Wireless monitoring method and device for intelligent building construction site
Through wireless monitoring methods, we obtain and analyze the environmental and behavioral data of the construction site, build digital twin models, identify abnormal behaviors and risks, solve the safety and efficiency problems of traditional construction monitoring methods, and realize intelligent monitoring of smart building construction sites.
Patent Information
- Application Number
- CN202411099076.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-10-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional building construction monitoring methods rely on manual supervision, which has the problems of low safety and low monitoring efficiency. It is difficult to meet the intelligent monitoring needs of smart building construction sites.
Using wireless monitoring methods, by acquiring construction site environment sensing parameters, surveillance videos and structural diagrams, we perform area segmentation, noise intensity calculation, dust concentration analysis, time-delay visual optimization, and optical flow motion characteristics analysis to build a digital twin construction scene model and identify Abnormal behaviors and risk levels enable real-time monitoring and risk decision-making.
It improves the safety and monitoring efficiency of the construction site, provides real-time and accurate environmental and behavioral data, helps prevent potential safety risks, optimizes risk decisions, and improves the safety and efficiency of the construction site.
Smart Images

Figure CN118865259A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of engineering monitoring, and in particular to a method and device for wireless monitoring of a smart building construction site. Background Art
[0002] The construction site is a complex and ever-changing environment. With the popularization of smart construction, the use of smart technology in construction has become a new trend. Traditional construction monitoring methods rely on manual supervision by site safety officers, which often have problems such as low safety and low monitoring efficiency. With the continuous development of intelligent building technology, the demand for monitoring of smart construction sites is increasing. Therefore, an intelligent construction site monitoring method is needed. Summary of the invention
[0003] In order to solve the above technical problems, the present invention proposes a method and device for wireless monitoring of a smart building construction site to solve at least one of the above technical problems.
[0004] To achieve the above object, the present invention provides a method for wireless monitoring of a construction site of a smart building, comprising the following steps: Step S1: Obtain construction site environmental perception parameters, construction site monitoring video and construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain a regional monitoring map; perform regional noise intensity calculation on the regional monitoring map based on the construction site environmental perception parameters to construct a regional noise intensity map; Step S2: Generate dust concentration spatial distribution data based on the construction site environmental perception parameters; dynamically render the construction site structure diagram based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model; Step S3: performing time-delay visual optimization on the construction site monitoring video to obtain a time-delay optimized video frame sequence; obtaining a personnel boundary frame image based on the time-delay optimized video frame sequence; Step S4: performing optical flow motion characteristic analysis on the person boundary frame image to generate motion vector deformation data; and constructing a behavior trajectory mapping diagram based on the motion vector deformation data; Step S5: construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; obtain abnormal behavior frequency data and risk level through the digital twin construction scene model; Step S6: locate the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0005] The present invention provides real-time data on the environmental conditions of the construction site by acquiring environmental perception parameters of the construction site, such as temperature, humidity, pressure, etc., which is helpful to understand the working environment and safety conditions of the construction site, acquires monitoring videos and structural diagrams of the construction site to provide comprehensive visual information for subsequent analysis and modeling, helps monitor construction activities and detect abnormal conditions, performs regional segmentation on the structural diagram of the construction site to divide the construction site into different areas, facilitates subsequent monitoring and analysis, and provides more accurate regional information, calculates regional noise intensity on regional monitoring maps based on environmental perception parameters of the construction site to obtain noise conditions in each area, and provides a basis for subsequent environmental monitoring and control, generates spatial distribution data of dust concentration based on environmental perception parameters of the construction site to provide detailed information on dust conditions at the construction site, and is helpful to evaluate the air quality and health risks of the construction site, combines dust concentration data with regional noise intensity maps to more accurately simulate environmental parameter scenarios of the construction site, and provides a reliable data basis for subsequent analysis and decision-making, improves the quality and clarity of monitoring videos through time-delay visual optimization, reduces delays in image transmission, makes personnel monitoring more accurate and real-time, and generates personnel boundary box images to effectively locate and identify personnel in the construction site. Personnel, providing data basis for subsequent behavior analysis and anomaly detection. Through optical flow motion characteristic analysis, the motion information of personnel in the monitoring video, including speed, direction and displacement, is obtained to provide data basis for subsequent behavior analysis. A behavior trajectory map is constructed to visualize the movement trajectory of personnel, which can more intuitively display the activities of personnel on the construction site and facilitate the detection and analysis of abnormal behavior. A digital twin construction scene model is constructed based on the behavior trajectory map to compare the actual construction site situation with the model, realize virtual simulation and monitoring, understand the status and potential risks of the construction site, and use the preset construction behavior specification database to perform abnormal behavior analysis on the digital twin construction scene model to detect and identify abnormal behaviors on the construction site, and discover potential safety risks and problems in advance. Abnormal behavior frequency data and risk level quantitatively evaluate the safety status of the construction site, and provide reliable data support for decision makers to take corresponding risk control measures. Abnormal area positioning determines the specific areas with potential risks and problems on the construction site, which helps to accurately locate and solve safety hazards. Risk decision optimization optimizes the abnormal area according to the risk level and abnormal behavior frequency data, so as to take appropriate measures to reduce risks and ensure the safety of the construction site.
