A new energy electric compressor durability test bench

By designing the durability test bench for new energy electric compressors, using real vehicle components and monitoring components to simulate the operation of the real vehicle air conditioning system, the problems of energy waste and insufficient reliability in the durability test of electric compressors are solved, and the electric compressors are realized Effective testing and energy savings.

CN117489578BActive Publication Date: 2024-11-22ZHEJIANG XINOLAN AUTOMOBILE AIR CONDITIONING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311469625.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-07
Publication Date
2024-11-22
Estimated Expiration
2043-11-07

AI Technical Summary

Technical Problem

The existing new energy electric compressor durability test bench cannot fully simulate the operation of the real vehicle air conditioning system, resulting in insufficient reliability of the electric compressor after actual loading, which may lead to failure of the thermal management system and affect the functions or performance of the entire vehicle.

Method used

A new energy electric compressor durability test bench was designed, including real vehicle components, monitoring components and air outlet components. By simulating the operation of the real vehicle air conditioning system, it uses condensers, evaporators, pipelines, dampers and sensors and other components. Monitor and adjust the exhaust pressure, suction pressure, exhaust temperature and suction temperature of the electric compressor in real time to ensure the reliability of the electric compressor, and realize data acquisition and analysis through software.

Benefits of technology

The reliability test of the electric compressor is realized, energy waste is avoided, and the electric compressor can meet the requirements of the thermal management system after actual loading, which improves the functions and performance of the entire vehicle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117489578B_ABST
    Figure CN117489578B_ABST
Patent Text Reader

Abstract

The present application provides a new energy electric compressor durability test bench, including a durability test bench, a computer, a signal collector and an electric compressor to be tested, wherein the lower end of the durability test bench is provided with a low-voltage power supply, and the upper end of the durability test bench is provided with a high-voltage power supply, and further includes: a real vehicle component, which is used to simulate the operation of the real vehicle air-conditioning system and cannot solve the problem of serious energy waste in the durability test of the electric compressor, and the real vehicle component includes a condenser, an evaporator and a pipeline, and the pipeline includes an exhaust pipe, a liquid pipe and an intake pipe. The present application solves the problem that the durability test of the electric compressor in practice cannot fully simulate the operation of the real vehicle air-conditioning system and cannot solve the problem of serious energy waste in the durability test of the electric compressor, which leads to the fact that the reliability of the compressor cannot meet the requirements after actual installation, which may cause the thermal management system to fail, and further affect the function or performance failure of the whole vehicle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of reliability testing of new energy thermal management systems, and in particular to a new energy electric compressor durability test bench. Background Art

[0002] New energy electric compressors play a key role in new energy thermal management systems. In addition to providing refrigerant drive for passenger compartment air conditioning and windshield defrosting and defogging, they also provide refrigerant drive for the vehicle's battery, motor, and electronic control thermal management system. Therefore, the reliability of new energy electric compressors is crucial.

[0003] At present, the new energy electric compressor durability test bench controls the exhaust pressure, suction pressure, and suction temperature to test the compressor durability. This method cannot fully simulate the operation of the actual vehicle air conditioning system and cannot solve the serious energy waste problem in the electric compressor durability test, which leads to the compressor durability test meeting the requirements according to the national recommended standards. After the actual installation, the compressor reliability cannot meet the requirements, which may cause the thermal management system to fail, thereby affecting the function or performance failure of the whole vehicle;

[0004] At present, the commonly adopted method in the industry is: in order to control the exhaust pressure, suction pressure and suction temperature of the electric compressor at the same time, another system is needed to support it. The condenser and evaporator are placed in two rooms respectively, and commercial refrigeration units are used to provide the condenser and evaporator with an environment that simulates the actual vehicle operating conditions, so as to achieve the purpose of controlling the exhaust pressure, exhaust temperature, suction pressure and suction temperature of the electric compressor, which will cause serious waste of energy.

[0005] Therefore, we made improvements to this and proposed a new energy electric compressor durability test bench. Summary of the invention

[0006] The purpose of the present invention is to address the problem that the durability test of an electric compressor in practice cannot fully simulate the operating conditions of an actual vehicle air-conditioning system and cannot solve the problem of serious energy waste in the durability test of an electric compressor, which leads to the compressor reliability failing to meet the requirements after actual installation on the vehicle, which may cause the thermal management system to fail, thereby affecting the function or performance failure of the entire vehicle.

