Pile installation method and method for calculating supply amount of lubricant used in said pile installation method

The use of a shear-thinning lubricant in tubular pile construction reduces friction and clogging, maintaining ground integrity and improving bearing capacity without disturbing the ground or requiring additional measures.

JP7567718B2Active Publication Date: 2024-10-16JFE STEEL CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2021137743
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-08-26
Publication Date
2024-10-16
Estimated Expiration
2041-08-26

AI Technical Summary

Technical Problem

Existing pile construction methods using tubular piles face issues with earth and sand clogging, leading to increased resistance and reduced bearing capacity, and often require additional measures like cement footings to compensate, while existing auxiliary methods cause ground disturbance and environmental issues.

Method used

A method involving the use of a lubricant with shear-thinning properties, supplied between the inner wall of the pile and the earth and sand, which reduces friction and prevents clogging by maintaining higher viscosity until sheared, allowing controlled application to prevent ground disturbance and improve bearing capacity.

Benefits of technology

The method effectively prevents earth and sand clogging, maintains ground integrity, and enhances bearing capacity without additional construction steps, reducing environmental impact and construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007567718000004
    Figure 0007567718000004
  • Figure 0007567718000005
    Figure 0007567718000005
  • Figure 0007567718000006
    Figure 0007567718000006
Patent Text Reader

Abstract

To provide a pile construction method capable of preventing sediment blockage in a pile without slackening or disarranging a ground and capable of suppressing occurrence of earth removal, and a calculation method of a supply amount of a lubricant used in the pile construction method.SOLUTION: In a construction method of a pile 1 making a tubular pile 1 rotationally penetrate a ground 3, when carrying out the rotational penetration, a lubricant 5 which has shear thinning viscosity in which viscosity is higher than that of water in a static state and viscosity becomes lower when receiving shear is supplied between an inner wall of the pile 1 and sediment inside the pile 1.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a pile installation method for rotating a tubular pile into ground, and a method for calculating the supply amount of lubricant used in the pile installation method. [Background technology]

[0002] Many methods have been proposed for driving a tubular pile, such as a steel pipe pile, into the ground by rotating the pile. For example, Patent Document 1 discloses a method for constructing a row of steel pipe piles by driving cutting steel pipe piles with a bit at the tip into a concrete revetment using a steel pipe pile driving device that rotates and drives the steel pipe piles. The use of cutting steel pipe piles with a bit at the tip has the advantage of increasing cutting ability and being able to destroy existing structures such as concrete and obstacles.

[0003] In the construction of tubular piles, particularly in the method of rotary driving of existing piles, in order to obtain the bearing capacity of the pile, after driving out the existing structure such as concrete, rotary driving of the pile is continued to a specified depth in the ground (for example, the supporting layer). During this process, the soil of the excavated ground, the rocks of the ground destroyed during excavation, or the fragments of the structure destroyed during excavation (hereinafter collectively referred to as "soil") create voids, reducing the bulk density and expanding the apparent volume. Therefore, the soil inside the pile and the soil on the outer periphery of the pile restrain the tubular pile from the inside and outside, respectively, and provide resistance when it is pressed into the pile. In addition, the increase in the force of the soil trapped in the pile that restrains the tubular pile leads to an increase in the friction between the inner surface of the pile and the soil inside the pile. Therefore, as the amount of excavated soil trapped in the pile increases, the phenomenon of soil clogging occurs inside the pile. The clogging inside the pile by the excavated soil further increases the pressing resistance of the tubular pile during construction.

[0004] Therefore, an auxiliary construction method for preventing blockage inside the pile during construction and reducing press-in resistance is disclosed, for example, in Patent Document 2. In Patent Document 2, a fluid such as water is discharged in the circumferential direction along the inner wall of the steel pipe pile near the tip of the steel pipe pile. This allows the fluid to be interposed between the inner wall of the steel pipe pile and the soil inside the pile, reducing friction between the inner wall of the pile and the soil inside the pile, making it less likely that blockage inside the pile will occur due to excavated soil. Another method is to use a screw auger placed inside the steel pipe pile to lift up and remove the soil inside the pipe, thereby preventing the inside of the pile from becoming clogged with soil and sand. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 4105076 A [Patent Document 2] JP 4242251 A Summary of the Invention [Problem to be solved by the invention]

[0006] As mentioned above, in the construction of tubular piles, it is necessary to prevent blockage of the pile by soil and sand that occurs during the excavation process. However, in the method of Patent Document 2, the soil inside the pile turns into mud when it mixes with the large amount of water discharged into the pile, and the muddy soil flows under the pile and is discharged to the ground from the outer surface of the pile, resulting in increased costs and environmental problems due to the disposal of the discharged soil (discharged soil). The same problem occurs when using a screw auger in combination with other construction methods, as soil is discharged from inside the pile.