[0006] Preferably, step S1 comprises the following steps: Step S11: Obtaining construction site environmental perception parameters, construction site monitoring video and construction site structural diagram; Step S12: performing regional segmentation on the construction site structure diagram to obtain a regional monitoring diagram; Step S13: Calculating the regional noise intensity of the regional monitoring map based on the construction site environment perception parameters to obtain regional noise intensity data; Step S14: Perform intensity map drawing processing on the regional noise intensity data to construct a regional noise intensity map. The present invention provides real-time data on the environmental conditions of the construction site by acquiring environmental perception parameters of the construction site, such as temperature, humidity, pressure, etc., which is helpful to understand the working environment and safety conditions of the construction site, acquires monitoring videos and structural diagrams of the construction site to provide comprehensive visual information for subsequent analysis and modeling, helps monitor construction activities and detect abnormal conditions, performs regional segmentation on the structural diagram of the construction site to divide the construction site into different areas, facilitates subsequent monitoring and analysis, and provides more accurate regional information, calculates regional noise intensity on regional monitoring maps based on environmental perception parameters of the construction site to obtain noise conditions in each area, and provides quantitative data on noise intensity at the construction site. The regional noise intensity data is used for environmental assessment of the construction site to help determine the source of noise and the area that affects the health and safety of workers, performs intensity mapping processing on the regional noise intensity data to visualize the noise intensity information, and constructs a regional noise intensity map. The regional noise intensity map provides noise distribution conditions in different areas of the construction site, and helps managers and workers understand the noise conditions at the construction site so as to take corresponding control measures and protective measures.
[0007] Preferably, step S1 comprises the following steps: Step S21: performing dust concentration distribution analysis on the construction site environmental perception parameters to generate dust concentration spatial distribution data; Step S22: performing regional structural feature analysis on the construction site structure diagram to generate construction area structural feature data; Step S23: reconstructing the three-dimensional scene of the construction area structural feature data to construct a three-dimensional scene model; Step S24: dynamically render the three-dimensional scene model based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model. The present invention understands the distribution of dust at the construction site by performing dust concentration distribution analysis on the environmental perception parameters of the construction site, including the concentration and spatial distribution of dust, generates dust concentration spatial distribution data to provide quantitative dust concentration information, helps evaluate the air quality of the construction site and the health status of workers, performs regional structural feature analysis on the construction site structure diagram to extract structural features of different regions, such as the height, shape, material and other information of the building, generates construction area structural feature data to provide a quantitative description of the structural features of each region of the construction site, and provides basic data for subsequent analysis and modeling, performs three-dimensional scene reconstruction on the construction area structural feature data to convert the structural features of the construction site into a three-dimensional scene model to achieve virtual reconstruction of the construction site, constructs a three-dimensional scene model to provide a visual presentation method, so that managers and workers can more intuitively understand the structure and layout of the construction site, dynamically renders the three-dimensional scene model based on the dust concentration spatial distribution data and the regional noise intensity map, combines the dust concentration and noise intensity information with the three-dimensional scene model, realizes dynamic environmental parameter simulation, and constructs a three-dimensional environmental parameter scene model to provide a realistic simulation environment, so that managers and workers can observe and evaluate the dust and noise conditions at the construction site in a virtual environment.
