Production Management System

The production management system addresses the issue of production interruptions by automatically replacing faulty component supply units, enhancing labor efficiency and productivity in component mounting machines.

JP7576173B2Active Publication Date: 2024-10-30FUJI CORP
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023529361
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-06-24
Publication Date
2024-10-30
Estimated Expiration
2041-06-24

AI Technical Summary

Technical Problem

Conventional automatic replacement systems for component supply units in component mounting machines stop production when an abnormality occurs, reducing labor-saving effects and productivity.

Method used

A production management system with a device pallet, replenishment pallet, and transport unit that automatically replaces a faulty component supply unit with a functional one, ensuring continuous production.

Benefits of technology

The system achieves significant labor savings and improves productivity by automatically replacing faulty component supply units, allowing uninterrupted operation of component mounting machines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007576173000001
    Figure 0007576173000001
  • Figure 0007576173000002
    Figure 0007576173000002
  • Figure 0007576173000003
    Figure 0007576173000003
Patent Text Reader

Abstract

This production management system comprises: a device pallet on which a plurality of component supplying units, which supply components to the component absorption positions of a component mounting machine for mounting the components on circuit boards, are aligned in a board carrying direction and are set; a resupply pallet that accommodates next component supplying units by which used component supplying units on the device pallet are to be replaced and that retrieves the used component supplying units; a carrying subsystem that disposes / removes and carries component supplying units between the device pallet and the resupply pallet; and a carriage control subsystem that, upon occurrence of a failure in a first component supplying unit having been set on the device pallet, controls the carrying subsystem to remove, from the device pallet, the first component supplying unit in which the failure has occurred and to carry and set, to the device pallet, a second component supplying unit by which the first component supplying unit in which the failure has occurred can be replaced and which is accommodated by the resupply pallet.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present specification relates to a production management system that manages a plurality of component supply units used in a component mounting machine. [Background technology]

[0002] A technology for mass-producing circuit board products by performing substrate-related operations on circuit boards is becoming widespread. A typical example of a substrate-related operation machine that performs substrate-related operations is a component mounting machine that mounts components on a circuit board. Many component mounting machines are equipped with detachable component supply units, and components are replenished by replacing the component supply units. In recent years, systems that manage the automatic replacement of component supply units have been put into practical use to reduce the labor required for component supply. A typical example of a component supply unit is a tape feeder that uses a carrier tape. An example of a technique related to the automatic replacement of a tape feeder is disclosed in Patent Document 1.

[0003] The production management system for a component mounting line disclosed in Patent Document 1 operates an automatic changer to change the feeder arrangement of each component mounter to the feeder arrangement specified in the production job. According to this, it is said that by changing the feeder arrangement, it is possible to increase production efficiency and shorten production time. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] International Publication No. 2018 / 087854 Summary of the Invention [Problem to be solved by the invention]

[0005] Incidentally, the automatic replacement system for component supply units described in Patent Document 1 and other publications is excellent in terms of labor saving in that it can automatically replace used tape feeders when the carrier tape has been used up. However, in conventional systems, when an abnormality occurs in a tape feeder during use, the automatic replacement function is stopped and a notification is given to an operator. When the automatic replacement function is stopped in this way, the effect of labor saving is reduced, which can be a factor in reducing productivity.

[0006] Therefore, an object of this specification is to provide a production management system that can achieve a significant labor-saving effect and contribute to improving productivity. [Means for solving the problem]

[0007] This specification discloses a production management system including a device pallet on which a plurality of component supply units that supply components to component suction positions of a component mounting machine that mounts components on a circuit board are arranged in a board transport direction and set; a supply pallet that stores a next component supply unit to replace a used component supply unit on the device pallet and collects the used component supply unit; a transport unit that attaches, detaches, and transports the component supply units between the device pallet and the supply pallet; and a transport control unit that controls the transport unit to remove the first component supply unit in which the abnormality has occurred from the device pallet, when an abnormality occurs in a first component supply unit set on the device pallet, and transport and set a second component supply unit that can replace the first component supply unit in which the abnormality has occurred and that is stored in the supply pallet, to the device pallet. Effect of the Invention

[0008] In the disclosed production management system, when an abnormality occurs in a component supply unit set on a device pallet, the transport control unit removes the component supply unit from the device pallet and controls the transport unit to set a replaceable second component supply unit on the device pallet. Therefore, when an abnormality occurs in a component supply unit, the production management system can automatically replace the component supply unit and continue production, resulting in a significant labor-saving effect and contributing to improved productivity. [Brief description of the drawings]

