Hybrid rotary pile construction method and pile construction jig

The hybrid rotary pile method with a pile construction jig addresses the issue of excessive rotational force on pile joints by enabling efficient, cost-effective installation and tilt correction through directional rotation and engaging parts, facilitating seamless pile construction.

JP7570792B2Active Publication Date: 2024-10-22GECOSS CORP
View PDF 14 Cites 0 Cited by

Patent Information

Application Number
JP2021173442
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2020-10-23
Filing Date
2021-10-22
Publication Date
2024-10-22
Estimated Expiration
2041-10-22

AI Technical Summary

Technical Problem

Existing rotary piles face issues with excessive rotational force affecting the joint between the lower and upper piles, leading to structural complexity and limited directional rotation, and are costly.

Method used

A hybrid rotary pile method using a pile construction jig that allows the lower pile to be rotated clockwise or counterclockwise, with engaging parts on both sides of the lower pile body, enabling efficient press-fitting and easy correction of tilt, using a speed reducer and pile construction jig to insert and remove the upper pile.

Benefits of technology

The method enables efficient installation of hybrid rotary piles without excessive rotational force on the joint, allowing for easy correction of tilt and reducing structural complexity and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007570792000001
    Figure 0007570792000001
  • Figure 0007570792000002
    Figure 0007570792000002
  • Figure 0007570792000003
    Figure 0007570792000003
Patent Text Reader

Abstract

To provide a construction method of a hybrid rotary pile and a pile construction jig which can press a hybrid rotary pile into a ground extremely efficiently without applying an excessive torque to a joint portion of a lower pile and an upper pile.SOLUTION: A hybrid rotary pile 1 is rotated to be pressed into a ground using a pile construction jig 6. The hybrid rotary pile 1 is formed of: a lower pile 2 having a blade 5 on an outer periphery of a lower pile body 4 comprising a steel pipe; and an upper pile 3 formed of a shaped steel and joined to an upper end portion of the lower pile 2. The pile construction jig 6 includes: a jig body 9 formed in a cylindrical shape into which the upper pile 3 can be inserted; and an engaging portion 7 provided at a lower end portion of the jig body 9 and engaging with an engaged portion 8 provided at an upper end peripheral portion of the lower pile 2. The engaging portion 7 is hung at both sides of the engaged portion 8 along an outer peripheral face of the lower pile body 4. At a lower end portion of the engaging portion 7, there is provided a hook 7a protruding at a lower end side of the engaged portion 8 in an L-shape in a circumferential direction of the lower pile body 4 along the outer peripheral face of the lower pile body 4.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction method for hybrid rotary piles and a pile construction jig used in said pile construction method, which prevents the joint between the lower pile and the upper pile from being adversely affected by excessive rotational force when a hybrid rotary pile, which has a lower pile body made of a steel pipe with wings on the outer periphery and an upper pile joined to the upper end of the lower pile, is rotated and pressed into the ground, and also enables the inclination of the pile that occurs during construction to be easily corrected. [Background technology]

[0002] In the fields of architecture and civil engineering, temporary platforms are constructed prior to the start of the main construction work in order to secure work space for construction machinery and space for the temporary storage of construction materials, etc. (See Figures 11(a) and (b)). In such cases, H-shaped steel piles are generally used as the platform piles for the temporary platforms.

[0003] Also, known examples of prefabricated steel piles include rotary piles having one or more blades on the outer periphery of the tip support part of the pile body made of a steel pipe (Patent Documents 1 and 2), and rotary piles in which a lower pile (rotary pile) having blades on the outer periphery of the tip support part is joined to the upper end of a steel pile such as an H-shaped steel pile as an upper pile (Patent Document 3).

[0004] This type of rotary pile has blades that not only function as excavation blades, but also function as resistance blades against the surrounding ground after construction.This means that even in intermediate layers that are shallower than the original supporting layer, a certain level of bearing capacity can be secured by the blades of the lower pile, allowing the pile length to be shortened.It also has the advantage of reducing the amount of waste soil that accompanies drilling, so demand is expected to grow in the future.

[0005] This type of rotary pile is set up on the ground surface along the leader of a pile driver and installed in the ground by rotating it using a reducer and pushing it into the ground. However, the latter type of rotary pile in particular has the problem that the joint between the lower pile and the upper pile is easily adversely affected by excessive rotational force.

