Device for pre-operational inspection of die casting machine, and method for pre-operational inspection of die casting machine

The pre-start inspection device for die-casting machines automates the evaluation and judgment of inspection data to streamline the inspection process, reducing operator burden and ensuring consistent quality assessments, thereby enhancing operational reliability and maintenance planning.

WO2024219434A1PCT designated stage expired Publication Date: 2024-10-24UBE MASCH CORP LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2024/015307
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-04-19
Filing Date
2024-04-17
Publication Date
2024-10-24

AI Technical Summary

Technical Problem

Die-casting machines require comprehensive pre-start inspections to ensure stable operation and high-quality cast products, but these inspections are labor-intensive and prone to variations in judgment among workers.

Method used

A pre-start inspection device that calculates evaluation values from actual data and compares them to reference ranges to determine the condition of the die-casting machine, reducing operator burden by automating pass/fail judgments and predicting maintenance needs based on trends.

Benefits of technology

The device streamlines the inspection process, reduces operator workload, and minimizes variations in judgment, enabling more reliable and efficient maintenance planning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024015307_24102024_PF_FP_ABST
    Figure JP2024015307_24102024_PF_FP_ABST
Patent Text Reader

Abstract

A device for pre-operational inspection of a die casting machine, characterized by comprising: a calculation means for calculating an evaluation value from actual data indicating an actual state of the die casting machine; and a determination means, wherein the determination means has in advance a reference range of the evaluation value at the start of an operation, and determines whether the state of the die casting machine is good or bad on the basis of the result of a comparison between the reference range and the evaluation value calculated by the calculation means.
Need to check novelty before this filing date? Find Prior Art

Description

Die-casting machine pre-operation inspection device and die-casting machine pre-operation inspection method

[0001] The present disclosure relates to a pre-operation inspection device for a die-casting machine and a pre-operation inspection method for a die-casting machine.

[0002] The process of producing castings by heating and melting metal such as aluminum alloy adjusted to a specified composition and injecting it into a mold cavity is called casting operation, and the equipment used for casting operation is called a die-casting machine. During this casting operation, it is desirable to achieve stable operation of the die-casting machine and a steady supply of high-quality castings. To achieve this, it is necessary to properly perform a pre-operational inspection of the die-casting machine before starting the casting operation.

[0003] The scope of pre-operation inspections of this die-casting machine covers a wide range of components, including the casting mold that is clamped to form the mold cavity, the casting machine that includes a clamping unit that mounts the casting mold and performs the clamping operation, and an injection unit that injects molten metal into the mold cavity, and peripheral equipment attached to the casting mold and casting machine. Peripheral equipment includes, for example, a molten metal holding furnace that maintains the molten metal at a predetermined temperature, a water supply unit that measures a predetermined amount of molten metal from the molten metal holding furnace and supplies it to the injection unit, a spraying unit that sprays mold release agents and lubricants onto the mold cavity of the casting mold and the injection sleeve of the injection unit, and a robotic device that removes the casting from the mold cavity. Robotic devices also include a transfer robot that transports the removed casting to a subsequent process, an insert robot that sets an insert member into the mold cavity, and an inspection robot that inspects the quality of the casting. In addition, specifications for vacuum suction inside the mold cavity or injection sleeve include a vacuum suction device, a hydraulic drive unit or electric drive unit that controls the operation of the injection unit and mold clamping unit, a temperature control unit that controls the temperature of the casting mold and injection sleeve, etc., a compressed air supply unit, an emergency stop device, etc.

[0004] The following Patent Documents 1 and 2 disclose techniques relating to the inspection of die-casting machines.

[0005] JP 11-58479 A JP 2012-35553 A

[0006] The present disclosure provides a pre-work inspection device for a die-casting machine and a pre-work inspection method for a die-casting machine that can reduce the burden on workers who perform pre-work inspections.

[0007] [1] A pre-start-up inspection device for a die-casting machine, comprising: a calculation means for calculating an evaluation value from actual data showing the actual state of the die-casting machine; and a judgment means, wherein the judgment means has a reference range for the evaluation value at the time of start-up, and judges whether the state of the die-casting machine is good or bad based on the result of comparing this reference range with the evaluation value calculated by the calculation means.

[0008] [2] The pre-start-of-work inspection device for a die-casting machine described in [1] above further comprises an acquisition means for acquiring actual data corresponding to each inspection item included in at least a portion of the plurality of inspection items, wherein the calculation means calculates the evaluation value from the actual data for each inspection item, and the determination means determines whether each inspection item is pass or fail based on a comparison result between the reference range and the evaluation value for each inspection item.

[0009] [3] The pre-operation inspection device for a die-casting machine described in [2] above, further comprising an inspection guide means for displaying on a monitor a list of the plurality of inspection items and whether or not each inspection item has been carried out.

[0010] [4] In the pre-start inspection device for a die-casting machine described in [2] or [3] above, the acquisition means acquires, for each inspection item, image data obtained by capturing an image of a part of the die-casting machine related to the inspection item, or sound data generated from the part, as the actual data.

[0011] [5] The pre-start inspection device for a die casting machine according to any one of [1] to [4] above, further comprising a judgment result output means for outputting the judgment result by the judgment means.

[0012] [6] The pre-start-of-work inspection device for a die-casting machine described in any one of [1] to [5] above, further comprising: a prediction means for predicting a future trend in the evaluation value from the trend up to the present of the evaluation value calculated by the calculation means; and a recommended timing output means for outputting a recommended timing for maintenance based on the trend predicted by the prediction means and the reference range when the trend predicted by the prediction means satisfies a predetermined condition.

[0013] [7] A pre-start-of-work inspection method for a die-casting machine executed by a pre-start-of-work inspection device, characterized in that the calculation means of the pre-start-of-work inspection device includes a calculation step in which an evaluation value is calculated from actual data indicating the actual state of the die-casting machine, and a judgment step, and in the judgment step, a judgment means of the pre-start-of-work inspection device judges whether the state of the die-casting machine is good or bad based on the result of comparing the evaluation value calculated in the calculation step with a reference range.

[0014] According to the present disclosure, a pre-work inspection device for a die-casting machine and a pre-work inspection method for a die-casting machine are provided that can reduce the burden on workers who perform pre-work inspections.

[0015] FIG. 1 is a schematic diagram illustrating a pre-work inspection device and a die-casting machine. FIG. 2 is a block diagram illustrating the functional configuration of the pre-work inspection device. FIG. 3 is a block diagram illustrating the hardware configuration of the pre-work inspection device. FIG. 4 is a flow diagram showing an example of a pre-work inspection using the pre-work inspection device 50. FIGS. 5(a) and 5(b) are schematic diagrams illustrating display screens during a pre-work inspection. FIGS. 6(a) and 6(b) are schematic diagrams illustrating display screens during a pre-work inspection. FIGS. 7(a) and 7(b) are schematic diagrams illustrating display screens during a pre-work inspection. FIGS. 8(a) and 8(b) are schematic diagrams illustrating display screens during a pre-work inspection. FIGS. 9(a) and 9(b) are schematic diagrams illustrating display screens during a pre-work inspection. FIGS. 10(a) and 10(b) are graphs illustrating the relationship between the predicted transition of the evaluation value and the recommended timing of maintenance. Fig. 11 is a flowchart illustrating a series of processes executed by the pre-work inspection device. Figs. 12(a) and 12(b) are schematic diagrams illustrating display screens when checking the results of pre-work inspections. Fig. 13 is a flowchart illustrating a series of processes executed by the pre-work inspection device.

[0016] An embodiment for carrying out the contents of the present disclosure will be described below with reference to the drawings. Note that the following embodiment is an example for explaining the present disclosure and is not intended to limit the present disclosure to the following content. Furthermore, not all of the combinations of features described in the embodiment are necessarily essential to solving the problems related to the present disclosure. Furthermore, in this embodiment, the scales and dimensions of each component may be exaggerated, or some components may be omitted.

[0017] A pre-operation inspection device according to one embodiment and a die-casting machine to be inspected using the pre-operation inspection device will be described with reference to Fig. 1. The pre-operation inspection device 50 (pre-operation inspection device for a die-casting machine) shown in Fig. 1 is a device for performing a pre-operation inspection of a die-casting machine 1. "Before starting work" refers to before the start of a casting operation in which molten metal is injected and filled into a mold cavity to produce a casting to be shipped as a product. The pre-operation inspection is performed, for example, once a day (every morning, in one example).

[0018] [Die Casting Machine] First, the die casting machine 1 will be described. The die casting machine 1 is a device that produces a casting by filling a mold with molten metal (hereinafter referred to as "molten metal") and molding it. The molten metal is obtained from, for example, an aluminum alloy. The die casting machine 1 includes, for example, a casting device 10, a casting mold 20, peripheral equipment 30, and a control device 40.