[0007] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:

[0008] New energy electric compressor durability test bench to improve the above problems.

[0009] The specific application is as follows:

[0010] A new energy electric compressor durability test bench, comprising a durability test bench, a computer, a signal collector and an electric compressor to be tested, wherein a low-voltage power supply is provided at the lower end of the durability test bench, a high-voltage power supply is provided at the upper end of the durability test bench, and further comprising:

[0011] The real vehicle assembly is used to simulate the operation of the real vehicle air conditioning system and cannot solve the serious energy waste problem in the durability test of the electric compressor. The real vehicle assembly includes a condenser, an evaporator and a pipeline. The pipeline includes an exhaust pipe, a liquid pipe and an air intake pipe. The exhaust pipe, the liquid pipe and the air intake pipe are respectively connected to the electric compressor, the condenser and the evaporator;

[0012] A monitoring component, used to detect temperature and pressure changes during the test, the monitoring component includes an evaporation air volume regulator, a condensation air volume regulator, a signal collector, a compressor speed regulator, a computer and a digital thermometer;

[0013] The air outlet assembly is used to adjust the air volume and wind direction. The air outlet assembly includes a first air door located at the rear end of the evaporator, a second air door located at the rear end of the condenser, a third air door connecting the first air door and the second air door, and an air cavity connecting the first air door, the second air door, the refrigerant body and the evaporating gas.

[0014] As the preferred technical solution of the present application, the electric compressor, condenser, evaporator and pipelines are consistent with the air-conditioning status of an actual vehicle, the refrigerant filling amount and lubricating oil filling amount in the air-conditioning are consistent with those of an actual vehicle, and the relative position of the electric compressor and evaporator is consistent with that of an actual vehicle.

[0015] As a preferred technical solution of the present application, a controller is provided in the electric compressor, a compressor temperature sensor is provided in the controller, and the compressor temperature sensor is used to monitor the temperature of the power module in the controller.

[0016] As a preferred technical solution of the present application, an exhaust pressure temperature sensor, a condensing pressure temperature sensor and an intake pressure temperature sensor are installed on the exhaust pipe, liquid pipe and intake pipe for monitoring and controlling the pressure and temperature of the refrigerant.

[0017] As a preferred technical solution of the present application, a condensation air inlet is installed in the wind cavity corresponding to the condenser, a condensation air outlet is provided at the rear end of the condenser, the condensation air outlet and the second air gate penetrate each other, and the condensation air inlet and the condensation air outlet are both provided with temperature sensors for monitoring the temperature of the condensation air inlet and the condensation air outlet.

[0018] As a preferred technical solution of the present application, an evaporation air inlet is installed in the wind cavity corresponding to the evaporator, the evaporation air inlet and the first air gate penetrate each other, an evaporation air outlet is provided at the upper end of the evaporator, and the evaporation air inlet and the evaporation air outlet are both provided with temperature sensors for monitoring the temperatures of the evaporation air inlet and the evaporation air outlet.

[0019] As a preferred technical solution of the present application, the third air gate is provided with a plurality of small temperature-variable holes, and the plurality of small temperature-variable holes can be partially opened and closed to adjust the air inlet temperature of the evaporation air inlet. The third air gate separates the condensation air outlet and the evaporation air inlet. The first air gate, the second air gate and the third air gate move in coordination with each other, and the distance between the air duct on the air cavity and the evaporation air outlet moves in coordination to control the exhaust pressure, exhaust temperature, intake pressure and intake temperature of the electric compressor.

[0020] As a preferred technical solution of the present application, a pointer pressure gauge and a digital thermometer are also provided at the upper end of the durability test bench. The pointer pressure gauge is used to monitor the exhaust pressure, condensing pressure and suction pressure, and the digital thermometer is used to monitor the exhaust temperature, condensing temperature and suction temperature. The positions monitored by the pointer pressure gauge and the digital thermometer are the same as those monitored by the exhaust pressure temperature sensor, the condensing pressure temperature sensor and the suction pressure temperature sensor, which are used to compare the difference in the measurement results of the two and are also convenient for observation. The number of the pointer pressure gauges and the digital thermometers is the same.