[0006] As a method for solving such problems, for example, Patent Document 3 discloses an invention of a steel pile installation device that includes a steel pile with an auger screw at the tip and an outer steel pipe that is fitted around the steel pile and rotary-driven into the ground.

[0007] Simply put, the steel pile has a configuration in which the shaft of the auger screw and the web of the steel structure are integrated, and a tip support plate / rotation stabilizing plate that is inscribed in the outer steel pipe is fixed to the tip of the steel structure, and a torque receiver is provided to engage with the outer steel pipe. Meanwhile, the outer steel pipe can be rotated at its upper part by a motor suspended from the crane of a work vehicle, and its lower part engages with the torque receiver to transmit the torque of the outer steel pipe to the auger screw for rotary excavation, and the rotation diameter of the auger screw is larger than the rotation diameter of the outer steel pipe.

[0008] Furthermore, Patent Document 4 discloses an invention relating to a connection structure between an excavation member used at the tip of a foundation pile and functioning as the foundation of a building, and a tubular body portion connected to the upper end of the excavation member.

[0009] Simply put, the excavation member comprises a cylindrical base body with a closed lower end, and a rotating blade on the outer surface of the base body that rotates around an axis together with the base body to excavate soil, and also comprises a cylindrical protrusion on the outer surface of the base body that protrudes radially outward.

[0010] The tubular portion comprises a cylindrical tubular body and an abutment portion protruding downward from the lower end of the tubular body. The abutment portion is composed of a first extension portion and a second extension portion which intersect with each other to form an L-shape, and an abutment surface having a surface normal which faces diagonally upward is formed at the interior angle formed by the intersection of the two extension portions.

[0011] By abutting the protrusion against the abutment surface and applying a contact force, the excavation member is pressed against the tubular body portion, eliminating any gaps at the joint between the excavation member and the tubular body portion and preventing the inflow of soil and sand through these gaps. [Prior art documents] [Patent documents]

[0012] [Patent Document 1] JP 2016-079619 A [Patent Document 2] JP 2015-129386 A [Patent Document 3] Japanese Patent Application Publication No. 6-272249 [Patent Document 4] JP 2015-200092 A Summary of the Invention [Problem to be solved by the invention]

[0013] However, in the invention of Patent Document 3, the rotational force of the motor is transmitted to the screw auger by a clutch mechanism, which can result in a pile driving device that is structurally complex and expensive.

[0014] In addition, the invention of Patent Document 4 has a problem in that the L-shaped abutment portion protruding from the lower end of the pipe body is formed on only one side of the protrusion protruding from the outer peripheral surface of the base of the drilling member, so that only the rotational force of the pipe body in one direction can be transmitted to the drilling member, and therefore the drilling member cannot be rotated freely in both forward and reverse directions.

[0015] The present invention has been made to solve these problems, and in particular, has an object to provide a construction method for a hybrid rotary pile that allows the hybrid rotary pile to be freely rotated in either clockwise or counterclockwise direction, and also enables it to be pulled out, thereby enabling the hybrid rotary pile to be installed at a specified depth effortlessly and extremely efficiently, and a pile construction jig for use in said construction method. [Means for solving the problem]

[0016] The present invention is a construction method for a hybrid rotary pile, which comprises a lower pile having wings on the outer periphery of a lower pile body made of a steel pipe, and an upper pile formed from structural steel and joined to the upper end of the lower pile, and which involves pressing the hybrid rotary pile into the ground while rotating it.The present invention is characterized by using a pile construction jig which comprises a jig body formed in a cylindrical shape through which the upper pile can be inserted, and an engaging portion provided at the lower end of the jig body and which engages with an engaged portion provided on the outer periphery of the upper end of the lower pile, the engaging portions being vertically installed on both sides of the engaged portion along the outer periphery of the lower pile body, and which includes the following steps. (1) A process of erecting the lower pile on the ground surface along the leader of a pile driver and connecting a reducer that moves up and down along the leader to the upper end of the lower pile. (2) activating the reducer and rotating the lower pile by the reducer while pressing it into the ground along the leader. (3) A process of temporarily stopping the reducer while leaving a portion of the upper end of the lower pile above ground, and disconnecting the reducer from the upper end of the lower pile. (4) A process of attaching the pile construction jig, with the upper pile already installed, to the upper end of the lower pile along the leader of the pile driver, and joining the upper pile and the lower end of the pile construction jig to the upper end of the lower pile. (5) A process of operating the reducer and rotating the lower pile via the pile construction jig while pressing the lower pile together with the upper pile into the ground. (6) A process in which, after the lower pile and the upper pile are pressed into the supporting layer, only the pile construction jig is pulled out from the ground.

