Hydrogen storage and distribution apparatus and method
The on-site hydrogen generation system with a flow control manifold and removable trailers addresses inefficiencies in hydrogen fueling by storing excess hydrogen and adjusting production to match demand, ensuring continuous supply and reducing waste.
Patent Information
- Application Number
- JP2022172128
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2021-10-29
- Filing Date
- 2022-10-27
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2042-10-27
AI Technical Summary
Existing hydrogen fueling systems face challenges in adjusting production rates to match intermittent usage patterns at fueling stations, leading to inefficiencies such as excess hydrogen discharge, shutdowns, and insufficient supply during high demand.
An on-site hydrogen generation system with a flow control manifold and removable trailers that store excess hydrogen, allowing flexible hydrogen distribution and storage to meet varying demand levels, including the use of compressors to adjust pressure and trailers for transport.
The system ensures continuous hydrogen supply by storing excess hydrogen for later use, reducing waste and minimizing shutdowns, and efficiently meeting fluctuating demand through operational flexibility.
Smart Images

Figure 0007588627000001 
Figure 0007588627000002 
Figure 0007588627000003
Abstract
Description
[Technical field]
[0001] The present invention relates to an apparatus for on-site hydrogen fuel distribution and storage, and a method for on-site hydrogen fuel distribution and storage. [Background technology]
[0002] Examples of hydrogen generation and supply systems are described in U.S. Patent Nos. 6,401,767, 6,619,336, 6,708,573, 6,745,801, 6,786,245, 7,028,724, 7,328,726, 7,793,675, 7,921,883, 8,020,589, 8,286, Nos. 675, 8,365,777, 8,453,682, 8,899,278, 9,074,730, 9,151,448, 9,261,238, 9,279,541, 9,404,620, 9,863,583, 10,502,649, and 10,508,770.
[0003] Some hydrogen fueling systems are supplied from trailers filled with hydrogen that are brought to a fueling station. In many cases, hydrogen fueling stations may not be in use at all for many hours, if not most of the day. However, when in use, there can be a large demand for hydrogen at the fueling station. In many cases, abundant storage is provided for hydrogen fuel, and the station is able to meet the high demand when it is present. Summary of the Invention
[0004] Some hydrogen generation and supply systems can generate hydrogen on-site. For example, hydrogen can be produced from methane via reforming, or hydrogen can be produced from ammonia via cracking. Equipment that produces hydrogen on-site has generally been deemed to have limited ability to adjust production rates. As a result, such equipment generally may not respond well to frequent starts and stops that may result from intermittent demand for hydrogen fuel at a fueling station to supply hydrogen fuel directly to the station for use in distributing hydrogen fuel to vehicles or other devices.
[0005] It was determined that this limited ability to adjust production rates may not align well with the intermittent usage patterns of fueling stations, and that production systems that may be configured to directly supply fuel for on-site distribution to vehicles or other devices at fueling stations may need to store the hydrogen gas produced when not being distributed or to utilize the hydrogen for alternative uses when not being used for distribution to other devices (e.g., vehicles that may run on hydrogen fuel).
[0006] An on-site hydrogen generation system for providing fuel to a fuel supply system having one or more fuel dispensers, the on-site hydrogen generation system being designed and configured to provide hydrogen generated in production for fuel distribution and / or storage, may be provided. When hydrogen produced by the hydrogen generation system is greater than (or exceeds) the distribution demand for the fuel supply station, the system may be configured to avoid the need to vent the generated hydrogen to the atmosphere (thus wasting or wasting the hydrogen). This configuration may also help to avoid the need to shut down the hydrogen generation system when there is excess demand, which may then result in long delays in restarting the hydrogen generation process when hydrogen demand at the fuel supply station may increase unexpectedly. Preferably, embodiments are provided that allow the same connections used to dispose of excess hydrogen supply to also be used to supply backup hydrogen fuel when the on-site hydrogen generation system is offline or otherwise provides an insufficient hydrogen flow to meet the current hydrogen demand of the fuel supply station for distribution to vehicles or other devices. In some embodiments, the fuel supply system may be advantageously configured to facilitate both the inlet of hydrogen fuel to the fuel supply station and the outlet of hydrogen fuel to other customers located remotely from the fuel supply station via one or more trailers (e.g., tube trailers). For example, in some embodiments, excess production may be used to supply trailers that are transported via trucks and / or trains for transporting fuel to other customers, and / or to supply trailers for on-site storage for subsequent use at the fuel supply stations of the fuel supply system.
[0007] One or more available trailers can be removably connected to receive excess hydrogen from the compressor for storage during periods of low hydrogen demand and can provide stored hydrogen to a flow control manifold for distribution at one or more dispensers at the fueling station to meet high demand conditions at the fueling station. The removable trailers can be removed when full and replaced with another empty trailer for transport to another off-site station. The embodiments can also be configured to allow additional full trailers to be connected to replace and / or supplement at least one trailer already connected to provide additional hydrogen to meet high demand episodes at the fueling station. Removable and interchangeable trailers can provide operational flexibility and can allow for on-site generation of hydrogen to provide hydrogen to an on-site station while also allowing for the removal of excess hydrogen. The embodiments can also allow for the uptake of additional hydrogen by adding additional trailers or replacing empty trailers with full trailers to accommodate situations where hydrogen demand at the on-site fueling station is high or expected to be high.
[0008] A hydrogen fuel distribution and storage apparatus may be provided. An embodiment of the hydrogen fuel distribution and storage apparatus may include a first compressor disposed to receive hydrogen from a hydrogen generation system, and a flow control manifold (FCM) disposed downstream of the first compressor to receive hydrogen for supply to at least one dispenser. The apparatus may also include at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor may be supplied to the at least one first trailer for storage while a demand for hydrogen at the FCM for distribution at the at least one dispenser is less than a rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer may pass to the FCM while a demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than a rate at which hydrogen is supplied to the first compressor.
[0009] Some embodiments of the hydrogen fuel distribution and storage apparatus can include additional compressors. For example, some embodiments can include a second compressor disposed between the first compressor and the FCM to increase the pressure of the hydrogen output from the second compressor from a first pressure to a second pressure higher than the first pressure before the hydrogen is delivered to the FCM. The apparatus can also include other elements. For example, a first storage vessel can be provided between the first compressor and the second compressor to store the hydrogen output from the first compressor before the hydrogen is delivered to the second compressor. As another example, there can be a second storage vessel between the second compressor and the FCM to store the hydrogen output from the second compressor before the hydrogen is delivered to the FCM for distribution.
