Impurity removing unit, and melting furnace, holding furnace, or transfer channel of molten metal equipped with impurity removing unit

By designing an impurity removal unit with an obstacle with a flow hole between the holding furnace chamber and the pumping outlet chamber, the problem of movement of floating substances and precipitated substances is solved, effective decontamination of metal liquids is achieved, and the quality of castings is improved.

JP2025072928AActive Publication Date: 2025-05-12NIPPON CRUCIBLE CO LTD TOKIO TOKYO +2
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2023183417
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-10-25
Publication Date
2025-05-12
Estimated Expiration
2043-10-25

AI Technical Summary

Technical Problem

The prior art is difficult to effectively inhibit the movement of floating substances and precipitated substances from the holding furnace chamber to the pumping outlet chamber, causing pollutants to mix into the metal liquid in the pumping outlet chamber, affecting the quality of the casting products.

Method used

An impurity removal unit with at least two obstacles is designed, and the obstacles are arranged in the direction of the flow of the metal liquid, with a flow hole at the bottom and a flow hole at the top allowing the metal liquid to pass while preventing the movement of the floating substance and the precipitated substance.

Benefits of technology

The floating and precipitated substances in the furnace chamber are effectively removed to prevent them from entering the pump out chamber, thereby improving the quality of the castings and ensuring the purity of the metal liquid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2025072928000001_ABST
    Figure 2025072928000001_ABST
Patent Text Reader

Abstract

To provide an impurity removing unit capable of preventing impurities from being mixed into molten metal.SOLUTION: An impurity removing unit 10 is installed on bottom walls 20, 30 surrounded with side walls 21, 31 and allowing molten metal to move thereabove in one direction. The impurity removing unit 10 includes at least two barriers 11, spaced apart along a direction of movement of the molten metal, for blocking the movement of the molten metal. Among the at least two barriers 11, a first flow passage 12 through which the molten metal can pass is formed in a lower portion of the barrier 11A located upstream of the movement direction of the molten metal; and a second flow passage 13 through which the molten metal can pass is formed in an upper portion of at least the other barrier 11B.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an impurity removal unit, and to a melting furnace, a holding furnace, or a transfer trough for molten metal that is equipped with an impurity removal unit. [Background technology]

[0002] For example, a melting and holding furnace includes a melting chamber for melting metals such as aluminum and aluminum alloys, a holding chamber for receiving the molten metal (so-called "molten metal") from the melting chamber and holding it at high temperature, and a pumping chamber for pumping out the molten metal. The holding chamber and the pumping chamber are arranged adjacent to each other and are separated by a partition wall, and the molten metal can move from the holding chamber to the pumping chamber through a communication part below the partition wall and above the bottom wall. The molten metal pumped out from the pumping chamber is used for casting, etc.

[0003] The molten metal in the holding chamber contains foreign matter such as oxides and hard spots as impurities. If the impurities move from the holding chamber to the pumping chamber together with the molten metal, the impurities will be mixed into the molten metal pumped out of the pumping chamber, and if the molten metal containing the impurities is used for casting or the like, it will cause a defective product. As such, since the quality of the molten metal has an important effect on the quality of castings and the like, measures are required to prevent the impurities from moving from the holding chamber to the pumping chamber together with the molten metal.

[0004] Patent Document 1 discloses a melting and holding furnace in which a step protruding above the bottom wall of the holding chamber is formed at the connection between the bottom wall of the pumping chamber side and the bottom wall of the holding chamber side below the partition wall, and a communication part is configured to open above the step. In the melting and holding furnace of Patent Document 1, even if precipitates in the holding chamber move to the pumping chamber together with the molten metal when the molten metal in the holding chamber moves to the pumping chamber, the movement of the precipitates is stopped at the step between the holding chamber and the pumping chamber, and the movement to the pumping chamber is restricted. In this way, the melting and holding furnace of Patent Document 1 prevents impurities from being mixed into the molten metal in the pumping chamber. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2019-109024 A Summary of the Invention [Problem to be solved by the invention]

[0006] Impurities present in the holding chamber include precipitates that sink to the bottom wall and accumulate, as well as suspended matter that floats on the surface of the molten metal. In the melting and holding furnace of Patent Document 1, the movement of precipitates in the holding chamber to the pumping chamber can be sufficiently restricted, but the movement of suspended matter cannot be sufficiently restricted. For example, when the molten metal in the holding chamber is stirred for flux treatment, suspended matter floating on the surface of the molten metal may move below the partition wall and move from the communication part to the pumping chamber. Or, when the molten metal in the pumping chamber is pumped out, the level of the molten metal in the holding chamber drops, and at this time, suspended matter floating on the surface of the molten metal may move below the partition wall and move from the communication part to the pumping chamber.

