Open cut tunnel inverted arch construction method

Through the method of rotary pile construction and grouting reinforcement, the problems of insufficient stability and waterproof performance of the tunnel foundation in the existing technology are solved, and the strength and waterproof performance of the tunnel foundation are improved.

CN118835641APending Publication Date: 2024-10-25CHINA RAILWAY SEVENTH GRP CO LTD +1
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202410987112.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

The existing invert construction method of open-cut tunnels has shortcomings in ensuring the stability of the tunnel foundation and waterproof performance, making it difficult to effectively transmit formation pressure and resist reaction forces.

Method used

A comprehensive method of rotary pile construction, concrete cushion pouring, geotextile laying, waterproofing treatment and grouting reinforcement is used to ensure the strength and waterproofing performance of the tunnel foundation. Specific steps include geological survey and design of rotary pile points, trench excavation after rotary pile holes are formed, steel cage connection, concrete pouring, waterproofing treatment and grouting reinforcement.

Benefits of technology

Through filling and excavation, integral casting of rotary piles and grouting reinforcement, the strength and waterproof performance of the tunnel foundation are improved, ensuring the improvement of tunnel stability and waterproof performance.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a construction method for an inverted arch of an open-cut tunnel. The construction method comprises the steps that S1, rotary excavating pile construction is conducted at corresponding point positions; s2, waterproof treatment is conducted on the pile head of the rotary excavating pile; s3, a concrete cushion layer is poured to the position above the designed pile top elevation of the rotary excavating pile; s4, geotextile is laid on the base face of the concrete cushion layer; s5, after the concrete protection layer is laid, bottom plate reinforcing steel bars are bound; and S6, inverted arch concrete is symmetrically and continuously poured from the center of the inverted arch to the two sides. The tunnel foundation is preliminarily formed through filling and excavating, then the rotary excavating piles are integrally poured through the grooves, grouting reinforcement is carried out, and therefore the strength of the tunnel foundation is guaranteed, waterproof treatment is carried out on pile heads, and the waterproof performance of a tunnel is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of open-cut tunnel construction, and in particular relates to an open-cut tunnel invert construction method. Background Art

[0002] In current tunnel construction, the invert is a reverse arch structure set at the bottom of the tunnel to improve the stress conditions of the upper support structure of the tunnel. It is one of the main components of the tunnel structure. On the one hand, it effectively transfers the stratum pressure above the tunnel to the underground through the tunnel side wall structure or the load on the road surface, and also effectively resists the reaction force from the stratum below the tunnel. The open-cut tunnel foundation generally includes the excavation section and the filling section, so the tunnel foundation needs to be strengthened to ensure the stability of the tunnel.

[0003] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention

[0004] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art, and the present invention provides an open-cut tunnel invert construction method.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] An open-cut tunnel invert construction method comprising:

[0007] Step S1, conduct geological survey on the tunnel extension path, design the rotary drilling pile points according to the survey results, excavate the tunnel excavation section, fill the tunnel filling section to above the invert bottom elevation, and perform rotary drilling pile construction at the corresponding points;

[0008] Step S2, excavating the tunnel excavation section and filling the tunnel filling section to below the elevation of the invert bottom, and waterproofing the pile heads of the rotary piles;

[0009] Step S3, pouring the concrete cushion layer, and pouring the concrete cushion layer to above the designed pile top elevation of the rotary pile;

[0010] Step S4, staking out the lining bottom plate and the invert position above the slow setting soil cushion layer, laying a geotextile on the concrete cushion layer base, and hanging a waterproof sheet above the geotextile;

[0011] Step S5, after laying the concrete protective layer, the bottom plate reinforcement is tied, the formwork of the bottom plate and the invert is installed, the formwork is fastened by bolts, and the pre-buried reinforcement corresponding to the formwork external support is inserted into the cushion layer;

[0012] Step S6, the invert concrete is poured symmetrically and continuously from the center of the invert to both sides, and cooling pipes are pre-buried in the invert concrete. The cooling pipes are arranged in the middle of the invert and are arranged in a serpentine shape along the extension direction of the tunnel.

