Intelligent extraction and collaborative sharing method of pipeline mining information based on AI technology
Through AI technology, the pipeline mining information is automatically extracted and matched, and the accurate sharing and timely push of information is achieved, and the accuracy and timeliness of information sharing in the existing technology is solved, which improves work efficiency and security.
Patent Information
- Application Number
- CN202410363142.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-28
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-03-28
AI Technical Summary
The sharing of existing pipeline mining information has problems such as poor accuracy, weak targeting and low timeliness, which are mainly due to the technical limitations of the construction unit, which leads to untimely information push and untimely monitoring of reading situations.
Using intelligent extraction and collaborative sharing methods of pipeline mining information based on AI technology, including automatically extracting professional information declared by the construction unit, matching the key information of the target pipeline through the preset matching strategy, and automatically pushing information to stakeholders based on the preset push strategy , monitor and compare the reading value with the preset threshold, and issue reminders of different levels.
Improve the efficiency and accuracy of information processing, realize timely sharing and precise positioning of information, enhance the effectiveness of information transmission, reduce risks, improve work efficiency and emergency response speed, reduce information leakage risks, and improve Information security.
Smart Images

Figure CN118227849B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of information collaborative sharing, and more specifically, to a pipeline mining information intelligent extraction and collaborative sharing method based on AI technology. Background Art
[0002] Pipeline line engineering refers to the engineering of connecting the starting station, intermediate station and terminal station of the pipeline with pipes, pipe fittings, valves, etc. to form a pipeline transportation line, including pipeline assembly and laying, installation of pipeline valves and pipe fittings, crossing obstacles such as rivers, lakes, roads, pipeline anti-corrosion and the construction of pipeline auxiliary structures such as soil and water conservation, line signs and other engineering projects. Pipeline line engineering is the main part of pipeline engineering, accounting for about 2 / 3 of the total investment in pipeline engineering. The construction procedure of pipeline line engineering is to first select routes and design line diagrams, and then carry out pipeline construction. At present, the sharing of pipeline mining information is mainly based on the shared information system, which is passively pushed by the construction unit. Due to the technical limitations of the construction unit, the information sharing has problems such as poor accuracy, weak pertinence and low timeliness. Therefore, a pipeline mining information intelligent extraction and collaborative sharing method based on AI technology is proposed. Summary of the invention
[0003] To achieve the above object, the present invention provides the following technical solutions:
[0004] The pipeline mining information intelligent extraction and collaborative sharing method based on AI technology includes the following steps:
[0005] Step 1: Automatically and intelligently extract corresponding professional information from the basic pipeline mining information reported by the construction unit;
[0006] Step 2: According to the preset matching strategy, the fuzzy location information in the professional information is automatically matched with the key information of the target pipeline;
[0007] Step 3: Automatically push pipeline mining information to stakeholders in key information according to the preset push strategy;
[0008] Step 4: Monitor the target stakeholder's reading of the pushed information, calculate the target stakeholder's reading value and compare it with the preset reading threshold of the target stakeholder. If the target stakeholder's reading value is greater than or equal to the preset reading threshold of the target stakeholder, no reminder is issued. If the target stakeholder's reading value is less than the preset reading threshold of the target stakeholder, different levels of reminders are issued according to the preset reminder strategy.
[0009] In a preferred embodiment, the corresponding professional information in the basic pipeline excavation information reported by the construction unit includes fuzzy location information of the pipeline excavation, pipeline professional information, and time information.
[0010] In a preferred embodiment, the key information of the target pipeline includes GIS information and information of relevant units.
