A method for building curtain wall construction

By establishing keel model diagrams and layout diagrams, pre-assembly of keels, and accurately projecting and adjustments during the installation process, the problem of high installation accuracy requirements of arc cement boards is solved, and the precise installation and gap treatment of arc cement boards is achieved , improves the beauty and waterproof performance of the facade.

CN118704782BActive Publication Date: 2024-11-15BEIJING URBAN CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411178716.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-15
Estimated Expiration
2044-08-27

AI Technical Summary

Technical Problem

The keel of the arc cement board and the arc cement board have high accuracy requirements during the installation process. If the shape and size of each arc cement board cannot be accurately matched during installation, there may be differences in height or uneven gaps, which is serious. Impacts the beauty and waterproof performance of the facade.

Method used

By establishing keel model diagrams and layout diagrams, pre-assembly keels, and accurately casting and adjusting during the installation process, ensuring the installation accuracy of the arc-shaped cement boards, fixing them with countersunk stainless steel self-tapping screws and appropriate gaskets to maintain gaps. Caulking and smearing mortar treatment for a tight fit.

Benefits of technology

The installation accuracy of curved cement boards is improved, the gaps are not uniform and the height difference is reduced, and the beauty and waterproof performance of the facade are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118704782B_ABST
    Figure CN118704782B_ABST
Patent Text Reader

Abstract

The present application discloses a method for building curtain wall construction. The method for building curtain wall construction includes: S1, accurately projecting control points according to the keel layout diagram; S2, establishing a keel model diagram; pre-assembling the keel according to the keel model diagram; S3, hoisting the keel as a whole after pre-assembly, and matching different facades with the positions of multiple control points during the hoisting process; S4, marking the surface material control points on the keel, and installing the curved cement board according to the surface material control points. The present application solves the technical problem that the keel of the curved cement board and the installation process of the curved cement board have high requirements for accuracy. If the shape and size of each curved cement board cannot be accurately matched during installation, height differences or uneven gaps may occur, which seriously affects the aesthetics and waterproof performance of the facade.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of curtain wall construction, and in particular to a method for constructing a building curtain wall. Background Art

[0002] In some projects with special requirements, the curved cement board used on the facade is a special-shaped building curtain wall component. For the accuracy of keel installation, the curved design requires that the curvature and position of the keel must be highly accurate. Any slight deviation may cause the subsequent installation of the curved cement board to be unsmooth, affecting the overall appearance. For example, if the curvature of the keel is inconsistent with the design requirements, the curved cement board may have problems such as large gaps, uneven splicing or inability to fit tightly during installation. The tight docking of the surface materials is also a key difficulty.

[0003] Due to its curved shape, the shape and size of each curved cement board need to be precisely matched, and during the installation process, it is necessary to ensure that the adjacent curved cement boards are tightly and seamlessly joined, which requires superb technology and strict quality control in both the processing and installation links. For example, if there is an error in the size of two adjacent curved cement boards during processing, or if they are not adjusted to the optimal position during installation, there may be height differences or uneven gaps, which will seriously affect the appearance and waterproof performance of the facade.

[0004] In view of the high precision requirements for the keel and installation of the curved cement slabs in the related technology, if the shape and size of each curved cement slab cannot be accurately matched during installation, height differences or uneven gaps may occur, seriously affecting the appearance and waterproof performance of the facade. No effective solution has been proposed so far. Summary of the invention

[0005] The main purpose of this application is to provide a building curtain wall construction method to solve the problem that the keel of the curved cement board and the curved cement board have high precision requirements during installation. If the shape and size of each curved cement board cannot be accurately matched during installation, height differences or uneven gaps may occur, which seriously affects the appearance and waterproof performance of the facade.

[0006] In order to achieve the above-mentioned purpose, the present application provides a building curtain wall construction method.

[0007] The building curtain wall construction method according to the present application comprises:

[0008] S1. Accurately project and measure control points according to the keel layout;

[0009] S2, establishing a keel model diagram; pre-assembling the keel according to the keel model diagram;

[0010] S3, hoisting the pre-assembled keel as a whole, and matching different facades with the positions of the plurality of control points during the hoisting process;

[0011] S4, marking the surface material control points on the keel, and installing the curved cement board according to the surface material control points;

[0012] S5. During the installation of the curved cement slab, if there is a local deviation of the keel, timely adjustment is made;

[0013] S6, filling the gap between two adjacent curved cement boards and painting the surfaces of the curved cement boards.