[0008] Preferably, the dynamic rendering in step S24 is specifically: Setting concentration levels based on spatial distribution data of dust concentration; Assigning concentration color based on the concentration level to obtain concentration level color data; Perform dust distribution drift simulation on the three-dimensional scene model based on the concentration level color data to obtain a dust distribution scene model; Perform regional noise attenuation change analysis on the regional noise intensity map to obtain regional noise attenuation data; Performing noise attenuation demarcation on the three-dimensional scene model based on the regional noise attenuation data to obtain a noise attenuation demarcation line; Generate dynamic noise rendering parameters based on regional noise intensity map; The noise attenuation boundary line is used to map the boundary line of the dust distribution scene model, and dynamic rendering is performed using dynamic noise rendering parameters to construct a three-dimensional environmental parameter scene model. The present invention sets concentration levels based on the spatial distribution data of dust concentration, and divides dust into different levels according to the size of the concentration, so as to indicate the degree of dust. The setting of the concentration level provides a simple and clear way to describe the dust concentration, which is convenient for subsequent visualization and analysis. The concentration color is assigned based on the concentration level, and each concentration level is corresponded to a color, so as to realize the mapping relationship between dust concentration and color. The concentration level color data is obtained to provide color information corresponding to the dust concentration in each area, so as to provide a basis for subsequent dust distribution simulation and visualization. The three-dimensional scene model is simulated for dust distribution drift based on the concentration level color data. The distribution and drift process of dust are simulated in the three-dimensional scene model according to the distribution of dust concentration, and the dust distribution scene model is obtained to provide a dynamic dust distribution scene, which helps to observe and evaluate the dust diffusion at the construction site. The regional noise attenuation change analysis is performed on the regional noise intensity map to understand the changing law of noise attenuation in different areas, including the propagation and attenuation of noise, and the regional noise attenuation data is obtained to provide quantitative information on noise attenuation in different areas. , providing basic data for subsequent noise analysis and modeling, performing noise attenuation demarcation on the 3D scene model based on regional noise attenuation data, demarcating the noise attenuation demarcation line in the 3D scene model according to the noise attenuation situation, and obtaining the noise attenuation demarcation line, providing the position and shape information of the noise attenuation demarcation line, which is used to distinguish different areas with high and low noise intensity, and generating dynamic noise rendering parameters based on the regional noise intensity map, determining the parameter settings of dynamic noise rendering according to the change of noise intensity, such as color change, animation effect, etc., and the dynamic noise rendering parameters provide a visualization method for noise, so that the change of noise is more intuitively presented in the 3D environmental parameter scene model, and mapping the demarcation line of the dust distribution scene model using the noise attenuation demarcation line, demarcating the noise attenuation area in the dust distribution scene model according to the position of the noise attenuation demarcation line, and performing dynamic rendering using the dynamic noise rendering parameters, visualizing the noise of the dust distribution scene model according to the intensity and change of the noise, and constructing a 3D environmental parameter scene model provides an environmental simulation that comprehensively considers dust distribution and noise.
[0009] Preferably, the specific steps of step S3 are: Step S31: extracting video frames from the construction site monitoring video to obtain a video frame sequence; Step S32: performing time delay visual optimization on the video frame sequence to obtain a time delay optimized video frame sequence; Step S33: performing visual detection of personnel on the delay-optimized video frame sequence to mark personnel position data; Step S34: performing boundary frame segmentation processing on the construction site monitoring video based on the personnel position data to obtain a personnel boundary frame image.
[0010] The present invention decomposes the video into a series of static image frames by extracting video frames of the construction site monitoring video for subsequent processing and analysis, and obtains a video frame sequence to provide continuous observation of the construction site, so that subsequent analysis is performed based on continuous image data, and the video frame sequence is subjected to time delay visual optimization to process the time delay difference between video frames, so that the video viewing experience is smoother and more coherent, and the delay optimized video frame sequence is obtained to provide better visual effects and reduce the jamming and discontinuity in the video, and the delay optimized video frame sequence is subjected to personnel visual detection to detect and identify personnel in the construction site, mark their location information, and mark the personnel location data to provide real-time personnel monitoring and positioning functions, so as to help managers understand the distribution of personnel at the construction site, and based on the personnel location data, the construction site monitoring video is subjected to bounding box segmentation processing to extract personnel from the video frame, generate a personnel bounding box image, and obtain the personnel bounding box image to further provide detailed analysis of personnel, such as the range of activities, behavior and other information of personnel, so as to provide key data for the safety management and monitoring of the construction site.
