Cross anchoring system steel tower column multi-layer horizontal position horizontal pre-assembly construction method

Through the multi-layer horizontal pre-assembly method of the cross-anchor system, the safety and economic problems of vertical pre-assembly of steel tower columns are solved, the assembly efficiency and accuracy are improved, and the high-precision installation of the bridge steel towers is ensured, which provides a good foundation for the bridge. The construction provided feasibility and technical support.

CN118745701APending Publication Date: 2024-10-08CHINA RAILWAY BAOJI BRIDGE YANGZHOU CO LTD +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410894246.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

The existing vertical pre-assembly of steel tower columns has problems such as low safety factor, poor economy, and low assembly efficiency and accuracy.

Method used

A multi-layer horizontal pre-assembly construction method using a cross-anchor system, including baseline correction, tire rack system setup, measurement control network layout, positioning and solidification of each block, precise positioning and installation of anchor pipes, and overall inspection and trimming. Through layering Assembly and measurement adjustments ensure assembly accuracy.

Benefits of technology

It improves the construction quality and efficiency of the multi-block pre-assembly operation of steel towers, ensures high-precision matching of each block, reduces construction risks, realizes high-precision hoisting of steel tower columns, shortens construction time, and improves economic benefits. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118745701A_ABST
    Figure CN118745701A_ABST
Patent Text Reader

Abstract

The invention discloses a cross anchoring system steel tower column multi-layer horizontal position horizontal pre-assembly construction method, which relates to the technical field of bridge construction, and comprises the following steps: S1, correcting the base line of each block body before pre-assembly; s2, setting a jig frame system; s3, laying a pre-assembly measurement control network; s4, positioning a lower-layer edge block body of the first section; s5, sequentially positioning lower-layer edge block bodies of other sections; s6, a first section of core concrete block body is positioned; s7, positioning the core concrete block bodies of the other sections in sequence; s8, positioning an upper-layer edge block body of the first section; s9, upper-layer edge block bodies of the other sections are positioned in sequence; s10, accurately positioning and mounting the anchor pipe; and S11, overall detection and finishing and axis system setting are carried out. The technical problems that in the prior art, steel tower vertical type pre-assembly is low in safety coefficient, poor in economical efficiency and low in assembly efficiency and precision are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a multi-layer horizontal pre-assembly construction method for steel tower columns of a cross-anchoring system. Background Art

[0002] The pre-assembly of steel towers is the link between manufacturing accuracy and bridge erection accuracy. Pre-assembly is mainly to test the manufacturing accuracy, overall manufacturing line shape and interface matching of steel towers, and is the prerequisite for ensuring smooth installation of bridges. The main purposes of pre-assembly are: verifying the matching of the interfaces of each block and segment of the steel tower, verifying the overall line shape of steel tower column manufacturing, verifying the feasibility of the manufacturing process of steel tower segments, verifying the reliability of steel tower segment manufacturing tooling, connecting temporary matching parts and adjustment devices between segments, and providing measured data for the steel tower manufacturing accuracy management system.

[0003] When the existing steel tower columns are pre-assembled in the factory using the traditional vertical method, the blocks involved in the pre-assembly are placed on the pre-assembly frame in the posture of a real bridge. Due to the influence of the assembly height, the factory can generally only achieve "1+1" segment pre-assembly. At the same time, vertical pre-assembly requires the production of special pre-assembly frames and supports. Due to the high height of the pre-assembly operation, the safety factor is low, and there are no advantages in terms of economy and assembly efficiency. Summary of the invention

[0004] The purpose of the present invention is to provide a multi-layer horizontal pre-assembly construction method for steel tower columns of a cross-anchor system, which solves the technical problems of low safety factor, poor economy, low assembly efficiency and low precision of vertical pre-assembly of steel towers in the prior art.