[0011] In a preferred embodiment, according to a preset matching strategy, the key information of the target pipeline is automatically matched to the fuzzy location information in the professional information:
[0012] Obtain the fuzzy location information in the professional information and confirm the monitoring area according to the preset matching strategy;
[0013] Obtain the topographic information of the monitoring area, which includes the bare land area coefficient, the vegetation area coefficient, the lake area coefficient, the total number of bare land pixels, the total number of vegetation pixels, the total number of lake pixels, and the total number of image pixels;
[0014] The specific steps to obtain it are as follows:
[0015] S1, obtain images of the monitoring area through an optical satellite outside the atmosphere, and send the obtained images to the cloud computing platform;
[0016] S2. When the cloud computing platform receives the image, it imports the vector file of the monitoring area, crops the image through ArcGIS software to obtain the image of the monitoring area, and pre-processes the image of the monitoring area;
[0017] S3, identifying the image of the monitoring area, and obtaining the total number of pixels of bare land, the total number of pixels of vegetation, the total number of pixels of lakes, and the total number of pixels of the image;
[0018] S4, mark the bare land area coefficient, vegetation area coefficient, and lake area coefficient as f1, f2, and f3 respectively, mark the total number of pixels of bare land as LDi, the total number of pixels of vegetation as ZBi, the total number of pixels of lakes as HPi, and the total number of pixels of the image as ZSi;
[0019] S5. Obtain the similarity of the monitoring area through the formula, XSi is the similarity of the monitoring area. Then, the GIS information in the key information of all pipelines and the regional similarity value XZi corresponding to the GIS information are obtained. The ratio of the regional similarity value XZi corresponding to all GIS information and the similarity XSi of the monitoring area is calculated. The GIS information corresponding to the regional similarity value XZi corresponding to the result with the ratio closest to one is the precise location of the target pipeline, and the corresponding target stakeholder units are matched through the preset precise location-target stakeholder unit form.
[0020] In a preferred embodiment, automatically pushing pipeline mining information to stakeholders in key information according to a preset push strategy means: acquiring real-time monitoring information of the target pipeline in the pipeline mining information and pushing information to corresponding target stakeholder units according to the precise location of the target pipeline.
[0021] In a preferred embodiment, monitoring the reading of the pushed information by the target stakeholder unit, calculating the reading value of the target stakeholder unit and comparing it with the preset reading threshold of the target stakeholder unit refers to:
[0022] Obtain various types of reading data of the target stakeholder unit and mark them as YSi respectively, obtain the preset interest coefficient corresponding to the target stakeholder unit, and then calculate the preset reading threshold of the target stakeholder unit, YZi=xi·BD, YZi is the preset reading threshold of the target stakeholder unit, xi is the preset interest coefficient corresponding to the target stakeholder unit, BD is the preset standard interest reference, and then calculate the reading value, YDi=∑(ki·YSi), YDi is the reading value of the target stakeholder unit, ki is the reading coefficient corresponding to each type of reading data, if the reading value of the target stakeholder unit is greater than or equal to the preset reading threshold of the target stakeholder unit, no reminder is issued, otherwise reminders of different levels are issued.
[0023] In a preferred embodiment, in step 4, if the reading value of the target stakeholder unit is less than the preset reading threshold of the target stakeholder unit, issuing reminders of different levels according to the preset reminder strategy means:
[0024] There is a preset reminder level-proportion interval form to calculate the proportion value. BL is a proportional value, r1 and r2 are both preset specific proportional coefficients, and a corresponding level of reminder is issued according to the reminder level corresponding to the proportional interval into which the proportional value BL falls.
[0025] Technical effects and advantages of the present invention:
[0026] The present invention utilizes AI technology to automatically extract professional information from the information reported by the construction unit, reduces the need for manual operation, improves the efficiency and accuracy of data processing, and realizes automated information processing; through the preset matching strategy, it can accurately match the fuzzy location information, quickly determine the exact location of the target pipeline, and help to accurately locate the pipeline; according to the preset push strategy, the relevant information can be automatically pushed to the stakeholders, ensuring the timely sharing of information and promoting the collaborative work of all participants; by monitoring the target stakeholders' reading of the pushed information, and based on the comparison of the reading value with the preset threshold, timely reminders can be issued, thereby enhancing the effectiveness of information transmission and ensuring that important information is not ignored.
