 can be further improved.
[0237] (Second embodiment: Sixth modified example of the operation of the construction work estimate creation system 100) 23, the calculation unit 18 calculates the shooting altitude based on the shooting interval In of the unmanned aerial vehicle 2 and a set overlap width that is preset as an overlap width (width of overlapping area) where the angles of view V of the unmanned aerial vehicle 2 at two adjacent points separated by the shooting interval In overlap with each other. Note that the set overlap width may be preset, for example, in the unmanned aerial vehicle 2, or may be preset in any of the components of the construction work estimate creation system 100.
[0238] At this time, the photographing condition acquisition unit 63 acquires the photographing interval In and then acquires the photographing altitude calculated by the calculation unit 18. That is, by acquiring the photographing interval In, the photographing altitude is automatically calculated according to the overlap width (overlap value) of the overlapping area set in advance. In this case, the appearance information D19 can be acquired with a minimum number of photographs (number of photographs) while satisfying a predetermined overlap value for the large existing building 200, and the data capacity of the appearance information D19 is reduced, so that the waiting time until the transmission of the appearance information D19 is completed can be shortened. This makes it possible to further improve the workability regarding the estimate for repairs, etc. of the existing building 200. Note that the overlap width may be a value sufficient for estimating a three-dimensional scene from a two-dimensional image using, for example, the above-mentioned SfM, and may be set to, for example, about 2 meters or more in actual measurement.
[0239] First, an example of information accompanying the operation of the construction work estimate creation system 100 will be described. The construction work estimate creation system 100 uses shooting condition information D17 including shooting interval information indicating the shooting interval In and set overlap width information indicating the set overlap width. The shooting interval information and the set overlap width information may be stored in advance in each component of the construction work estimate creation system 100, or may be stored by accepting input from the user U. The set overlap width indicates a value required, for example, as processed appearance information D193, when generating visual information showing the entire existing building 200 by synthesizing multiple building part appearance information D191, or when generating a three-dimensional modeling image of the existing building 200 based on the two-dimensional appearance information.
[0240] As an example of the photographing interval information and the set overlap width information, FIG. 23(a) shows the photographing altitude calculated by the calculation unit 18 based on the photographing interval In and the set overlap width (calculated photographing altitude) before application, and FIG. 23(b) shows the photographing altitude after application. Note that FIG. 23(a) to FIG. 23(b) are side views corresponding to points P1 and P2 in the plan view of FIG. 15(a).
[0241] 20, and the angles of view V1 and V2 are set for the unmanned aerial vehicle 2 in the sky above the points P1 and P2 on the roof of the existing building 200. The shooting angle θ, the vertical width w1 within the angle of view, the height h1 from the roof to the camera 21 of the unmanned aerial vehicle 2 at the points P11 and P21 above before the application of the calculated shooting altitude, the height h2 of the existing building 200, and the adjusted height h4 of the unmanned aerial vehicle 2 from the points P11 and P21 above to the points P12 and P22 above before and after the application of the calculated shooting altitude are set to the same values at the points P1 and P2. At this time, the sum of the heights h1 and h2 is the shooting altitude before the application of the calculated shooting altitude, and the sum of the heights h1, h2, and the adjusted height h4 is the calculated shooting altitude. The angles of view V1 and V2 are in the shape of a regular square pyramid with a shooting angle θ of approximately 90°, and are symmetrical with respect to the vertical direction in the side view shown in Figures 23(a) and 23(b). In this case, the distance from point P1 to the outer edge of the angle of view V1 and the distance from point P2 to the outer edge of the angle of view V2 are both w1 / 2. The overlapping vertical width w3 is the width in the flight direction of the overlapping area between the angle of view V1 at points P11 and P12 in the sky above point P1 and the angle of view V2 at points P21 and P22 in the sky above point P2.
[0242] In this case, the unmanned aerial vehicle 2 before the application of the calculated shooting altitude flies from an overhead point P11 toward an overhead point P21 while maintaining the shooting altitude, for example, as shown in FIG. 23(a). At this time, the overlap vertical width w3=w1 / 2+w1 / 2-In, that is, the overlap vertical width w3=vertical width within the angle of view w1-shooting interval In. Here, if the overlap vertical width w3 does not satisfy the set overlap vertical width w3' in the flight direction among the preset overlap widths, it is necessary to correct at least one of the shooting interval In and the vertical width within the angle of view w1. However, since the vertical width within the angle of view w1 is a parameter that can be changed by adjusting the shooting altitude, the calculation unit 18 calculates the calculated shooting altitude or the adjusted height h4, and therefore the operation of the unmanned aerial vehicle 2 can be controlled so as to satisfy the set overlap vertical width w3' at any shooting interval In.