[0005] The present application discloses a multi-layer horizontal pre-assembly construction method of a cross-anchor system steel tower column, comprising the following steps:

[0006] S1: Baseline correction of each block before pre-assembly: Before pre-assembly, the baseline of each block is corrected;

[0007] S2: Tire frame system setting: According to the tire frame construction drawings, arrange the ground platform and support plate in the pre-assembly operation area to form a pre-assembly tire frame;

[0008] S3: Laying out the pre-assembly measurement control network: Based on the segment vertical and horizontal bidirectional reference lines, lay out the plane and level height measurement control network in the pre-assembly operation area;

[0009] S4: Positioning the lower side blocks of the first section: placing the lower side blocks of the first section on the pre-assembled frame, aligning the vertical and horizontal baselines of the outer wall panels with the pre-assembled frame layout baselines, using a level to monitor and adjust, and after passing the inspection, perform stacking and fixing;

[0010] S5: Position the lower edge blocks of the remaining segments in sequence: Place the lower edge blocks of the remaining segments on the pre-assembled tire frame in sequence, align the longitudinal baselines, monitor and adjust the blocks using a level, use a steel plate ruler to detect the spacing between the horizontal base coils of each block, and use the measurement control network to measure the linearity and elevation of the lower edge blocks. After passing the measurement, fix the blocks with code to complete the assembly of the lower edge blocks;

[0011] S6: Positioning the first segment core concrete block: an inner support is arranged in the box of the lower side block, and the first segment core concrete block is positioned so that the longitudinal baseline of the anchor web plate inside it is aligned with the laying baseline of the pre-assembled tire frame, and at the same time, the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower side block is controlled to ensure that the distance is qualified;

[0012] S7: Position the remaining segment core concrete blocks in sequence: sequentially place the remaining segment core concrete blocks on the upper layer of the lower edge blocks, align their longitudinal baselines, and control and adjust the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower edge block to ensure that the distance is qualified. At the same time, the measurement control network is used to measure and detect the linearity and elevation of the core concrete blocks. After passing the measurement, the core concrete blocks are fixed with code to complete the assembly of the core concrete blocks;

[0013] S8: Positioning the upper side block of the first section: turning the upper side block of the first section 180 degrees and placing it on the core concrete block, aligning the longitudinal and transverse baselines of its outer wall panels with the pre-assembled tire frame layout baselines, and at the same time controlling the distance between its side wall panels and the longitudinal baseline of the side wall panels of the core concrete block to ensure that the distance is qualified;

[0014] S9: Position the upper side blocks of the remaining segments in sequence: turn the upper side blocks of the remaining segments 180 degrees in sequence and place them on the core concrete block, align their longitudinal baselines, and control the distance between the side wall panels and the longitudinal baseline of the side wall panels of the core concrete block to ensure that the distance is qualified. At the same time, use the measurement control network to measure and detect the linearity and elevation of the upper side blocks. After passing the measurement, perform coding and fixing to complete the assembly of the upper side blocks to form pre-assembled blocks;

[0015] S10: Accurate positioning and installation of anchor pipe: Use measuring instrument and positioning tooling to position and install anchor pipe;

[0016] S11: Overall inspection, trimming and axis system setting: release the constraint on one end of the inner support to release the stress, and inspect and modify the size of each box opening, the misalignment of the wall plate and the anchor web at the joint. After completion, reconnect one end of the inner support to complete the construction.

[0017] The present application adopts a horizontal assembly form, and each block is assembled and measured and adjusted in layers, and finally an overall inspection is performed to further ensure the accuracy of the assembly.

[0018] Based on the above technical solution, the embodiment of the present application can also be improved as follows:

[0019] Furthermore, the step S2 also includes: using a level to detect the pre-assembled tire frame to ensure that the flatness of the tire frame is within 2 mm. The beneficial effect of using this part is to ensure accuracy by controlling the flatness.

[0020] Furthermore, in the step S2, steel plates are laid in the pre-assembly operation area to increase the bearing capacity of the pre-assembly operation area. The beneficial effect of adopting this step is to ensure stability during assembly by increasing the bearing capacity.

[0021] Furthermore, the inner support in step S6 needs to be arranged in the anchor box of the lower edge block and the joint area on site, and the flatness deviation of the inner support is controlled within 2 mm. The beneficial effect of adopting this step is to further ensure the accuracy of assembly.

[0022] Furthermore, the working environment temperature variation of steps S1-S11 is less than 2°C. The beneficial effect of adopting this step is to avoid excessive temperature difference and affect the assembly accuracy.

[0023] Furthermore, the step S9 also includes the following steps: using the measurement control network to measure and detect the linearity and elevation of the upper edge blocks, the lower edge blocks and the core concrete blocks, and making overall adjustments to meet the requirements based on the measurement results. The beneficial effect of this step is that the measurement accuracy is ensured through the measurement control network.