[0007] Furthermore, it is difficult to control the range of application of these auxiliary methods, and in actual construction, in order to prevent the occurrence of areas where the auxiliary methods are not applied, the auxiliary methods are often applied more than necessary. In this case, although the workability is improved, the ground at the specified depth reached by the pile tip is loosened or disturbed. In particular, when it is desired to bury the pile tip in the bearing layer to obtain a large bearing capacity, loosening the bearing layer leads to a decrease in the bearing capacity of the pile, which is a very big problem. Therefore, it is necessary to take separate measures to ensure the bearing capacity of the pile, such as constructing a base fixing part with cement mortar at the tip of the pile, which makes the construction more complicated.

[0008] The present invention has been made to solve such problems, and aims to provide a pile construction method that can prevent blockage by soil and sand inside the pile without loosening and disturbing the ground at a specified depth, and also suppress the occurrence of soil removal, and a method for calculating the supply amount of lubricant used in said pile construction method. [Means for solving the problem]

[0009] (1) The pile construction method of the present invention is a method for rotary-inserting a tubular pile into the ground, and when the rotary insertion is performed, a lubricant having shear thinning properties, which means that the viscosity of the lubricant is statically higher than that of water but decreases when subjected to shear, is supplied between the inner wall of the pile and the soil and sand contained within the pile.

[0010] (2) In addition, in the above-mentioned (1), the lubricant is supplied from the lubricant stored within the pile.

[0011] (3) In the above-mentioned (1) or (2), the lubricant is not supplied after the pile reaches a predetermined depth in the ground.

[0012] (4) In the above (1) or (2), the supply amount V(L) of the lubricant is set so as to satisfy the following formula (1). 19.4 π D in·(H-10D out )≦V≦19.4·π·D in ·(H+5D out ) ···(1) Where, H: Distance from the ground surface to a given depth (m) D out :Outer diameter of pile (m) D in : Inside diameter of pile (m)

[0013] (5) Furthermore, the method for calculating the supply amount of a lubricant according to the present invention is a method for calculating the supply amount of a lubricant used in the pile construction method according to any one of (1) to (3) above, Test construction is carried out on ground with similar properties to the target construction site. determining a relationship between the application depth in the trial application and the amount of lubricant used; The method includes a step of setting the amount of lubricant to be supplied based on the obtained relational expression, the inner circumference of the pile used in the trial construction, the actual construction depth, and the inner circumference of the pile to be used in the actual construction. Effect of the Invention

[0014] In the present invention, by rotating and penetrating the pile using a lubricant having shear thinning properties, which is statically more viscous than water and whose viscosity decreases when subjected to shear, the lubricant reduces friction between the inner wall of the pile and the soil inside the pile, thereby preventing blockage by the soil. In addition, in areas not affected by the shear force caused by the rotation of the pile, the lubricant does not penetrate into the soil inside the pile, preventing the ground around the pile from being loosened or disturbed more than necessary. Therefore, it is possible to suppress the generation of muddy soil and sand as soil discharge. Also, the bearing capacity of the pile can be exhibited without additional construction such as the construction of a foot protection section. [Brief description of the drawings]

[0015] [Figure 1] FIG. 1 is a diagram for explaining a pile construction method according to the first embodiment of the present invention (part 1). [Diagram 2] FIG. 2 is an explanatory diagram (part 2) of the pile construction method according to the first embodiment of the present invention. [Diagram 3] 2A and 2B are diagrams showing another embodiment 1 of the excavation member for the pile shown in FIG. 1, where FIG. 2A is a cross-sectional view and FIG. 2B is a bottom view. [Figure 4] 3A and 3B are views showing another embodiment 2 of the excavation member for the pile shown in FIG. 1, in which FIG. 3A is a cross-sectional view and FIG. 3B is a bottom view. [Diagram 5] 4A and 4B are diagrams showing another embodiment 3 of the excavation member for the pile shown in FIG. 1, in which FIG. 4A is a cross-sectional view and FIG. 4B is a bottom view. [Figure 6] 1. FIG. 4 is a three-dimensional view showing another embodiment 4 of the excavation member for the pile shown in FIG. [Figure 7] 1. FIG. 4 is a three-dimensional view showing another embodiment 5 of the excavation member for the pile shown in FIG. [Figure 8] FIG. 2 is a diagram illustrating a method for mixing lubricant materials. [Figure 9] FIG. 4 is a diagram illustrating another aspect of the pile construction method according to the first embodiment of the present invention. [Figure 10] 1 is a graph showing the relationship between the penetration length of a pile into the ground and the amount of lubricant used. [Figure 11] 1 is a graph showing experimental results according to an embodiment, comparing an example of the invention (with lubricant) with a comparative example (without lubricant) from three perspectives. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0016] [Embodiment 1] The pile construction method according to this embodiment involves rotating a tubular pile into the ground to a predetermined depth, and during the rotational penetration, a lubricant that is statically more viscous than water and has shear thinning properties that reduce the viscosity when subjected to shear is supplied between the inner wall of the pile and the soil inside the pile. In this embodiment, the lubricant is supplied from a lubricant stored inside the pile. Here, tubular piles refer to hollow cylindrical piles that are long in the axial direction. For example, there is a "precast pile." More specifically, there are prestressed concrete piles (PC piles), pretensioned prestressed concrete piles (PHC piles), SC piles with steel pipes wrapped around the outer periphery of the concrete, PRC piles made of concrete with high-strength rebars, and steel pipe piles. The application to steel pipe piles is particularly favorable because the ratio of the pipe thickness to the pipe diameter (diameter-thickness ratio) is small and the penetration resistance is small. The predetermined depth is not particularly limited, but may be, for example, the depth to which the tip of the pile is desired to reach in terms of design. More specifically, it may be the penetration length, the vicinity of the bearing layer of the ground, or the top end of the bearing layer. The latter two correspond to the case where the tip of the pile is to reach the bearing layer of the ground, and it is possible to increase the bearing capacity of the tubular pile.