[0007] Thus, the melting and holding furnace of Patent Document 1 has a problem in that it is not possible to sufficiently prevent impurities from being mixed into the molten metal in the pumping chamber. This problem also exists in holding furnaces that do not have a melting chamber.

[0008] The present invention has been made with a focus on solving the above problems, and aims to provide an impurity removal unit that can suppress the mixing of impurities into molten metal. Another aim of the present invention is to provide a melting and holding furnace or holding furnace (hereinafter, in this disclosure, the melting and holding furnace is also included in the holding furnace and is simply referred to as a "holding furnace") equipped with an impurity removal unit to suppress the mixing of impurities into the molten metal in the pumping chamber. Another aim of the present invention is to provide a melting furnace equipped with an impurity removal unit to suppress the mixing of impurities into the molten metal flowing out from the melting furnace. Another aim of the present invention is to provide a transfer trough equipped with an impurity removal unit to remove impurities mixed into the molten metal delivered from a melting furnace or the like to various supply destinations. [Means for solving the problem]

[0009] In order to solve the above problems, the present invention provides an impurity removal unit as described in item 1 below.

[0010] Item 1. An impurity removal unit that is surrounded by a side wall and is installed on a bottom wall above which molten metal can move in one direction, at least two barriers spaced apart along a direction of movement of the molten metal, the at least two barriers blocking the movement of the molten metal; An impurity removal unit, wherein a first passage hole through which the molten metal passes is formed in the lower part of the barrier located most upstream in the direction of movement of the molten metal among the at least two barriers, and a second passage hole through which the molten metal passes is formed in the upper part of at least one of the other barriers.

[0011] Furthermore, the impurity removal unit of the present invention includes an impurity removal unit described in the following item 2 as a preferred embodiment of the impurity removal unit described in item 1 above.

[0012] Item 2. The impurity unit according to item 1, a base resting on the bottom wall, the at least two barrier walls standing on the base; a pair of guides extending from the base and sandwiching the at least two barriers from both sides; an impurity unit, wherein the base, the at least two barriers and the pair of guides are integrated together;

[0013] Furthermore, the impurity unit of the present invention includes, as a preferred embodiment of the impurity removal unit described in item 2 above, an impurity removal unit described in item 3 below.

[0014] Item 3. The impurity unit according to item 2, wherein an embedding portion for embedding a heater is formed in at least one of the pair of guides and / or the base.

[0015] Furthermore, the impurity removal unit of the present invention includes, as a preferred embodiment of the impurity removal unit described in item 2 or 3 above, an impurity removal unit described in item 4 below.

[0016] Item 4. A degassing device including a gas introduction pipe through which an insoluble gas is introduced and a bubble generator that generates bubbles of the insoluble gas, Item 4. The impurity unit according to item 2 or 3, wherein the gas introduction pipe extends along one of the pair of guides, and the bubble generator is attached to the base so as to emit bubbles above the base.

[0017] In order to solve the above problems, the present invention also provides a holding furnace as described in item 5 below.

[0018] Item 5. A holding furnace having at least a holding chamber for holding molten metal and a pumping chamber for pumping out the molten metal flowing from the holding chamber, A holding furnace comprising the impurity removal unit according to any one of items 1 to 4, which is installed on the bottom wall of the pumping chamber or the bottom wall of the holding chamber.

[0019] In the holding furnace described in item 5, the impurity removal unit is preferably removably installed on the bottom wall of the pumping chamber or the bottom wall of the holding chamber, but may be integrated with the bottom wall of the pumping chamber or the bottom wall of the holding chamber.

[0020] In order to solve the above problems, the present invention also provides a melting furnace as described in item 6 below.

[0021] Item 6. A melting furnace equipped with a melting chamber for melting metals, A melting furnace comprising an impurity removal unit according to any one of items 1 to 4, installed on a bottom wall of the melting chamber.

[0022] In the melting furnace described in item 6, the impurity removal unit is preferably removably installed on the bottom wall of the melting chamber, but may be integrated with the bottom wall of the melting chamber.

[0023] In order to solve the above problems, the present invention also provides a transfer trough as described in item 7 below.

[0024] Item 7. A transfer trough for transferring molten metal, A transfer trough comprising an impurity removal unit according to any one of items 1 to 4, installed on a bottom wall of the transfer trough.

