Steel sheet pile splitting jig
The steel sheet pile splitting jig simplifies the separation of stacked piles by leveraging a curved design for easy insertion and leverage, addressing durability and complexity issues in existing tools.
Patent Information
- Application Number
- JP2024019745
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2024-02-13
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-02-13
AI Technical Summary
Existing steel sheet pile separation tools are prone to deterioration due to high forces applied to rotating shafts, have complex structures, and require labor-intensive manual intervention to separate stacked steel sheet piles.
A steel sheet pile splitting jig with a curved front part for easy insertion between piles, utilizing the principle of leverage to separate piles without movable parts, ensuring durability and ease of use.
The jig effectively separates steel sheet piles with minimal effort, maintaining durability and simplicity, reducing the need for complex structures and manual labor.
Smart Images

Figure 0007566383000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction tool used for peeling off and lifting a plurality of stacked steel sheet piles one by one. [Background technology]
[0002] Steel sheet piles are made of steel, so they can be used to build highly rigid walls in a relatively short period of time. In addition, they have excellent water-stopping properties, so they are widely used as earth retaining walls when constructing underground structures and as temporary enclosures when constructing port and water facilities.
[0003] A plurality of steel sheet piles are usually stacked and arranged in a bundle at the site. When a steel sheet pile is to be split, that is, separated from the bundle of stacked steel sheet piles, the steel sheet pile to be separated is connected to a crane and lifted up. However, when the steel sheet piles are stored in such a stacked state, the upper steel sheet pile may be embedded in the lower steel sheet pile due to the weight of the steel sheet pile itself, and the steel sheet piles may not be peeled off and the whole bundle of steel sheet piles may be lifted up. In such a case, a manual work is performed to insert a crowbar into the gap between the steel sheet piles to widen the gap, but this work requires a lot of labor and time.
[0004] Patent Document 1 discloses a steel sheet pile peeling and lifting jig that can easily and safely peel and lift steel sheet piles that are wedged together. The jig is composed of a clamp member having a clamping portion that clamps the web surface of the steel sheet pile, and an arm member that is long and pivoted to the clamp member at approximately the center. The clamp member clamps the web surface, the tip of the arm member is inserted between the web surface of the steel sheet pile to be lifted and the web surface of the steel sheet pile below it, and the base of the arm member is lifted, so that by using the principle of leverage, the tip of the arm member presses the web surface of the lower steel sheet pile downward, peeling the steel sheet piles that are wedged together and lifting the upper steel sheet pile. This jig consists of a clamp member that clamps the web surface of the steel sheet pile, and an arm member that presses the lower steel sheet pile downward using the principle of a lever. Both members are constructed by supporting an axle member attached to the clamp member in a bearing hole provided in the arm portion. Not only is the structure complex, but it also has durability problems because the axle portion bears the weight of the steel sheet pile. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] Patent Publication No. 2000-118947 Summary of the Invention [Problem to be solved by the invention]
[0006] In the above-mentioned prior art, a member for clamping the steel sheet pile and a member for pulling off the steel sheet pile under the clamped steel sheet pile by the principle of leverage are supported by a rotating shaft. In this case, a large force is applied to the rotating shaft and the rotating bearing, and deterioration is accelerated every time it is used. In addition, the structure is inevitably complicated, and there are problems in terms of manufacturing and handling.
[0007] The present invention provides a steel sheet pile splitting jig, which is a tool for peeling off stacked and bundled steel sheet piles one by one, and which is resistant to deterioration even when handling steel sheet piles for a long period of time. [Means for solving the problem]
[0008] The present invention, which has solved the above problems, is as follows.
[0009] (First aspect) A steel sheet pile splitting jig, a front portion of the steel sheet pile splitting jig has a curved portion whose lower portion is curved upward toward the front, the front portion is inserted between the steel sheet pile webs, and the curved portion is a portion that comes into contact with a lower steel sheet pile web, The central portion of the steel sheet pile splitting jig has a steel sheet pile web insertion portion at an upper portion of the central portion, The steel sheet pile web insertion portion has a portion formed rearwardly above and below the upper portion of the front portion, and a steel sheet pile web can be inserted therein; The rear portion of the steel sheet pile splitting jig has an upper lifting portion, Steel sheet pile splitting jig.
[0010] (Action and effect) The steel sheet pile splitting jig has a lower part (lower front part) in side view that curves upward toward the tip. The steel sheet pile splitting jig uses the principle of leverage to pull off the steel sheet pile by lifting the rear part upward, and because the lower front part curves upward toward the tip, lifting the rear part allows the steel sheet pile splitting jig to rotate smoothly, and the contact part between the curved part at the lower front part and the lower steel sheet pile web acts as a fulcrum to easily exert the principle of leverage. The tip is preferably acutely angled, which has the advantage that it can be easily inserted into the gap between the underside of the web of the upper steel sheet pile and the top side of the web of the lower steel sheet pile, which are the objects to be removed.
[0011] The height from the top of the front part to the top of the steel sheet pile web insertion part is greater than the thickness of the web, which makes it possible to insert the steel sheet pile web into the steel sheet pile web insertion part of the steel sheet pile removal tool.
[0012] The upper and lower parts of the steel sheet pile web insertion part are formed rearward and above and below the upper part of the front part. Therefore, when the rear part of the steel sheet pile splitting jig is lifted so as to rotate upward after the steel sheet pile web is inserted into the steel sheet pile web insertion part, the tip part of the steel sheet pile web can move relatively downward from the upper part of the front part in the steel sheet pile web insertion part of the steel sheet pile splitting jig. Therefore, when the rear part of the steel sheet pile splitting jig is lifted, the steel sheet pile splitting jig can rotate, and the principle of leverage is easily exerted.