[0019] The casting apparatus 10 is an apparatus for obtaining a casting product by injecting and filling a mold cavity formed by a casting mold 20 with molten metal. The casting apparatus 10 includes, for example, an injection unit 11, a mold clamping unit 12, and a drive unit 13.

[0020] The injection unit 11 is a part that injects molten metal into the mold cavity of the casting mold 20. The injection unit 11 supplies a predetermined amount of molten metal into a cylindrical injection sleeve whose tip is connected to the mold cavity, and then presses the molten metal from the rear end of the injection sleeve with a plunger tip to inject and fill the mold cavity. The injection sleeve may be arranged horizontally, vertically, or at any angle between the horizontal and vertical directions. Furthermore, the injection is not limited to the injection of the molten metal in the injection sleeve by pressing the plunger tip into the mold cavity. For example, a sealed container may be filled with pressurized gas to pressurize the molten metal surface, and the molten metal may be injected and filled via a feed pipe connecting the mold cavity to the molten metal. Alternatively, a liquid transport pump or other transport means may be used instead of pressurized gas.

[0021] For stable production of high-quality castings, it is preferable to precisely control the pressure and speed of the molten metal pressed by the plunger tip under optimal conditions depending on the casting operation. The pressure applied by the plunger tip to the molten metal is referred to as the casting pressure, and the speed at which the molten metal is pressed is referred to as the injection speed. Controlling the pressing speed is referred to as injection filling control. The injection sleeve and plunger tip may be excessively heated by the high-temperature molten metal, resulting in thermal expansion or deformation, which may affect the operation of the plunger tip. To avoid this thermal effect, it is preferable to circulate a cooling medium through the injection sleeve and plunger tip to maintain an optimal temperature. The state of adhesion of molten metal residue or the state of application of lubricant, which may affect the injection filling control, as well as the circulation state or actual temperature state of the cooling medium, which may affect the thermal expansion and deformation of the plunger tip, may be checked during a pre-operation inspection. Alternatively, the vibration or acoustic state of the plunger tip during operation may be checked during a pre-operation inspection.

[0022] Furthermore, for example, in order to prevent oxidation of the molten metal and to prevent gas from being entrained in the mold cavity, the inside of the injection sleeve may be evacuated to maintain a suitable vacuum state. In this case, the pre-operation inspection may check for foreign matter in the vacuum suction path, the wear state of vacuum seal members, etc., and the actual vacuum state. As such, there are a wide variety of inspection items for the pre-operation inspection to ensure stable operation of the injection unit 11 and stable production of high-quality castings.

[0023] The mold clamping unit 12 performs mold clamping and mold opening operations while supporting the casting mold 20. The mold clamping and mold opening operations are referred to as mold opening and closing operations. A mold cavity is formed by the mold clamping operation, and a casting is removed from the mold cavity by an ejection operation after the mold opening operation. Any of the following may be selected: a configuration in which the mold opens and closes horizontally, a configuration in which the mold opens and closes vertically, a configuration in which the mold opens and closes using a combination of a linearly reciprocating drive means and multiple link mechanisms, or a configuration in which the mold opens and closes using a linearly reciprocating drive means.

[0024] To ensure stable production of high-quality castings through stable operation of the clamping unit 12, a wide range of inspection items may be checked during pre-operation inspections, similar to those for the injection unit 11. For example, the state of application of lubricant to sliding members, which greatly affect the mold opening / closing and ejection operations, the pressing force used to clamp the casting mold 20 and hold the mold cavity, vibrations during the mold opening / closing and ejection operations, and the parallelism of the clamping members supporting the casting mold 20 may be checked. The pressing force used to hold the mold cavity is called the clamping force.

[0025] The drive unit 13 is a drive source that controls the operations of the injection unit 11 and the mold clamping unit 12. The drive unit 13 may also have a function of driving the casting mold 20. In the schematic diagram of FIG. 1 , the drive unit 13 is connected to the injection unit 11, but the drive unit 13 may also be connected to at least one of the mold clamping unit 12 and the casting mold 20. A drive unit 13 may be provided for each of the injection unit 11, the mold clamping unit 12, and the casting mold 20. The drive unit 13 may be an electric drive device having a conversion means, such as a ball screw, that converts the rotational motion of an electric motor into linear motion. The drive unit 13 may be a hydraulic drive device using a hydraulic motor that performs rotational motion or a hydraulic cylinder that performs linear motion instead of an electric motor. The drive unit 13 may also be a hybrid drive device that combines an electric drive device and a hydraulic drive device.

[0026] For example, a hydraulic drive unit, which is widely used in casting operations, is often used as the drive unit 13. In this case, inspection items to be checked in the pre-operation inspection may include, for example, the condition of a hydraulic oil tank that stores hydraulic oil, the amount (referred to as oil volume) or temperature (referred to as oil temperature) of hydraulic oil in the hydraulic oil tank, the state of deterioration or contamination of the hydraulic oil, the state of a hydraulic pump that controls the discharge pressure and discharge rate of the hydraulic oil, the actual discharge pressure, discharge rate, and rotation state of a hydraulic motor that controls the rotational motion of the hydraulic pump, the state of a hydraulic circuit that connects the hydraulic pump with the injection unit and the mold clamping unit and controls the circulation of hydraulic oil, and the state of replenishment or replacement of hydraulic oil. For example, in a case where multiple accumulators (pressure accumulators) are provided and the injection speed and injection pressure of the injection filling control are controlled according to the casting operation, the charge pressure and charge amount of hydraulic oil to the accumulators may also be added to the inspection items in the pre-operation inspection. In this way, in order to ensure stable production of high-quality castings through stable operation of the drive unit 13, a wide range of inspection items may be checked before starting work, just as with the injection unit 11 and the mold clamping unit 12.

[0027] The casting mold 20 is a component that forms a mold cavity through the clamping operation of the clamping unit 12. Once the casting mold 20 has formed the mold cavity, high-temperature molten metal is injected and filled into the mold cavity through the injection unit 11. The molten metal then cools and solidifies within the mold cavity, and the cooled and solidified casting is removed from the mold cavity through the mold opening and ejection operations of the clamping unit 12. The temperature of the casting mold 20 increases due to the high-temperature molten metal. Furthermore, during the injection and solidification of the molten metal, it is desirable to maintain the casting mold 20 at an appropriate temperature, for example, by circulating a cooling medium. To prevent the high-temperature molten metal from burning into the mold cavity, a release agent spraying process may be performed before the molten metal is injected and filled, in which a release agent or the like is uniformly applied toward the mold cavity. To prevent oxidation of the molten metal or the entrapment of gases or the like, the mold cavity may be evacuated.

[0028] In the pre-operation inspection, inspection items may include, for example, the connection and circulation status of the cooling medium, the temperature control status of the casting mold 20, the application and remaining status of the mold release agent in the mold cavity, the status of foreign matter adhering to the mold cavity, the remaining status of the cast product in the mold, the status of the mold cavity, and the status of vacuum suction. In this way, similar to the casting apparatus 10, a wide range of inspection items may be checked in the pre-operation inspection in order to ensure stable operation of the casting mold 20 and stable production of high-quality cast products.

[0029] The peripheral equipment 30 includes various devices arranged around the casting device 10 and the casting mold 20. In the present disclosure, the peripheral equipment 30 is also included in the die-casting machine 1. The peripheral equipment 30 includes, for example, a lubricant supply device 31, a robot device 32, a spray device 33, a molten metal supply device 34, a molten metal holding furnace 35, a cooling medium circulator 36, an air supply device 37, and an emergency stop device 38. Note that FIG. 1 shows each device of the peripheral equipment 30 diagrammatically, and these devices are arranged in appropriate positions depending on the casting operation. In addition to the above-described devices, the peripheral equipment 30 may also include a vacuum suction device that applies vacuum to the mold cavity or injection sleeve, an automatic mold exchange device that automatically attaches and detaches the casting mold 20 to the mold clamping unit 12, an inert gas supply device that supplies an inert gas to prevent oxidation of the molten metal, a quality control device that controls the quality of the casting product, and an operation monitoring device that monitors the operating status of the casting operation. As with the casting device 10 and the casting mold 20, a wide range of inspection items may be checked before starting work for the peripheral equipment 30 to ensure stable operation of the peripheral equipment 30 and the stable production of high-quality castings.

