Ground reinforcement method

By using a smaller diameter long steel pipe with temperature sensors to monitor urethane injection material penetration, the method addresses incomplete filling in ground reinforcement, ensuring safe tunnel excavation by identifying and reinforcing unimproved areas.

JP7578978B2Active Publication Date: 2024-11-07CATEX CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2021064948
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-04-06
Publication Date
2024-11-07
Estimated Expiration
2041-04-06

AI Technical Summary

Technical Problem

Existing ground reinforcement methods using long steel pipes and urethane injection materials fail to adequately fill areas with cracks and voids, leading to unimproved regions and potential ground collapse during tunnel excavation.

Method used

Install a smaller diameter long steel pipe adjacent to the main pipe with temperature sensors to monitor the injection material's penetration, using the heat generated by the curing reaction to identify unimproved areas and perform supplementary injections.

Benefits of technology

Accurately determines improved and unimproved ground areas, preventing ground collapse by ensuring complete reinforcement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007578978000001
    Figure 0007578978000001
  • Figure 0007578978000002
    Figure 0007578978000002
  • Figure 0007578978000003
    Figure 0007578978000003
Patent Text Reader

Abstract

To obviate natural ground collapse in tunnel excavation and secure tunnel excavation safety by simply and surly getting hold of filling state of an injection material injected into an unexcavated natural ground of the tunnel in preceding natural ground reinforcement work and by reinforcing an unimproved area.SOLUTION: The natural ground reinforcement method includes placing a long steel pipe 3 for detection adjacent to a placed long steel pipe 1 before injection of a urethane injection material 10 into the natural ground, providing temperature sensors 5a to 5c inside the long steel pipe for detection, getting hold of an improved area in the natural ground by measuring temperature with the temperature sensors after the urethane injection material is injected from the long steel pipe to the natural ground, and conducting supplemental injection to the place judged that it is an unimproved area through the long steel pipe for detection.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to preliminary ground reinforcement work during tunnel excavation. [Background technology]

[0002] When excavating a tunnel, a method known as long steel pipe forepiling is known in which long steel pipes are cast into the ground surrounding the tunnel in front of it and ground improvement material is injected from within the long steel pipes to improve the ground. For example, in the construction method shown in Patent Document 1, as shown in Fig. 9, multiple long steel pipes 1 of about 10 to 20 m are installed around the periphery of a tunnel by connecting multiple steel pipes of about 3 m, and after the installation of the long steel pipes 1, a ground improvement material 10 is injected into each long steel pipe 1. The ground improvement material 10 injected into the long steel pipe 1 penetrates into gaps and cracks in the ground around the long steel pipe 1 through multiple discharge holes provided on the periphery of the long steel pipe 1 and hardens, thereby reinforcing the ground. As this ground improvement material 10, a urethane injection material is widely used in terms of its improvement effect and ease of workability. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Japanese Patent Application Publication No. 08-121073 Summary of the Invention [Problem to be solved by the invention]

[0004] However, the ground requiring such preliminary ground reinforcement work is highly heterogeneous, and there may be areas with many cracks or large voids and cracks in the ground. In such a case, as shown in Fig. 10, even if a set amount of grouting material 10 is injected, the grouting material 10 may escape into voids and cracks outside the reinforcement range and may not be sufficiently injected into the specified reinforcement range, resulting in the formation of an unimproved area S in the ground around the long steel pipe 1. If such unimproved areas S are formed in large numbers in the longitudinal direction of the long steel pipe 1, collapses C from the unimproved areas S in the ground around the long steel pipe 1 may occur during tunnel excavation, which will have a significant impact on the safety of tunnel excavation.