[0013] The rear part of the steel sheet pile splitting jig has an upper lifting part. The upper lifting part may be, for example, a hoisting tool connection part. By connecting a wire or the like and lifting it up with a crane or the like, the steel sheet pile splitting jig rotates with the contact part between the curved part at the lower part of the front part and the lower steel sheet pile web as a fulcrum, with the steel sheet pile web clamped in the steel sheet pile web insertion part. This rotation allows the principle of leverage to work, making it possible to peel the upper steel sheet pile from the lower steel sheet pile. If a large force is not required to peel the steel sheet piles from the lower steel sheet pile due to the overlapping of the steel sheet piles, they can be peeled off by human force. In this case, a structure such as a hoisting tool connection part is not particularly required, and it is sufficient to lift the rear end part of the steel sheet pile splitting jig upward as the upper lifting part.
[0014] (Second aspect) The steel sheet pile web insertion portion includes a steel sheet pile web insertion portion upper portion, a steel sheet pile web insertion portion front portion, and a steel sheet pile web insertion portion rear portion, The upper part of the steel sheet pile web insertion portion is formed toward the rear at a height that allows the steel sheet pile web to be inserted into the steel sheet pile web insertion portion, The front part of the steel sheet pile web insertion part is formed downward from the rear end part of the upper part of the front part, The rear part of the steel sheet pile web insertion part is formed in a convex and curved shape toward the lower side of the steel sheet pile splitting jig from the rear end part of the upper part of the steel sheet pile web insertion part to the lower end part of the front part of the steel sheet pile web insertion part. The steel sheet pile splitting jig according to claim 1.
[0015] (Action and effect) In a second aspect, the steel sheet pile web insertion portion comprises an upper part of the steel sheet pile web insertion portion, a front part of the steel sheet pile web insertion portion, and a rear part of the steel sheet pile web insertion portion. The upper part of the steel sheet pile web insertion portion is formed at a height that allows the steel sheet pile web to be inserted into the steel sheet pile web insertion portion. Therefore, the front part of the steel sheet pile splitting jig is inserted between the upper and lower steel sheet piles, and the steel sheet pile web can be smoothly inserted into the steel sheet pile web insertion portion. The upper part of the steel sheet pile web insertion portion is preferably flat. This makes it possible for the upper part of the steel sheet pile web insertion portion to be stably positioned on the steel sheet pile web after the steel sheet pile web is inserted into the steel sheet pile web insertion portion.
[0016] The front part of the steel sheet pile web insertion part is formed downward from the rear end of the upper part of the front part. Therefore, when the rear part of the steel sheet pile splitting jig is lifted so as to rotate upward, the tip of the steel sheet pile web can rotate relatively downward from the height of the upper surface of the front part with the rear end of the upper part of the front part as a base axis. Therefore, the steel sheet pile splitting jig is easy to rotate, and has a feature that the principle of leverage is easily exerted.
[0017] The rear part of the steel sheet pile web insertion part is formed in a convex and curved shape toward the bottom of the steel sheet pile splitting jig, and is formed from the rear end of the upper part of the steel sheet pile web insertion part to the lower end of the front part of the steel sheet pile web insertion part. Therefore, when the rear part of the steel sheet pile splitting jig is lifted, the front end of the steel sheet pile web can be moved smoothly while being in contact with the rear part of the steel sheet pile web insertion part of the steel sheet pile splitting jig, so that the steel sheet pile splitting jig can be rotated smoothly, the leverage principle is smoothly exerted, and the steel sheet pile can be smoothly pulled off.
[0018] (Third aspect) The front end of the upper part of the steel sheet pile web insertion part is located rearward of the rear end of the upper part of the front part. The steel sheet pile splitting jig according to claim 1.
[0019] (Action and effect) In a third aspect, the front end portion of the upper portion of the steel sheet pile web insertion portion is located rearward of the rear end portion of the upper portion of the front portion. When the front end of the upper part of the steel sheet pile web insertion part is located forward of the rear end of the upper part of the front part, the front end of the upper part of the steel sheet pile web insertion part comes into contact with the upper surface of the steel sheet pile web and presses it downward while the rear part is being lifted upward and rotated. Therefore, the other end part of the steel sheet pile web opposite to the one end part sandwiched in the steel sheet pile web insertion part receives a downward force, and there is a possibility that the overlap with the steel sheet pile below will become stronger. On the other hand, when the front end of the upper part of the steel sheet pile web insertion part is located rearward of the rear end of the upper part of the front part, when the rear part of the steel sheet pile splitting jig is lifted upward and rotated, the front end of the upper part of the steel sheet pile web insertion part is unlikely to come into contact with the upper surface of the steel sheet pile web, so that it is possible to prevent the upper steel sheet pile and the lower steel sheet pile from overlapping each other too closely. Therefore, it is preferable that the front end portion of the upper portion of the steel sheet pile web insertion portion is located rearward of the rear end portion of the upper portion of the front portion. In addition, the term "the front end of the upper part of the steel sheet pile web insertion part is located rearward of the upper rear end of the front part" means that when the steel sheet pile splitting jig is placed horizontally in the usable state, the front end of the upper part of the steel sheet pile web insertion part is located rearward of the vertically upper rear end of the upper part of the front part.
[0020] (Fourth aspect) The front end of the upper part of the steel sheet pile web insertion portion is located rearward of the rear end of the upper part of the front portion. The steel sheet pile splitting jig according to claim 2.