[0017] As described above, the lubricant of the present embodiment has shear thinning properties, and has a viscosity that does not allow the lubricant to penetrate into the ground in a stationary state. The properties of the lubricant will be described in detail later. Although the present invention is not limited to the method of supplying the lubricant between the inner wall of the tubular pile and the soil inside the tubular pile, a method of simply supplying the lubricant includes a method of storing the lubricant inside the pile, particularly on the soil in the ground, and applying the lubricant thereto. This method will be specifically described below as an example.

[0018] First, as shown in Fig. 2(a), with the bottom end of the pile 1 driven into the ground 3, lubricant 5 is poured into the pile from the top end side of the pile 1, and a predetermined amount of lubricant 5 is accumulated inside the pile 1. Due to the characteristics of the lubricant 5 described below, it naturally accumulates on top of the soil of the ground 3 (on the surface of the ground 3 in this figure). Next, as shown in FIG. 2( b ), the pile driver 7 has a leader 9 which grips the upper end of the pile 1 and rotates to drive the pile into the ground 3 . By doing as described above, the pile 1 can be constructed by the rotary penetration method while supplying the lubricant 5 stored in the pile 1 between the inner wall of the pile 1 and the soil inside the pile 1. This will be described in detail with reference to FIG.

[0019] Fig. 1 shows the state in which the pile 1, with the lubricant 5 stored inside, is being rotated and driven into the ground 3, Fig. 1(a) being a plan view and Fig. 1(b) being a longitudinal cross-sectional view. The lubricant 5 used in the present invention has a static viscosity higher than that of water. Therefore, even if the lubricant 5 is poured into the pile 1 and comes into contact with the surface of the ground 3, it does not permeate into the ground 3 like water does, but is retained on top of the soil and sand of the ground 3 and accumulates inside the pile 1. When the pile 1 is rotated and inserted in this state, the lubricant 5 near the inner wall of the pile 1 is subjected to shear force as indicated by the white arrow in Figure 1(a) and its viscosity decreases (see the light gray area in Figure 1(a)). As the viscosity of the lubricant 5 decreases, the lubricant 5 permeates like water into the soil of the ground 3 along the inner wall of the pile 1 as shown in FIG. 1(b), and the lubricant 5 is supplied between the inner wall of the pile 1 and the soil inside the pile 1. In other words, the lubricant 5 is supplied by lowering the viscosity of the lubricant 5 stored inside the pile 1 due to shear caused by the rotation of the pile 1, and as a result, the lubricant 5 permeates into the soil of the ground 3 along the inner wall of the pile 1. This reduces friction between the inner wall of the pile 1 and the soil inside the pile 1, improving workability and preventing soil blockage inside the pile 1. 1(a) and (b), the lubricant 5 in the area away from the inner wall of the pile 1 (see the dark gray area in FIG. 1) remains static and has a higher viscosity than water, so it does not penetrate into the soil of the ground 3 but is held on top of the soil of the ground 3 and remains pooled within the pile 1. Then, as the rotational penetration progresses, some of the lubricant 5 that remains pooled within the pile 1 is newly supplied between the newly generated inner wall of the pile 1 and the soil within the pile 1.

[0020] The pile 1 of this embodiment is provided at its tip with an excavation member 11 that is provided so as to protrude inward of the pile 1. This excavation member 11 is preferable because it temporarily forms a gap between the inner wall of the pile 1 and the soil inside the pile 1 when the pile 1 is rotated and penetrated, making it easier for the lubricant 5 to penetrate and enabling effective supply.

[0021] As another embodiment of the excavation member 11, for example, as shown in Fig. 3, a tubular member having a thickness greater than the thickness of the pile 1 may be provided at the tip of the pile 1 (another embodiment 1). Also, as shown in Fig. 4, a bit having a width greater than the thickness of the pile 1 may be provided at the tip of the pile 1 (another embodiment 2).

[0022] Furthermore, as shown in FIG. 5, the bit may be provided on the inner wall of the pile 1 (another embodiment 3). The soil blockage in the pile 1 is D in (D in It is empirically known that the depth of the pile is more than 1 times the inner diameter of the pile. Therefore, in the case of the other mode 3, the bit is placed at a depth of D in It is preferable that the height of the sensor be within 10 mm. Also, as shown in Figs. 6 and 7, a spiral blade or a double spiral blade may be provided so as to protrude inward from the pile 1 (other embodiment 4, other embodiment 5).