[0010] An embodiment of the hydrogen fuel distribution and storage apparatus may include only a single first trailer, or may include multiple first trailers. Some embodiments may also utilize one or more second trailers. For example, an embodiment may include at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor at a second pressure can be supplied to the at least one second trailer for storage while the demand for hydrogen at the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one second trailer can pass to the FCM while the demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. It should be understood that the at least one second trailer may be a single trailer or may be multiple trailers. In some embodiments, the first trailer and the second trailer may be tube trailers.
[0011] In some embodiments, the at least one second trailer can be arranged and configured to directly supply hydrogen stored in the at least one second trailer to the FCM while the demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. The at least one first trailer can be arranged and configured to directly supply hydrogen stored in the at least one first trailer to the FCM while the demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. In embodiments utilizing both one or more first trailers and one or more second trailers, both sets of trailers can be arranged and configured to directly supply hydrogen stored in the trailer to the FCM while the demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
[0012] The at least one first trailer can include at least one detachable tube trailer, or a plurality of detachable tube trailers. The at least one second trailer can include at least one detachable tube trailer, or a plurality of detachable tube trailers. Tube trailers, and other types of detachable trailers, can be transportable via trucks on roadways and / or trains on railroads. The detachable trailers can be exchanged for other trailers. For example, an empty trailer can be exchanged for a full trailer filled with hydrogen. As another example, to receive additional hydrogen, a full trailer filled with hydrogen can be removed and exchanged for an empty trailer. In some embodiments, additional trailers can also be utilized to provide additional hydrogen storage capacity.
[0013] Some embodiments of the hydrogen fuel distribution and storage apparatus may be configured as a hydrogen fuel generation, distribution, and storage apparatus that includes a hydrogen production system. The hydrogen production system included in such embodiments of the apparatus may, in some embodiments, include an ammonia cracker or a methane reformer having at least one reformer device. Other embodiments may utilize other types of hydrogen production systems.
[0014] A method of generating, storing, and / or distributing hydrogen is also provided. An embodiment of the method may include compressing hydrogen received from a hydrogen generation system to a first pressure and supplying hydrogen to a flow control manifold (FCM) for supply to at least one dispenser. In response to a demand for hydrogen at the FCM for distribution at the at least one dispenser being less than a rate at which hydrogen is supplied to the first compressor, at least a portion of the hydrogen output from the first compressor may be supplied to at least one first trailer disposed between the first compressor and the FCM such that the hydrogen output from the first compressor can be supplied to the at least one first trailer for storage. In response to a demand for hydrogen at the FCM for distribution at the at least one dispenser being greater than a rate at which hydrogen is supplied to the first compressor, hydrogen stored in the at least one first trailer may be supplied to the FCM for distribution at the at least one dispenser.
[0015] An embodiment of the method may include supplying hydrogen at a first pressure to a second compressor disposed between the first compressor and the FCM to increase the pressure of the hydrogen to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM. In response to a demand for hydrogen at the FCM for distribution at the at least one dispenser being less than the rate at which hydrogen is supplied to the first compressor, at least a portion of the hydrogen output from the second compressor may be supplied to at least one second trailer disposed between the second compressor and the FCM such that the hydrogen output from the first compressor can be supplied to the at least one second trailer for storage. In response to a demand for hydrogen at the FCM for distribution at the at least one dispenser being greater than the rate at which hydrogen is supplied to the first compressor, hydrogen stored in the at least one second trailer may be output to the FCM for distribution at the at least one dispenser.
[0016] In embodiments of the method, the at least one first trailer may be a single trailer or may be multiple trailers. In embodiments of the method that utilize at least one second trailer, the at least one second trailer may be a single trailer or multiple trailers. Each of the trailers may be a tube trailer, or other type of trailer suitable for storing hydrogen for transport along railroads or roadways.
[0017] For embodiments of the method, the at least one first trailer can include at least one removable tube trailer, or multiple removable tube trailers. The at least one second trailer can also include at least one removable tube trailer, or multiple removable tube trailers (when utilized). Tube trailers, and other types of removable trailers, can be transportable via trucks on roadways and / or trains on railroads. Removable trailers can be exchanged for other trailers. For example, an empty trailer can be exchanged for a full trailer filled with hydrogen. As another example, to receive additional hydrogen, a full trailer filled with hydrogen can be removed and replaced with an empty trailer. In some embodiments, additional trailers can also be utilized to provide additional hydrogen storage capacity.
[0018] In some embodiments of the method, the at least one second trailer can be positioned and configured such that hydrogen stored in the at least one second trailer can be directly supplied to the FCM while a demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than a rate at which hydrogen is supplied to the first compressor. The at least one first trailer can also be positioned and configured such that hydrogen stored in the at least one first trailer can be directly supplied to the FCM while a demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than a rate at which hydrogen is supplied to the first compressor.
[0019] In embodiments of the method that use only the at least one first trailer, the at least one first trailer can be a single trailer or multiple trailers. The at least one first trailer can be arranged and configured such that hydrogen stored in the at least one first trailer can be supplied directly to the FCM during times when the demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
[0020] A hydrogen fuel generation, distribution, and storage apparatus is also provided. An embodiment of the apparatus can include a hydrogen generation system including an ammonia cracker or a methane reformer having at least one reformer device. A first compressor can be positioned to receive hydrogen from the hydrogen generation system, at least one dispenser can be positioned to distribute hydrogen to the vehicle, and a flow control manifold (FCM) can be positioned downstream of the first compressor and upstream of the at least one dispenser to receive hydrogen for supplying to the at least one dispenser. An embodiment of the apparatus can also include a second compressor positioned between the first compressor and the FCM to increase a pressure of hydrogen output from the compressor from the first pressure to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM. Embodiments may also include a first storage vessel disposed between the first compressor and the second compressor for storing hydrogen output from the first compressor before the hydrogen is provided to the second compressor, and a second storage vessel disposed between the second compressor and the FCM for storing hydrogen output from the second compressor before the hydrogen is provided to the FCM for distribution.
[0021] An embodiment of the hydrogen fuel generation, distribution, and storage apparatus may also include at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage while a demand for hydrogen at the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer can pass to the FCM while a demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
[0022] Embodiments of the hydrogen fuel generation, distribution, and storage apparatus may also include at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor can be supplied to the at least one second trailer for storage while demand for hydrogen at the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one second trailer can pass to the FCM while demand for hydrogen at the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
[0023] In some embodiments, the one or more first trailers can be configured to store hydrogen at a first pressure at which the hydrogen is output from the first compressor. The one or more second trailers can be configured to store hydrogen at a second pressure that is higher than the first pressure. The second pressure can be, for example, the pressure of the hydrogen output from the second compressor. In such embodiments, the first pressure can be considered low pressure (LP) and the second pressure can be considered medium pressure (MP) or high pressure (HP).
