Manufacturing evaluation device and manufacturing evaluation method
The manufacturing evaluation device predicts energy consumption and environmental load using shape and component data, addressing the lack of environmental assessment at the product design stage, enabling sustainable product development by providing critical insights for reducing environmental impact.
Patent Information
- Application Number
- PCT/JP2024/000130
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-05-15
- Filing Date
- 2024-01-09
- Publication Date
- 2024-11-21
AI Technical Summary
Current manufacturing processes lack the capability to predict and assess environmental impact during the product design stage, primarily focusing on quality, cost, and delivery dates, with no effective means to measure environmental loads at this upstream phase, hindering advanced energy savings and sustainability efforts.
A manufacturing evaluation device that uses shape and component configuration data to predict energy consumption and environmental load, incorporating a manufacturing process identification unit, lead time calculation, environmental load identification, and screen generation to provide designers with insights for reducing environmental impact during product design.
Enables designers to predict and minimize the environmental load and energy consumption of manufacturing processes at the product design stage, facilitating more sustainable product development and reducing environmental impact throughout the manufacturing process.
Smart Images

Figure JP2024000130_21112024_PF_FP_ABST
Abstract
Description
Manufacturing evaluation device and manufacturing evaluation method
[0001] The present invention relates to a manufacturing evaluation device and a manufacturing evaluation method. The present invention claims priority to Japanese Patent Application No. 2023-079780, filed on May 15, 2023, and the contents of that application are incorporated by reference into the present application in designated states where incorporation by reference of documents is permitted.
[0002] As companies are now required to solve environmental issues, such as achieving carbon neutrality, manufacturers are being asked to conduct environmental assessments during product design to clarify the environmental impact of their products. Traditionally, designers have typically designed products using product quality, cost, delivery time, and other evaluation KPIs. However, the future requirement for environmental assessment as a KPI could place an additional burden on designers. Meanwhile, in recent years, the manufacturing industry has been working to reduce the energy consumption of manufacturing equipment and visualize its impact. Specifically, as shown in Patent Document 1, it is becoming increasingly possible to obtain actual values for environmental impact information, such as the power consumption of manufacturing equipment and direct greenhouse gas emissions, in manufacturing processes downstream of the engineering chain.
[0003] Patent Document 1 describes an energy consumption measurement data processing device that collects measurement data related to energy consumption based on measurement point setting data and aggregates and processes the measurement data, and includes an energy system aggregate data processing unit that processes energy system aggregate data, which is aggregate data along an energy system, and the energy system aggregate data processing unit generates the energy system aggregate data from the energy system setting data and energy system measurement point correspondence setting data, which sets a correspondence between the energy system setting data and the measurement point setting data, or outputs settings for generating the energy system aggregate data.
[0004] By using such equipment, it will be possible to actually measure the energy consumption of the actual manufacturing process and manufacturing equipment, and it is thought that it will be possible to grasp the current state of energy consumption in the manufacturing environment.However, there is no mention of measuring such environmental impacts at the product design stage, which is further upstream in the engineering chain.
[0005] JP 2013-44589 A
[0006] In this context, in order to achieve even more advanced energy conservation, it is important to provide a system that helps reduce the environmental impact of the manufacturing environment at the upstream design stage.
[0007] The object of the present invention is to provide technology that brings us closer to realizing a sustainable society by enabling product design to be carried out while predicting the energy consumption and environmental load of the manufacturing environment at the product design stage.
[0008] The present application includes a plurality of means for solving at least part of the above-mentioned problems, examples of which are as follows: A manufacturing evaluation device according to one aspect of the present invention for solving the above-mentioned problems comprises a manufacturing process identification unit that identifies a manufacturing process for a part using shape data including at least the shape and dimensions of the part and part configuration data including the material of the part, a lead time calculation unit that calculates a lead time in the manufacturing process, a process time identification unit that identifies a process time according to the lead time, an environmental load identification unit that identifies an environmental load according to the process time, and a screen generation unit that generates a screen showing the environmental load.
[0009] The present invention provides a technology that enables a product to be designed while predicting the energy consumption and environmental load of the manufacturing environment at the design stage. Problems, configurations, and effects other than those described above will become clear from the following description of the preferred embodiment of the invention.
