Filling materials for underground walls
A filling material using montmorillonite particles and a polymer compound with anionic functional groups forms a three-dimensional structure for high vibration damping and long-term stability, addressing the shortcomings of existing underground wall materials.
Patent Information
- Application Number
- JP2021115275
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-07-12
- Publication Date
- 2024-10-16
- Estimated Expiration
- 2041-07-12
AI Technical Summary
Existing filling materials for constructing underground walls to prevent the propagation of ground environmental vibrations lack sufficient vibration-proofing properties and long-term stability, as evidenced by the low performance of displacement-absorbing piles.
A filling material composed of montmorillonite particles, a polymer compound with an anionic functional group in its molecular chain, and water, forming a three-dimensional structure with moisture-retaining properties, which bonds montmorillonite particles via the polymer compound, creating a tabular combination that retains water and enhances vibration damping.
The material achieves high vibration damping properties and long-term stability by maintaining water retention and preventing vibration propagation, with a wave impedance ratio of 0.2 or less, ensuring effective isolation of vibrations from sources like traffic and construction.
Smart Images

Figure 0007568591000002 
Figure 0007568591000003 
Figure 0007568591000004
Abstract
Description
[Technical field]
[0001] The present invention relates to a filling material for constructing underground walls used to construct vibration isolation walls as a measure against the propagation path of ground environmental vibrations. [Background technology]
[0002] Measures to block the propagation path of ground environmental vibrations are used to construct underground walls in the ground through which the vibrations are transmitted.
[0003] As a method for constructing underground walls that block vibrations, for example, Patent Document 1 discloses a method in which displacement absorbing piles are installed between the ground improvement area and an adjacent existing structure or the surrounding ground to absorb displacement, thereby suppressing ground displacement and vibration associated with ground improvement. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2020-70582 A Summary of the Invention [Problem to be solved by the invention]
[0005] However, filling materials used to construct underground walls as a countermeasure against the propagation path of ground environmental vibrations must be vibration-proof, and this vibration-proofing is governed by the ratio α of the wave impedance (density x propagation speed) of the ground through which the vibration is transmitted and the vibration blocking wall. α<1.0 corresponds to mixed soil, mud walls, foam walls, etc., while α>1.0 corresponds to rigid walls such as soil cement and steel sheet piles. And when α<<1.0 or α>>1.0, the vibration-proofing is high. In addition, the retention of underground walls is also required, and high long-term stability is also required.
[0006] However, the displacement absorbing pile for absorbing displacement used in Patent Document 1 has low vibration isolation and insufficient long-term stability.
[0007] Therefore, an object of the present invention is to provide a filling material for constructing underground walls, which has high vibration-proofing properties and high retention and long-term stability of the underground walls. [Means for solving the problem]
[0008] The above-mentioned problems of the present invention can be solved by the present invention described below. That is, the present invention (1) comprises at least montmorillonite particles, a polymer compound having an anionic functional group in the molecular chain, and water, The tabular bonded montmorillonite particles are connected in a three-dimensional direction and have a three-dimensional structure that forms a moisture-retaining portion that retains the water, and water is retained in the moisture-retaining portion. the three-dimensional structure is composed of layered sections stacked in a stacking direction and cross-linked sections that are connected to adjacent layered sections and cross-linked, and the moisture-retaining section is formed by being surrounded by the layered sections and the cross-linked sections; the tabular bonded material of the montmorillonite particles is formed by bonding a side of the montmorillonite particle to a molecular chain of the polymer compound, so that a plurality of the montmorillonite particles are bonded to each other via the polymer compound; A filling material for underground wall construction characterized by It provides .
[0010] In addition, the present invention ( 2 ) is characterized in that the polymer compound having an anionic functional group in the molecular chain is a straight-chain anionic polymer compound which is a copolymer of acrylic acid and acrylamide (1 ) The present invention provides a filling material for constructing underground walls.
[0011] In addition, the present invention ( 3 The mass ratio of the polymer having an anionic functional group in the molecular chain to the montmorillonite particles (polymer compound / montmorillonite particles) is 0.02 to 0.40. Or (2) The present invention provides a filling material for constructing underground walls.
[0012] In addition, the present invention ( 4) is characterized in that the mass ratio of the montmorillonite particles to the water in the filling material for underground wall construction (montmorillonite particles / water in the filling material for underground wall construction) is 0.020 to 0.30. 3 ) a filling material for constructing underground walls.