[0024] Other details, objects, and advantages of the hydrogen fuel supply system, hydrogen fuel generation, distribution, and storage apparatus, hydrogen fuel distribution and storage apparatus, and methods of making and using the same will become apparent as the following description of specific exemplary embodiments thereof proceeds. [Brief description of the drawings]
[0025] Exemplary embodiments of a hydrogen fuel supply system, a hydrogen fuel generation, distribution, and storage device, a hydrogen fuel distribution and storage device, and methods of making and using the same are illustrated in the drawings included herein, It should be understood that like reference numbers used in the drawings may identify like components.
[0026] [Figure 1] 1 is a schematic diagram of a first exemplary embodiment of a hydrogen fuel generation, distribution, and storage device.
[0027] [Diagram 2] 2 is a schematic diagram of a second exemplary embodiment of a hydrogen fuel generation, distribution, and storage apparatus.
[0028] [Diagram 3] 1 is a schematic diagram of a third exemplary embodiment of a hydrogen fuel generation, distribution, and storage apparatus. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0029] 1-3, a hydrogen fuel generation, distribution, and storage apparatus may be provided at a single site such that hydrogen provided by a hydrogen generation system may be supplied to one or more dispensers at a fuel supply station at the same site. The hydrogen generation system may include, for example, an ammonia cracker system or a methane reformer system.
[0030] For example, the hydrogen production system can include at least one methane reformer that reforms methane to form hydrogen (H2). The reformer device can include, for example, a steam reforming, autothermal reforming, or partial oxidation based device configured to facilitate chemical synthesis to produce pure hydrogen gas from methane. The reformer device can include, for example, an autothermal reforming (ATR) device or a steam methane reforming (SMR) device. These devices can be configured to utilize catalysts to facilitate the production of hydrogen at relatively high temperatures and pressures.
[0031] As another example, the hydrogen generation system can include an ammonia (NH3) cracker system. The ammonia cracker system can be configured to crack ammonia to form hydrogen gas. The ammonia gas can be heated, vaporized, and then cracked to form hydrogen gas and other gases (e.g., nitrogen gas). The hydrogen gas formed via the cracker can be separated from the nitrogen gas for supply to an on-site fuel supply station having one or more dispensers. The ammonia cracker can be configured to facilitate dissociation of ammonia gas at a preselected cracking pressure at an elevated temperature (e.g., a temperature of 800°C, or other suitable temperature). A catalyst can also be utilized to facilitate the cracking of the ammonia gas.
[0032] The hydrogen production system can be configured to utilize a purification system, or gas separation system, to separate the formed hydrogen gas from other gases (e.g., nitrogen, carbon dioxide, etc.). Such purification systems can include, for example, a pressure swing adsorption system (PSA) and / or a temperature swing adsorption system (TSA). Other types of purification systems can alternatively or additionally be utilized. In some embodiments, the hydrogen gas output from the hydrogen production system can be purified such that the hydrogen output from the hydrogen production system is at least 99 mol% hydrogen, at least 99.5 molar percent (mol%) hydrogen, or at least 99.7 mol% hydrogen (e.g., in the range of 99.7 mol% hydrogen to 99.999 mol% hydrogen).
[0033] The hydrogen gas output from the hydrogen production system may then be supplied from the hydrogen production system to a first compressor, which may be a low pressure (LP) compressor (which may also be referred to as an LP compressor), or a medium pressure (MP) compressor or a high pressure (HP) compressor (see, for example, the embodiment of FIG. 3).
[0034] The hydrogen compressed via the first compressor may, in some embodiments, comprise hydrogen that is at least 99.97 mol% hydrogen. The compressed hydrogen stream may also, in some embodiments, comprise impurities having a concentration of up to 300 ppm (e.g., in the range of 0 ppm to 300 ppm). Impurities up to 300 ppm (e.g., impurities in the range of 0 ppm to 300 ppm cumulatively) can include water present at up to 5 ppm, total hydrocarbons excluding methane or other single carbon equivalent hydrocarbons at up to 2 ppm, oxygen at up to 5 ppm, methane at up to 100 ppm, helium at up to 300 ppm, nitrogen at up to 300 ppm, argon at up to 300 ppm, carbon dioxide at up to 2 ppm, carbon monoxide at up to 0.2 ppm, total sulfur compounds at up to 0.004 ppm, formaldehyde at up to 0.2 ppm, formic acid at up to 0.2 ppm, ammonia at up to 0.1 ppm, and halogenated compounds at up to 0.05 ppm. It should be understood that the term "maximum" refers to an impurity concentration ranging from 0 to an upper limit value of the impurity (e.g., 0-5 ppm for water, 0-100 ppm for methane, 0-300 ppm for nitrogen, 0-300 ppm for all impurities present in the hydrogen stream, etc.).
[0035] The hydrogen supply conduit can be arranged to transport hydrogen from the hydrogen production system to the first compressor. The first compressor can be sized and configured to meet the hydrogen flow rate (e.g., 25 kg / hr, 5 kg / hr to 30 kg / hr, 1 kg / hr to 50 kg / hr, etc.) available from the hydrogen production system. The first compressor can be sized and arranged to pressurize hydrogen for storage within at least one tube trailer via at least one tube trailer supply conduit and / or supply hydrogen to another storage device (e.g., an LP storage vessel, an MP storage vessel, or other type of storage vessel) via a first storage device supply conduit.
[0036] Each tube trailer may be a removable and / or replaceable trailer: if the first trailer is full, it may be replaced with an empty trailer to allow hydrogen to be stored inside, or another trailer may be connected to provide additional removable storage so that additional excess hydrogen can be fed into the added trailer for storage (instead of removing and replacing the filled first trailer).
[0037] Each storage vessel may be a single vessel or may be a storage unit including multiple storage vessels. For example, in some embodiments, LP storage and MP storage may each be provided via multiple storage vessels arranged in a storage unit located at a particular storage location, at a fuel distribution site or other location adjacent to the fuel distribution site of the apparatus.