[0021] (Action and effect) Also in the fourth aspect, the front end portion of the upper portion of the steel sheet pile web insertion portion is located rearward of the upper rear end portion of the front portion in side view (upper rear end portion of the front portion). When the front end of the upper part of the steel sheet pile web insertion part is located forward of the rear end of the upper part of the front part, the front end of the upper part of the steel sheet pile web insertion part comes into contact with the steel sheet pile web and presses it downward during the upward rotation of the rear part. Therefore, the other end part of the steel sheet pile web opposite to the one end part sandwiched in the steel sheet pile web insertion part receives a downward force, and there is a possibility that the overlap with the steel sheet pile below will become stronger. On the other hand, when the front end of the upper part of the steel sheet pile web insertion part is located rearward of the rear end of the upper part of the front part, the front end of the upper part of the steel sheet pile web insertion part is less likely to come into contact with the steel sheet pile web when the rear part of the steel sheet pile splitting jig is rotated upward, so that it is possible to mitigate the strong overlap between the upper steel sheet pile and the steel sheet pile below. Therefore, it is preferable that the front end portion of the upper portion of the steel sheet pile web insertion portion is located rearward of the rear end portion of the upper portion of the front portion.
[0022] (Fifth aspect) The length from the front end of the front section to the rear end of the rear section is 30 to 70 cm, and the length from the front end of the front section to the rear end of the upper part of the front section is 10 to 30 cm. The steel sheet pile splitting jig according to any one of claims 1 to 4.
[0023] (Action and effect) The size of the steel sheet pile splitting jig can be changed according to the shape and size of the steel sheet pile to be split. However, in consideration of portability, operability, etc., the total length is preferably 30 to 70 cm. In addition, the length from the front end to the rear end of the upper part of the front end depends on the distance between the steel sheet piles, but is preferably 10 to 30 cm in consideration of operability, etc. Compared with the length of this portion, the longer the total length is, the smaller the force required to pull off the steel sheet pile is, due to the principle of leverage. When stacked steel sheet piles are to be torn apart using the steel sheet pile splitting jig of the present invention, an upward force is applied near the connection part of the lifting device at the rear part of the steel sheet pile splitting jig, with the contact part between the lower part of the front part of the steel sheet pile splitting jig and the lower steel sheet pile web as a fulcrum, and the vicinity of the connection part of the lifting device becomes the force point. At this time, the rear end part of the upper part of the front part becomes the point of application that applies an upward force to the steel sheet pile web. Therefore, the larger the ratio of the distance from the fulcrum to the point of application and the distance from the fulcrum to the point of application, the larger the force acting on the point of application. Therefore, the longer the total length of the steel sheet pile splitting jig is compared with the length from the front tip to the rear end of the upper part of the front part, the more effectively the steel sheet pile can be torn apart.
[0024] From this point of view, it is advantageous to make the length from the center to the rear part of the steel sheet pile splitting jig longer, since this increases the force applied to the steel sheet pile. On the other hand, when considering the distance to tear off the steel sheet pile, it is advantageous for the length of the front portion to be longer. However, if the entire steel sheet pile splitting jig becomes large, it becomes difficult to handle. Considering the above, the above size is preferable. Effect of the Invention
[0025] According to the present invention, it is possible to easily separate a steel sheet pile from a stack of steel sheet piles without requiring complicated operations. In addition, the steel sheet pile splitting jig of the present invention has no moving parts and does not change its shape during the peeling operation, so it is unlikely to be damaged during use and has excellent durability. [Brief description of the drawings]
[0026] [Figure 1] 1A is a plan view of a steel sheet pile splitting jig according to the present invention, FIG. 1B is a side view thereof, and FIG. 1C is an enlarged view of an M1 portion thereof. [Diagram 2] 4A and 4B are a plan view and a side view of a steel sheet pile splitting jig according to another embodiment of the present invention. [Diagram 3] 4A and 4B are a plan view and a side view of a steel sheet pile splitting jig according to another embodiment of the present invention. [Figure 4] 1A is a plan view of a steel sheet pile splitting jig according to the present invention with a hanging fitting and a handle attached thereto, and FIG. 1B is a side view thereof. [Diagram 5] FIG. 2 shows a bundle of steel sheet piles in a stacked state. [Figure 6A] 1 is a schematic diagram showing a state in which the steel sheet pile splitting jig according to the present invention is used (only the web part of the steel sheet pile is shown). (a) Before the steel sheet pile splitting jig is inserted (b) After the steel sheet pile splitting jig is inserted [Figure 6B] FIG. 6B is an enlarged view of the M2 portion in FIG. 6A. [Figure 7A]1 is a schematic diagram showing a state in which the steel sheet pile splitting jig according to the present invention is used (only the web portion of the steel sheet pile is shown). (a) A state in which the rear part of the steel sheet pile splitting jig is pulled up, and (b) A state in which the rear part of the steel sheet pile splitting jig is further pulled up. [Figure 7B] FIG. 7B is an enlarged view of the M3 portion in FIG. 7A. (a) The front end 4F of the upper part of the steel sheet pile web insertion part is located rearward of the rear end 2B of the upper part of the front part. (b) The entire end 4F of the upper part of the steel sheet pile web insertion part is located forward of the rear end 2B of the upper part of the front part. [Figure 7C] FIG. 7B is an enlarged view of the M3 portion in FIG. 7A. (a) A case where the steel sheet pile web insertion portion front portion 4V is formed below the front portion upper rear end portion 2B. (b) A case where the steel sheet pile web insertion portion front portion 4V is not provided. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0027] Hereinafter, a preferred embodiment of the present invention will be described. Note that the following description and drawings merely show one embodiment of the present invention, and the contents of the present invention should not be interpreted as being limited to this embodiment.
[0028] (Steel sheet pile) Steel sheet piles come in various patterns, such as U-shaped, hat-shaped, Z-shaped, linear, and H-shaped, and have joints at both ends of the unevenly molded steel plates, which are then joined together to form a wall. For example, in the case of a U-shaped steel sheet pile, as shown in Figure 5, the cut surface perpendicular to the longitudinal direction has a nearly flat bottom (web) and wall sections (flanges) that extend outward from both sides to the top. Joints are provided at both ends of the upper part of the wall. The unit weight is several tens to several hundreds of kg / m. There are two main uses: permanent and temporary. Permanent steel sheet piles are used as permanent structures, while temporary steel sheet piles are mainly used as temporary earth retaining walls before the construction of the main structure. Specific uses include river banks, port quays, earth retaining walls, water cut-off walls, and seismic reinforcement, and are widely used in construction work.