[0013] In addition, the present invention ( 5 ) is characterized in that the mass ratio of the polymer compound having an anionic functional group in the molecular chain to the water in the filling material for underground wall construction (polymer compound / water in the filling material for underground wall construction) is 0.0010 to 0.020. 4 ) a filling material for constructing underground walls. Effect of the Invention
[0014] According to the present invention, it is possible to provide a filling material for constructing underground walls that has high vibration-proofing properties and high retention and long-term stability of the underground walls. [Brief description of the drawings]
[0015] [Figure 1] FIG. 2 is a schematic cross-sectional view for explaining the structure of the filling material for underground wall construction of the present invention. [Diagram 2] FIG. 2 is a schematic diagram for explaining a tabular bond of montmorillonite particles. [Diagram 3] 1 is an SEM photograph (2000x) of a cross section of the filling material for underground wall construction of Example 1. [Figure 4] 1 is an SEM photograph (3000x) of a cross section of the filling material for underground wall construction of Example 1. [Diagram 5] FIG. 1 is a schematic flow diagram showing a bender element tester. [Figure 6] FIG. 1 is a schematic diagram showing how a hole wall retention test is carried out. [Figure 7] 13 shows the results of a hole wall retention test. [Figure 8] 13 is a graph showing the results of an evaluation of vibration reduction properties of Example 2. [Figure 9]1 is a graph showing the results of an evaluation of vibration reduction properties in Comparative Example 1. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] The filling material for underground wall construction of the present invention contains at least montmorillonite particles, a polymer compound having an anionic functional group in the molecular chain, and water, The tabular aggregates of montmorillonite particles are connected in three-dimensional directions and have a three-dimensional structure that forms a moisture-retaining portion that retains the water, and water is retained in the moisture-retaining portion. the tabular bonded material of the montmorillonite particles is formed by bonding a side of the montmorillonite particle to a molecular chain of the polymer compound, so that a plurality of the montmorillonite particles are bonded to each other via the polymer compound; It is a filling material for underground wall construction characterized by the above.
[0017] The filling material for underground wall construction of the present invention will be described with reference to Figs. 1 and 2. Fig. 1 is a schematic cross-sectional view for explaining the structure of the filling material for underground wall construction of the present invention. Fig. 2 is a schematic view for explaining the bound material of montmorillonite particles. In Fig. 1, the filling material for underground wall construction 1 has a flat bound material of montmorillonite particles 2 and water (not shown) held in a water holding portion 3 formed by the flat bound material of montmorillonite particles 2. In this filling material for underground wall construction 1, the flat bound material of montmorillonite particles 2 has a structure connected in a three-dimensional direction, and is composed of layered portions 5 stacked in the stacking direction and bridging portions 6 that connect and bridge adjacent layered portions 5, and has a three-dimensional structure in which the bridging portions 6 are connected to the layered portions 5. In other words, the cross-linked portions 6 spread in the stacking direction between adjacent layer portions 5 and connect them by bridging, thereby supporting the space between the adjacent layer portions 5 and maintaining a gap in which water is retained, and the gap between the layer portions 5 and 5 is partitioned by the cross-linked portions 6 to form a moisture retention portion 3. The moisture retention portion 3 is formed by the adjacent layer portions 5 and the cross-linked portions 6, and water is retained in the moisture retention portion 3. Note that water has been omitted from FIG. 1 for convenience of drawing.
[0018] In FIG. 2, the flat-plate-like bound material 2 of montmorillonite particles is formed by montmorillonite particles 11 and a polymer compound 12 having an anionic functional group in the molecular chain. The flat part of the montmorillonite particle 11 is negatively charged, and the side part is positively charged, so that the positive charges are present so as to surround the periphery of the flat-plate-like montmorillonite particle 11. In contrast, the polymer compound 12 has an anionic functional group in the molecular chain, so that negative charges are scattered along the molecular chain. The side part of the montmorillonite particle 11 is electrostatically bound to the molecular chain of the polymer compound 12, and a plurality of montmorillonite particles 11 are bound via the polymer compound 12 to form the flat-plate-like bound material 2 of montmorillonite particles. At this time, the binding of the montmorillonite particles 11 forms a flat-plate-like bound material. Therefore, the flat-plate-like bound material 2 of montmorillonite particles is a bound material of montmorillonite particles, and has a flat shape. 2 shows an example in which the montmorillonite particles 11 are linked and bonded in only one direction, but in reality, they are linked and bonded in two dimensions. As described above, the bonded aggregate 2 of the tabular montmorillonite particles spreads in three dimensions in the filling material 1 for constructing underground diaphragm walls.
[0019] The filling material for constructing underground walls of the present invention contains at least montmorillonite particles, a polymer compound having an anionic functional group in the molecular chain, and water.