[0038] In some embodiments, the pressurization provided by the first compressor may pressurize the hydrogen to a pressure within a first preselected pressure range of 20 MPa to 40 MPa. Other embodiments (e.g., the embodiment of FIG. 3 utilizing a single first compressor) may utilize other pressures within different ranges (e.g., 20-80 MPa or 25-65 MPa, 35 MPa, 40 MPa, 45 MPa, 50 MPa, 55 MPa, 60 MPa, 15 MPa to 65 MPa, etc.).
[0039] The embodiments may also utilize a second compressor (e.g., the MP compressor shown in FIGS. 1 and 2) configured to receive hydrogen from the first compressor, or a first storage vessel disposed between the first and second compressors via a second compressor supply conduit. The second compressor may be configured to increase the pressure of the hydrogen received from the first storage vessel (e.g., the LP storage vessel shown in FIGS. 1 and 2) or the first compressor to a second higher pressure within a preselected second pressure range (e.g., a pressure between 30-80 MPa, a pressure between 30-70 MPa, etc.). The second compressor may output hydrogen for supply to the second storage vessel via a second storage supply conduit. The second storage vessel may be arranged and configured to hold and store hydrogen at this second pressure level (e.g., the MP storage vessel shown in FIGS. 1 and 2) for supply to a flow control manifold (FCM) via a FCM supply conduit. The FCM may also be positioned and configured to receive hydrogen from one or more tube trailers via one or more hydrogen tube trailer FCM supply conduits. The FCM may be fluidly connected to one or more dispensers of a fuel distribution system to provide hydrogen to the dispensers for dispensing to fuel tanks of one or more vehicles or other devices. The FCM may be configured to simultaneously dispense hydrogen to one or more dispensers of a fuel station to provide hydrogen to the dispensers for fueling fuel tanks of different vehicles or other devices located near the dispensers receiving the hydrogen. The supply of hydrogen at the dispensers may occur after or before payment for the hydrogen is made at the fuel station or fuel station dispenser kiosk.
[0040] With reference to the embodiment shown in FIG. 1, one or more removable (or replaceable) tube trailers can receive LP hydrogen from a first compressor (e.g., an LP compressor) to provide excess storage capacity for hydrogen. Each tube trailer can be a removable and / or replaceable trailer. When a first trailer is full, it can be replaced with an empty trailer (e.g., the trailer shown in dashed lines) to allow hydrogen to be stored therein, or another trailer (e.g., the trailer shown in dashed lines) can be connected to provide additional removable storage such that additional excess hydrogen can be supplied to the added trailer for storage (instead of removing and replacing the filled first trailer).
[0041] The tube trailer or multiple tube trailers can then be configured to supply LP hydrogen to the FCM to provide hydrogen directly to the FCM for distribution when the demand for hydrogen exceeds the flow of hydrogen that can be provided via the second storage vessel and the hydrogen generation system. The controller can actuate valving of the conduits and other operational control units to change the flow path such that when the tube trailer outputs hydrogen stored therein to the FCM for distribution, hydrogen output from the first compressor (e.g., LP compressor) is no longer supplied to the tube trailer. Hydrogen generated via the hydrogen generation system can continue to supply hydrogen to the first compressor (e.g., LP compressor) for delivery towards the FCM, so that the generated hydrogen is also being supplied to the FCM to meet the demand for hydrogen while hydrogen from the one or more tube trailers is being supplied to the FCM.
[0042] With reference to the embodiment shown in Figure 3, one or more tube trailers can receive LP or MP hydrogen from the first compressor to provide excess storage capacity for hydrogen. Each tube trailer can be a removable and / or replaceable trailer. If the first trailer is full, it can be replaced with an empty trailer (e.g., the trailer shown in dashed lines) to allow hydrogen to be stored therein, or another trailer (e.g., the trailer shown in dashed lines) can be connected to provide additional removable storage so that additional excess hydrogen can be supplied to the added trailer for storage (instead of removing and replacing the filled first trailer).
[0043] The tube trailer or multiple tube trailers can then be configured to supply hydrogen to the FCM to provide hydrogen directly to the FCM for distribution when demand for hydrogen exceeds the flow of hydrogen that can be provided via the second storage vessel and the hydrogen generation system. The controller can actuate valving of the conduits and other operational control units to change the flow path of the hydrogen such that hydrogen output from the first compressor is no longer supplied to the tube trailer when the tube trailer outputs hydrogen stored therein to the FCM for distribution. Hydrogen produced via the hydrogen generation system can continue to supply hydrogen to the first compressor to be fed towards the FCM to meet demand for hydrogen while hydrogen from the one or more tube trailers is being supplied to the FCM.
[0044] Referring to the embodiment shown in FIG. 2, a plurality of first tube trailers can receive LP hydrogen from the LP compressor to provide excess storage capacity for hydrogen. Each first tube trailer can be a removable and / or replaceable trailer. When one of the first trailers becomes full, it can be replaced with an empty trailer to allow hydrogen to be stored therein, or another first trailer can be connected to provide additional removable storage so that additional excess hydrogen can be supplied to the added first trailer for storage (instead of removing and replacing a filled first trailer). Adding another first trailer can be utilized instead of replacing a full trailer, for example, in situations where a large demand for hydrogen is expected and additional storage capacity may be required on-site.
[0045] The first tube trailer can be configured to supply hydrogen to the FCM to provide hydrogen directly to the FCM for distribution when the demand for hydrogen exceeds the flow of hydrogen that can be provided via the MP storage vessel and the hydrogen generation system. The controller can actuate valving of the conduits and other operational control units to change the flow path of the hydrogen such that hydrogen output from the first compressor is no longer supplied to the first tube trailer and the first tube trailer outputs hydrogen stored therein to the FCM for distribution. Hydrogen produced via the hydrogen generation system can continue to supply hydrogen to the first compressor to be supplied towards the FCM to meet the demand for hydrogen while hydrogen from the first tube trailer is being supplied to the FCM.
[0046] A plurality of second tube trailers can receive MP hydrogen from a second compressor (e.g., MP compressor) to also provide excess storage capacity for hydrogen. Each second tube trailer can be a removable and / or replaceable trailer. If one of the second trailers becomes full, it can be replaced with an empty trailer to allow hydrogen to be stored therein, or another second trailer can be connected to provide additional removable storage so that additional excess hydrogen can be fed to the added second trailer for storage (instead of removing and replacing a filled second trailer). Adding another second trailer can be utilized instead of replacing a full trailer, for example, in situations where a large demand for hydrogen is expected and additional storage capacity may be required on-site.