[0025] In the transfer gutter described in item 7, the impurity removal unit is preferably removably installed on the bottom wall of the transfer gutter, but may be integrated with the bottom wall of the transfer gutter. Effect of the Invention

[0026] According to the impurity removal unit of the present invention, it is possible to effectively remove impurities such as precipitates and floating matter mixed in the molten metal. Therefore, for example, in a holding furnace equipped with an impurity removal unit, it is possible to prevent impurities from being mixed into the molten metal in the pumping chamber, in a melting furnace equipped with an impurity removal unit, it is possible to prevent impurities from being mixed into the molten metal flowing out of the melting furnace, and in a transfer trough equipped with an impurity removal unit, it is possible to prevent impurities from being mixed into the molten metal delivered from a melting furnace or the like to various supply destinations. [Brief description of the drawings]

[0027] [Figure 1] FIG. 1 shows a schematic diagram of the holding furnace. [Diagram 2] FIG. 2 shows a perspective view of the impurity removal unit. [Diagram 3] FIG. 3 shows a plan view of the impurity removal unit. [Figure 4] FIG. 4 is a perspective view of a cross section taken along line AA in FIG. [Diagram 5] FIG. 5 is a perspective view of the cross section taken along line BB in FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0028] The impurity removal unit of the present invention is for removing impurities mixed in the molten metal from the molten metal. The impurities include precipitates that sink to the bottom of the molten metal as well as suspended matter that floats on the surface of the molten metal. In other words, the impurity removal unit of the present invention can effectively remove precipitates that sink to the bottom of the molten metal and suspended matter that floats on the surface of the molten metal from the molten metal.

[0029] The impurity removal unit of the present invention can be applied to, for example, a melting furnace for melting metals such as aluminum and aluminum alloys, a holding furnace (including a melting and holding furnace) for holding molten metal, which is molten metal, at high temperature, and a transfer trough for distributing molten metal from a melting furnace to various destinations. In a melting furnace, it is possible to prevent impurities from being mixed into the molten metal flowing out of the melting furnace through the outlet from the inside of the melting furnace. In a holding furnace, it is possible to prevent impurities from being mixed into the molten metal that flows from the holding chamber into the pumping chamber and is pumped out. In a transfer trough, it is possible to prevent impurities from being mixed into the molten metal that is distributed to various destinations from a melting furnace. The impurity removal unit of the present invention can be applied to various machines, instruments, tools, and the like in which molten metal is present in a recess surrounded by side walls on the bottom wall and the molten metal can move in one direction above the bottom wall.

[0030] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. In the following embodiments, an example in which an impurity removal unit of the present invention is applied to a holding furnace will be described.

[0031] 1 shows a schematic configuration of a holding furnace 1 equipped with an impurity removal unit 10 of this embodiment. The holding furnace 1 includes at least a holding chamber 2 for holding molten metal, such as aluminum or an aluminum alloy, at a high temperature, and a pumping chamber 3 for pumping out the molten metal. The molten metal is supplied from a melting furnace, for example, via a transfer trough. Alternatively, if the holding furnace 1 is a melting and holding furnace further equipped with a melting chamber for melting metal, the molten metal is supplied to the holding chamber 2 from the melting chamber.

[0032] The holding chamber 2 is in the shape of a container with an opening at the top, and includes a bottom wall 20 and a side wall 21. The holding chamber 2 holds the molten metal in a space surrounded by the side wall 21 and above the bottom wall 20. A lid 22 is removably provided at the top of the holding chamber 2. The top opening of the holding chamber 2 is closed by the lid 22 so as to be freely opened and closed. A heater 4 such as a burner or heater is attached to the lid 22. The molten metal in the holding chamber 2 is heated by the heater 4 and held at a temperature higher than the melting temperature of the metal.

[0033] The pumping chamber 3 is disposed adjacent to the holding chamber 2. The pumping chamber 3 has a container shape with an opening at the top, and includes a bottom wall 30 and a side wall 31. In this embodiment, the bottom wall 20 of the holding chamber 2 and the bottom wall 30 of the pumping chamber 3 are integral, and the side wall 21 of the holding chamber 2 and the side wall 31 of the pumping chamber 3 are integral. The holding chamber 2 and the pumping chamber 3 are separated by being partitioned by a partition wall 5. A molten metal communication part 50 is formed below the partition wall 5 and above the bottom walls 20 and 30, and the molten metal in the holding chamber 2 can move from the holding chamber 2 to the pumping chamber 3 (in the direction of the arrow X in FIG. 1) through the communication part 50 below the partition wall 5 on the bottom wall 20. When the molten metal is stored in the pumping chamber 3, the molten metal in the holding chamber 2 moves to the pumping chamber 3 when the molten metal in the pumping chamber 3 is pumped out and the liquid level of the molten metal drops.

[0034] The holding chamber 2 and the pumping chamber 3 (and also the melting chamber) are formed by lining a casing made of a metal such as steel with a fireproof material. If necessary, a heat insulating material may be interposed between the casing and the fireproof material.