[0010] 1 is a diagram showing an example of the configuration of a manufacturing evaluation device; FIG. 2 is a diagram showing an example of the processing flow of manufacturing evaluation processing; FIG. 3 is a diagram showing an example of the processing flow in a manufacturing process identification step of manufacturing evaluation processing; FIG. 4 is a diagram showing an example of the processing flow in an environmental load identification step of manufacturing evaluation processing; FIG. 5 is a diagram showing an example of a manufacturing evaluation screen; FIG. 6 is a diagram showing an example of parts configuration data; FIG. 7 is a diagram showing an example of manufacturing equipment data; FIG. 8 is a diagram showing an example of the hardware configuration of a manufacturing evaluation device; FIG. 9 is a diagram showing a modified example of the processing flow of manufacturing evaluation processing; FIG. 10 is a diagram showing an example of the use of manufacturing evaluation data.
[0011] Hereinafter, embodiments of the present invention will be described with reference to the drawings. The examples are illustrative of the present invention, and for clarity of explanation, appropriate omissions and simplifications have been made. The present invention can be implemented in various other forms. Unless otherwise specified, each component may be singular or plural.
[0012] In order to facilitate understanding of the invention, the position, size, shape, range, etc. of each component shown in the drawings may not represent the actual position, size, shape, range, etc. Therefore, the present invention is not necessarily limited to the position, size, shape, range, etc. disclosed in the drawings.
[0013] Examples of various types of information may be described using expressions such as "table," "list," and "queue," but the various types of information may be expressed using data structures other than these. For example, various types of information such as "XX table," "XX list," and "XX queue" may be expressed as "XX information." When describing identification information, expressions such as "identification information," "identifier," "name," "ID," and "number" are used, but these are interchangeable. Furthermore, in the embodiments, identification information described using these expressions is expressed using symbols, numbers, natural language, or a combination thereof, but the identification information may be in a format other than these.
[0014] When there are multiple components with the same or similar functions, they may be described using the same reference numeral with different subscripts. When there is no need to distinguish between these multiple components, the subscripts may be omitted.
[0015] In the embodiments, processing performed by executing a program may be described. Here, a computer executes the program using a processor (e.g., a CPU or a GPU) and performs processing defined by the program using storage resources (e.g., memory) and interface devices (e.g., communication ports). Therefore, the entity performing the processing by executing the program may be the processor. Similarly, the entity performing the processing by executing the program may be a controller, device, system, computer, or node having a processor. The entity performing the processing by executing the program may be any computing unit, and may include a dedicated circuit that performs specific processing. Here, the dedicated circuit may be, for example, an FPGA (Field Programmable Gate Array), an ASIC (Application Specific Integrated Circuit), a CPLD (Complex Programmable Logic Device), or the like.
[0016] A program may be installed on a computer from a program source. The program source may be, for example, a program distribution server or a computer-readable storage medium. When the program source is a program distribution server, the program distribution server may include a processor and storage resources for storing the program to be distributed, and the processor of the program distribution server may distribute the program to be distributed to other computers. In addition, in the embodiments, two or more programs may be realized as one program, or one program may be realized as two or more programs.
[0017] Furthermore, although the present invention is typically realized by an information processing device, it may also be realized as a platform having the functions of the present invention.
[0018] 1 is a diagram illustrating an example of the configuration of a manufacturing evaluation device 100. For example, the manufacturing evaluation device 100 is an information processing device including a storage unit 110, a processing unit 120, an input receiving unit 130, an output processing unit 140, and a communication unit 150.
[0019] The manufacturing evaluation device 100 predicts energy consumption and environmental impact based on the time required to execute an efficient manufacturing process, primarily using product design information such as production volume, component configuration, component shape, and dimensions. This allows designers to modify the design information by referring to the predicted environmental impact. In other words, products can be designed while minimizing the environmental impact of the manufacturing process.
[0020] The storage unit 110 includes part configuration data 111, part shape data 112, facility power data 113, and environmental load conversion coefficient 114. The part configuration data 111 is, for example, part configuration information (BOM: Bill of Materials) that includes at least the parts that make up the part and the materials of the parts. Details of the part configuration data 111 will be described later.
[0021] The part shape data 112 is, for example, shape data including at least the shape and dimensions of the part. Specifically, the part shape data 112 is various types of so-called three-dimensional CAD data, but is not limited to this and may also be two-dimensional CAD data.
