Feeding control system and control method for uranium tetrafluoride preparation process
By designing a feeding control system in the uranium conversion process and using components such as electronic scales, screw conveyors, and pneumatic regulating valves, precise feeding of UO2 powder and anhydrous HF was achieved, solving the problem of inaccurate measurement by volumetric method and improving It improves the automation level and production capacity stability of the uranium conversion process and ensures the quality of UF4 products.
Patent Information
- Application Number
- CN202411060707.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-10-01
AI Technical Summary
In the existing uranium conversion process, the volumetric method for measuring the amount of anhydrous HF is inaccurate, leading to problems of waste of HF gas and uneven quality of UF4.
A feeding control system for uranium tetrafluoride preparation process is designed. Through the UO2 feeding mechanism and HF feeding mechanism, combined with electronic scales, screw conveyors, heating and pressurizing devices, pneumatic regulating valves and mass flow meters, the controller is used The screw speed of the screw conveyor and the opening of the pneumatic regulating valve are adjusted in real time to achieve precise feed control of UO2 powder and anhydrous HF, ensuring that the feed mass ratio is around 1:3.38.
It achieves precise control of raw materials in the preparation process of uranium tetrafluoride, reduces energy consumption, improves the stability and productivity of the fluidized bed, and ensures the quality consistency of UF4 products.
Smart Images

Figure CN118718901A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of uranium conversion, in particular to a feed control system and a control method for a uranium tetrafluoride preparation process. Background Art
[0002] Uranium conversion is a front-end process in nuclear fuel preparation, which reacts UO2 powder with anhydrous HF gas to generate UF4. The fluidized bed is the core reaction equipment in the uranium conversion process. The main raw materials entering the equipment are UO2 powder and anhydrous HF gas. Accurately measuring the amount of anhydrous HF is not only to ensure the reaction needs, but also an effective way to reduce production costs.
[0003] At present, the volumetric method is usually used to measure the amount of anhydrous HF. The volumetric method requires that the anhydrous HF be heated to above 82°C to completely vaporize the liquid HF (HF molecules undergo dissociation reaction during the vaporization process, that is, the HF molecules that are clustered together separate into independent HF molecules), and then continuously and stably input into the fluidized bed. According to the physical and chemical properties of HF, a metal rotor flowmeter is usually used to measure the volume of HF gas, and then the amount of UO2 powder input into the fluidized bed is reasonably increased or decreased based on the volumetric measurement results of HF gas.
[0004] However, in the actual production process of uranium conversion, due to the large amount of anhydrous HF used, the heating equipment is not sufficient to heat a large amount of liquid HF raw material to above 82°C, and it can usually only be heated to about 60°C. At this temperature, the anhydrous HF is in a state of gas-liquid coexistence, resulting in inaccurate HF gas metering (the actual amount of substance corresponding to the measured volume > the theoretical amount of substance corresponding to the measured volume), and thus unable to match the appropriate UO2 powder feed amount, resulting in a large amount of HF gas waste in the fluidized bed (theoretically, HF gas is required to be added in excess of 10% according to the reaction requirements, but in reality HF gas will be in excess of 20%-30%), as well as the problem of uneven UF4 quality. Summary of the invention
[0005] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a feed control system and a control method for a uranium tetrafluoride preparation process, which solves the problem that the method for measuring the amount of anhydrous HF (volume method) in the existing uranium tetrafluoride preparation process is inaccurate in measurement, thereby causing the problem of uneven UF4 quality.