[0005] The present invention has been made to solve the above problems, and has as its object to easily and reliably grasp the filling status of the injection material injected into the unexcavated ground of a tunnel during preliminary ground reinforcement work, and to reinforce the unimproved areas, thereby preventing the collapse of the ground during tunnel excavation and ensuring the safety of the tunnel excavation. [Means for solving the problem]

[0006] The present invention is as follows. 1. A method of reinforcing the ground by casting multiple long steel pipes into the unexcavated ground of a tunnel and injecting urethane injection material into cracks in the surrounding ground from discharge holes provided on the outer periphery of the long steel pipes through the inner space of the long steel pipes, This is a ground reinforcement method characterized by the fact that prior to injecting urethane injection material into the ground, a long detection steel pipe is cast adjacent to the long steel pipe that has already been cast, a temperature sensor is installed inside the long detection steel pipe, and after the urethane injection material is injected from the long steel pipe into the ground, the temperature is measured with the temperature sensor to identify improved areas in the ground, and supplementary injection is performed through the long detection steel pipe in any areas determined to be unimproved. 2. A ground reinforcement method as described in 1 above, characterized in that the long steel pipe for detection has a smaller diameter than the long steel pipe. 3. A ground reinforcement method as described in 1 or 2 above, characterized in that the long steel pipe for detection is driven in parallel to the long steel pipe. 4. A ground reinforcement method described in any one of 1 to 3 above, characterized in that the temperature sensors are installed in multiple locations along the longitudinal direction of the long steel pipe for detection. 5. A ground reinforcement method described in any one of 1 to 4 above, characterized in that the temperature sensor installed in the long detection steel pipe is retrieved after measuring the temperature, and the long detection steel pipe is left in the ground to be used for supplementary injection into the ground.

[0007] The present invention is characterized in that a long detection steel pipe is cast adjacent to a long steel pipe cast prior to the injection of polyurethane injection material into the ground, a temperature sensor is installed inside the long detection steel pipe, and after the polyurethane injection material is injected from the long steel pipe into the ground, the temperature is measured with the temperature sensor to identify improved areas in the ground, and supplementary injection is carried out through the long detection steel pipe in areas determined to be unimproved areas. According to this configuration, when the urethane grout is injected into the long steel pipe, the urethane grout flowing out from the discharge hole of the long steel pipe penetrates into the cracks in the ground around the long steel pipe and hardens. The urethane grout hardens in about one minute after injection, and the hardening reaction generates reaction heat of about 100°C, which is transmitted through the ground to a temperature sensor installed in the detection long steel pipe that is cast adjacent to the long steel pipe. By measuring the temperature with this temperature sensor, the penetration range of the urethane grout flowing out from the long steel pipe can be grasped, and the improved and unimproved areas of the ground can be recognized. Next, the unimproved areas recognized here can be improved by installing an injection material in the detection long steel pipe left in the ground after recovering the temperature sensor in the detection long steel pipe, and supplementing the unimproved areas with urethane grout.

[0008] In addition, by making the diameter of the long steel pipe for detection smaller than that of the long steel pipe for injection, the temperature sensor installed in the long steel pipe for detection can be reliably contacted with the inner wall of the long steel pipe for detection, and the temperature of the urethane injection material transmitted through the ground can be accurately measured. In addition, the small diameter of the long steel pipe for detection can shorten the pouring time, and the impact on the construction time of the preliminary ground reinforcement work can be suppressed.

[0009] In addition, by casting a long steel pipe for detection parallel to the long steel pipe, the filling status of the urethane injection material can be grasped more accurately.

[0010] Furthermore, by installing multiple temperature sensors along the longitudinal direction of the long steel detection pipe, the filling status of the urethane injection material can be grasped more accurately.

[0011] Furthermore, by configuring the temperature sensor installed inside the long steel detection pipe to be retrieved after measuring the temperature, it becomes possible to leave the long steel detection pipe in the ground and use it for supplementary injection into unimproved areas. Effect of the Invention

[0012] According to the present invention, by simply and reliably identifying improved and unimproved areas of the ground in preliminary ground reinforcement work and reinforcing the unimproved areas, it is possible to prevent the collapse of the ground during tunnel excavation. [Brief description of the drawings]