[0020] Montmorillonite particles are composed of multiple montmorillonite unit crystals stacked in layers. The montmorillonite unit crystals are composed of a tetrahedral sheet in which tetrahedra formed by silicon atoms and oxygen atoms are connected in a sheet-like shape, and an octahedral sheet in which ochedra formed by aluminum atoms and hydroxyl groups are connected in a sheet-like shape, forming a sandwich structure in which one octahedral sheet is sandwiched between two tetrahedral sheets.
[0021] Montmorillonite particles are tabular in shape and have a diameter of about 5 to 10 μm.
[0022] Montmorillonite unit crystals are the main component of bentonite, acid clay, etc. Bentonite is a type of tuff, and is a rock mainly composed of montmorillonite that has been subjected to thermal and stress changes for a long period of time and has been chemically altered. Bentonite is preferred as the raw material for the montmorillonite particles of the filling material for underground wall construction of the present invention. And, bentonite crushed into powder is preferably used as the raw material for the filling material for underground wall construction of the present invention.
[0023] The polymer compound having an anionic functional group in the molecular chain is not particularly limited as long as it has an anionic functional group in the molecular chain and can be electrostatically bonded to the side of the montmorillonite particle. Examples of the polymer compound having an anionic functional group in the molecular chain include homopolymers of acrylic acid, methacrylic acid, itaconic acid, maleic acid, acrylamido 2-methylpropanesulfonic acid, vinylsulfonic acid, styrenesulfonic acid, etc., or copolymers of one or more of acrylic acid, methacrylic acid, itaconic acid, maleic acid, acrylamido 2-methylpropanesulfonic acid, vinylsulfonic acid, and styrenesulfonic acid with acrylamide. Among these, the polymer compound having an anionic functional group in the molecular chain is preferably a straight-chain anionic polymer compound that is a copolymer of acrylic acid and acrylamide.
[0024] The molecular weight of the polymer compound having an anionic functional group in the molecular chain is not particularly limited, but is preferably 2 million or more and 10 million or less. The polymer compound having an anionic functional group in the molecular chain is in the form of a powder made of an acrylic polymer having an ionization degree of 0 to 100 mol % and a water-in-oil emulsion type having a dispersed particle size of 100 μm or less. The molecular weight of the polymer compound can be produced by a known method described in JP-B-34-10644 and the like.
[0025] The polymer compound having an anionic functional group in the molecular chain is different from the superabsorbent polymer used in the above Patent Document 1. Generally, the superabsorbent polymer has a water absorption capacity (amount) of 100 to 1000 times its own weight in water, but the polymer compound having an anionic functional group in the molecular chain used in the filling material for underground wall construction of the present invention does not have such water absorption capacity that it absorbs 100 to 1000 times its own weight in water. In addition, the polymer compound having an anionic functional group in the molecular chain used in the filling material for underground wall construction of the present invention has cohesive properties, but the superabsorbent polymer used in the above Patent Document 1 does not have cohesive properties. In addition, the superabsorbent polymer used in the above Patent Document 1 has a three-dimensional crosslinked structure, but the polymer compound having an anionic functional group in the molecular chain used in the filling material for underground wall construction of the present invention does not have a three-dimensional crosslinked structure but has a chain-like molecular structure.
[0026] The filling material for constructing underground walls of the present invention contains water. Water is present in the gaps between the tabular aggregates of montmorillonite particles and is added to maintain the size of the gaps.
[0027] In the filling material for underground wall construction of the present invention, the mass ratio of the polymer compound having anionic functional groups in the molecular chain to the montmorillonite particles (polymer compound / montmorillonite particles) is preferably 0.020 to 0.40, particularly preferably 0.040 to 0.20. When the mass ratio of the polymer compound to the montmorillonite particles (polymer compound / montmorillonite particles) is within the above range, a flat plate-like bond of the montmorillonite particles can be produced, and the retention performance of the underground wall can be obtained.
[0028] In the filling material for underground wall construction of the present invention, the mass ratio of the montmorillonite particles to water (moisture content in the filling material for underground wall construction) (montmorillonite particles / water) is preferably 0.020 to 0.30, particularly preferably 0.040 to 0.20. When the mass ratio of the montmorillonite particles to water (montmorillonite particles / water) is within the above range, the filling material has a hardness that allows it to be applied.
[0029] In the filling material for underground wall construction of the present invention, the mass ratio of the polymer compound to water (moisture content in the filling material for underground wall construction) (polymer compound / water) is preferably 0.0010 to 0.020, particularly preferably 0.0020 to 0.012. When the mass ratio of the polymer compound to water (polymer compound / water) is within the above range, the filling material has a hardness that allows it to be applied.
[0030] In addition to the above, the filling material for underground wall construction of the present invention may contain other components that are appropriately used in filling materials for underground wall construction. Examples of other components that are appropriately contained in the filling material for underground wall construction of the present invention include dispersants such as polycarboxylate anionic surfactants.