[0006] The technical solution of the present invention is: a feed control system for a uranium tetrafluoride preparation process, which is used to control the feed flow rate of two raw materials input into a fluidized bed, the two raw materials include anhydrous HF and UO2 powder, and the fluidized bed is provided with a feed port A for inputting anhydrous HF and a feed port B for inputting UO2 powder; It includes a UO2 feeding mechanism, an HF feeding mechanism and a controller; the UO2 feeding mechanism includes a UO2 hopper, an electronic scale and a screw conveyor; powdered UO2 is stored in the UO2 hopper; the electronic scale is arranged at the lower end of the UO2 hopper and is used to weigh the UO2 hopper in real time; the two ends of the screw conveyor are respectively a feeding end and a discharging end, the feeding end of the screw conveyor is connected to the inside of the UO2 hopper through a pipeline, and the discharging end of the screw conveyor is connected to the feeding port B of the fluidized bed through a pipeline; the HF feeding mechanism includes an HF storage tank, a temperature and pressure device, a pneumatic regulating valve and a mass flow meter; liquid anhydrous HF is stored in the HF storage tank; the two ends of the temperature and pressure device are respectively an inlet end and an outlet end, and the inlet end of the temperature and pressure device is connected to the fluidized bed through a pipeline The HF storage tank is connected, and the outlet end of the temperature-raising and pressurizing device is connected with the feed port A of the fluidized bed through a pipeline, which is used to heat the liquid HF to a gas-liquid mixed state and provide a flow driving force for the gas-liquid mixed HF in the pipeline; the pneumatic regulating valve and the mass flow meter are sequentially connected in series on the pipeline between the outlet end of the temperature-raising and pressurizing device and the feed port A of the fluidized bed, wherein the pneumatic regulating valve is relatively close to the temperature-raising and pressurizing device, and is used to adjust the pipeline opening and thus control the flow of anhydrous HF in the pipeline, wherein the mass flow meter is relatively close to the fluidized bed, and is used to cumulatively measure the mass of anhydrous HF flowing therethrough; the signal input end of the controller is electrically connected to the electronic scale and the mass flow meter, respectively, and the signal output end of the controller is electrically connected to the screw conveyor and the pneumatic regulating valve, respectively.
[0007] A further technical solution of the present invention is: UO2 hopper-screw conveyor-fluidized bed are arranged in sequence from high to low, so that UO2 powder is transferred downward by gravity flow.
[0008] A further technical solution of the present invention is: the HF feeding mechanism also includes a first maintenance bypass and a second maintenance bypass; the first maintenance bypass is arranged in parallel with the pneumatic regulating valve, the first maintenance bypass includes a manual stop valve A, the second maintenance bypass is arranged in parallel with the mass flow meter, and the second maintenance bypass includes a manual stop valve B.
[0009] The technical solution of the present invention is: a feeding control method for a uranium tetrafluoride preparation process, based on a feeding control system for a uranium tetrafluoride preparation process, the steps are as follows: S01, parameter setting: It is known that the hydrofluorination reaction formula of UO2 and HF is: UO2+4HF﹦UF4+2H2O; according to the process requirement that the gas phase raw material in the gas-solid reaction in the fluidized bed needs to be 10% in excess, and the ratio of the two raw materials in the above balanced hydrofluorination reaction formula, the mass ratio of HF to UO2 feed is determined to be 1:3.38; It is known that the screw speed of the screw feeder is proportional to the output of UO2 powder, and the corresponding output of UO2 powder of the screw conveyor at different screw speeds is determined, and the corresponding relationship between the screw speed and the output of UO2 powder is established; S02, feeding control: UO2 feeding mechanism and HF feeding mechanism are started respectively, and UO2 powder and anhydrous HF are respectively conveyed to the fluidized bed; the controller receives data sent by the electronic scale to calculate the cumulative weight of UO2 powder feeding in real time, and receives data sent by the mass flow meter to calculate the cumulative weight of anhydrous HF feeding in real time, and calculates the ratio of the cumulative weight of anhydrous HF feeding to the cumulative weight of UO2 powder feeding at the current time, which is recorded as the mass ratio of HF to UO2 feeding at the current time; the controller compares the mass ratio of HF to UO2 feeding at the current time with the mass ratio of HF to UO2 feeding calculated in the previous step, and controls the screw speed of the screw conveyor and / or the opening of the pneumatic regulating valve in real time according to the comparison result.
[0010] A further technical solution of the present invention is: in step S02, the control rules are as follows: if the current HF to UO2 feed mass ratio is greater than 1:3.38, the opening of the pneumatic control valve is controlled to be reduced to reduce the HF supply and / or the screw speed of the screw conveyor is controlled to be accelerated to increase the UO2 supply; if the current HF to UO2 feed mass ratio is less than 1:3.38, the opening of the pneumatic control valve is controlled to be increased to increase the HF supply and / or the screw speed of the screw conveyor is controlled to be slowed down to reduce the UO2 supply, so that the HF to UO2 feed mass ratio dynamically floats around 1:3.38.
[0011] A further technical solution of the present invention is that the liquid anhydrous HF in the HF storage tank is heated to 62° C. by a temperature-raising and pressurizing device to obtain HF in a gas-liquid mixed state, and the HF pressure in this state is 0.3±0.02 MPa.
[0012] Compared with the prior art, the present invention has the following advantages: 1. Based on the principle of weight control, it can accurately control the feeding of two raw materials (UO2 powder and anhydrous HF) in the preparation process of uranium tetrafluoride, realize the automatic interlocking control of anhydrous HF feeding and UO2 powder feeding, and improve the automation level of uranium tetrafluoride preparation process.