[0013] The present invention will be further described in the following detailed description by way of non-limiting examples of exemplary embodiments according to the invention and with reference to the several drawings mentioned, in which like reference numerals refer to like elements throughout the several views of the drawings. [Figure 1] 1A and 1B are explanatory diagrams for explaining the ground reinforcement method of the embodiment, in which (a) shows a state in which multiple long steel pipes have been cast into the ground in front of the tunnel, and (b) shows a state in which a long steel pipe for detection has been cast adjacent to the long steel pipes. [Diagram 2] 1A and 1B are explanatory diagrams for explaining the ground reinforcement method of the embodiment, where (a) shows the state in which a temperature sensor is installed inside a long steel pipe for detection, and (b) shows the state in which urethane injection material is injected from the long steel pipe into the ground. [Diagram 3] FIG. 4 is an explanatory diagram for explaining the temperature sensor. [Figure 4]3A and 3B are explanatory diagrams for explaining the display format of the temperature measured by the above-mentioned temperature sensors, where (a) shows a format in which the vertical axis is temperature and the horizontal axis is the position of each temperature sensor, and (b) shows a format in which the vertical axis is temperature and the horizontal axis is time. [Diagram 5] 1A and 1B are explanatory diagrams for explaining the ground reinforcement method of the embodiment, in which (a) shows the state in which injection materials are installed inside the long steel pipe for detection, and (b) shows the state in which capture injection is performed through the long steel pipe for detection. [Figure 6] FIG. 2 is an explanatory diagram for explaining the natural ground reinforcement method of the embodiment, showing the state in which capture injection has been carried out through a long steel pipe for detection. [Figure 7] FIG. 2 is an explanatory diagram for explaining the injection material. [Figure 8] FIG. 13 is an explanatory diagram for explaining a method for checking the filling status of natural ground in an embodiment. [Figure 9] FIG. 1 is an explanatory diagram for explaining a general ground reinforcement method, where (a) shows a cross-sectional view and (b) shows an enlarged longitudinal section. [Figure 10] FIG. 1 is an explanatory diagram for explaining a conventional natural ground reinforcement method, showing a state in which injection material has escaped into voids and cracks outside the reinforcement area. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] The matters shown herein are illustrative and are intended to exemplify the embodiments of the present invention, and are described for the purpose of providing what is believed to be the most effective and easily understandable explanation of the principles and conceptual features of the present invention. In this respect, it is not intended to show structural details of the present invention beyond the extent necessary for a fundamental understanding of the present invention, and the description in conjunction with the drawings will make it clear to those skilled in the art how some forms of the present invention can be actually embodied.

[0015] The present invention will now be described in detail with reference to the accompanying drawings.

[0016] In the natural ground reinforcement method of this embodiment, as shown in Fig. 1(a), prior to the excavation of the tunnel, a number of long steel pipes 1 are cast in the natural ground ahead of the tunnel periphery by a known method (see Fig. 9(a)). Each of these long steel pipes 1 is cast from within the tunnel cross section inside the support 2 laid immediately adjacent to the excavation point toward the natural ground ahead at an elevation angle of 8 to 10 degrees. Generally, the casting length is set to 12.5 m, and a predetermined length is cast by connecting steel pipes of about 3 m each. In addition, the letter "P" in the figure indicates the direction of tunnel excavation.

[0017] Next, as shown in Fig. 1(b), a long steel pipe for detection 3 is cast adjacent to the long steel pipe 1 by a known method. This long steel pipe for detection 3 is selected from some of the cast long steel pipes 1, and is cast parallel to the long steel pipe 1, preferably at the midpoint between the adjacent long steel pipes 1. Specifically, the long steel pipe for detection 3 is the same length as the long steel pipe 1, and cast at approximately the same height as the adjacent long steel pipe 1. Furthermore, the aperture of the long steel pipe for detection 3 is smaller than that of the long steel pipe 1, and from the viewpoint of workability, it is desirable that the diameter be 76.3 mm or less. It is not necessary to cast the detection long steel pipes 3 adjacent to all of the long steel pipes 1. Taking into consideration the ground conditions appearing at the tunnel cross section, the detection long steel pipes 3 will be cast in appropriate areas, such as areas where ground prone to collapse is distributed or at the boundary between ground layers.