[0017] In particular, by vertically installing the engaging parts of the pile construction jig on both sides of the engaged part along the outer circumferential surface of the lower pile body, the lower pile can be freely rotated in both clockwise and counterclockwise directions, and by providing a hook (horizontal part) that protrudes in an L-shape in the circumferential direction of the lower pile body along the outer circumferential surface of the lower pile body at the lower end of the engaging part, the lower pile can be pulled out via the pile construction jig, so that hard ground can be easily excavated and the inclination of the lower pile body that occurs during excavation can be easily corrected. Furthermore, by rotating the lower pile, it is possible to prevent excessive rotational force from acting on the joint between the lower pile and the upper pile.

[0018] In addition, by forming the jig body of the pile construction jig with an inner diameter that can circumscribe the upper end of the lower pile body and the engaged portion (capable of containing the upper end of the lower pile body and the engaged portion), and by providing the engaging portion on the inner side of the jig body, the engaging portion can be easily engaged with the engaged portion at the upper end of the lower pile body.

[0019] In other words, when the lower end of the jig body is circumscribed against the upper end of the lower pile body and the engaged portion, and the pile construction jig is then rotated around its axis, the engaged portion is automatically inserted between the engaging portions at a position where the engaged portion and the gap portion w coincide.

[0020] When the engaged portion is inserted between the engaging portions, the lower end of the jig body is placed on the topmost blade attached to the upper end of the lower pile body, so that the pile construction jig can be held at the upper end of the lower pile body and will not fall below the lower pile body. Also, a stopper that receives the lower end of the jig body may be separately attached to the outer periphery of the upper end of the lower pile body.

[0021] In addition, since the engaging portion is stored within the jig body and does not protrude from the periphery or the lower end of the jig body, it does not become a resistance body of the hole wall when the hybrid rotary pile is pressed in, so that the hybrid rotary pile can be pressed in very efficiently into the ground. In addition, it is possible to prevent damage to the engaging portion when the pile construction jig is installed, transported, or otherwise handled. Effect of the Invention

[0022] According to the present invention, when constructing a hybrid rotary pile consisting of a lower pile made of a steel pipe and an upper pile made of structural steel such as an H-shaped steel joined to the upper end of the lower pile, the lower pile can be rotated and pressed into the ground without applying excessive rotational force to the joint between the lower pile and the upper pile.

[0023] In addition, the engaging portion provided at the lower end of the pile construction jig is vertically installed along the outer peripheral surface of the lower pile body on both sides of the engaged portion provided at the upper end of the lower pile, allowing the lower pile to be rotated freely in both clockwise and counterclockwise directions.Furthermore, a hook is provided at the lower end of the engaging portion which protrudes in an L-shape circumferentially around the lower pile body along the outer peripheral surface of the lower pile body from the underside of the engaged portion, allowing the lower pile to be pulled out.This makes it easy to excavate hard ground and also makes it easy to correct any inclination of the pile that occurs during excavation. [Brief description of the drawings]

[0024] [Figure 1] FIG. 1 is a front view of a pile construction jig according to one embodiment of the present invention, which is used when installing a hybrid rotary pile made of a steel pipe and a shaped steel by rotary pressing into the ground. [Diagram 2] Figure (a) is an enlarged view of a portion of the hybrid rotary pile and the pile construction jig, and Figure (b) is a cross-sectional view along line I-I in Figure (a). [Diagram 3] FIG. 2 is a front view showing the state in which the lower end of the pile construction jig is engaged with the upper end of the lower pile of the hybrid rotary pile. [Figure 4] FIG. 1 shows an example of a hybrid rotary pile, where FIG. 1(a) is a front view and FIG. 1(b) is an enlarged cross-sectional view of line R-R in FIG. [Diagram 5] FIG. 11 shows another embodiment of the pile construction jig, in which FIG. 11(a) is a partially enlarged view of the hybrid rotary pile and the pile construction jig, and FIG. 11(b) is a cross-sectional view taken along line H-H in FIG. [Figure 6]It is a front view showing a state in which the lower end of the pile driving jig is engaged with the upper end of the lower pile of the hybrid rotary pile. [Figure 7] Another embodiment of the pile driving jig. Fig. (a) is a partially enlarged view of the hybrid rotary pile and the pile driving jig, and Fig. (b) is a cross-sectional view taken along line II-II in Fig. (a). [Figure 8] It is a front view showing a state in which the lower end of the pile driving jig is engaged with the upper end of the lower pile of the hybrid rotary pile. [Figure 9] Another embodiment of the pile driving jig. Fig. (a) is a partially enlarged view of the hybrid rotary pile and the pile driving jig, and Fig. (b) is a cross-sectional view taken along line HH-HH in Fig. (a). [Figure 10] Figs. (a) to (d) are explanatory diagrams showing the construction procedure of the hybrid rotary pile using the pile driving jig. [Figure 11] A temporary scaffold using a hybrid rotary pile for the foundation pile. Fig. (a) is a partial perspective view, and Fig. (b) is a partial plan view.