[0013] Preferably, in step S1, after the rotary bored piles are bored, trenches are excavated between the pile holes of each rotary bored pile, steel cages are placed in the pile holes and the trenches successively, the steel cages in the trenches are fixedly connected to the steel bars in the pile holes, and connecting beams are formed between the rotary bored piles by pouring concrete to connect the multiple rotary bored piles into one.

[0014] Preferably, a plurality of pre-buried pipes penetrating in the longitudinal direction are preset in the connecting beam, and after the initial setting of the connecting beam, grouting pipes are driven downward through the pre-buried pipes, and grouting of the invert foundation is performed through the grouting pipes.

[0015] Preferably, in step S2, firstly, a cement-based penetrating crystallization coating is applied to the pile end surface, and the coating is applied to a range of not less than 200 mm from the base surface of the bottom plate concrete cushion layer, and then cement mortar is applied;

[0016] After the pile head is wrapped with non-woven fabric, a reverse-adhesive waterproof sheet is set up and fixed with steel strips and cement nails. After fixing, the cement nail fixing place is wrapped with two-component polysulfide sealing paste;

[0017] When the pile head is chiseled off, the pile top elevation is made higher than the designed pile top elevation. The waterproof board is turned up at the root of the pile head and sealed with polysulfide sealing paste. The pile passes through the waterproof layer. The waterproof board is fully adhered to the base surface within 100mm around the pile and sealed with butyl intersecting sealant. A waterstop steel plate is set in the middle of the bottom plate. The waterstop steel plate is tightly welded to the pipe column and a circle of water-swelling waterstop strips is set.

[0018] Preferably, the geotextile is in close contact with the cushion concrete, and is fixed to the concrete cushion by hot-melt pads and nails. The fixing points are arranged in a regular plum blossom shape, and the fixing spacing of the bottom plate or the upper support is 1-1.5m.

[0019] Preferably, a construction joint is provided between the concrete of two adjacent sections of the inverted arch along the extension direction of the tunnel, and a waterstop is provided in the construction joint. The waterstop is installed in a basin-type manner to ensure that the concrete at the waterstop is tightly engaged with the waterstop. Before pouring concrete at the construction joint, the concrete on the surface of the construction joint needs to be roughened and cleaned, and then a penetrating crystalline waterproof coating is applied.

[0020] Preferably, the invert is excavated and cast in sections, with a single cycle construction length of 10m. Before excavation, a total station is used to lay out and determine the excavation section. A level is used to measure the ground elevation of the excavation section and determine the excavation depth of each control point.

[0021] Preferably, manual excavation is used in conjunction with an excavator for soil and soft surrounding rock that can be excavated by an excavator. Blasting is used for excavation sections with isolated rocks or stone surrounding rock. The blasting is loosening blasting. Five elevation control points are set at equal intervals on the section. The elevation of each control point is checked while excavation is underway. For soil and soft surrounding rock, manual excavation is used 30 cm above the base elevation to avoid mechanical damage to the foundation.

[0022] Preferably, the inverted arch concrete is demoulded after its strength reaches 10 MPa, and the contact surface of subsequent concrete construction is roughened after demoulding to remove the floating slurry on the concrete surface and expose 75% of fresh aggregate. After roughening, the loose slag on the surface is washed clean with high-pressure water, and water is sprinkled for curing.

[0023] Beneficial effects: The tunnel foundation is initially formed by filling and excavating, and then the rotary piles are poured in one piece through the grooves, and grouting reinforcement is carried out to ensure the strength of the tunnel foundation. The pile heads are waterproofed to ensure the waterproof performance of the tunnel. DETAILED DESCRIPTION

[0024] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.

[0027] A method for constructing an open-cut tunnel invert arch comprises the following steps: step S1, geological survey is conducted on the tunnel extension path, rotary pile positions are designed according to the survey results, and then filling and excavation schemes are determined according to the actual elevation, excavation sections are excavated on the tunnel extension path, and filling sections are filled to 0.25m above the invert arch bottom elevation, and rotary pile construction is performed at corresponding points; when the pile position is staked out, the longitudinal and lateral allowable deviations of the pile meet the inspection requirements, and guard piles are respectively set at 2m from the center in front, behind, left and right of the pile, so as to detect the pile center and elevation at any time. The guard piles are set in a concrete-wrapped steel bar manner, and protection is strengthened during the construction process to ensure that the center of the guard pile connection line always coincides with the center of the pile position.

