Power supply system for an electrolyzer plant and control method thereof

The power supply system for hydrogen electrolyzer plants addresses grid fault challenges by coordinating grid and energy storage power to ensure continuous operation and stability, preventing shutdowns and maintaining hydrogen production.

WO2026233538A1PCT designated stage Publication Date: 2026-11-12HITACHI ENERGY LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
PCT/EP2025/062352
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2025-05-06
Publication Date
2026-11-12

AI Technical Summary

Technical Problem

Large-scale hydrogen electrolyzer plants face challenges in maintaining operation during grid faults, leading to sudden power loss and potential disruptions, which can cause safety hazards and production losses.

Method used

A power supply system with a converter system, energy storage system, and control system that coordinates power from the grid and energy storage to maintain electrolyzer operation during faults, allowing for fault ride-through capability.

Benefits of technology

Ensures continuous hydrogen production during grid faults by dynamically managing power distribution, preventing sudden shutdowns and maintaining grid stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure EP2025062352_12112026_PF_FP_ABST
    Figure EP2025062352_12112026_PF_FP_ABST
Patent Text Reader

Abstract

A power supply system (100) for an electrolyzer plant (200) comprising a converter system (10) configured to transfer power to a plurality of electrolyzers (201, 202, 203, 204) in the electrolyzer plant (200) from a power source (300) coupled to a power grid; an energy storage system (30) arranged in the power supply system (100); and a control system (20) configured to dynamically control the operation of at least one electrolyzer (201) from the plurality of electrolyzers (201, 202, 203, 204) during a grid fault to provide a fault-ride through for the at least one electrolyzer (201) during the grid fault, and to coordinate the supply of power to the at least one electrolyzer (201) from at least one of the power grid (300) and the energy storage system (30).
Need to check novelty before this filing date? Find Prior Art

Description

POWER SUPPLY SYSTEM FOR AN ELECTROLYZER PLANT AND CONTROL METHOD THEREOFTECHNICAL FIELD

[0001] The present disclosure generally relates to fault ride-through control of a hydrogen electrolyzer plant, in particular, to a power supply system for a hydrogen electrolyzer plant and a method for controlling the power supply system.BACKGROUND

[0002] Hydrogen is an energy carrier that can be used to decarbonize sectors that are difficult to address using other methods, such as long-distance transportation (heavy payload trucks, flights, ferries), steelmaking, and ammonia production. To ensure that hydrogen production is climate-friendly (e.g., green hydrogen), it must be produced through electrolysis, which splits water into oxygen and hydrogen using electricity from renewable sources. Hydrogen has also been proposed as an enabler for power generation in a power system that connects intermittent renewable energy sources. Hydrogen can be produced abundantly when there is excess renewable power (from wind or solar) and when the electricity prices are low. Thus, a hydrogen production plant (hydrogen electrolyzer plant) can behave as a flexible load in the power system, and further, the hydrogen production plant can be made to operate with renewable power generators and additionally contribute to ancillary grid services.

[0003] A large-scale hydrogen production plant can be operated through a Medium Voltage (MV) grid or a High Voltage (HV) grid. A power supply scheme for a large-scale hydrogen production plant includes several HV and MV power transformers, circuit breakers, disconnectors, and power electronics converters to supply power for a plurality of electrolyzer stacks in the hydrogen production plant. A hydrogen production plant also referred to simply as a hydrogen plant, in another configuration, can comprise a plurality of electrolyzer stacks along with their respective converters and transformers as needed for power conversion and isolation, connected as distributed loads in a power system.

[0004] There are grid codes for fault ride-through (FRT) for large power generators. The ability to ride through faults, which refers to the capacity to continue operating a power generator (e.g. a wind farm) without disconnecting from the power grid during a fault condition, has been widely implemented in grid-connected power plants worldwide, including wind and solar photovoltaic plants. Currently, wind power plants are explicitly required to possess fault ride-through capabilities. For large loads, such as a large-scale hydrogen electrolyzer plants, it is important to ensure there is no sudden loss of load because of a fault situation in the power grid. As in the case of large power generators, any sudden loss of load can affect the frequency stability in the power grid. Given that future hydrogen electrolyzer plants may achieve MVA / MW ratings comparable to those of large wind power plants, it is anticipated that similar fault ride-through requirements will also be imposed on these electrolyzer plants. Therefore, solutions that can contribute to maintaining the operation of large loads similar to FRT required for power sources (e.g., a wind farm) are desired for electrolyzer plants.SUMMARY

[0005] According to an embodiment of the present disclosure, a power supply system of an electrolyzer plant is provided. The power supply system includes a converter system configured to transfer power to a plurality of electrolyzers, in the electrolyzer plant from a power source coupled to a power grid; an energy storage system arranged in the power supply system; and a control system configured to control the operation of at least one electrolyzer from the plurality of electrolyzers during a grid fault to provide a fault-ride through for the at least one electrolyzer during the grid fault, and to coordinate the supply of power to the at least one electrolyzer from at least one of the power grid and the energy storage system.

[0006] In an example, the energy storage system is connected to a DC line in the power system through a dedicated DC / DC converter.

[0007] In an example, the power supply system comprises an energy storage system connected to an AC line in the power system through a dedicated DC / AC converter.

[0008] In an example, the energy storage system is at least one of a battery energystorage system, a supercapacitor and a fuel cell-based generator.

[0009] In an example, the power source is a renewable power source, and the energy storage system compensates for supplying power to the electrolyzers during energy fluctuations in the renewable power source.

[0010] In an example, the control system is configured to operate the plurality of the electrolyzers to draw a predetermined amount of active power from the power grid to provide grid services.

[0011] In an example, the control system is configured to dynamically control the operation of the at least one electrolyzer by providing a load setpoint for the at least one electrolyzer based on the value of grid voltage during the grid fault for regulating the power drawn by the at least one electrolyzer.

[0012] In an example, the control system is configured to dynamically control the at least one electrolyzer by providing a load setpoint for the at least one electrolyzer based on the value of remaining power in the ESS during the grid fault for regulating the power drawn by the at least one electrolyzer.

[0013] In an example, the control system is configured to dynamically control the at least one electrolyzer by providing a load setpoint for the at least one electrolyzer based on the value of grid voltage during the grid fault and the value of remaining power in the ESS during the grid fault for regulating the power drawn by the at least one electrolyzer.

[0014] In an example, the control system is configured to control the operation of the at least one electrolyzer to maintain the load of the at least one electrolyzer at the same level during the grid fault as it was before the grid fault.

[0015] In an example, the control system is configured to control the operation of the at least one electrolyzer by periodically adjusting a load setpoint to reduce the load level of the at least one electrolyzer by a predetermined level during the grid fault until the detection of a recovery phase of the grid fault.

[0016] In an example, the control system is configured to dynamically control the operation the at least one electrolyzer by providing a load setpoint to first operate the at least one electrolyzer at a reduced load level and then in a standby mode during the gridfault until detection of a recovery phase of the grid fault.

[0017] In an example, the control system is configured to dynamically control the at least one electrolyzer by: providing a load setpoint to operate the at least one electrolyzer either at a reduced load or in a standby mode during the grid fault; and after detecting a recovery phase of the grid fault, providing a new load setpoint to return the at least one electrolyzer to its pre-fault load level.

[0018] In an example, during at least a portion of the grid fault period, the at least one electrolyzer is entirely powered by the energy storage system, and the control system is configured to control the energy storage system such that the power supplied from the energy storage system to the at least one electrolyzer is according to a load setpoint provided to the at least one electrolyzer.

[0019] In an example, during at least a portion of the grid fault period, the at least one electrolyzer is entirely powered by the power grid, and the control system is configured to control the converter system 10 such that the power supplied from the power grid to the at least one electrolyzer via the converter system is according to a load setpoint provided to the at least one electrolyzer.