[0047] The second tube trailer can be configured to supply hydrogen to the FCM to provide hydrogen directly to the FCM for distribution when hydrogen demand exceeds the flow of hydrogen that can be provided via the MP storage vessel and the hydrogen generation system. The controller can actuate valving of the conduits and other operational control units to change the flow path of the hydrogen such that hydrogen output from the second compressor (e.g., MP compressor) is no longer supplied to the second tube trailer, and the second tube trailer outputs hydrogen stored therein to the FCM for distribution. Hydrogen generated via the hydrogen generation system can continue to supply hydrogen to the first compressor to be supplied to the second compressor to be supplied to the FCM to meet hydrogen demand, while hydrogen from the second tube trailer is being supplied to the FCM.
[0048] In the embodiment of FIG. 2, hydrogen from one or more of the first tube trailers can be directly supplied to the FCM, while hydrogen from one or more of the second tube trailers is also directly supplied to the FCM. This supply of hydrogen can occur while hydrogen is also being supplied to the FCM via the hydrogen generation system (such as via the first and second compressors). The controller can actuate valving of conduits and other operational control units to change the flow path of hydrogen such that the second and first tube trailers are no longer supplied with hydrogen, and the first and second tube trailers output the hydrogen stored therein to the FCM for distribution. All hydrogen from the hydrogen generation system, or associated intermediate storage unit, can be supplied to the FCM, while the first and second tube trailers are also utilized to supply hydrogen to the FCM for distribution.
[0049] In yet other embodiments, the first tube trailer and / or the second tube trailer can be configured to supply hydrogen to the hydrogen stream upstream of the FCM for supply to the FCM. For example, instead of being supplied directly to the FCM, hydrogen stored in one or more first tube trailers can be supplied to a second compressor supply conduit to undergo additional compression before being supplied to the FCM. Figures 1 and 2 illustrate such a feature by illustrating a hydrogen distribution conduit for supplying hydrogen stored in one or more tube trailers to a first storage conduit so that such hydrogen can then be supplied to the second compressor. Figure 2 also illustrates a flow path option for distributing hydrogen from the second tube trailer so that the second tube trailer can supply hydrogen to a second storage vessel (MP storage) downstream of the second compressor to indirectly supply hydrogen to the FCM instead of directly supplying hydrogen to the FCM. The controller can actuate valving of the conduits and other operational control units to change the flow path of the hydrogen such that hydrogen is no longer supplied to the first tube trailer, and the first tube trailer outputs hydrogen stored therein to the second compressor for indirectly supplying hydrogen to the FCM (e.g., the embodiment of Figs. 1 and 2). The controller can also actuate valving of the conduits and other operational control units to change the flow path of the hydrogen such that hydrogen is no longer supplied to the second tube trailer, and the second tube trailer outputs hydrogen stored therein downstream of the second compressor for supplying to the second storage unit for indirectly supplying hydrogen to the FCM (e.g., Fig. 2).
[0050] The hydrogen generation system can be configured to throttle back or increase hydrogen production to meet the fuel demand at a fueling station having at least one dispenser. The hydrogen production can be adjusted to meet the hydrogen demand at the fueling station. If the hydrogen generation system is running at full speed and there is not enough usage from the one or more dispensers, then the excess hydrogen gas can be sent to at least one trailer (e.g., at least one tube trailer) for storage. In such a situation, the hydrogen gas can be pressurized, for example, via a first compressor and then delivered to at least one trailer for storage therein. Hydrogen pressurized within this first pressure range (e.g., 20 MPa to 30 MPa, 20 MPa to 70 MPa, 30 MPa to 50 MPa, etc.) can be transported to the one or more tube trailers, for example, via a tube trailer storage conduit disposed between the first compressor and the one or more tube trailers.
[0051] In response to determining that the demand for hydrogen to be dispensed at one or more dispensers of the fueling station is low, the hydrogen generation system may be throttled to slow the hydrogen production rate. This may be done, for example, to attempt to operate the hydrogen generation system in a way that may better match the actual hydrogen usage rate at the fueling station. In some embodiments, the hydrogen generation system may be throttled, for example, from a maximum production rate to a minimum production rate. In some embodiments, when the hydrogen generation system is operated at maximum production capacity, the minimum production rate may be about half of the full production capacity (e.g., in some embodiments where the maximum production capacity is 25 kg / hr, the minimum production capacity may be 12.5 kg / hr, e.g., in embodiments where the maximum production capacity may be between 30 kg / hr, 20 kg / hr, or 35 kg / hr and 18 kg / hr, the minimum production rate may be 15 kg / hr, or 10 kg / hr, or less than 12.5 kg / hr, etc.).
[0052] After a hydrogen production system is slowed down to a lower speed (e.g., minimum production capacity), it can often take a significant amount of time for production to return to maximum production capacity. For example, in some embodiments, it can take the hydrogen production system approximately one hour to change its operating output from minimum output to maximum hydrogen production output after the system's operating capacity is adjusted. Such a delay can vary depending on the size, type (e.g., cracker or reformer, etc.) and operating capacity of the hydrogen production system. Such output delays can be due to the time it takes the hydrogen production system to increase production from a previous minimum operating capacity setting to a maximum production setting after a hydrogen output adjustment is made by a controller or operator. Such types of delays can also occur in response to adjustments from operating at a maximum output speed to a minimum output speed (e.g., it can take approximately one hour for the hydrogen production system's output to decrease to minimum output after being adjusted to change output from maximum output capacity to minimum output capacity).
[0053] In situations where the hydrogen generation system is operating at a low operating output rate and the dispensing needs of one or more dispensers of the on-site fuel supply station increase to a level that exceeds their capacity, additional hydrogen fuel that may be needed for dispensing at one or more dispensers may be provided via stored hydrogen held in one or more tube trailers. The use of stored hydrogen from one or more trailers can also provide for situations where the hydrogen generation system is operating at maximum capacity and the demand for hydrogen exceeds the hydrogen production capacity for a period of time.
[0054] For example, in the third embodiment shown in solid lines in FIG. 3, there may be a single compressor and a single trailer to provide such flexibility between storage and output for hydrogen distribution. In such an embodiment, the single trailer may be configured to hold and store hydrogen gas at any pressure of 20 MPa, 30 MPa, 40 MPa, 50 MPa, or other preselected first storage pressure (e.g., pressures between 20 Mpa and 60 MPa, or other pressures). The first single compressor may be sized to meet the maximum and minimum flow rates of the hydrogen production system (e.g., 25 kg / hr to 12.5 kg / hr, or 30 kg / hr to 10 kg / hr, etc.). When the hydrogen production system is operating at maximum speed and there is not enough usage from the dispenser, excess hydrogen gas may be sent to the trailer for storage. If the hydrogen generation system slows down its production rate and the on-site fueling station's dispenser unexpectedly increases its hydrogen distribution needs, the necessary additional hydrogen supply can be provided via hydrogen stored in the tube trailer while the hydrogen generation system's production is increased to better match the new demand for hydrogen at the dispenser. The stored hydrogen can be mixed with the hydrogen output from the trailer and output from the first compressor to be fed towards the fuel dispenser for distribution to indirectly supply hydrogen to the FCM, or the stored hydrogen can be fed directly from the tube trailer to the FCM.