[0009] [Figure 1] 1 is a perspective view showing a configuration example of a production management system according to an embodiment and a substrate-related work line to which the system is applied; [Diagram 2] FIG. 2 is a block diagram showing a control configuration of a production management system. [Diagram 3] FIG. 11 is an operational flow diagram illustrating an outline of the operation of a component mounting machine in a substrate-related work line. [Figure 4] FIG. 11 is an operational flow diagram illustrating the operation of the production management system when an abnormality occurs in a tape feeder (component supply unit). [Diagram 5] 13A to 13C are diagrams illustrating the operation of removing and recovering a tape feeder in which an abnormality has occurred. [Figure 6] 6 is a diagram for explaining, following the operation in FIG. 5, the operation of transporting and setting a replaceable tape feeder. FIG. [Figure 7] 13A and 13B are diagrams illustrating the operation of transporting and setting a replaceable tape feeder before removing a tape feeder in which an abnormality has occurred. [Figure 8] 8 is a diagram for explaining, following the operation in FIG. 7, the operation of removing and recovering the tape feeder in which an abnormality has occurred. FIG. [Figure 9] 13A and 13B are diagrams illustrating an operation of removing a tape feeder in which an abnormality has occurred by transporting a replaceable tape feeder. [Figure 10]10 is a diagram illustrating an operation of setting a replaceable tape feeder and recovering a tape feeder in which an abnormality has occurred, following the operation of FIG. 9. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] 1. Configuration of substrate-to-substrate work line 9 First, the configuration of the substrate-related work line 9 to which the production management system 1 of the embodiment is applied will be described with reference to FIG. 1. As shown by the arrow in the upper left of FIG. 1, the front, rear, left and right of the substrate-related work line 9 are conveniently defined. The substrate-related work line 9 is configured with a plurality of substrate-related work machines lined up in the left-right direction. That is, a solder printer 91, a print inspection machine 92, a first component mounting machine 93, a second component mounting machine 94, a third component mounting machine 95, a substrate appearance inspection machine (not shown), and a reflow machine (not shown) are lined up from the left (upstream side) to the right (downstream side). The direction from the left to the right is the substrate transport direction.

[0011] Each of the substrate-related work machines performs a predetermined work on the circuit board, i.e., substrate-related work. More specifically, the solder printer 91 prints solder paste on the board in a specified pattern shape. The print inspector 92 captures and inspects the solder printing state on the circuit board. The first component mounter 93, the second component mounter 94, and the third component mounter 95 pick up components from the tape feeder 8 described later and mount them on the solder printed on the circuit board.

[0012] A board visual inspection machine takes images of components mounted on a circuit board and inspects their mounting condition. A reflow machine heats and cools the solder to ensure that the components are soldered properly. Board-related work is not limited to the above-mentioned tasks, but also includes various associated tasks. For example, board-related work includes the loading and unloading and positioning of circuit boards, and the confirmation work of taking images of circuit boards and components to confirm their position and orientation.

[0013] The first component mounting machine 93, the second component mounting machine 94, and the third component mounting machine 95 have the same structure. The component mounting machines (93, 94, 95) are configured by assembling on a base 99 a device pallet 9A, an in-machine replenishment pallet 9B, a board transport device not visible in FIG. 1, a component transfer device, and a control device 96 (see FIG. 2).

[0014] The device pallet 9A is disposed at approximately the middle height on the front side of the base 99. The device pallet 9A operates as a component supplying device. The device pallet 9A has a plurality of slots extending in the front-rear direction and formed at a predetermined pitch in the left-right direction (board conveying direction). A tape feeder 8 is inserted from the front side into each slot and set. Each slot corresponds to a plurality of arrangement positions where each of the plurality of tape feeders 8 is set.

[0015] Tape feeder 8 supplies components using a carrier tape that stores a plurality of components. Tape feeder 8 supplies components by pulling out a carrier tape from a built-in reel and sending it to a component suction position set in component mounting machines (93, 94, 95). Tape feeder 8 is one form of a component supply unit. Tape feeder 8 can be used interchangeably with first component mounting machine 93, second component mounting machine 94, and third component mounting machine 95. Furthermore, a mixture of multiple types of tape feeders 8 having different width dimensions in the left-right direction or internal structures may be permitted.

[0016] The in-machine replenishment pallet 9B is disposed below the device pallet 9A on the front side of the base 99. Like the device pallet 9A, the in-machine replenishment pallet 9B has a plurality of slots extending in the front-rear direction and formed at a predetermined pitch in the left-right direction. The in-machine replenishment pallet 9B stores used tape feeders 8 and the next tape feeder 8 to be used in place of a used tape feeder 8 in each slot. The number of slots of the in-machine replenishment pallet 9B is the same as that of the device pallet 9A, but may be different.

[0017] A "used tape feeder 8" refers to a tape feeder that has been set on the device pallet 9A and has been used up to the end of the carrier tape. A "next tape feeder 8" refers to a tape feeder that is used next when a tape feeder 8 currently in use that is set on the device pallet 9A has been used up. Therefore, if an abnormality occurs with the tape feeder 8 currently in use, the "next tape feeder 8" can be used as a substitute (a replaceable item). The "next tape feeder 8" is replenished by the operator as appropriate according to the progress of the mounting work of the component mounting machine (93, 94, 95).