[0243] Next, an example of the operation of the construction work estimate preparation system 100 will be described.
[0244] In the photographing condition acquisition step S23, the photographing condition acquisition unit 63 acquires photographing condition information D17 including photographing interval information and set overlap width information of the unmanned aerial vehicle 2. After that, the calculation unit 18 calculates the calculated photographing altitude based on the photographing interval information and set overlap width information previously acquired by the photographing condition acquisition unit 63. In addition, the photographing condition acquisition unit 63 acquires the calculated photographing altitude calculated by the calculation unit 18.
[0245] Then, in an operation control step S25, the operation control unit 502 receives a control signal to start shooting from the control device 1, and then controls the flight operation of the unmanned aircraft 2 based on the flight path L contained in the flight path information D16 generated by the flight path generation unit 62 in the flight path generation step S22 and the calculated shooting altitude contained in the shooting altitude information D171 acquired by the shooting condition acquisition unit 63 in the shooting condition acquisition step S23.
[0246] In detail, as shown in FIG. 23(b), for example, the unmanned aerial vehicle 2 ascends from the sky point P11 to the sky point P12, which is above the adjusted height h4 and corresponds to the calculated shooting altitude, and then flies toward the sky point P22 while maintaining the calculated shooting altitude. At this time, the relationship is: vertical width within the angle of view w1'=shooting interval In+set overlap vertical width w3'. In this way, by calculating the shooting altitude that satisfies the vertical width within the angle of view w1', the unmanned aerial vehicle 2 can complete acquisition of the exterior information D19 with a minimum number of shots (number of shots) while satisfying a predetermined overlap value for the large existing building 200. Note that, when the adjusted height h4 is less than 0, that is, the calculated shooting altitude is lower than the shooting altitude, it is preferable to descend from the sky point P11 by the adjusted height h4 and then fly while maintaining the calculated shooting altitude, since it is possible to acquire clearer exterior information D19 while satisfying the predetermined overlap value.
[0247] Furthermore, depending on the calculated shooting altitude, when the appearance information D19 becomes unclear at some shooting points of the existing building 200 due to being too far away from the existing building 200, the unmanned aerial vehicle 2 may be manually flown to the shooting point and a close-up image may be supplemented to the appearance information D19. Furthermore, a three-dimensional modeling image with no blurring may be generated by using the appearance information D19 acquired by the unmanned aerial vehicle 2 under the control of the operation control unit 502 and the supplemented image taken by the unmanned aerial vehicle 2 manually.
[0248] According to this embodiment, the construction work estimate creation system 100 includes an operation control unit 502 that controls the flight operation of the unmanned aerial vehicle 2 based on the flight path L generated based on the acquired shooting range R and the acquired shooting altitude, and controls the shooting operation of the unmanned aerial vehicle 2 based on the shooting operation specified based on the acquired number of shots. Therefore, by setting the shooting range R to match the existing building 200, the entire existing building 200 can be automatically photographed according to the generated flight path L. This can improve the workability of estimating repairs and the like for the existing building 200.
[0249] Furthermore, according to this embodiment, the flight path generating unit 62 generates a flight path L that includes a direction that is approximately perpendicular to the longest side AB among the sides of the acquired polygonal shooting range R. This simplifies the process compared to the calculation of the flight path L based on a side other than the longest side AB, and the flight path L can be generated efficiently. This improves the efficiency of estimating repairs and the like for the existing building 200.
[0250] According to this embodiment, the operation control unit 502 automatically evacuates the unmanned aerial vehicle 2 to the takeoff point when the remaining charge of the battery 22 falls below a preset lower limit on the flight path L, and then resumes image capture from the point on the flight path L where the evacuation began when the remaining charge of the battery 22 reaches a predetermined value or more. This makes it possible to control the flight and image capture operations of the unmanned aerial vehicle 2 for a longer period of time. This makes it possible to improve the workability of estimating repairs and the like even for larger existing buildings 200.