[0030] The lubricant supply device 31 periodically applies an appropriate amount of lubricant to the injection unit 11 and mold clamping unit 12 of the casting device 10, or to the casting mold 20. For this purpose, the following may be checked as inspection items in a pre-work inspection: the type of lubricant, the amount of lubricant stored, the amount and state of application of the lubricant, the degree of lubricant deterioration and foreign matter contamination, the leakage or clogging state of the lubricant supply line, and the replenishment or replacement state of the lubricant.

[0031] The robot device 32 may include an unloading robot that grasps the casting with a chuck and removes it from the mold cavity following the mold opening and ejection operations, and a transport robot that transports the removed casting to a subsequent process such as a deburring process or a heat treatment process. The robot device 32 may also include an insert robot that sets an insert member or core part, etc., in a predetermined position in the mold cavity before injection and filling with molten metal, an inspection robot that performs a quality inspection of the removed casting, or a monitoring robot that monitors the casting operation. For example, the shape of the chuck, the position at which the chuck grasps the casting, the motion trajectory for removing the casting, and the motion trajectory and coordination status of each robot device may be checked as inspection items in a pre-work inspection.

[0032] The spray device 33 sprays either a release agent or a lubricant, depending on the casting operation. The peripheral equipment 30 may include multiple spray devices 33 each spraying a different material. For example, a release agent is used to prevent the mold cavity from seizing due to high-temperature molten metal. A lubricant is used to maintain the lubricity of sliding members. Alternatively, a spray device 33 that sprays compressed air without using a release agent or lubricant may be provided. This compressed air spray (hereinafter referred to as "air blow") may be used, for example, in a cleaning process to remove excess release agent and molten metal residue remaining in the mold cavity, or to remove residue adhering to the plunger tip or injection sleeve. This air blow may also be used to clarify the view when a monitoring robot, etc., is observing the condition of the mold cavity or the casting. For example, the following may be inspected in the pre-work inspection: identification of the release agent or lubricant; the spray trajectory and amount of the release agent or lubricant; the adhesion state of the release agent and lubricant; the state of the air blow; the state of leakage or clogging of the release agent and lubricant; and the state of replenishing or replacing the release agent and lubricant.

[0033] The melt supply device 34 supplies molten metal from the molten metal holding furnace 35 into the injection sleeve of the injection unit 11. The supply of molten metal is referred to as melt supply. For example, a part of the robot device 32 may be incorporated into the melt supply device 34, and the molten metal may be supplied by scooping molten metal from the molten metal holding furnace 35 with a ladle, which is a bowl-shaped heat-resistant container. Alternatively, the molten metal in the molten metal holding furnace 35 may be connected to the injection sleeve by a melt supply pipe, and the molten metal may be supplied via the melt supply pipe. Alternatively, the molten metal holding furnace 35 may be tilted to supply molten metal directly into the injection sleeve. The method of supplying molten metal may be selected depending on the casting operation. In any melt supply method, the amount of molten metal supplied (the amount of molten metal supplied) may be controlled depending on the type of molten metal, the volume of the mold cavity, the quality of the casting, and the like. The amount of molten metal supplied may be measured using a melt level detection rod or the like. For example, the adjustment of the hot water amount measuring means, the capacity of the ladle, the cleaning state of the ladle and hot water supply pipe, and the operating trajectory and operating time of the hot water supply device 34 may be checked as inspection items during the pre-work inspection.

[0034] The molten metal holding furnace 35 melts a metal material, such as an aluminum alloy, adjusted to a predetermined composition and maintains the molten metal material (i.e., molten metal) at a predetermined temperature. The molten metal holding furnace 35 may also be used to remove oxides and impurities or adjust the composition of the molten metal. A separate melting furnace may be provided to melt the metal material, and the molten metal may be supplied from this melting furnace to the molten metal holding furnace 35. The supply of molten metal from the melting furnace to the molten metal holding furnace 35 is referred to as molten metal replenishment. To prevent oxidation of the molten metal, an inert gas supply means may be provided to supply an inert gas to the melting furnace and the molten metal holding furnace 35. For example, the following may be inspected during the pre-operation inspection: the temperature of the molten metal; adjustment of a molten metal level gauge or other molten metal amount measuring means; confirmation of the floating state of oxides or impurities (referred to as the molten metal surface state); the state of the molten metal replenishment; and the state of the inert gas supply means.

[0035] The cooling medium circulator 36 circulates the cooling medium toward the casting mold 20, the injection sleeve of the injection unit 11, the plunger tip of the injection unit 11, etc., to adjust the temperature state of the components through which the refrigerant is circulated. For example, the following inspection items may be checked in the pre-work inspection: leakage and clogging of the cooling medium circulation circuit, the connection state of the circulation circuit, the amount of cooling medium circulated, the amount of cooling medium stored, deterioration and contamination of the cooling medium, and the replenishment or replacement state of the cooling medium.

[0036] The air supply device 37 supplies compressed air to devices in the peripheral equipment 30 that require compressed air, such as the spray device 33. If the casting device 10 or the casting mold 20 requires compressed air, the air supply device 37 may supply compressed air to the casting device 10 or the casting mold 20. For example, the amount and pressure of the compressed air supply, the amount of compressed air stored, the state of air leaks or air blockages in the compressed air supply line, the state of moisture contained in the compressed air and the state of water drainage, and the state of the compressed air storage tank may be checked as inspection items in the pre-work inspection.

[0037] The emergency stop device 38 is used when an abnormality occurs in the die-casting machine 1 or when a symptom of an abnormality is detected, and the die-casting machine 1 needs to be stopped immediately (i.e., an emergency stop). The emergency stop device 38 may be provided in each of the casting machine 10 and the peripheral equipment 30. An inspector or a casting operator operating the casting operation manually operates the emergency stop device 38. When an abnormality is detected using a monitoring device or the like, at least a portion of the die-casting machine 1 may automatically perform an emergency stop. The range of equipment to be stopped in an emergency is determined by the emergency stop device 38 provided in each of the die-casting machines. Therefore, for example, whether the emergency stop device 38 operates correctly, the range of the emergency stop, and the recovery procedure after the emergency stop may be checked as inspection items during a pre-work inspection.

[0038] The control device 40 controls at least the casting device 10 and the peripheral equipment 30. The control device 40 includes, for example, a casting control unit 41 and a peripheral control unit 42. The casting control unit 41 controls the casting operation of the casting device 10. The peripheral control unit 42 controls each device included in the peripheral equipment 30. The casting control unit 41 and the peripheral control unit 42 may be communicatively connected to each other. The casting control unit 41 may issue control commands necessary for the casting operation to the peripheral control unit 42, and the peripheral control unit 42 may control the peripheral equipment 30 based on the issued control commands. Information indicating the operating status of the peripheral equipment 30 may be transferred from the peripheral control unit 42 to the casting control unit 41, and the casting control unit 41 may perform overall control of the casting operation of the die casting machine 1. In FIG. 1 , the control device 40 is shown separate from the casting device 10 and the peripheral equipment 30, but the control device 40 may be integrated with the casting device 10. Alternatively, the casting control unit 41 may be integrated with the casting device 10, and the peripheral control unit 42 may be integrated with the peripheral equipment 30. In this way, the casting control unit 41 and the peripheral control unit 42 may be individually arranged in each facility.

[0039] High-quality castings can be stably produced by accurately interlocking the casting device 10, the casting mold 20, and the peripheral equipment 30 during casting operations. The emergency stop device 38 and the control device 40 are also interlocked. Therefore, the operating status of the control device 40, the communication status between the casting control unit 41 and the peripheral control unit 42, the communication status between the peripheral control unit 42 and each piece of peripheral equipment 30, and the interlocking status between the emergency stop device 38 and the control device 40 may be checked as inspection items during a pre-work inspection.

[0040] [Pre-Work Inspection Device] Next, the pre-work inspection device 50 will be described. The pre-work inspection device 50 is a device that executes processing for a pre-work inspection of the die-casting machine 1 together with operation by an inspector (user). The inspector performs a pre-work inspection using the pre-work inspection device 50. The pre-work inspection device 50 is configured by one or more computers. The one or more computers that make up the pre-work inspection device 50 include a computer that can be carried by the inspector. The pre-work inspection device 50 may be configured by a single computer, which may be a laptop, tablet terminal, or smartphone. The pre-work inspection device 50 may be communicably connected to the control device 40 of the die-casting machine 1.

[0041] The pre-work inspection device 50 includes, for example, a computer main body 52, an input device 53, an output device 54, a camera 55, and a microphone 56. The computer main body 52 is a device (the main body of the computer) that executes the main functions of the computer that constitutes the pre-work inspection device 50. The input device 53 may be any device that allows a user to input desired information into the computer main body 52, and specific examples thereof include operation interfaces such as a keypad, a mouse, and an operation controller.