[0018] A replaceable item is not limited to the "next tape feeder 8." For example, even a tape feeder 8 prepared for a changeover when changing the type of circuit board is a replaceable item if it supplies the same type of parts as the tape feeder 8 in use. Similarly, even a tape feeder 8 that is temporarily placed on in-machine supply pallet 9B and has no specified use is a replaceable item if it supplies the same type of parts as the tape feeder 8 in use.

[0019] The board transport device carries in, positions, and carries out the circuit board. The component transfer device uses a suction nozzle to pick up components from the tape feeder 8 on the device pallet 9A and mounts the components on the solder printed on the circuit board. The control device 96 controls the tape feeder 8, the board transport device, and the component transfer device based on operation data described below, and proceeds with the component mounting work. The control device 96 is configured using a computer device, or is configured by communication-connecting multiple computer devices distributed in the component mounting machine (93, 94, 95).

[0020] A line management device 97 is provided on the substrate-related operation line 9. The line management device 97 is disposed adjacent to the left side of the separately mounted replenishment pallet device 7, which will be described later. The line management device 97 is connected to communicate with a plurality of substrate-related operation machines. The line management device 97 manages operation data describing the operation content of substrate-related operations that differ for each type of circuit board. The line management device 97 sends each operation data to the plurality of substrate-related operation machines based on a production plan for circuit boards. The line management device 97 also monitors the operating status of the plurality of substrate-related operation machines.

[0021] 2. Configuration of the Production Management System 1 of the Embodiment Next, the configuration of the production management system 1 according to the embodiment will be described with reference to Figures 1 and 2. The production management system 1 is composed of a device pallet 9A and an in-machine replenishment pallet 9B in the component mounting machine (93, 94, 95), as well as a separate replenishment pallet device 7, a conveying unit 3, and a conveying control unit 4.

[0022] The separate supply pallet device 7 is provided adjacent to the left side of the solder printing machine 91, separately from the component mounting machines (93, 94, 95). The separate supply pallet device 7 is disposed at the same height as the device pallet 9A of the component mounting machines (93, 94, 95). Like the device pallet 9A, the separate supply pallet device 7 has a plurality of slots that extend in the front-rear direction and are formed at a predetermined pitch in the left-right direction. The separate supply pallet device 7 stores the above-mentioned "used tape feeder 8", "next tape feeder 8", etc. in each of its slots.

[0023] The number of slots in the separate supply pallet device 7 is the same as that of the device pallet 9A and the in-machine supply pallet 9B. However, the separate supply pallet device 7 is provided in common for the three component mounting machines (93, 94, 95). Therefore, the tape feeders 8 to be stored in the separate supply pallet device 7 and the reels (types of components) to be built into the tape feeders 8 are appropriately determined, taking into consideration the different mounting numbers (consumption speeds of components) for each type of component assigned to the component mounting machines (93, 94, 95). For example, tape feeders 8 that supply components with a high consumption rate are preferentially stored in the separate supply pallet device 7.

[0024] The transport unit 3 attaches / detaches and transports the tape feeders 8 between the device pallet 9A, the in-machine replenishment pallet 9B, and the separate replenishment pallet device 7. The transport unit 3 is formed in a vertically long box shape with an open rear side. The transport unit 3 is provided so as to be movable in the left-right direction along a track provided in front of the three component mounting machines (93, 94, 95) and the separate replenishment pallet device 7.

[0025] The middle rails 21 and the lower rails 22, which correspond to the track section, are provided in front of the bases 99 of the multiple substrate-related operating machines and in front of the separate replenishment pallet device 7, respectively. The middle rails 21 and the lower rails 22 extend in the left-right direction. The height position of the middle rail 21 is unified to the midpoint between the device pallet 9A and the in-machine replenishment pallet 9B. The height position of the lower rail 22 is unified to the height of the bottom of the in-machine replenishment pallet 9B. As a result, the multiple middle rails 21 and the multiple lower rails 22 form two parallel track sections that continue from the separate replenishment pallet device 7 to the third component mounting machine 95.

[0026] Meanwhile, the transport unit 3 has a middle stage running part 23 and a lower stage running part 24 on its rear side. The middle stage running part 23 is engaged with the middle stage rail 21 so as to be able to run. The lower stage running part 24 is engaged with the lower stage rail 22 so as to be able to run. The middle stage running part 23 further includes a drive source that generates power for running, for example a motor that drives the running wheels. As a result, the transport unit 3 is mounted on the middle stage rail 21 and the lower stage rail 22, and moves by running in the left-right direction.