[0027] The reminder mechanism of the present invention is also helpful for risk management. Through reminders of different levels, stakeholders can take timely measures to reduce or avoid risks that may be caused by failure to process information in a timely manner. The data analysis and processing capabilities provided by the present invention provide decision makers with data-based decision support, helping managers make more scientific and reasonable decisions. The automation of the entire process improves work efficiency, and when an emergency response is required, information can be quickly transmitted to key units, thereby increasing the speed of emergency response. Moreover, automated information processing and push reduce the risk of information leakage that may occur during manual processing, thereby improving the security of information. In addition, due to the use of AI technology, the present invention has strong adaptability, can cope with different working environments and changes, and continuously provide stable services. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to facilitate understanding by those skilled in the art, the present invention is further described below in conjunction with the accompanying drawings;
[0029] Figure 1 This is a schematic diagram of the pipeline mining information intelligent extraction and collaborative sharing method based on AI technology in the present invention. DETAILED DESCRIPTION
[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] Example 1
[0032] The pipeline mining information intelligent extraction and collaborative sharing method based on AI technology can automatically and intelligently extract the corresponding professional information such as location information, pipeline professional information, time information, etc. from the basic pipeline mining information reported by the construction unit through AI technology, and then automatically match key data such as GIS data, stakeholder unit data, etc., and finally automatically push the pipeline mining information to the stakeholder units. At the same time, monitor the reading of the pushed information by the stakeholder units, and make AI intelligent reminders for the reading value that is lower than the preset reading threshold of the target stakeholder unit, thereby realizing the collaborative sharing of pipeline mining information. Specifically, it includes the following steps:
[0033] Step 1: Automatically and intelligently extract corresponding professional information from the basic pipeline mining information reported by the construction unit;
[0034] Step 2: According to the preset matching strategy, the fuzzy location information in the professional information is automatically matched with the key information of the target pipeline;
[0035] Step 3: Automatically push pipeline mining information to stakeholders in key information according to the preset push strategy;
[0036] Step 4: Monitor the target stakeholder's reading of the pushed information, calculate the target stakeholder's reading value and compare it with the preset reading threshold of the target stakeholder. If the target stakeholder's reading value is greater than or equal to the preset reading threshold of the target stakeholder, no reminder is issued. If the target stakeholder's reading value is less than the preset reading threshold of the target stakeholder, different levels of reminders are issued according to the preset reminder strategy.
[0037] The corresponding professional information from the basic pipeline excavation information reported by the construction unit includes but is not limited to the fuzzy location information, pipeline professional information, and time information of the pipeline excavation. The key information of the target pipeline includes but is not limited to GIS information and information of relevant units.
[0038] According to the preset matching strategy, the key information for automatically matching the fuzzy location information in the professional information to the target pipeline is:
[0039] Obtain the fuzzy location information in the professional information and confirm the monitoring area according to the preset matching strategy;
[0040] Obtain the terrain information of the monitoring area, which includes the bare land area coefficient, the vegetation area coefficient, the lake area coefficient, the total number of pixels of bare land, the total number of pixels of vegetation, the total number of pixels of lakes, and the total number of pixels of the image; mark the bare land area coefficient, the vegetation area coefficient, and the lake area coefficient as f1, f2, and f3, respectively, reflecting the degree of their respective important influence on the similarity calculation of the monitoring area, mark the total number of pixels of bare land as LDi, the total number of pixels of vegetation as ZBi, the total number of pixels of lakes as HPi, and the total number of pixels of the image as ZSi; obtain the similarity of the monitoring area through the formula, XSi is the similarity of the monitoring area. Then, the GIS information in the key information of all pipelines and the regional similarity value XZi corresponding to the GIS information are obtained. The regional similarity value XZi corresponding to the GIS information is the standard value of the target area obtained by calculating the terrain information after regional division in advance. The ratio of the regional similarity value XZi corresponding to all GIS information and the similarity XSi of the monitoring area is calculated. The GIS information corresponding to the regional similarity value XZi corresponding to the result with the ratio closest to one is the precise location of the target pipeline, and the corresponding target stakeholder units are matched through the preset precise location-target stakeholder unit form. Through the AI matching of fuzzy location information and GIS data, the fuzzy location information is converted into accurate GIS data with high accuracy and strong pertinence. By comparing GIS data with stakeholder unit data, information is pushed to the stakeholders involved in a targeted manner.
[0041] Automatically pushing pipeline mining information to stakeholders in key information according to a preset push strategy means: acquiring real-time monitoring information of the target pipeline in the pipeline mining information and pushing information to corresponding target stakeholder units according to the precise location of the target pipeline.