[0042] The output device 54 is a device for notifying the user of information output from the computer main body 52. ​​The output device 54 is, for example, a monitor (hereinafter referred to as "monitor 54a") that displays the information output from the computer main body 52. ​​The monitor 54a may be any device capable of displaying graphics, a specific example of which is a liquid crystal panel. The input device 53 and the monitor 54a may be integrated as a touch panel, or the computer main body 52, the input device 53, and the monitor 54a may be integrated as in a tablet terminal.

[0043] The camera 55 is a device that forms an image of light obtained within its field of view to generate image information. The camera 55 is, for example, a digital camera. The microphone 56 is a device that detects sounds generated in its surroundings and generates sound data. The sound data is a waveform that represents changes in signal strength over time. Below, the pre-work inspection device 50 will be described in detail using an example in which the pre-work inspection device 50 is a tablet terminal with a built-in camera 55 and microphone 56.

[0044] The plurality of inspection items to be inspected using the pre-work inspection device 50 are determined in advance. The plurality of inspection items may include two or more items for which the pre-work inspection device 50 judges whether the items are good or bad based on the data provided, and two or more items for which an inspector visually judges whether the items are good or bad. For the two or more inspection items for which an inspector visually judges whether the items are good or bad, the judgment results may be input to the pre-work inspection device 50. The plurality of inspection items may include two or more items to be performed before powering on the die-casting machine 1, and two or more items to be performed after powering on the die-casting machine 1 and before the start of casting operation of the die-casting machine 1.

[0045] 2 schematically shows an example of the functional configuration of the pre-work inspection device 50. The computer main unit 52 of the pre-work inspection device 50 has, as functional configurations (hereinafter referred to as "functional blocks"), an input information acquisition unit 62, an inspection guide unit 64, an actual data acquisition unit 66, an evaluation value calculation unit 68, an evaluation value storage unit 70, a pass / fail determination unit 72, a first output unit 74, a transition prediction unit 76, and a second output unit 78. The processing executed by each of these functional blocks corresponds to the processing executed by the computer main unit 52.

[0046] The input information acquiring unit 62 acquires user input via the input device 53. The input information acquiring unit 62 may acquire user input based on a user operation (e.g., tapping) on ​​a screen displayed on the monitor 54a. The inspection guide unit 64 (inspection guide means) displays a list of multiple inspection items and whether or not each inspection item has been performed on the monitor 54a. In addition to displaying the list of multiple inspection items and whether or not each inspection item has been performed, the inspection guide unit 64 may also display various information on the monitor 54a to help the inspector perform inspection work smoothly.

[0047] The actual data acquisition unit 66 (acquisition means) acquires actual data indicating the actual state of the die-casting machine 1. In this disclosure, the "actual state" in the actual data refers to a state that can be recognized by the inspector himself, and the actual data does not include signals detected by various sensors built into the die-casting machine 1. A state that can be recognized by the inspector himself is, for example, a state that can be recognized by the inspector visually or a state that can be recognized by the inspector auditory sense (ears). The actual data acquisition unit 66 acquires actual data corresponding to each inspection item included in at least a portion (two or more inspection items) of the multiple inspection items. Note that there may be one or more inspection items as needed.

[0048] For each inspection item, the actual data acquisition unit 66 may acquire image data obtained by capturing an image of a part of the die-casting machine 1 related to the inspection item, or sound data generated from the part, as actual data. The image data may be either still image data or video data. The actual data acquisition unit 66 may acquire image data from the camera 55 for an inspection item for which image data is to be acquired. The actual data acquisition unit 66 may acquire sound data from the microphone 56 for an inspection item for which sound data is to be acquired. When the inspection item is a physical quantity such as oil volume, gas pressure, air pressure, or temperature, the part related to the inspection item is a gauge (instrument) that displays the measured value of the physical quantity. When the inspection item is sound, the part related to the inspection item is a component or device that is the source of the sound.

[0049] The evaluation value calculation unit 68 (calculation means) calculates an evaluation value from the actual data acquired by the actual data acquisition unit 66. The evaluation value calculation unit 68 may calculate an evaluation value from the actual data for each inspection item. A method for calculating an evaluation value from the actual data for each inspection item is predetermined. In one example, when the inspection item is a physical quantity such as oil amount, gas pressure, air pressure, or temperature, the evaluation value calculation unit 68 reads a current measurement value of the physical quantity from image data using image processing and calculates the current measurement value as the evaluation value. When the inspection item is sound, the evaluation value calculation unit 68 may read a feature value from sound data and calculate the feature value as the evaluation value. The feature value in the sound data is, for example, a statistical quantity such as the maximum or average amplitude of the sound data (waveform data representing time changes in signal strength). Alternatively, the feature value in the sound data may be a frequency that becomes a peak in a spectrum obtained by frequency-converting the sound data.

[0050] The evaluation value storage unit 70 stores the evaluation values ​​calculated by the evaluation value calculation unit 68. The evaluation value storage unit 70 stores, for example, an evaluation value for each inspection item. The evaluation value storage unit 70 stores the evaluation values, and the evaluation values ​​are accumulated as the pre-work inspection is repeated.

[0051] The pass / fail determination unit 72 (determination means) has a standard range of evaluation values ​​in advance, and determines the pass / fail status of the die-casting machine 1 based on the comparison result between this standard range and the evaluation value calculated by the evaluation value calculation unit 68. The pass / fail determination means determining whether the die-casting machine 1 is in a state in which it is acceptable to perform casting operations to obtain actual cast products. For example, the pass / fail determination unit 72 compares the standard range with the evaluation value calculated by the evaluation value calculation unit 68 for each inspection item, and determines the pass / fail status of the inspection item based on the comparison result. The standard range is predetermined for each inspection item. The pass / fail determination unit 72 may determine that an inspection item is pass if the evaluation value is within the standard range, and may determine that an inspection item is fail if the evaluation value is not within the standard range. Hereinafter, a determination that an inspection item is pass will be referred to as a "pass determination," and a determination that an inspection item is fail will be referred to as a "fail determination."

[0052] The standard range may be defined by a lower limit and an upper limit. The standard range may be defined as a range equal to or greater than a predetermined value, in which case comparison with the standard range may be performed based on whether the evaluation value is equal to or greater than the predetermined value. The standard range may be defined as a range equal to or less than a predetermined value, in which case comparison with the standard range may be performed based on whether the evaluation value is equal to or less than the predetermined value.

[0053] The first output unit 74 (judgment result output means) outputs the judgment result by the pass / fail judgment unit 72. The first output unit 74 displays the judgment result by the pass / fail judgment unit 72 on the monitor 54a, for example. For each inspection item, when the judgment result by the pass / fail judgment unit 72 is a pass judgment, the first output unit 74 may display information indicating that the judgment result is a pass judgment on the monitor 54a. For a certain inspection item, when the judgment result by the pass / fail judgment unit 72 is a fail judgment, the first output unit 74 may display information indicating that the judgment result is a fail judgment on the monitor 54a. As information indicating that the judgment result is a fail judgment, the first output unit 74 may display information indicating that maintenance is required for that inspection item on the monitor 54a.

[0054] The transition prediction unit 76 (prediction means) predicts the future transition of the evaluation value from the transition up to the present of the evaluation value calculated by the evaluation value calculation unit 68. When the future transition predicted by the transition prediction unit 76 satisfies a predetermined condition, the second output unit 78 (recommended timing output means) outputs the recommended timing for maintenance based on the future transition and the above-mentioned standard range. The functions of the transition prediction unit 76 and the second output unit 78 will be described in detail later.

[0055] 3 schematically shows the hardware configuration of the pre-work inspection device 50. The computer main body 52 of the pre-work inspection device 50 includes, for example, a circuit 91. The circuit 91 has a processor 92, a memory 93, a storage 94, an input / output port 95, and a communication port 96. The storage 94 is configured with one or more non-volatile memory devices such as a flash memory or a hard disk. The storage 94 stores programs for configuring each of the above-mentioned functional blocks.

[0056] The memory 93 is composed of one or more volatile memory devices such as a random access memory. The memory 93 temporarily stores programs loaded from the storage 94. The processor 92 is composed of one or more arithmetic devices such as a CPU (Central Processing Unit) or a GPU (Graphics Processing Unit). The processor 92 configures the above-mentioned functional blocks by executing the programs loaded into the memory 93. The results of calculations by the processor 92 are temporarily stored in the memory 93. The input / output port 95 inputs and outputs information to and from the input device 53, output device 54, camera 55, microphone 56, etc. in response to a request from the processor 92. The communication port 96 communicates with the control device 40 via a wired, wireless, or network line, etc.