[0027] Furthermore, the transport section 3 includes a non-contact power receiving section 25 at a height position between the middle run section 23 and the lower run section 24, at a height position that does not impede the attachment and detachment of the tape feeder 8. The non-contact power receiving section 25 receives power in a non-contact manner from non-contact power transmitting sections (not shown) provided at the corresponding heights of the multiple substrate-related operation machines. This covers the power consumption within the transport section 3.

[0028] The transport unit 3 has a lifting drive unit 26 and an exchange unit 27 inside the box shape. The lifting drive unit 26 drives the exchange unit 27 to lift from the height of the device pallet 9A to the height of the in-machine replenishment pallet 9B. An example of the lifting drive unit 26 is a ball screw feed mechanism, but is not limited thereto.

[0029] The replacement unit 27 has an internal space that accommodates one or more tape feeders 8. The replacement unit 27 also has a feeder attachment / detachment mechanism (not shown). The feeder attachment / detachment mechanism drives the tape feeder 8 accommodated in the internal space backward to set or store it on the pallet. The feeder attachment / detachment mechanism drives the tape feeder 8 set or stored on the pallet forward to remove the tape feeder 8 from the pallet and store it in the internal space. The above-mentioned pallet means the device pallet 9A, the in-machine replenishment pallet 9B, and the separate replenishment pallet device 7. The applicant of the present application has disclosed a detailed configuration example of the replacement unit 27 in International Publication No. 2019 / 239475.

[0030] The transport control unit 4 controls the transport unit 3. The transport control unit 4 is configured using a computer device. The location where the transport control unit 4 is provided is not particularly limited.

[0031] The above-mentioned next tape feeder 8 is prepared in advance by the operator, and is further stored by the operator in the in-machine replenishment pallet 9B or the separate replenishment pallet device 7. The conveying section 3 can convey the next tape feeder 8 stored in the separate replenishment pallet device 7 to the in-machine replenishment pallet 9B.

[0032] When a used tape feeder 8 occurs on the device pallet 9A, the transport unit 3 performs a replacement operation under control of the transport control unit 4. That is, the transport unit 3 removes the used tape feeder 8 from the device pallet 9A, and transports and sets the next tape feeder 8 to the device pallet 9A. In response to the next tape feeder 8 being provided for use, the operator repeats the work of preparing the next tape feeder 8.

[0033] 3. Control configuration of production management system 1 Next, the control configuration of the production management system 1 will be described in relation to the substrate-related work line 9 with reference to Fig. 2. Note that Fig. 2 illustrates only one feeder control unit 81 provided in each of the multiple tape feeders 8. In each component mounting machine (93, 94, 95), when a tape feeder 8 is set on the device pallet 9A, the feeder control unit 81 of that tape feeder 8 is automatically connected for communication with the control device 96. This allows the control device 96 to identify the individual tape feeders 8 lined up on the device pallet 9A and the type of components supplied by each tape feeder 8.

[0034] Furthermore, the control device 96 individually commands each feeder control unit 81 of the multiple tape feeders 8 to perform a component supply operation. The feeder control unit 81 that receives the command controls the feeding of the carrier tape and executes a component supply operation at the component suction position. When the carrier tape has been fed to its end and used, the corresponding feeder control unit 81 becomes used. The feeder control unit 81 transmits a signal to the control device 96 that the carrier tape has been fed to its end. Therefore, the control device 96 can recognize within a short period of time that a used tape feeder 8 has occurred.

[0035] Furthermore, at least some of the tape feeders 8 have a self-monitoring function that monitors their own operating conditions to detect abnormalities, and an automatic recovery function that attempts to resolve an abnormality when an abnormality occurs within the tape feeders 8. Most of the self-monitoring and automatic recovery functions are configured using a combination of software in the feeder control unit 81 and sensors (not shown). There are two types of abnormalities: those that can be automatically recovered from, and those that cannot be automatically recovered from and require action by an operator. In the latter case, automatically replacing the tape feeder 8 shortens the response time and is more productive than notifying an operator and waiting for action.

[0036] An example of an abnormality that may be automatically restored is an abnormality in which the number of tape feeders 8 that operate simultaneously is limited due to power supply capacity restrictions. In this case, the tape feeders 8 that were forcibly stopped due to the restriction can be restored to a normal state by operating them later. Abnormalities that cannot be automatically restored are diverse, including mechanical operation abnormalities, sensor failures, and software control abnormalities.

[0037] The feeder control unit 81 transmits the details of the detected abnormality to the control device 96. The determination of whether or not to execute an automatic return operation based on the automatic return function may be made autonomously by the feeder control unit 81, or the control device 96 may make the determination and issue a command to the feeder control unit 81. The feeder control unit 81 transmits the result of success or failure when the automatic return operation is executed to the control device 96. Therefore, the control device 96 can recognize a tape feeder 8 in which an abnormality that cannot be automatically returned to has occurred. Note that in addition to the feeder control unit 81 detecting an abnormality through self-monitoring, the higher-level control device 96 may also detect an abnormality in the tape feeder 8.