[0013] 2. Anhydrous HF (liquid), one of the raw materials for preparing uranium tetrafluoride, does not need to be heated to above 82°C for decomposition. It only needs to be heated to a gas-liquid mixed state before it can be used to supply the fluidized bed, thereby reducing the energy consumption of the uranium tetrafluoride preparation process.
[0014] 3. The supply of two raw materials (UO2 powder and anhydrous HF) in the preparation process of uranium tetrafluoride is stable and controllable, which improves the stability of continuous operation of the fluidized bed, helps to achieve long-term continuous production, and improves the production capacity of the uranium tetrafluoride preparation process.
[0015] The present invention is further described below in conjunction with the figures and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the structure of the present invention.
[0017] Legend: fluidized bed 100; feed port A 101; feed port B 102; UO2 hopper 11; electronic scale 12; screw conveyor 13; HF storage tank 21; temperature increasing and pressurizing device 22; pneumatic regulating valve 23; mass flow meter 24; controller 3.
[0018] Special note: The dotted arrow lines connecting the components in the figure indicate the electrical connection method and the input and output direction of the signal, and the solid arrow lines connecting the components in the figure indicate the flow / transport direction of the raw materials. DETAILED DESCRIPTION Example 1
[0019] A feed control system for a uranium tetrafluoride preparation process is used to control the feed flow rates of two raw materials input into a fluidized bed 100, wherein the two raw materials include anhydrous HF and UO2 powder. A feed port A101 for inputting anhydrous HF and a feed port B102 for inputting UO2 powder are provided on the fluidized bed 100, wherein the feed port A101 is located at the lower end of the fluidized bed 100, and the feed port B102 is located at the upper end of the fluidized bed 100.
[0020] like Figure 1 As shown, the feed control system of the uranium tetrafluoride preparation process includes a UO2 feeding mechanism, a HF feeding mechanism and a controller 3.
[0021] The UO2 feeding mechanism includes a UO2 hopper 11, an electronic scale 12 and a screw conveyor 13. Powdered UO2 is stored in the UO2 hopper 11. The electronic scale 12 is arranged at the lower end of the UO2 hopper 11 and is used to weigh the UO2 hopper 11 in real time. The two ends of the screw conveyor 13 are respectively a feed end and a discharge end. The feed end of the screw conveyor 13 is connected to the UO2 hopper 11 through a pipeline, and the discharge end of the screw conveyor 13 is connected to the feed port B102 of the fluidized bed 100 through a pipeline.
[0022] The HF feeding mechanism includes an HF storage tank 21, a temperature-raising and pressurizing device 22, a pneumatic regulating valve 23 and a mass flowmeter 24. Liquid anhydrous HF is stored in the HF storage tank 21. The two ends of the temperature-raising and pressurizing device 22 are respectively an inlet end and an outlet end. The inlet end of the temperature-raising and pressurizing device 22 is connected to the HF storage tank 21 through a pipeline, and the outlet end of the temperature-raising and pressurizing device 22 is connected to the feed port A101 of the fluidized bed 100 through a pipeline, which is used to heat the liquid HF to a gas-liquid mixed state and provide a flow driving force for the gas-liquid mixed HF in the pipeline. The pneumatic regulating valve 23 and the mass flow meter 24 are sequentially connected in series on the pipeline between the outlet end of the temperature increasing and pressurizing device 22 and the feed port A101 of the fluidized bed 100, wherein the pneumatic regulating valve 23 is relatively close to the temperature increasing and pressurizing device 22, and is used to adjust the pipeline opening and thus control the flow rate of anhydrous HF in the pipeline, wherein the mass flow meter 24 is relatively close to the fluidized bed 100, and is used to cumulatively measure the mass of anhydrous HF flowing therethrough.
[0023] The signal input end of the controller 3 is electrically connected to the electronic scale 12 and the mass flow meter 24 respectively, and the signal output end of the controller 3 is electrically connected to the screw conveyor 13 and the pneumatic regulating valve 23 respectively.
[0024] Preferably, the UO2 hopper 11 - screw conveyor 13 - fluidized bed 100 are arranged in sequence from high to low, so that the UO2 powder is transferred downward by gravity.