[0022] The facility power data 113 is information that includes at least information specifying the amount of power consumption per operating hour of each manufacturing facility. However, the facility power data 113 is not limited to this, and for example, the amount of power consumption per operating hour may be set for each predetermined date and time division (e.g., month, etc.).
[0023] The environmental load conversion coefficient 114 is information that includes information specifying at least the environmental load per unit of power consumption (e.g., greenhouse gas emissions). Note that the environmental load conversion coefficient 114 is not limited to this, and for example, the environmental load per unit of power consumption may be set for each predetermined time period (e.g., daytime, nighttime, etc.). This is because clean energy includes energy that utilizes natural phenomena, and many of these energy sources have power generation capacities that are affected by the time of day. For example, since solar power generation cannot be expected to be used at night, it is desirable to convert the environmental load to a higher value.
[0024] Greenhouse gases include various gases that are believed to have a greenhouse effect. Representative examples include carbon dioxide (CO2 ), methane (CH 4 ), nitrous oxide (N 2 O), hydrofluorocarbons (HFCs), perfluorocarbons (PFCs), sulfur hexafluoride (SF 6 ) but is not limited to these, and does not necessarily have to include these and may be any of them, or the greenhouse effect may be converted to any of the gases.
[0025] The processing unit 120 includes a manufacturing process specifying unit 121 , a lead time calculation unit 122 , an environmental load specifying unit 123 , a process time specifying unit 124 , a power consumption specifying unit 125 , and a screen generation unit 126 .
[0026] The manufacturing process specification unit 121 specifies a manufacturing process for a part using shape data including at least the part's shape and dimensions and part configuration data including the part's material. The manufacturing process specification unit 121 also receives design specifications for the part, including either or both of the part's tolerance and surface roughness. The manufacturing process specification unit 121 also determines a manufacturing process that satisfies the part's shape and dimensions using the part's material, and determines processing conditions for applying the manufacturing process that satisfy the design specifications. The processing conditions include control parameters of the equipment used in the manufacturing process (e.g., the rotation speed and rotation angle of the rotating part, cutting speed, etc.).
[0027] The lead time calculation unit 122 calculates the lead time in the manufacturing process. Specifically, the lead time calculation unit 122 calculates the processing time required to realize the material of the part and the shape and dimensions of the part according to the design specifications as the lead time. If the above-mentioned processing conditions (equipment control parameters) are specified, the lead time calculation unit 122 calculates the processing time under those processing conditions.
[0028] The environmental load identifying unit 123 identifies the environmental load according to the process time. Specifically, the environmental load identifying unit 123 identifies the environmental load according to the power consumption calculated by the power consumption identifying unit 125 and the process time identified by the process time identifying unit 124.
[0029] The process time specifying unit 124 specifies the process time based on the lead time. Specifically, the process time specifying unit 124 specifies the process time using the lead time, the preparation time, and the waiting time.
[0030] The power consumption amount specifying unit 125 specifies the power consumption amount during the process time.
[0031] The screen generator 126 generates a screen showing the environmental load. The screen generator 126 includes information showing parts or manufacturing processes that have a large impact on the environmental load in the screen showing the environmental load.
[0032] The input receiving unit 130 receives input of various data. Specifically, the input receiving unit 130 receives input of design information such as part configuration data 111 and part shape data 112 from a product designer.
[0033] The output processing unit 140 outputs to the designer a screen or the like containing information on the environmental load in the input design information.
[0034] The communication unit 150 communicates with other devices via a network.
[0035] 2 is a diagram showing an example of a processing flow of the manufacturing evaluation process. The manufacturing evaluation process is started when the manufacturing evaluation device 100 receives a start instruction from a designer or the like. Alternatively, the manufacturing evaluation process may be started at a predetermined date and time (e.g., 1:00 PM every day) or at predetermined intervals (e.g., once a week).
[0036] The manufacturing evaluation process mainly includes a manufacturing process identification step S01 that accepts input of design information such as part configuration data 111, such as a BOM, and part shape data 112, such as CAD, and identifies the manufacturing process and lead time; a manufacturing data addition step S02 that adds information about the manufacturing process and lead time to the part configuration data 111; an environmental load identification step S03 that identifies the process time based on the process lead time and the power consumption based on the process time, and identifies the environmental load based on the power consumption; an environmental data addition step S04 that adds environmental load data to the part configuration data 111; and an environmental data visualization step S05 that visualizes and displays the environmental load data.