[0023] As described above, the excavation members 11 that form gaps in the inner peripheral surface of the pile 1 may be disposed continuously or discretely in the circumferential direction. Moreover, the gap formed on the inner peripheral surface of the pile 1 can be a very small space because it is for the purpose of facilitating the supply of the lubricant 5 between the inner wall of the pile 1 and the soil inside the pile 1. Therefore, it is sufficient for the width of the excavation members 11 to protrude inward from the pile 1 to be 5 mm or more. It should be noted that the excavation members 11 that form gaps on the inner peripheral surface of the pile 1 are not essential, and a normal pipe that does not have these excavation members 11 may be used as the pile.

[0024] Next, the lubricant 5 of the present embodiment will be described in detail below. As described above, the lubricant 5 of the present embodiment has a static viscosity higher than that of water, and has shear thinning properties, that is, the viscosity decreases when sheared. Examples of the lubricant 5 include bentonite liquid and liquids containing water-soluble polymers.

[0025] As described above, the lubricant 5 of this embodiment has a static viscosity higher than that of water. Such lubricant 5 is less likely to penetrate than water into the soil inside the pile 1 or into the ground 3 at a predetermined depth reached by the tip of the pile 1 unless a shear force is applied. Therefore, compared to the conventional case where water is discharged onto the inner wall of the pile 1 for construction, loosening or disturbing the ground 3 can be suppressed. As a result, the bearing capacity of the pile 1 can be exhibited. In addition, since the soil inside the pile 1 is not turned into mud, the occurrence of soil discharge can be suppressed.

[0026] It is also preferable to adjust the viscosity of the lubricant 5 according to the water permeability of the ground 3 to be excavated. This point will be described below.

[0027] Generally, the permeability coefficient, which indicates the permeability of ground 3, can be found by the "Soil Permeability Testing Method" (JIS A 1218, 2009). The "Soil Permeability Testing Method" is based on the permeability of water at a temperature of 15 degrees Celsius. It is known that at the same temperature, permeability is proportional to the density of the liquid and inversely proportional to the viscosity coefficient. Therefore, by making corrections taking into account the density and viscosity of lubricant 5 at a temperature of 15 degrees Celsius, the permeability coefficient of lubricant 5 in said ground 3 is defined by the following formula (2).

number

[0028] In the present invention, "statically more viscous than water" means that the permeability coefficient k of the lubricant 5 at a temperature of 15 degrees Celsius calculated by the above formula (2) is less than the permeability coefficient k of water at a temperature of 15 degrees Celsius. w Here, in the case of coarse-grained, uniform-grained ground, the permeability is generally high, and the water permeability coefficient k w is 1×10 -3 (m / s) or more. Therefore, the viscosity coefficient μ of the lubricant 5 is at least the viscosity coefficient μ of water. w It is preferable that the concentration is 100 times or more. Specifically, if the viscosity of the lubricant 5 is set so that the permeability coefficient k of the above-mentioned lubricant 5 satisfies the following formula (3), it can be reliably determined that the lubricant 5 will not penetrate into the ground 3 when in a stationary state in the ground 3 where the pile 1 is constructed, which is preferable. k<1×10 -5 (3) If the lubricant 5 has a viscosity that does not allow it to penetrate into the ground 3 in a stationary state, the lubricant 5 will not penetrate anywhere other than between the inner wall of the pile 1 and the soil inside the pile 1. This makes it possible to minimize the amount of lubricant 5 used. Furthermore, it is also possible to store the lubricant inside the pile 1, particularly on top of the soil of the ground 3.

[0029] Also, since the lubricant 5 does not penetrate into the soil inside the pile 1, the amount of lubricant 5 required for construction can be calculated in advance. A specific example of the calculation method will be described later in the second and third embodiments, but the amount of lubricant 5 required for construction can be calculated based on the inner diameter and penetration length of the pile 1. Here, the penetration length of the pile 1 corresponds to the "predetermined specified depth." Also, when the tip of the pile is to reach the supporting layer of the ground 3, the "depth from the ground surface to the top end of the supporting layer in the ground 3" is used instead of the "predetermined specified depth."

[0030] As described above, the lubricant 5 of the present embodiment has shear thinning properties, that is, the viscosity of the lubricant 5 decreases due to shear force. A fluid having such properties is called a pseudoplastic fluid, and the higher the shear rate (=shear rate), the lower the viscosity of the fluid. The lubricant 5 preferably has a large decrease in viscosity due to shear, since this makes it easier for the lubricant 5 to penetrate between the soil and sand in the pile 1 and the inner wall of the pile 1. Specifically, it is preferable for the lubricant 5 to satisfy the following formula (4). (μ´ / μ)<1×10 -1 (4) μ: Viscosity coefficient of the lubricant at a temperature of 15 degrees Celsius and a shear rate of 0.01 (1 / s) or less (Pa s) μ´: Viscosity coefficient of the lubricant at a temperature of 15 degrees Celsius and a shear rate of 2.5 (1 / s) or less (Pa s) The viscosity coefficient of a liquid as a function of shear rate can be measured using a rotational viscometer as described in "Method of Measuring Viscosity of Liquids."