[0028] The drilling wall mud is prepared with high-quality clay. The drilling rig mud is prepared outside the hole. After the drilling rig is in place, the drilling rig is turned on to align the center of the drill barrel with the center of the designed pile position, and then slowly guide it into the wellbore, adjust the verticality of the drill rod, inject the prepared mud into the hole, and then drill. When drilling, first hang the drill barrel vertically and stabilize it, then lower it to the working surface at a uniform speed, rotate the drill bucket and apply pressure to squeeze the soil into the drill barrel. After confirming that the drill residue in the drill barrel is filled, reverse and close the bottom of the drill bucket, lift the drill rod to drive the drill barrel, and inject mud into the hole at the same time. After ensuring the water head in the hole, lift the drill barrel out of the hole, and start slowly when lifting the drill. Finally, use the hydraulic system to open the barrel door and remove the drill residue. Then repeat the process and drill in a cycle until the hole is formed. During the drilling process, check the hole frequently to prevent necking and drill jamming; and carefully fill in the original construction record, record the formation changes, related problems encountered during the drilling process, treatment measures and effects in detail. During the construction process, the verticality of the hole can be repeatedly checked through the three-way vertical control system of the drilling rig itself to ensure the quality of the hole. After the steel cage is hoisted in, the performance indicators of the mud in the hole and the thickness of the sediment at the bottom of the hole are checked before pouring underwater concrete.

[0029] Step S2, excavate the tunnel excavation section and fill the tunnel filling section to below the elevation of the bottom of the inverted arch, and waterproof the pile head of the rotary pile. Step S3, pour the concrete cushion layer, and pour the concrete cushion layer to above the designed pile top elevation of the rotary pile; Step S4, stake out the lining bottom plate and the inverted arch position above the slow setting soil cushion layer, lay a geotextile on the concrete cushion layer base, and hang a waterproof board above the geotextile; Step S5, tie the bottom plate steel bars after laying the concrete protective layer, and install the templates of the bottom plate and the inverted arch. The bottom plate template is installed with a large steel template, and the templates are fastened with bolts, and the cushion layer is inserted with embedded steel bars corresponding to the template external support; an arc template is used above the arch line, and the template should have sufficient strength, rigidity and stability and be firmly fixed. During the concrete pouring process, the template shall not be displaced. Step S6, the invert concrete is poured symmetrically and continuously from the center of the invert to both sides, and cooling pipes are pre-buried in the invert concrete. The cooling pipes are arranged in the middle of the invert and are arranged in a serpentine shape along the extension direction of the tunnel.

[0030] In an optional embodiment, in step S1, after the rotary drilling piles are bored, trenches are excavated between the pile holes of each rotary drilling pile, steel cages are placed in the pile holes and the trenches in turn, the steel cages in the trenches are fixedly connected to the steel bars in the pile holes, and a connecting beam is formed between the rotary drilling piles by pouring concrete to connect the multiple rotary drilling piles into one;

[0031] First, pour concrete in the part of the pile hole below the trench. After preliminary forming, pour the trench. The upper surface elevation of the connecting beam in the trench should not be higher than the design elevation of the concrete cushion layer. After the initial setting of the connecting beam, install a template on the upper end of the pile hole or fill the soil as a template to complete the pouring of the rotary bored pile.

[0032] In an optional embodiment, a plurality of pre-buried pipes are preset in the connecting beam and penetrate in the longitudinal direction. The pre-buried pipes are steel pipes. After the initial setting of the connecting beam, grouting pipes are driven downward through the pre-buried pipes. Grouting anchor rods can be externally provided in the grouting pipes. Grouting of the invert foundation is performed through the grouting pipes. After the grouting is completed, the grouting anchor rods can be retained in the foundation, thereby enhancing the stability of the tunnel.