[0018] Next, as shown in FIG. 2(a), a plurality of temperature sensors 5a, 5b, 5c (three in the figure) are installed along the longitudinal direction of the long steel pipe 3 for detection. Each of these temperature sensors 5a to 5c is attached to a core material 6 such as a PVC pipe. Furthermore, a cable 7 extending from each of the temperature sensors 5a to 5c is connected to a display unit 8 (see FIG. 3). This display unit 8 can display the temperature measured by each of the temperature sensors 5a to 5c. Furthermore, the temperature sensors 5a to 5c may be commercially available, but those using thermocouples or platinum resistance thermometers are preferable. Furthermore, it is preferable that the temperature sensors 5a to 5c contact the inner wall of the long steel pipe 3 for detection or face each other with a small gap therebetween.

[0019] After that, as shown in FIG. 2(b), a urethane injection material 10 is injected from the long steel pipe 1 by a known method. Specifically, an injection material such as a tube (not shown) is inserted into the long steel pipe 1, and the urethane injection material 10 is injected from an injection adapter attached to the end of the tube. The urethane injection material 10 injected into the long steel pipe 1 fills gaps and cracks in the natural ground from a discharge hole (not shown) provided on the outer periphery of the long steel pipe 1, and reinforces the natural ground by hardening. However, if the natural ground has an area with many cracks or an area with large gaps or cracks, even if a set amount of urethane injection material 10 is injected, the injection material 10 will escape into gaps and cracks outside the reinforcement area and will not be injected sufficiently into the specified reinforcement area, resulting in the formation of an unimproved area S in the natural ground around the long steel pipe 1.

[0020] The urethane injection material 10 hardens in about one minute after injection, and the hardening reaction generates reaction heat of about 100°C, which is transmitted through the natural ground to the temperature sensors 5a to 5c installed in the long steel pipe for detection 3 that is cast adjacent to the long steel pipe 1. Each of these temperature sensors 5a to 5c measures the transmitted temperature, and the measured temperature is displayed as a numerical value or a graph on the display unit 8 (see Figure 4). The penetration range of the urethane injection material 10 in the longitudinal direction of the natural ground can be grasped based on the difference in temperature between the temperature sensors 5a to 5c. In the example shown, the temperature at the intermediate position measured by the temperature sensor 5b does not rise, so it is determined that an unimproved area S (see Figure 2(b)) exists there.

[0021] Next, as shown in Fig. 5(a), the temperature sensors 5a-5c are removed from the long steel pipe for detection 3, and an injection material 11 is installed. This injection material 11 includes packers 12 that divide the inside of the long steel pipe for detection 3 in the longitudinal direction, and injection tubes 13 with open ends bound together between each packer 12 (see Fig. 7). The long steel pipe for detection 3 is provided with discharge holes (not shown) over its entire length for infiltrating the injection material 10' into the ground.

[0022] Next, as shown in Fig. 5(b), the grouting material 10' is captured and injected by a known method into the unimproved area S through the long steel pipe for detection 3. By reinforcing the unimproved area S in this way, it is possible to prevent the collapse of the ground during tunnel excavation (see Fig. 6). The injection material 10' may be the urethane injection material 10 or may be of a different type from the urethane injection material 10.

[0023] Here, a method for checking the filling status of the natural ground by the transfer of temperature will be described. As shown in FIG. 8, a temperature sensor 5 is installed in a simulated natural ground modeled on sandy soil, earth and sand, crushed rock, etc., and a heat source 15 is installed at a predetermined distance L from the temperature sensor 5. Since the reaction heat due to the hardening of the urethane injection material 10 is about 100°C, the temperature of the heat source 15 is set to 100°C, the distance L between the heat source 15 and the temperature sensor 5 is changed, and the temperature detected by the temperature sensor 5 at each distance L is measured. By storing the results in a database, in the above-mentioned natural ground reinforcement method, the distance between the temperature sensors 5a to 5c and the solidified body of the urethane injection material 10 in the natural ground, i.e., the natural ground improvement area, can be grasped from the temperature detected by the temperature sensors 5a to 5c installed in the long steel pipe 3 for detection, and the unimproved area S of the natural ground can be determined based on this distance. The determination of the unimproved area S of the natural ground may be made by a worker or by a control unit such as a computer.