[0038] When a tape feeder 8 is stored on the in-machine replenishment pallet 9B, the feeder control section 81 and the control device 96 are automatically connected for communication, just as when the tape feeder 8 is set on the device pallet 9A. This enables the control device 96 to identify the individual tape feeders 8 lined up on the in-machine replenishment pallet 9B and the type of parts supplied by each tape feeder 8.

[0039] Each control device 96 of the component mounting machines (93, 94, 95) is communicatively connected to the transport control unit 4 via a line management device 97. This allows the control device 96 to transmit to the transport control unit 4 information identifying the individual tape feeders 8 that have been used and tape feeders 8 in which an abnormality has occurred, in association with information on their slots (arrangement positions).

[0040] The transport control unit 4 is communicatively connected to the separately-mounted replenishment pallet device 7 in addition to the line management device 97. When a tape feeder 8 is stored in the separately-mounted replenishment pallet device 7, the feeder control unit 81 of that tape feeder 8 is automatically communicatively connected to the transport control unit 4. This enables the transport control unit 4 to identify the individual tape feeders 8 lined up in the separately-mounted replenishment pallet device 7 and the type of parts supplied by each tape feeder 8.

[0041] The conveyance control unit 4 also transmits commands to the conveyance unit 3 to control its operation. The commands from the conveyance control unit 4 are transmitted, for example, by wireless communication, but are not limited thereto. The conveyance control unit 4 controls the replacement operation of the conveyance unit 3 when the tape feeder 8 set on the device pallet 9A has been used. In detail, the conveyance control unit 4 controls the conveyance unit 3 to remove the tape feeder 8 from the device pallet 9A and to collect it on the in-machine replenishment pallet 9B or the separate replenishment pallet device 7. Furthermore, the conveyance control unit 4 controls the conveyance unit 3 to take out the next tape feeder 8 from the in-machine replenishment pallet 9B or the separate replenishment pallet device 7, and transport it to the device pallet 9A and set it there.

[0042] Furthermore, the conveyance control unit 4 controls the recovery operation of the conveyance unit 3 when an abnormality occurs in the tape feeder 8 set on the device pallet 9A. In detail, the conveyance control unit 4 controls the conveyance unit 3 to remove the tape feeder 8 in which the abnormality has occurred from the device pallet 9A and to recover it on the in-machine replenishment pallet 9B or the separate replenishment pallet device 7. Furthermore, the conveyance control unit 4 controls the conveyance unit 3 to remove a tape feeder 8 that can replace the tape feeder 8 in which the abnormality has occurred from the in-machine replenishment pallet 9B or the separate replenishment pallet device 7 and to convey it to the device pallet 9A and attach it there.

[0043] The control method of the transport control unit 4 will be specifically described in the explanation of the operation later. Note that there may be cases where the next tape feeder 8 is not yet prepared for the replacement operation, or where there is no alternative tape feeder 8 for the recovery operation. In such cases, the transport control unit 4 notifies the operator of this and waits for a response.

[0044] 4. Operation of component placement machines (93, 94, 95) Prior to describing the operation of the production management system 1, an overview of the operation of the component mounting machines (93, 94, 95) will be described with reference to FIG. 3. The operation flow shown in FIG. 3 is mainly controlled by the control device 96. In step S1 of FIG. 3, the component mounting machines (93, 94, 95) start the operation of mounting components. The following steps S2 and S4 are executed at each predetermined control cycle time or at each interval of the mounting operation. Alternatively, steps S2 and S4 may be executed by interrupt processing.

[0045] In step S2, the control device 96 determines whether or not a used tape feeder 8 has occurred. If a used tape feeder 8 has occurred, the control device 96 branches the execution of the operation flow to step S3, and if a used tape feeder 8 has not occurred, the control device 96 advances the execution of the operation flow to step S4. In step S3, the control device 96 requests the transport control unit 4 to replace the tape feeder 8. When making the request, the control device 96 associates information identifying the individual used tape feeder 8 with information on its slot and transmits the information to the transport control unit 4. The transport control unit 4 that has accepted the request controls the replacement operation of the transport unit 3 based on the received information. After this, the execution of the operation flow is merged with step S4.

[0046] In step S4, the control device 96 determines whether or not there is a tape feeder 8 in which an abnormality has occurred. If not, execution of the operation flow is returned to step S1, and the installation work continues. If there is, in step S5, the tape feeder 8 in which an abnormality has occurred attempts an automatic return operation. In the next step S6, the control device 96 determines whether or not the tape feeder 8 in question has returned to a normal state. If it has returned, execution of the operation flow is returned to step S1, and if it has not returned, execution of the operation flow proceeds to step S7. Note that if an abnormality that does not allow automatic return occurs and an automatic return operation is not attempted, and if an abnormality occurs in a tape feeder 8 that does not have an automatic return function, execution of the operation flow proceeds unconditionally immediately from step S4 to step S7.