[0029] Steel sheet piles vary in width, length, height, and thickness, and are generally heavy because they are made of metal. Usually, multiple steel sheet piles are used, so they are stored in a stacked state before use. Since they are generally heavy, when they are stored stacked, some deformation occurs due to the weight. In addition, when steel sheet piles are reused, they may have scratches, deformation, or rust depending on the location. In such stacked steel sheet piles, the upper and lower steel sheet piles may be firmly attached to each other due to their own weight in some places. As shown in Figure 5, when multiple steel sheet piles are stacked, the lower steel sheet pile bears the large weight of the entire upper steel sheet pile, and if you simply try to lift the upper steel sheet pile, the lower steel sheet pile will also be lifted together with the lower steel sheet pile without being peeled off. In such a case, it is possible to insert a crowbar or the like between the steel sheet pile webs and manually pull off the upper and lower steel sheet piles, but this is usually not easy.
[0030] The steel sheet pile splitting jig of the present invention is used in such a case. The steel sheet pile splitting jig is a tool used to separate an upper steel sheet pile from an underlying steel sheet pile when multiple steel sheet piles are stored in a stack. Here, peeling off refers to pulling away one end of an upper steel sheet pile web from one end of a lower web in overlapping steel sheet piles.
[0031] (Steel sheet pile splitting jig) Taking the steel sheet pile splitting jig 1 shown in FIG. 1 as an example, the configuration and function of each part will be described. As shown in Figure 1, the steel sheet pile splitting jig 1 of the present invention has a front portion KF of the steel sheet pile splitting jig 1 which is the portion to be inserted between the steel sheet pile 10 webs of stacked steel sheet piles 10 (see Figure 5), a central portion KM in which the steel sheet pile web insertion portion 4 is provided which is the portion into which the end of the steel sheet pile 10 web is inserted and through which the steel sheet pile splitting jig 1 rotates to transmit a force in the peeling direction to the steel sheet pile 10, and a rear portion KB in which an upward lifting portion is provided.
[0032] The steel sheet pile splitting jig 1 can be made of metals such as iron and aluminum, resin, etc., but is not limited to these. The steel sheet pile splitting jig 1 is preferably structured without moving parts. If it has rotating parts, etc., moving parts such as the rotating shaft are subject to large forces when handling heavy objects, which makes them prone to deterioration and breakage. It is preferable that the front section KF, the center section KM, and the rear section KB are formed from a single member. By adopting such a structure, it is possible to obtain the characteristics of being less prone to breakdowns, having excellent durability, and being easy to handle due to its simple structure. In this case, the steel sheet pile web insertion portion 4 can be formed as a notch portion by cutting out the center portion KM of the steel sheet pile splitting jig 1. Alternatively, each part may be fabricated and then the steel sheet pile splitting jig 1 may be finally fabricated by welding or the like.
[0033] The front portion KF preferably has a shape in which the front portion upper portion 2 is substantially flat and substantially linear in side view. This shape facilitates insertion between the steel sheet piles 10 and the webs of the steel sheet piles 10. In addition, the front portion upper portion 2 of the steel sheet pile splitting jig 1 can be brought into intimate contact with the underside of the web of the upper steel sheet pile 10, which is the target to be peeled off. Furthermore, it becomes possible to smoothly insert the steel sheet pile 10 web into the steel sheet pile web insertion portion 4 in the center portion KM.
[0034] The front lower part 3 has a front lower curved part 3C curved upward toward the front, and the front tip part 2F of the front part KF is preferably formed at an acute angle. This allows the front part KF to be inserted smoothly between the stacked steel sheet piles 10. After the web of the steel sheet pile 10 is inserted into the steel sheet pile web insertion portion 4, the rear portion KB of the steel sheet pile splitting jig 1 is lifted upward so as to rotate in order to pull off the steel sheet pile 10. At this time, the front portion lower curved portion 3C of the front portion lower portion 3 comes into contact with the upper surface of the web of the steel sheet pile 10 on the lower side, and the principle of leverage works with the contact portion as a fulcrum. In Fig. 1, the hoisting tool connection part 6 provided at the rear part as an upward lifting part can be, for example, a hoisting tool connection hole 6A. A hoisting fitting 7 or the like is connected to the hoisting tool connection hole 6A, and a wire 9 or the like is engaged thereto, and the steel sheet pile splitting jig 1 is pulled up in a manner that rotates forward. At this time, as described above, the front part lower curved part 3C of the front part lower part 3 comes into contact with the upper surface part of the steel sheet pile web on the lower side, and the contact part becomes a fulcrum. The hoisting tool connection part 6 becomes a force point, and the front part upper rear end part 2B becomes a point of action, and the upper steel sheet pile 10 is lifted upward.
[0035] When the steel sheet pile splitting jig 1 is pulled up while rotating forward, the front lower curved portion 3C of the front lower portion 3 comes into contact with the web of the steel sheet pile 10 below. The contact portion moves in the forward direction of the front lower curved portion 3C as the rotation of the steel sheet pile splitting jig 1 progresses. This movement proceeds smoothly because the front lower curved portion 3C has a shape that is smoothly curved toward the front and upward. Note that the front lower curved portion 3C does not need to be formed up to the front tip portion 2F, but it is preferable that it is formed up to the front tip portion 2F because the above-mentioned effect is more easily achieved.