[0057] The hardware configuration of the pre-work inspection device 50 is not necessarily limited to one in which each functional block is configured by a program. For example, each functional block of the pre-work inspection device 50 may be configured by a dedicated logic circuit or an ASIC (Application Specific Integrated Circuit) that integrates such dedicated logic circuits. The pre-work inspection device 50 may also be configured by multiple computers connected to each other so that they can communicate with each other. For example, the quality determination unit 72 may be a functional block included in a computer that configures the control device 40.

[0058] [Pre-Work Inspection Method] Next, an example of a pre-work inspection method executed by the above-described pre-work inspection device 50 will be described. Fig. 4 illustrates a process flow of a pre-work inspection performed by an inspector using the pre-work inspection device 50. This process flow is executed before the die-casting machine 1 to be inspected starts casting operation.

[0059] First, step S01 is executed. In step S01, for example, an inspector starts the pre-work inspection device 50 and then inputs user input indicating an instruction to start an inspection into the pre-work inspection device 50. FIG. 5A illustrates an example of a screen displayed on the monitor 54a immediately after the pre-work inspection device 50 is started. In one example, in response to the start of the pre-work inspection device 50, the inspection guide unit 64 displays a first instruction button 102 and a second instruction button 104 on the monitor 54a. When the first instruction button 102 is pressed, the input information acquisition unit 62 accepts user input indicating an instruction to start a pre-work inspection. Details of the second instruction button 104 will be described later.

[0060] In response to step S01, the pre-work inspection device 50 executes step S02. In step S02, for example, the inspection guide unit 64 displays a list of inspection items and whether each inspection item has been performed on the monitor 54a. Displaying whether each inspection item has been performed means displaying, for each inspection item, information indicating whether the inspection related to that item has been performed.

[0061] 5B illustrates an example of a screen on the monitor 54a that displays a list of inspection items and whether each inspection item has been performed. As shown in FIG. 5B, the inspection guide unit 64 may display title information 106, a plurality of item selection buttons 112, and a plurality of pieces of execution result information 114 on the monitor 54a. One item selection button 112 and one piece of execution result information 114 are assigned to each inspection item. When a large number of inspection items are set, the screen may be able to slide or scroll up and down or left and right by a user operation, for example.

[0062] The title information 106 is information indicating the content (title) currently displayed on the screen in text. When a list of inspection items is displayed, for example, the text "Inspection Item List" is displayed. Each of the multiple item selection buttons 112 includes the name of an inspection item and is a button selectable by the user. Each of the multiple execution result information 114 is information indicating whether the inspection item identified by the corresponding item selection button 112 has been performed. The inspection guide unit 64 may display the execution result information 114 on the monitor 54a so that the display mode when the corresponding inspection item has been performed differs from the display mode when the corresponding inspection item has not been performed. In one example, when the corresponding inspection item has not been performed, a white square is displayed as the execution result information 114. When the corresponding inspection item has already been performed, a square with a mark or the like inside, or a square with a pattern or color is displayed as the execution result information 114.

[0063] Next, step S03 is executed. In step S03, for example, the inspector selects an item to be inspected from among a plurality of inspection items. The inspector may press an item selection button 112 corresponding to the item to be inspected from a plurality of item selection buttons 112 representing a list of a plurality of inspection items on the monitor 54a.

[0064] In response to step S03, the pre-work inspection device 50 executes step S04. In step S04, for example, the inspection guide unit 64 displays an area map corresponding to the inspection item selected in step S03 on the monitor 54a. As shown in FIG. 6A, in step S04, the inspection guide unit 64 may display title information 106 and an area map 120 on the monitor 54a. The inspection guide unit 64 switches the characters in the title information 106 in response to the selection result in step S03.

[0065] The area map 120 is a map that shows, for example, the layout of the die-casting machine 1 in a plan view (viewed vertically from above). The inspection guide unit 64 may display information indicating the location of the area related to the selected inspection item (hereinafter referred to as the "inspection target area IS") on the area map 120. By displaying the inspection target area IS on the area map 120, the inspector can easily move the inspection target area IS to a position where it can be inspected. This reduces the possibility of an inspection error and shortens the inspection time.

[0066] After the inspector moves the inspection target area IS to a position where it can be inspected, the pre-work inspection device 50 executes step S05. For example, after the inspector moves to the above-mentioned position, the inspector inputs an instruction to activate the camera 55 into the computer main body 52, thereby executing step S04. Alternatively, the inspector may move to the above-mentioned position and point the camera 55 toward the inspection target area IS, which causes the computer main body 52 to automatically execute step S05. In step S05, for example, the inspection guide unit 64 displays a guide on the monitor 54a to smoothly acquire actual data corresponding to the selected inspection item.

[0067] In one example, as shown in FIG. 6( b), the inspection guide unit 64 switches from displaying the area map 120 to displaying a preview screen 122 captured by the camera 55. The inspector aims the camera 55 at the inspection target area IS so that the inspection target area IS and the two-dimensional code CO associated with the inspection target area IS are displayed on the preview screen 122. In the example shown in FIG. 6( b), the inspection target area IS for which the inspection item is the hydraulic oil level is labeled "IS1." A two-dimensional code is, for example, a code having a structure in which squares or dots called cells are arranged in a grid pattern. When the inspection target area IS is included in the preview screen 122 and the inspector issues a user instruction to read the code, the inspection guide unit 64 reads the two-dimensional code. The inspection guide unit 64 may confirm the consistency of the inspection target area IS based on information obtained by reading the two-dimensional code.

[0068] If the two-dimensional code is read and consistency is not confirmed, the inspection guide unit 64 may, for example, display a message on the monitor 54a indicating that the inspection items and the inspection target area IS are not consistent. In response to the message, the inspector may reselect the inspection target area IS. Alternatively, if the two-dimensional code CO is dirty or damaged, the inspector may perform maintenance such as cleaning or re-covering the two-dimensional code CO, or may report this to the manager or other person in charge of managing the die-casting machine 1. In this way, by reading the two-dimensional code CO and confirming consistency, inspection errors can be reliably avoided and highly accurate pre-work inspections can be performed.

[0069] If the two-dimensional code is read and consistency is confirmed, the inspection guide unit 64 displays on the monitor 54a a screen tailored to the means for acquiring actual data corresponding to the currently selected inspection item. If the inspection item is hydraulic oil level, for example, image data obtained by photography is acquired as the actual data. In this case, the inspection guide unit 64 displays a preview screen 122 and an execution instruction button 124 on the monitor 54a.

[0070] The inspection guide unit 64 may display an image on the monitor 54a to guide the user in obtaining more appropriate actual data. The inspection guide unit 64 may display a standard image 128 corresponding to the inspection target area IS1 at a predetermined position within the preview screen 122. The standard image 128 may have a shape corresponding to the inspection target area IS1 and may be displayed as a watermark so that the background can be seen. The standard image 128 may be registered in advance in the computer main unit 52 according to the inspection item (inspection target area IS).

[0071] The execution instruction button 124 is a button for issuing an instruction to execute data acquisition. When the execution instruction button 124 is pressed by the inspector, the actual data acquisition unit 66 executes acquisition of actual data. In the example shown in FIG. 7A , when the execution instruction button 124 is pressed by the inspector, the actual data acquisition unit 66 executes image capture by the camera 55. As a result, image data within the field of view corresponding to the preview screen 122 is acquired as actual data.

[0072] In one example, the inspector adjusts one or more of his / her own position, the position and posture of the camera 55, and the zoom of the camera 55 so that the inspection target area IS1 in the preview screen 122 is superimposed on the standard image 128. Then, the inspector presses the execution instruction button 124 with the inspection target area IS1 in the preview screen 122 superimposed on the standard image 128. In this way, by displaying the standard image 128 in the preview screen 122, image data suitable for the inspection can be more reliably obtained. Note that the inspection guide unit 64 may display a shooting guide image, such as a frame that indicates the ideal position of the inspection target area IS1 in the preview screen 122, instead of the standard image 128.

[0073] Instead of or in addition to displaying the standard image 128 within the preview screen 122, the inspection guide unit 64 may acquire image data obtained by photographing the inspection target area IS1, and then display the image based on the acquired image data and the standard image 128 side by side on the monitor 54a. By displaying these two images side by side, the inspector can visually check whether the acquired image data is suitable for inspection before making a pass / fail judgment.

[0074] Next, the pre-work inspection device 50 executes step S08. The pre-work inspection device 50 may subsequently execute step S08 in response to completion of execution of step S07. Alternatively, the inspection guide unit 64 may display an execution instruction button 126 on the monitor 54a, as shown in FIG. 7A. The execution instruction button 126 is a button for instructing the start of a pass / fail judgment based on the acquired actual data. After step S07, the pre-work inspection device 50 may execute step S08 in response to the inspector pressing the execution instruction button 126.