[0014] Furthermore, the installation of the curved cement board in step S4 includes the following steps:

[0015] S4.1. The installation sequence of the curved cement slabs is from the lower layer to the upper layer according to different construction sections;

[0016] S4.2, pasting a waterproof breathable membrane on the back of the curved cement board;

[0017] S4.2.1, pasting the waterproof breathable membrane layer by layer from the bottom in an overlapping manner;

[0018] S4.2.2, the lap length of the waterproof breathable membrane in the horizontal and vertical directions shall not be less than 100mm;

[0019] S4.3, after pasting, immediately install the curved cement board;

[0020] S4.4. Mark the control points of different construction sections.

[0021] Furthermore, step S4.3 includes:

[0022] S4.3.1. Use countersunk stainless steel self-tapping screws to fix the curved cement board to the keel;

[0023] S4.3.1.1. First fix the middle part of the curved cement board, and then fix the surrounding parts;

[0024] S4.3.1.2. During installation, the curved cement board should be close to the keel and not move; the screw spacing should be less than or equal to 250mm, and the distance between the screw and the board edge should not be less than 15mm.

[0025] Further, step S6 includes the following steps:

[0026] S6.1. The curved cement board is installed horizontally and a gap of 3-5 mm is maintained by using a suitable gasket;

[0027] S6.2, caulking treatment of joint positions;

[0028] S6.2.1. Attach the mesh seam tape with the seam as the center;

[0029] S6.2.2. Use caulking compound to smooth the screw heads;

[0030] S6.2.3, Use plastering mortar to smooth the entire curved surface;

[0031] S6.2.4, embed reinforcing mesh cloth into the plaster mortar;

[0032] S6.2.5 Drying;

[0033] S6.2.6. Apply outdoor primer on the surface of the plaster mortar; use a special brushing device to clean impurities on the surface of the primer and apply topcoat.

[0034] Furthermore, in step S6.2.6, the painting device painting includes:

[0035] A machine, a cleaning and painting mechanism for cleaning impurities on the surface of the primer and applying topcoat;

[0036] The cleaning and painting mechanism comprises: a cleaning component for cleaning impurities on the surface of the primer and a spraying component for spraying the primer.

[0037] Further, the cleaning component includes: a preliminary cleaning component for preliminary cleaning of the primer surface, and a secondary cleaning component for secondary cleaning of the primer surface;

[0038] The preliminary cleaning assembly comprises: a cleaning member, and a telescopic rod hinged to the cleaning member; the telescopic rod is mounted on one side of the machine platform;

[0039] A disc is coaxially connected to the side wall of the outer side of the cleaning member, and a hinge shaft is provided on the disc; a hinge rod is coaxially connected to the hinge shaft, and an extrusion block is hingedly connected to the other end of the hinge rod; the outer side of the extrusion block is slidably connected to a limited block; an air bag is installed on the extended stroke of the extrusion block; the air outlet end of the air bag is connected to a connecting pipe, and a slider is slidably installed in the connecting pipe;

[0040] The secondary cleaning assembly comprises: an air nozzle connected to the slider, and a high-pressure air source for supplying air to the air nozzle;

[0041] When the cleaning member is cleaning, it drives the disc to rotate, and then drives the hinge rod to swing, thereby driving the extrusion block to intermittently squeeze the airbag, so that the slider drives the air nozzle to swing back and forth.

[0042] Furthermore, the cleaning member is composed of a plurality of arc-shaped cleaning parts connected in sequence; two adjacent arc-shaped cleaning parts are connected via a flexible connecting member.

[0043] Furthermore, the end of the cleaning member is provided with a roller, an arc-shaped scraper, and a lever in sequence;

[0044] The shifting rod abuts against the end of the cleaning member.

[0045] Furthermore, the spraying assembly includes:

[0046] A spray gun, a delivery pump connected to the spray gun, and a storage tank connected to the delivery pump;

[0047] A support frame is installed at the bottom of the spray gun, a moving component for driving the support frame to move is installed at the bottom of the support frame, and an anti-shake component is installed on the support frame;

[0048] The moving assembly includes: moving wheels arranged in sequence along the up and down directions, a connecting frame connected to the moving wheels, and a third motor driving the moving wheels to move.