[0036] As shown in Fig. 1, the central part KM is provided with a protruding part 5, below which a steel sheet pile web insertion part 4 is provided. The front part KF is inserted between the stacked steel sheet piles 10, and the web part of the upper steel sheet pile 10 is inserted into the steel sheet pile web insertion part 4. The upper part 4U of the steel sheet pile web insertion part is preferably substantially flat and substantially linear in side view. The upper part 4U of the steel sheet pile web insertion part may be parallel to the plane formed by the upper front part 2 of the front part KF, but may be inclined in either the front or rear direction. A form inclined forward and upward is preferable. This is because it makes it easier to insert the steel sheet pile 10 web. Also, when the steel sheet pile splitting jig rotates, the front end part 4F of the upper part of the steel sheet pile web insertion part is less likely to come into contact with the steel sheet pile 10 web.
[0037] The steel sheet pile web insertion portion front part 4V is formed downward from the front part upper rear end part 2B, which is the rear end of the front part upper part 2 of the front part KF. The steel sheet pile web insertion portion front part 4V may be formed vertically downward from the front part upper rear end part 2B, or may be formed diagonally backward as shown in Fig. 1. This is because even if the steel sheet pile splitting jig 1 rotates and becomes nearly vertical, the web part of the steel sheet pile 10 does not come into close contact with the steel sheet pile web insertion portion front part 4V.
[0038] The rear part 4W of the steel sheet pile web insertion part is formed so as to connect the rear end of the upper part 4U of the steel sheet pile web insertion part and the lower end 4T (lower end 4T of the front part of the steel sheet pile web insertion part) of the front part 4V of the steel sheet pile web insertion part. When the steel sheet pile 10 is pulled apart by the principle of leverage, the steel sheet pile splitting jig 1 rotates. Before the rotation, the end of the web part of the steel sheet pile 10 is in contact with the upper part 4U of the steel sheet pile web insertion part and is in contact with the upper part of the rear part 4W of the steel sheet pile web insertion part (rear end 4B of the upper part of the steel sheet pile web insertion part) or is present near the upper part of the rear part 4W of the steel sheet pile web insertion part (rear end 4B of the upper part of the steel sheet pile web insertion part). When the steel sheet pile splitting jig 1 rotates, the web portion end of the steel sheet pile 10 is displaced downward in the rear part 4W of the steel sheet pile web insertion part. At this time, the web portion end of the steel sheet pile 10 may move while being in contact with the rear part 4W of the steel sheet pile web insertion part. Therefore, if the rear part 4W of the steel sheet pile web insertion part has an uneven surface, the smooth movement of the web portion end of the steel sheet pile 10 is hindered. For this reason, the rear part 4W of the steel sheet pile web insertion part is preferably structured without unevenness. The rear part 4W of the steel sheet pile web insertion part is preferably shaped as a curved surface that is convex downward in the steel sheet pile splitting jig 1. This is because the movement of the web portion end of the steel sheet pile 10 proceeds smoothly. The rear part 4W of the steel sheet pile web insertion part may have a cylindrical side surface shape (arc-shaped in side view).
[0039] As shown in FIG. 2, the steel sheet pile web insertion part 4 may be composed of the steel sheet pile web insertion part upper part 4U and a substantially cylindrical side part (a substantially arc-shaped part 4C in side view). As shown in the figure, the steel sheet pile web insertion part 4 is formed downward from the rear end part 2B of the upper part of the front part, and is formed on a convex and curved surface downward and rearward from the rear end part 4B of the upper part of the steel sheet pile web insertion part. Even in this form, the same effect as the steel sheet pile web insertion part 4 shown in FIG. 1 is exhibited. That is, the web part end of the steel sheet pile 10 is positioned so as to contact the substantially arc-shaped part 4C in side view of the steel sheet pile web insertion part 4 when inserted into the steel sheet pile web insertion part 4. From this state, when the rear part KB of the steel sheet pile splitting jig 1 is lifted and rotated, the web part end of the steel sheet pile 10 can be smoothly moved below the steel sheet pile web insertion part 4 along the substantially arc-shaped part 4C in side view. Therefore, the steel sheet pile 10 can be peeled off with a small force. In Fig. 2, the steel sheet pile web insertion portion 4 is exemplified as being composed of the steel sheet pile web insertion portion upper portion 4U and a substantially cylindrical side portion (a substantially arc-shaped portion 4C in side view), but the substantially cylindrical side portion (a substantially arc-shaped portion 4C in side view) is not limited thereto as long as the same effect is achieved. For example, a shape having an elliptical shape in side view or a curved shape convex downward can achieve the same effect.
[0040] The steel sheet pile web insertion part upper front end 4F is preferably located rearward of the front part upper rear end 2B. Fig. 1(c) shows an enlarged view of the steel sheet pile web insertion part 4. The imaginary line I shown by a vertical two-dot chain line is drawn vertically upward from the front part upper rear end 2B. It shows that the steel sheet pile web insertion part upper front end 4F is located rearward of the front part upper rear end 2B by ΔL. If the upper front end 4F of the steel sheet pile web insertion part is located forward of the upper rear end 2B of the front part of the front part KF, the upper front end 4F of the steel sheet pile web insertion part will come into contact with the web portion of the steel sheet pile 10 while the rear part KB is rotating upward, and will press the steel sheet pile 10 downward, causing a stronger overlap with the steel sheet pile 10 below, which may result in it being difficult to pull it off. On the other hand, if the upper front end 4F of the steel sheet pile web insertion portion is located rearward of the upper rear end 2B of the front portion, when the rear portion of the steel sheet pile splitting jig 1 is rotated upward, the upper front end 4F of the steel sheet pile web insertion portion is less likely to come into contact with the web portion of the steel sheet pile 10, making it less likely that the above-mentioned problems will occur. Therefore, it is preferable that the steel sheet pile web insertion portion upper front end portion 4F is located rearward of the front portion upper rear end portion 2B of the front portion KF.