[0033] In an optional embodiment, in step S2, firstly, a cement-based penetrating crystallization coating is applied to the pile end surface, and the coating is applied to a range of not less than 200 mm from the base surface of the bottom plate concrete cushion layer, and then a 10 mm thick cement mortar is applied;

[0034] After wrapping the pile head with 400g / m2 non-woven fabric, set up a 2mm thick anti-adhesive EVA waterproof sheet and fix it with steel strips and cement nails. The circumferential spacing of the steel strips + cement nails is 300mm. After fixing, use a two-component polysulfide sealant to wrap the cement nail fixings.

[0035] When the pile head is chiseled off, the pile top elevation is made 100mm higher than the designed pile top elevation structure, and the pile head is made to penetrate 100mm into the bottom plate structure. The waterproof board is turned up at the root of the pile head, and a two-component polysulfide sealing paste is used for sealing. The pile passes through the waterproof layer, and the waterproof board is fully adhered to the base surface within 100mm around the pile, and the sealing end is adhered with butyl intersecting sealant. A waterstop steel plate is set in the middle of the bottom plate, the waterstop steel plate is tightly welded to the pipe column, and a circle of water-swelling waterstop strips is set.

[0036] In an optional embodiment, a 0.2m thick gravel cushion layer + 0.15m thick C25 concrete cushion layer is set on the top of the plain concrete pile, connected to the tunnel floor, and C25 concrete is used to backfill at different heights of the structure. Specifically, a 0.2m thick C25 concrete cushion layer is set within the range of -0.25m of the designed top elevation of the bored pile, and a fixed steel formwork is installed to control the concrete pouring range. The construction width of the concrete cushion layer in the fill section is greater than 0.1m outside the lining structure to facilitate the installation of the bottom slab concrete pouring template. The cushion layer width of the fill type I lining structure is 19.129m; the cushion layer width of the fill type II lining structure is 19.534m; the cushion layer width of the fill type III lining structure is 19.934m, and the thickness is 0.2m. Install the fixed steel formwork to pour concrete.

[0037] The construction width of the concrete cushion layer in the excavation section is 0.1m greater than the outside of the lining structure to facilitate the installation of the bottom plate concrete pouring formwork. The width of the cushion layer of the excavation type III lining structure is 16.5m, and the cushion layer thickness is 0.15m to 1.455m. The cushion layer C25 concrete is poured by installing and adding a fixed steel mold. The top surface curve elevation of the cushion layer adopts a processed and fixed mold to control the linear shape.

[0038] After the cushion construction is completed, the strength reaches 5MPa. The lining bottom plate and the upper supply position are laid out on the cushion concrete, and the geotextile is laid. The geotextile is closely attached to the cushion concrete, and the geotextile is fixed to the concrete cushion by hot-melt pads and nails. The fixed points are arranged in a plum blossom shape, and the fixed spacing of the bottom plate or the upper supply is 1-1.5m. The geotextiles are connected by overlapping, and the overlapping width is not less than 10cm. The overlapping parts can be welded by point bonding. When laying the buffer layer, it should be as close to the base surface as possible, and it should not be pulled too tight or have large bags, so as not to affect the laying of the waterproof board.

[0039] In the present embodiment, a construction joint is provided between two adjacent sections of inverted arch concrete along the extension direction of the tunnel, a water stop is provided in the construction joint, and the waterproof board is laid horizontally (circumferentially) to avoid overlapping surfaces at the inner corners. The water stop should be installed in a basin-type manner to ensure that the bubbles generated during vibration can be discharged smoothly, so that the concrete at the water stop position and the water stop are closely engaged; the concrete at the water stop position should be fully vibrated to ensure that the concrete at the construction joint position is fully dense, and the steel edge rubber water stop only allows on-site butt joints (mechanical butt joints are adopted), and other types of joints (cross, T-shaped) are required to provide prefabricated joints, and the tensile strength of the joint position shall not be less than 80% of the parent material strength. When the water stop is subjected to joint processing at the construction site, before pouring the concrete at the construction joint position, the surface concrete of the construction joint needs to be roughened and cleaned, and then the penetrating crystallization waterproof coating is applied.

[0040] In an optional embodiment, the invert is excavated (or filled) and cast in sections. Before excavation, a total station is used to stake out the excavation section, and a level is used to measure the ground elevation of the excavation section to determine the excavation depth of each control point. The construction length of a single cycle is 10m. Before excavation, a total station is used to stake out the excavation section, and a level is used to measure the ground elevation of the excavation section to determine the excavation depth of each control point.