[0035] As shown in Fig. 1, the holding furnace 1 is equipped with an impurity removal unit 10 for the purpose of suppressing impurities from being mixed into the molten metal that flows from the holding chamber 2 into the pumping chamber 3 and is pumped out from the pumping chamber 3. The impurity removal unit 10 can be installed on the bottom wall 20 of the holding chamber 2. As a result, before flowing from the holding chamber 2 through the communication part 50 below the partition wall 5 into the pumping chamber 3, when the molten metal moves in one direction (towards the pumping chamber 3) above the bottom wall 20 within the holding chamber 2, the impurities mixed in the molten metal are removed from the molten metal by the impurity removal unit 10.

[0036] When the impurity removal unit 10 is installed on the bottom wall 20 of the holding chamber 2, it is preferable that the impurity removal unit 10 is disposed in close proximity to the partition wall 5. Since the communication part 50 below the partition wall 5 is the outlet for the molten metal in the holding chamber 2, when the impurity removal unit 10 is disposed in close proximity to the partition wall 5, impurities can be most effectively removed from the molten metal flowing from the holding chamber 2 to the pumping chamber 3. Note that the impurity removal unit 10 only needs to be close to the partition wall 5, and may be disposed immediately adjacent to the partition wall 5.

[0037] Alternatively, the impurity removal unit 10 can be installed on the bottom wall 30 of the pumping chamber 3. In this way, when the molten metal flows from the holding chamber 2 through the communication part 50 below the partition wall 5 into the pumping chamber 3 and then moves in one direction (the direction opposite to the holding chamber 2) above the bottom wall 30 within the pumping chamber 3, impurities mixed in the molten metal are removed from the molten metal by the impurity removal unit 10.

[0038] The impurity removal unit 10 may be removably installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, or may be integrated with the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3. In this embodiment, the impurity removal unit 10 is detachable from the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3. If the impurity removal unit 10 is detachable, the holding chamber 2 and the pumping chamber 3 can be easily cleaned when cleaning the holding furnace 1, for example, and the impurity removal unit 10 can also be easily cleaned and reused, which is preferable.

[0039] 1 to 5, the impurity removal unit 10 includes at least two barrier walls 11 spaced apart along the moving direction of the molten metal. In this embodiment, the impurity removal unit 10 includes two barrier walls 11. Here, the moving direction of the molten metal is the direction in which the holding chamber 2 and the pumping chamber 3 are aligned (the direction of arrow X in FIG. 1), since the molten metal moves from the holding chamber 2 to the pumping chamber 3 in the holding furnace 1.

[0040] The barrier 11 is a plate having a thickness, and can be made of a fireproof material such as brick or cement. In this embodiment, the barrier 11 is rectangular. The height of the barrier 11 is designed so that when the barrier 11 is installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, the height is higher than the maximum liquid level of the molten metal, that is, the upper end of the barrier 11 always protrudes from the liquid level of the molten metal. The length of the barrier 11 is designed so that when the barrier 11 is installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, no gap is generated between both ends of the barrier 11 in the length direction and the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3. By designing the height and length of the barrier 11 as described above, the barrier 11 is installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3 so as to basically block the movement of molten metal, in other words, to block the movement of molten metal in parts other than the first communication hole 12 and the second communication hole 13 described below. The thickness of the barrier 11 is designed so that when the barrier 11 is installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, the barrier 11 has a strength such that the barrier 11 is not easily damaged or deformed by the movement of molten metal.

[0041] Among the at least two barriers 11, the barrier 11A located at the most upstream side in the moving direction of the molten metal has a first through hole 12 formed in its lower part. The lower part of the barrier 11A is a part lower than 1 / 2 of the height of the barrier 11A. The first through hole 12 is located at a position significantly lower than the liquid level (hereinafter referred to as the "lowest liquid level of the molten metal") when the molten metal accumulated in the holding chamber 2 or the pumping chamber 3 of the holding furnace 1 in which the impurity removal unit 10 is installed, or in other places such as the melting chamber or the transfer trough of the melting furnace, is assumed to be reduced to the lowest level. The first through hole 12 penetrates the barrier 11A in the thickness direction and allows the molten metal to move from one side of the barrier 11A to the other side. The shape and size of the first through hole 12 are not particularly limited and can be designed to be an appropriate shape and size that allows the molten metal to move smoothly. For example, the shape of the first through hole 12 can be a horizontally long rectangular shape in a cross-sectional view, and the size of the first through hole 12 can be 50 mm long and 100 mm wide.

[0042] By forming the first through hole 12 below the barrier wall 11A, even if the molten metal passes through the barrier wall 11A through the first through hole 12, the floating matter F floating on the surface of the molten metal hits the barrier wall 11A and cannot pass through it, so that the floating matter F is prevented from moving together with the molten metal. This makes it possible to prevent as much as possible the floating matter F, among the impurities mixed in the molten metal, from moving from the holding chamber 2 to the pumping chamber 3 and being present in the molten metal in the pumping chamber 3. This makes it possible to suppress the floating matter F from being mixed into the molten metal pumped out from the pumping chamber 3.