[0041] The upper part 4U of the steel sheet pile web insertion part has a role of holding the web part of the steel sheet pile 10. The steel sheet pile splitting jig 1 does not have to have the upper part 4U of the steel sheet pile web insertion part. In this case, however, when the steel sheet pile splitting jig 1 is inserted into the stacked steel sheet piles 10, the position of the steel sheet pile splitting jig 1 becomes unstable. Therefore, it is preferable that the steel sheet pile splitting jig 1 has the upper part 4U of the steel sheet pile web insertion part.
[0042] Fig. 1 shows an example in which a lifting tool connection part 6 (lifting tool hole 6A) is provided as an upper lifting part at the rear part KB of the steel sheet pile splitting jig 1. As shown in Fig. 4, a lifting tool 7 such as a shackle 7A can be attached to the lifting tool hole (6A). A wire 9 or the like is fastened to the lifting tool 7, and the wire 9 can be connected to a crane or the like to lift the rear part KB of the steel sheet pile splitting jig 1 upward.
[0043] In Fig. 1, the hoisting gear connection hole 6A is shown at the rear part KB of the steel sheet pile splitting jig 1, but it is not limited to the hoisting gear connection hole 6A as long as a wire or the like can be secured thereto. For example, a mounting shaft may be formed in advance at the rear part of the steel sheet pile splitting jig 1, and a wire 9 or the like may be secured thereto. It is preferable to provide the hoisting gear connection part 6 at the rear part of the steel sheet pile splitting jig 1 as much as possible. This is because the principle of leverage can be efficiently utilized.
[0044] There may be cases where the steel sheet piles are loosely gripped together and can be pulled apart by hand without using mechanical force. In such cases, the lifting device connection part 6, which is intended for use with a crane or the like, is not necessary. It is also possible to manually lift the rear part KB upward to pull the upper steel sheet pile away from the steel sheet pile directly below it. In such cases, the upward lifting part can be regarded as the same as the rear part KB.
[0045] 1 and 2 show a form having a protrusion 5 on the upper part of the steel sheet pile web insertion part 4, but as shown in Fig. 3, a form having no protrusion and having flat upper surfaces of the center part KM and the rear part KB may be used. In this case, a communication hole may be opened in the upper part of the steel sheet pile splitting jig 1 from the center part KM to the rear part KB to form a handle part 11.
[0046] FIG. 4 shows a steel sheet pile splitting jig 1 to which a hanging fitting 7 (7A) and a handle 8 are attached. The hanging fitting connection portion 6 in this form is a hanging fitting connection hole 6A. For example, a shackle 7A or the like can be used as the hanging fitting 7. The hanging fitting 7 can be connected to the hanging fitting connection hole 6A provided in the rear portion KB of the steel sheet pile splitting jig 1. A wire whose tip is closed with a sleeve, circular sleeve, wire clip, or the like can be fastened to the hanging fitting 7. A handle 8 can be attached to the top of the steel sheet pile splitting jig 1. When carrying the jig, it can be used to insert the steel sheet pile splitting jig 1 between the steel sheet piles 10. The handle 8 can be made of metal, plastic, or the like.
[0047] (Use of steel sheet pile splitting jig) The use of the steel sheet pile splitting jig 1 will be described below with reference to the drawings. Usually, a plurality of steel sheet piles 10 are stacked and left stationary. Since the flange 10F portion widens toward the top, when stacked as shown in FIG. 5, the upper and lower steel sheet piles 10A and 10B are tightly adhered to each other, and it is not easy to separate them. The right side of Fig. 6A shows the web portion of the steel sheet pile 10 when the stacked steel sheet pile 10 is cut in a direction perpendicular to the plane shown in Fig. 5. In the example of Fig. 6A, the steel sheet pile splitting jig 1 has an acute-angled tip 2F, the front upper part 2 of the front part KF has a flat shape, and the front lower part 3 is curved upward near the tip to form the front part tip 2F. Due to this shape, the steel sheet pile splitting jig 1 can be smoothly inserted between the steel sheet pile webs 10A and 10B. As shown in Fig. 6B, the web of the steel sheet pile 10 is inserted until its tip contacts the rear end 4B (rear end 4B of the upper part of the steel sheet pile web insertion part) of the steel sheet pile web insertion part upper part 4U of the steel sheet pile splitting jig 1 or the rear part 4W of the steel sheet pile web insertion part. At this time, the lower surface of the upper part 4U of the steel sheet pile web insertion part is located on the upper surface of the steel sheet pile 10 web, and the posture of the steel sheet pile splitting jig 1 is kept stable.
[0048] Next, the wire 9, which is hooked to the shackle 7 or the like attached to the hoisting tool connection part 6 provided on the rear part KB of the steel sheet pile splitting jig 1, is pulled up by a lifting machine such as a crane. The steel sheet pile 10A receives an upward force mainly from the rear end part 2B of the front part upper part 2, and one end of the steel sheet pile 10A is lifted up as shown in FIG. 7A. At this time, a part of the front part lower curved part 3C of the front part lower part 3 contacts the steel sheet pile 10B and becomes a fulcrum S. Since the rear part KB of the steel sheet pile splitting jig 1 is lifted up by a lifting machine or the like, the steel sheet pile splitting jig 1 rotates to the right. Therefore, the fulcrum S moves forward on the front part lower curved part 3C, and moves the steel sheet pile 10B to the left in FIG. 7A. In order to smoothly move the fulcrum S, it is preferable that the front part lower curved part 3C has a smooth shape. For example, it is preferable that the front lower curved portion 3C has a curved shape such as a substantially circular arc or a substantially elliptical arc.
[0049] Here, we will explain a preferred shape of the steel sheet pile web insertion part 4. We will explain a case where the steel sheet pile web insertion part 4 has a steel sheet pile web insertion part upper part 4U, a steel sheet pile web insertion part front part 4V, and a steel sheet pile web insertion part rear part 4W, which is a representative form of the steel sheet pile web insertion part 4. However, the shape of the steel sheet pile web insertion part may be, for example, the shape shown in Fig. 2, and is not limited thereto.