[0011] Preferably, the specific steps of step S31 are: Step S311: annotate the video frame sequence with timestamps frame by frame to generate video frame annotation points; Step S312: calculating the average moving time between the video frame annotation points to obtain the average moving time of the annotation points in each frame; Step S313: identifying the video frame annotation points exceeding the standard based on the average moving time of the annotation points in each frame, so as to mark the frame points exceeding the delay standard; Step S314: performing video frame positioning based on the frame point where the delay exceeds the standard, so as to obtain the video frame where the delay exceeds the standard; Step S315: Calculate the time difference of the video frame with excessive delay and the video frame sequence to obtain delay time difference data; Step S316: Perform delay visual optimization on the video frames with excessive delay based on the delay time difference data to generate a delay optimized video frame sequence. The present invention adds time information to each video frame by performing frame-by-frame timestamp annotation on a video frame sequence for subsequent time delay calculation and analysis, generates video frame annotation points to provide timestamp data for each video frame, facilitates subsequent calculation of the time difference between each frame, performs inter-frame average movement time calculation on the video frame annotation points to obtain the average time difference between each frame, thereby understanding the average movement speed of the video frame, and obtains the average movement time of each frame annotation point as a reference for subsequent over-standard frame point identification, which is used to determine whether the video frame has a time delay problem, performs over-standard frame point identification on the video frame annotation points based on the average movement time of each frame annotation point, detects video frame points that exceed a preset time threshold, marks them as over-standard frame points for time delay, and quickly identifies video frames with time delay problems for further processing and Analysis, video frame positioning based on the frame points with excessive delay is performed to accurately locate the video frames with excessive delay, which is convenient for subsequent processing and optimization, and the video frames with excessive delay are obtained to provide specific examples of delay problems, help determine the specific location where the delay occurs, and perform time difference calculation on the video frames with excessive delay and video frame sequences. Calculate the time difference between the video frames with excessive delay and other video frames to obtain delay time difference data. The obtained delay time difference data provides time information about the video frames with excessive delay, which helps to further analyze and optimize the delay problem, and perform delay visual optimization on the video frames with excessive delay based on the delay time difference data. According to the size of the time difference, the video frames with excessive delay are appropriately processed and optimized to generate a delay optimized video frame sequence, which provides video frames after delay optimization processing, making the viewing experience smoother and more coherent.
[0012] Preferably, the specific steps of step S4 are: Step S41: performing multi-frame optical flow tracking on the person boundary frame image to obtain dynamic optical flow tracking data; Step S42: performing optical flow motion characteristic analysis on the dynamic optical flow tracking data to generate motion vector deformation data; Step S43: performing behavior trajectory analysis on the motion vector deformation data to generate dynamic behavior trajectory data; Step S44: spatially map the dynamic behavior trajectory data to construct a behavior trajectory mapping diagram.
[0013] The present invention tracks the motion trajectory of a person between consecutive frames by performing multi-frame optical flow tracking on a person boundary box image to obtain dynamic optical flow tracking data. The dynamic optical flow tracking data provides speed and direction information of the person's motion, providing a basis for subsequent motion characteristic analysis and behavior trajectory generation. The dynamic optical flow tracking data is subjected to optical flow motion characteristic analysis to analyze the motion pattern and behavior characteristics of the person, and motion vector deformation data is generated. The generated motion vector deformation data provides detailed information about the person's motion, including acceleration, displacement, etc., providing a basis for subsequent behavior trajectory analysis and spatial mapping. The motion vector deformation data is subjected to behavior trajectory analysis to identify and extract the behavior trajectory of the person, and dynamic behavior trajectory data is generated. The generated dynamic behavior trajectory data displays the motion path and behavior pattern of the person at the construction site, helps analyze the behavior habits and activity range of the person, and spatially maps the dynamic behavior trajectory data to map the behavior trajectory onto a plan view or a three-dimensional model of the construction site, and constructs a behavior trajectory mapping diagram. The constructed behavior trajectory mapping diagram intuitively displays the motion trajectory of the person at the construction site, helping managers to better understand the spatial distribution and trend of personnel activities.
[0014] Preferably, the specific steps of step S5 are: Step S51: constructing a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; Step S52: performing abnormal behavior analysis on the digital twin construction scene model based on a preset construction behavior specification database to obtain abnormal behavior data; Step S53: performing abnormal frequency statistics on the abnormal behavior data to obtain abnormal behavior frequency data; Step S54: Evaluate the risk level of abnormal behavior based on the abnormal behavior frequency data to obtain a risk level. The present invention constructs a twin model of a three-dimensional environmental parameter scene model based on a behavior trajectory mapping diagram to correspond the actual construction scene with the digital model, construct a digital twin construction scene model, and construct a digital twin construction scene model to provide a virtual construction environment for simulating and analyzing various situations and changes in the construction process. The digital twin construction scene model is analyzed for abnormal behavior based on a preset construction behavior specification database to detect and identify abnormal behaviors in the digital twin construction scene model to obtain abnormal behavior data. The abnormal behavior data helps to determine whether there are behaviors that do not meet the specifications during the construction process, and to discover potential safety problems or construction hazards in advance. The abnormal frequency statistics of the abnormal behavior data are performed to obtain the frequency of occurrence of abnormal behaviors during the construction process, and the abnormal behavior frequency data are obtained to quantify the degree of occurrence of different abnormal behaviors, which helps to evaluate the severity and impact range of the abnormal behaviors. The abnormal behavior risk level is assessed based on the abnormal behavior frequency data. According to the frequency and severity of the abnormal behavior, the risk level of each abnormal behavior is evaluated, and the risk level obtained helps managers identify and prioritize high-risk abnormal behaviors to ensure the safety and efficiency of the construction process.