[0031] The filling material for underground wall construction of the present invention has a flat-plate-like bound material of montmorillonite particles formed by binding montmorillonite particles. The flat-plate-like bound material of montmorillonite particles is flat in shape and is connected in three dimensions. Note that the connection in three dimensions does not mean a structure in which flat-plate-like objects extending in two dimensions are layered, but means a structure in which the side of a flat-plate-like bound material extending in a two-dimensional direction is connected to the flat part of another flat-plate-like bound material extending in a two-dimensional direction.
[0032] The three-dimensional structure formed by the tabular bonded material of montmorillonite particles is preferably a structure consisting of layered parts stacked in the stacking direction and cross-linked parts connecting and bridging adjacent layered parts, with the adjacent layered parts and cross-linked parts forming a moisture-retaining part. In such a three-dimensional structure, the cross-linked parts spread in the stacking direction between adjacent layered parts and connect them by cross-linking, thereby supporting the space between adjacent layered parts and maintaining a gap for retaining water, and the gap between the layered parts is divided by the cross-linked parts, forming a moisture-retaining part.
[0033] In addition, in the filling material for underground wall construction of the present invention, water is retained in the moisture-retaining portion formed by the tabular bond of montmorillonite particles, thereby allowing water to be retained in the filling material for underground wall construction of the present invention.
[0034] In the filling material for underground wall construction of the present invention, the flat-shaped bonded material of montmorillonite particles is composed of montmorillonite particles and a polymeric compound having an anionic functional group in the molecular chain. The positive charges present on the sides of the montmorillonite particles and the negative charges scattered on the molecular chain of the polymeric compound having an anionic functional group in the molecular chain electrostatically bond the sides of the montmorillonite particles to the molecular chain of the polymeric compound having an anionic functional group in the molecular chain. As a result, a plurality of montmorillonite particles are bonded via the polymeric compound having an anionic functional group in the molecular chain to form a flat-shaped bonded material of montmorillonite particles. For example, in Figures 3 and 4, it is observed that the molecular chain of the polymeric compound extends from the flat-shaped bonded material of montmorillonite particles, and it can be seen that the montmorillonite particles are bonded in a flat shape by the action of the polymeric compound having an anionic functional group in the molecular chain.
[0035] The filling material for underground wall construction of the present invention is a material for constructing a vibration isolating wall that is installed to prevent traffic vibrations from roads, railways, etc., machine vibrations from factories, etc., and construction work vibrations generated during construction work, etc., from propagating to the surrounding ground. The vibration isolating wall is installed between a vibration source and adjacent land or the surrounding ground. Therefore, the filling material for underground wall construction of the present invention is cast into the ground between the vibration source and adjacent land or the surrounding ground.
[0036] The filling material for underground wall construction of the present invention has high vibration-proofing properties. The vibration-proofing properties of the filling material for underground wall construction are understood by the wave impedance ratio α. The wave impedance ratio α is the ratio of the wave impedance (density × propagation speed) of medium B (vibration blocking wall) to the wave impedance (density × propagation speed) of medium A when a different medium B (vibration blocking wall) is provided in a uniform medium A, and is expressed by the following formula (1): Wave impedance ratio α=(ρ2V2) / (ρ1V1) (1) (where ρ1 is the density of medium A (t / m 3 ) and ρ2 is the density of medium B (t / m 3), where V1 is the propagation velocity of the S-wave in medium A (m / sec), and V2 is the propagation velocity of the S-wave in medium B (m / sec). In formula (1), the filling material for underground wall construction (medium B) of the present invention has a ρ1 of 1.8 t / m 3 , the ratio α of the wave impedance (ρ2V2 (ρ2: density of the filling material for underground wall construction of the present invention, V2: propagation speed of S-waves in the filling material for underground wall construction of the present invention)) to the wave impedance (ρ1V1) of the ground (medium A) where V1 is 100 m / sec, is preferably 0.2 or less, more preferably 0.1 or less, and particularly preferably 0.05 or less. When the wave impedance ratio α of the filling material for underground wall construction is within the above range, the vibration-proofing properties are improved. On the other hand, when the wave impedance ratio α of the filling material for underground wall construction is less than the above range, the vibration-proofing properties are reduced.