[0024] Furthermore, the step S9 also includes performing a baseline deviation detection on the pre-assembled blocks. The game effect of adopting this step is that the detection and adjustment structure can be further ensured through the deviation detection.

[0025] Furthermore, the specific steps of performing baseline deviation detection on the pre-assembled blocks are as follows:

[0026] Step S901: Use a total station to measure the deviation of the longitudinal baseline of the outer wall plate of the pre-assembled block, take the intersection of the longitudinal baseline of the wall plate of the lower edge block and the tower bottom edge as the origin, use the multi-round measurement method to measure points A and B on the edge of the corner, then use the AB line as a reference to rotate 90° to make a vertical line (detection line), and detect the offset distance L1 from this vertical line to the intersection of the longitudinal baseline of the wall plate of the upper edge block and the tower top edge;

[0027] Calculation formula for the baseline deviation of the outer wall:

[0028]

[0029] Where: L1 is the deviation value of the longitudinal baseline of the outer wall plate; L is the total length of each round of pre-assembly of the steel tower column; C1 is the deviation of the baseline of the outer wall plate; if the C1 value is qualified, proceed to the next step; if it is unqualified, make adjustments and repeat this step;

[0030] Step S902: Measure the deviation of the longitudinal baseline of the anchor web of the core concrete block, and use the intersection of the vertical line of the core concrete block wall plate with the bottom plate of the lower edge block and the upper edge block as a reference to make a ground plumb line, and detect the offset distances L2 and L3 between the longitudinal baseline of the anchor web of the core concrete block and the plumb line at the intersection of the bottom edge of the lower edge block and the top edge of the upper edge block;

[0031] The calculation formula of the core concrete block deviation from the base line along the bridge direction is:

[0032]

[0033] Where: L2 and L3 are the longitudinal baseline deviation values ​​of the anchor web of the core concrete block, L is the length of the pre-assembled block, and C2 is the deviation of the core concrete block along the bridge baseline. If the C2 value is qualified, the test is completed. If it is unqualified, adjustments are made and this step is repeated.

[0034] Furthermore, step S9 also includes detecting the longitudinal baseline misalignment and transverse baseline misalignment between the lower edge blocks, the upper edge blocks and the core concrete blocks. If qualified, proceed to the next step; if unqualified, repeat this step. The beneficial effect of adopting this step is that the accuracy of the pre-assembled section can be ensured through dependent detection.

[0035] Furthermore, the specific steps of step S10 are as follows:

[0036] Use tooling to locate the anchor point and tower exit point of the cable, then use the stretched wire method to simulate the spatial position of the center line of the cable, and use a ruler to check the deviation between the thin wire at the two ends of each cable duct and the cable duct center in turn. After passing the test, weld the anchor pipe for reinforcement.

[0037] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:

[0038] This application not only effectively guarantees the construction quality of the pre-assembly of multiple blocks of the steel tower of the bridge, greatly improving the construction efficiency of the pre-assembly and the matching accuracy of each block, but also the high-precision pre-assembly quality also lays a solid foundation for the smooth erection and installation of the bridge. The hoisting and positioning of each block of the steel tower at the construction site have met the high-precision requirements of the design (≤5mm), and the steel tower column bridge position has achieved ultra-efficient construction of one block in 2 days, which has saved time for the full bridge to be connected, with significant economic and social benefits. At the same time, the good manufacturing quality and installation results of this application have also effectively verified the feasibility of the multi-layer horizontal pre-assembly technology of steel tower blocks, providing technical support for subsequent pre-assembly of similar or similar steel towers, and has reference significance for the development of pre-assembly technology of steel towers for large bridges in the future. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0040] Figure 1 A schematic diagram of a process for a multi-layer horizontal pre-assembly construction method of a cross-anchorage system steel tower column according to a specific embodiment of the present invention;

[0041] Figure 2 for Figure 1 Schematic diagram of step S4 in FIG.