[0020] In an example, during at least a portion of the grid fault period, the at least one electrolyzer is jointly powered by the power grid and the energy storage system and the control system is configured to control the converter system and the energy storage system such that the sum of the power supplied from the energy storage system and the power supplied from the power grid is according to a load setpoint provided to the at least one electrolyzer, and wherein the control operation by the control system is coordinated to first operate the converter system to provide maximum power from the power grid to the at least one electrolyzer and to provide balance power as needed from the ESS to meet the load of the at least one electrolyzer set by the load setpoint provided to the at least one electrolyzer.

[0021] In an example, the control system is communicatively connected to a local controller of the converter system, and a local controller of a dedicated converter of the energy storage system; and wherein the control system is implemented in a plant controller of the electrolyzer plant.

[0022] In an example, the converter system comprises a plurality of AC / DC converters, each of which is coupled to one of the plurality of electrolyzers; at least one AC / DC converter from the plurality of AC / DC converters is a thyristor-based rectifier, which is coupled in parallel with a compensation converter unit that includes a diode rectifier and a compensation DC / DC converter; and the control system is configured to operate the compensation converter unit to transfer power to the electrolyzer connected to the thyristor-based rectifier during the grid fault.

[0023] According to another embodiment of the present disclosure, a method for controlling a power supply system of an electrolyzer plant is provided. The power supply system includes a converter system configured to transfer power to a plurality of electrolyzers in the electrolyzer plant from a power source coupled to a power grid; and an energy storage system arranged in the power supply system. The method includes the step of controlling the operation of at least one electrolyzer from the plurality of electrolyzers during a grid fault to provide a fault-ride through for the at least one electrolyzer during the grid fault and coordinating the supply of power to the at least one electrolyzer from at least one of the power grid and the energy storage system.

[0024] In an example, controlling the operation of at least one electrolyzer includes providing a load setpoint to operate the at least one electrolyzer (201) either at a reduced load level or in a standby mode during the grid fault; and after detecting a recovery phase of the grid fault, providing a new load setpoint to return the at least one electrolyzer (201) to its pre-fault load level.

[0025] In an example, controlling the operation of at least one electrolyzer includes periodically adjusting a load setpoint to reduce the load level of the at least one electrolyzer by a predetermined level during the grid fault until the detection of a recovery phase of the grid fault.BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The disclosed aspects will hereinafter be described in connection with the appended drawings that are provided to illustrate but not to limit the scope of the presentdisclosure.

[0027] Figure 1 is a block diagram of a power supply system according to an embodiment of the present disclosure.

[0028] Figure 2 illustrates an exemplary implementation of the power supply system for powering a large-scale electrolyzer plant.

[0029] Figure 3 is an enlarged view of a power supply section of the power supply system, as shown in Figure 2.

[0030] Figure 4 is a flowchart of a method for controlling a power supply system integrated with an electrolyzer plant according to an embodiment of the present disclosure.

[0031] Figures 5A-5B, 6A-6B, and 7A-7B illustrate various features or modes of the method illustrated in Figure 4 under different scenarios.DETAILED DESCRIPTION

[0032] Power loss, for example caused by a grid fault in a hydrogen plant (also referred to as electrolyzer plant) can cause disruption in the production of hydrogen as the grid fault can immediately trigger an emergency shutdown of the electrolyzers in the hydrogen plant. In such cases, the electrolyzers that are shut down before operation for generation of hydrogen need to be purged with nitrogen to flush out hydrogen and oxygen that may have mixed during the grid fault which leads to a loss of power to electrolyzers. Some situations could lead to an explosion if the gases are not handled safely. Therefore, following such shutdown procedures, restarting the electrolyzers might take several minutes, which results in loss of production and also loss of load for the electrical grid. Moreover, there can be other detrimental effects because of sudden shutdown, for example sudden shutdown can induce reverse current flow from the cathode to the anode through the piping outlets, accelerating electrolyzer electrode degradation.

[0033] To address this challenge, the present disclosure introduces a power control scheme that implements a power supply solution for electrolyzers. This approach ensures that the electrolyzer plant maintains active power consumption both during andafter a grid fault and avoids any sudden change for the electrolyzer plant and also for the power grid when it has recovered from a grid fault.

[0034] According to examples of one aspect of the present disclosure, a power supply system is provided. The power supply system includes a converter system, an energy storage system (ESS), and a control system. The converter system transfers power from a power source (for example, a power grid) to a plurality of hydrogen electrolyzers (hereinafter referred to as "electrolyzers") in a hydrogen electrolyzer plant (which may also be called a hydrogen plant or an electrolyzer plant). The energy storage system is configured to supply power to the plurality of electrolyzers in the hydrogen electrolyzer plant either independently or in combination with the power grid, thereby ensuring that these electrolyzers can draw power even during a grid fault and can ride through the grid fault. During the grid fault, the control system operates the converter system and as needed the energy storage system to supply power to the plurality of electrolyzers in the electrolyzer plant and dynamically manage the operation of these electrolyzers to enable them to have fault ride-through (FRT) capability.

[0035] In examples of the present disclosure, the grid fault period includes both the period of grid voltage collapse (e.g., the duration in which the power grid voltage stays collapsed) and the period of grid voltage recovery (e.g., the duration in which the power grid voltage builds up to the normal grid voltage level). In the invention, the term grid fault is mainly used to refer to a fault in the power grid but in a general sense in view of the fault ride-through (FRT) capability for the electrolyzers refers to a fault in the main power source in an electrolyzer plant.

[0036] Figure 1 shows a power supply system 100 according to an example of the present disclosure, which includes a converter system 10, a control system 20, an ESS 30, and a dedicated converter 40 for the ESS 30. An example of ESS 30 is a Battery Energy Storage System (BESS), supercapacitors or capacitors, fuel cell-based generators or such energy storage systems.

[0037] The converter system 10 is connected between the AC power source 300 and the hydrogen electrolyzers. The AC power source 300 can either be a power grid, a supply derived from the power grid (through use of high voltage or / and medium voltagedistribution transformers) or a renewable power source (e.g. a wind or a solar farm) that may be connected to the power grid or may be operated in isolation. The converter system 10 transfers electric power from the power source 300 to a plurality of hydrogen electrolyzers in the electrolyzer plant. The voltage Vac at the input side of the converter system 10 can be regarded as the power grid voltage or as a voltage that is derived from the power grid voltage. By monitoring the voltage Vac, variations in the power grid voltage (RMS value) can be determined. The current lac at the input side of the converter system 10 is the current transferred from the power source 300 to the converter system 10. The value of this current depends on the power that is being transferred to the electrolyzers by operating the converter system 10 to produce a desired amount of hydrogen according to the set points provided to the electrolyzers.

[0038] The electrolyzer plant 200 includes a plurality of electrolyzers, such as electrolyzers 201-204. Each electrolyzer can include multiple electrolytic cells connected in series, parallel, or a combination of both. This configuration provides the electrolyzer with flexibility and diversity, making it suitable for applications at different voltage levels e.g. at LV and MV voltage levels.

[0039] The electrolyzer plant 200 refers to a collection of multiple electrolyzers designed for hydrogen production and may also denote a hydrogen plant that incorporates additional units, such as water desalination units, hydrogen storage units, and a power substation to supply electricity to the electrolyzers and various other components to support the operation of these units. Figure 1 illustrates a simplified power supply system 100 in an electrolyzer plant in accordance with an embodiment of the present disclosure. The electrolyzers may be connected between positive and negative DC terminals (refer to 10A and 10B, output of the AC -DC converter system 10 in Figure 1) of the DC side. The positive and negative busbars (DC+ and DC-) in the converter system are provisioned with a bipolar topology, DC potential (+ or -) and GND when the converter in the converter system has a unipolar topology or configuration.