[0050] The steel sheet pile splitting jig 1 is lifted upward by a lifting machine or the like, and the front part KF rotates downward. As shown in FIG. 7A, in this case, it is considered that one end of the web 10W of the steel sheet pile 10 in the steel sheet pile web insertion part 4 moves downward through the steel sheet pile web insertion part rear part 4W while contacting the steel sheet pile web insertion part rear part 4W. If the steel sheet pile web insertion part rear part 4W has unevenness, the smooth movement of the end of the web 10W of the steel sheet pile 10 is hindered. For this reason, it is preferable that the steel sheet pile web insertion part rear part 4W has a structure without unevenness. The shape of the steel sheet pile web insertion part rear part 4W is preferably a curved shape that is convex toward the bottom of the steel sheet pile splitting jig 1. This is because one end of the web 10W of the steel sheet pile 10 can move smoothly. The steel sheet pile web insertion part rear part 4W may have a cylindrical side shape (arc shape in side view).
[0051] As described above, when the front upper rear end 2B of the front upper part 2 of the steel sheet pile splitting jig 1 is in contact with the web 10W of the steel sheet pile 10A, one end of the web 10W of the steel sheet pile 10A located in the steel sheet pile web insertion section 4 moves downward through the rear part 4W of the steel sheet pile web insertion section. It is preferable that the steel sheet pile web insertion portion 4 has an opening at the front and is formed above and below the upper front portion toward the rear. Figures 7C(a) and (b) are enlarged views of part M3 in Figure 7A. Figure 7C(a) shows a shape in which the steel sheet pile web insertion portion 4 is formed above and below the upper front portion 2 toward the rear, and Figure 7C(b) shows a shape in which the steel sheet pile web insertion portion 4 is not formed below the upper front portion 2 toward the rear. In other words, this is a case in which the steel sheet pile web insertion portion front portion 4V is not provided. As shown in the enlarged view in Figure 7C(b), if the front part 4V of the steel sheet pile web insertion part is not provided, the upper front end part 4F of the steel sheet pile web insertion part will contact the upper surface of the web part of the steel sheet pile 10A, and the steel sheet pile splitting jig 1 cannot rotate any further and therefore cannot rotate to the state shown in Figure 7A(b).As a result, the leverage effect is not fully exerted and the steel sheet pile 10A cannot be sufficiently pulled away from the steel sheet pile 10B. Therefore, it is preferable that the steel sheet pile web insertion portion front part 4V and the steel sheet pile web insertion portion rear part 4W are formed to extend below the front part upper part 2 of the front part KF of the steel sheet pile splitting jig 1.
[0052] FIG. 6B shows the details of the steel sheet pile web insertion part 4. FIG. 6B is an enlarged view of the M2 part in FIG. 6A, and is a side view of the steel sheet pile splitting jig 1 and the steel sheet pile 10 web. In FIG. 6B, the rear lower end part 10AB of the steel sheet pile 10 web is in contact with the steel sheet pile web insertion part rear part 4W. The vertical upper position 10AC of the front part upper rear end part 2B of the steel sheet pile A is on the web of the steel sheet pile 10A, which is vertically above the front part upper rear end point 2B. It is preferable that the length L1 between the front part lower end part 4T of the steel sheet pile web insertion part on the front part 4V of the steel sheet pile web insertion part and the front part upper rear end part 2B is approximately the same as the length L2 between the steel sheet pile rear end part 10AB on the web of the steel sheet pile 10A and the vertical upper position 10AC of the front part upper rear end point 2B of the steel sheet pile A. However, if the lengths L1 and L2 are not significantly different, the effect of the leverage can be exerted. The angle θ between the upper front section 2 and the front section 4V of the steel sheet pile web insertion section affects the range within which the steel sheet pile splitting jig 1 can rotate. For example, if θ is 180 degrees, as mentioned above, the steel sheet pile splitting jig 1 is prevented from rotating sufficiently, making it difficult to utilize the leverage principle. The angle θ is preferably between 90 degrees and 170 degrees. It is even more preferable that it is between 100 degrees and 150 degrees. If it is within this range, the steel sheet pile splitting jig 1 can rotate sufficiently, and the leverage effect can be utilized.
[0053] The steel sheet pile splitting jig 1 is lifted upward by a lifting machine or the like, and the front part KF rotates downward. FIG. 7B(a) is an enlarged view of the portion M3 in FIG. 7A(a). FIG. 7B(a) shows a case where the steel sheet pile web insertion part upper front end 4F is located rearward of the front part upper rear end 2B of the front part KF of the steel sheet pile splitting jig 1, and FIG. 7B(b) shows a case where it is located forward. FIG. 7B(a) and FIG. 7B(b) show a case where the steel sheet pile splitting jig 1 is rotated to the same degree. As shown in FIG. 7B(a), when the tip 4F is located rearward of the front part upper rear end 2B, the tip 4F is not in contact with the web part of the steel sheet pile 10A. In this case, the steel sheet pile splitting jig 1 can be further rotated as shown in FIG. 7A(b), and the steel sheet piles 10A and 10B can be further pulled apart by the principle of leverage. On the other hand, when the top end 4F of the steel sheet pile web insertion part is located forward of the top rear end 2B of the front part as shown in Fig. 7B(b), the top front end 4F of the steel sheet pile web insertion part is in contact with the web part of the steel sheet pile 10A. In this case, the steel sheet pile 10A receives a downward force F from the top front end 4F of the steel sheet pile web insertion part, and the steel sheet pile splitting jig 1 can no longer rotate relative to the steel sheet pile 10A, and the principle of leverage no longer works effectively. As a result, the other end of the web of the steel sheet pile 10A other than the one end at the steel sheet pile web insertion part 4 receives a force in the direction of the steel sheet pile 10B, and the overlap becomes stronger, which causes an obstacle to the peeling. Therefore, it is preferable that the upper tip 4F of the steel sheet pile web insertion part is located rearward of the upper rear end 2B of the front part KF of the steel sheet pile splitting jig 1 rather than forward.