[0055] If additional hydrogen is needed, a second trailer filled with hydrogen (shown in dashed lines in FIG. 3) can be connected to provide the additional hydrogen. If additional storage capacity is needed for storage and / or removal of hydrogen produced from the hydrogen production system, the second trailer can also be connected as an empty trailer to be filled with additional hydrogen. A third trailer, or other additional second trailers, can also be added to provide additional storage capacity and / or more hydrogen capacity.
[0056] When the stored hydrogen is not expected to be needed, the single full trailer can be removed and replaced with an empty replacement first trailer. The empty replacement single trailer can then be filled with hydrogen. The removed full trailer can be transported via truck or rail to another site where the demand for hydrogen may be higher.
[0057] It should be understood that the single trailer arrangement of the embodiment shown in solid lines in Figures 1 and 3 can allow a hydrogen fuel generation, distribution, and storage device to take in hydrogen or take out hydrogen. For example, when a trailer is full, it can be transported off-site to another fueling station, and then an empty replacement trailer can be connected to replace the removed trailer, which is used to take out hydrogen to the other station. As another example, if a trailer is empty and stored hydrogen may be needed, the empty trailer can be replaced with a full replacement trailer to provide additional hydrogen capacity at the station for fueling with one or more dispensers, or another full trailer can be connected to provide additional hydrogen (e.g., a second additional full trailer, shown in dashed lines in Figures 1 and 3, can be added to the system to provide additional hydrogen for the fueling station).
[0058] In the embodiment shown in FIG. 2, and in the embodiments shown in FIGS. 1 and 3, which may utilize an additional second trailer shown in dashed lines, multiple trailers may be utilized for the storage and subsequent use of hydrogen to meet the hydrogen dispensing demand at the on-site fueling station. For example, there may be multiple tube trailers arranged for the storage of hydrogen. In some arrangements (e.g., the embodiment of FIG. 2), one or more first trailers may be configured to store hydrogen at a first pressure or a first pressure level, and other second trailers may be configured and arranged to store at a second pressure level or a second pressure. The additional trailers may provide additional storage capacity at different pressure levels (e.g., may include a third trailer that may be utilized as an additional first trailer and / or an additional second trailer). Additionally, one or more of the trailers may be arranged to provide hydrogen directly from the trailer to at least one fuel dispenser to increase station capacity and conserve energy.
[0059] In the multiple trailer embodiment shown in FIG. 2, for example, the low pressure trailer can store hydrogen at a first pressure level (e.g., pressures of 20 MPa to 30 MPa, or 20 MPa to 40 MPa), and the high pressure trailer can store hydrogen at a second pressure level higher than the first pressure level (e.g., pressures above 30 MPa, pressures of 40 MPa to 70 MPa, pressures of 50 MPa to 70 MPa, etc.). The trailer storage provided by the multiple trailers can allow for matching the production and usage of hydrogen provided by the hydrogen generation system. Additionally, the utilization of two or more trailers at each pressure level of the station allows for trailers to be removed when full, or replaced when empty, so that trailers can be used to match station demand. This allows the trailers of the hydrogen fuel generation, distribution, and storage equipment to provide both intake and removal capabilities. For example, when a trailer is full, it can be transported off-site to another fueling station, and then an empty replacement trailer can be connected to replace the removed full trailer that is used to extract hydrogen to the other station. As another example, when a trailer is empty and stored hydrogen may be needed, the empty trailer can be replaced with a full replacement trailer to provide additional hydrogen capacity at a station for fueling with one or more dispensers (e.g., allowing hydrogen to be imported via one or more trailers delivered to the site). It should be understood that transportation of tube trailers to and from one or more fueling station sites of the apparatus for hydrogen import and extraction can be via truck driving the trailer along roadways and / or rail transport.
[0060] Of course, some embodiments can be configured to utilize only one or more trailers arranged to store hydrogen at the same pressure. The embodiments of Figures 1 and 3 show example arrangements for such embodiments, using only a single trailer as shown in solid lines, or using multiple trailers as shown via dashed lines.
[0061] The use of removable and interchangeable trailers to provide extra hydrogen storage capacity and / or hydrogen removal capacity can provide improved operational flexibility. For example, in some embodiments, trailers can be removed and replaced to accommodate times of low and high hydrogen fueling demand at a particular on-site fueling station. For example, a site operator can manage the hydrogen production process and trailer usage such that an initial full trailer will be replaced with another empty trailer, or an additional full trailer will be plugged in to replace an empty trailer as needed for the station's expected hydrogen usage cycle. The removal and removal of full trailers can be managed to accommodate the expected daily hydrogen usage of the on-site fueling station and the daily cycle that may exist between periods of low demand (e.g., times when there are only a few vehicles that may obtain fuel from one or more dispensers at the fueling station) and periods of high demand (e.g., times when there are many vehicles obtaining fuel from one or more dispensers at the fueling station).
[0062] A schedule for replacing trailers or adding additional trailers can also be designed to implement a time-of-day strategy for removable trailers. For example, if fueling by customers or users typically occurs during a particular fuel demand period (e.g., 8 p.m. to 4 a.m.), the operator may seek to have at least one full trailer connected and ready to provide hydrogen to meet the start of an expected high demand period (e.g., 8 p.m. in an exemplary fuel demand period from 8 p.m. to 4 a.m.) and may seek to have at least one empty trailer available at the end of the fuel demand period (e.g., 4 a.m. in an exemplary fuel demand period from 8 p.m. to 4 a.m.) to be filled to provide additional hydrogen storage capacity for the start of the next high demand cycle (e.g., 8 p.m. in an exemplary fuel demand period from 8 p.m. to 4 a.m.).
[0063] It is understood that a schedule for adding or replacing trailers can be tailored to meet the needs of a particular site. The use of trailers can also allow for flexibility in dealing with situations where an unexpected demand for hydrogen occurs or where a significant increase in hydrogen demand may unexpectedly occur. For example, in response to an unexpected demand that is detected, a trailer can be transported to the site and / or a full trailer that may be on-site but not connected to the distribution system can be connected to the system to provide additional hydrogen to meet the unexpected demand.