[0037] 3 is a diagram showing an example of a processing flow of the manufacturing process identification step of the manufacturing evaluation processing. First, the manufacturing process identification unit 121 reads the part configuration data 111 and the part shape data 112 as inputs (step S011).
[0038] The manufacturing process specification unit 121 also receives input of a product production plan as premise information before calculation (step S012). The production plan is information that specifies the planned production quantity of a product for each predetermined period. This is because the operating time of the manufacturing line changes depending on the planned production quantity.
[0039] Then, the manufacturing process specifying unit 121 receives a rough process selection for each part (step S013). Examples of processes include "cutting (forming parts by cutting)," "near net shape (printing with a 3D printer)," and "forging." The manufacturing process specifying unit 121 receives the settings here so that the manufacturing process of the product can be roughly determined.
[0040] Then, the manufacturing process specifying unit 121 receives input of design specifications such as tolerances and surface roughness (step S014). Generally, if the tolerances and surface roughness values in finishing are set low, it is estimated that additional processes such as finishing and polishing will be required, which will affect the lead time.
[0041] Then, the manufacturing process specifying unit 121 generates a plurality of realistic process candidates (N candidates) (step S015). Specifically, the manufacturing process specifying unit 121 uses the shape and dimensions of the part to design a plurality of manufacturing process candidates in cooperation with a CAM (Computer Aided Manufacturing) tool or the like.
[0042] In this case, the manufacturing process specifying unit 121 determines a manufacturing process that satisfies the shape and dimensions of the part using the material of the part, and determines processing conditions that apply the manufacturing process and satisfy the design specifications.
[0043] The lead time calculation unit 122 then selects the i-th process candidate (i is an integer equal to or greater than 1) (step S016), calculates the lead time of the equipment (step S017), and repeats the processes of steps S016 and S017 while incrementing i until i matches N (step S018).
[0044] Then, the manufacturing process specifying unit 121 specifies a candidate process that will minimize the lead time (step S019).
[0045] The above is an example of the processing flow of the manufacturing process identification step of the manufacturing evaluation processing. According to the manufacturing process identification step, it is possible to identify a candidate process that minimizes the lead time.
[0046] 4 is a diagram showing an example of a process flow in the environmental load identification step of the manufacturing evaluation process. First, the process time identification unit 124 calculates and identifies the process time based on the lead time (step S031). Specifically, for each process included in the selected candidate process, the process time identification unit 124 identifies the process time using the lead time, preparation time, and waiting time. More specifically, the process time identification unit 124 determines the process time by adding, for example, statistical values of preparation time and waiting time of a process similar to the selected process to the lead time calculated by the lead time calculation unit 122 in step S017. Note that the process time identification unit 124 is not limited to using statistical values of preparation time and waiting time of a process similar to the selected process, but may also use a predetermined preparation time and waiting time.
[0047] The power consumption specifying unit 125 then calculates the process power consumption (step S032). Specifically, the power consumption specifying unit 125 refers to the equipment power data 113 to specify, for each process included in the selected process candidate, information specifying the power consumption per operating hour of the manufacturing equipment that carries out that process. The power consumption specifying unit 125 then calculates the process power consumption for each process, using the process time specified by the process time specifying unit 124 in step S031 as the operating time. Specifically, the power consumption specifying unit 125 calculates the product of the process time and the power consumption for each process, and determines the result as the process power consumption.
[0048] Then, the environmental load identifying unit 123 calculates an index value indicating the environmental load (step S033). Specifically, the environmental load identifying unit 123 refers to the environmental load conversion coefficient 114 and converts the process power consumption of each process included in the selected process candidate into an environmental load. Specifically, the environmental load identifying unit 123 calculates the product of the power consumption and the environmental load conversion coefficient for each process, and sets this as the environmental load. For example, CO 2 When converting the amount of CO2 emitted, the environmental load identifying unit 123 uses the amount of power consumption and the amount of CO2 emitted as the environmental load conversion coefficient 114. 2 The product of the emission factors is calculated as an index value for environmental impact.
[0049] The above is an example of the process flow of the environmental load identification step of the manufacturing evaluation process. According to the environmental load identification step, it is possible to identify the environmental load for a candidate process that has the shortest lead time.