[0042] Figure 3 for Figure 1 Schematic diagram of step S5;

[0043] Figure 4 for Figure 1 Schematic diagram of step S6;

[0044] Figure 5 for Figure 1 Schematic diagram of step S7;

[0045] Figure 6 for Figure 1 Schematic diagram of step S8;

[0046] Figure 7 for Figure 1 Schematic diagram of step S9;

[0047] Figure 8 for Figure 1 Schematic diagram of step S10;

[0048] Fig. 9A schematic diagram of a baseline system of a multi-layer horizontal pre-assembly construction method for a cross-anchorage system steel tower column according to a specific embodiment of the present invention;

[0049] Fig.10 It is a schematic diagram of a pre-assembly cradle of a multi-layer horizontal pre-assembly construction method of a cross-anchor system steel tower column according to a specific embodiment of the present invention;

[0050] Fig.11 It is a schematic diagram of the inner support of a multi-layer horizontal pre-assembly construction method of a cross-anchorage system steel tower column according to a specific embodiment of the present invention;

[0051] Fig.12 A schematic diagram of the outer wall plate baseline deviation detection of a multi-layer horizontal pre-assembly construction method for a cross-anchored steel tower column according to a specific embodiment of the present invention;

[0052] Fig.13 for Fig.12 Schematic diagram of detection arrangement points;

[0053] Fig.14 It is a schematic diagram of detecting the deviation of the core concrete block along the bridge direction of the baseline of a multi-layer horizontal pre-assembly construction method of a cross-anchorage system steel tower column according to a specific embodiment of the present invention;

[0054] Fig.15 It is a schematic diagram of anchor pipe center deviation detection in a multi-layer horizontal pre-assembly construction method of a cross-anchoring system steel tower column according to a specific embodiment of the present invention;

[0055] Fig.16 yes Fig.15 Schematic diagram from another angle;

[0056] The specific reference numerals are as follows:

[0057] 1-steel tower column block, 2-lower side block, 3-core concrete block, 4-upper side block, 5-pre-assembled frame, 6-ground platform, 7-support plate, 8-ground sample control line, 8-outer wall plate, 9-anchor pipe, 10-inner support. DETAILED DESCRIPTION

[0058] The following embodiments of the technical solution of the present invention are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention.

[0059] It should be noted that, unless otherwise specified, the technical terms or scientific terms used in this application should have the common meanings understood by those skilled in the art to which the present invention belongs.

[0060] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0061] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0062] Embodiment 1:

[0063] like Figure 1-16 As shown, the present application discloses a multi-layer horizontal pre-assembly construction method of a cross-anchoring system steel tower column, wherein the steel tower column includes lower side blocks, core concrete blocks, upper side blocks, anchor pipes and other components, that is, it is assembled in a horizontal manner, which can not only improve the construction quality of the pre-assembly operation of the steel tower multi-block, so that the construction efficiency of the pre-assembly operation and the matching accuracy of each block are greatly improved, and the high-precision pre-assembly quality also lays a solid foundation for the smooth erection and installation of the bridge. The main tower of Changtai Yangtze River Bridge adopts a "steel-concrete" combined structure space diamond-shaped bridge tower. The top of the main tower is 362m high. The outer contour of the upper tower column steel tower is an octagon with a cross-sectional size of 13m×13m to 16m×16m. Due to the limitation of the lifting capacity of the bridge erection crane, each tower section needs to be divided into 3 blocks for separate manufacturing, shipment and hoisting.

[0064] The specific steps of this application are as follows:

[0065] S1: Before pre-assembly, the baseline of each block is corrected; each block in this step includes lower edge blocks, core concrete blocks, upper edge blocks and other blocks. Due to assembly errors and welding deformations in the manufacturing process of each block, the longitudinal and transverse baselines deviate from the theoretical positions after the block is manufactured. It is necessary to use processing technology to eliminate the manufacturing errors in each block, and correct the longitudinal and transverse baselines based on the block reference edge and contour feature points, and use the corrected baselines as the reference processing technology to ensure the accuracy of the baselines of each block during pre-assembly;

[0066] S2: According to the construction drawings of the tire frame, the ground platform and the support plate are arranged in the pre-assembly operation area to form a pre-assembly tire frame; when supporting, the density of the ground platform support arrangement is ensured, so as to ensure that each block is in good condition on the pre-assembly tire frame during assembly; after the pre-assembly tire frame is arranged, the pre-assembly tire frame is detected by a level to ensure that the flatness of the pre-assembly tire frame is within 2mm, and the slope of the pre-assembly tire frame meets the requirements of the slope of the drawings, and the placement lines of each block involved in the pre-assembly and the pre-assembly vertical and horizontal baselines (ground sample lines) are placed on the pre-assembly tire frame using a theodolite; at the same time, steel plates are laid in the pre-assembly operation area to improve the bearing capacity of the pre-assembly operation area, because the pre-assembly operation needs to select a site with sufficient foundation bearing capacity, but due to the heavy weight of the steel segment, it is usually necessary to adopt measures such as laying steel plates on the concrete site to improve its bearing capacity;

[0067] Because there are gaps between the steel plate and the concrete site, and between the frame steel, uneven settlement will occur after the pre-assembly steel tower blocks are placed on the frame. Therefore, it is necessary to pre-press the pre-assembly frame system before pre-assembly to eliminate the above-mentioned gaps, so as to avoid settlement during pre-assembly and improve the accuracy of pre-assembly.