[0031] The lubricant 5 having the above-mentioned properties is, for example, 1 ml of water. 3 Bentonite liquid containing 120 kg or more of bentonite per 1 m of water 3 Examples include liquids containing 3 kg or more of acrylic acid-based water-soluble polymer mixed with water.

[0032] As a method for mixing the materials for the lubricant 5 as described above, for example, a dynamic mixer method or a static mixer method can be used. The dynamic mixer method is a method in which, as shown in FIG. 8(a), ingredients for lubricant 5 are placed in a water tank 13, mixed with a mixer 15 to produce lubricant 5, and the produced lubricant 5 is pumped out by a pump 17. In the static mixer method, as shown in FIG. 8(b), the materials for the lubricant 5 are simultaneously fed into a pipe 19 and mixed while being fed by turbulent stirring generated by a mixing element 21 installed in the pipe 19.

[0033] The dynamic mixer method can mix any kind of raw material for the lubricant 5, but requires a separate water tank 13 and mixer 15 for mixing, which increases the size of the construction equipment. In the static mixer method, the raw material of the lubricant 5 must be in a liquid state, but since the mixer 15 is not required, the equipment can be simplified. Therefore, it is advisable to select an appropriate mixing method according to the materials, such as using a dynamic mixer method when the material for the lubricant 5 contains powder, and using a static mixer method when the material is all liquid.

[0034] 1 and 2, an example is described in which the pile 1 is rotated and driven in a state in which the lubricant 5 is stored inside the pile 1, but the present invention is not limited to this. For example, the lubricant 5 may be stored in a storage tank (not shown) provided on the outside of the pile 1, and the lubricant 5 may be supplied from the storage tank into the pipe of the pile 1. 9, a lubricant supply pipe 23 for supplying the lubricant 5 may be disposed in the axial direction along the inner wall of the pile 1, and the lubricant 5 may be discharged from a discharge hole formed at the tip of the lubricant supply pipe 23 to supply the lubricant 5 between the inner wall of the pile 1 and the soil inside the pile 1. In this case, the discharge hole for discharging the lubricant 5 may be provided not only at the tip of the lubricant supply pipe 23 but also on the side surface.

[0035] As described above, in this embodiment, by supplying lubricant 5 having shear thinning properties between the inner wall of pile 1 and the soil inside pile 1 while rotating and penetrating pile 1, the lubricant 5 reduces friction between the inner wall of pile 1 and the soil inside pile 1, improving workability and suppressing soil blockage. Furthermore, in areas not affected by the shear force caused by the rotation of the pile 1, the lubricant 5 has a higher viscosity than water and is therefore less likely to penetrate into the soil. This makes it possible to prevent the ground 3 around the pile 1 from being loosened or disturbed more than necessary, and also to prevent the muddy soil from being discharged onto the ground. In particular, when constructing a tubular pile in soil (or ground containing coarse, uniform grain size soil) the soil inside the pile has high permeability, and water penetrates into the soil without mixing with the sand. Therefore, even if water is used, friction between the inner wall of the pile and the soil inside the pile is not reduced, and blockage inside the pile is likely to occur. Even in such soil conditions, the construction method of the present invention reduces friction between the inner wall of the pile 1 and the soil inside the pile 1, improving workability and enabling construction while suppressing soil blockage. In other words, the construction method of the present invention can achieve the above effects regardless of the properties of the ground, that is, even in highly permeable ground, without any problems.

[0036] [Embodiment 2] In the first embodiment, the lubricant 5 is supplied between the inner wall of the pile and the soil inside the pile, thereby reducing the resistance during construction and preventing the soil from clogging the inside of the pile. Although the lubricant 5 is less likely to penetrate into the soil and sand than the water that has been used conventionally, and is less likely to loosen the ground 3, it is possible to actively cause soil blockage by controlling the supply of the lubricant 5 and not supplying the lubricant 5 at a certain depth. In this case, the bearing capacity of the pile 1 can be further improved.