[0021] As a preferred technical solution of the present application, the evaporating air volume regulator, the condensing air volume regulator and the compressor speed regulator can manually adjust the parameters required for each working condition of the durability test.

[0022] As the preferred technical solution of the present application, the computer realizes communication through the host computer via the signal collector and the compiled software, and can control and monitor the relevant required parameters through the computer, form a curve and achieve real-time data collection at the same time, and store it in the database to provide a basis for experimental analysis.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] In the scheme of this application:

[0025] 1. Use an air conditioning system that is the same as the actual vehicle, consisting of an electric compressor, a condenser, an evaporator, and is composed of an expansion valve, an exhaust pipe, an intake pipe, and a liquid pipe. Ensure that the relative position of the electric compressor and the evaporator is consistent with that of the actual vehicle, and the refrigerant charge and lubricant oil charge in the air conditioner are consistent with those of the actual vehicle. At the same time, the condensation air outlet and the evaporation air inlet are installed on the air cavity. The air cavity is linked with the first air door, the second air door, and the third air door. Under the combined operation of the pressure gauge, the evaporation air volume regulator, the digital thermometer, the condensation air volume regulator, the compressor speed regulator, the signal collector, the high-voltage power supply, the low-voltage power supply, the computer and the software, the parameters required for each working condition of the durability test are adjusted to monitor in real time, thereby ensuring the reliability of the electric compressor;

[0026] 2. Through the exhaust pressure, suction pressure and suction temperature of the electric compressor, by adjusting the distance between the first damper, the second damper, the third damper and the air duct on the air cavity and the evaporation air outlet, when the actual required evaporation air inlet temperature is higher than the ambient temperature, by adjusting the number of opening and closing of the temperature-changing small holes on the third damper, the hot air blown out of the condensation air outlet is mixed with the ambient temperature and mixed to the required temperature in the air cavity; when the actual required evaporation air inlet temperature is lower than the ambient temperature, by adjusting the distance between the air duct on the air cavity and the evaporation air outlet, the cold air blown out of the evaporation air outlet is mixed with the ambient temperature and mixed to the required temperature in the air cavity, and at the same time, the evaporation air volume is adjusted by the evaporation air volume regulator to control the suction pressure and suction temperature of the electric compressor, and the exhaust pressure and exhaust temperature of the electric compressor are controlled by adjusting the opening size of the second damper and adjusting the condensation air volume by the condensation air volume regulator, which can solve the serious energy waste problem in the durability test of the electric compressor;

[0027] 3. By installing temperature and pressure sensors on the condenser, evaporator, electric compressor, exhaust pipe, liquid pipe and suction pipe, the durability test bench receives data through various sensors and uses the background software to connect and monitor synchronously. The computer communicates with the host computer through the signal collector and the compiled software, and the computer can be used to control and monitor the relevant parameters, form curves, and achieve real-time data collection, which is stored in the database to provide a basis for test analysis. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 The overall structural diagram of the new energy electric compressor durability test bench provided for this application;

[0029] Figure 2 This is an enlarged left-side structural diagram of the new energy electric compressor durability test bench provided in this application;

[0030] Figure 3 This is a rear-view enlarged structural schematic diagram of the new energy electric compressor durability test bench provided in this application.

[0031] Indicated in the figure:

[0032] 1. Durability test bench; 2. First damper; 3. Second damper; 4. Third damper; 5. Air chamber;

[0033] 6. Evaporator; 7. Evaporation air inlet; 8. Evaporation air outlet; 9. Evaporation air volume regulator;

[0034] 10. Condenser; 11. Condensation air inlet; 12. Condensation air outlet; 13. Condensation air volume regulator;

[0035] 14. Intake pipe; 15. Liquid pipe; 16. Exhaust pipe;

[0036] 17. Digital thermometer; 18. Compressor speed regulator; 19. Signal collector;

[0037] 20. Computer; 21. High voltage power supply; 22. Low voltage power supply; 23. Electric compressor. DETAILED DESCRIPTION

[0038] To make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be described clearly and completely in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them.

[0039] Therefore, the following detailed description of the embodiments of the present invention is not intended to limit the scope of the invention claimed for protection, but merely represents some embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. It should be noted that the embodiments of the present invention and the features and technical solutions in the embodiments can be combined with each other without conflict.