[0040] During the grid fault, unless actively controlled the plurality of electrolyzers in the electrolyzer plant may not be operational due to power loss. When activelycontrolled, the electrolyzer can be operated in one or more states. For example, during a fault or failing power, the electrolyzers may transition to a different state that includes operating the electrolyzers with a new load setpoint that reduces power consumption, or ramping up to reach the pre-fault state when the power grid voltage is recovering or recovered, or operating some or all the electrolyzers in a standby mode where no hydrogen may be produced but it may be relatively easier to start hydrogen production when power source is restored (fault ceases to exist) or initiate a safe shutdown process for the electrolyzers when there is a limited backup power source or back up Energy Storage System is about to be exhausted. Such active control is provided with the control system 20.

[0041] The Energy Storage System (ESS) 30 is coupled to the converter system 10. For example, the ESS 30 is connected to a direct current (DC) bus bar connected to the output of the converter system 10 in the power supply system 100 either directly or via a dedicated DC / DC converter 40 (i.e., ESS-dedicated converter 40). By controlling the DC / DC converter 40, the power transferred from / to the ESS 30 can be regulated. For Fault Ride-Through of the electrolyzers, ESS 30 is operated to provide the balance power (ie., compensation power) required to operate the electrolyzers which may be operating in one of the operating states mentioned earlier. Further, implementation details will be further explained in conjunction with Figure 2.

[0042] According to examples of the present disclosure, the power supply system 100 may alternatively include an ESS coupled to an alternating current (AC) line in the power supply system 100 via a dedicated DC / AC converter (not shown) instead of the ESS in the DC side of the converter system 10. For example, the ESS may be connected to at least one phase of a three-phase AC line. Upon detection of a fault (e.g., voltage sag or power interruption) in said at least one phase, the ESS may provide power to the faulty phase through the dedicated DC / AC converter after isolating the faulty phase from the power grid to power the electrolyzers along with the remaining two phases continue energized by the power grid in the power source 300. Further implementation details will be further explained in conjunction with Figure 2.

[0043] The storage capacity of the ESS is predetermined based on the hydrogenproduction requirements, which are associated with the application scenario of the electrolyzer plant. For example, the storage capacity of the ESS depends on the maximum balance power that might be required during the grid fault, which is associated with the electrolyzer's load setpoint (i.e., load rate or level). The electrolyzer's load setpoint, in turn, is determined by its application scenario. For applications requiring continuous and stable hydrogen supply (e.g., steel plants), a larger ESS capacity is needed to maintain near-full load operation during the grid fault. For buffered hydrogen storage applications (e.g., hydrogen refueling stations), a smaller ESS capacity may suffice, as the electrolyzer can operate at a reduced load level or standby mode during the grid fault. Once the storage capacity of the ESS is determined, the most suitable ESS type (e.g., BESS or supercapacitors) can be selected based on technical and economic considerations.

[0044] For example, steel plants require a continuous and stable hydrogen supply. To maintain electrolyzer operation near the pre-fault level during the grid fault, the load setpoint must remain as close as possible to the pre-fault level, necessitating a large ESS storage capacity. Hydrogen storage stations, however, do not always need high hydrogen production rates. During the grid fault, the electrolyzer load setpoint can be reduced or even switched to standby mode, allowing for a smaller ESS capacity. Chemical plants often depend on precise and stable hydrogen flow for critical reactions. Any interruption could compromise product quality or even cause safety incidents. Thus, during the grid fault, the electrolyzer must maintain near-normal operation, requiring a large-capacity ESS to ensure uninterrupted power supply.

[0045] The control system 20 coordinates the control of the converter system 10 and the ESS-dedicated converter (e.g., dedicated DC / DC or DC / AC converter) to ensure that during a grid fault, either or both the power grid 300 and the ESS 30 collectively supply power to the electrolyzers in the electrolyzer plant 200, thereby enabling the electrolyzers to achieve Fault Ride-Through (FRT) capability. The control system 20 also coordinates with the electrolyzer plant by providing reference set points to the electrolyzers in view of the status or condition (e.g. grid fault condition or extent of availability of the power from the power grid, especially when the power grid is basedon renewable power sources, and state of ESS with regards to available power from the ESS, requirements relating to hydrogen production, etc.). The control system 20 is configured to detect grid related conditions and operate the converter system 10, ESS 30 directly or through the ESS-dedicated converter to provide power to the electrolyzers to operate the electrolyzers without any interruptions even during the grid fault condition. The control system can also be configured to coordinate with the electrolyzers to change the operating states of the electrolyzers in response to the detected or determined conditions relating to the power grid and ESS.

[0046] In another example, the control system 20 is configured as a plant-level controller for the hydrogen plant or as a high-level controller for a section of the hydrogen plant to coordinate with one or more local controllers and additional controllers (e.g., an electrolyzer controller, a ESS controller, converter system controller). For instance, the control system 20 can communicate with an electrolyzer controller (200C in Figure 1), which manages the operations of the electrolyzers within the electrolyzer plant. The control system 20 can obtain electrolyzer-related parameters (e.g., operational parameters) and transmit load setpoints, i.e., electrolyzer load value or corresponding values for H2 production to the electrolyzer controller 200C. The control system 20 can communicate with a grid controller (not shown) to obtain grid-related parameters, including power dispatch values for operating the electrolyzer plant 200 (i.e., active power the electrolyzer plant 200 can draw from grid 300). The control system 20 can communicate with a local controller 10C of the converter system 10 to receive voltage and current measurements from both the input and output sides of the converter system 10 and send power setpoints to the local controller 10C for operating the converter system 10. The control system 20 can communicate with a local controller 40C of the ESS-dedicated converter 40 and / or ESS 30 to obtain the available power capacity (remaining energy) of the ESS 30 and transmit power setpoints to the local controller 40C for operating the ESS-dedicated converter 40.

[0047] In an example, the control system 20 can be deployed within the plant controller of the hydrogen electrolyzer plant. In another example, some or all the functions of the control system 20 can be integrated (embedded) into either the local controller 10C orthe local controller 40C or with the electrolyzer controller 200C. In yet another example, the control system 20 can include a controller that controls the operation of the power supply system and the electrolyzers.

[0048] Figure 2 illustrates a power supply system configuration, which is connected to a power grid 300, for powering a large-scale electrolyzer plan. The main components of the power supply system 100 and various arrangements of the ESS in the power supply system 100 will be described below with reference to Figure 2.

[0049] Referring to Figure 2, the power supply system 100 includes multiple substations 11 and 12 and an optional static synchronous compensator (STATCON) 13. Each substation supplies power to a portion of the plurality of electrolyzers. For clarity, only two substations, namely, first and second substations 11 and 12, are shown in Figure 2 connected with electrolyzers.

[0050] Each substation of the power supply system 100 can be implemented in a similar manner. Below, the first substation 11 will be used as an example to illustrate the implementation of a power supply system for electrolyzers.

[0051] With continued reference to Figure 2, the first substation 11 includes a power transformer 112 to step down the high voltage from the power grid to a medium voltage level, a first power supply section 114, and a second power supply section 116. The primary winding 112A of the transformer 112 is coupled to the power grid 300, and the two secondary windings 112B and 112C are respectively coupled to the first power supply section 114 and the second power supply section 116. The transformer 112 is used to reduce the voltage (e.g., high voltage) from the power grid 300 and transmit the reduced voltage, such as medium voltage, to the first and second power supply sections 114 and 116. Therefore, the transformer 112 may be referred to as an upstream stepdown transformer 112.

[0052] In general, each power supply section (114, 116) is configured to power a set of electrolyzers and includes a plurality of downstream step-down transformers for converting medium voltage to low voltage, as well as a plurality of sets of AC / DC converters. Each set of AC / DC converters is coupled to a corresponding downstream step-down transformer at its input and electrolyzers at its output. Each power supplysection is implemented in a similar manner. Below, using the first power supply section 114 as an example, the implementation of the power supply section will be described.