[0251] Moreover, according to this embodiment, the system further includes a server 3 that can be controlled independently of the operation control unit 502 and the like, receives two-dimensional appearance information photographed by the unmanned aerial vehicle 2 via the wireless communication network 9, and acquires a three-dimensional modeling image showing the existing building 200 based on the received two-dimensional appearance information. That is, the operation of the unmanned aerial vehicle 2 can be controlled without waiting until the three-dimensional modeling image showing the existing building 200 based on the two-dimensional appearance information is generated and acquired. Therefore, the acquisition of the three-dimensional modeling image and the photographing of other existing buildings 200 by the unmanned aerial vehicle 2 can be carried out in parallel. This makes it possible to further improve the workability of estimating repairs and the like for the existing building 200.
[0252] According to the present embodiment, the unmanned aerial vehicle further includes a server 3 that receives the appearance information D19 photographed by the unmanned aerial vehicle 2 via the wireless communication network 9, and a transmission control unit that controls the transmission of the appearance information D19 to the server 3. That is, the appearance information D19 can be re-photographed and then transmitted, or multiple pieces of appearance information D19 relating to multiple existing buildings 200 can be collectively transmitted. Therefore, it is not necessary to wait to re-photograph the appearance information D19 or to photograph other existing buildings until the transmission of the appearance information D19 is completed due to line congestion caused by the transmission of large amounts of data. This can further improve the workability of estimating repairs, etc. of the existing building 200. In addition, the number of data transmissions can be reduced by re-photographing the appearance information D19 or collectively transmitting multiple pieces of appearance information D19. Furthermore, the waiting time until the transmission of the appearance information D19 is completed can be shortened by moving to a short-distance wireless communication range or the like and transmitting data. This can further improve the workability of estimating repairs, etc. of the existing building 200.
[0253] Furthermore, according to this embodiment, the operation control unit 502 controls the shooting operation of the unmanned aerial vehicle 2 after the authentication unit 65 authenticates that the approval information is valid. This makes it possible to easily and reliably check whether flight permission for the unmanned aerial vehicle 2 has been forgotten or has expired, and to avoid or prevent illegal acts by the user U. This makes it possible to improve the accuracy of compliance with laws and regulations regarding the operation of the unmanned aerial vehicle 2 used to estimate repairs and the like for the existing building 200.
[0254] Furthermore, according to this embodiment, the operation control unit 502 controls the photographing operation of the unmanned aerial vehicle 2 after either the number of photographs based on the acquired photographing altitude or the photographing altitude based on the acquired number of photographs is calculated. This makes it possible to automatically optimize the number of photographs, thereby reducing the communication capacity and storage capacity of the system and the effort required to check the photographed content. This makes it possible to further improve the workability of estimating repairs and the like for the existing building 200.
[0255] According to this embodiment, the unmanned aerial vehicle 2 further includes a calculation unit 18 that calculates the shooting altitude based on the shooting interval In of the unmanned aerial vehicle 2 and a preset overlap width, and the shooting condition acquisition unit 63 acquires the shooting altitude calculated by the calculation unit 18 after acquiring the shooting interval In. That is, the shooting altitude is automatically calculated according to the preset overlap width (overlap value) by acquiring the shooting interval In. Therefore, it is possible to complete acquisition of the appearance information D19 with a minimum number of shootings (number of shots) while satisfying a predetermined overlap value for a large existing building 200, and since the data capacity of the appearance information D19 is reduced, the waiting time until the transmission of the appearance information D19 is completed can be shortened. This can further improve the workability regarding estimates for repairs and the like of the existing building 200.