[0040] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings. Example 1

[0041] like Figure 1-3 As shown, this embodiment proposes a new energy electric compressor durability test bench, and this embodiment proposes a new energy electric compressor 23 durability test bench, including a durability test bench 1, a computer 20, a signal collector 19 and an electric compressor 23 to be tested, the lower end of the durability test bench 1 is provided with a low-voltage power supply 22, the upper end of the durability test bench 1 is provided with a high-voltage power supply 21, and also includes:

[0042] The real vehicle assembly is used to simulate the operation of the real vehicle air conditioning system and the serious energy waste problem in the endurance test of the electric compressor 23. The real vehicle assembly includes a condenser 10, an evaporator 6 and a pipeline. The pipeline includes an exhaust pipe 16, a liquid pipe 15 and an air intake pipe 14. The exhaust pipe 16, the liquid pipe 15 and the air intake pipe 14 are respectively connected to the electric compressor 23, the condenser 10 and the evaporator 6;

[0043] The air vent assembly is used to adjust the air volume and wind direction, and the air vent assembly includes a first air door 2 located at the rear end of the evaporator 6, a second air door 3 located at the rear end of the condenser 10, a third air door 4 connecting the first air door 2 and the second air door 3, and an air cavity 5 connecting the first air door 2, the second air door 3 and the refrigerant body and the evaporated gas.

[0044] A condensation air inlet 11 is installed in the air cavity 5 corresponding to the condenser 10, and a condensation air outlet 12 is provided at the rear end of the condenser 10. The condensation air outlet 12 and the second air door 3 penetrate each other. The condensation air inlet 11 and the condensation air outlet 12 are both provided with temperature sensors for monitoring the temperatures of the condensation air inlet 11 and the condensation air outlet 12.

[0045] An evaporation air inlet 7 is installed in the wind cavity 5 corresponding to the evaporator 6. The evaporation air inlet 7 and the first air door 2 penetrate each other. An evaporation air outlet 8 is provided at the upper end of the evaporator 6. The evaporation air inlet 7 and the evaporation air outlet 8 are both provided with temperature sensors for monitoring the temperatures of the evaporation air inlet 7 and the evaporation air outlet 8.

[0046] The third damper 4 is provided with a plurality of temperature-changing small holes, and the plurality of temperature-changing small holes can be partially opened and closed to adjust the air inlet temperature of the evaporation air inlet 7. The third damper 4 separates the condensation air outlet 12 and the evaporation air inlet 7. The first damper 2, the second damper 3, and the third damper 4 move in coordination with each other, and the distance between the air duct on the air cavity 5 and the evaporation air outlet 8 moves in coordination with each other, to control the exhaust pressure, exhaust temperature, intake pressure, and intake temperature of the electric compressor 23.

[0047] By adjusting the third damper 4, the air is introduced according to the ambient temperature, and the number of temperature-changing small holes is adjusted to realize circulating air induction in cooperation with the air cavity 5 and the damper. For example, when the ambient temperature is 30° and the actual required evaporation air inlet temperature is 20°, the distance between the air duct on the air cavity 5 and the evaporation air outlet 8 is adjusted to mix the cold air blown out of the evaporation air outlet 8 to the required temperature in the air cavity 5. At the same time, the evaporation air volume is adjusted by the evaporation air volume regulator 9 to control the suction pressure and suction temperature of the electric compressor 23. When the ambient temperature is 20° and the actual required evaporation air inlet temperature is 30°, the suction pressure and suction temperature of the electric compressor 23 are controlled. By adjusting the number of openings and closings of the temperature-changing small holes on the third air door 4, the hot air blown out of the condensing air outlet 12 is mixed to the required temperature in the air chamber 5. At the same time, the evaporating air volume is adjusted by the evaporating air volume regulator 9 to control the suction pressure and suction temperature of the electric compressor 23. By adjusting the opening size of the second air door 3 and the condensing air volume regulator 13, the external commercial refrigeration unit is avoided for regulation. In actual situations, the actual required evaporating air inlet temperature is achieved by integrating the cold and hot air between the machines, which can greatly avoid energy waste and achieve the effect of energy saving and environmental protection.