Embodiments for Carrying Out the Invention

[0025] Figs. 1 - 9 show an embodiment of the present invention, and illustrate a pile driving jig that transmits the rotational force of a speed reducer installed on a pile driver to a hybrid rotary pile when the hybrid rotary pile is press-fitted while being rotated underground.

[0026] In the figure, the hybrid rotary pile 1 is formed of a lower pile 2 and an upper pile 3 joined to the upper end of the lower pile 2. The lower pile 2 has a lower pile main body 4 made of a steel pipe and one or more blades 5 attached to the outer periphery of the lower pile main body 4. An engaged portion 8 that engages with an engaging portion 7 formed at the lower end of a pile driving jig 6 described later is formed on the outer peripheral surface of the upper end of the lower pile main body 4.

[0027] The engaged portion 8 is formed from a vertically elongated rectangular steel piece, which is attached to the upper outer peripheral surface of the lower pile main body 4 by welding or by mounting bolts along the pipe axis direction of the lower pile main body 4, and is also attached at equal intervals (for example, 45° or 90° intervals) around the circumference of the lower pile main body 4.

[0028] In addition, the steel piece serving as the engaged portion 8 is attached so that its upper end portion (e.g., the upper half) protrudes a predetermined length upward from the upper end surface of the lower pile main body 4, and is attached opposite each other in the diameter direction of the lower pile main body 4.

[0029] The bolted steel pieces are removable, and steel pieces with optimal cross-sectional diameter and length are attached depending on the magnitude of rotational force transmitted to the lower pile 2.

[0030] The blades 5 are attached at equal intervals, one at the tip of the lower pile body 4, and one or more above the tip. The blades 5 are attached in a disk shape that continues for one revolution around the circumferential direction of the lower pile body 4, or in a spiral shape that continues for several revolutions around the circumferential direction of the lower pile body 4.

[0031] Furthermore, the blades 5 are attached to the outer peripheral surface of the lower pile body 4 by welding or by mounting bolts, and in particular the bolted blades 5 are made removable, and by changing the outer diameter, number and / or spacing according to the bearing capacity of the stratum at the tip of the pile, a specified bearing capacity can be obtained even in an intermediate layer that is shallower than the original bearing layer.

[0032] The upper pile 3 is formed from shaped steel such as H-shaped steel, I-shaped steel or channel steel, or a cross-shaped steel, and is joined to the upper end of the lower pile body 4 by welding or by mounting bolts.

[0033] In addition, the length of the upper piles 3 can be extended as desired by adding more sections depending on the depth of the supporting layer. Also, because the upper piles 3 are made of structural steel such as H-shaped steel or cross-shaped steel, the upper piles 3 can be easily joined to the lower piles 2 and to each other by welding or fastening bolts using the flanges and / or webs of the upper piles 3. Furthermore, the upper piles 3 can be set up on the ground as temporary columns, and components such as beams and braces can be easily joined using the flanges and / or webs as joints.

[0034] The pile construction jig 6 has a jig body 9 and multiple engagement portions 7 formed at the lower end of the jig body 9, and the jig body 9 is formed from a steel pipe having an outer diameter approximately the same as that of the lower pile body 4 of the lower pile 2, and an inner diameter allowing the upper pile 3 to be inserted therethrough.