[0025] Preferably, the HF feeding mechanism further comprises a first maintenance bypass (not shown in the figure) and a second maintenance bypass (not shown in the figure). The first maintenance bypass is arranged in parallel with the pneumatic regulating valve, and the first maintenance bypass comprises a manual shut-off valve A, and the second maintenance bypass is arranged in parallel with the mass flow meter, and the second maintenance bypass comprises a manual shut-off valve B.
[0026] Briefly describe the working principle of the present invention: A feeding control method for a uranium tetrafluoride preparation process is based on the above-mentioned feeding control system for the uranium tetrafluoride preparation process, and the steps are as follows: S01, parameter setting: The hydrofluorination reaction formula of UO2 and HF is known to be: UO2+4HF﹦UF4+2H2O; according to the process requirement that the gas phase raw material in the gas-solid reaction in the fluidized bed needs to be in excess of 10%, and the ratio of the two raw materials in the above balanced hydrofluorination reaction formula, the mass ratio of HF to UO2 feed is determined to be 1:3.38; it is known that the screw speed of the screw feeder is proportional to the output of UO2 powder, the UO2 powder output corresponding to the screw conveyor at different screw speeds is determined, and the corresponding relationship between the screw speed and the output of UO2 powder is established.
[0027] S02, feeding control: UO2 feeding mechanism and HF feeding mechanism are started respectively, and UO2 powder and anhydrous HF are respectively conveyed to fluidized bed 100; controller 3 receives data sent by electronic scale 12 to calculate the cumulative weight of UO2 powder feeding in real time (with the continuous discharge of UO2 hopper 11, the weighing value of electronic scale 12 continues to decrease, and the difference between the initial weighing value and the current weighing value is the cumulative weight of UO2 powder feeding), controller 3 receives data sent by mass flow meter 24 to calculate the cumulative weight of anhydrous HF feeding in real time, calculates the ratio of the cumulative weight of anhydrous HF feeding to the cumulative weight of UO2 powder feeding at the current time, and records it as the mass ratio of HF to UO2 feeding at the current time; controller 3 compares the mass ratio of HF to UO2 feeding at the current time with the mass ratio of HF to UO2 feeding calculated in the previous step, and controls the screw speed of screw conveyor 13 and / or the opening of pneumatic regulating valve 23 in real time according to the comparison result.
[0028] In this step, the control rules are as follows: if the current HF and UO2 feed mass ratio is greater than 1:3.38, the opening of the pneumatic control valve 23 is controlled to be reduced to reduce the HF supply and / or the screw speed of the screw conveyor 13 is controlled to be accelerated to increase the UO2 supply; if the current HF and UO2 feed mass ratio is less than 1:3.38, the opening of the pneumatic control valve 23 is controlled to be increased to increase the HF supply and / or the screw speed of the screw conveyor 13 is controlled to be slowed down to reduce the UO2 supply, so that the HF and UO2 feed mass ratio dynamically floats around 1:3.38.
[0029] In this step, the liquid anhydrous HF in the HF storage tank 21 is heated to 62° C. by the temperature increasing and pressurizing device 22 to obtain HF in a gas-liquid mixed state, and the HF pressure in this state is 0.3±0.02 MPa.
[0030] For example: if the feed flow rate of anhydrous HF is set to 80 kg / h, the corresponding UO2 powder feed rate can be controlled at 260-270 kg / h, and the opening of the pneumatic control valve is automatically adjusted between 40%-75%. The excess amount of HF in the fluidized bed tail gas is 8%-12%, and the quality qualification rate of UF4 products can reach more than 99.5%.