[0053] For clarity, an enlarged view of the first power supply section 114 is shown in Figure 3. It should be noted that, in addition to the converters 1143-1146 included in the power supply section 114, which are shown within the dashed box in Figure 3, the converter system 10 may also include converters included in other power supply sections, such as 116, 124, and 126.

[0054] Referring to Figure 3, the first power supply section 114 comprises a first downstream step-down transformer 1141 coupled to a set of AC / DC converters 1143 and 1144, and a second downstream step-down transformer 1142 coupled to another set of AC / DC converters 1145 and 1146. The first and second downstream step-down transformers 1141 and 1142 are used to reduce the voltage from the transformer 112, for instance, converting medium voltage to low voltage. The primary winding 1141 A of the first downstream step-down transformer 1141 and the primary winding 1142 A of the second downstream step-down transformer 1142 are respectively connected to the secondary winding 112B of the upstream transformer 112. One secondary winding 114 IB of the first downstream step-down transformer 1141 is connected to the AC / DC converter 1143, which powers the electrolyzer 201. Another secondary winding 1141C of the first downstream step-down transformer 1141 is connected to the AC / DC converter 1144, which powers the electrolyzer 202. Similarly, one secondary winding 1142B of the second downstream step-down transformer 1142 is connected to the AC / DC converter 1145, which powers the electrolyzer 203. Another secondary winding 1142C of the second downstream step-down transformer 1142 is connected to the AC / DC converter 1146, which powers the electrolyzer 204.

[0055] According to examples of the present disclosure, each AC / DC converter can be implemented in various ways, such as through a thyristor-based rectifier, a Voltage Source Converter (VSC), a diode rectifier in conjunction with a DC / DC converter, and so forth.

[0056] In the example where the AC / DC converter is implemented as a thyristor-based rectifier, a compensation converter unit (not shown), which includes a diode rectifierand a compensation DC / DC converter, is coupled in parallel to the thyristor-based rectifier. In this example, when the grid voltage is below a predefined voltage level (i.e., the minimum AC voltage required by the thyristor-based rectifier to facilitate power transfer from AC to DC), for example during a period when the grid voltage is greater than the critical supply voltage V* (to be described below) and less than the aforementioned predefined voltage level , the compensation converter unit is operated to transfer power from the grid to the electrolyzer. This operation ensures continuous power supply, keeps the electrolyzer online, and prevents an emergency stop. The predefined voltage level for example is 0.9pu or 0.95pu and above. In this case, the thyristor-based rectifier will remain inactive until the grid voltage exceeds the aforementioned predefined voltage level.

[0057] The diode rectifier and the compensation DC / DC converter can be rated at a low power level (e.g., the minimum power required for the operation of the electrolyzer). This is because they only need to maintain the electrolyzer to operate with a minimal power supply or at a standby mode during a grid fault. As a result, the compensation converter unit remains low- cost hardware. During normal operation, the compensation converter unit can be bypassed or work in parallel with the main power supply.

[0058] In addition, according to examples of the present disclosure, the power supply system 100 can include a plurality of switches arranged at different positions within the power supply system 100, such as circuit breakers, switchgear, or disconnectors. Configuring these switches can enhance the flexibility and reliability of the power supply system 100. For example, during maintenance or troubleshooting, a faulty component can be isolated by operating the corresponding switch, thereby ensuring the normal operation of other components.

[0059] In an embodiment, referring to Figure 2, the power supply system 100 includes one or more of the following switches: a switch 113 arranged between the high-voltage (HV) busbar and the primary winding 110A of the upstream step-down transformer 112, a switch 115 arranged between the secondary winding 112B of the upstream step-down transformer 112 and the medium-voltage (MV) busbar, and a switch 117 arranged between the MV busbar and the primary winding 1141 A or 1142 A of the downstreamstep-down transformer 1141 or 1142. By operating these switches, it is possible to electrically connect or disconnect a set of electrolyzers. In addition, although not shown, switches can also be provided between each AC / DC converter and the corresponding electrolyzer. By operating these switches, the power supply to a single electrolyzer can be electrically connected or disconnected.

[0060] As mentioned earlier, the second power supply section 116 can be implemented in a manner similar to that of the first power supply section 114; the second substation 12 can be implemented in a manner similar to that of the first substation 11, and therefore, no further details are provided here other than making a reference to the similarity.

[0061] Below, some configurations of the (additional ESSs) coupled with AC lines are described.

[0062] In the first substation 11, one or more ESSs can be arranged at one or more of the following locations, with each ESS is coupled to one phase of the coupled AC line: coupled to the HV busbar; on the primary side of the upstream step-down transformer 112 (e.g., between the primary winding 112A of the upstream step-down transformer 112 and the switch 113); on the secondary side of the upstream step-down transformer 112 (e.g., between the secondary winding 112B of the upstream step-down transformer 112 and the first power supply section 114, or between the secondary winding 112C of the upstream step-down transformer 112 and the second power supply section 116); on the primary side of the first downstream step-down transformer 1141 (e.g., between the primary winding 1141 A of the first downstream step-down transformer 1141 and the switch 117); on the secondary side of the first downstream step-down transformer 1141 (e.g., between the secondary winding 1141B of the first downstream step-down transformer 1141 and the AC / DC converter 1143, or between the secondary winding 1141C of the first downstream step-down transformer 1141 and the AC / DC converter 1144); on the primary side of the second downstream step-down transformer 1142 (e.g., between the primary winding 1142 A of the second downstream step-down transformer 1142 and the switch 117); and on the secondary side of the second downstream stepdown transformer 1142 (e.g., between the secondary winding 1142B of the seconddownstream step-down transformer 1142 and the AC / DC converter 1145, or between the secondary winding 1142C of the second downstream step-down transformer 1142 and the AC / DC converter 1146).

[0063] It should be noted that energy storage systems connected at different locations (i.e., connected to different voltage levels) can have different storage capacities, and correspondingly, varying power compensation capabilities. These energy storage systems can additionally be used to provide grid services, especially when connected with a renewable power source.

[0064] In the second substation 12, one or more ESSs can be arranged in a manner similar to that described above. The arrangement in the second substation 12 may differ from that in the first substation 11, for example, in terms of quantity and / or location.

[0065] Below, some configurations of ESSs coupled with DC lines are described.

[0066] In the first substation 11, one or more ESSs can be arranged on the DC sides of one or more AC / DC converters, for example, between an AC / DC converter and the corresponding electrolyzer.

[0067] In the second substation 12, one or more ESSs can be arranged in a manner similar to that described above. The arrangement in the second substation 12 may differ from that in the first substation 11, for example, in terms of quantity and / or location.

[0068] According to an example of the present disclosure, the power supply system 100 can be expanded by including additional substations. In this way, more electrolyzers can be powered by the expanded power supply system. This configuration is useful for efficiently supplying power to large-scale electrolyzer plants.

[0069] According to examples of another aspect of the present disclosure, a method for controlling the power supply system 100 is provided. Figure 4 is a flowchart of an exemplary control method 400 for controlling the power supply system 100. The control method 400 can be executed by the aforementioned control system 20.

[0070] According to the control method 400, the operation of each electrolyzer in the plurality of the electrolyzers can be controlled, or only the operation of some electrolyzers in the plurality of the electrolyzers may be controlled. For simplicity and clarity, the control method 400 will be described below using an example in which thecontrol system 20 controls the operation of one electrolyzer, such as electrolyzer 201, making reference to the power drawn by the electrolyzer 201. The method is applicable also to the plurality of the electrolyzer, in which case the total power drawn by the plurality of the electrolyzers needs to be considered. The operation of individual electrolyzers or / and the plurality of the electrolyzers can be controlled by a controller of the electrolyzers, for example through a local controller 200C.