[0050] 5 is a diagram showing an example of a manufacturing evaluation screen. The manufacturing evaluation screen 40 is generated by the screen generation unit 126 throughout the manufacturing evaluation process and is displayed by the output processing unit 140. The manufacturing evaluation screen 40 accepts various inputs and updates the display as needed to reflect the results of the inputs. The manufacturing evaluation screen 40 includes an input setting acceptance area 41, an analysis procedure acceptance area 42, and an analysis result display area 43.
[0051] The input setting receiving area 41 is an area for receiving input information, including a project file name, component configuration data for receiving input specifying the storage location of component configuration data 111, component shape data for receiving input specifying the storage location of component shape data 112, facility power data for receiving input specifying the storage location of facility power data 113, and environmental load conversion coefficients for receiving input specifying the storage location of environmental load conversion coefficients 114.
[0052] The analysis procedure reception area 42 is an area for receiving instructions for the analysis procedure. Instructions for the analysis procedure are received by inputting them into buttons or the like corresponding to the processing procedure provided in advance. For example, the analysis procedure reception area 42 has seven steps of the procedure, which receive instructions for start, drawing number selection, process identification, manufacturing data addition, environmental load identification, environmental data addition, and save, respectively. The user, or designer, can obtain the results of estimating the environmental load from the design information by operating these buttons in order according to the analysis procedure.
[0053] For example, when an input is made to the process identification button, processing of the manufacturing process identification step S01 is started, the analysis result display area 43 is updated, and candidate manufacturing processes are displayed. When an input is made to the environmental load identification button, processing of the environmental load identification step S03 is started, the analysis result display area 43 is updated, and information indicating the environmental load is displayed. In particular, the information indicating the environmental load includes information indicating parts or manufacturing processes that have a large impact on the environmental load. It is desirable to use a Pareto chart or a pie chart for such information. By displaying the information using a Pareto chart or a pie chart, it becomes easier to grasp points for improvement, and the visualization effect is high.
[0054] The analysis result display area 43 is an area that displays the results of processing performed by the analysis procedure. The analysis result display area 43 includes a process candidate display area 44 that shows candidate manufacturing processes, and an environmental load data display area 45 that shows the environmental load. The environmental load data display area 45 includes a Pareto chart and a pie chart, as described above. In particular, the Pareto chart shows the elements with the greatest impact on the horizontal axis and the cumulative results on the vertical axis, making it possible to see at a glance which parts or process elements dominate the cumulative results of the environmental load.
[0055] FIG. 6 is a diagram showing an example of parts configuration data. The parts configuration data 111 includes a product name 111a, a part name 111b, a type 111c, a manufacturer name 111d, a quantity 111e, specifications 111f, a material 111g, and a drawing number 111h. Generally, a product name 111a is provided for each product, and a type 111c, a manufacturer name 111d, a quantity 111e, specifications 111f, a material 111g, and a drawing number 111h are provided for each component that constitutes the product and each component that constitutes the component. The material 111g, in particular, is an important factor in determining and selecting a manufacturing process. The drawing number 111h is a number used to reference the drawing file for the component. The parts configuration data 111 can also be a typical BOM.
[0056] 7 is a diagram showing an example of manufacturing equipment data. The manufacturing equipment data is data that is added to the parts configuration data 111 as additional information by being associated with the drawing number 111h. The manufacturing equipment data may be data of a system commonly known as BOP (Bill of Process). In addition to BOP data such as the drawing number 111h, process 111j, location 111k, building 111m, equipment 111n, and equipment information 111p, the manufacturing equipment data is associated with environmental data 111r. The environmental data 111r is information on the environmental load identified by the environmental load identification unit 123.
[0057] Of these, the BOP data is information added and supplemented in the manufacturing data addition step S02, and the environmental data 111r is information on the environmental load added and supplemented in the environmental data addition step S04.
[0058] The information on the process 111j, location 111k, building 111m, equipment 111n, and equipment information 111p is information that identifies the part manufacturing process indicated by the drawing number, the location where the process is performed, and the building, equipment, and other equipment details. This information is determined according to the manufacturing environment of each manufacturer, and therefore is either determined in advance or supplemented in advance based on actual results.