Claims
1. A feed control system for a uranium tetrafluoride preparation process, which is used to control the feed flow rates of two raw materials fed into a fluidized bed, the two raw materials comprising anhydrous HF and UO2 powder, and the fluidized bed is provided with a feed port A for feeding anhydrous HF and a feed port B for feeding UO2 powder; Its characteristics are: It includes a UO2 feeding mechanism, an HF feeding mechanism and a controller; the UO2 feeding mechanism includes a UO2 hopper, an electronic scale and a screw conveyor; powdered UO2 is stored in the UO2 hopper; the electronic scale is arranged at the lower end of the UO2 hopper and is used to weigh the UO2 hopper in real time; the two ends of the screw conveyor are respectively a feeding end and a discharging end, the feeding end of the screw conveyor is connected to the inside of the UO2 hopper through a pipeline, and the discharging end of the screw conveyor is connected to the feeding port B of the fluidized bed through a pipeline; the HF feeding mechanism includes an HF storage tank, a temperature and pressure device, a pneumatic regulating valve and a mass flow meter; liquid anhydrous HF is stored in the HF storage tank; the two ends of the temperature and pressure device are respectively an inlet end and an outlet end, and the inlet end of the temperature and pressure device is connected to the fluidized bed through a pipeline The HF storage tank is connected, and the outlet end of the temperature-raising and pressurizing device is connected with the feed port A of the fluidized bed through a pipeline, which is used to heat the liquid HF to a gas-liquid mixed state and provide a flow driving force for the gas-liquid mixed HF in the pipeline; the pneumatic regulating valve and the mass flow meter are sequentially connected in series on the pipeline between the outlet end of the temperature-raising and pressurizing device and the feed port A of the fluidized bed, wherein the pneumatic regulating valve is relatively close to the temperature-raising and pressurizing device, and is used to adjust the pipeline opening and thus control the flow of anhydrous HF in the pipeline, wherein the mass flow meter is relatively close to the fluidized bed, and is used to cumulatively measure the mass of anhydrous HF flowing therethrough; the signal input end of the controller is electrically connected to the electronic scale and the mass flow meter, respectively, and the signal output end of the controller is electrically connected to the screw conveyor and the pneumatic regulating valve, respectively.
2. The feed control system for the uranium tetrafluoride preparation process according to claim 1, characterized in that: The UO2 hopper-screw conveyor-fluidized bed are arranged in sequence from high to low, so that the UO2 powder is transferred downward by gravity.
3. The feed control system for the uranium tetrafluoride preparation process according to claim 2, characterized in that: The HF feeding mechanism also includes a first maintenance bypass and a second maintenance bypass; the first maintenance bypass is arranged in parallel with the pneumatic regulating valve, the first maintenance bypass includes a manual stop valve A, the second maintenance bypass is arranged in parallel with the mass flow meter, and the second maintenance bypass includes a manual stop valve B.
4. A method for controlling the feeding of uranium tetrafluoride preparation process, based on the feeding control system of uranium tetrafluoride preparation process according to any one of claims 1 to 3, characterized in that the steps are: as follows: S01, parameter setting: The hydrofluorination reaction formula of UO2 and HF is known to be: UO2+4HF﹦UF4+2H2O; according to the process requirement that the gas phase raw material in the gas-solid reaction in the fluidized bed needs to be in excess of 10%, and the ratio of the two raw materials in the above balanced hydrofluorination reaction formula, the mass ratio of HF to UO2 feed is determined to be 1:3.38; it is known that the screw speed of the screw feeder is proportional to the output of UO2 powder, the UO2 powder output corresponding to the screw conveyor at different screw speeds is determined, and the corresponding relationship between the screw speed and the output of UO2 powder is established. 5.S02, feeding control: the UO2 feeding mechanism and the HF feeding mechanism are started respectively, and UO2 powder and anhydrous HF are respectively conveyed to the fluidized bed; the controller receives the data sent by the electronic scale to calculate the cumulative weight of the UO2 powder feed in real time, and the controller receives the data sent by the mass flow meter to calculate the cumulative weight of the anhydrous HF feed in real time, and calculates the ratio of the cumulative weight of the anhydrous HF feed to the cumulative weight of the UO2 powder feed at the current time, which is recorded as the mass ratio of HF to UO2 feed at the current time; the controller compares the mass ratio of HF to UO2 feed at the current time with the mass ratio of HF to UO2 feed calculated in the previous step, and controls the screw speed of the screw conveyor and / or the opening of the pneumatic regulating valve in real time according to the comparison result.
6. The method for controlling feed in a uranium tetrafluoride preparation process according to claim 4, characterized in that: In step S02, the control rules are as follows: if the current HF and UO2 feed mass ratio is greater than 1:3.38, the opening of the pneumatic control valve is controlled to be reduced to reduce the HF supply and / or the screw speed of the screw conveyor is controlled to be accelerated to increase the UO2 supply; if the current HF and UO2 feed mass ratio is less than 1:3.38, the opening of the pneumatic control valve is controlled to be increased to increase the HF supply and / or the screw speed of the screw conveyor is controlled to be slowed down to reduce the UO2 supply, so that the HF and UO2 feed mass ratio dynamically floats around 1:3.
38.
7. The method for controlling feed in a uranium tetrafluoride preparation process according to claim 5, characterized in that: The liquid anhydrous HF in the HF storage tank is heated to 62°C by a temperature-raising and pressurizing device to obtain HF in a gas-liquid mixed state. The HF pressure in this state is 0.3±0.02MPa.