[0071] The electric power transferred to the electrolyzer 201 includes the following three situations. 1) The electrolyzer 201 receives electric power only from the power grid 300. In this case, the current IELE of the electrolyzer 201 equals the current IDCI transmitted to the electrolyzer 201 through the converter system 10. 2) The electrolyzer 201 receives electric power only from the ESS 30. In this case, the current IELE of the electrolyzer 201 equals the current IDC2 transmitted to the electrolyzer 201 through the dedicated converter 40. 3) The electrolyzer 201 receives electric power from both the power grid 300 and the ESS 30. In this case, the current IELE of the electrolyzer 201 equals the sum of the current IDCI transmitted to the electrolyzer 201 through the converter system 10 and the current IDC2 transmitted to the electrolyzer 201 through the dedicated converter 40, i.e., IELE = IDCI + IDC2.

[0072] In general, during a grid fault, the operation of electrolyzer 201 is dynamically controlled by supplying electric power from the power grid 300 and / or the ESS 30 to the electrolyzer 201, thereby enabling fault ride-through (FRT) capability for the electrolyzer 201 during the grid fault. The power drawn by the electrolyzer 201 is controlled using the load setpoint for the electrolyzer 201. The control of the electrolyzer's 201 operation includes coordination with converter controllers to supply power to the electrolyzer 201 according to the load setpoint for the electrolyzer 201.

[0073] With reference to Figure 4, at block 410, the control system 20 detects whether a grid fault occurs based on at least one grid-related parameter. The power grid-related parameter(s) may be obtained from either:(a) a grid voltage measurement at the point of common coupling (PCC) or at any of the bus bars or transformers illustrated in Figure 2, or at the input of the converter system 10, or (b) an activation signal from a protection device within electrolyzer plant.

[0074] The grid fault refers to a fault in the power grid, for example, a short circuit fault in a portion of the power grid 300 that causes a sudden fall in the power grid voltage. In such a scenario, the power grid voltage suddenly drops from a normal level to a low value, sometimes zero or nearly zero for a short duration. In another situation when the grid fault is in one of the phases in three phase system, the drop in the voltage will be seen in the phase that has a fault. The power may still be transferred to the electrolyzers from the healthy phases, and if the power is not sufficient to operate the electrolyzers at the pre-fault level, balance power will be provided by the ESS.

[0075] The power grid-related parameters that can indicate a fault include voltage, current, or the rate of change in voltage over time measured on the input side of the converter system 10. The power grid-related parameters can also include voltage, current, or the rate of change of voltage over time measured at the PCC (Point of Common Coupling). Additionally, the power grid-related parameters can include estimated values derived from measured values. For instance, some parameters that cannot be obtained through direct measurement can be acquired through calculation or estimation processes in the control system 20. The control system 20 acquires or tracks the power grid voltage, as well as active power load values contributed by the electrolyzers to operate the electrolyzers if needed for providing grid services.

[0076] In an example, the control system 20 can detect protection device activation signals. A low-voltage grid fault may trigger the activation of protection devices, such as a protection relay. The control system 20 can infer the occurrence of a low-voltage grid fault by receiving activation signals from these protection devices.

[0077] Upon detection of a grid fault, method 400 will proceed to block 420. If no grid fault is detected, block 410 will be repeatedly executed until a grid fault is detected, and then method 400 will proceed to block 420.

[0078] At block 420, the control system 20 determines whether the current grid voltage is greater than the critical supply voltage V*, and whether the electrolyzer 201 needs to draw power from the ESS 30 and then control the operation of the electrolyzer (201) based on the determinations and coordinate the supply of power to the electrolyzer 201 from at least one of the power grid (300) and the energy storage system (30).

[0079] In an example, controlling the operation of electrolyzer 201 includes continuous adjustment, such as modifying the load setpoint based on variations in the power grid voltage. In another example, controlling the operation of electrolyzer 201 includes step changes in the load setpoint for the electrolyzer 201, e.g., reducing the load setpoint from 50% load rate (load setpoint value) to 20% load rate (load setpoint value), and stepwise increasing the load setpoint for the electrolyzer 201 during grid recovery when the power grid voltage is sufficiently recovered (e.g., the power grid voltage is restored to a value above 0.8 pu).

[0080] The critical supply voltage V* is predetermined. When the power grid voltage is less than or equal to V*, loads (e.g., electrolyzer 201) are prohibited from drawing power from the power grid 300. When the power grid voltage is greater than the critical supply voltage V*, loads (e.g., electrolyzer 201) are permitted to draw power from the power grid 300. In Figures 5A and 6A, the critical supply voltage V* is illustrated as 0.2 pu. It should be understood that this value is merely an example, and the critical supply voltage may be preset to other values in compliance with applicable grid codes.

[0081] According to examples of the present disclosure, the critical supply voltage V* can be preset based on one or more of the following factors: 1) grid codes, regulations, or standards (where the critical supply voltage V* will be adjusted accordingly when the power grid codes, regulations, or standards change); 2) rules set by converter suppliers for the converters in the power system (e.g., based on the requirements for conversion efficiency of the converters, loads / electrolyzers are allowed to draw power from the power grid through the converters only when the power grid voltage is greater than the critical supply voltage V*); 3) stability requirements for the electrolyzer plant (e.g., according to historical data and / or model calculations, if the power grid voltage is less than or equal to the critical supply voltage V*, drawing power from the power grid would cause the operational stability of the electrolyzer plant to fall below a stability threshold; thus, the critical supply voltage V* is derived as the critical grid voltage ensuring that the plant’s operational stability meets the stability threshold).

[0082] In general, whether the electrolyzer 201 needs to draw power from the ESS 30is determined based on the power that is still possible to be provided to the electrolyzer 201 by the power grid 300 and the demand power of the electrolyzer 201 to be operated uninterrupted at the same level as that before the fault and without overstressing any of the components in the power supply system (for example converter system 10 which because of the low voltage situation will be getting operated to draw increased current lac to transfer the same value of power as that transferred during the normal operation).

[0083] Specifically, when the power that the power grid 300 can provide to the electrolyzer 201 is greater than or equal to the demand power of electrolyzer 201 (which may correspond to its load setpoint), the control system 20 determines that the demand power of the electrolyzer 201 is completely provided by the power grid 300 even during the fault without overstressing the converter system 10 (lac is within the specified max limit) and does not need to draw power from the ESS 30.

[0084] When the power that can be provided by the power grid 300 to the electrolyzer 201 is less than the demand power of electrolyzer 201 or the converter system 10 is likely to be overstressed due to an overcurrent situation i.e. when the converter system 10 is operated to deliver the demand power of electrolyzer 201, the current lac through the power devices is likely to be above its maximum current (maximum current limit) or power conversion is beyond the capability of the converter system 10 because of lower voltage at the input of the converter system 10, the control system 20 operates the converter system 10 at its maximum current limit and determines that balance power from ESS 30 is needed and provides a power setpoint to ESS 30 for the balance power. Therefore, when the current lac input to the converter system 10 has reached its maximum current limit, the control system 20 determines that the electrolyzer 201 needs to draw power from the ESS 30. If the current lac input to the converter system 10 has not reached its maximum current limit, the control system 20 determines whether it can meet the power demand of the electrolyzer 201 after adjusting the current input to the converter system 10 to the maximum current limit. If so, the control system 20 determines that the electrolyzer 201 does not need to draw power from the ESS 30; if not, the control system 20 determines that the electrolyzer 201 needs to draw power from the ESS 30.