[0037] One example of such control of the supply of the lubricant 5 is to control the timing of stopping the supply. Specifically, after the tip of the pile reaches a predetermined depth in the ground 3, the lubricant 5 is not supplied. In the pile construction method of this embodiment, the pile 1 is rotated and penetrated into the ground 3 in a layer (middle layer) before the predetermined depth as described in the first embodiment while supplying the lubricant 5. After the tip of the pile 1 reaches the predetermined depth, the pile 1 is rotated and penetrated without supplying the lubricant 5. In particular, when the tip of the pile 1 is rotated and penetrated into the supporting layer, the above-mentioned "predetermined depth" may be replaced with "near the supporting layer". In this way, the tip of the pile 1 can reach the supporting layer without loosening or disturbing the supporting layer and while causing soil blockage. In addition, in the case where the lubricant 5 is directly supplied to the vicinity of the tip of the pile 1 through the lubricant supply pipe 23 as shown in Fig. 9, the discharge of the lubricant 5 from the lubricant supply pipe 23 may be stopped when the tip of the pile 1 reaches a predetermined depth. Furthermore, in the case where the tip of the pile 1 is made to reach the supporting layer, the discharge of the lubricant 5 from the lubricant supply pipe 23 may be stopped when the tip of the pile 1 reaches the vicinity of the supporting layer. As described above, according to this embodiment, after the pile 1 reaches a predetermined depth, by not supplying the lubricant 5, soil blockage is actively caused in the pile 1 at a predetermined depth in the ground 3, and the bearing capacity of the pile 1 can be improved. Furthermore, when the tip of the pile 1 is allowed to reach the bearing layer, by not supplying the lubricant 5 after the pile 1 reaches the vicinity of the bearing layer, soil blockage is actively caused in the pile at the bearing layer, and the bearing capacity of the pile 1 can be improved.

[0038] [Embodiment 3] Another example of controlling the supply of the lubricant 5 is to stop the supply by controlling the supply amount. Specifically, the lubricant 5 (for example, lubricant stored in the pile 1 or in a storage tank) is exhausted when the tip of the pile reaches a predetermined depth in the ground 3. This method will be described in detail using the case of constructing the pile 1 by the method described in Figs. 1 and 2 as an example. The construction method for the piles in Figures 1 and 2 involves rotating and penetrating the pile 1 with lubricant 5 stored inside it, reducing the viscosity of part of the lubricant 5 by the shear force associated with the rotation of the pile 1, and allowing the reduced-viscosity lubricant 5 to permeate the soil and sand in the ground 3, thereby supplying the lubricant 5 between the inner wall of the pile and the soil and sand inside the pile. Therefore, the inventors conducted the following experiment to examine how much of the lubricant 5 stored inside the pile is supplied between the inner wall of the pile and the soil inside the pile.

[0039] In this experiment, a steel pipe with a diameter of 318.5 mm and a plate thickness of 7.9 mm was used as the pile 1, and after the tip of the steel pipe was driven into the ground 3, a certain amount of lubricant 5 was poured into the pile from above, and the steel pipe was rotated to penetrate (see Figure 2). At this time, the rotation was stopped at appropriate times to check the height of the lubricant 5 that had accumulated above the soil inside the pile. From this height, the amount of lubricant 5 remaining on the surface of the ground 3 was calculated, and the amount of lubricant 5 supplied was calculated from the difference with the initial amount poured in. FIG. 10 shows the relationship between the penetration length of the steel pipe into the ground and the calculated supply amount of the lubricant 5.

[0040] As shown in FIG. 10, it can be seen that the penetration length of the steel pipe and the supply amount of the lubricant 5 are in a proportional relationship. As described above, the lubricant 5 has a static viscosity higher than that of water and a shear thinning property, which means that the viscosity of the lubricant 5 decreases when subjected to shear. Therefore, the amount of lubricant 5 supplied per penetration length is considered to be proportional to the circumferential length of the inner diameter of the steel pipe. From the above, the amount (L) of lubricant 5 required for penetration of 1 m can be expressed by the following formula (5). in is the inner diameter of the pile (m), 18.433 is the proportionality coefficient in Figure 10, and 0.95096 is the circumference (m) of the inner diameter of a steel pipe with a diameter of 318.5 mm and a thickness of 7.9 mm.

number

[0041] The above formula (5) represents the amount of lubricant 5 required for 1 m of penetration, so by multiplying this by the penetration length (m) over which the lubricant 5 is to be rotated while being supplied, the total amount of lubricant 5 required can be calculated, i.e., the amount of lubricant 5 that should be stored in the pile pipe before construction.

[0042] Furthermore, if the amount of stored lubricant 5 is the amount for the penetration length X (m), the stored lubricant 5 will run out when the penetration length reaches X (m), and therefore no lubricant 5 will be supplied even if the pile 1 is rotated and penetrated to a depth beyond that. Therefore, by setting the amount of lubricant 5 so that the lubricant 5 is used up when the pile 1 reaches a predetermined depth, it is possible to stop the supply of lubricant 5 after the pile 1 reaches the predetermined depth. If the lubricant 5 is not supplied, as in the case of construction without using the auxiliary construction method, soil blockage occurs within the pile 1 as the pile 1 is rotated and penetrated, thereby improving the bearing capacity performance of the pile 1. Furthermore, when the tip of the pile is caused to reach the bearing layer of the ground 3, the above-mentioned "predetermined depth" is the "upper end of the bearing layer."