[0035] The engagement portion 7 is formed from a steel piece having a rectangular cross-section and a vertically elongated L-shape, and the steel piece is attached to the outer peripheral surface of the lower end portion of the jig body 9 by welding or by mounting bolts, and is attached at a predetermined interval around the circumferential direction of the jig body 9.

[0036] In addition, each engaging portion 7 is attached so that its lower end side portion (e.g., the lower half) protrudes a certain length downward from the lower end surface of the jig main body 9, and every two engaging portions 7, 7 adjacent to each other in the circumferential direction of the jig main body 9 form a pair, and one steel piece is attached to each pair in an inverted L-shape.

[0037] Furthermore, hooks (horizontal portions) 7a, 7a at the lower end portions are opposed to each other, and are attached so as to have a gap w slightly wider than the width of the engaged portion 8 between the opposed hooks 7a, 7a.

[0038] When the pile construction jig 6 is erected on the upper end of the lower pile 2, the engaged portions 8, 8 of the lower pile 2 are simultaneously inserted between each pair of engaging portions 7, 7 through the gaps w between the hooks 7a, 7a.

[0039] In addition, with the engaged portion 8 inserted between each pair of engaging portions 7, 7, when the pile construction jig 6 rotates around its axis, one of the engaging portions 7, 7 engages (abuts) with the engaged portion 8 in the circumferential direction of the pile construction jig 6, causing the lower pile 2 to rotate clockwise or counterclockwise together with the pile construction jig 6.

[0040] Furthermore, the engaged portion 8 is positioned on one side of the engaging portions 7, 7, and the lower end portion 8a of the engaged portion 8 engages (abuts) with one of the hooks 7a of the engaging portions 7, 7, so that the lower pile 2 is pulled up together with the pile construction jig 8.

[0041] With this configuration, with the engaged portion 8 inserted between the engaging portions 7, 7, the pile construction jig 6 can be rotated alternately clockwise and counterclockwise and raised and lowered, thereby allowing the lower pile 2 to be rotated clockwise and counterclockwise and raised and lowered together with the pile construction jig 6.This allows the lower pile 2 to be rotationally driven into the desired depth together with the upper pile 3 very efficiently without applying excessive rotational force to the joint between the lower pile 2 and the upper pile 3.

[0042] Figures 5 and 6 show another embodiment of the pile construction jig, in which each pair of engaging portions 7, 7 does not have a hook (horizontal portion) 7a, 7a at the lower end, is formed with a rectangular cross-section, and is formed into a simple columnar shape that continues along the axial direction of the lower pile 2, making it easy to manufacture.

[0043] Furthermore, if tapered surfaces 7b, 7b that diverge in an eight-shape toward the lower end are formed opposite each other on the opposing surfaces of the lower end of each pair of engaging portions 7, 7, the engaged portion 8 of the lower pile 2 can be smoothly inserted between the engaging portions 7, 7 even if the gap w between the engaging portions 7, 7 is narrow.

[0044] Figures 7 and 8 also show another embodiment of the present invention, in which the jig body 9 of the pile construction jig 6 has an inner diameter capable of circumscribing the upper end and engaged portion 8 of the lower pile body 4 of the lower pile 2, and the engaging portions 7, 7 are formed on the inner surface of the lower end of the jig body 9.

[0045] Furthermore, guide ribs 10 are attached between each of the engagement portions 7, 7 adjacent to each other in the circumferential direction of the jig body 9, except for the section of the gap portion W. The guide rib 10 is formed from a steel piece that forms an arc along the inner peripheral surface of the jig body 9, and the steel piece is attached at the same level as the hooks 7a, 7a of each of the engagement portions 7, 7, and is attached horizontally along the inner peripheral surface of the jig body 9.

[0046] 9 also illustrates another embodiment of the present invention, in which the jig body 9 of the pile construction jig 6 has an inner diameter capable of circumscribing the lower pile body 4 and engaged portion 8 of the lower pile 2, and the engaging portions 7, 7 are formed on the inner peripheral surface of the lower end portion of the jig body 9. In addition, the engaging portion 7 does not have a hook 7a, and is formed in a columnar shape in the axial direction of the lower pile body 4.

[0047] Further, guide ribs 10 are attached between each of the engagement portions 7, 7 adjacent to each other in the circumferential direction of the jig body 9, except for the section of the gap portion W. The guide ribs 10 are attached at the same level as the lower ends of the engagement portions 7, 7, and are attached horizontally along the inner peripheral surface of the jig body 9.