[0049] Furthermore, the anti-shake component is composed of a double bearing connected to the spray gun and a gravity component rotatably mounted on the outer wall of the double bearing.

[0050] In the embodiment of the present application, a keel model diagram, a keel layout diagram, and a pre-assembled curved cement board are established, and the method of timely adjustment during the installation process is adopted, through S1, according to the keel layout diagram, accurately projecting control points; S2, establishing a keel model diagram; pre-assembling keels according to the keel model diagram; S3, hoisting the pre-assembled keel as a whole, and in the hoisting process, matching different facades with the positions of multiple control points respectively; S4, marking the surface material control points on the keel, and installing the curved cement board according to the surface material control points; S5, during the installation of the curved cement board, if there is a keel S6, filling the gap between the two adjacent curved cement boards and painting the surface of the curved cement boards, so as to achieve the purpose of accurately installing the curved cement boards to the control points and reducing the deviations, thereby achieving the technical effect of improving the installation accuracy of the curved cement boards, and further solving the technical problem that due to the high precision requirements for the keels of the curved cement boards and the installation of the curved cement boards, if the shapes and sizes of each curved cement board cannot be accurately matched during installation, height differences or uneven gaps may occur, which seriously affects the aesthetics and waterproof performance of the facade. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:

[0052] Figure 1 is a schematic diagram of a process according to an embodiment of the present application;

[0053] Figure 2 is a flow chart of step S6 according to an embodiment of the present application;

[0054] Figure 3 is an axial schematic diagram of a painting device according to an embodiment of the present application;

[0055] Figure 4 is a schematic structural diagram of a painting device according to an embodiment of the present application;

[0056] Figure 5 is a schematic structural diagram of a cleaning and brushing mechanism according to an embodiment of the present application;

[0057] Figure 6 yes Figure 5 A partial enlarged view of part A;

[0058] Figure 7 yes Figure 5 A partial enlarged view of part B;

[0059] Figure 8 is an exploded schematic diagram of a cleaning component according to an embodiment of the present application;

[0060] Fig. 9 yes Figure 8 A partial enlarged view of part C in the middle;

[0061] Fig.10 is a schematic structural diagram of an anti-shake component according to an embodiment of the present application;

[0062] Fig.11 is a schematic diagram of the structure of the active shaft and the active shaft according to an embodiment of the present application;

[0063] Fig.12 is a structural schematic diagram of a traveling mechanism according to an embodiment of the present application;

[0064] Fig.13 is a schematic diagram of the structure of a mobile component according to an embodiment of the present application;

[0065] Fig.14 is a schematic structural diagram of a flexible connector according to an embodiment of the present application;

[0066] Fig.15 is a cross-sectional view of a cleaning element according to an embodiment of the present application.

[0067] Reference numerals

[0068] 1. Machine; 2. Traveling mechanism; 3. Cleaning and brushing mechanism; 21. Driving wheel; 22. Driven wheel; 23. First gear; 24. Second gear; 25. First motor; 26. Chain; 31. Cleaning assembly; 32. Spraying assembly; 311. Preliminary cleaning assembly; 312. Secondary cleaning assembly; 3111. Cleaning piece; 3112. Telescopic rod; 3113. Disc; 3114. Articulated rod; 3115. Extrusion block; 3116. Limit block; 3117. Air bag; 3118. Connecting pipe; 3119. Sliding block; 3121. Air nozzle; 3122. High-pressure gas source; 31111, arc-shaped cleaning part; 31112, flexible connecting part; 31113, roller; 31114, arc-shaped scraper; 31115, lever; 31116, driven shaft; 31117, driving shaft; 31118, ball bearing; 31119, second motor; 311121, bump; 4, mounting seat; 321, spray gun; 322, supporting frame; 323, moving assembly; 324, anti-shake part; 3231, moving wheel; 3232, connecting frame; 3233, third motor; 3241, double bearing; 3242, gravity part. DETAILED DESCRIPTION

[0069] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0070] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0071] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present invention and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0072] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those skilled in the art, the specific meanings of these terms in the present invention can be understood according to specific circumstances.