[0043] The position of the upper end of the first through hole 12 is preferably 50 mm to 200 mm below the position of the lowest liquid level of the molten metal. This effectively prevents the floating matter F floating on the liquid level of the molten metal from passing through the barrier 11A from the first through hole 12, even if the floating matter F moves slightly downward along the barrier 11A with the movement of the molten metal. In addition, the position of the lower end of the first through hole 12 is preferably 50 mm to 100 mm above the position of, for example, the upper surface of the bottom wall 20, 30 of the holding furnace 1 on which the impurity removal unit 10 is installed, or the upper surface of the melting chamber or transfer trough of the melting furnace (hereinafter referred to as the "bottom wall on which the impurity removal unit 10 is installed"). This also reduces the passage of the precipitate P settling at the bottom of the molten metal from the first through hole 12 through the barrier 11A with the movement of the molten metal.

[0044] At least one of the at least two barriers 11, the other one 11B, has a second through hole 13 formed in its upper part. The upper part of the barrier 11B is a part above 1 / 2 the height of the barrier 11B. The second through hole 13 is located above the first through hole 12, and is located at a position far above the upper surface of the bottom wall on which the impurity removal unit 10 is installed, or the upper surface of the base 14 if the impurity removal unit 10 includes a base 14. The second through hole 13 penetrates the barrier 11B in the thickness direction and allows the molten metal to move from one side to the other side of the barrier 11B. The shape and size of the second through hole 13 are not particularly limited, and can be designed to be an appropriate shape and size that allows the molten metal to move smoothly. For example, the shape of the second through hole 13 can be a horizontally long rectangular shape in a cross-sectional view, and the size of the second through hole 13 can be 50 mm long and 100 mm wide.

[0045] By forming second through hole 13 above barrier 11B, even if molten metal passes through barrier 11A via second through hole 13, precipitate P that settles at the bottom of the molten metal (near bottom walls 20, 30) hits barrier 11B and cannot pass through barrier 11B, and precipitate P is prevented from moving together with the molten metal. This makes it possible to minimize the movement of precipitate P, among the impurities mixed in the molten metal, from holding chamber 2 to pumping chamber 3 and remaining in the molten metal in pumping chamber 3. This makes it possible to suppress the incorporation of precipitate P into the molten metal pumped out from pumping chamber 3.

[0046] The position of the lower end of the second through hole 13 is preferably 200 mm or more and 600 mm or less above the position of the upper surface of the bottom wall or the upper surface of the base 14 on which the impurity removal unit 10 is installed. This effectively prevents the precipitate P, which settles at the bottom of the molten metal, from passing through the barrier 11B from the second through hole 13, even if the precipitate P moves slightly upward along the barrier 11B with the movement of the molten metal. In addition, when the barrier 11B on which the second through hole 13 is formed is disposed in close contact with the partition wall 5, the second through hole 13 is formed below the lower end of the partition wall 5. In addition, the position of the upper end of the second through hole 13 is preferably 50 mm or more and 100 mm or less below the position of the lowest liquid level of the molten metal. This effectively prevents the suspended matter F floating on the liquid level of the molten metal from passing through the barrier 11B from the second through hole 13 with the movement of the molten metal, even if the suspended matter F is mixed in the molten metal that has passed through the barrier 11A.

[0047] The impurity removal unit 10 preferably includes, in addition to the at least two barrier walls 11, a base 14 from which the barrier walls 11 stand. The base 14 is a plate having a thickness, and can be formed of a fireproof material such as brick or cement. The base 14 is integrated with the at least two barrier walls 11. The base 14 is placed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3. This makes it possible to easily install the at least two barrier walls 11 on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3.

[0048] In this embodiment, the base 14 is rectangular. The thickness of the base 14 is designed to have a strength that does not easily break or deform the base 14. The length of the base 14 is designed so that when the base 14 is installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, no gaps are generated between both ends of the base 11 in the longitudinal direction and the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3. The width of the base 14 is designed so that all the barriers 11 can be integrated on the upper surface.

[0049] The impurity removal unit 10 preferably includes at least two barrier walls 11, as well as a pair of guides 15 sandwiching the at least two barrier walls 11 from both sides. The guides 15 are plate-like with a certain thickness, and can be made of a refractory material such as brick or cement. The pair of guides 15 are integrated with the at least two barrier walls 11. In this embodiment, the pair of guides 15 rise from the base 14 and are integrated with the base 14.

[0050] When the at least two barriers 11 are installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, the pair of guides 15 come into contact with the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3. As a result, when the at least two barriers 11 are inserted into the holding chamber 2 or the pumping chamber 3 and installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, the pair of guides 15 slide on the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3, so that the at least two barriers 11 can be easily inserted into the holding chamber 2 or the pumping chamber 3. In addition, when the at least two barriers 11 are installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, the pair of guides 15 come into contact with the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3, so that no gap is generated between both ends of the barriers 11 in the length direction and the side wall 21 of the holding chamber 2 or the side wall 31 of the pumping chamber 3.