[0075] In step S08, for example, the evaluation value calculation unit 68 calculates an evaluation value from the actual data acquired in step S07. When the inspection target is a physical quantity such as the amount of working oil, the evaluation value calculation unit 68 reads a current measurement value of the physical quantity from the image data acquired in step S07 by image processing, and calculates the current measurement value as the evaluation value. The current measurement value may be the value indicated on a scale of an instrument (gauge) included in the image acquired by capturing the image in step S07. The evaluation value calculation unit 68 may read the current measurement value by any image processing method.

[0076] In step S08, the evaluation value storage unit 70 may save (store) the evaluation value calculated by the evaluation value calculation unit 68. The evaluation value storage unit 70 may store the evaluation value calculated by the evaluation value calculation unit 68 in association with the inspection item. The evaluation value storage unit 70 may store the evaluation value calculated by the evaluation value calculation unit 68 in association with information indicating the time (e.g., date) when the inspection was performed.

[0077] Next, the pre-work inspection device 50 executes step S09. In step S09, for example, the pass / fail determination unit 72 determines whether the selected inspection item is pass / fail based on a comparison result between the evaluation value obtained in step S08 and a standard range corresponding to the selected inspection item. In one example, if the evaluation value obtained in step S08 is within the standard range, the pass / fail determination unit 72 determines that the inspection result for the selected inspection item indicates a state in which there is no problem even if the casting operation is performed (i.e., a pass / fail determination). If the evaluation value obtained in step S08 is not within the standard range, the pass / fail determination unit 72 determines that the inspection result for the selected inspection item indicates a state in which there is a high possibility of a problem occurring if the casting operation is performed (i.e., a fail determination). Below, a case in which the pass / fail determination result in step S09 indicates a state in which there is no problem even if the casting operation is performed will first be described.

[0078] Next, the pre-work inspection device 50 executes step S10. In step S10, for example, the first output unit 74 displays the list of inspection items again on the monitor 54a. At this time, the list of inspection items is displayed in a state in which the display mode of the execution result information 114 corresponding to the selected inspection item has changed from the display mode before the inspection was performed. In addition to the execution result information 114, the list of inspection items may also be displayed in a state in which the display mode of the item selection buttons 112 has changed from the display mode before the inspection was performed.

[0079] By changing the display mode of the execution result information 114 before and after the inspection, the inspector can easily grasp which inspection items have already been inspected and which inspection items have not yet been inspected. The first output unit 74 may change the display mode of the execution result information 114 and display a list of the inspection items on the monitor 54a only when the result of the pass / fail determination indicates that there is no problem in carrying out the casting operation. In this case, changing the display mode of the execution result information 114 corresponds to displaying the result of the pass / fail determination (the determination that there is no problem in carrying out the casting operation).

[0080] Until inspection of all inspection items is completed, the series of steps S03 to S10 are repeated for all inspection items for which actual data is acquired and a pass / fail judgment is made. Here, a specific example will be described in which "pump motor sound" is selected as an inspection item. The pump to be inspected IS may be a hydraulic pump that adjusts the discharge pressure and discharge amount of hydraulic oil, and the motor sound may be sound generated from the motor inside the hydraulic pump.

[0081] In FIG. 8( a), when the inspection item is the pump motor sound, the pump, which is the inspection target part IS, is marked with "IS2." The inspection target part IS2 is marked with a two-dimensional code CO corresponding to the inspection target part IS2. In step S05, after the consistency is confirmed by reading the two-dimensional code CO, the inspector presses the execution instruction button 124. Pressing the execution instruction button 124 causes recording (collection of sound data) to be performed by the microphone 56. The time for collecting sound data may be determined in advance.

[0082] Before the collection of sound data is started, the inspection guide unit 64 may display an image showing the inspector a suitable position for collecting sound data on the preview screen 122. In one example, the inspection guide unit 64 displays a standard image of the inspection target area IS2 on the preview screen 122, and the inspector presses the execution instruction button 124 with the inspection target area IS2 overlapping the standard image on the preview screen 122.

[0083] After the sound data is collected, the inspection guide unit 64 may display the sound data ID acquired via the microphone 56 and the standard sound data SD representing the standard of the sound data side by side on the monitor 54a, as shown in FIG. 8( b). By displaying these two images side by side, the inspector can visually confirm whether the acquired sound data is suitable for inspection before making a pass / fail judgment. In order to record the location at which the sound data was acquired, the inspector may acquire an image that allows the location at which the sound data was acquired to be determined.

[0084] Following acquisition of the sound data in step S07, or in response to the inspection person pressing the execution instruction button 126, the evaluation value calculation unit 68 calculates an evaluation value from the sound data acquired in step S07. The evaluation value calculation unit 68 may calculate, as the evaluation value, a statistical quantity such as the maximum or average amplitude of the sound data, which is waveform data representing the time change in signal strength. The evaluation value calculation unit 68 may also calculate, as the evaluation value, a frequency that becomes a peak in a spectrum (a graph representing the change in signal strength according to the change in frequency) obtained by frequency converting the sound data. Other steps among steps S03 to S10 that have not been described are executed in the same way as when the inspection item is the hydraulic oil amount.

[0085] Of all the inspection items, the series of steps S03 to S10 are not executed for items for which the pass / fail judgment is made solely by the inspector's visual inspection without acquiring actual data. For inspection items for which the pass / fail judgment is made solely by visual inspection, for example, after steps S03 and S04 are executed, the inspector inputs the visually confirmed judgment result into the computer main body 52 of the pre-work inspection device 50. Even for inspection items for which the pass / fail judgment is made solely by visual inspection, if the pass / fail judgment result is satisfactory, the first output unit 74 may display a list of inspection items on the monitor 54a with the display mode of the corresponding execution result information 114 changed.

[0086] 9A shows an example of a screen that is displayed when inspection of all inspection items is completed and the results of the pass / fail judgment for all inspection items are passed. The first output unit 74 may display all of the execution result information 114 on the monitor 54a in a display mode that indicates that the inspection is completed and that the inspection results are satisfactory.

[0087] Step S11 is executed after inspection of all inspection items has been completed and the pass / fail judgment results for all inspection items have been determined to be pass. In step S11, for example, the inspector inputs a user input indicating an instruction to end the pre-work inspection into the computer main body 52 of the pre-work inspection device 50. In one example, the first output unit 74 displays an inspection end button 118 on the monitor 54a along with a list indicating that the results of all inspection items are good. The inspection end button 118 is a button for inputting an instruction to end the pre-work inspection. When the inspector presses the inspection end button 118, the pre-work inspection device 50 executes processing to end the pre-work inspection. Note that the inspection end button 118 may be displayed so that it can be pressed by the inspector only when all inspection items have been completed and the results of all inspection items are pass.

[0088] While the series of steps S03 to S10 are repeated, in step S09, the quality determination unit 72 may determine that there is a high possibility of a problem occurring if a casting operation is performed under the current conditions for a certain inspection item. In this case, the first output unit 74 outputs a maintenance required signal as the determination result by the quality determination unit 72. For example, as shown in FIG. 9( b), the first output unit 74 displays warning information 132 on the monitor 54a. The warning information 132 is information including a message indicating that maintenance is required for a specific inspection item.

[0089] When the maintenance required signal is output, for example, the inspector or a worker contacted by the inspector performs maintenance on the inspection items determined to require maintenance. After completing the maintenance, the inspector may input a user input indicating that the maintenance on the inspection items has been completed into the computer main unit 52 of the pre-work inspection device 50. Then, the series of steps S03 to S10 may be resumed.

[0090] In response to the execution of step S11, the pre-work inspection device 50 executes step S12. In step S12, for example, the transition prediction unit 76 predicts a future transition of the evaluation value from the current transition of the evaluation value for each inspection item for which actual data is acquired and a pass / fail judgment is performed. Fig. 10(a) illustrates an example of a graph showing a future transition predicted from the current transition of the evaluation value.

[0091] In the graph of FIG. 10( a), the horizontal axis represents the number of operating days (or operating hours) of the die-casting machine 1, and the vertical axis represents the evaluation value. FIG. 10( a) illustrates an example of an evaluation value related to the motor noise of a pump. In FIG. 10( a), "0" on the horizontal axis represents the current time point, and the plots marked with "AD" represent the actually calculated evaluation value. In other words, a collection of multiple values ​​AD represents the progress of the evaluation value up to the present. The line marked with "PL" is a first-order approximation line calculated based on the multiple values ​​AD. The first output unit 74 calculates the approximation line PL, for example, using the least squares method. Note that the first output unit 74 may calculate a second-order or higher-order approximation line instead of a first-order approximation line as a predicted progress of the evaluation value.