[0073] In addition, the terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0074] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0075] like Figure 1-Figure 15 As shown, the present application relates to a building curtain wall construction method, which includes:

[0076] S1. According to the keel layout diagram of the corresponding project, accurately project and measure the control points; when installing the keel, strictly follow the keel layout diagram;

[0077] S2. Establish a keel model diagram; pre-assemble keels according to the keel model diagram; the maximum keel spacing is 600mm or 625mm; pre-assemble keels according to the keel model diagram, and pre-assembly can improve the efficiency and accuracy of keel installation; for example, in a large commercial construction project, through pre-assembly of keels, it was found that the processing dimensions of some keels were deviated, and adjustments and replacements were made in time, avoiding problems found during installation at the construction site, thereby ensuring that the project can be completed on time and with high quality;

[0078] S3. The pre-assembled keel is hoisted as a whole, and during the hoisting process, different facades are matched with the positions of multiple measurement control points respectively; ensuring that the position and posture of the keel after installation are accurate, greatly reducing the possibility of correction after installation, saving time and cost;

[0079] S4. Mark the surface material control points on the keel and install the curved cement board according to the surface material control points; the surface material control points can provide a clear position reference for the installation of the curved cement board, ensuring that the installation position of each cement board is accurate, making the entire installation effect more neat and beautiful;

[0080] S4.1. The installation sequence of the curved cement slab is from the lower layer to the upper layer according to the different construction sections. Starting from the lower layer provides a stable foundation support for the installation of the upper layer. After the lower cement slab is firmly installed, it can better bear the weight of the upper cement slab, ensuring the stability and safety of the entire structure. It avoids the risk of objects falling due to the construction below when the upper layer is not installed completely.

[0081] S4.2, paste a waterproof breathable membrane on the back of the curved cement board;

[0082] S4.2.1. Adhere the waterproof breathable membrane layer by layer from the bottom by overlapping. Adhere the waterproof breathable membrane layer by layer from the bottom to ensure that the pasting order of the membrane is reasonable. The bottom as the foundation can better bear the weight and tension of the upper membrane, and reduce the problems of wrinkles and hollows in the membrane during the pasting process.

[0083] S4.2.2 The overlap length of the waterproof breathable membrane in the horizontal and vertical directions shall not be less than 100 mm, which can ensure that there is sufficient overlap between adjacent waterproof breathable membranes to form an effective waterproof seal and prevent moisture from penetrating from the overlap;

[0084] S4.3. After pasting, install the curved cement board immediately to prevent the waterproof breathable membrane from being contaminated, damaged or displaced in the exposed environment;

[0085] S4.3.1. Use countersunk stainless steel self-tapping screws to fix the curved cement board to the keel;

[0086] S4.3.1.1. First fix the middle part of the curved cement board, then fix the surrounding parts; this can better make the cement board bear the force evenly and improve the firmness and stability of the fixation;

[0087] S4.3.1.2. During installation, the curved cement board should be close to the keel and not move, ensuring that the curved cement board and the keel are tightly connected; the screw spacing should be less than or equal to 250mm, and the distance between the screw and the board edge should be no less than 15mm;

[0088] S4.4. Mark the control points of different construction sections. This helps ensure that the construction location and size of each construction section are accurate and meet the design requirements, thereby improving the accuracy and quality of the overall construction. If a problem occurs, it can also be traced back to the specific construction section through the control point marking, which facilitates the location and resolution of the problem.

[0089] S5. During the installation of the curved cement board, if there is a local deviation of the keel, adjust it in time; adjust the local deviation in time to prevent the deviation from accumulating in the subsequent installation process and affecting the overall installation effect;

[0090] S6. Fill the gap between two adjacent curved cement boards and paint the surface of the curved cement boards.

[0091] S6.1. Install the curved cement board horizontally and use appropriate gaskets to maintain a gap of 3-5 mm;

[0092] S6.2. After the installation of the curved cement board is completed, the joints should be caulked immediately;

[0093] S6.2.1. A mesh cloth seam tape is embedded around the seam, preferably a 100 mm wide mesh cloth seam tape, to enhance the tensile strength and crack resistance of the seam and prevent cracking at the seam during subsequent use;

[0094] S6.2.2. Use caulking material to smooth the screw heads, which is more beautiful and can avoid unevenness caused by protruding screw heads, reduce the risk of scratches, and enhance the protection of screw heads to prevent them from corrosion and damage;

[0095] S6.2.3, Use plastering mortar to smooth the entire curved surface, making the surface of the curved cement board more flat and smooth, providing a good foundation for subsequent construction steps;

[0096] S6.2.4, Use reinforcing mesh cloth embedded in the plastering mortar to enhance the strength and crack resistance of the mortar layer;

[0097] S6.2.5 Drying;

[0098] S6.2.6. Apply outdoor primer on the surface of the plaster mortar. The primer must dry for at least 24 hours. Since the primer takes a long time to dry, impurities may adhere to the surface of the primer during the drying process. Therefore, a special brushing device is required to clean the impurities on the surface of the primer and apply the topcoat.