[0051] In this embodiment, the guide 15 has a rectangular shape in a plan view. The thickness of the guide 15 is designed to have a strength that does not easily cause the guide 15 to break or deform. The width of the base 15 is designed to be able to integrate all the barrier walls 11. The height of the guide 15 is designed to be greater than the maximum liquid level of the molten metal when the barrier walls 11 are installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3, that is, so that the upper end of the guide 15 always protrudes above the liquid level of the molten metal. In this embodiment, the height of the guide 15 and the height of the barrier walls 11 are the same.

[0052] The impurity removal unit 10 of this embodiment includes two barrier walls 11, a base 14, and a pair of guides 15, and has a box shape with an open top, with the two barrier walls 11 forming opposing front and rear surfaces, the base 14 forming a bottom surface, and the pair of guides 15 forming opposing side surfaces. This allows the impurity removal unit 10 to be easily installed on the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3 by submerging the impurity removal unit 10 in the molten metal.

[0053] In the impurity removal unit 10, it is preferable that an embedded portion 16 for embedding a heater is formed in at least one of the pair of guides 15 and / or the base 14. The embedded portion 16 is a cavity formed in the guide 15 or the base 14, and by embedding a heater, the molten metal can be indirectly heated. This makes it possible to suppress a decrease in the temperature of the molten metal, so that the molten metal maintained at a high temperature can be pumped out of the pumping chamber 3. There is no particular limitation on the heater as long as it can be embedded in the embedded portion 16.

[0054] It is preferable that embedded portion 16 is formed in at least one of the pair of guides 15, and that the upper end of embedded portion 16 is open on the upper surface of guide 15. This allows the heater to be easily embedded in guide 15. It is also preferable that embedded portion 16 is L-shaped and extends from guide 15 to base 14. This allows the heater to be easily embedded in base 14.

[0055] The impurity removing unit 10 preferably includes a degassing processor 17. The degassing processor 17 includes a gas inlet pipe 18 through which an inert gas is introduced, and a bubble generator 19 that generates bubbles of the inert gas.

[0056] The gas introduction pipe 18 is formed in a pipe shape having openings at both ends, and extends vertically along one of the pair of guides 15. One end of the gas introduction pipe 18 is connected to the bubble generator 19, and the other end of the gas introduction pipe 18 protrudes above the guide 15 and is connected to a gas supply pipe extending from an inert gas supply source. The concept includes insoluble gases, gases that do not dissolve in the molten metal, and gases that are difficult to dissolve in the molten metal. Examples of insoluble gases that can be used include inert gases such as argon, and gases such as nitrogen and chlorine. The gas introduction pipe 18 is, for example, a pipe body made of a metal such as steel, stainless steel, or cast iron, covered with a porous fireproof material.

[0057] The bubble generator 19 is in the shape of a hollow box, and in this embodiment, for example, is rectangular in plan view. The bubble generator 19 is attached to the base 14 so as to emit bubbles above the base 14. The bubble generator 19 has, for example, an internal space and is made of the same metal body as the gas introduction pipe 18, and is covered with a porous fireproof material. One end of the bubble generator 19 is connected to one end of the gas introduction pipe 18, and an insoluble gas is introduced into the bubble generator 19.

[0058] At the other end of the bubble generator 19, a release section 190 is formed, which converts the insoluble gas introduced into the bubble generator 19 into bubbles and releases them above the base 14. The release section 190 is composed of, for example, a plurality of gas circulation holes formed on the upper surface of the metallic main body constituting the bubble generator 19, and a large number of fine pores in the porous refractory material. The insoluble gas introduced into the bubble generator 19 passes through the gas circulation holes and the fine pores in the porous refractory material, and is broken down into fine bubbles at that time, and is released above the base 14. Gases such as hydrogen dissolved in the molten metal are captured by the fine bubbles of the insoluble gas rising in the molten metal, and are released from the molten metal to the outside.

[0059] The bubble generator 19 is embedded in the base 14, but may be provided on the base 14. The gas introduction pipe 18 is provided inside the guide 15, but may be partially or entirely embedded in the guide 15.

[0060] The degassing processor 17 is not limited to the configuration of the present embodiment described above, and any known degassing processor may be used.