[0068] S3: Based on the bidirectional vertical and horizontal reference lines of the segments, a plane and leveling height measurement control network is laid out in the pre-assembly operation area; the purpose of setting up the measurement control network is to directly and accurately monitor the pre-assembly frame and all measurement points of the pre-assembly through the measurement control network to avoid the accumulation of measurement errors;

[0069] S4: placing the lower block of the first segment on the pre-assembled frame, aligning the longitudinal and transverse baselines of the outer wall plate with the pre-assembled frame layout baseline, using a level to monitor and adjust, and after passing, stacking; the monitoring and adjustment of the level, specifically using the level to detect the height of the longitudinal baseline at the two ends of the side wall plate of the corresponding block to adjust the block to a horizontal state, the horizontal elevation deviation of the longitudinal baseline is ≤1.0mm, and after passing, it is stacked with the frame;

[0070] S5: sequentially place the lower edge blocks of the remaining segments on the pre-assembly frame, align the longitudinal baselines, monitor and adjust the blocks using a level, use a steel ruler to detect the spacing between the horizontal base coils of the blocks, and use the measurement control network to measure the linearity and elevation of the lower edge blocks. After passing the measurement, fix the blocks with code to complete the assembly of the lower edge blocks; similarly, use a level to adjust the corresponding blocks to a horizontal state;

[0071] S6: an inner support is arranged in the box of the lower side block, and the first segment core concrete block is positioned so that the longitudinal baseline of the anchor web inside it is aligned with the layout baseline of the pre-assembled tire frame, and the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower side block is controlled to ensure that the distance is qualified. Specifically, the vertical line method (rough adjustment) and theodolite measurement (fine adjustment) are used to align the horizontal baseline with the horizontal baseline of the lower side block;

[0072] S7: sequentially place the remaining segment core concrete blocks on the upper layer of the lower edge blocks, align their longitudinal baselines, and at the same time control and adjust the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower edge block to ensure that the distance is qualified, and at the same time use the measurement control network to measure and detect the linearity and elevation of the core concrete blocks, and perform coding after passing the test to complete the assembly of the core concrete blocks; specifically, align the horizontal baseline with the horizontal baseline of the lower edge block, detect the spacing between the horizontal base coils of each segment, and fine-tune to meet the requirements;

[0073] S8: Turn the upper side block of the first segment over 180 degrees and place it on the core concrete block, so that the longitudinal and transverse baselines of its outer wall plate are aligned with the pre-assembled tire frame layout baseline, and at the same time, the distance between its side wall plate and the longitudinal baseline of the side wall plate of the core concrete block needs to be controlled to ensure that the distance is qualified; use the vertical line method (rough adjustment) and theodolite measurement (fine adjustment) to align its transverse baseline with the transverse baseline of the lower block;

[0074] S9: Turn the upper edge blocks of the remaining segments over 180 degrees in turn and place them on the core concrete block, align their longitudinal baselines, and control the distance between the side wall panels and the longitudinal baseline of the side wall panels of the core concrete block to ensure that the distance is qualified. At the same time, use the measurement control network to measure and detect the linearity and elevation of the upper edge blocks. After passing the measurement, fix the code to complete the assembly of the upper edge blocks to form a pre-assembled block; specifically, align the transverse baseline with the transverse baseline of the core concrete block, detect the spacing between the transverse base coils of each segment, and fine-tune to meet the requirements;

[0075] S10: Use measuring instruments and positioning tools to position and install anchor pipes; specifically, use measuring instruments and tools to accurately locate the anchor point and the tower exit point of the inclined cable, then use the wire method to simulate the spatial position of the center line of the inclined cable, and use a ruler to sequentially detect the deviation between the fine wire at the two ends of each cable guide and the cable guide tube center. After passing the test, weld the anchor pipe for reinforcement;

[0076] S11: Release the constraint on one end of the inner support to release the stress, and detect and modify the box opening size, wall panel and anchor web misalignment at the joint, and reconnect one end of the inner support to complete the construction; specifically: release the constraint on one end of each inner support, and after the stress is completely released, detect the box opening size, wall panel and anchor web misalignment at the joint of each block, trim the out-of-tolerance part, and reconnect the inner support after passing the test; detect the length of the pre-assembled block, axis deviation, anchor pipe concentricity and other points, install the matching parts after passing the test, and lay out monitoring points and bridge installation alignment lines.