[0059] 8 is a diagram showing an example of the hardware configuration of the manufacturing evaluation apparatus 100. The manufacturing evaluation apparatus 100 can be realized as a general computer 900 including a processor 901, a hardware memory 902 such as a RAM (Random Access Memory), an external storage device 903 such as a hard disk drive (HDD) or an SSD (Solid State Drive), a reading device 905 for reading information from a portable storage medium 904 such as a CD (Compact Disk) or a DVD (Digital Versatile Disk), an input device 906 such as a keyboard, a mouse, a barcode reader, or a touch panel, an output device 907 such as a display, and a communication device 908 for communicating with other computers via a communication network such as a LAN or the Internet, or as a network system including a plurality of such computers 900. The reading device 905 may be capable of not only reading from the portable storage medium 904 but also writing to it.
[0060] The processor 901 is, for example, a CPU (Central Processing Unit) or a GPU (Graphics Processing Unit). The processor 901 performs various processes by executing various predetermined programs loaded from an external storage device 903 to a memory 902. The programs are, for example, application programs that can be executed on an OS (Operating System) program. The programs may be installed in the external storage device 903 from a portable storage medium 904 via a reading device 905, or may be downloaded from a network via a communication device 908 and executed by the processor 901.
[0061] For example, the manufacturing process identification unit 121, the lead time calculation unit 122, the environmental load identification unit 123, the process time identification unit 124, the power consumption identification unit 125, and the screen generation unit 126 can be realized by loading a program stored in an external storage device 903 into the memory 902 and executing it on the processor 901.
[0062] The input receiving unit 130 can be realized by the processor 901 using the input device 906 and the communication device 908. The output processing unit 140 can be realized by the processor 901 using the output device 907 and the communication device 908. The storage unit 110 can be realized by the processor 901 using the memory 902 or the external storage device 903. The communication unit 150 can be realized by the processor 901 using the communication device 908.
[0063] The above is an example of the manufacturing evaluation device 100 according to an embodiment of the present invention. Note that the present invention is not limited to the above-described example, and various modifications are included. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and the present invention is not necessarily limited to an apparatus including all of the described configurations. It is possible to replace part of the configuration of an embodiment with another configuration, and it is also possible to add the configuration of another embodiment to the configuration of an embodiment. It is also possible to delete part of the configuration of an embodiment.
[0064] For example, in the above embodiment, part configuration and part shape data are exemplified as design information to be input, but this is not limiting, and it is also possible to input a manufacturing process and a lead time (or process time) separately calculated in accordance with the design information. 2 This includes, but is not limited to, various greenhouse gases.
[0065] Furthermore, for example, in the above-described embodiment, the data stored in the storage unit 110 is used in the manufacturing evaluation device 100, but this is not limiting. For example, the manufacturing evaluation device 100 may be communicably connected to other devices via the network 50, and some or all of the information in the storage unit 110 may be made accessible, i.e., shareable, or data shared with other devices via cloud storage or the like may be used.
[0066] 9 is a diagram showing a modified example of the processing flow of the manufacturing evaluation process. In this modified example, data sharing with other devices is performed using cloud storage or the like, as described above. After performing the environmental data visualization step S05, the processing unit 120 performs a data sharing step S06. Specifically, the processing unit 120 copies the candidate manufacturing processes identified in the manufacturing process identification step S01 and the environmental loads identified in the environmental load identification step S03 to the cloud storage.
[0067] 10 is a diagram showing an example of how manufacturing evaluation data is used. A designer 10 is responsible for product design and a user of the manufacturing evaluation device 100. Cloud storage 60 stores and shares component configuration data 111, component shape data 112, facility power data 113, and environmental load conversion coefficient 114 shared from the manufacturing evaluation device 100, as well as environmental loads 61 and manufacturing process candidates 62. The data in cloud storage 60 can be accessed by personnel such as an equipment operator 11 who operates the manufacturing equipment, a line maintenance technician 12 who performs maintenance on the production equipment, a process designer 13 who is responsible for designing and developing the production process, a procurement technician 14 who negotiates material procurement and costs, and a product sales technician 15 who is responsible for selling the completed product.
[0068] For example, the process designer 13 refers to the environmental load 61 and calculates the CO 2 It can be used to improve the efficiency of processes with high CO emissions. 2 If an effective reduction effect on emissions can be found, the product sales representative 15 can use this as a selling point during sales.