[0041] For soil and soft surrounding rock that can be excavated by excavator, manual excavation is carried out with the help of excavator. For the excavation section with isolated rocks or stone surrounding rock, blasting excavation is adopted. The blasting method is loosening blasting. Five elevation control points are set at equal intervals on the section. The elevation of each control point is checked while excavation is underway. For soil and soft surrounding rock, 30cm above the base elevation should be reserved for manual excavation to avoid mechanical damage to the foundation.

[0042] The inverted arch is designed with C35 reinforced concrete. The steel bars are made in a centralized steel bar processing plant and installed on site in the tunnel. The steel bars are made on a customized steel bar trolley. The connection of the steel bars should ensure that the length, width and thickness of the weld meet the requirements. The installation should ensure uniform spacing and the allowable deviation of each steel bar is within the allowable range of the specification.

[0043] The formwork is constructed with steel formwork, and the rigidity and flatness of the formwork meet the requirements. The support adopts Φ42×3.5mm seamless steel pipe as support to ensure the reasonable and reliable support. The parts with loose joints are filled and sealed with expansion glue to prevent leakage of concrete during pouring, which will cause the concrete to have a rough surface.

[0044] In an optional embodiment, during the pouring construction of the inverted arch, the concrete is vibrated and compacted while pouring. The vibrator is inserted and vibrated. The vibrating rod should be vertical, fast in and slow out, and the vibrating points should be evenly distributed on the surface. The spacing should not exceed the vibrating range of the vibrating rod, and the distance from the template should be not less than 10 cm. A chisel should be used where the vibrating rod cannot be used. In order to cool down, the concrete mixing station ground material storage silo adopts a fully enclosed material shed, and a spraying device is installed on the roof of the shed. When the temperature in the material shed rises, the tap water spraying is turned on to effectively reduce the temperature in the material shed. At the same time, an air conditioner is installed in the material shed. When the temperature is too high, the air conditioner is turned on to cool down. The mixing water is cooled by a refrigerator. When the temperature is too high, a large amount of ice cubes are added to the water reservoir to reduce the water temperature. The water reservoir should be equipped with a roof to avoid direct sunlight. The powder tank of the mixing station is equipped with a fully enclosed material shed, and a spraying device is installed on the roof to spray water for cooling. At the same time, an air conditioner is installed in the material shed, which can effectively reduce the temperature in the material shed.

[0045] The invert arch concrete is demoulded after its strength reaches 10 MPa. After demoulding, the contact surface for subsequent concrete construction is roughened to remove the floating slurry on the concrete surface. The surface is roughened to expose 75% of the fresh aggregate. After roughening, the loose slag on the surface is washed clean with high-pressure water, and then water is sprinkled for maintenance.

[0046] The curing agent on the connection surface between new and old concrete must be cleaned up, and it is not allowed to directly water the concrete surface for curing without covering it.

[0047] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.

Claims

1. A method for constructing an open-cut tunnel invert, characterized in that: include: Step S1, conduct geological survey on the tunnel extension path, design the rotary drilling pile points according to the survey results, excavate the tunnel excavation section, fill the tunnel filling section to above the invert bottom elevation, and perform rotary drilling pile construction at the corresponding points; Step S2, excavating the tunnel excavation section and filling the tunnel filling section to below the elevation of the invert bottom, and waterproofing the pile heads of the rotary piles; Step S3, pouring the concrete cushion layer, and pouring the concrete cushion layer to above the designed pile top elevation of the rotary pile; Step S4, staking out the lining bottom plate and the invert position above the slow setting soil cushion layer, laying a geotextile on the concrete cushion layer base, and hanging a waterproof sheet above the geotextile; Step S5, after laying the concrete protective layer, the bottom plate reinforcement is tied, the formwork of the bottom plate and the invert is installed, the formwork is fastened by bolts, and the pre-buried reinforcement corresponding to the formwork external support is inserted into the cushion layer; Step S6, the invert concrete is poured symmetrically and continuously from the center of the invert to both sides, and cooling pipes are pre-buried in the invert concrete. The cooling pipes are arranged in the middle of the invert and are arranged in a serpentine shape along the extension direction of the tunnel.