[0037] The propagation speed of the S-wave of the filling material for underground wall construction of the present invention is preferably 30 m / sec or less, more preferably 15 m / sec or less. And, it is particularly preferable that the filling material for underground wall construction of the present invention does not propagate S-waves. In the present invention, the propagation speed of the S-wave of the medium (vibration barrier wall or ground) is measured using a bender element tester shown in FIG. 5. FIG. 5 is a schematic flow diagram showing a bender element tester for measuring the propagation speed of the S-wave of the medium vibration barrier wall or ground. In FIG. 5, the bender element tester 20 has a test container 27 filled with the medium 21 to be measured, a transmitting bender element 22 provided on the transmitting side of the medium 21 to be measured, a receiving bender element 23 provided on the receiving side of the medium 21 to be measured, a signal generator 25 that generates a test wave to be transmitted to the transmitting bender element 22, an amplifier 24 that amplifies the signal generated by the signal generator 25, and a waveform measuring instrument 26 that measures the received wave received by the receiving bender element 23. In the bender element tester 20, the amplifier 24 is electrically connected to the transmitting bender element 22, the signal generator 25 is electrically connected to the amplifier 24, and the waveform measuring device 26 is electrically connected to a position behind the amplifier 24 and before the transmitting bender element 22. The test wave of the amplifier 24 is transmitted to the transmitting bender element 22 and is also input to the waveform measuring device 26. The propagation velocity was measured using the bender element tester 20, and a propagation velocity of 30 kN / m was applied to the medium 21. 2 With this pressure applied, a test wave (frequency: 2 to 60 Hz) is generated by signal generator 25 and amplified by amplifier 24, transmitted to transmitting bender element 22, transmitted through medium 21, and received by receiving bender element 23. The transmitted wave and the test wave directly input from amplifier 26 are measured by a waveform measuring device. Next, the propagation time t of the transmitted wave from transmitting bender element 22 to receiving bender element 23 is found from the phase difference between the obtained transmitted wave and the test wave. Then, the propagation speed V of the transmitted wave through the medium is calculated using the formula "V=h / t" from the propagation time t of the transmitted wave and the interval h between transmitting bender element 22 and receiving bender element 23.
[0038] The filling material for underground wall construction of the present invention has high retention of underground walls. The retention of underground walls is grasped by a hole wall retention test. The test method of the hole wall retention test in the present invention will be described with reference to FIG. 6. In FIG. 6, (A) is a schematic perspective view showing a test container for hole wall retention test, (B) is a schematic perspective view showing a state in which a partition plate is installed in the test container shown in (A), and (C) is a schematic front view showing a state in which a test material filling section and a sand layer filling section of the test container with the partition plate installed are filled with a test material and wet sand, respectively. In the method of performing the hole wall retention test, first, a partition plate 32 is installed in a test container 31 made of a transparent material shown in (A) as shown in (B), and a test material 35 is filled in the test material filling section 33 and wet sand 36 is filled in the sand layer filling section 34 as shown in (C). Next, the partition plate 32 is gently pulled up vertically and removed from the test container 31. Next, the wall retention of the test material 35 is observed. The evaluation of the wall retention is as follows: when the test material 35 layer is observed from the front, if the width of the test material 35 layer after the partition plate is pulled out at a position 20% from the bottom of the test material 35 layer is 90% or more of the width of the test material 35 layer before the partition plate is pulled out, the wall retention is "good", and if it is less than 80%, the wall retention is "bad". For example, FIG. 7 shows an example of the test result. FIG. 7 is a photograph showing the test result, where (A) is the observation result from diagonally above, and (B) is the observation result from the front. In the test material on the left of (A) and (B) in FIG. 7, even when the partition plate is pulled out, the width at the position 20% from the bottom of the test material layer hardly changes, and the wall retention is judged to be "good". On the other hand, in the test materials in the center and right of Figure 7 (A) and (B), after the partition plate is pulled out, the width at the 20% position from the bottom of the test material layer is very small, and the wall retention is judged to be "x". In the hole wall retention test, the width 41 of the test material filling part 33 is 15.7 to 16.7 cm, the width 42 of the sand layer filling part 34 is 15.7 to 16.7 cm, the depth 43 of the test material filling part 33 and the sand layer filling part 34 is 16.0 to 18.5 cm, and the height 44 of the test material 35 layer and the height 45 of the wet sand 36 layer are 18.5 cm.
[0039] The filling material for underground wall construction of the present invention provides high long-term stability of the underground wall. In the filling material for underground wall construction of the present invention, the polymer having anionic functional groups in the molecular chain that bonds the montmorillonite particles together is a polymer with low water absorption, so even if cations such as calcium ions and sodium ions are present in the ground to be constructed, the water in the filling material for underground wall construction is unlikely to be discharged outside after construction. Therefore, the filling material for underground wall construction of the present invention provides high long-term stability after construction in the ground to be constructed. On the other hand, the displacement absorbing pile for absorbing displacement of Patent Document 1 uses a superabsorbent polymer (SAP), so if cations such as calcium ions and sodium ions are present in the ground to be constructed, the water impregnated in the displacement absorbing pile is discharged outside. Paragraph 0026 of Patent Document 1 states, "Here, the forced drainage agent is a salt such as calcium chloride or sodium chloride that forcibly discharges water impregnated in the displacement absorbing pile. In terms of function, for example, when polyacrylate-based SAP absorbs water, it ionizes, and when a forced drainage agent solution, which is an aqueous solution of the forced drainage agent, is poured from the outside, the ion concentration inside and outside the molecule is high outside and low inside, so the phenomenon in which water flows from the inside to the outside due to osmotic pressure is applied. Note that magnesium chloride or aluminum chloride may also be used as the forced drainage agent." It states that in displacement absorbing piles that use superabsorbent polymers, if cations such as calcium ions or sodium ions are present outside, that is, in the ground to be driven into, the water impregnated inside will be discharged to the outside.