[0099] It can be seen from the above description that in the embodiment of the present application, a keel model diagram, a keel layout diagram, a pre-assembled curved cement board, and timely adjustments during the installation process are adopted, through S1, accurately projecting control points according to the keel layout diagram; S2, establishing a keel model diagram; pre-assembling keels according to the keel model diagram; S3, hoisting the keel after pre-assembly as a whole, and in the hoisting process, matching different facades with the positions of multiple control points respectively; S4, marking the surface material control points on the keel, and installing the curved cement board according to the surface material control points; S5, the process of installing the curved cement board In the process, if there is a local deviation of the keel, timely adjustment is made; S6, filling the gap between the two adjacent curved cement boards and painting the surface of the curved cement board, so as to achieve the purpose of accurately installing the curved cement board to the control point and reducing the deviation, thereby achieving the technical effect of improving the installation accuracy of the curved cement board, and further solving the technical problem that due to the high precision requirements for the keel of the curved cement board and the curved cement board during installation, if the shape and size of each curved cement board cannot be accurately matched during installation, height differences or uneven gaps may occur, causing serious impact on the appearance and waterproof performance of the facade.

[0100] Preferably, in step S6.2.6, the painting device comprises: a machine 1, a traveling mechanism 2 for driving the machine 1 to move, and a cleaning and painting mechanism 3 for cleaning impurities on the surface of the primer and applying the topcoat;

[0101] The traveling mechanism 2 includes: a driving wheel 21, and a driven wheel 22 moving with the driving wheel 21; there are two driving wheels 21, which are coaxially connected, and a first gear 23 is fixedly installed on the connecting shaft, a chain 26 is meshed on the first gear 23, and a second gear 24 is meshed on the chain 26. The second gear 24 is coaxially connected to the output shaft of the first motor 25, and is used to drive the driving wheel 21 to rotate through the first motor 25; the traveling mechanism 2 can also be a universal wheel installed at the bottom of the machine 1, and the staff can move the machine 1 by pushing the machine 1 by hand.

[0102] The cleaning and painting mechanism 3 includes: a cleaning component 31 for cleaning impurities on the primer surface, and a spraying component 32 for spraying primer; firstly, the impurities on the primer surface are cleaned by the cleaning component 31, and then the primer surface is sprayed with paint by the spraying component 32, so as to improve the spraying effect.

[0103] When working on the surface of a low-rise curved cement slab, set up a scaffold and place the painting device on the top of the scaffold; when working on the surface of a high-rise curved cement slab, place the painting device on a hanging basket or a lifting platform.

[0104] Preferably, the cleaning component 31 includes: a preliminary cleaning component 311 for preliminary cleaning of the primer surface, and a secondary cleaning component 312 for secondary cleaning of the primer surface;

[0105] The preliminary cleaning assembly 311 includes: a cleaning member 3111 and a telescopic rod 3112 hinged to the cleaning member 3111; the telescopic rod 3112 is slidably mounted on one side of the machine 1 to support the cleaning member 3111;

[0106] A disc 3113 is coaxially connected to the side wall of the cleaning member 3111, and a hinge shaft is fixedly installed on the side wall of the disc 3113; a hinge rod 3114 is coaxially hinged to the hinge shaft, and the hinge rod 3114 is hinged by two hinge units hinged to each other;

[0107] The other end of the hinge rod 3114 is hinged with an extrusion block 3115; the outer side of the extrusion block 3115 is slidably connected to a limit block 3116, and the limit block 3116 is provided with a slide groove adapted to the extrusion block 3115, so that the extrusion block 3115 can slide along the limit block 3116; an air bag 3117 is installed on the extended stroke of the extrusion block 3115; the air outlet end of the air bag 3117 is connected to a connecting pipe 3118, and a slider 3119 is slidably installed in the connecting pipe 3118;