[0061] The impurity removal unit 10 of the present embodiment described above includes at least two barriers 11 that are spaced apart along the direction of movement of the molten metal and block the movement of the molten metal, and a first through hole 12 through which the molten metal passes is formed in the lower part of the barrier 11A located at the most upstream side in the direction of movement of the molten metal among the at least two barriers 11, and a second through hole 13 through which the molten metal passes is formed in the upper part of at least one other barrier 11B. As a result, according to the impurity removal unit 10 of the present embodiment, even if the molten metal contains precipitates P and floating matter F as impurities, when the molten metal passes through the first through hole 12 at the lower part of the barrier 11A, the floating matter F is prevented from moving together with the molten metal by the barrier 11A, and when the molten metal passes through the second through hole 13 at the upper part of the barrier 11B, the precipitates P is prevented from moving together with the molten metal by the barrier 11B, so that the impurities are effectively removed from the molten metal by the movement of the molten metal.

[0062] Therefore, by applying the impurity removal unit 10 to the holding furnace 1, it is possible to prevent precipitates P from being mixed into the molten metal that flows from the holding chamber 2 to the pumping chamber 3 and is pumped out from the pumping chamber 3, so that clean (high-quality) molten metal with no or very few impurities can be used for casting, etc.

[0063] Moreover, the impurity removal unit 10 of this embodiment has a box shape in which at least two barrier walls 22, the base 14, and a pair of guides 15 are integrated together. Therefore, according to the impurity removal unit 10 of this embodiment, the impurity removal unit 10 can be easily installed in the holding furnace 1. Furthermore, the impurity removal unit 10 can be easily removed from the holding furnace 1, which makes it easy to clean the holding furnace 1 and the impurity removal unit 10, and allows the impurity removal unit 10 to be reused.

[0064] Moreover, in the impurity removal unit 10 of the present embodiment, an embedding portion 17 for embedding a heater is formed in at least one of the pair of guides 15 and / or the base 14. Therefore, according to the impurity removal unit 10 of the present embodiment, a decrease in the temperature of the molten metal can be suppressed.

[0065] The impurity removal unit 10 of this embodiment also includes a degassing processor 17 including a gas introduction pipe 18 into which an insoluble gas is introduced and a bubble generator 19 that generates bubbles of the insoluble gas, the gas introduction pipe 18 extending along one of the pair of guides 15, and the bubble generator 19 attached to the base 14 so as to emit bubbles above the base 14. Thus, according to the impurity removal unit 10 of this embodiment, gases such as hydrogen dissolved in the molten metal can be removed from the molten metal by the bubbles.

[0066] Although one embodiment of the present invention has been described above, the above-described embodiment is merely illustrative and not restrictive. Therefore, the present invention is not limited to the above-described embodiment, and various modifications are possible without departing from the spirit of the present invention.

[0067] For example, in the above-described embodiment, the impurity removal unit 10 includes two barriers 11. In contrast, as a modified example, the impurity removal unit 10 may include three or more barriers 11. When the impurity removal unit 10 includes three or more barriers 11, the third and subsequent barriers are formed with either the first through hole 12 or the second through hole 13. For example, when the impurity removal unit 10 includes four barriers 11, the barrier 11A on the most upstream side in the moving direction of the molten metal is formed with the first through hole 12, the barrier 11B on the next downstream side is formed with the second through hole 13, the barrier 11 on the next downstream side is formed with the first through hole 12, and the barrier 11 on the next downstream side is formed with the second through hole 13. In this way, the first through hole 12 and the second through hole 13 are alternately formed in the multiple barriers 11 arranged from the upstream side to the downstream side in the moving direction of the molten metal, thereby effectively suppressing the intrusion of impurities such as floating matter F and precipitate P into the molten metal. Furthermore, it is not necessarily necessary to alternately form the first through holes 12 and the second through holes 13 in multiple barriers 11. As long as the first through hole 12 is formed in the barrier 11A located most upstream in the direction of movement of the molten metal and the second through hole 13 is formed in at least one other barrier 11B, the first through hole 12 or the second through hole 13 can be formed freely.

[0068] For example, in the above-described embodiment, the impurity removal unit 10 includes a pair of guides 15. However, as a modified example, the impurity removal unit 10 may not include the pair of guides 15, and may have at least two barriers 11 integrated with the base 14.

[0069] For example, in the above-described embodiment, the impurity removal unit 10 includes the base 14. However, as a modified example, the impurity removal unit 10 may not include the base 14, and may have at least two barriers 11 integrated with a pair of guides 15.

[0070] For example, in the above-described embodiment, the impurity removal unit 10 includes the base 14 and the pair of guides 15. In contrast, as a modified example, the impurity removal unit 10 may not include the base 14 and the pair of guides 15, and may be configured only with at least two barrier walls 11. In this case, the impurity removal unit 10 (at least two barrier walls 11) is integrated with the bottom wall 20 of the holding chamber 2 or the bottom wall 30 of the pumping chamber 3.

[0071] For example, in the embodiment described above, embedded portion 16 for embedding a heater is formed in guide 15 or base 14 of impurity removal unit 10. In contrast, as a modified example, the molten metal may be directly heated by, for example, immersing an immersion heater or a throw-in heater in the molten metal without forming embedded portion 16 in guide 15 or base 14 of impurity removal unit 10. Alternatively, the molten metal may not be heated by a heater or the like in impurity removal unit 10.