[0040] The method for producing the filling material for underground wall construction of the present invention is not particularly limited, and any method may be used. An example of the method for producing the filling material for underground wall construction of the present invention is shown below, but the present invention is not limited to the material produced by this method.
[0041] The method for producing the filling material for underground wall construction of the present invention may, for example, include a method for producing a filling material for underground wall construction, which comprises a first step of mixing bentonite powder with adjusted water in which a dispersant is dissolved, and stirring the mixture, and a second step of mixing a polymer compound having an anionic functional group in the molecular chain with the mixture (1) obtained by carrying out the first step, and stirring the mixture.
[0042] The bentonite powder in the first step is obtained by pulverizing the bentonite to, for example, 5 to 10 μm. The dispersant in the first step is the same as the dispersant in the filling material for underground wall construction of the present invention. In the first step, the dispersant is dissolved in the adjusted water in advance to prepare the adjusted water in which the dispersant is dissolved, and the adjusted water in which the dispersant is dissolved is mixed with the bentonite powder and stirred for, for example, 60 to 120 seconds. The content of the dispersant in the adjusted water in which the dispersant is dissolved is appropriately selected, but the content of the dispersant is preferably 0.1 to 1.0 mass%. In the first step, the mixed amount of the bentonite powder and the adjusted water in which the dispersant is dissolved is such that the mass ratio of the bentonite powder to the adjusted water (excluding the dispersant) (bentonite powder / adjusted water) is preferably 0.020 to 0.30, particularly preferably 0.040 to 0.20.
[0043] The polymer compound having an anionic functional group in the molecular chain in the second step is the same as the polymer compound having an anionic functional group in the molecular chain in the filling material for underground wall construction of the present invention. In the second step, a polymer compound having an anionic functional group in the molecular chain is mixed with the mixture (1) obtained by carrying out the first step, and stirred for, for example, 60 to 360 seconds. In the second step, the amount of the polymer compound having an anionic functional group in the molecular chain is such that the mass ratio of the polymer compound to the water content in the adjusted water in which the dispersant mixed in the first step is dissolved (polymer compound / water in the filling material for underground wall construction) is preferably 0.0010 to 0.020, particularly preferably 0.0020 to 0.012. In addition, the amount of the polymer compound is such that the mass ratio of the polymer compound having an anionic functional group in the molecular chain to the bentonite powder (polymer compound / montmorillonite particles) is preferably 0.020 to 0.40, particularly preferably 0.040 to 0.20.
[0044] The filling material for underground wall construction of the present invention can be obtained by carrying out the above-mentioned method for producing the filling material for underground wall construction of the present invention.
[0045] The filling material for constructing underground walls of the present invention is prepared by an appropriate method and then cast into the ground where the underground wall is to be formed.
[0046] The present invention will be described in more detail below with reference to examples, but the present invention is not limited thereto. EXAMPLES
[0047] Example 1 (First step) 2 g of a dispersant (a type of polycarboxylate anionic surfactant) was dissolved in 928.9 g of water to prepare adjusted water in which the dispersant was dissolved. Next, 150 g of bentonite powder (manufactured by Hojun Co., Ltd., dry sieve (53 μm) residue 10.0% or less) was mixed with the entire amount of the adjusted water in which the dispersant had been dissolved, and stirred for 120 seconds to obtain mixture (1). (Second process) 10 g of a copolymer of acrylic acid and acrylamide (manufactured by Hymo Co., Ltd., product name SAVE-SP construction method additive L1) was mixed with the mixture (1) obtained above, and stirred for 300 seconds to obtain a filling material for underground wall construction. Next, the obtained filling material for underground wall construction was observed with an SEM, and SEM photographs were taken. The results are shown in Figure 3 (2000x) and Figure 4 (3000x).
[0048] The copolymer of acrylic acid and acrylamide used in the second step (manufactured by Hymo Co., Ltd., trade name SAVE-SP Construction Method Additive L1) is a polymeric compound having an anionic functional group in the molecular chain.