[0047] In step S7, the control device 96 requests the transport control unit 4 to perform recovery operation for the tape feeder 8. When making the request, the control device 96 transmits information identifying the individual tape feeder 8 in which the abnormality occurred and information about the slot in association with each other to the transport control unit 4. Upon receiving the request, the transport control unit 4 controls the recovery operation of the transport unit 3 based on the received information. After this, execution of the operation flow is returned to step S1.

[0048] As described above, even if an abnormality occurs in tape feeder 8 and the component mounting machines (93, 94, 95) temporarily suspend production, tape feeder 8 is automatically replaced by the recovery operation of production management system 1. Therefore, the component mounting machines (93, 94, 95) can automatically resume production.

[0049] 5. Operation of Production Control System 1 Next, the recovery operation of the production management system 1 when an abnormality occurs in the tape feeder 8 will be described with reference to the operation flow in Fig. 4 and the schematic diagrams in Figs. 5 and 6. The operation flow shown in Fig. 4 describes the details of the recovery operation of step S7 in Fig. 3, and is mainly carried out under control of the conveyance control unit 4. Here, it is assumed that the replacement unit 27 of the conveyance unit 3 has an internal space for accommodating one tape feeder 8, in other words, that the conveyance unit 3 is configured to be capable of conveying one tape feeder 8. It is also assumed that tape feeder 8B that can replace tape feeder 8A in which an abnormality has occurred is stored in the separately-mounted supply pallet device 7.

[0050] In step S11 of Fig. 4, the transport control unit 4 receives a request for a recovery operation from the control device 96, and further acquires information for identifying the tape feeder 8A in which an abnormality has occurred on the device pallet 9A, and information on its slot SA. Next, the transport control unit 4 determines a replaceable tape feeder 8B stored in the separate supply pallet device 7 and its slot SB based on the acquired information. The transport control unit 4 also determines in advance an empty slot SC for collection. Fig. 5 illustrates the above-mentioned tape feeders (8A, 8B) and slots (SA, SB, SC).

[0051] In the next step S12, the transport control unit 4 controls the first half of the recovery operation of the transport unit 3. First, the transport unit 3 moves to a position directly opposite the slot SA of the device pallet 9A. Second, the transport unit 3 removes the tape feeder 8A in which an abnormality has occurred and stores it in the replacement unit 27 (see arrow M1 in FIG. 5). Third, the transport unit 3 moves to a position directly opposite the vacant slot SC of the separate replenishment pallet device 7 while transporting the tape feeder 8A (see dashed arrow M2). Fourth, the transport unit 3 stores and recovers the tape feeder 8A in the slot SC (see dashed arrow M3).

[0052] In the next step S13, the transport control unit 4 controls the latter half of the recovery operation of the transport unit 3. First, the transport unit 3 moves to a position directly opposite the slot SB of the separate replenishment pallet device 7. Second, the transport unit 3 takes out the next tape feeder 8B and stores it in the replacement unit 27 (see arrow M4 in FIG. 5). Third, the transport unit 3 moves to a position directly opposite the slot SA of the device pallet 9A while transporting the tape feeder 8B (see dashed arrow M5). Fourth, the transport unit 3 sets the tape feeder 8B in the slot SA (see dashed arrow M6). This essentially ends the recovery operation.

[0053] In the next step S14, the transport control unit 4 notifies the control device 96 that the recovery operation has ended. This allows the control device 96 to return to step S1 in Fig. 3 and resume the mounting operation using the replaceable tape feeder 8B. Note that step S14 may be omitted, and the control device 96 may automatically identify that the replaceable tape feeder 8B has been set in the slot SA, and resume the mounting operation.

[0054] Also, replaceable tape feeder 8B may be stored in in-machine replenishment pallet 9B. In this case, the movement distance of conveying unit 3 in the left-right direction is small, and lifting and lowering operation of replacement unit 27 by lifting and lowering drive unit 26 is essential. Even so, conveying unit 3 can perform an operation equivalent to the recovery operation exemplified in Figures 5 and 6. Also, the replacement operation performed in step S3 in Figure 3 is the same as the recovery operation, except for the difference in whether or not the carrier tape in tape feeder 8 has been used up to its end.

[0055] In the production management system 1 of the embodiment, when an abnormality occurs in the tape feeder 8A set on the device pallet 9A, the conveyance control unit 4 removes the tape feeder 8A from the device pallet 9A and controls the conveyance unit 3 to set a replaceable second tape feeder 8B on the device pallet 9A. Therefore, when an abnormality occurs in the tape feeder 8A, the production management system 1 can automatically replace the tape feeder 8A and continue production of the component mounting machine (93, 94, 95). As a result, a significant labor-saving effect can be obtained and it can contribute to improving productivity.