[0015] Preferably, the specific steps of step S6 are: Step S61: locating the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; Step S62: Predicting potential risks for abnormal area data to generate potential risk data for the construction site; Step S63: Optimize the risk decision of the potential risk data of the construction site to obtain regional risk decision optimization data to perform wireless monitoring operations. The present invention locates the specific area where abnormal behavior exists in the construction site by locating the abnormal area based on the abnormal behavior frequency data and the risk level, and obtains the abnormal area data. The abnormal area data helps the management personnel to quickly understand the distribution of abnormal behavior, take targeted measures to process and monitor, and predicts the potential risks of the abnormal area data, analyzes the potential risk factors and consequences in the abnormal area, and generates the potential risk data of the construction site. The generated potential risk data of the construction site helps the management personnel to predict the potential risk situation and provide a basis for formulating risk management strategies, and optimizes the risk decision of the potential risk data of the construction site according to the risk level and potential risk factors, and obtains the regional risk decision optimization data. The regional risk decision optimization data helps the management personnel to formulate more effective risk management measures and monitoring strategies, and improve the safety and efficiency of the construction site.
[0016] In this specification, a wireless monitoring device for a smart building construction site is provided, which is used to execute the wireless monitoring method for a smart building construction site as described above, including: The regional segmentation module is used to obtain the construction site environmental perception parameters, the construction site monitoring video and the construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain the regional monitoring map; calculate the regional noise intensity of the regional monitoring map based on the construction site environmental perception parameters to construct the regional noise intensity map; Dynamic rendering module, used to generate dust concentration spatial distribution data based on construction site environmental perception parameters; dynamically render the construction site structure diagram based on dust concentration spatial distribution data and regional noise intensity map, and construct a three-dimensional environmental parameter scene model; The delay optimization module is used to perform delay visual optimization on the construction site monitoring video to obtain a delay optimized video frame sequence; based on the delay optimized video frame sequence, a personnel boundary box image is obtained; The behavior trajectory module is used to analyze the optical flow motion characteristics of the person's bounding box image and generate motion vector deformation data; and to construct a behavior trajectory map based on the motion vector deformation data; The abnormal behavior module is used to construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram, and to construct a digital twin construction scene model; the abnormal behavior frequency data and risk level are obtained through the digital twin construction scene model; The risk decision module is used to locate abnormal areas based on abnormal behavior frequency data and risk levels to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0017] The present invention provides visual perception and structural information of the entire construction site and specific areas through the regional segmentation module, providing basic data for subsequent monitoring and analysis. The regional noise intensity map helps identify and locate the noise source in the construction site, which is helpful to evaluate the potential impact of noise on workers and equipment. The dynamic rendering module provides a comprehensive simulation and visualization of the environmental parameters of the construction site, so that monitoring personnel can more intuitively understand the environmental conditions of the construction site. The three-dimensional environmental parameter scene model helps predict and evaluate the distribution of dust and noise in the construction site, providing a reference for optimizing construction plans and worker arrangements. The delay optimization module improves the quality and clarity of the monitoring video, reduces the video delay, and enables monitoring personnel to observe and analyze the situation on the construction site more accurately. The personnel boundary box image is used for further motion analysis and behavior recognition, helping monitoring personnel detect and track the construction site. The behavior trajectory module provides quantitative analysis of the movement and behavior of personnel on the construction site, and detects abnormal movement and behavior. The behavior trajectory map intuitively displays the movement paths and activity areas of personnel on the construction site, which helps monitoring personnel to have an overall understanding of the construction site and detect anomalies. The abnormal behavior module provides detection and identification of abnormal behaviors on the construction site, helping monitoring personnel to promptly discover potential safety risks. The digital twin construction scene model simulates and predicts various behaviors and scenarios on the construction site, and provides decision support for risk assessment and preventive measures. The risk decision-making module can conduct more targeted monitoring and intervention on the construction site based on the location and risk level of the abnormal area, improve the safety and efficiency of the construction site, optimize risk decisions, help monitoring personnel to reasonably allocate resources and take appropriate measures, and reduce potential safety risks and work interruptions. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A schematic diagram of the steps of a method for wireless monitoring of a construction site of a smart building according to the present invention; Figure 2 Detailed implementation flow chart of step S1; Figure 3 Detailed implementation flow chart of step S2; Figure 4 Detailed implementation flow chart of step S3. DETAILED DESCRIPTION
[0019] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.