[0085] The control system 20 coordinates with the electrolyzer controller 200C to operate the electrolyzer 201 to draw power according to the load setpoint provided by the control system 20. The control system 20 can control the converter system 10 to adjust the power (voltage and / or current) transferred to the electrolyzer 201 from the converter system 10, thereby regulating hydrogen production (i.e., the load of the electrolyzer 201). The electrolyzer controller 200C manages the auxiliary components of the electrolyzer 201 based on the load setpoint provided to the electrolyzer 201.

[0086] Detailed implementations of block 420 for different cases are described below.

[0087] Case I

[0088] Referring to block 421, when the current grid voltage is greater than the critical supply voltage (V*) during the gird fault, the operation of the electrolyzer 201 can be adjusted to standby mode or with a reduced load setpoint. This adjustment will require less power than the power required at the pre- fault level and ensure that the current input to the converter system remains within the limit of its maximum current. In this scenario, the electrolyzer 201 does not need to draw power from the ESS 30, and the electrolyzer 201 operates solely on power from the power grid 300. The control system 20 dynamically regulates the operation of the converter system 10 depending on the change in the input voltage at the converter system 10 during the fault period including the change in the voltage during the recovery period. In an example, the control system 20 determines a setpoint SP1 (power setpoint) for the converter system 10 and transmits the determined setpoint SP1 to converter system 10 (for example to the local controller 10C, and then the local controller 10C operates the converter system 10 according to the setpoint SP1) to ensure that the power supplied to the electrolyzer 201 from the power grid 300 matches the power, which is according to a load setpoint determined by the control system 20 for of the electrolyzer 201. The setpoint SP1, for example, is a current setpoint or a power setpoint. The control system 20 can determine the load setpoint for the electrolyzer 201 based on the value of the power grid voltage Vac during the grid fault. During the duration in which the power grid voltage is changing, the control system 20 dynamically adjusts the load setpoint for the electrolyzer 201 according to the changes in the power grid voltage. During at least a portion of the gridfault period, the control system 20 can determine the load setpoint for the electrolyzer 201 to maintain the load of the electrolyzer 201 at the same level during the grid fault as it was before the grid fault.

[0089] Case II

[0090] Referring to block 422, when the power grid voltage Vac during the grid fault is greater than the critical supply voltage V*, and even if the current input to the converter system is adjusted to its maximum current, the power required by the electrolyzer 201 will still not be satisfied, the converter system will be controlled to transfer the maximum power that can be drawn from the power grid. In this case, the electrolyzer 201 will need to draw power from the ESS 30. The control system 20 coordinately controls the converter system 10 and the ESS 30 (for example through the dedicated converter 40). This ensures that the power provided to the electrolyzer 201 from both the power grid 300 and the ESS 30 matches the power, which is according to a load setpoint determined by the control system 20 for the electrolyzer 201. In an example, the control system 20 implements maximum current control for the converter system 10 by setting the setpoint SP1 for the converter system 10 to make its output current be the maximum current limit (e.g., the maximum value within its adjustable range), that is, IDCI equals the maximum current limit of the converter system 10. Then, the control system 20 calculates the supplemental current IDC2 required from the ESS 30 based on the equation TELE = IDCI + IDC2. Based on the calculated value of IDC2, the control system 20 determines a setpoint SP2 (power setpoint) for the dedicated converter 40 and sends the determined setpoint SP2 to the ESS 30, for example to the local controller 40C and the local controller 40C will then operate the dedicated converter 40 according to setpoint SP2. The control system 20 can determine the load setpoint for the electrolyzer 201 based on the value of the power grid voltage Vac and the value of the remaining power of the ESS 30 during the grid fault.

[0091] In an example, during the duration in which the power grid voltage is changing, the control system 20 dynamically controls the operation of the electrolyzer 201 by providing the load setpoint to first operate the electrolyzer 201 at a reduced load level and then in a standby mode during the grid fault until detection of a recovery phase ofthe grid fault.

[0092] In another example, the control system 20 dynamically controls the electrolyzer 201 by providing load setpoints to operate the at least one electrolyzer (201) either at a reduced load level or in a standby mode during the grid fault; and after detecting a recovery phase of the grid fault, providing a new load setpoint to return the electrolyzer 201 to its pre-fault load level.

[0093] In case II, as the power grid voltage Vac increases during the power grid recovery period, a situation may arise where a power supply from the ESS 30 is no longer required. That is, the electrolyzer 201 becomes entirely powered by the power grid 300. At this point, the control system 20 applies the same control method / strategy as described in Case I above.

[0094] Case III

[0095] Referring to block 423, when the current grid voltage Vac is less than the critical supply voltage V*, the electrolyzer 201 is entirely powered by the ESS 30, the control system 20 operates the ESS 30, for example by operating the dedicated converter 40. The control system 20 determines a setpoint SP2 for the dedicated converter 40 and sends the determined setpoint SP2 to the local controller 40C. This ensures that the power provided to the electrolyzer 201 from the ESS 30 matches the power, which is according to a load setpoint determined by the control system 20 for of the electrolyzer 201. During the duration in which the power grid voltage is changing, the control system 20 dynamically adjusts the load setpoint for the electrolyzer 201 according to the changes in the power grid voltage. During at least a portion of the grid fault period, the control system 20 can determine the load setpoint for the electrolyzer 201 to maintain the load of the electrolyzer 201 at the same level during the grid fault as it was before the grid fault.

[0096] In case III, as the power grid voltage Vac increases, when it exceeds the critical supply voltage V*, the electrolyzer 201 enters the aforementioned co-supply mode, receiving power from both the power grid 300 and the ESS 30. The control system 20 applies the same control strategy as described in Case II. With a further increase in the power grid voltage Vac, when the ESS 30 becomes unnecessary and the electrolyzer201 transitions to full grid supply, the control system 20 applies the same control strategy as described in Case I.

[0097] Case IV

[0098] Referring to block 424, if the power grid voltage fails to begin recovery within a predetermined time period and the remaining energy of the ESS 30 may become insufficient to support the electrolyzer 201 in reaching its pre-fault state after a certain predefined time period (e.g., when the ESS 30's capacity is likely to be depleted after a predefined time period, say lOmin), the control system 20 will generate a new load setpoint (a new load value) for the electrolyzer 201 so that the electrolyzer 201 can be operated to consume lesser power from the ESS 30.

[0099] For the new load setpoint, in one scenario, the control system 20 reduces the load level of the electrolyzer 201 relative to its present level (e.g., decreasing the load level from the present 80% loading to 50% loading). In another scenario, if the ESS 30’s remaining capacity is extremely limited to sustain powering the electrolyzer 201 even with the reduced load level and the power grid 300 is not yet in the recovery phase, the control system 20 can periodically determine a further reduced new load setpoint (e.g., further decreasing the load level from the present 50% loading to a 20% loading), the stepwise reduction continues until the further reduction would cause the power supply to the electrolyzer 201 to fall below its minimum operating power, in which case the final load setpoint will correspond to the standby power level of the electrolyzer 201 or until a recovery in the power grid voltage is detected by the control system 30. In yet another scenario where the ESS 30 is on the verge of complete depletion, the control system 20 will control the electrolyzer 201 to safely shut down by utilizing the remaining energy of the ESS 30.

[0100] The method 400 under different scenarios will be described further with reference to Figures 5A-5B, 6A-6B, and 7A-7B. These figures are exemplary illustrations to depict control method of the invention and are not necessarily made to scale, for example the slopes depicted in the figures may vary according to the type of grid faults, the response time of the controller and electrolyzers.