[0056] 6. Application forms Next, an application in which the operation of the transport unit 3 is different from that of the embodiment will be described with reference to Figs. 7 and 8. In the application, the configurations of the substrate-related work line 9 and the production management system 1 are the same as those of the embodiment. In the application, the transport unit 3 performs a recovery operation that prioritizes the setting of an alternative tape feeder 8B over the removal of an abnormal tape feeder 8A.

[0057] At the start of the recovery operation in the applied form, the transport control unit 4 accepts a request for the recovery operation from the control device 96, and further acquires information for identifying the individual tape feeder 8A in which an abnormality has occurred on the device pallet 9A, information on its slot SA, and information on a slot SD that is already empty on the device pallet 9A. The slot SD is a second arrangement position different from the slot SA from which the tape feeder 8A is removed. Next, the transport control unit 4 determines a replaceable tape feeder 8B stored in the separate supply pallet device 7 and its slot SB based on the acquired information. In addition, the transport control unit 4 predetermines an empty slot SC for collection. FIG. 7 illustrates the above-mentioned tape feeders (8A, 8B) and slots (SA, SB, SC, SD).

[0058] The conveyance control unit 4 controls the conveyance unit 3 to set the next tape feeder 8B in the first half of the recovery operation. The conveyance unit 3 first moves to a position directly opposite the slot SB of the separate supply pallet device 7. The conveyance unit 3 then takes out the replaceable tape feeder 8B and stores it in the replacement unit 27 (see arrow N1 in FIG. 7). The conveyance unit 3 then moves to a position directly opposite the empty slot SD of the device pallet 9A, conveying the tape feeder 8B (see dashed arrow N2). The conveyance unit 3 then sets the tape feeder 8B in the slot SD (see dashed arrow N3). This allows the control device 96 to resume control of the mounting operation, and the component mounting machines (93, 94, 95) to resume production.

[0059] Next, the conveyance control unit 4 controls the conveyance unit 3 to recover the tape feeder 8A in which an abnormality has occurred during the latter half of the recovery operation. The conveyance unit 3 first moves to a position directly opposite the slot SA of the device pallet 9A. The conveyance unit 3 secondly removes the tape feeder 8A in which an abnormality has occurred and stores it in the replacement unit 27 (see arrow N4 in FIG. 8). The conveyance unit 3 thirdly conveys the tape feeder 8A while moving to a position directly opposite the vacant slot SC of the separate supply pallet device 7 (see dashed arrow N5). The conveyance unit 3 fourthly stores and recovers the tape feeder 8A in the slot SC (see dashed arrow N6). This essentially ends the recovery operation.

[0060] In the applied form, as in the embodiment, the tape feeder 8A in which an abnormality has occurred can be automatically replaced, and the component mounting machines (93, 94, 95) can continue production. As a result, a significant labor-saving effect can be obtained and it can contribute to improving productivity. Furthermore, by giving priority to setting the replaceable tape feeder 8B, it is possible to hasten the time when the component mounting machines (93, 94, 95) can resume production, compared to the embodiment. However, after the recovery operation, the control device 96 needs to use the slot SD in which the tape feeder 8B is set instead of the slot SA (by changing the component suction position) to control the mounting operation.

[0061] 7. Variations Next, a modified embodiment in which the configuration and operation of the conveying unit 3 are different from those of the embodiment will be described with reference to Figures 9 and 10. In the modified embodiment, the exchange unit 27 of the conveying unit 3 has an internal space that houses multiple tape feeders 8, in other words, the conveying unit 3 is configured to be able to convey multiple tape feeders 8.

[0062] At the start of the recovery operation in the modified embodiment, the transport control unit 4 receives a request for the recovery operation from the control device 96, and further acquires information for identifying the individual tape feeder 8A in which an abnormality has occurred on the device pallet 9A, and information on its slot SA. Next, the transport control unit 4 determines a replaceable tape feeder 8B stored in the separate supply pallet device 7, and its slot SB, based on the acquired information. In the modified embodiment, an empty slot SC for recovery is not required. FIG. 9 illustrates the above-mentioned tape feeders (8A, 8B) and slots (SA, SB).

[0063] The conveyance control unit 4 controls the conveyance unit 3 to accommodate the two tape feeders (8A, 8B) in the first half of the recovery operation. The conveyance unit 3 first moves to a position directly opposite the slot SB of the separate replenishment pallet device 7. The conveyance unit 3 then takes out the replaceable tape feeder 8B and accommodates it in the replacement unit 27 (see arrow P1 in FIG. 9). The conveyance unit 3 then moves to a position directly opposite the slot SA of the device pallet 9A (see dashed arrow P2). The conveyance unit 3 then removes the tape feeder 8A in which an abnormality has occurred and accommodates it in the replacement unit 27 (see dashed arrow P3). The replacement unit 27 of the conveyance unit 3 is now in a state in which it accommodates the two tape feeders (8A, 8B) (see FIG. 10).