[0108] The secondary cleaning component 312 includes: an air nozzle 3121 connected to the slider 3119, and a high-pressure air source 3122 for supplying air to the air nozzle 3121; the high-pressure air source 3122 can be a high-pressure air source 3122 for spraying high-pressure gas, or a high-pressure air source 3122 for causing the air nozzle 3121 to inhale air;

[0109] When the cleaning member 3111 is cleaning, the rotating shaft of the cleaning member 3111 rotates, driving the disc 3113 to rotate, so that the hinge shaft of the disc 3113 drives the hinge rod 3114 to swing back and forth, thereby driving the extrusion block 3115 to intermittently squeeze the airbag 3117 or stretch the airbag 3117, and then driving the slider 3119 to slide back and forth along the connecting tube 3118, thereby driving the air nozzle 3121 to swing back and forth. During the swinging process of the air nozzle 3121, the part cleaned by the cleaning member 3111 is cleaned for the second time.

[0110] Preferably, the cleaning member 3111 is composed of a plurality of arc-shaped cleaning portions 31111 connected in sequence; two adjacent arc-shaped cleaning portions 31111 are connected via a flexible connector 31112, and the connection via the flexible connector 31112 allows a certain swinging space between the two adjacent arc-shaped cleaning portions 31111, thereby making it easier to adapt to arc surfaces of different curvatures, thereby achieving a better cleaning effect; the flexible connector 31112 may be a rubber strip, a belt, etc.; as an optional method, two adjacent arc-shaped cleaning portions 31111 may also be hinged to each other.

[0111] Preferably, the end of the cleaning member 3111 is provided with a roller 31113, an arc-shaped scraper 31114, and a lever 31115 in sequence;

[0112] The rotating shaft of the cleaning member 3111 is composed of a driven rotating shaft 31116, a driving rotating shaft 31117 coaxially slidably connected with the driven rotating shaft 31116, and a ball 31118 rollingly installed between the driven rotating shaft 31116 and the driving rotating shaft 31117; when the driving rotating shaft 31117 rotates, the driven rotating shaft 31116 does not rotate along with the driving rotating shaft 31117;

[0113] The roller 31113 is coaxially connected to the driving shaft 31117. When the cleaning member 3111 moves, the roller 31113 is in frictional contact with the surface of the arc-shaped cement board, so that the roller 31113 rolls. When the roller 31113 rolls, the disc 3113 is driven to rotate synchronously.

[0114] The arc-shaped cleaning portion 31111 is coated on the surface of the driven shaft 31116, and the disc 3113 and the arc-shaped scraper 31114 are fixedly mounted on the driving shaft 31117;

[0115] The arc scraper 31114 is coaxially connected to a second motor 31119, and the second motor 31119 is used to drive the active shaft 31117 to rotate when the roller 31113 cannot rotate, or to rotate when the arc cleaning portion 31111 needs to be cleaned; the second motor 31119 is preferably a self-locking motor;

[0116] The end of the arc-shaped cleaning portion 31111 has a protrusion 311121, and the lever 31115 abuts against the protrusion 311121 at the end of the cleaning member 3111, which is used to prevent the arc-shaped cleaning portion 31111 from rotating during cleaning; on the other hand, it is used to drive the cleaning member 3111 to rotate when the cleaning member 3111 needs to rotate; preventing the arc-shaped cleaning portion 31111 from rotating by itself during cleaning is to ensure the consistency and stability of the cleaning effect. For example, the arc-shaped cleaning portion 31111 rotates by itself, which may cause some areas to be over-cleaned, while other areas are not cleaned enough, resulting in uneven cleaning effect;

[0117] When there is no need to clean impurities on the surface of the arc-shaped cleaning portion 31111, the arc-shaped cleaning portion 31111 moves along the surface of the arc-shaped cement board. During the movement, on the one hand, it cleans impurities on the surface of the arc-shaped cement board, and on the other hand, it drives the roller 31113 to rotate, thereby driving the disc 3113 to rotate, so that the spray gun swings intermittently;

[0118] When the arc-shaped cleaning portion 31111 needs to be cleaned, the second motor 31119 is started, and the second motor 31119 drives the active shaft 31117 to rotate. During the rotation of the active shaft 31117, on the one hand, it drives the air nozzle 3121 to swing back and forth; on the other hand, it drives the arc-shaped scraper 31114 to rotate. During the rotation of the arc-shaped scraper 31114, impurities remaining on the surface of the arc-shaped cleaning portion 31111 during cleaning are scraped off, so that the arc-shaped cleaning portion 31111 maintains a good cleaning effect; at the same time, the second motor 31119 drives the lever 31115 to rotate, and during the rotation of the lever 31115, the arc-shaped cleaning portion 31111 is moved to turn over the arc-shaped cleaning portion 31111;