[0043] Further consideration will be given to the case where the tip of pile 1 reaches the supporting layer of ground 3. The depth to which the pile 1 is driven from the top of the bearing layer is generally set based on the outer diameter of the pile. For example, a bearing pile is generally driven from the top of the bearing layer to a maximum depth of about five times the outer diameter of the pile. Therefore, when the lubricant 5 is supplied over the entire penetration length, the supply amount of the lubricant 5 is at most the amount (H+5D out ) times. Here, H is the depth from the ground surface to the top of the supporting layer (m), D out is the outer diameter of the pile (m), 5D out indicates 5 times the outer diameter of the pile.

[0044] On the other hand, if it is desired to improve the bearing capacity of the pile 1 by not supplying the lubricant 5 to the bearing layer, it is preferable to set the supply amount so that the lubricant 5 is used up before the pile 1 reaches the bearing layer, as described above. How high up the lubricant 5 should be used up effectively depends on the ground conditions and the outer diameter of the pile 1, but it is preferable to use it up about 10 times the outer diameter of the pile 1, for example. Therefore, the supply amount of the lubricant 5 should be at least the amount shown in formula (5) (H-10D out ) times. Here, 10D out indicates 10 times the outer diameter of the pile. Therefore, when the tip of the pile is to reach the bearing layer of the ground 3 or into the bearing layer, it is preferable to set the supply amount V(L) of the lubricant 5 so as to satisfy the following formula (1). 19.4 π Din ·(H-10D out )≦V≦19.4·π·D in ·(H+5D out ) ···(1) Note that this is the case where the tip of the pile 1 reaches the supporting layer, but the same effect can be obtained for other reasons. When the tip of the pile 1 does not reach the supporting layer, H may be set to "the distance from the ground surface to a predetermined depth in the ground 3." Here, if the "predetermined depth" is considered to be "up to the top of the supporting layer," the supply amount of the lubricant 5 can be controlled, including the case where the tip of the pile 1 reaches the supporting layer.

[0045] It should be noted that the above formula (1) is defined based on the proportionality coefficient (see FIG. 10) between the penetration length of the pile 1 and the amount of lubricant supplied, which was obtained from the above-mentioned experiment. However, it is also possible to carry out a similar experiment depending on the properties of the lubricant 5 and the ground 3, and set the amount of lubricant 5 supplied based on the proportionality coefficient obtained as a result. In this case, the method of calculating the amount of lubricant to be supplied includes a step of carrying out a trial construction in ground having properties similar to those of the construction target, and determining a relationship between the construction depth in the trial construction and the amount of lubricant used, and a step of setting the amount of lubricant to be supplied based on the determined relationship, the inner circumference of the pile used in the trial construction, the actual construction depth, and the inner circumference of the pile to be used in the actual construction. A specific example of the method for calculating the amount of lubricant supplied will be described below.

[0046] First, prepare a steel pipe A (inner circumference b (m)) and lubricant B for trial construction. Next, trial construction will be carried out on ground with properties similar to those of the planned construction site, using the same method as in the experiment described above. Then, the proportionality coefficient a is calculated based on the proportional relationship between the installation depth of steel pipe A in the trial installation and the amount of lubricant B used.

[0047] Based on the proportionality coefficient a obtained as above and the inner circumference b (m) of the steel pipe A, the supply amount V (L) of the lubricant 5 in the actual construction is set so as to satisfy the following formula (6).

number

[0048] In addition, when the lubricant 5 is directly supplied to the vicinity of the tip of the pile 1 through the lubricant supply pipe 23 as shown in Fig. 9, the supply amount of the lubricant 5 may be set using the supply speed of the lubricant 5 by the pump, the rotational penetration speed of the pile 1 into the ground, and a predetermined depth to which the pile 1 penetrates from the surface of the ground 3, and the discharge of the lubricant 5 from the lubricant supply pipe 23 may be stopped when the set supply amount runs out. Furthermore, when the tip of the pile 1 is made to reach the supporting layer, the supply amount of the lubricant 5 may be set using the depth from the surface of the ground 3 to the top end of the supporting layer, and the discharge of the lubricant 5 from the lubricant supply pipe 23 may be stopped when the set supply amount runs out.

[0049] As described above, according to this embodiment, after the pile 1 reaches a predetermined depth, by not supplying the lubricant 5, soil blockage is actively caused in the pile 1 at a predetermined depth in the ground 3, and the bearing capacity of the pile 1 can be improved. Furthermore, when the tip of the pile 1 is to reach the bearing layer, the supply amount of the lubricant 5 is set using the depth to the top end of the bearing layer, and the lubricant 5 is not supplied in the vicinity of the bearing layer, so that soil blockage is actively caused in the pile at the bearing layer, and the bearing capacity of the pile 1 can be improved. EXAMPLES