[0064] Next, the conveyance control unit 4 controls the conveyance unit 3 to set or store the two tape feeders (8A, 8B) in the latter half of the recovery operation. The conveyance unit 3 first moves to a position where the slot SA of the device pallet 9A and the stored tape feeder 8B face each other. The conveyance unit 3 secondly sets the tape feeder 8B in the slot SA (see arrow P4 in FIG. 10). The conveyance unit 3 thirdly moves to a position where the slot SB of the separate supply pallet device 7 and the stored tape feeder 8A face each other (see dashed arrow P5). The conveyance unit 3 fourthly stores and recovers the tape feeder 8A in the slot SB (see dashed arrow P6). This essentially ends the recovery operation.

[0065] In the modified embodiment, as in the embodiment, the tape feeder 8A in which an abnormality has occurred can be automatically replaced, and the component mounting machine (93, 94, 95) can continue production. As a result, a significant labor-saving effect can be obtained and productivity can be improved. Furthermore, by moving the replaceable tape feeder 8B to the device pallet 9A while conveying it, the component mounting machine (93, 94, 95) can resume production earlier than in the embodiment. In addition, both the device pallet 9A and the separate supply pallet device 7 do not need vacant slots.

[0066] 8. Applications and Modifications of the Embodiments It is possible to omit one of the in-machine replenishment pallet 9B and the separate replenishment pallet device 7, and to simplify the configuration of the transport section 3. For example, if the in-machine replenishment pallet 9B is omitted and a replaceable tape feeder 8B is stored in the separate replenishment pallet device 7, the lifting and lowering drive section 26 of the transport section 3 becomes unnecessary. Also, when an abnormality occurs in the tape feeder 8A in the device pallet 9A of the first component mounting machine 93, it is possible to procure a replaceable tape feeder 8B from the in-machine replenishment pallet 9B of the second component mounting machine 94. The embodiment can be applied and modified in various other ways. [Explanation of symbols]

[0067] 1: Production management system 26: Lifting drive unit 27: Exchange unit 3: Transport unit 4: Transport control unit 7: Separate supply pallet device 8, 8A, 8B: Tape feeder 81: Feeder control unit 9: Substrate work line 93: First component placement machine 94: Second component placement machine 95: Third component placement machine 96: Control unit 97: Line management device 9A: Device pallet 9B: In-machine supply pallet SA, SB, SC, SD: Slots

Claims

1. a device pallet for arranging a plurality of component supply units in a board transport direction and supplying the components to component suction positions of a component mounting device that mounts components on a circuit board; a supply pallet for storing a next component supply unit to replace a used component supply unit on the device pallet and for recovering the used component supply unit; a transport unit that transports and attaches the component supply unit between the device pallet and the supply pallet; a transport control unit that controls the transport unit to perform a recovery operation in which, when an abnormality occurs in a first component supply unit set on the device pallet, the first component supply unit in which the abnormality occurs is removed from the device pallet, and a second component supply unit that can replace the first component supply unit in which the abnormality occurs and is stored in the supply pallet is transported to the device pallet and set thereon; Equipped with The component supply unit has an automatic recovery function for attempting to eliminate the abnormality, The transport control unit is When the abnormality occurs and there is a possibility of automatic recovery, the necessity of the recovery operation is determined depending on whether the automatic recovery operation of the first component supply unit is successful or not; When an abnormality occurs that cannot be automatically restored, the recovery operation is immediately performed. Production management system.

2. the device pallet has a plurality of arrangement positions for holding a respective one of the first component supply units; the transport control unit controls the transport unit to set the second component supply unit in the arrangement position that has become vacant after the first component supply unit has been removed. The production management system according to claim 1.

3. the device pallet has a plurality of arrangement positions for holding a respective one of the first component supply units; the transport control unit controls the transport unit to set the second component supply unit at a second arrangement position that is different from the first arrangement position from which the first component supply unit is removed and that is vacant in advance. The production management system according to claim 1 or 2.

4. 4. The production management system according to claim 1, wherein the supply pallet is provided in common for a plurality of the component mounting machines and is provided separately from the component mounting machines.

5. The abnormality from which automatic recovery is possible is a case in which recovery is possible by operating the part supply unit that has been forcibly stopped due to a restriction on the number of the part supply units that can be operated simultaneously due to a power supply capacity restriction. The production management system according to any one of claims 1 to 4.

Citation Information

Patent Citations

  • Component mounting method and component mounting device

    JP2017045791A

  • Cassette feeder replacement system of component mounting machine

    JP2020010069A

  • Component packaging system

    JP2021016009A

  • Component mounting line production management system and production management method

    WO2018087854A1

  • Mounting system, mobile work device, and mobile work management method

    WO2020039543A1