[0024] It should be noted that the present invention is not limited to the examples, and various modifications can be made within the scope of the present invention according to the purpose and application. That is, in the above examples, the present invention is applied to long steel pipe forepiling that reinforces the front ground along the outer periphery of a tunnel, but the present invention is not limited to this, and for example, the present invention can also be applied to long mirror reinforcement work, side piles, and leg piles that use similar long steel pipes.

[0025] In addition, in the above embodiment, a long steel pipe 3 for detection having a smaller diameter than the long steel pipe 1 was used, but this is not limited to this, and for example, a long steel pipe 3 for detection having the same diameter as the long steel pipe 1 or a larger diameter than the long steel pipe 1 may be used.

[0026] In addition, in the above embodiment, an example was given of the long steel pipe 3 for detection being cast parallel to the long steel pipe 1, but this is not limited to this, and for example, the long steel pipe 3 for detection may be cast at a slight inclination (for example, an inclination of ±5 degrees) relative to the long steel pipe 1.

[0027] Furthermore, in the above embodiment, an example was given of a configuration in which multiple temperature sensors 5a to 5c are installed along the longitudinal direction within the long steel pipe for detection 3, but this is not limited to this, and for example, when the length of the long steel pipe for detection 3 is relatively short, a single temperature sensor may be installed within the long steel pipe for detection 3.

[0028] As a reference example, a ground reinforcement method is provided in which multiple long steel pipes are cast into the unexcavated ground of a tunnel, and urethane injection material is allowed to penetrate through the inner space of the long steel pipes and into cracks in the surrounding ground from discharge holes provided on the outer periphery of the long steel pipes to reinforce the ground, in which a detection hole is drilled adjacent to the cast long steel pipes prior to injecting the urethane injection material into the ground, a temperature sensor is installed in the detection hole, and after injecting the urethane injection material from the long steel pipes into the ground, the temperature is measured with the temperature sensor to identify improved areas in the ground, and supplementary injection is performed through the long steel pipes installed in the detection hole in areas determined to be unimproved areas. [Industrial Applicability]

[0029] The present invention is widely used as a technique relating to natural ground reinforcement methods. [Explanation of symbols]

[0030] 1; long steel pipe, 3; long steel pipe for detection, 5a-5c; temperature sensor, 10; urethane injection material, 11; injection material, S; unimproved area.

Claims

1. In this method, a plurality of long steel pipes are cast into the unexcavated ground of a tunnel, and a urethane injection material is injected into cracks in the surrounding ground from discharge holes provided on the outer periphery of the long steel pipes through the inner space of the long steel pipes to reinforce the ground. This is a ground reinforcement method characterized by the fact that prior to injecting urethane injection material into the ground, a long detection steel pipe is cast adjacent to the long steel pipe that has already been cast, a temperature sensor is installed inside the long detection steel pipe, and after the urethane injection material is injected from the long steel pipe into the ground, the temperature is measured with the temperature sensor to identify improved areas in the ground, and supplementary injection is performed through the long detection steel pipe in any areas determined to be unimproved.

2. 2. The ground reinforcement method according to claim 1, wherein the long steel pipe for detection has a smaller diameter than the long steel pipe.

3. 3. The ground reinforcement method according to claim 1, wherein the detection long steel pipe is driven in parallel to the long steel pipe.

4. 4. The natural ground reinforcement method according to claim 1, wherein a plurality of the temperature sensors are installed along the longitudinal direction of the long steel pipe for detection.

5. A ground reinforcement method as described in any one of claims 1 to 4, characterized in that the temperature sensor installed in the long steel pipe for detection is retrieved after measuring the temperature, and the long steel pipe for detection is left in the ground for use in supplementary injection into the ground.

Citation Information

Patent Citations

  • Measurement of improving range of ground in chemical grout injection work

    JP1986274013A

  • Prior reinforcement method by steel pipe, and device by use thereof

    JP1996121073A

  • Method of estimating permeation range of chemical for solidifying bedrock

    JP2003130830A

  • Thermometer and freezing method using it

    JP2004028935A

  • Hollow pipe body and tunnel construction method using the same

    JP2010248758A