[0020] The present application example provides a method and device for wireless monitoring of smart building construction sites. The execution subjects of the method and device for wireless monitoring of smart building construction sites include but are not limited to the following: mechanical equipment, data processing platform, cloud server node, network upload device, etc. that are equipped with the system can be regarded as the general computing nodes of the present application, and the data processing platform includes but is not limited to: at least one of an audio and image management system, an information management system, and a cloud data management system.
[0021] See also Figures 1 to 4 The present invention provides a method for wireless monitoring of a construction site of a smart building, the method comprising the following steps: Step S1: Obtain construction site environmental perception parameters, construction site monitoring video and construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain a regional monitoring map; perform regional noise intensity calculation on the regional monitoring map based on the construction site environmental perception parameters to construct a regional noise intensity map; Step S2: Generate dust concentration spatial distribution data based on the construction site environmental perception parameters; dynamically render the construction site structure diagram based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model; Step S3: performing time-delay visual optimization on the construction site monitoring video to obtain a time-delay optimized video frame sequence; obtaining a personnel boundary frame image based on the time-delay optimized video frame sequence; Step S4: performing optical flow motion characteristic analysis on the person boundary frame image to generate motion vector deformation data; and constructing a behavior trajectory mapping diagram based on the motion vector deformation data; Step S5: construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; obtain abnormal behavior frequency data and risk level through the digital twin construction scene model; Step S6: locate the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0022] The present invention provides real-time data on the environmental conditions of the construction site by acquiring environmental perception parameters of the construction site, such as temperature, humidity, pressure, etc., which is helpful to understand the working environment and safety conditions of the construction site, acquires monitoring videos and structural diagrams of the construction site to provide comprehensive visual information for subsequent analysis and modeling, helps monitor construction activities and detect abnormal conditions, performs regional segmentation on the structural diagram of the construction site to divide the construction site into different areas, facilitates subsequent monitoring and analysis, and provides more accurate regional information, calculates regional noise intensity on regional monitoring maps based on environmental perception parameters of the construction site to obtain noise conditions in each area, and provides a basis for subsequent environmental monitoring and control, generates spatial distribution data of dust concentration based on environmental perception parameters of the construction site to provide detailed information on dust conditions at the construction site, and is helpful to evaluate the air quality and health risks of the construction site, combines dust concentration data with regional noise intensity maps to more accurately simulate environmental parameter scenarios of the construction site, and provides a reliable data basis for subsequent analysis and decision-making, improves the quality and clarity of monitoring videos through time-delay visual optimization, reduces delays in image transmission, makes personnel monitoring more accurate and real-time, and generates personnel boundary box images to effectively locate and identify personnel in the construction site. Personnel, providing data basis for subsequent behavior analysis and anomaly detection. Through optical flow motion characteristic analysis, the motion information of personnel in the monitoring video, including speed, direction and displacement, is obtained to provide data basis for subsequent behavior analysis. A behavior trajectory map is constructed to visualize the movement trajectory of personnel, which can more intuitively display the activities of personnel on the construction site and facilitate the detection and analysis of abnormal behavior. A digital twin construction scene model is constructed based on the behavior trajectory map to compare the actual construction site situation with the model, realize virtual simulation and monitoring, understand the status and potential risks of the construction site, and use the preset construction behavior specification database to perform abnormal behavior analysis on the digital twin construction scene model to detect and identify abnormal behaviors on the construction site, and discover potential safety risks and problems in advance. Abnormal behavior frequency data and risk level quantitatively evaluate the safety status of the construction site, and provide reliable data support for decision makers to take corresponding risk control measures. Abnormal area positioning determines the specific areas with potential risks and problems on the construction site, which helps to accurately locate and solve safety hazards. Risk decision optimization optimizes the abnormal area according to the risk level and abnormal behavior frequency data, so as to take appropriate measures to reduce risks and ensure the safety of the construction site.