[0101] Figures 5A-5B, 6A-6B, and 7A-7B illustrate various features or modes ofmethod 400 under different scenarios. In the graphs of Figures 5A-5B, 6A-6B, and 7A-7B, the horizontal axis (X-axis) represents time. In the graphs of Figures 5 A, 6A and 7A, the vertical axis (Y-axis) represents voltage. The solid line Vac represents the changes in power grid voltage over time. In the graphs of Figures 5B, 6B and 7B, the horizontal axis (X-axis) represents time, and the vertical axis (Y-axis) represents power, where Porid represents the changes in electric power supplied by the power grid 300 to the electrolyzer 201 through the converter system 10 over time; PESS represents the changes in electric power supplied by the ESS 30 to the electrolyzer 201 over time; and PELE represents the changes in electric power drawn or received by the electrolyzer 201 from either the power grid 300, the ESS 30, or a combination of both over time.

[0102] In Figures 5A, 6A and 7A, the power grid voltage curve is provided based on grid codes as a reference for the behavior of the electrolyzer plant (or a portion thereof) in response to a grid fault. In some examples, the power grid voltage curve corresponds to the reference Fault Ride-Through (FRT) voltage curve for the electrolyzer 201. The reference FRT voltage curve aligns with relevant standards (such as international, national, and industry standards) and can be adjusted according to updates to these standards. To illustrate the FRT capability of the electrolyzer 201, an FRT voltage curve derived from established FRT voltage profiles, which is similar to those used for grid-connected power sources (e.g., wind farm power systems), is employed.

[0103] With reference to Figures 5A-5B, 6A-6B, and 7A-7B, at time tO, the electrolyzer 201 operates normally to produce hydrogen and, if necessary, is used to provide grid services by drawing an assigned active power from the power grid. At this point, the power grid is working normally i.e. there is no grid fault, and the electrolyzer 201 for the sake of this example is being operated to contribute to an 80% load level (pre-fault load level). At time tl, a grid fault occurs, causing a voltage collapse in the power grid voltage. Upon grid fault detection, the control system (20) dynamically regulates the electrolyzer (201) operation through coordinated control of the converter system (10) and ESS (30).

[0104] With continued reference to Figures 5A-5B, 6A-6B, and 7A-7B, from timetO to tl, the power grid voltage remains at a normal level, for reference, it is considered here as 1.0 pu. At time tl, the power grid voltage collapses due to a grid fault and remains depressed until time t2 during which time the fault is isolated or cleared. During the period from time tl to t2, the power grid voltage dips to its lowest level depending on the type of the fault. The voltage dip may be either a zero voltage (as shown in Figures 5A and 6A) or a non-zero low voltage (e.g., 0.3 pu, as illustrated in Figure 7A). Grid voltage recovery begins at time t2 and is completed at time t4 at which point the power grid voltage has sufficiently recovered (e.g. 0.9 pu or 1.0 pu). Desirably for maintaining grid codes, the electrolyzer 201 restores its power consumption to the prefault state (pre-fault level) within a predetermined duration after the power grid voltage recovers to a predetermined level, such as the normal level or 85% to 90% of the normal level. This restoration process is illustrated in these Figures, where the active load of electrolyzer 201 returns to the pre-fault state at time t5.

[0105] Referring to Figures 5A and 5B, a case where the power grid voltage totally collapses during the grid fault (from time tl to time t4), the electrolyzer 201 's load rate remains constant at its pre-fault level (e.g., 80%) during the grid fault. From time tl to t2, the power grid voltage Vac is nearly zero; the electrolyzer 201 operates entirely on ESS 30 power during the grid fault; and the control system 20 operates according to the strategy described in Case III above to power the electrolyzer 201 with power from the ESS 30. From time t2 to t3, although the power grid voltage Vac is recovering, it remains below the critical supply voltage V*, and the load is prohibited from drawing power from the power grid 300. Thus, during this time period, the electrolyzer 201 is still fully powered by the ESS 30, and the control strategy remains identical to the tl-t2 period. From t3 to t5, the power grid voltage Vac exceeds V*, allowing the load to draw power from the power grid 300. During this time period, the electrolyzer 201 is powered by the power grid 300 and the ESS 30 in coordination. In an embodiment, during this period, as the power grid voltage increases, the power supply from the power grid 300 to the electrolyzer 201 increases at a predetermined slope following the rate at which the power grid voltage is recovering, and the power drawn from the ESS 30 to the electrolyzer 201 decreases at a corresponding rate. The sum of the power drawnfrom the power grid 300 and the ESS 30 equals the power required by the electrolyzer 201 to maintain its operation at the pre-fault level; that is, in this example, the load setpoint for the electrolyzer 201 always corresponds to the power to operate the electrolyzer 201 at an 80% load rate (80% load level).

[0106] Referring to Figures 6A and 6B, during the time period tl to t2, the power grid voltage is nearly zero. At time tl, the control system 20 determines a new load setpoint for the electrolyzer 201 (e.g., 20%), which is reduced compared to the pre-fault load setpoint (80%). From time tl to t2, the electrolyzer 201 is entirely powered by the ESS 30. The control system 20 follows the strategy to power the electrolyzer 201 with an ESS-only supply case described in Case III. From t2 to t3, although the power grid voltage Vac is recovering, it remains below the critical supply voltage V*, and the load is prohibited from drawing power from the power grid. Thus, during this time period, the electrolyzer 201 is still fully powered by the ESS 30, and the control strategy remains identical to the tl-t2 period. From time t3 to t5, the power grid voltage Vac exceeds V*, allowing the load to draw power from the power grid 300. The electrolyzer 201 receives coordinated power from both the power grid 300 and the ESS 30. The control system 20 dynamically increases the load setpoint for the electrolyzer 201, as illustrated in Figures 6A and 6B, after the power grid starts to recover, in which case the load setpoint for the electrolyzer 201 is associated with the rate at which the power grid is recovering and balance power needed is provided by the ESS 30. Another way to implement powering the electrolyzer 201 at the pre-fault level is to issue a step change in the load setpoint at the time the power grid 300 has sufficiently recovered, in which case the electrolyzer 201 will draw power according to its own response rate to the step change in the load setpoint. In Figure 6B, by time t5, the load setpoint returns to the pre-fault level (e.g., 80%). The control system 20 follows the strategy of providing a coordinated supply to the electrolyzer 201, according to the case described in Case II.

[0107] Referring to Figures 7A and 7B, during the time period tl to time t2, the power grid voltage is at a non-zero low voltage level, such as 0.3 pu. In this embodiment, the lowest voltage level is already greater than the critical supply voltage V*, so thereis no situation where the load is prohibited from drawing power from the power grid. After detection of the grid fault, i.e. after time tl, the control system 20 determines a new load setpoint of 50% for the electrolyzer 201, which is lower than the pre-fault load setpoint of 80%. During the time period tl to time t2, the power supplied to the electrolyzer 201 is partially from the power grid 300 and partially from the ESS 30. The control system 20 controls the converter system 10 in the maximum current mode (e.g., maximum power point tracking (MPPT) mode), so that the electrolyzer 201 receives as much power as possible from the power grid 300, while the ESS 30 provides the balance power required to meet the power corresponding to the new load setpoint of 50%. During the time period t2 -t3, although the power grid voltage is climbing, the control strategy for this time period is the same as that for the time period tl-t2 because the control system 20 has not changed the load setpoint of the electrolyzer 201. During the time period t3 to t5, the control system 20 dynamically increases the load setpoint of the electrolyzer 201 until the load setpoint of the electrolyzer 201 equals the pre-fault load setpoint by time t5. For this time period, the control system 20 follows the control strategy for providing a coordinated supply to the electrolyzer 201, a case described in Case II.

[0108] It should be noted that Figures 5A-5B, 6A-6B, and 7A-7B present exemplary implementations only. Any implementation incorporating control strategies described in one or more of Cases I-IV can be realized through appropriate application or combination of the above embodiments and shall fall within the protection scope of the present disclosure.