[0042] Monitoring the target stakeholder's reading of the pushed information, calculating the target stakeholder's reading value and comparing it with the preset reading threshold of the target stakeholder means:
[0043] Obtain various types of reading data of the target stakeholder and mark them as YSi, such as reading time, number of clicks, page browsing speed, etc., which reflect the carefulness and seriousness of the reading data, obtain the preset interest coefficient corresponding to the target stakeholder, and then calculate the preset reading threshold of the target stakeholder, YZi=xi·BD, YZi is the preset reading threshold of the target stakeholder, xi is the preset interest coefficient corresponding to the target stakeholder, reflecting the closeness of the interest relationship between the target stakeholder and the pipeline mining, BD is the preset standard interest reference, and then calculate the reading value, YDi=Σ(ki·YSi), YDi is the reading value of the target stakeholder, ki is the reading coefficient corresponding to each type of reading data, if the reading value of the target stakeholder is greater than or equal to the preset reading threshold of the target stakeholder, then no reminder is issued, otherwise, reminders of different levels are issued. Specifically, in step 4, if the reading value of the target stakeholder is less than the preset reading threshold of the target stakeholder, then reminders of different levels are issued according to the preset reminder strategy, which means: there is a preset reminder level-proportion interval form, and the proportion value is calculated, BL is a proportional value, r1 and r2 are both preset specific proportional coefficients. A reminder of a corresponding level is issued according to the reminder level corresponding to the proportional interval in which the proportional value BL falls. The larger the proportional value, the higher the reminder level corresponding to the proportional interval in which it falls, which means that the reading level of the target stakeholder is lower, which is not enough to ensure the degree of information sharing, and may cause problems such as missing information. The overall intelligent extraction and collaborative sharing of pipeline mining information are highly timely, and automatic extraction, automatic matching, and automatic sending are adopted. The construction unit submits pipeline mining information with one click, and the background AI automatically processes and pushes it to improve timeliness. It can also provide intelligent reminders for those who fail to read the information in time.
[0044] Example 2
[0045] The pipeline mining information intelligent extraction and collaborative sharing method based on AI technology includes the following steps:
[0046] Step 1: Automatically and intelligently extract the corresponding professional information from the basic pipeline mining information declared by the construction unit; Step 2: According to the preset matching strategy, automatically match the fuzzy position information in the professional information with the key information of the target pipeline; Step 3: Automatically push the pipeline mining information to the stakeholders in the key information according to the preset push strategy; Step 4: Monitor the reading of the pushed information by the target stakeholder, calculate the reading value of the target stakeholder and compare it with the preset reading threshold of the target stakeholder. If the reading value of the target stakeholder is greater than or equal to the preset reading threshold of the target stakeholder, no reminder will be issued. If the reading value of the target stakeholder is less than the preset reading threshold of the target stakeholder, different levels of reminders will be issued according to the preset reminder strategy.
[0047] Automatic and intelligent extraction of professional information: First, the corresponding professional information will be automatically extracted from the basic pipeline excavation information reported by the construction unit. These professional information mainly include the fuzzy location information of pipeline excavation, pipeline professional information and time information.
[0048] Automatically match the key information of the target pipeline: Under the preset matching strategy, the fuzzy location information in the professional information is automatically matched with the key information of the target pipeline. The key information mainly includes GIS information and stakeholder information. By comparing the regional similarity values corresponding to each GIS information, the location of the pipeline can be accurately determined and the corresponding stakeholder can be matched.
[0049] Automatically push pipeline mining information: According to the preset push strategy, pipeline mining information is automatically pushed to stakeholders in key information.
[0050] Monitor reading status and issue reminders: Monitor the reading status of pushed information by target stakeholders in real time, and compare the reading value with the preset threshold. If the reading value is lower than the threshold, issue a reminder of the corresponding level according to the preset reminder strategy.
[0051] In addition, when matching the key information of the target pipeline, the AI-based pipeline mining information intelligent extraction and collaborative sharing method will also obtain the terrain information of the monitoring area, including the bare land area coefficient, vegetation area coefficient, lake area coefficient, etc., and calculate the similarity of the monitoring area. At the same time, the method will also obtain various types of reading data and preset interest coefficients of the target stakeholder units to calculate the reading threshold and reading value. If the reading value of the target stakeholder unit is less than the preset reading threshold, different levels of reminders will be issued according to the preset reminder strategy. This process is achieved by calculating the proportion value and the reminder level corresponding to the proportion interval in which the proportion value falls.
[0052] The AI-based pipeline mining information intelligent extraction and collaborative sharing method has the following implementation significance:
[0053] High accuracy: Through AI matching of fuzzy location information and GIS data, the fuzzy location information can be converted into accurate GIS data.
[0054] Highly targeted: By comparing GIS data with the data of stakeholders, targeted information can be pushed to relevant stakeholders.