[0054] The upper part 4U of the steel sheet pile web insertion part is preferably substantially flat and substantially linear in side view. The upper part 4U of the steel sheet pile web insertion part may be parallel to the plane formed by the upper front part 2 of the front part KF, but may be inclined in either the front or rear direction. A form inclined upward and forward is preferable, because this makes it easier to insert the steel sheet pile web.
[0055] In Fig. 7B, if the length L3 between the front end 4F of the upper part of the steel sheet pile web insertion part and the rear end 4B of the upper part of the steel sheet pile web insertion part, which is the length of the upper part of the steel sheet pile web insertion part 4U, is too short, the stability of the steel sheet pile splitting jig 1 will be deteriorated when one end of the web of the steel sheet pile 10A is inserted into the steel sheet pile web insertion part 4. Also, if it is too long, as described above, the steel sheet pile 10A will receive a downward force from the front end 4F of the upper part of the steel sheet pile web insertion part, and the steel sheet pile splitting jig 1 will no longer be able to rotate with respect to the steel sheet pile 10A. Therefore, L3 is determined taking these conditions into consideration.
[0056] The steel sheet pile splitting jig 1 rotates forward by lifting the rear part KB upward, and pulls off the steel sheet pile 10 by the principle of leverage. It is effective to use mechanical force to lift the rear part KB. The rear part KB is provided with a hoisting gear connection part 6. For example, a wire is hooked to a shackle 7A connected to the hoisting gear connection part 6, and by pulling the wire upward with a crane or the like, the rear part KB of the steel sheet pile splitting jig 1 is lifted upward, and the steel sheet pile splitting jig 1 rotates. At this time, the front part lower curved part 3C of the front part lower part 3 comes into contact with the lower steel sheet pile B at the contact part S, and the steel sheet pile 10A is pulled upward with the contact part S as a fulcrum, the hoisting gear connection part 6 as a force point, and the front part upper rear end part 2B as a force point.
[0057] The steel sheet pile splitting jig 1 according to the present invention has no movable parts in the main body and is formed, for example, from a single member, and is therefore characterized by superior durability, ease of manufacture, simple use, and ease of maintenance, compared with conventionally disclosed ones.
[0058] The technical scope of the present invention is not limited to the above-described embodiments, and various modifications can be made without departing from the spirit of the present invention. [Explanation of symbols]
[0059] 1...steel sheet pile splitting jig, 2...upper front section, 2F...front tip section, 2B...rear end of upper front section, 3...lower front section, 3C...curved lower front section, 4...steel sheet pile web insertion section, 4U...upper steel sheet pile web insertion section, 4V...front steel sheet pile web insertion section, 4W...rear steel sheet pile web insertion section, 4F...front end of upper steel sheet pile web insertion section, 4B...rear end of upper steel sheet pile web insertion section, 4T...lower front end of steel sheet pile web insertion section, 4C...approximately arc-shaped section when viewed from the side, 5...protruding section , 6... hoisting device connection part, 6A... hoisting device connection hole, 7... hoisting hardware, 7A... hoisting hardware (shackle), 8... handle part, 9... wire, 10... steel sheet pile, 10A steel sheet pile, 10AB... rear end part of steel sheet pile A, 10AC... vertically upward position of rear end point 2B of the upper part of the front part of steel sheet pile A, 10B steel sheet pile, 10C steel sheet pile, 10D steel sheet pile, 11... handle part, KF... front part, KM... center part, KB... rear part, I... imaginary line, S... contact part of front part lower curved part 3C and steel sheet pile 10B
Claims
1. A steel sheet pile splitting jig, a front portion of the steel sheet pile splitting jig has a curved portion whose lower portion is curved upward toward the front, the front portion is inserted between the steel sheet pile webs, and the curved portion is a portion that comes into contact with a lower steel sheet pile web, The central portion of the steel sheet pile splitting jig has a steel sheet pile web insertion portion at an upper portion of the central portion, The steel sheet pile web insertion portion has a portion formed rearwardly above and below the upper portion of the front portion, and a steel sheet pile web can be inserted therein; The rear portion of the steel sheet pile splitting jig has an upper lifting portion, Steel sheet pile splitting jig.
2. The steel sheet pile web insertion portion includes a steel sheet pile web insertion portion upper portion, a steel sheet pile web insertion portion front portion, and a steel sheet pile web insertion portion rear portion, The upper part of the steel sheet pile web insertion portion is formed toward the rear at a height that allows the steel sheet pile web to be inserted into the steel sheet pile web insertion portion, The front part of the steel sheet pile web insertion part is formed downward from the rear end part of the upper part of the front part, The rear part of the steel sheet pile web insertion part is formed in a convex and curved shape toward the lower side of the steel sheet pile splitting jig from the rear end part of the upper part of the steel sheet pile web insertion part to the lower end part of the front part of the steel sheet pile web insertion part. The steel sheet pile splitting jig according to claim 1.
3. The front end of the upper part of the steel sheet pile web insertion part is located rearward of the rear end of the upper part of the front part. The steel sheet pile splitting jig according to claim 1.
4. The front end of the upper part of the steel sheet pile web insertion portion is located rearward of the rear end of the upper part of the front portion. The steel sheet pile splitting jig according to claim 2.
5. The length from the front end to the rear end of the rear section is 30 to 70 cm, and the length from the front end to the rear end of the upper part of the front section is 10 to 30 cm. The steel sheet pile splitting jig according to any one of claims 1 to 4.
Citation Information
Patent Citations
Jig for separating and hoisting steel sheet pile
JP2000118947A
Suspension tool for work material
JP2001019343A
Plank separator
JP2001214433A
Steel sheet pile peeling jig
JP2020186577A