[0048] The refrigerant and compressor lubricating oil of the air-conditioning system are filled according to the actual vehicle standard, and under the premise that the electric compressor 23 and the evaporator 6 are in the same position relative to the actual vehicle, in order to save energy, the evaporation pressure and return air temperature are adjusted through the air volume flow between the evaporative air volume regulator 9 and the first air door 2, the second air door 3, and the third air door 4. The first air door 2 and the second air door 3 are used to adjust the required mixed air volume through the condenser 10 and the evaporator 6, and the exchange air volume between the two cavities is adjusted by the number of opening and closing of the variable temperature holes in the third air door 4. The durability of the electric compressor 23 sample is tested by changing the parameters.

[0049] Through the exhaust pressure, suction pressure, and suction temperature of the electric compressor 23, by adjusting the distance between the air duct on the air cavity 5 and the evaporation air outlet 8 to coordinate the movement, by adjusting the air volume through the evaporation air volume regulator 9 and the condensation air volume regulator 13 to simulate various operating conditions of the actual vehicle air conditioner, the exhaust pressure, exhaust temperature, suction pressure, and suction temperature of the electric compressor 23 are controlled, so that the electric compressor 23 completes the reliability test under these operating conditions. The exhaust pressure and exhaust temperature of the electric compressor 23 are adjusted by adjusting the opening size of the first air door 2 and adjusting the air volume of the condensation air volume regulator 13. The suction pressure and suction temperature of the electric compressor 23 are adjusted by adjusting the opening size of the second air door 3, the opening size of the third air door 4, the distance between the air duct on the air cavity 5 and the evaporation air outlet 8, and the evaporation air volume regulator 9. Through the temperature adjustment, energy waste can be greatly avoided. Example 2

[0050] As a preferred embodiment, based on the above method, a further monitoring component is used to detect temperature and pressure changes during the test process. The monitoring component includes an evaporating air volume regulator 9, a condensing air volume regulator 13, a signal collector 19, a compressor speed regulator 18, a computer 20 and a digital thermometer 17.

[0051] An exhaust pressure temperature sensor, a condensing pressure temperature sensor and an intake pressure temperature sensor are installed on the exhaust pipe 16, the liquid pipe 15 and the intake pipe 14 to monitor and control the pressure and temperature of the refrigerant.

[0052] The electric compressor 23, condenser 10, evaporator 6 and pipelines are consistent with the air-conditioning status of an actual vehicle. The relative positions of the electric compressor 23 and the evaporator 6 are consistent with those of an actual vehicle. The refrigerant filling amount and oil circulation amount in the pipelines are consistent with the air-conditioning status of an actual vehicle. A controller is provided in the electric compressor 23, and a compressor temperature sensor is provided in the controller. The compressor temperature sensor is used to monitor the temperature of the power module in the controller.

[0053] By monitoring through various sensors, the parameters of each working condition of the durability test can be stably monitored and curves can be drawn through software, so as to understand in real time whether there are any abnormal situations in the tested products or test conditions during the test, facilitate data analysis, and provide an effective basis for iterative product improvement. Example 3

[0054] As a preferred embodiment, on the basis of the above-mentioned manner, further, a pointer pressure gauge and a digital thermometer 17 are further provided at the upper end of the durability test bench 1. The pointer pressure gauge is used to monitor the exhaust pressure, condensing pressure and suction pressure, and the digital thermometer 17 is used to monitor the exhaust temperature, condensing temperature and suction temperature. The positions monitored by the pointer pressure gauge and the digital thermometer 17 are the same as those monitored by the exhaust pressure temperature sensor, the condensing pressure temperature sensor and the suction pressure temperature sensor, so as to compare the difference in the measurement results of the two and facilitate observation. The number of the pointer pressure gauges and the digital thermometers 17 is the same.

[0055] The evaporation air volume regulator 9, the condensation air volume regulator 13 and the compressor speed regulator 18 can manually adjust the parameters required for each working condition of the durability test. The computer 20 communicates with the host computer through the signal collector 19 and the compiled software, and the computer 20 can be used to control and monitor the relevant required parameters, form a curve, and achieve real-time data collection at the same time, and store it in the database to provide a basis for test analysis.