[0055] High timeliness: The solution adopts automatic extraction, automatic matching, and automatic sending. The construction unit submits pipeline mining information with one click, and the background AI automatically processes and pushes it to improve timeliness. It can also provide intelligent reminders of different levels for those who fail to read the information in time.
[0056] The corresponding professional information from the basic pipeline excavation information reported by the construction unit includes the fuzzy location information of pipeline excavation, pipeline professional information, and time information. The key information of the target pipeline includes GIS information and information of relevant units.
[0057] According to the preset matching strategy, the key information for automatically matching the fuzzy location information in the professional information to the target pipeline is:
[0058] Obtain the fuzzy location information in the professional information and confirm the monitoring area according to the preset matching strategy;
[0059] Obtain the topographic information of the monitoring area, which includes the bare land area coefficient, the vegetation area coefficient, the lake area coefficient, the total number of bare land pixels, the total number of vegetation pixels, the total number of lake pixels, and the total number of image pixels;
[0060] The specific steps to obtain it are as follows:
[0061] S1, obtain images of the monitoring area through an optical satellite outside the atmosphere, and send the obtained images to the cloud computing platform;
[0062] S2. When the cloud computing platform receives the image, it imports the vector file of the monitoring area, crops the image through ArcGIS software to obtain the image of the monitoring area, and pre-processes the image of the monitoring area;
[0063] S3, identifying the image of the monitoring area, and obtaining the total number of pixels of bare land, the total number of pixels of vegetation, the total number of pixels of lakes, and the total number of pixels of the image;
[0064] S4, mark the bare land area coefficient, vegetation area coefficient, and lake area coefficient as f1, f2, and f3 respectively, mark the total number of pixels of bare land as LDi, the total number of pixels of vegetation as ZBi, the total number of pixels of lakes as HPi, and the total number of pixels of the image as ZSi;
[0065] S5. Obtain the similarity of the monitoring area through the formula, XSi is the similarity of the monitoring area. Then, the GIS information in the key information of all pipelines and the regional similarity value XZi corresponding to the GIS information are obtained. The ratio of the regional similarity value XZi corresponding to all GIS information and the similarity XSi of the monitoring area is calculated. The GIS information corresponding to the regional similarity value XZi corresponding to the result with the ratio closest to one is the precise location of the target pipeline, and the corresponding target stakeholder units are matched through the preset precise location-target stakeholder unit form.
[0066] Automatically pushing pipeline mining information to stakeholders in key information according to a preset push strategy means: acquiring real-time monitoring information of the target pipeline in the pipeline mining information and pushing information to corresponding target stakeholder units according to the precise location of the target pipeline.
[0067] Monitoring the target stakeholder's reading of the pushed information, calculating the target stakeholder's reading value and comparing it with the preset reading threshold of the target stakeholder means:
[0068] Obtain various types of reading data of the target stakeholder unit and mark them as YSi respectively, obtain the preset interest coefficient corresponding to the target stakeholder unit, and then calculate the preset reading threshold of the target stakeholder unit, YZi=xi·BD, YZi is the preset reading threshold of the target stakeholder unit, xi is the preset interest coefficient corresponding to the target stakeholder unit, BD is the preset standard interest reference, and then calculate the reading value, YDi=Σ(ki·YSi), YDi is the reading value of the target stakeholder unit, ki is the reading coefficient corresponding to each type of reading data, if the reading value of the target stakeholder unit is greater than or equal to the preset reading threshold of the target stakeholder unit, no reminder is issued, otherwise reminders of different levels are issued.
[0069] In step 4, if the reading value of the target stakeholder unit is less than the preset reading threshold of the target stakeholder unit, different levels of reminders are issued according to the preset reminder strategy, which means:
[0070] There is a preset reminder level-proportion interval form to calculate the proportion value. BL is a proportional value, r1 and r2 are both preset specific proportional coefficients, and a corresponding level of reminder is issued according to the reminder level corresponding to the proportional interval into which the proportional value BL falls.