[0109] According to examples of the present disclosure, the energy storage system 30 can be used either in scenarios where electrolyzers operate based on a dispatch value supplied by the power grid controller to the control system 20 and the energy storage system 30 helps to provide fault ride-through to the electrolyzers, or in scenarios where fluctuations in the power source are compensated by the energy storage system 30, particularly when the power source comprises a renewable power source. Thus, the energy storage system helps in providing grid service along with the electrolyzers that draw active power according to the dispatch value to provide grid services.

[0110] The previous description is provided to enable any person skilled in the art to practice the various aspects described herein. Various modifications to these aspects will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other aspects. Thus, the claims are not intended to be limited to the aspects shown herein. All structural and functional equivalent transformations to the elements of the various aspects of the present disclosure, which are known or to be apparent to those skilled in the art, are intended to be covered by the claims.

Claims

WHAT IS CLAIMED IS:

1. A power supply system (100) for an electrolyzer plant (200), comprising: a converter system (10) configured to transfer power to a plurality of electrolyzers (201, 202, 203, 204) in the electrolyzer plant (200) from a power source (300) coupled to a power grid;an energy storage system (30) arranged in the power supply system (100); and a control system (20) configured to control the operation of at least one electrolyzer (201) from the plurality of electrolyzers (201, 202, 203, 204) during a grid fault to provide a fault-ride through for the at least one electrolyzer (201) during the grid fault, and to coordinate the supply of power to the at least one electrolyzer (201) from at least one of the power grid and the energy storage system (30).

2. The power supply system (100) of claim 1, wherein the energy storage system (30) is connected to a DC line in the power system (100) either directly or via a dedicated DC / DC converter (40).

3. The power supply system (100) of claim 1, wherein the power supply system (100) comprises an energy storage system connected to one phase of an AC line in the power system (100) via a dedicated DC / AC converter.

4. The power supply system (100) of claim 1, wherein the energy storage system comprises at least one of a battery energy storage system, a supercapacitor and a fuel cell-based generator.

5. The power supply system (100) of claim 1, wherein the power source (300) comprises a renewable source and the energy storage system (30) compensates for supplying power to the plurality of electrolyzers (201, 202, 203, 204) during energy fluctuations in the renewable power source.

6. The power supply system (100) of claim 1, wherein the control system (20) is configured to operate the plurality of the electrolyzers to draw a predetermined amount of active power from the power grid to provide grid services.

7. The power supply system (100) of claim 1, wherein the control system (20) is configured to dynamically control the operation of the at least one electrolyzer (201) by providing a load setpoint for the at least one electrolyzer (201) based on the value of grid voltage during the grid fault for regulating the power drawn by the at least one electrolyzer (201).

8. The power supply system (100) of claim 1, wherein the control system (20) is configured to dynamically control the operation of the at least one electrolyzer (201) by providing a load setpoint for the at least one electrolyzer (201) based on the value of remaining power in the energy storage system (30) during the grid fault for regulating the power drawn by the at least one electrolyzer (201).

9. The power supply system (100) of claim 1, wherein the control system (20) is configured to dynamically control the operation of the at least one electrolyzer (201) by providing a load setpoint for the at least one electrolyzer (201) based on the value of grid voltage during the grid fault and the value of remaining power in the energy storage system (30) during the grid fault for regulating the power drawn by the at least one electrolyzer (201).

10. The power supply system (100) of claim 1, wherein the control system (20) is configured to control the operation of the at least one electrolyzer (201) to maintain the load of the at least one electrolyzer (201) at the same level during the grid fault as it was before the grid fault.

11. The power supply system (100) of claim 1, wherein the control system (20) is configured to control the operation of the at least one electrolyzer (201) by periodicallyadjusting a load setpoint for the at least one electrolyzer (201) to reduce the load level of the at least one electrolyzer (201) by a predetermined level during the grid fault until detection of a recovery phase of the grid fault.

12. The power supply system (100) of claim 1, wherein the control system (20) is configured to dynamically control the operation the at least one electrolyzer (201) by providing a load setpoint for the at least one electrolyzer (201) to first operate the at least one electrolyzer (201) at a reduced load level and then in a standby mode during the grid fault until detection of a recovery phase of the grid fault.

13. The power supply system (100) of claim 1, wherein the control system (20) is configured to dynamically control the at least one electrolyzer (201) by:providing a load setpoint to operate the at least one electrolyzer (201) either at a reduced load level or in a standby mode during the grid fault; andafter detecting a recovery phase of the grid fault, providing a new load setpoint to return the at least one electrolyzer (201) to its pre-fault load level.

14. The power supply system (100) of claim 1, wherein during at least a portion of the grid fault period, the at least one electrolyzer (201) is entirely powered by the energy storage system (30), and the control system (20) is configured to control the energy storage system (30) such that the power supplied from the energy storage system (30) to the at least one electrolyzer (201) is according to a load setpoint provided to the at least one electrolyzer (201).

15. The power supply system (100) of claim 1, wherein during at least a portion of the grid fault period, the at least one electrolyzer (201) is entirely powered by the power grid, and the control system (20) is configured to control the converter system (10) such that the power supplied from the power grid to the at least one electrolyzer (201) via the converter system is according to a load setpoint provided to the at least one electrolyzer (201).

16. The power supply system (100) of claim 1, wherein during at least a portion of the grid fault period, the at least one electrolyzer (201) is jointly powered by the power grid and the energy storage system (30), and the control system (20) is configured to control the converter system (10) and the energy storage system (30) such that the sum of the power supplied from the energy storage system (30) and the power supplied from the power grid is according to a load setpoint provided to the at least one electrolyzer (201), andwherein the control operation by the control system (20) is coordinated to first operate the converter system (10) to provide maximum power from the power grid to the at least one electrolyzer (201) and to provide balance power as needed from the energy storage system (30) to meet the load level of the at least one electrolyzer (201) set by the load setpoint provided to the at least one electrolyzer (201).

17. The power supply system (100) of claim 1, wherein the control system (20) is communicatively connected to a local controller (10C) of the converter system (10), and a local controller (40C) of a dedicated converter (40) of the energy storage system (30);and wherein the control system (20) is arranged in a plant controller of the electrolyzer plant (200).

18. The power supply system (100) of claim 1, wherein the converter system (10) comprises a plurality of ACZDC converters, each of which is coupled to one of the plurality of electrolyzers (201, 202, 203, 204);at least one ACZDC converter from the plurality of ACZDC converters is a thyristor-based rectifier, which is coupled in parallel with a compensation converter unit that includes a diode rectifier and a compensation DCZDC converter; andthe control system (20) is configured to operate the compensation converter unit to transfer power to the electrolyzer connected to the thyristor-based rectifier during the grid fault.

19. A method for controlling a power supply system (100) of an electrolyzer plant (200),the power supply system (100) comprising:a converter system (10) configured to transfer power to a plurality of electrolyzers (201, 202, 203, 204) in the electrolyzer plant (200) from a power source (300) coupled to a power grid;an energy storage system (30) arranged in the power supply system (100); the method comprising the step of:controlling the operation of at least one electrolyzer (201) from the plurality of electrolyzers (201, 202, 203, 204) during a grid fault to provide a fault-ride through for the at least one electrolyzer (201) during the grid fault, and coordinating the supply of power to the at least one electrolyzer (201) from at least one of the power grid (300) and the energy storage system (30).

20. The method of claim 19, wherein controlling the operation of at least one electrolyzer (201) comprises:providing a load setpoint to operate the at least one electrolyzer (201) either at a reduced load level or in a standby mode during the grid fault; andafter detecting a recovery phase of the grid fault, providing a new load setpoint to return the at least one electrolyzer (201) to its pre-fault load level.

21. The method of claim 19, wherein controlling the operation of at least one electrolyzer (201) comprises:periodically adjusting a load setpoint to reduce the load level of the at least one electrolyzer (201) by a predetermined level during the grid fault until detection of a recovery phase of the grid fault.