[0077] Further explanation is given to the support plate. The pre-assembly cradle in the present application provides effective support for the entire pre-assembly process through the close connection between its top support plate and the outer wall plate of the lower edge block. It is usually necessary to adjust the elevation of the support plate to accurately control the outer contour line of the steel tower column. However, due to local unevenness of the outer wall plate during block manufacturing, when the lower edge block is placed on the cradle, part of the support plate and the outer wall plate are separated. After the core concrete block and the upper block are placed, the gap between the support plate and the outer wall plate will be eliminated under the influence of gravity, but the lower edge block that has been precisely positioned will be disturbed, causing the longitudinal baseline of the lower edge block to shift. In order to avoid this problem, it is necessary to strictly check the close contact between the cradle support plate and the lower edge block after the lower edge block is placed in place, and add a sticking plate or a pad to the empty support plate to ensure its effective connection.

[0078] Among them, the internal support in step S6 needs to be arranged in the anchor box of the lower side block and the site joint area, and the flatness deviation of the internal support is controlled within 2mm; for further explanation of this step, because the core concrete block is a hollow rectangular structure, its own rigidity is weak, and only longitudinal ribs are set on the anchor web, and no transverse ribs are set, which causes the anchor web to deflect in the horizontal position, especially in the anchor box area due to its large deadweight. The deflection problem is more prominent, which seriously affects the position accuracy of the anchor box. Therefore, it is necessary to set an internal support in the lower side block box, and the internal support needs to be arranged in the anchor box and the site joint area, and its flatness deviation is controlled within 2mm. Before installing the anchor pipe of the core concrete block, it is necessary to detect the characteristic points of each anchor box to ensure that the position accuracy of the anchor box is within the allowable deviation range before welding the anchor pipe.

[0079] In this application, when assembling each block, the baseline is controlled layer by layer, and the vertical and horizontal baseline spacing of each block is finely adjusted layer by layer through the measurement control network, so as to control the position of each layer of blocks on the pre-assembly frame. After the positioning of each layer of blocks is completed, the linearity and elevation measurement and detection are carried out, and the assembly of the next layer of blocks can be carried out only after passing the measurement. After the positioning of each layer of blocks in the whole round is completed, the detection points of the round segment are re-measured as a whole, and the overall adjustment is made to pass according to the measurement results.

[0080] At the same time, the assembly warehouse bottom of this application should be selected in the factory to reduce the impact of external factors such as temperature on the accuracy during operation and testing. The measurement operations of pre-assembly length and baseline deviation are carried out under the condition that the ambient temperature change is less than 2°C, reducing the adverse effect of temperature difference on measurement accuracy.

[0081] In step S11 of the present application, the length of the pre-assembled block is tested by using measuring tools such as a steel tape measure, a spring scale, and a magnetic base for direct testing, and one point is tested at each of the four sides of the objective question at the longitudinal baseline position. In order to reduce system errors, the entire tower is required to be measured with the same steel tape measure, and the tension is applied in strict accordance with the steel tape measure measurement operating procedures, and the measurement data is corrected with the steel tape measure correction value; considering the human reading error, the measurement operator is required to be fixed and the operation method is consistent.

[0082] The step S9 described in the present application also includes performing baseline deviation detection on the pre-assembled blocks, and the specific steps are as follows:

[0083] Step S901: Use a total station to measure the deviation of the longitudinal baseline of the outer wall plate of the pre-assembled block, take the intersection of the longitudinal baseline of the wall plate of the lower edge block and the tower bottom edge as the origin, use the multi-round measurement method to measure points A and B on the edge of the corner, then use the AB line as a reference to rotate 90° to make a vertical line (detection line), and detect the offset distance L1 from this vertical line to the intersection of the longitudinal baseline of the wall plate of the upper edge block and the tower top edge;

[0084] Calculation formula for the baseline deviation of the outer wall:

[0085]

[0086] Where: L1 is the deviation value of the longitudinal baseline of the outer wall plate; L is the total length of each round of pre-assembly of the steel tower column; C1 is the deviation of the baseline of the outer wall plate; if the C1 value is qualified, proceed to the next step; if it is unqualified, make adjustments and repeat this step;

[0087] Step S902: Measure the deviation of the longitudinal baseline of the anchor web of the core concrete block, and use the intersection of the vertical line (detection line) of the core concrete block wall plate with the bottom plate of the lower edge block and the upper edge block as a reference to make a ground plumb line, and detect the offset distances L2 and L3 between the longitudinal baseline of the anchor web of the core concrete block and the plumb line at the intersection of the bottom edge of the lower edge block and the top edge of the upper edge block;

[0088] The calculation formula of the core concrete block deviation from the base line along the bridge direction is:

[0089]

[0090] Where: L2 and L3 are the longitudinal baseline deviation values ​​of the anchor web of the core concrete block, L is the length of the pre-assembled block, and C2 is the deviation of the core concrete block along the bridge baseline. If the C2 value is qualified, the test is completed. If it is unqualified, adjustments are made and this step is repeated.

[0091] Among them, step S9 also includes the detection of longitudinal baseline misalignment and transverse baseline misalignment between the lower edge blocks, the upper edge blocks and the core concrete blocks, wherein the longitudinal baseline misalignment of each block is directly detected by a steel ruler, and the transverse baseline misalignment of each block in the segment is detected by a theodolite in combination with a steel ruler.

[0092] The following table is the allowable deviation table for this application:

[0093]

[0094]

[0095] In the description of the present invention, a large number of specific details are described. However, it is understood that embodiments of the present invention can be practiced without these specific details. In some instances, well-known methods, structures and techniques are not shown in detail so as not to obscure the understanding of this description.

[0096] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0097] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.

Claims

1. A multi-layer horizontal pre-assembly construction method for a cross-anchored steel tower column, characterized in that: The following steps are involved: S1: Baseline correction of each block before pre-assembly: Before pre-assembly, the baseline of each block is corrected; S2: Tire frame system setting: According to the tire frame construction drawings, arrange the ground platform and support plate in the pre-assembly operation area to form a pre-assembly tire frame; S3: Laying out the pre-assembly measurement control network: Based on the segment vertical and horizontal bidirectional reference lines, lay out the plane and leveling height measurement control network in the pre-assembly operation area; S4: Positioning the lower side blocks of the first section: placing the lower side blocks of the first section on the pre-assembled frame, aligning the vertical and horizontal baselines of the outer wall panels with the pre-assembled frame layout baselines, using a level to monitor and adjust, and after passing the inspection, perform stacking and fixing; S5: Position the lower edge blocks of the remaining segments in sequence: Place the lower edge blocks of the remaining segments on the pre-assembled tire frame in sequence, align the longitudinal baselines, monitor and adjust the blocks using a level, use a steel plate ruler to detect the spacing between the horizontal base coils of each block, and use the measurement control network to measure the linearity and elevation of the lower edge blocks. After passing the measurement, fix the blocks with code to complete the assembly of the lower edge blocks; S6: Positioning the first segment core concrete block: an inner support is arranged in the box of the lower side block, and the first segment core concrete block is positioned so that the longitudinal baseline of the anchor web plate inside it is aligned with the laying baseline of the pre-assembled tire frame, and at the same time, the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower side block is controlled to ensure that the distance is qualified; S7: Position the remaining segment core concrete blocks in sequence: sequentially place the remaining segment core concrete blocks on the upper layer of the lower edge blocks, align their longitudinal baselines, and control and adjust the distance between the longitudinal baseline of the side wall plate and the longitudinal baseline of the side wall plate of the lower edge block to ensure that the distance is qualified. At the same time, the measurement control network is used to measure and detect the linearity and elevation of the core concrete blocks. After passing the measurement, the core concrete blocks are fixed with code to complete the assembly of the core concrete blocks; S8: Positioning the upper side block of the first section: turning the upper side block of the first section 180 degrees and placing it on the core concrete block, aligning the longitudinal and transverse baselines of its outer wall panels with the pre-assembled tire frame layout baselines, and at the same time controlling the distance between its side wall panels and the longitudinal baseline of the side wall panels of the core concrete block to ensure that the distance is qualified; S9: Position the upper side blocks of the remaining segments in sequence: turn the upper side blocks of the remaining segments 180 degrees in sequence and place them on the core concrete block, align their longitudinal baselines, and control the distance between the side wall panels and the longitudinal baseline of the side wall panels of the core concrete block to ensure that the distance is qualified. At the same time, use the measurement control network to measure and detect the linearity and elevation of the upper side blocks. After passing the measurement, perform coding and fixing to complete the assembly of the upper side blocks to form pre-assembled blocks; S10: Accurate positioning and installation of anchor pipe: Use measuring instrument and positioning tooling to position and install anchor pipe; S11: Overall inspection, trimming and axis system setting: release the constraint on one end of the inner support to release the stress, and inspect and trim the size of each box opening, the misalignment of the wall plate and the anchor web at the joint. After completion, reconnect one end of the inner support to complete the construction.

2. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The step S2 also includes: using a level to detect the pre-assembled tire frame to ensure that the flatness of the tire frame is within 2 mm.

3. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: In the step S2, steel plates are laid in the pre-assembly operation area to improve the bearing capacity of the pre-assembly operation area.

4. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The inner support in step S6 needs to be arranged in the anchor box of the lower edge block and the joint area of ​​the construction site, and the flatness deviation of the inner support is controlled within 2 mm.

5. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The working environment temperature variation of steps S1-S11 is less than 2°C.

6. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The step S9 also includes the following steps: using the measurement control network to measure and detect the linearity and elevation of the upper edge blocks, the lower edge blocks and the core concrete blocks, and making overall adjustments to meet the requirements based on the measurement results.

7. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The step S9 also includes performing a baseline deviation detection on the pre-assembled blocks.

8. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 7 is characterized in that: The specific steps of performing baseline deviation detection on the pre-assembled blocks are as follows: Step S901: Use a total station to measure the deviation of the longitudinal baseline of the outer wall plate of the pre-assembled block, take the intersection of the longitudinal baseline of the wall plate of the lower edge block and the tower bottom edge as the origin, use the multi-round measurement method to measure points A and B on the edge of the corner, then use the AB line as a reference to rotate 90° to make a vertical line (detection line), and detect the offset distance L1 from this vertical line to the intersection of the longitudinal baseline of the wall plate of the upper edge block and the tower top edge; Calculation formula for the baseline deviation of the outer wall panel: Where: L1 is the deviation value of the longitudinal baseline of the outer wall plate; L is the total length of each round of pre-assembly of the steel tower column; C1 is the deviation of the baseline of the outer wall plate; if the C1 value is qualified, proceed to the next step; if it is unqualified, make adjustments and repeat this step; Step S902: Measure the deviation of the longitudinal baseline of the anchor web of the core concrete block, and use the intersection of the vertical line of the core concrete block wall plate with the bottom plate of the lower edge block and the upper edge block as a reference to make a ground plumb line, and detect the offset distances L2 and L3 between the longitudinal baseline of the anchor web of the core concrete block and the plumb line at the intersection of the bottom edge of the lower edge block and the top edge of the upper edge block; The calculation formula of the core concrete block deviation from the base line along the bridge direction is: Where: L2 and L3 are the longitudinal baseline deviation values ​​of the anchor web of the core concrete block, L is the length of the pre-assembled block, and C2 is the deviation of the core concrete block along the bridge baseline. If the C2 value is qualified, the test is completed. If it is unqualified, adjustments are made and this step is repeated.

9. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The step S9 also includes detecting the longitudinal baseline misalignment and the transverse baseline misalignment between the lower edge blocks, the upper edge blocks and the core concrete blocks. If qualified, proceed to the next step; if unqualified, repeat this step.

10. The multi-layer horizontal pre-assembly construction method of cross-anchored steel tower columns according to claim 1 is characterized in that: The specific steps of step S10 are as follows: Use tooling to locate the anchor point and tower exit point of the cable, then use the stretched wire method to simulate the spatial position of the center line of the cable, and use a ruler to check the deviation between the thin wire at the two ends of each cable duct and the cable duct center in turn. After passing the test, weld the anchor pipe for reinforcement.

Citation Information

Cited By

  • Manufacturing method for fish-bellied section tower section of oval suspension bridge steel tower

    CN121611052A

  • Method for manufacturing an elliptic suspension bridge steel tower fish-belly section tower segment

    CN121611052B