[0071] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0072] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0073] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0074] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0075] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0076] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. The pipeline mining information intelligent extraction and collaborative sharing method based on AI technology is characterized by: The following steps are involved: Step 1: Automatically and intelligently extract corresponding professional information from the basic pipeline mining information reported by the construction unit; Step 2: According to the preset matching strategy, the fuzzy location information in the professional information is automatically matched with the key information of the target pipeline; Step 3: Automatically push pipeline mining information to stakeholders in key information according to the preset push strategy; Step 4: monitor the target stakeholder's reading of the pushed information, calculate the target stakeholder's reading value and compare it with the preset reading threshold of the target stakeholder. If the target stakeholder's reading value is greater than or equal to the preset reading threshold of the target stakeholder, no reminder is issued. If the target stakeholder's reading value is less than the preset reading threshold of the target stakeholder, different levels of reminders are issued according to the preset reminder strategy. According to the preset matching strategy, the key information for automatically matching the fuzzy location information in the professional information to the target pipeline is: Obtain the fuzzy location information in the professional information and confirm the monitoring area according to the preset matching strategy; Obtain the topographic information of the monitoring area, which includes the bare land area coefficient, the vegetation area coefficient, the lake area coefficient, the total number of bare land pixels, the total number of vegetation pixels, the total number of lake pixels, and the total number of image pixels; The specific steps to obtain it are as follows: S1, obtain images of the monitoring area through an optical satellite outside the atmosphere, and send the obtained images to the cloud computing platform; S2. When the cloud computing platform receives the image, it imports the vector file of the monitoring area, crops the image through ArcGIS software to obtain the image of the monitoring area, and pre-processes the image of the monitoring area; S3, identifying the image of the monitoring area, and obtaining the total number of pixels of bare land, the total number of pixels of vegetation, the total number of pixels of lakes, and the total number of pixels of the image; S4, mark the bare land area coefficient, vegetation area coefficient, and lake area coefficient as f1, f2, and f3 respectively, mark the total number of pixels of bare land as LDi, the total number of pixels of vegetation as ZBi, the total number of pixels of lakes as HPi, and the total number of pixels of the image as ZSi; S5. Obtain the similarity of the monitoring area through the formula, XSi is the similarity of the monitoring area. Then, the GIS information in the key information of all pipelines and the regional similarity value XZi corresponding to the GIS information are obtained. The ratio of the regional similarity value XZi corresponding to all GIS information and the similarity XSi of the monitoring area is calculated. The GIS information corresponding to the regional similarity value XZi corresponding to the result with the ratio closest to one is the precise location of the target pipeline, and the corresponding target stakeholder units are matched through the preset precise location-target stakeholder unit form; Automatically pushing pipeline mining information to stakeholders in key information according to a preset push strategy means: acquiring real-time monitoring information of the target pipeline in the pipeline mining information and pushing information to corresponding target stakeholders according to the precise location of the target pipeline; Monitoring the target stakeholder's reading of the pushed information, calculating the target stakeholder's reading value and comparing it with the preset reading threshold of the target stakeholder means: Obtain each type of reading data of the target stakeholder unit and mark them as YSi respectively, obtain the preset interest coefficient corresponding to the target stakeholder unit, and then calculate the preset reading threshold of the target stakeholder unit, YZi=xi·BD, YZi is the preset reading threshold of the target stakeholder unit, xi is the preset interest coefficient corresponding to the target stakeholder unit, BD is the preset standard interest reference, and then calculate the reading value, YDi=Σ(ki·YSi), YDi is the reading value of the target stakeholder unit, ki is the reading coefficient corresponding to each type of reading data, if the reading value of the target stakeholder unit is greater than or equal to the preset reading threshold of the target stakeholder unit, then no reminder is issued, otherwise different levels of reminders are issued; In step 4, if the reading value of the target stakeholder unit is less than the preset reading threshold of the target stakeholder unit, different levels of reminders are issued according to the preset reminder strategy, which means: There is a preset reminder level-proportion interval form to calculate the proportion value. BL is a proportional value, r1 and r2 are both preset specific proportional coefficients, and a corresponding level of reminder is issued according to the reminder level corresponding to the proportional interval into which the proportional value BL falls.
2. The method for intelligent extraction and collaborative sharing of pipeline mining information based on AI technology according to claim 1 is characterized in that: The corresponding professional information from the basic pipeline excavation information reported by the construction unit includes the fuzzy location information, pipeline professional information and time information of the pipeline excavation.
3. The method for intelligent extraction and collaborative sharing of pipeline mining information based on AI technology according to claim 2 is characterized in that: The key information of the target pipeline includes GIS information and information of stakeholders.