[0119] When it is necessary to clean the other side of the arc-shaped cleaning portion 31111, the second motor 31119 is reversed to cause the arc-shaped scraper 31114 to rotate relative to the arc-shaped cleaning portion 31111 in the opposite direction; in this way, the cleaning side and the non-cleaning side of the arc-shaped cleaning portion 31111 can be alternately exchanged and cleaned during each exchange process; in addition, when the cleaning side rotates to the side away from the arc-shaped cement board, the staff can easily observe whether the surface of the arc-shaped cleaning portion 31111 has been cleaned; if stubborn impurities are found to remain, the staff can manually further clean the arc-shaped cleaning portion 31111.

[0120] Preferably, a mounting seat 4 is also installed on one side of the telescopic rod 3112 connected to the cleaning member 3111; the mounting seat 4 includes: a base detachably connected to the end of the telescopic rod 3112, a sliding seat slidably connected to the base, and an elastic member installed between the sliding seat and the base.

[0121] Preferably, the spray assembly 32 includes: a spray gun 321, a delivery pipe connected to the spray gun 321, a delivery pump connected to the delivery pipe, and a storage tank connected to the delivery pump; the storage tank is used to store paint; the delivery pump is used to deliver the paint in the storage tank to the spray gun 321.

[0122] A support frame 322 is installed at the bottom of the spray gun 321, a moving assembly 323 for driving the support frame 322 to move is installed at the bottom of the support frame 322, and an anti-shake component 324 is installed on the support frame 322 to prevent the spray gun 321 from shaking due to the swing of the random platform 1;

[0123] The moving assembly 323 includes: moving wheels 3231 arranged in sequence along the up-down direction, a connecting frame 3232 connected to the moving wheels 3231, and a third motor 3233 driving the moving wheels 3231 to move;

[0124] The anti-shake component 324 is composed of a double bearing 3241 connecting the spray gun and the conveying pipeline, and a gravity component 3242 rotatably installed on the outer wall of the double bearing 3241; the setting of the double bearing 3241 allows the spray gun to rotate freely relative to the pipeline, and the design of the gravity component 3242 allows the spray gun to spray while maintaining a horizontal posture without swinging with the shaking of the hanging basket, thereby reducing the impact of the shaking of the hanging basket; the double bearing 3241 is preferably a high-quality and low-friction double bearing 3241.

[0125] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A building curtain wall construction method, characterized in that: The method includes: S1. Accurately project and measure control points according to the keel layout; S2, establishing a keel model diagram; pre-assembling the keel according to the keel model diagram; S3, hoisting the pre-assembled keel as a whole, and matching different facades with the positions of the plurality of control points during the hoisting process; S4, marking the surface material control points on the keel, and installing the curved cement board according to the surface material control points; S5. During the installation of the curved cement slab, if there is a local deviation of the keel, timely adjustment is made; S6, filling the gap between two adjacent curved cement boards and painting the surfaces of the curved cement boards; Step S6 includes the following steps: S6.

1. The curved cement board is installed horizontally and a gap of 3-5 mm is maintained by using a suitable gasket; S6.2, caulking treatment of joint positions; S6.2.