[0056] When the present application is in use: an air-conditioning system identical to that of an actual vehicle is adopted, specifically consisting of an electric compressor 23, a condenser 10, an evaporator 6, and an expansion valve, an exhaust pipe 16, an intake pipe 14, and a liquid pipe 15. The relative positions of the electric compressor 23 and the evaporator 6 are ensured to be consistent with those of an actual vehicle, and the refrigerant charge and lubricating oil charge in the air conditioner are consistent with those of an actual vehicle. At the same time, the condensing air outlet 12 and the evaporating air inlet 7 are installed on the wind cavity 5, and the wind cavity 5 is linked with the first damper 2, the second damper 3, and the third damper 4. Under the combined operation of a pressure gauge, an evaporating air volume regulator 9, a digital thermometer 17, a condensing air volume regulator 13, a compressor speed regulator 18, a signal collector 19, a high-voltage power supply 21, a low-voltage power supply 22, a computer 20, and software, the parameters required for each working condition of the durability test are adjusted to perform real-time monitoring, thereby ensuring the reliability of the electric compressor 23.

[0057] In order to adjust the intake and exhaust temperature and intake and exhaust pressure required for the durability test, when the actual required evaporation air inlet temperature is higher than the ambient temperature, the hot air blown out of the condensation air outlet 12 is mixed with the ambient temperature by adjusting the number of opening and closing of the temperature-changing small holes on the third air door 4, and mixed to the required temperature in the air cavity 5; when the actual required evaporation air inlet temperature is lower than the ambient temperature, the cold air blown out of the evaporation air outlet 8 is mixed with the ambient temperature by adjusting the distance between the air duct on the air cavity 5 and the evaporation air outlet 8, and mixed to the required temperature in the air cavity 5, and at the same time, the evaporation air volume is adjusted by the evaporation air volume regulator 9 to control the intake pressure and intake temperature of the electric compressor 23, and the exhaust pressure and exhaust temperature of the electric compressor 23 are controlled by adjusting the opening size of the second air door 3 and adjusting the condensation air volume by the condensation air volume regulator 13, which can solve the serious energy waste problem in the durability test of the electric compressor 23.

[0058] At the same time, the exhaust pressure, exhaust temperature, suction pressure and suction temperature of the electric compressor 23 are monitored synchronously by installing temperature and pressure sensors on the condenser 10, the evaporator 6, the electric compressor 23, the exhaust pipe 16, the liquid pipe 15 and the suction pipe 14, and receiving data through various sensors on the durability test bench 1 and utilizing the connection of the background software, which can greatly avoid energy waste.

[0059] During the durability test of the electric compressor 23, the electric compressor 23 to be tested is fixed on the durability test bench 1, connected to the air-conditioning system, and vacuumed and refrigerant and lubricating oil are added according to the specifications. After power-on, the software can detect various parameters before the electric compressor 23 is turned on, such as: suction pressure, suction temperature, exhaust pressure, exhaust temperature, controller temperature, ambient temperature and humidity, etc., and record them through the computer 20 and save them in the database.

[0060] When conducting various durability test conditions, the software will monitor in real time various parameters of the operation of the electric compressor 23 (such as: the speed of the electric compressor 23, the power of the electric compressor 23, the temperature of the controller of the electric compressor 23, the operating time, the suction pressure of the electric compressor 23, the suction temperature of the electric compressor 23, the exhaust pressure of the electric compressor 23, the exhaust temperature of the electric compressor 23, the condensing pressure, the condensing temperature, the condensing inlet temperature, the condensing outlet temperature, the evaporating inlet temperature, the evaporating outlet temperature) and form a curve. At the same time, the operating condition parameters and the set condition parameters are monitored and compared in real time to form a curve. If the set range is exceeded, the computer 20 will alarm.

[0061] When the test is completed, the test data is analyzed by software and generated in the form of a curve on the computer 20. The test data is analyzed to evaluate the quality and reliability of the product. Through the data transmitted by the sensor and the automatic analysis of the software, various parameters of the unit can be accurately recorded. At the same time, all real-time monitoring data of the test is stored in the database for future query and analysis to provide a basis for product improvement.

[0062] The above embodiments are only used to illustrate the present invention and are not intended to limit the technical solutions described in the present invention. Although the present invention has been described in detail with reference to the above embodiments, the present invention is not limited to the above specific implementation methods. Therefore, any modification or equivalent replacement of the present invention; and all technical solutions and improvements thereof that do not depart from the spirit and scope of the invention are included in the scope of the claims of the present invention.