[0072] For example, in the embodiment described above, the impurity removal unit 10 is equipped with the degassing processor 17. In contrast, as a modified example, the impurity removal unit 10 does not need to be equipped with the degassing processor 17, and gases such as hydrogen contained in the molten metal do not need to be removed in the impurity removal unit 10.

[0073] For example, in the above-described embodiment, the impurity removal unit 10 is applied to the holding furnace 1. In contrast, as a modified example, the impurity removal unit 10 may be applied to a melting furnace. The melting furnace includes at least a melting chamber for melting metal, and the molten metal generated by melting the metal in the melting chamber flows out from a tapping port to the outside. By installing the impurity removal unit 10 on the bottom wall of the melting chamber, the impurities of precipitates P and floating matter F mixed in the molten metal are removed by the impurity removal unit 10 while the molten metal moves to the tapping port. Therefore, it is possible to prevent impurities from being mixed into the molten metal flowing out of the melting furnace. The impurity removal unit 10 is preferably installed in a position close to the tapping port on the bottom wall of the melting chamber.

[0074] The melting chamber may have a structure including a melting section for melting metal, and a tapping section having a tapping port for receiving molten metal from the melting section, temporarily holding the molten metal, and then allowing it to flow out of the tapping port. In this case, the impurity removal unit 10 is preferably installed on the bottom wall of the tapping section of the melting chamber, in a position adjacent to the tapping port.

[0075] As another modified example, the impurity removal unit 10 may be applied to a transfer gutter. The transfer gutter is formed in a concave shape in cross section, and transports molten metal flowing out from, for example, a melting furnace and distributes it to various destinations. By installing the impurity removal unit 10 on the bottom wall of the transfer gutter, impurities such as precipitates P and floating matter F mixed in the molten metal are removed by the impurity removal unit 10 while the molten metal moves to various destinations. This makes it possible to prevent impurities from being mixed into the molten metal that is distributed from a melting furnace or the like to various destinations. [Explanation of symbols]

[0076] 1 Holding furnace 2 Treatment tank 3. Electrolysis Apparatus 10 Impurity Removal Unit 11 Barriers 11A The barrier located most upstream in the direction of molten metal movement of at least two barriers 11B At least one other barrier than at least two barriers 12 First flow hole 13 Second flow hole 14 Base 15 Guide 16 Embedded part 17 Degasser

Claims

1. An impurity removal unit that is surrounded by a side wall and is installed on a bottom wall above which molten metal can move in one direction, at least two barriers spaced apart along a direction of movement of the molten metal, the at least two barriers blocking the movement of the molten metal; An impurity removal unit, wherein a first passage hole through which the molten metal passes is formed in the lower part of the barrier located most upstream in the direction of movement of the molten metal among the at least two barriers, and a second passage hole through which the molten metal passes is formed in the upper part of at least one of the other barriers.

2. 2. The impurity unit according to claim 1, a base resting on the bottom wall, the at least two barrier walls standing on the base; a pair of guides extending from the base and sandwiching the at least two barriers from both sides; an impurity unit, wherein the base, the at least two barriers and the pair of guides are integrated together;

3. 3. The impurity unit according to claim 2, wherein an embedding portion for embedding a heater is formed in at least one of the pair of guides and / or the base.

4. A degassing device is provided, the degassing device including a gas introduction pipe through which an insoluble gas is introduced and a bubble generator for generating bubbles of the insoluble gas, 3. The impurity unit of claim 2, wherein the gas inlet pipe extends along one of the pair of guides, and the bubble generator is attached to the base so as to emit bubbles above the base.

5. A holding furnace including at least a holding chamber for holding molten metal and a pumping chamber for pumping out the molten metal flowing from the holding chamber, A holding furnace comprising the impurity removal unit according to claim 1 , which is installed on a bottom wall of the pumping chamber or on a bottom wall of the holding chamber.

6. A melting furnace having a melting chamber for melting metal, A melting furnace comprising the impurity removal unit according to claim 1 , which is installed on a bottom wall of the melting chamber.

7. A transfer trough for transferring molten metal, A transfer trough comprising an impurity removal unit according to claim 1 , installed on a bottom wall of the transfer trough.

Citation Information

Patent Citations

  • Tundish for continuous casting

    JP1989075153A

  • Method for reducing inclusions in tundish

    JP1993169207A

  • Removing method for inclusion in molten metal by tundish

    JP1995144261A

  • Method for removing inclusion in tundish, and weir used therefor

    JP2005000957A

  • Method for removing inclusion in tundish for continuous casting, and tundish for continuous casting

    JP2006035272A