[0256] Although some embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These novel embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the spirit of the invention. These embodiments and their modifications are included in the scope and spirit of the invention, and are included in the scope of the invention and its equivalents described in the claims. [Explanation of symbols]
[0257] 100 Construction work estimate creation system 200 Existing buildings 1 Control device 10. Chassis 101, 201 CPU 102, 202 ROM 103, 203 RAM 104, 204 Preservation Department 105~107, 205 I / F 108 Input section 109 Display section 110, 210 Internal Bus 11 Wireless Communication Section 12 Storage section 13 Construction Scope Acquisition Department 14 Building Materials Information Acquisition Department 15 Building Materials Quantity Calculation Department 16 Unit Price Acquisition Department 17 Construction work cost output section 61 Shooting range acquisition unit 62 Flight route generation unit 63 Shooting condition acquisition unit 64 Shooting action identification unit 65 Authentication Department 66 Calculation section 2 Unmanned aerial vehicle 20 Control Unit 21 Camera 22 Battery 23 Rotor motor 50 Flight Controller 501 Sensor information acquisition unit 502 Motion control section 51 Wireless Communication Department 52 Storage section 53 ESC 3 Server 7 Database 71 Unmanned Aerial Vehicle Information Table 72 Appearance Information Table 73 Construction Work Information Table 74 Building material construction information table 75 Approval Information Table 9 Wireless communication network S11 Construction scope acquisition step S12 Building material information acquisition step S13 Building material quantity calculation step S14 Unit price acquisition step S15 Construction work cost output step S21 Shooting range acquisition step S22 Flight route generation step S23 Shooting condition acquisition step S24 Shooting action identification step S25 Motion control step S26 Authentication Step S27: Appearance information storage step D11 Construction Information D12 Building material information D13 Construction cost D14 Unmanned Aerial Vehicle Identification Information D15 Shooting range information D16 Flight Route Information D17 Shooting Condition Information D18 Unmanned Aircraft Flight Information D19 Appearance Information D71 Reference Unmanned Aircraft Identification Information D72 Reference Appearance Information D73 Reference building work identification information D74 Reference Construction Information D75 Reference building material information D76 Construction information for reference D77 Reference approval information
Claims
1. In a construction work estimate creation system using an unmanned aerial vehicle, an estimate is created for new construction work on an existing building using an unmanned aerial vehicle. a construction scope acquisition unit that acquires a construction scope of a construction work specified from exterior information showing an exterior of an existing building photographed by the unmanned aerial vehicle; A building material information acquisition unit that acquires identification information of building materials to be used in the construction work specified by a user; A building material quantity calculation unit that calculates the number of pieces of the building material to be used in the construction work from the construction scope acquired by the construction scope acquisition unit and the identification information of the building material acquired by the building material information acquisition unit; a unit price acquisition unit that refers to a database in which identification information of a building material is linked to the unit price of the building material and the unit price of construction work in advance, and acquires from the database the unit price of the building material and the unit price of construction work corresponding to the identification information of the building material acquired by the building material information acquisition unit; a construction work cost output unit that outputs a construction work cost according to the number of pieces of the construction material calculated by the construction material number calculation unit, the unit price of the construction material acquired by the unit price acquisition unit, and the unit price of the construction work; To be prepared A construction work estimate creation system using unmanned aerial vehicles.
2. The building material information acquisition unit acquires characteristics of the building material to be used in the construction work specified by the user, and acquires identification information of the building material corresponding to the acquired characteristics of the building material from a database in which the characteristics of the building material and identification information of the building material are previously associated with each other.
2. A construction work estimate creation system using an unmanned aerial vehicle as claimed in claim 1.
3. The construction area acquisition unit further acquires a construction area of the building construction specified by the user, The building material information acquisition unit refers to a database in which characteristics of building materials, construction areas, and identification information of building materials are previously associated with each other, and acquires, from the database, identification information of the building materials corresponding to the characteristics of the building materials and the construction areas acquired by the construction area acquisition unit.
3. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 2.
4. The construction area acquisition unit further acquires a construction area of the building construction specified by the user, The unit price acquisition unit refers to a database in which identification information of building materials, a construction area, and a unit price of construction are previously linked, and acquires from the database a unit price of construction corresponding to the identification information of the building materials acquired by the building material information acquisition unit and the construction area acquired by the construction scope acquisition unit.
2. A construction work estimate creation system using an unmanned aerial vehicle as claimed in claim 1.
5. Unmanned aerial vehicles and a photographing range acquisition unit for acquiring a planar photographing range of the unmanned aerial vehicle; a flight path generating unit that generates a horizontal flight path of the unmanned aerial vehicle based on the shooting range acquired by the shooting range acquisition unit; a photographing condition acquisition unit that acquires a photographing altitude and a number of photographs in the photographing range acquired by the photographing range acquisition unit; a photographing operation identification unit that identifies a photographing operation on the flight path based on the number of photographs acquired by the photographing condition acquisition unit; an operation control unit that controls a flight operation of the unmanned aerial vehicle based on the flight path generated by the flight path generation unit and the shooting altitude acquired by the shooting condition acquisition unit, and controls the shooting operation of the unmanned aerial vehicle based on the shooting operation identified by the shooting operation identification unit; Further equipped with The construction area acquisition unit acquires a construction area of the construction work specified from the appearance information photographed by the unmanned aerial vehicle controlled by the operation control unit. A construction work estimate creation system using the unmanned aerial vehicle according to any one of claims 1 to 4.