[0069] In addition, when new equipment is introduced, data such as the power consumption of the new equipment can be added by the line maintenance staff 12 or equipment operator 11 to the parts configuration data 111 or equipment power data 113, so that the latest data can be shared with the designers 10 and process designers 13 and used to analyze environmental impacts and create process programs. In this way, using this system makes the supply chain seamless, further reducing the overall environmental impact and leading to effective design and manufacturing.
[0070] Some or all of the above-described units, configurations, functions, processing units, etc. may be implemented in hardware, for example, by designing them as integrated circuits. Furthermore, the above-described units, configurations, functions, etc. may be implemented in software by a processor interpreting and executing a program that implements each function. Information such as the programs, tables, and files that implement each function can be stored in a memory, a recording device such as a hard disk, or a recording medium such as an IC card, SD card, or DVD.
[0071] It should be noted that the control lines and information lines in the above-described embodiments are those considered necessary for the explanation, and do not necessarily show all the control lines and information lines in the product. In reality, it can be considered that almost all components are interconnected. The present invention has been described above, focusing on the embodiments.
[0072] 100: manufacturing evaluation device, 110: memory unit, 111: component configuration data, 112: component shape data, 113: equipment power data, 114: environmental load conversion coefficient, 120: processing unit, 121: manufacturing process identification unit, 122: lead time calculation unit, 123: environmental load identification unit, 124: process time identification unit, 125: power consumption identification unit, 126: screen generation unit, 130: input reception unit, 140: output processing unit, 150: communication unit.
Claims
1. A manufacturing evaluation device comprising: a manufacturing process identification unit that identifies a manufacturing process for a part using shape data including at least the shape and dimensions of the part and part configuration data including the material of the part; a lead time calculation unit that calculates a lead time in the manufacturing process; a process time identification unit that identifies a process time in accordance with the lead time; an environmental load identification unit that identifies an environmental load in accordance with the process time; and a screen generation unit that generates a screen showing the environmental load.
2. A manufacturing evaluation device as described in claim 1, wherein the manufacturing process identification unit receives design specifications for the part, and the lead time calculation unit calculates as the lead time the processing time required to realize the material of the part and the shape and dimensions of the part in the design specifications.
3. A manufacturing evaluation device according to claim 2, characterized in that the manufacturing process specification unit accepts at least one or both of the tolerance and surface roughness of the part as the design specifications.
4. A manufacturing evaluation device as described in claim 3, wherein the manufacturing process specification unit determines a manufacturing process that satisfies the shape and dimensions of the part using the material, and determines processing conditions that satisfy the design specifications by applying the manufacturing process, and the processing conditions include control parameters of equipment used in the manufacturing process.
5. A manufacturing evaluation device according to claim 4, characterized in that the lead time calculation section calculates the processing time under the processing conditions.
6. A manufacturing evaluation device according to claim 1, characterized in that said process time determination unit determines said process time using said lead time, preparation time and waiting time.
7. A manufacturing evaluation device as described in claim 1, further comprising an energy consumption determination unit that determines the amount of energy consumed during the process time, and the environmental load determination unit determines the environmental load according to the amount of energy consumed calculated by the energy consumption determination unit.
8. A manufacturing evaluation device as claimed in claim 1, characterized in that the screen generation unit includes information indicating the part or the manufacturing process that has a large impact on the environmental load on the screen indicating the environmental load.
9. A manufacturing evaluation device according to claim 1, further comprising: a storage unit for storing the manufacturing process, the shape data, the parts configuration data or the environmental load in a manner that allows the manufacturing process, the shape data, the parts configuration data or the environmental load to be shared with other devices.
10. A manufacturing evaluation method using an information processing device, wherein the information processing device carries out the following steps: a manufacturing process identification step of identifying a manufacturing process for the part using shape data including at least the shape and dimensions of the part and part configuration data including the material of the part; a lead time calculation step of calculating a lead time in the manufacturing process; a process time identification step of identifying a process time in accordance with the lead time; an environmental load identification step of identifying an environmental load in accordance with the process time; and a screen generation step of generating a screen showing the environmental load.
Citation Information
Patent Citations
Method and device for planning manufacturing line
JP1993081291A
Method and system for automatically evaluating manufacturing efficiency
JP1993114003A
Press work process output system, its program, press work estimation system and its program
JP2004086271A
Environmental load display device, environmental load display method and environmental load display program
JP2008065768A
Manufacturing process improvement support system, manufacturing process improvement support, and manufacturing process improvement program
JP2012128818A