[0049] <Evaluation method> (Scanning Electron Microscopy (SEM)) The samples were pretreated by the following procedures: 1. flash freezing, 2. freeze-drying, and 3. sectioning of the dried samples. Next, measurements were performed using a scanning electron microscope (JSM-IT500HR, manufactured by JEOL Ltd.) under the conditions of (signal SED, incident voltage 3.0 kV, WD 50.0 mm, magnification: 2000x and 3000x).
[0050] (Measurement of density) The wet density can be calculated by dividing the mass m of the sample by the volume V determined by each method. Note that since the filling material for underground wall construction is not self-supporting, it cannot be calculated using a normal soil wet density test.
[0051] (Measurement of S-wave propagation velocity) The test was carried out using a bender element tester shown in FIG. The test material was filled into the test container 27 of the bender element tester 20. The test material was then subjected to a load of 30 kN / m 2 With this pressure applied, a test wave (frequency: 2 to 60 Hz) was generated by signal generator 25, amplified by amplifier 24, and transmitted to transmitting bender element 22, where it was transmitted through the test material. The transmitted wave was received by receiving bender element 23, and the transmitted wave through the test material and the test wave directly input from amplifier 24 were measured by a waveform measuring device. Next, the propagation time t of the transmitted wave from transmitting bender element 22 to receiving bender element 23 was calculated from the phase difference between the obtained transmitted wave and the test wave. Then, the propagation velocity V2 of the transmitted wave through the test sample was calculated from the propagation time t of the transmitted wave and the interval h between transmitting bender element 22 and receiving bender element 23 using the formula "V=h / t". In addition, ρ1 is 1.6t / m 3 The ratio of the wave impedance (ρ1V1) of the test material (medium B) to the wave impedance (ρ2V2 (ρ2: density of the test material, V2: propagation velocity of the S-wave of the test material)) of the ground (medium A) with V1 of 100 m / s is calculated by the following formula (1): Wave impedance ratio α=(ρ2V2) / (ρ1V1) (1) (where ρ1 is the density of medium A (t / m 3 ) and ρ2 is the density of medium B (t / m 3), where V1 is the propagation velocity of the S-wave in medium A (m / sec), and V2 is the propagation velocity of the S-wave in medium B (m / sec). The calculation was done using the following formula. In addition, when measuring the S-wave propagation velocity of the test sample, if no transmitted waves are observed due to the high vibration-proofing properties of the test sample, the propagation velocity V2 will be recorded as "0 (unmeasurable)" and the wave impedance ratio α will be recorded as "0".
[0052] (Hole wall retention test) A hole wall retention test was carried out using the test vessel and partition plate shown in FIG. A partition plate 32 was placed in the test container 31, a test material 35 was placed in the test material filling section 33, and dry sand (Ube silica sand No. 6, soil particle density ρs 2.634 g / cm 3 ) was placed in the sand layer filling section 34. 3 , fine grain content 1.1%), relative density Dr = 50% (packing density ρd = 1.452 g / cm 3 ) was filled in. Then, water was poured into the bottom of the sand to saturate it. Next, the partition plate 32 was slowly pulled up vertically and removed from the test container 31. Next, the retention of the walls of the test material was observed. The wall retention was evaluated by observing the test material layer from the front. If the width of the test material layer after the partition plate was removed at a position 20% from the bottom of the test material layer was 90% or more of the width of the test material layer before the partition plate was removed, the wall retention was rated as "good", and if it was less than 80%, the wall retention was rated as "poor".
[0053] Example 2 The same procedure as in Example 1 was carried out except that the mixing amounts of each compounding material were as shown in Table 1, and the S-wave propagation velocity and hole wall retention tests were carried out. The results are shown in Table 1.
[0054] Comparative Example 1 10g of superabsorbent resin (made by Hymo, product name Hymosub 300) was mixed with 1000g of water and stirred for 120 seconds. 5g of copolymer of acrylic acid and acrylamide (made by Hymo, product name SAVE-SP construction method additive L1) was mixed with the mixture obtained above to prepare an injection treatment liquid. The injection treatment liquid was mixed with mountain sand at an injection rate of 60% to obtain a mixed material. A measurement test of the S-wave propagation velocity was carried out, and the results are shown in Table 1.
[0055] Comparative Example 2 100 g of bentonite powder (manufactured by Hojun Co., Ltd., dry sieve residue of 10.0% or less (53 μm)) was mixed with 960.0 g of water and stirred for 120 seconds. Next, a hole wall retention test was carried out, and the results are shown in Table 1 and FIG.
[0056] [Table 1]
[0057] In the table, polymer compound A refers to a copolymer of acrylic acid and acrylamide.