[0050] Experiments were conducted to verify the effects of the pile construction method of the present invention, and the results are described below. As an example of the present invention, a steel pipe with a diameter of 318.5 mm and a plate thickness of 7.9 mm was used as the pile 1, and construction was performed by the method described in FIG. 1 and FIG. 2. As a comparative example, the same steel pipe was constructed by rotary penetration without supplying the lubricant 5. A laser range finder was attached to the leader 9 holding the pile 1, facing vertically downward. The top height of the soil taken into the pile 1 was continuously measured by this laser range finder. Meanwhile, the penetration length of the pile 1 was continuously measured by a function provided on the pile driver 7. The difference between the top height of the soil in the pile 1 and the depth of the tip of the pile was taken as the "length of the soil in the pile." FIG. 11 shows a graph comparing the length of soil inside the pile relative to the penetration length of the steel pipe, the pushing force required to penetrate the steel pipe, and the rotational torque required to rotate the steel pipe for the invention example (with lubricant) and the comparative example (without lubricant). The dashed lines in Figures 11(a) to 11(c) indicate the penetration length when the lubricant 5 stored in advance inside the pile in the example of the invention is used up. In other words, it can be determined that the lubricant 5 is supplied between the inner wall of the pile and the soil inside the pile up to a penetration length slightly exceeding 4m, and that the lubricant 5 is not supplied in the deeper range. The point at which the remaining amount of lubricant 5 in the pile 1 becomes 0 is determined as the point at which the lubricant 5 is used up.

[0051] As shown in Figure 11(a), in the comparative example (without lubricant), the elongation of the soil inside the pile becomes smaller from about a penetration length of 1.5 m. This indicates that soil blockage begins to occur inside the pile from about a penetration length of 1.5 m. Also, as shown in Figures 11(b) and 11(c), as the elongation of the soil inside the pile becomes smaller, the pushing force and rotation torque become larger, and it can be seen that construction resistance increases due to soil blockage occurring inside the pile.

[0052] On the other hand, in the example of the invention (with lubricant), the soil inside the pile continues to expand stably until the penetration length reaches the position of the dashed line, that is, while the lubricant 5 is being supplied, and it can be seen that soil blockage inside the pile is prevented. The pushing force and rotation torque are also stable at low values, and the construction resistance is also small. In the example of the invention, after the penetration length exceeds the broken line position, that is, after the supply of the lubricant 5 is stopped, the extension of the soil inside the pile decreases and the pushing force and rotation torque also increase. This indicates that the lack of supply of the lubricant 5 causes soil blockage inside the pile.

[0053] As described above, according to this embodiment, it has been demonstrated that it is possible to prevent soil blockage in the pile 1 and reduce construction resistance by rotating and penetrating the pile 1 while supplying the lubricant 5 between the inner wall of the pile 1 and the soil inside the pile 1. It has also been demonstrated that it is possible to improve the bearing capacity performance of the pile 1 by actively causing soil blockage at the end of construction (after the tip of the pile 1 reaches the specified depth) by not supplying the lubricant 5 after a specified depth. [Explanation of symbols]

[0054] 1 stake 3 Ground 5. Lubricants 7 Pile driver 9. Leader 11 Excavation materials 13. Aquarium 15 Mixer 17 Pump 19 Piping 21 Mixing element 23 Lubricant supply pipe

Claims

1. A method for constructing a pile, comprising the steps of: supplying a lubricant having a static viscosity higher than that of water and a shear-thinning property that reduces viscosity when subjected to shear force between an inner wall of the pile and soil and sand contained within the pile when a tubular pile is rotary-driven into the ground; A pile construction method, characterized in that the permeability coefficient k (m / s) of the lubricant in the ground satisfies the following formula (3), and the ratio of the viscosity coefficient (Pa s) of the lubricant according to the shear rate satisfies the following formula (4). k < 1 × 10 -5 ...(3) (μ´ / μ)<1×10 -1 ...(4) μ: Viscosity coefficient of the lubricant at a shear rate of 0.01 (1 / s) or less at a temperature of 15 degrees Celsius μ´: Viscosity coefficient of the lubricant at a shear rate of 2.5 (1 / s) or less at a temperature of 15 degrees Celsius

2. 2. The pile installation method according to claim 1, wherein the lubricant is supplied from a lubricant stored within the pile.

3. 3. A pile construction method as claimed in claim 1 or 2, characterized in that after the pile reaches a predetermined depth in the ground, the pile is rotated and penetrated without supplying the lubricant, thereby actively causing soil blockage within the pile.

4. 3. The pile construction method according to claim 1, wherein the supply amount V(L) of the lubricant is set so as to satisfy the following formula (1): 19.4 π D in ・(H-10D out )≦V≦19.4・π・D in ・(H+5D out ) ... (1) Where, H: Distance from the ground surface to a given depth (m) D out :Outer diameter of pile (m) D in :Inner diameter of pile (m)

Citation Information

Patent Citations

  • Pile driving method

    JP1981119032A

  • Open ended steel pipe pile for rotatingly jacking and rotatingly jacking method for open ended steel pipe pile

    JP2005127095A

  • Steel pipe pile for rotation press fit and press fit construction method using steel pipe pile

    JP2007284866A

  • Stable liquid composition of swollen superabsorbent polymer for ground excavation and construction method using the same

    JP2013057061A

  • Pile driving method and pile

    JP2016030925A