[0064] It will be appreciated that embodiments of the hydrogen fuel supply system, hydrogen fuel generation, distribution, and storage apparatus, hydrogen fuel distribution and storage apparatus, and methods of making and using same may each be configured to include process control elements arranged and configured to monitor and control operation (e.g., an automated process control system having at least one workstation including temperature and pressure sensors, flow sensors, a processor, non-transitory memory, and at least one transceiver for communicating with the sensor elements, valves, and a controller for providing a user interface for the automated process control system, which may run on the workstation and / or on another computing device of the apparatus).
[0065] It should be understood that modifications to the embodiments explicitly shown and discussed herein can be made to meet a particular set of design goals or a particular set of design criteria. For example, the arrangement of valves, piping, and other conduit elements (e.g., conduit connections, tubing, seals, etc.) for interconnecting different units of the apparatus for fluid communication of fluids between the different units can be arranged to meet a particular layout design that corresponds to the available area of the fuel system, the sized equipment of the system, and other design considerations. As another example, the flow rates, pressures, and temperatures of fluids passing through different elements of the apparatus, as well as through other apparatus elements, can be varied to accommodate different fuel system design configurations and other design criteria. As yet another example, the material compositions for the different structural components of the apparatus can be any type of suitable material that may be required to meet a particular set of design criteria.
[0066] As another example, it is contemplated that certain features described either individually or as part of an embodiment may be combined with other individually described features or parts of other embodiments. Thus, elements and acts of various embodiments described herein may be combined to provide further embodiments. While certain exemplary embodiments of a hydrogen fuel supply system, a hydrogen fuel generation, distribution, and storage device, a hydrogen fuel distribution and storage device, and methods of making and using the same have been shown and described above, it should be clearly understood that the invention is not limited thereto and may be variously embodied in other ways and practiced within the scope of the following claims. The present invention can be embodied in the following manner. (Appendix 1) 1. A hydrogen fuel distribution and storage device comprising: a first compressor positioned to receive hydrogen from the hydrogen production system; a flow control manifold (FCM) disposed downstream of the first compressor to receive the hydrogen for supply to at least one dispenser; and at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage while a demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 2) 2. The hydrogen fuel distribution and storage apparatus of claim 1, comprising: a second compressor disposed between the first compressor and the FCM to increase a pressure of the hydrogen output from the first compressor from a first pressure to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM. (Appendix 3) a first storage vessel between the first compressor and the second compressor for storing the hydrogen output from the first compressor before the hydrogen is supplied to the second compressor; and a second storage vessel between the second compressor and the FCM for storing the hydrogen output from the second compressor before the hydrogen is provided to the FCM for distribution. (Appendix 4) 3. The hydrogen fuel dispensing and storage apparatus of claim 2, comprising at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor can be supplied to the at least one second trailer for storage while a demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and such that the hydrogen from the at least one second trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 5) 5. The hydrogen fuel distribution and storage apparatus of claim 4, wherein the at least one first trailer is a single trailer or multiple trailers, and the at least one second trailer is a single trailer or multiple trailers. (Appendix 6) the at least one second trailer is positioned and configured such that the hydrogen stored in the at least one second trailer is directly supplyable to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; 5. The hydrogen fuel dispensing and storage apparatus of claim 4, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 7) the at least one first trailer is a single trailer or a plurality of trailers; 3. The hydrogen fuel dispensing and storage apparatus of claim 2, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 8) the at least one first trailer is a single trailer or a plurality of trailers; 2. The hydrogen fuel dispensing and storage apparatus of claim 1, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 9) 2. The hydrogen fuel distribution and storage apparatus of claim 1, wherein the at least one first trailer comprises at least one detachable tube trailer. (Appendix 10) 2. The hydrogen fuel distribution and storage apparatus of claim 1, wherein the hydrogen fuel distribution and storage apparatus is a hydrogen fuel generation, distribution, and storage apparatus that includes the hydrogen generation system. (Appendix 11) 11. The hydrogen fuel distribution and storage apparatus of claim 10, wherein the hydrogen production system includes an ammonia cracker or a methane reformer having at least one reformer device. (Appendix 12) 1. A method for producing, storing, and / or distributing hydrogen, comprising: compressing hydrogen received from a hydrogen production system to a first pressure; providing the hydrogen to a flow control manifold (FCM) for delivery to at least one dispenser; in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is less than a rate at which hydrogen is supplied to the first compressor, supplying at least a portion of the hydrogen output from the first compressor to at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage; and in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is greater than the rate at which hydrogen is supplied to the first compressor, outputting hydrogen stored in at least one first trailer to the FCM for distribution at the at least one dispenser. (Appendix 13) 13. The method of claim 12, comprising supplying the hydrogen at the first pressure to a second compressor disposed between the first compressor and the FCM to increase a pressure of the hydrogen to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM. (Appendix 14) in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is less than a rate at which hydrogen is supplied to the first compressor, supplying at least a portion of the hydrogen output from the second compressor to at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one second trailer for storage; outputting hydrogen stored in at least one second trailer to the FCM for distribution at the at least one dispenser in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 15) 15. The method of claim 14, wherein the at least one first trailer is a single trailer or a plurality of trailers, and the at least one second trailer is a single trailer or a plurality of trailers. (Appendix 16) the at least one second trailer is positioned and configured such that the hydrogen stored in the at least one second trailer is directly supplyable to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; 15. The method of claim 14, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 17) the at least one first trailer is a single trailer or a plurality of trailers; 14. The method of claim 13, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer is supplyable directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 18) the at least one first trailer is a single trailer or a plurality of trailers; 13. The method of claim 12, wherein the at least one first trailer is positioned and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for dispensing at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor. (Appendix 19) 2. The method of claim 1, wherein the at least one first trailer comprises at least one detachable tube trailer. (Appendix 20) 1. A hydrogen fuel generation, distribution, and storage device comprising: a hydrogen production system including an ammonia cracker or a methane reformer having at least one reformer device; a first compressor positioned to receive hydrogen from the hydrogen production system; at least one dispenser positioned to dispense the hydrogen to a vehicle; a flow control manifold (FCM) disposed downstream of the first compressor and upstream of the at least one dispenser to receive the hydrogen for supply to the at least one dispenser; a second compressor disposed between the first compressor and the FCM for increasing a pressure of the hydrogen output from the compressor from a first pressure to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM; a first storage vessel disposed between the first compressor and the second compressor for storing the hydrogen output from the first compressor before the hydrogen is supplied to the second compressor; a second storage vessel disposed between the second compressor and the FCM for storing the hydrogen output from the second compressor before the hydrogen is provided to the FCM for distribution; at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage while the demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; and at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor can be supplied to the at least one second trailer for storage while a demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and at least one second trailer such that the hydrogen from the at least one second trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
Claims
1. 1. A hydrogen fuel distribution and storage device comprising: a first compressor positioned to receive hydrogen from the hydrogen production system; a flow control manifold (FCM) disposed downstream of the first compressor to receive the hydrogen for supply to at least one dispenser; at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage while the demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; a second compressor disposed between the first compressor and the FCM for increasing a pressure of the hydrogen output from the first compressor from a first pressure to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM; a first storage vessel, the first storage vessel being a single vessel, located between the first compressor and the second compressor for storing the hydrogen output from the first compressor before the hydrogen is supplied to the second compressor.