Claims

1. A new energy electric compressor durability test bench, comprising a durability test bench (1) and an electric compressor to be tested (23), characterized in that: The durability test bench (1) is provided with a low-voltage power supply (22) at the lower end, and a high-voltage power supply (21) at the upper end, and further comprises: A real vehicle component, used to simulate the operation of a real vehicle air conditioning system and the durability test of an electric compressor (23), the real vehicle component comprising a condenser (10), an evaporator (6) and a pipeline, the pipeline comprising an exhaust pipe (16), a liquid pipe (15) and an intake pipe (14); A monitoring component, used to detect temperature and pressure changes during the test process, the monitoring component comprising an evaporation air volume regulator (9), a condensation air volume regulator (13), a signal collector (19), a compressor speed regulator (18), a computer (20), a pointer pressure gauge and a digital thermometer (17); An air outlet assembly, used for adjusting the air volume and air direction, the air outlet assembly comprising a first air door (2) located at the rear end of the evaporator (6), a second air door (3) located at the rear end of the condenser (10), a third air door (4) connected to the first air door (2) and the second air door (3), and an air cavity (5) connected to the first air door (2), the second air door (3), the condenser (10), and the evaporator; The evaporation air volume regulator (9), the condensation air volume regulator (13) and the compressor speed regulator (18) are capable of manually adjusting the parameters required for each operating condition of the durability test; Signals are transmitted between the computer (20) and the signal collector (19) through software, and a host computer is provided for communication between the computer (20) and the signal collector (19) for controlling and monitoring relevant durability test parameters; A condensation air outlet (12) is installed in the air cavity (5) corresponding to the condenser (10), a condensation air inlet (11) is provided at the front end of the condenser (10), the condensation air outlet (12) and the second air door (3) penetrate each other, and the condensation air inlet (11) and the condensation air outlet (12) are both provided with temperature sensors for monitoring the temperatures of the condensation air inlet (11) and the condensation air outlet (12); An evaporation air inlet (7) is installed in the air cavity (5) corresponding to the evaporator (6); the evaporation air inlet (7) and the first air door (2) penetrate each other; an evaporation air outlet (8) is provided at the upper end of the evaporator (6); and both the evaporation air inlet (7) and the evaporation air outlet (8) are provided with temperature sensors for monitoring the temperatures of the evaporation air inlet (7) and the evaporation air outlet (8); The third damper (4) is provided with a plurality of temperature-changing small holes, and the plurality of temperature-changing small holes can be partially opened and closed, and are used to adjust the air inlet temperature of the evaporation air inlet (7). The third damper (4) separates the condensation air outlet (12) and the evaporation air inlet (7), and the distance between the air duct on the air cavity (5) and the evaporation air outlet (8) moves in coordination, and is used to control the exhaust pressure, exhaust temperature, intake pressure, and intake temperature of the electric compressor (23).

2. The new energy electric compressor durability test bench according to claim 1 is characterized in that: The electric compressor (23), condenser (10), evaporator (6) and pipelines are consistent with the state of an actual vehicle air conditioner, and the relative position of the electric compressor (23) and evaporator (6) is consistent with that of an actual vehicle.

3. The new energy electric compressor durability test bench according to claim 1 is characterized in that: The electric compressor (23) is provided with a controller, and the controller is provided with a compressor temperature sensor, and the compressor temperature sensor is used to monitor the temperature of a power module in the controller.

4. The new energy electric compressor durability test bench according to claim 1 is characterized in that: An exhaust pressure temperature sensor, a condensing pressure temperature sensor and an intake pressure temperature sensor are installed on the exhaust pipe (16), the liquid pipe (15) and the intake pipe (14) for monitoring and controlling the pressure and temperature of the refrigerant.

5. The new energy electric compressor durability test bench according to claim 4 is characterized in that: The pointer pressure gauge and the digital thermometer (17) are arranged at the upper end of the durability test bench (1); the pointer pressure gauge is used to monitor the exhaust pressure, condensing pressure and suction pressure; the digital thermometer (17) is used to monitor the exhaust temperature, condensing temperature and suction temperature; the positions monitored by the pointer pressure gauge and the digital thermometer (17) are the same as the positions monitored by the exhaust pressure temperature sensor, the condensing pressure temperature sensor and the suction pressure temperature sensor, so as to compare the difference in the measurement results of the two and facilitate observation; the number of the pointer pressure gauge and the digital thermometer (17) is the same.