[0023] In the embodiment of the present invention, refer to Figure 1 , is a schematic diagram of a step flow chart of a method for wireless monitoring of a construction site of a smart building according to the present invention. In this example, the steps of the method for wireless monitoring of a construction site of a smart building include: Step S1: Obtain construction site environmental perception parameters, construction site monitoring video and construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain a regional monitoring map; perform regional noise intensity calculation on the regional monitoring map based on the construction site environmental perception parameters to construct a regional noise intensity map; In this embodiment, based on sensors and equipment, such as noise sensors, air quality sensors, temperature and humidity sensors, etc., environmental perception parameters of the construction site are obtained, surveillance cameras are installed or existing surveillance equipment is used to obtain surveillance videos of the construction site, and a structural diagram of the construction site is obtained. Image processing algorithms or computer vision technology are used to perform regional segmentation on the structural diagram of the construction site. The regional segmentation is based on the color, texture, shape and other features of the image to separate different areas in the structural diagram to form a regional monitoring map. Based on the environmental perception parameters of the construction site and the regional monitoring map, the noise intensity of each area is calculated, and the environmental perception parameters and pixel values of the regional monitoring map are used for relevant calculations, or a pre-established model is used to estimate the noise intensity, and the noise intensity information of each area is integrated into an image to form a regional noise intensity map. The regional noise intensity map is a grayscale map or a color map, in which different colors or brightness represent different noise intensity levels.
[0024] Step S2: Generate dust concentration spatial distribution data based on the construction site environmental perception parameters; dynamically render the construction site structure diagram based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model; In this embodiment, the construction site environmental perception parameters are used to calculate the spatial distribution of dust concentration in different areas according to factors such as the source of dust, wind direction, and meteorological conditions. The spatial distribution data of dust concentration is combined with the regional noise intensity map, and the construction site structure map is dynamically rendered according to the dust concentration and noise intensity information of each area. Dynamic rendering is achieved through graphic rendering technology, and the information of dust concentration and noise intensity is superimposed on the structure map in a visual way to form a three-dimensional environmental parameter scene model. Transparency, color mapping and other methods are considered in the rendering process to intuitively represent the distribution of dust concentration and noise intensity.
[0025] Step S3: performing time-delay visual optimization on the construction site monitoring video to obtain a time-delay optimized video frame sequence; obtaining a personnel boundary frame image based on the time-delay optimized video frame sequence; In this embodiment, image processing techniques such as inter-frame difference or optical flow method are performed on the surveillance video to detect moving targets in the video and track their motion trajectories. The video frames are time-delay optimized according to the motion trajectory and speed of the targets to reduce motion blur and delay effects. An interpolation or compensation algorithm is used to generate a delay-optimized video frame sequence. In the delay-optimized video frame sequence, a target detection or pedestrian detection algorithm is used to detect and locate personnel at the construction site, and the detected personnel are marked with bounding boxes to form a personnel bounding box image sequence, where each bounding box represents the position and size of a person in the corresponding video frame.
[0026] Step S4: performing optical flow motion characteristic analysis on the person boundary frame image to generate motion vector deformation data; and constructing a behavior trajectory mapping diagram based on the motion vector deformation data; In this embodiment, for a sequence of images of personnel boundary boxes, an optical flow algorithm (such as the Lucas-Kanade algorithm, the Farne back algorithm, etc.) is used to calculate the motion vector of the personnel in each boundary box. The optical flow algorithm calculates the displacement vector of each pixel point, and obtains the average motion vector of the personnel in each boundary box by averaging or statistically analyzing the displacement vectors. The motion vector data is used to analyze the behavior trajectory of the personnel at the construction site, and the size, direction, time series and other information of the motion vector are considered. Different behavior patterns, such as stillness, walking, running, etc., are identified according to the motion vector of the personnel, and the behavior trajectory information is mapped to a structural diagram or a plan view of the construction site to construct a behavior trajectory mapping diagram, and arrows, trajectory segments and the like are used to represent the movement direction and path of the personnel.