2. The open-cut tunnel invert construction method according to claim 1, characterized in that: In step S1, after the rotary drilling piles are bored, trenches are excavated between the pile holes of each rotary drilling pile, steel cages are placed in the pile holes and the trenches in turn, the steel cages in the trenches are fixedly connected to the steel bars in the pile holes, and connecting beams are formed between the rotary drilling piles by pouring concrete to connect the multiple rotary drilling piles into one.

3. The open-cut tunnel invert construction method according to claim 2, characterized in that: A plurality of pre-buried pipes penetrating in the longitudinal direction are preset in the connecting beam. After the initial setting of the connecting beam, grouting pipes are driven downward through the pre-buried pipes, and grouting of the invert foundation is carried out through the grouting pipes.

4. The open-cut tunnel invert construction method according to claim 1, characterized in that: In step S2, firstly, a cement-based penetrating crystallization coating is applied to the pile end surface, and the coating is applied to a range of not less than 200 mm from the base surface of the bottom plate concrete cushion layer, and then cement mortar is applied; After the pile head is wrapped with non-woven fabric, a reverse-adhesive waterproof sheet is set up and fixed with steel strips and cement nails. After fixing, the cement nail fixing place is wrapped with two-component polysulfide sealing paste; When the pile head is chiseled off, the pile top elevation is made higher than the designed pile top elevation. The waterproof board is turned up at the root of the pile head and sealed with polysulfide sealing paste. The pile passes through the waterproof layer. The waterproof board is fully adhered to the base surface within 100mm around the pile and sealed with butyl intersecting sealant. A waterstop steel plate is set in the middle of the bottom plate. The waterstop steel plate is tightly welded to the pipe column and a circle of water-swelling waterstop strips is set.

5. The open-cut tunnel invert construction method according to claim 1, characterized in that: The geotextile is in close contact with the cushion concrete and is fixed to the concrete cushion by hot-melt pads and nails. The fixing points are arranged in a regular plum blossom shape, and the fixing spacing of the bottom plate or overhead supply is 1-1.5m.

6. The open-cut tunnel invert construction method according to claim 1, characterized in that: A construction joint is set between the two adjacent sections of the invert concrete along the extension direction of the tunnel. A waterstop is set in the construction joint. The waterstop is installed in a basin-like manner to ensure that the concrete at the waterstop is tightly engaged with the waterstop. Before pouring concrete at the construction joint, the concrete on the surface of the construction joint needs to be roughened and cleaned, and then coated with penetrating crystalline waterproof coating.

7. The open-cut tunnel invert construction method according to claim 1, characterized in that: The invert is excavated and cast in sections, with a single cycle construction length of 10m. Before excavation, a total station is used to stake out and determine the excavation section. A level is used to measure the ground elevation of the excavation section and determine the excavation depth of each control point.

8. The open-cut tunnel invert construction method according to claim 7, characterized in that: For soil and soft surrounding rock that can be excavated by excavator, manual excavation is carried out with the help of excavator. For the excavation section with isolated rocks or stone surrounding rock, blasting excavation is adopted. The blasting method is loosening blasting. Five elevation control points are set at equal intervals on the section. The elevation of each control point is checked while excavation is underway. For soil and soft surrounding rock, manual excavation is adopted 30 cm above the base elevation to avoid mechanical damage to the foundation.

9. The open-cut tunnel invert construction method according to claim 1, characterized in that: The invert arch concrete is demoulded after its strength reaches 10 MPa. After demoulding, the contact surface for subsequent concrete construction is roughened to remove the floating slurry on the concrete surface. The surface is roughened to expose 75% of the fresh aggregate. After roughening, the loose slag on the surface is washed clean with high-pressure water, and then water is sprinkled for maintenance.

Citation Information

Cited By

  • Open cut tunnel plain concrete pile composite foundation and construction method

    CN119824877A

  • A composite foundation of open-cut tunnel concrete pile and construction method

    CN119824877B

  • Soft soil open cut tunnel base excavation and inverted arch forming auxiliary device and shape control method

    CN120520271A

  • A soft soil open-cut tunnel base excavation and invert arch forming auxiliary device and shape control method

    CN120520271B