[0092] In step S12, the second output unit 78 determines whether the predicted change in the evaluation value satisfies a predetermined condition to determine whether to output a recommended maintenance timing. For example, the second output unit 78 determines whether the predicted evaluation value according to the approximation line PL N days from now (N is an integer equal to or greater than 3) is within a reference range for the evaluation value. As shown in FIG. 10( a), if the predicted evaluation value N days from now is within the reference range, the second output unit 78 determines not to output a recommended maintenance timing. On the other hand, as shown in FIG. 10( b), if the predicted evaluation value N days from now is not within the reference range, the second output unit 78 determines to output a recommended maintenance timing.

[0093] If it is determined in step S12 that the predetermined conditions are satisfied for any of the inspection items and that a recommended maintenance timing should be output, the pre-work inspection device 50 executes step S13. In step S13, for example, the second output unit 78 displays the recommended maintenance timing on the monitor 54a. In one example, the second output unit 78 determines the intersection of the approximation line PL calculated in step S12 with the upper or lower limit of the reference range and displays information including a message indicating that maintenance is recommended after X days (X is an integer equal to or less than N) on the monitor 54a. The second output unit 78 may display the recommended maintenance timing on the monitor 54a using a graph instead of or in addition to the information including the message. If it is determined in step S12 that a recommended maintenance timing should not be output for all inspection items for which actual data is acquired, the pre-work inspection device 50 does not execute step S13.

[0094] Next, the pre-operation inspection device 50 executes step S14. In step S14, for example, the first output unit 74 outputs an operation permission signal to the control device 40 of the die-casting machine 1. The first output unit 74 may output the operation permission signal based on an operation by the inspector, such as pressing down on the monitor 54a. The die-casting machine 1 may be configured not to start casting operation unless it receives the operation permission signal from the pre-operation inspection device 50.

[0095] Next, step S15 is executed, and in response to the execution of step S15, the die-casting machine 1 executes step S16. In step S15, for example, an inspector or a worker such as an operator contacted by the inspector inputs a user input indicating an instruction to start work into the control device 40. Then, in step S16, the control device 40 starts a casting operation by the die-casting machine 1.

[0096] In the above explanation, the processing flow has been described with a focus on the relationship between the inspector, the pre-work inspection device 50, and the die-casting machine 1. Next, with reference to Fig. 11, the processing flow will be described with a focus on the processing executed by the pre-work inspection device 50.

[0097] The pre-work inspection device 50 (computer main body 52) first executes steps S21 and S22. In step S21, for example, the actual data acquisition unit 66 acquires actual data for the selected inspection item and then stores the actual data. Step S21 corresponds to step S07 in the processing flow shown in FIG. 4. In step S22, for example, the evaluation value calculation unit 68 calculates an evaluation value for the selected inspection item from the actual data acquired in step S21, and the evaluation value storage unit 70 stores the evaluation value. Step S22 corresponds to step S08 in the processing flow shown in FIG. 4.

[0098] Next, the pre-work inspection device 50 executes step S23. In step S23, for example, the pass / fail determination unit 72 compares the evaluation value calculated in step S22 with a reference range to determine the pass / fail status of the selected inspection item. Step S23 corresponds to step S09 in the processing flow shown in Fig. 4. The pre-work inspection device 50 repeats steps S21 to S23 for two or more inspection items for which pass / fail determination is to be performed using actual data.

[0099] In step S23, if the result of the pass / fail judgment for a certain inspection item indicates that a problem is likely to occur when the die-casting machine 1 is operated (step S23: NO), the processing executed by the pre-work inspection device 50 proceeds to step S24. In step S24, the first output unit 74 outputs a signal (information) indicating that maintenance is required to the output device 54.

[0100] On the other hand, if the pass / fail judgment results for all of the two or more inspection items that involve the acquisition of actual data and all of the two or more inspection items that do not involve the acquisition of actual data are pass in step S23, the processing executed by the pre-work inspection device 50 proceeds to step S31. In step S31, for example, the second output unit 78 determines whether or not a recommended maintenance timing is necessary based on the predicted transition of the evaluation value predicted by the transition prediction unit 76. In one example, the second output unit 78 determines whether or not the predicted value N days later in the predicted transition of the evaluation value is within a reference range. Step S31 corresponds to step S12 in the processing flow shown in FIG. 4.

[0101] In step S31, if it is determined that the predicted value N days later for any inspection item is not within the reference range (step S31: NO), the process executed by the pre-work inspection device 50 proceeds to step S32. In step S32, for example, the second output unit 78 outputs the number of days on which the approximation line PL, which represents the predicted transition of the evaluation value, falls outside the reference range as the recommended timing for maintenance. Step S32 corresponds to step S13 in the process flow shown in FIG. 4.

[0102] On the other hand, in step S31, if it is determined that the predicted values ​​N days later are within the reference range for all inspection items for which actual data is acquired (step S31: YES), the processing executed by the pre-work inspection device 50 proceeds to step S33 without going through step S32. Even when step S32 is executed, the processing executed by the pre-work inspection device 50 proceeds to step S33 after execution of step S32.

[0103] In step S33, for example, the first output unit 74 outputs a signal indicating permission for the casting operation to the die-casting machine 1. Step S33 corresponds to step S14 in the processing flow shown in FIG.

[0104] Next, a process executed when the second instruction button 104 illustrated in FIG. 5A is pressed will be described. When the second instruction button 104 is pressed, the input information acquisition unit 62 accepts a user input indicating an instruction to start a display for checking the results of the pre-work inspection. The second instruction button 104 is used when an inspector or other worker wants to check the results of past pre-work inspections. The inspector may press the second instruction button 104 while performing a pre-work inspection if they want to check the past inspection results for any inspection item.

[0105] For example, when the second instruction button 104 is pressed, the inspection guide unit 64 displays on the monitor 54a a list of inspection items made up of a plurality of item selection buttons 112. The inspector or the like selects and presses one of the plurality of item selection buttons 112 that corresponds to the inspection item for which the inspector wishes to check past inspection results. When one item selection button 112 is selected, the inspection guide unit 64 displays performance data related to the inspection item corresponding to that item selection button 112 on the monitor 54a.

[0106] 12(b), performance data 142 related to the selected inspection item is displayed on the monitor 54a. The performance data 142 may be displayed in a table format or a graph format. The performance data 142 may include the inspection date, the inspector, actual data, evaluation values, maintenance history, and special notes. The information to be displayed among the performance data 142 may be switched depending on an operation on the monitor 54a. Performance data related to two or more inspection items may be displayed together on the monitor 54a.

[0107] 4 and 12 are merely examples and may be modified as appropriate. In the above-described process flows, the pre-work inspection device 50 may execute one step and the next step in parallel, or may execute the steps in an order different from that of the above-described example. The pre-work inspection device 50 may omit any step, or may execute a process in any step that is different from that of the above-described example.

[0108] The pre-work inspection device 50 may execute the process flow shown in Fig. 13 instead of the process flow shown in Fig. 11. The process flow shown in Fig. 13 differs from the process flow shown in Fig. 11 in that if the determination result for any of the inspection items in step S23 is a negative determination, the process executed by the pre-work inspection device 50 proceeds to step S41. Hereinafter, the inspection item determined to be a negative determination will be referred to as the "target inspection item."

[0109] In step S41, for example, the pass / fail judgment unit 72 judges whether the deviation between the evaluation value obtained for the target inspection item and the reference range is equal to or less than a threshold. The deviation between the evaluation value and the reference range is calculated as the difference between the evaluation value and either the upper limit or the lower limit of the reference range. In step S41, if the deviation is greater than the threshold (step S41: NO), the processing executed by the pre-work inspection device 50 proceeds to step S24.

[0110] On the other hand, if the deviation is equal to or less than the threshold value in step S41 (step S41: YES), the processing executed by the pre-operation inspection device 50 proceeds to step S42. In step S42, for example, the actual data acquisition unit 66 acquires actual data obtained when the die-casting machine 1 is operated in trial operation mode. Hereinafter, the actual data acquired when the die-casting machine 1 is operated in trial operation mode will be referred to as "trial operation data" to distinguish it from the actual data acquired in step S21. The actual data acquisition unit 66 saves the acquired trial operation data.

[0111] In the trial operation mode, for example, the die casting machine 1 performs operations similar to casting operations without producing a casting product. Operations similar to casting operations include, for example, the forward and backward movement of the plunger tip of the injection unit 11, the mold opening and closing operation of the mold clamping unit 12, and the operation of each piece of equipment included in the peripheral equipment 30, such as the operation of the emergency stop device 38. Operation in the trial operation mode may also include adjustment and cleaning of equipment included in the die casting machine 1. Operation in the operational trial operation mode may also include the operation of trial producing a casting product using actual molten metal.