[0048] In all of the embodiments shown in Figures 7 to 9, the engagement portions 7, 7 are attached within the jig body 9 and do not protrude beyond the lower end of the jig body 9, so that the lower end of the pile construction jig 6 can be easily engaged with the upper end of the lower pile 2.

[0049] In other words, by circumscribing the lower end of the jig body 9 with the upper end of the lower pile body 4 and the engaged portion 8, and rotating the jig body 9 around its axis, the engaged portion 8 is inserted between the engaging portions 7, 7 at a position where the positions of the engaged portion 8 and the gap portion w coincide.

[0050] Furthermore, when the lower end of the jig body 9 is circumscribed against the upper end of the lower pile body 4 and the engaged portion 8, the hook (horizontal portion) 7a of the engaging portion 7 and the guide rib 10 abut against the upper end of the engaged portion 8 from above and below, preventing the jig body 9 from falling, and the pile construction jig 6 can be freely rotated around its axis at the upper end of the lower pile body 4.

[0051] In addition, when the engaged portion 8 is inserted between the engaging portions 7, 7, the lower end of the jig body 9 is placed on the blade 5 attached to the upper end of the lower pile body 4, so that the pile construction jig 6 does not fall any further. A stopper (not shown) for receiving the lower end of the jig body 9 may be separately attached to the outer circumferential surface of the upper end of the lower pile body 4.

[0052] Furthermore, since the engaging portions 7,7 are stored within the jig body 9 and do not protrude from the lower end of the jig body 9, damage to the engaging portions 7,7 can be prevented when the pile driving jig 6 is handled.

[0053] The pile driving jig 6 thus formed is connected to a reducer 12 of a pile driver 11, and is adapted to ascend and descend along a leader 13 together with the reducer 12 while being rotated by the reducer 12 (see FIG. 10).

[0054] Next, a method for constructing a hybrid rotary pile using the pile driving jig 6 of the present invention will be described (see Figs. 10(a) to (d)). (1) First, the lower pile 2 is set vertically on the ground surface along the leader 13 of the pile driver 11, and the reducer 12 is connected to the upper end of the lower pile 2. (2) Next, the reducer 12 is operated, and the lower pile 2 is rotated by the reducer 12 while being pressed into the ground along the leader 13. Then, the reducer 12 is stopped temporarily with a portion of the upper end of the lower pile 2 remaining above ground, and the reducer 12 is temporarily disconnected from the upper end of the lower pile 2. (3) Next, the pile construction jig 6, into which the upper pile 3 has been inserted beforehand, is vertically attached to the upper end of the lower pile 2 along the leader 13. Then, the lower end of the upper pile 3 is joined to the upper end of the lower pile 2, and the lower end of the pile construction jig 6 is engaged with the upper end of the lower pile 2. In this case, the pile construction jig 6 is erected on the upper end of the lower pile 2, and at the same time, the engaged portion 8 of the lower pile 2 is inserted between the engaging portions 7, 7 of the pile construction jig 6 through the gap w between the hooks 7a, 7a, so that the lower end of the pile construction jig 6 engages with the upper end of the lower pile 2. The lower end of the upper pile 3 may be joined to the upper end of the lower pile body 4 of the lower pile 2 by welding or by a joining plate and a joining bolt. Alternatively, the upper pile 3 may be first set up on the upper end of the lower pile 2 , and then the pile construction jig 6 may be placed over the upper pile 3 and its lower end engaged with the upper end of the lower pile 2 .

[0055] (4) Next, the reducer 12 is operated again, and the lower pile 2 is rotated together with the pile construction jig 6 while being pressed into the ground together with the upper pile 3. During the construction of the lower pile 2, if the lower pile 2 hits a hard stratum and cannot be pressed in smoothly, or if the lower pile 2 is tilted at an angle, the pile construction jig 6 can be rotated together with the lower pile 2 several times clockwise and counterclockwise, or raised and lowered while rotating forward and backward, thereby enabling the lower pile 2 to be pressed in smoothly and the tilt of the lower pile 2 to be easily corrected. (5) Then, once the lower pile 2 and the upper pile 3 have been installed in the specified stratum, only the pile construction jig 6 is detached from the upper end of the lower pile 2 and pulled out from the ground, completing the construction of the hybrid rotary pile 1. [Industrial Applicability]