1. Attach the mesh seam tape with the seam as the center; S6.2.

2. Use caulking compound to smooth the screw heads; S6.2.3, Use plastering mortar to smooth the entire curved surface; S6.2.4, embed reinforcing mesh cloth into the plaster mortar; S6.2.5 Drying; S6.2.6, apply outdoor primer on the surface of the plaster mortar; use a special brushing device to clean the impurities on the surface of the primer, and apply topcoat; In step S6.2.6, the painting device painting includes: A machine, a cleaning and painting mechanism for cleaning impurities on the surface of the primer and applying topcoat; The cleaning and painting mechanism comprises: a cleaning component for cleaning impurities on the surface of the primer, and a spraying component for spraying the primer; The cleaning component comprises: a preliminary cleaning component for preliminary cleaning of the primer surface, and a secondary cleaning component for secondary cleaning of the primer surface; The preliminary cleaning assembly comprises: a cleaning member, and a telescopic rod hinged to the cleaning member; the telescopic rod is mounted on one side of the machine platform; A disc is coaxially connected to the side wall of the outer side of the cleaning member, and a hinge shaft is provided on the disc; a hinge rod is coaxially connected to the hinge shaft, and an extrusion block is hingedly connected to the other end of the hinge rod; the outer side of the extrusion block is slidably connected to a limited block; an air bag is installed on the extended stroke of the extrusion block; the air outlet end of the air bag is connected to a connecting pipe, and a slider is slidably installed in the connecting pipe; The secondary cleaning assembly comprises: an air nozzle connected to the slider, and a high-pressure air source for supplying air to the air nozzle; When the cleaning member is cleaning, it drives the disc to rotate, and then drives the hinged rod to swing, thereby driving the extrusion block to intermittently squeeze the airbag, so that the slider drives the air nozzle to swing back and forth; The cleaning member is composed of a plurality of arc-shaped cleaning parts connected in sequence; two adjacent arc-shaped cleaning parts are connected by a flexible connecting member; The end of the cleaning member is provided with a roller, an arc-shaped scraper, and a lever in sequence; The lever abuts against the end of the cleaning member; When there is no need to clean impurities on the surface of the arc-shaped cleaning part, the arc-shaped cleaning part moves along the surface of the arc-shaped cement board. During the movement, on the one hand, it cleans impurities on the surface of the arc-shaped cement board, and on the other hand, it drives the roller to rotate, thereby driving the disc to rotate, so that the spray gun swings intermittently; When the arc-shaped cleaning part needs to be cleaned, the second motor is started, and the second motor drives the active shaft to rotate. During the rotation of the active shaft, on the one hand, it drives the air nozzle to swing back and forth; on the other hand, it drives the arc-shaped scraper to rotate. During the rotation of the arc-shaped scraper, impurities remaining on the surface of the arc-shaped cleaning part during cleaning are scraped off, so that the arc-shaped cleaning part maintains a good cleaning effect; at the same time, the second motor drives the lever to rotate, and during the rotation of the lever, the arc-shaped cleaning part is moved to turn over; When it is necessary to clean the other side of the arc-shaped cleaning portion, the second motor reverses to cause the arc-shaped scraper and the arc-shaped cleaning portion to rotate in opposite directions relative to each other; in this way, the cleaning side and the non-cleaning side of the arc-shaped cleaning portion can be alternately exchanged and cleaned during each exchange process; in addition, when the cleaning side rotates to the side away from the arc-shaped cement board, the staff can easily observe whether the surface of the arc-shaped cleaning portion has been cleaned.

2. The building curtain wall construction method according to claim 1, characterized in that: The installation of the curved cement board in step S4 includes the following steps: S4.

1. The installation sequence of the curved cement slabs is from the lower layer to the upper layer according to different construction sections; S4.2, pasting a waterproof breathable membrane on the back of the curved cement board; S4.2.1, pasting the waterproof breathable membrane layer by layer from the bottom in an overlapping manner; S4.2.2, the lap length of the waterproof breathable membrane in the horizontal and vertical directions shall not be less than 100mm; S4.3, after pasting, immediately install the curved cement board; S4.

4. Mark the control points of different construction sections.

3. The building curtain wall construction method according to claim 2, characterized in that: Step S4.3 includes: S4.3.

1. Use countersunk stainless steel self-tapping screws to fix the curved cement board to the keel; S4.3.1.

1. First fix the middle part of the curved cement board, and then fix the surrounding parts; S4.3.1.

2. During installation, the curved cement board should be close to the keel and not move; the screw spacing should be less than or equal to 250mm, and the distance between the screw and the board edge should not be less than 15mm.

4. The building curtain wall construction method according to claim 1, characterized in that: The spraying assembly comprises: A spray gun, a delivery pump connected to the spray gun, and a storage tank connected to the delivery pump; A support frame is installed at the bottom of the spray gun, a moving component for driving the support frame to move is installed at the bottom of the support frame, and an anti-shake component is installed on the support frame; The moving assembly includes: moving wheels arranged in sequence along the up and down directions, a connecting frame connected to the moving wheels, and a third motor driving the moving wheels to move.

5. The building curtain wall construction method according to claim 4, characterized in that: The anti-shake component is composed of a bearing connected to the spray gun and a gravity component rotatably mounted on the outer wall of the bearing.