6. The imaging range acquisition unit acquires the imaging range having a polygonal shape, The flight path generation unit generates the flight path including a direction substantially perpendicular to the longest side of each side of the polygonal shooting range acquired by the shooting range acquisition unit.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
7. The operation control unit controls the operation of the unmanned aerial vehicle so that, when the remaining charge of the battery mounted on the unmanned aerial vehicle falls below a preset lower limit on the flight path generated by the flight path generation unit, the unmanned aerial vehicle automatically retreats to a takeoff point, and when the remaining charge of the battery thereafter reaches a predetermined value or more, the unmanned aerial vehicle resumes photographing from the point on the flight path where the retreat began.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
8. The unmanned aerial vehicle further includes a server that is controllable independently of the shooting range acquisition unit, the flight path generation unit, the shooting condition acquisition unit, the shooting operation identification unit, and the operation control unit, receives two-dimensional appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle via a wireless communication network, and acquires a three-dimensional modeling image showing the existing building based on the received two-dimensional appearance information.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
9. A server that receives, via a wireless communication network, appearance information showing the appearance of the existing building photographed by the unmanned aerial vehicle; a transmission control unit that controls transmission of the appearance information to the server; Further, 6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
10. The system further includes an authentication unit that, by referring to a database in which unmanned aircraft identification information that identifies the unmanned aircraft is linked to approval information indicating flight permission for the unmanned aircraft in a Drone / UAS Information Platform System (DIPS) or a Flight Information Sharing System (FISS), authenticates that the approval information corresponding to the unmanned aircraft is valid; The operation control unit controls the operation of the unmanned aerial vehicle after the authentication unit authenticates that the approval information is valid.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
11. A calculation unit that calculates the number of shots based on the shooting altitude or the shooting altitude based on the number of shots, The photographing condition acquisition unit acquires either one of the number of photographs and the photographing altitude first, and then acquires the other calculated by the calculation unit.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
12. A calculation unit that calculates the photographing altitude based on a photographing interval of the unmanned aerial vehicle and a preset overlap width that is a width where the angles of view of the unmanned aerial vehicle at two adjacent points separated by the photographing interval overlap each other, The photographing condition acquisition unit acquires the photographing interval and then acquires the photographing altitude calculated by the calculation unit.
6. A construction work estimate preparation system using an unmanned aerial vehicle as claimed in claim 5.
13. A method for preparing an estimate for construction work on an existing building using an unmanned aerial vehicle, comprising: A construction scope acquisition step for acquiring a construction scope of a building construction project designated from exterior information showing an exterior of an existing building photographed by the unmanned aerial vehicle; A building material information acquisition step of acquiring identification information of building materials to be used in the construction work designated by a user; A building material quantity calculation step of calculating the number of parts of the building materials to be used in the construction work from the construction scope acquired in the construction scope acquisition step and the identification information of the building materials acquired in the building material information acquisition step; A unit price acquisition step of acquiring the unit price of the building material and the unit price of the construction work corresponding to the identification information of the building material acquired by the building material information acquisition step by referring to a database in which the identification information of the building material, the unit price of the building material, and the unit price of the construction work are linked in advance; a construction work cost output step of outputting a construction work cost according to the number of parts of the building material calculated by the construction material number calculation step, the unit price of the building material acquired by the unit price acquisition step, and the unit price of the construction work; Having A method for preparing an estimate for construction work using an unmanned aerial vehicle, comprising:
14. In a program for creating an estimate for construction work on an existing building using an unmanned aerial vehicle, A construction scope acquisition step for acquiring a construction scope of a building construction project designated from exterior information showing an exterior of an existing building photographed by the unmanned aerial vehicle; A building material information acquisition step of acquiring identification information of building materials to be used in the construction work designated by a user; A building material quantity calculation step of calculating the number of parts of the building materials to be used in the construction work from the construction scope acquired in the construction scope acquisition step and the identification information of the building materials acquired in the building material information acquisition step; A unit price acquisition step of acquiring the unit price of the building material and the unit price of the construction work corresponding to the identification information of the building material acquired by the building material information acquisition step by referring to a database in which the identification information of the building material, the unit price of the building material, and the unit price of the construction work are linked in advance; a construction work cost output step of outputting a construction work cost according to the number of parts of the building material calculated by the construction material number calculation step, the unit price of the building material acquired by the unit price acquisition step, and the unit price of the construction work; to have a computer execute A program for creating construction work estimates using unmanned aerial vehicles.
Citation Information
Patent Citations
System, device, and method for additional construction adjustment, program, and data recording medium
JP2002297694A
Work support system, work support method and work support program
JP2018197998A
Method for measuring building
JP2020012774A
Estimation preparing system for roof painting or waterproof construction
JP2018055351A