[0056] The present invention provides a hybrid rotary pile, which consists of a lower pile having wings on the outer periphery of the lower pile body made of a steel pipe, and an upper pile formed from structural steel and joined to the upper end of the lower pile, that can be rotary-driven into the ground very efficiently without applying excessive rotational force to the joint between the lower pile and the upper pile, and can easily correct any inclination of the hybrid rotary pile that occurs during construction. [Explanation of symbols]

[0057] 1 Hybrid Rotary Pile 2 Lower pile 3 Upper pile 4 Lower pile body 5. Feather 6 Pile construction jig 7 Engagement part 7a Hook (horizontal part) 7b Taper 8 Engaged part 8a Lower end 9 Jig body 10 Guide rib 11 Pile driver 12 Reducer 13 Leader w Gap

Claims

1. A construction method for a hybrid rotary pile, which comprises a lower pile having wings on the outer periphery of a lower pile body made of a steel pipe, and an upper pile formed of a shaped steel and joined to the upper end of the lower pile, and which presses the hybrid rotary pile into the ground while rotating it, the construction method for a hybrid rotary pile comprising: a jig body formed in a cylindrical shape through which the upper pile can be inserted; and an engagement portion provided at the lower end of the jig body, the engagement portion having an engagement portion provided in a columnar shape along the axial direction of the lower pile body on the upper outer periphery of the lower end of the lower pile body, the engagement portion being vertically arranged in a columnar shape along the axial direction of the lower pile body, the lower end of the engagement portion being provided with an L-shaped hook that protrudes in a circumferential direction of the lower pile body along the outer periphery of the lower pile body, and the engagement portion is arranged so as to be engageable between the engagement portions through a gap provided between the tip ends of the hooks. (1) A process of erecting the lower pile on the ground surface along the leader of a pile driver and connecting a reducer that moves up and down along the leader to the upper end of the lower pile. (2) activating the reducer and rotating the lower pile by the reducer while pressing the lower pile into the ground along the leader. (3) A process of temporarily stopping the reducer while leaving a portion of the upper end of the lower pile above ground, and then disconnecting the reducer from the upper end of the lower pile. (4) A process of attaching the pile construction jig, into which the upper pile has already been installed, to the upper end of the lower pile along the leader. (5) A step of joining the lower end of the upper pile to the upper end of the lower pile. (6) A process of engaging the engaging portions of the pile construction jig with both sides of the engaged portion of the upper end portion of the lower pile. (7) A process of operating the reducer to rotate the lower pile via the pile construction jig while pressing the lower pile together with the upper pile into the ground. (8) A process in which, after the lower pile and the upper pile are pressed into the supporting layer, only the pile construction jig is pulled out from the ground.

2. A construction method for a hybrid rotary pile as described in claim 1, characterized in that during construction, the construction jig is raised and lowered while rotating forward and backward together with the lower pile and the upper pile.

3. A pile construction jig used to press a hybrid rotary pile, which consists of a lower pile having wings on the outer periphery of a lower pile body made of a steel pipe, and an upper pile formed of a structural steel and joined to the upper end of the lower pile, into the ground while rotating it, characterized in that the pile construction jig has a jig body formed in a cylindrical shape into which the upper pile can be inserted, and an engaging portion provided at the lower end of the jig body and engaging both sides of an engaged portion provided in a columnar shape along the axial direction of the lower pile body on the upper outer periphery of the lower end of the lower pile body, the engaging portion being vertically provided in a columnar shape along the axial direction of the lower pile body, and the lower end side of the engaged portion is provided along the outer periphery of the lower pile body in an opposing circumferential direction of the lower pile body, and the engaged portion is provided so as to be engageable between the engaging portions through a gap provided between the tip ends of the hooks.

4. 4. The pile construction jig according to claim 3, wherein the jig body has an inner diameter capable of circumscribing the upper end portion of the lower pile body and the engaged portion, and the engaging portion and the L-shaped hook are provided on the inner side of the jig body.

Citation Information

Patent Citations

  • Penetration of casing and casing for extension

    JP1987086228A

  • Device for removing existing concrete pile

    JP1993033342A

  • Cap for rotating burying and extraction of winged steel pipe piles

    JP1994030224U

  • Erecting device for shape steel pile and shape steel pile used for the device

    JP1994272249A

  • Rotational embedding method for existing pile with less soil displacement

    JP2003253671A