[0058] (Reference example 1) A pore wall retention test was conducted using water as the test sample, and the results are shown in Figure 7.
[0059] In addition, in FIG. 7, the left photographs of (A) and (B) show the results of Example 2, the center photographs show the results of Comparative Example 2, and the right photographs show the results of Reference Example 1.
[0060] In the filling materials for underground wall construction of Examples 1 and 2, the polymer having anionic functional groups in the molecular chains that bond the montmorillonite particles together is a polymer with low water absorption, so even if cations such as calcium ions and sodium ions are present in the ground into which the material is to be poured, the water in the filling materials for underground wall construction is unlikely to be discharged after pouring. Therefore, it is clear from common technical knowledge that the filling materials for underground wall construction of Examples 1 and 2 have high long-term stability. On the other hand, since the displacement absorbing pile of Comparative Example 1 uses a super absorbent polymer (SAP), if cations such as calcium ions, sodium ions, etc. are present in the ground into which the pile is to be driven, the water impregnated in the displacement absorbing pile will be discharged to the outside. Therefore, it is clear from common technical knowledge that the filling material for the displacement absorbing pile of Comparative Example 1 has low long-term stability.
[0061] (Vibration reduction evaluation) A vibration-isolating wall was formed in the ground where the vibration-isolating wall was to be poured, using the filling material for underground wall construction manufactured in Example 2 and the filling material for displacement absorbing piles manufactured in Comparative Example 1, and the wall was vibrated with a vibrator (vertical vibrator) to evaluate its vibration reduction properties. First, the test material was poured to form a vibration isolating wall with a width of 7.6 m, a thickness of 0.5 m, and a depth of 5.5 m. Then, one month after pouring, the vibrator was excited at the ground surface at a position 2 m from the vibration isolating wall, and vibration measurements were taken at positions 3 m, 5 m, and 10 m from the excitation position, sandwiching the vibration isolating wall. The results are shown in Figure 8 (Example 2) and Figure 9 (Comparative Example 1). [Explanation of symbols]
[0062] 1. Filling material for vibration barrier construction 2. Tabular bond of montmorillonite particles 3 Moisture retention part 5 Layer 6 Crosslinked part 11 Montmorillonite unit crystal 12 Polymers with anionic functional groups in the molecular chain 20 Bender element test machine 21 Medium 22 Sending vendor element 23 Receiving vendor element 24 Amplifier 25 Signal Generator 26 Waveform measuring instrument 27 Test vessel 31 Test vessel 32 Partition 33 Test material filling section 34 Sand layer filling section 35 Test Materials 36 Wet Sand 41 Width of test material filling section 42 Width of sand layer filling 43 Depth of test material filling section and sand layer filling section 44 Height of test material layer and wet sand layer
Claims
1. The composition contains at least montmorillonite particles, a polymer compound having an anionic functional group in the molecular chain, and water, the tabular bonded mass of montmorillonite particles is connected in a three-dimensional direction and has a three-dimensional structure that forms a moisture-retaining portion that retains water, water is retained in the moisture-retaining portion, the three-dimensional structure is composed of layered portions that are stacked in the stacking direction and cross-linked portions that are connected to adjacent layered portions, and the moisture-retaining portion is formed by being surrounded by the layered portions and the cross-linked portions; the tabular bonded material of the montmorillonite particles is formed by bonding a side of the montmorillonite particle to a molecular chain of the polymer compound, so that a plurality of the montmorillonite particles are bonded to each other via the polymer compound; A filling material for underground wall construction characterized by:
2. 2. A filling material for underground wall construction according to claim 1, characterized in that the polymer compound having an anionic functional group in the molecular chain is a straight-chain anionic polymer compound which is a copolymer of acrylic acid and acrylamide.
3. The filling material for underground wall construction according to claim 1 or 2, characterized in that the mass ratio of the polymer compound having an anionic functional group in the molecular chain to the montmorillonite particles (polymer compound / montmorillonite particles) is 0.02 to 0.
40.
4. The filling material for underground wall construction according to any one of claims 1 to 3, characterized in that the mass ratio of the montmorillonite particles to the water in the filling material for underground wall construction (montmorillonite particles / water in the filling material for underground wall construction) is 0.020 to 0.
30.
5. The mass ratio of the polymer compound having an anionic functional group in the molecular chain to the water in the filling material for underground wall construction (polymer compound / water in the filling material for underground wall construction) is 0.0010 to 0.020.
Citation Information
Patent Citations
Lubricant for jacking method
JP2004189936A
Method for constructing underground wall
JP2012031664A
Ground displacement suppression method and displacement absorption pile
JP2020070582A
Construction of a fluid impermeable subterranean barrier wall
US5947644A