[0112] Next, the pre-work inspection device 50 executes steps S43 and S44. In step S43, for example, the evaluation value calculation unit 68 calculates an evaluation value from the test run data acquired in step S42, similar to step S22. In step S44, for example, the quality determination unit 72 performs quality determination based on the comparison result between the evaluation value calculated in step S42 and the reference range, similar to step S23.

[0113] If the determination result in step S44 is a pass judgment (step S44: YES), the process executed by the pre-work inspection device 50 proceeds to step S31. On the other hand, if the determination result in step S44 is a fail judgment (step S44: NO), the process executed by the pre-work inspection device 50 proceeds to step S24. As described above, in the process flow shown in FIG. 13 , even if the initial pass / fail judgment is a fail judgment, if the evaluation value calculated from the trial run data obtained during operation in trial run mode is within the reference range, the final inspection result of the target inspection item will be a pass judgment.

[0114] The inspection guide unit 64 may be capable of displaying instructions regarding the pre-work inspection and sensors such as the camera 55 included in the pre-work inspection device 50 on the monitor 54a based on the operation of the inspector. The inspection guide unit 64 may display a screen on the monitor 54a for registering information regarding the pre-work inspection, such as the inspector, inspection date, and inspection content. The inspection guide unit 64 may display a screen on the monitor 54a for the inspector to sign and record their signature at the end of the pre-work inspection. The pre-work inspection device 50 (first output unit 74) may notify the inspector of information indicating the result of the pass / fail determination by the pass / fail determination unit 72 by a method other than displaying it on the monitor 54a, such as a sound.

[0115] The pre-work inspection device 50 may be capable of printing a report showing the inspection results, outputting it as a PDF, or distributing it to a manager of the die-casting machine 1, based on the operation of the inspector. The pre-work inspection device 50 may be used to perform pre-work inspections of each of a plurality of die-casting machines 1. The pre-work inspection device 50 may record data related to the pre-work inspection for each die-casting machine 1. In one example of the various examples described above, at least some of the matters described in the other examples may be combined.

[0116] [Summary of the present disclosure] The above-described pre-operation inspection device (50) includes a calculation means (68) that calculates an evaluation value from actual data that indicates the actual state of the die-casting machine (1), and a determination means (72). The determination means (72) has a reference range of evaluation values ​​at the start of operation in advance, and determines whether the state of the die-casting machine (1) is good or bad based on the comparison result between this reference range and the evaluation value calculated by the calculation means (68).

[0117] As described above, there are many items to be checked in the pre-operation inspection of a die-casting machine. In contrast, the pre-operation inspection device (50) calculates an evaluation value from actual data indicating the actual state of the die-casting machine (1), and determines whether the evaluation value is good or bad based on a comparison between the evaluation value and a reference range. Since the evaluation is performed by the device, the burden on the worker performing the inspection can be reduced. For example, when a worker visually determines whether the condition is good or bad, the worker must visually check the inspection target and then grasp the current condition of the inspection target. The worker must then determine whether the grasped condition is good or bad. Since such manual checking by the worker is replaced by a judgment by the device, the burden on the worker is reduced. Furthermore, the occurrence of variability in the judgment results among workers can be suppressed.

[0118] The above-described pre-work inspection device (50) may further include an acquisition means (66) for acquiring actual data corresponding to each inspection item included in at least a portion of the plurality of inspection items. The calculation means (68) may calculate an evaluation value from the actual data for each inspection item. The determination means (72) may determine the pass / fail status of each inspection item based on a comparison result between a reference range and the evaluation value. In this case, the device may determine the pass / fail status of each inspection item, thereby further reducing the burden on the worker.

[0119] The above-described pre-work inspection device (50) may further include an inspection guide means (64) that displays a list of multiple inspection items and whether each inspection item has been performed on the monitor (54a). In this case, the operator can easily identify the inspection items that have not yet been performed from the content displayed on the monitor (54a). This allows the inspection work to proceed smoothly. In addition, since the possibility that some inspection items will not be performed is reduced, more stable casting operations are possible.

[0120] In the pre-operation inspection device 50 described above, the acquisition means 66 may acquire, for each inspection item, image data obtained by capturing an image of the part (IS) of the die-casting machine 1 related to the inspection item, or sound data generated from the part (IS) as actual data. In this case, the operator can perform the inspection using the device while recognizing the condition of the part related to the inspection item. This makes it possible to more reliably identify conditions that are not suitable for casting operation in the die-casting machine 1 during the pre-operation inspection.

[0121] The above-described pre-work inspection device (50) may further include a judgment result output means (74) for outputting the judgment result of the judgment means (72). In this case, the worker can easily understand the result of the pass / fail judgment.

[0122] The above-described pre-work inspection device (50) may further include a prediction means (76) for predicting a future trend in the evaluation value from the current trend of the evaluation value calculated by the calculation means (68), and a recommended timing output means (78) for outputting a recommended timing for maintenance based on the trend predicted by the prediction means (76) and a reference range when the trend predicted by the prediction means (76) satisfies a predetermined condition. In this case, a worker or an operator of the die-casting machine (1) can know when maintenance is necessary before it is determined that maintenance is necessary in the pre-work inspection. This allows maintenance of the die-casting machine (1) to be carried out in a planned manner.

[0123] The pre-work inspection method described above is an inspection method performed by the pre-work inspection device (50). This inspection method includes a calculation step in which the calculation means (68) of the pre-work inspection device (50) calculates an evaluation value from actual data indicating the actual state of the die-casting machine (1), and a judgment step. In the judgment step, the judgment means (72) of the pre-work inspection device (50) judges whether the state of the die-casting machine (1) is good or bad based on the comparison result between the evaluation value calculated in the calculation step and a reference range. This pre-work inspection method, like the above-mentioned pre-work inspection device (50), can reduce the burden on the worker performing the inspection.

[0124] 1... die casting machine, 50... pre-work inspection device, 54a... monitor, 64... inspection guide section, 66... ​​actual data acquisition section, 72... pass / fail judgment section, 74... first output section, 76... transition prediction section, 78... second output section.

Claims

1. A start-up inspection device for a die-casting machine, comprising: a calculation means for calculating an evaluation value from actual data showing the actual condition of the die-casting machine; and a judgment means, wherein the judgment means has a reference range for the evaluation value at the start of work in advance, and judges whether the condition of the die-casting machine is good or bad based on a comparison result between this reference range and the evaluation value calculated by the calculation means.

2. A pre-operation inspection device for a die casting machine as described in claim 1, further comprising an acquisition means for acquiring the actual data corresponding to each inspection item included in at least a portion of a plurality of inspection items, said calculation means for calculating the evaluation value from the actual data for each inspection item, and said judgment means for judging the pass / fail of each inspection item based on a comparison result between said reference range and said evaluation value.

3. A pre-operation inspection device for a die casting machine as described in claim 2, further comprising an inspection guide means for displaying on a monitor a list of said plurality of inspection items and whether or not each of said inspection items has been inspected.

4. A pre-operation inspection device for a die-casting machine as described in claim 2, characterized in that the acquisition means acquires, for each inspection item, image data obtained by imaging a part of the die-casting machine related to that inspection item, or sound data generated from that part, as the actual data.

5. A pre-operation inspection device for a die casting machine as claimed in any one of claims 1 to 4, further comprising a judgment result output means for outputting the judgment result made by said judgment means.

6. A pre-start inspection device for a die-casting machine as claimed in any one of claims 1 to 4, further comprising: a prediction means for predicting a future trend of said evaluation value from the trend up to the present of said evaluation value calculated by said calculation means; and a recommended timing output means for outputting a recommended timing for maintenance based on the trend predicted by said prediction means and said reference range when the trend predicted by said prediction means satisfies a predetermined condition.

7. A pre-start-up inspection method for a die-casting machine executed by a pre-start-up inspection device, comprising: a calculation step in which a calculation means of the pre-start-up inspection device calculates an evaluation value from actual data showing the actual state of the die-casting machine; and a judgment step in which a judgment means of the pre-start-up inspection device judges whether the state of the die-casting machine is good or bad based on a result of comparing the evaluation value calculated in the calculation step with a reference range.

Citation Information

Patent Citations

  • Start-up inspection device for automatic operative construction equipment

    JP2000096630A

  • Die casting process management device by generated sound source tone quality analysis

    JP2020093269A

  • Molding system

    JP2021041454A

  • Quality determination method for die-casting machine

    JP2022147196A