2. 2. The hydrogen fuel distribution and storage apparatus of claim 1, comprising a second storage vessel between the second compressor and the FCM for storing the hydrogen output from the second compressor before the hydrogen is supplied to the FCM for distribution.
3. 2. The hydrogen fuel dispensing and storage apparatus of claim 1, comprising at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor can be supplied to the at least one second trailer for storage while a demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and such that the hydrogen from the at least one second trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
4. 4. The hydrogen fuel distribution and storage system of claim 3, wherein the at least one first trailer is a single trailer or a plurality of trailers and the at least one second trailer is a single trailer or a plurality of trailers.
5. the at least one second trailer is arranged and configured such that the hydrogen stored in the at least one second trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; 4. The hydrogen fuel distribution and storage system of claim 3, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
6. the at least one first trailer is a single trailer or a plurality of trailers; 2. The hydrogen fuel distribution and storage apparatus of claim 1, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
7. the at least one first trailer is a single trailer or a plurality of trailers; 2. The hydrogen fuel distribution and storage apparatus of claim 1, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
8. The hydrogen fuel distribution and storage system of claim 1 , wherein the at least one first trailer comprises at least one detachable tube trailer.
9. 10. The hydrogen fuel distribution and storage system of claim 1, wherein the hydrogen fuel distribution and storage system is a hydrogen fuel generation, distribution and storage system that includes the hydrogen production system.
10. 10. The hydrogen fuel distribution and storage apparatus of claim 9, wherein the hydrogen production system comprises an ammonia cracker or a methane reformer having at least one reformer device.
11. 1. A method for producing, storing, and / or distributing hydrogen, comprising: compressing hydrogen received from a hydrogen production system to a first pressure; providing the hydrogen to a flow control manifold (FCM) for delivery to at least one dispenser; In response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is less than a rate at which hydrogen is supplied to the first compressor, supplying at least a portion of the hydrogen output from the first compressor to at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage; outputting hydrogen stored in at least one first trailer to the FCM for distribution at the at least one dispenser in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is greater than the rate at which hydrogen is supplied to the first compressor; supplying the hydrogen at the first pressure to a second compressor disposed between the first compressor and the FCM to increase the pressure of the hydrogen to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM; storing the hydrogen output from the first compressor in a first storage vessel, the first storage vessel being between the first compressor and the second compressor, before the hydrogen is supplied to the second compressor.
12. In response to a demand for hydrogen in the FCM for distribution at the at least one dispenser that is less than a rate at which hydrogen is supplied to the first compressor, supplying at least a portion of the hydrogen output from the second compressor to at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one second trailer for storage; and outputting hydrogen stored in at least one second trailer to the FCM for distribution at the at least one dispenser in response to a demand for hydrogen at the FCM for distribution at the at least one dispenser that is greater than the rate at which hydrogen is supplied to the first compressor.
13. 13. The method of claim 12, wherein the at least one first trailer is a single trailer or a plurality of trailers and the at least one second trailer is a single trailer or a plurality of trailers.
14. the at least one second trailer is arranged and configured such that the hydrogen stored in the at least one second trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; 13. The method of claim 12, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
15. the at least one first trailer is a single trailer or a plurality of trailers; 12. The method of claim 11, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
16. the at least one first trailer is a single trailer or a plurality of trailers; 12. The method of claim 11, wherein the at least one first trailer is arranged and configured such that the hydrogen stored in the at least one first trailer can be supplied directly to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
17. The method of claim 11 , wherein the at least one first trailer comprises at least one detachable tube trailer.
18. 1. A hydrogen fuel generation, distribution, and storage device comprising: a hydrogen production system including an ammonia cracker or a methane reformer having at least one reformer device; a first compressor positioned to receive hydrogen from the hydrogen production system; at least one dispenser positioned to dispense the hydrogen to a vehicle; a flow control manifold (FCM) disposed downstream of the first compressor and upstream of the at least one dispenser for receiving the hydrogen for supply to the at least one dispenser; a second compressor disposed between the first compressor and the FCM for increasing a pressure of the hydrogen output from the first compressor from a first pressure to a second pressure higher than the first pressure before the hydrogen is supplied to the FCM; a first storage vessel, the first storage vessel being a single vessel disposed between the first compressor and the second compressor for storing the hydrogen output from the first compressor before the hydrogen is supplied to the second compressor; a second storage vessel disposed between the second compressor and the FCM for storing the hydrogen output from the second compressor before the hydrogen is provided to the FCM for distribution; at least one first trailer disposed between the first compressor and the FCM such that hydrogen output from the first compressor can be supplied to the at least one first trailer for storage while the demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and hydrogen from the at least one first trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor; and at least one second trailer disposed between the second compressor and the FCM such that hydrogen output from the second compressor can be supplied to the at least one second trailer for storage while a demand for hydrogen in the FCM for distribution at the at least one dispenser is less than the rate at which hydrogen is supplied to the first compressor, and at least one second trailer such that the hydrogen from the at least one second trailer can pass to the FCM while the demand for hydrogen in the FCM for distribution at the at least one dispenser is greater than the rate at which hydrogen is supplied to the first compressor.
Citation Information
Patent Citations
A method for supplying gas
CN111692520B
Hydrogen supplying station and its control method
JP2004116544A
Pressure cycle management in compressed gas dispensation system
JP2013002635A
Fuel gas distribution method
JP2019128038A
Hydrogen supply system, hydrogen station and hydrogen demand-supply management method
JP2021134863A