[0027] Step S5: construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; obtain abnormal behavior frequency data and risk level through the digital twin construction scene model; In this embodiment, the behavior trajectory mapping map is integrated with the three-dimensional environmental parameter scene model to construct a digital twin construction scene model. The behavior trajectory mapping map provides the movement path and behavior pattern of the personnel, while the three-dimensional environmental parameter scene model provides the distribution of environmental parameters such as dust concentration and noise intensity. The two are combined to construct a digital twin construction scene model, which simulates the three-dimensional structure, environmental parameters and personnel behavior of the construction site in a virtual environment, and establishes a preset construction behavior specification database, which includes construction behavior specifications that meet safety standards. The behavior trajectory in the digital twin construction scene model is compared and analyzed with the construction behavior specification database to identify abnormal behaviors that do not meet the specifications, and the frequency data of the abnormal behavior is calculated, that is, the number of times or proportion of abnormal behaviors occurring within a certain period of time. According to the frequency data and severity of the abnormal behavior, the risk level of each abnormal behavior is given to evaluate the safety status of the construction site.
[0028] Step S6: locate the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0029] In this embodiment, based on the abnormal behavior frequency data and the risk level, the area where the abnormal behavior exists is determined, and the area in the digital twin construction scene model is divided into different spatial units, such as grid units or area units. For each spatial unit, the comprehensive risk value of the abnormal behavior in the unit is calculated according to the abnormal behavior frequency data and the weight of the risk level. According to the comprehensive risk value, the abnormal area, that is, the spatial unit with a higher risk, is determined, and the risk decision is further optimized for the abnormal area to determine the appropriate wireless monitoring operation. Factors to be considered include the nature of the abnormal behavior, the risk level, the size and shape of the abnormal area, etc. Based on these factors, the number, location and monitoring strategy of monitoring equipment to be deployed are determined, and risk decisions are optimized, so that monitoring resources are effectively utilized, and abnormal behavior can be monitored and responded to in a timely manner.
[0030] In this embodiment, refer to Figure 2 , is a flowchart of detailed implementation steps of step S1. In this embodiment, the detailed implementation steps of step S1 include: Step S11: Obtaining construction site environmental perception parameters, construction site monitoring video and construction site structural diagram; Step S12: performing regional segmentation on the construction site structure diagram to obtain a regional monitoring diagram; Step S13: Calculating the regional noise intensity of the regional monitoring map based on the construction site environment perception parameters to obtain regional noise intensity data; Step S14: Perform intensity map drawing processing on the regional noise intensity data to construct a regional noise intensity map. In this embodiment, environmental perception sensors are deployed, such as noise sensors, dust sensors, temperature and humidity sensors, etc., to obtain relevant parameters of the construction site environment. The sensors monitor the environmental parameters in real time and transmit the data to the data acquisition system. Monitoring cameras are installed or existing monitoring camera systems are used to obtain monitoring videos of the construction site. The monitoring videos cover various areas of the construction site and provide real-time or recorded video data. The structural diagram or plan view of the construction site is obtained, which is an existing design drawing or a drawing obtained by measurement and drawing. The structural diagram should include information such as buildings, roads, and equipment layout at the construction site. According to the content and requirements of the structural diagram of the construction site, the diagram The area on the paper is divided and marked with rectangles, polygons or other shapes. According to the area division results, the corresponding regional monitoring map is generated. Each area is represented by a different mark or color in the map. For each area, the noise intensity of the area is calculated according to the environmental perception parameter data. The noise intensity calculation method is selected according to specific needs, such as weighted averaging or statistical analysis based on the noise sensor data. Image processing or drawing tools are used to draw a regional noise intensity map based on the processed regional noise intensity data. The intensity map uses different colors or color levels to represent noise of different intensities, so as to intuitively display the noise conditions in different areas of the construction site.
[0031] In this embodiment, refer to Figure 3 , is a flowchart of detailed implementation steps of step S2. In this embodiment, the detailed implementation steps of step S2 include: Step S21: performing dust concentration distribution analysis on the construction site environmental perception parameters to generate dust concentration spatial distribution data; Step S22: performing regional structural feature analysis on the construction site structure diagram to generate construction area structural feature data; Step S23: reconstructing the three-dimensional scene of the construction area structural feature data to construct a three-dimensional scene model; Step S24: dynamically render the three-dimensional scene model based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model. In this embodiment, based on the collected environmental perception parameters, a mathematical model or an empirical formula is used to analyze the dust concentration distribution, and the dust generation source, diffusion law, wind direction, meteorological conditions and other factors are considered to calculate the spatial distribution data of dust concentration in different areas, obtain the structural diagram of the construction site, which is a plane diagram or a three-dimensional model, and perform regional structural feature analysis on the structural diagram, including the location, shape, size and other features of elements such as buildings, equipment, and roads, extract and record the structural feature data of each area, such as the geometric shape, height, area and other information of the area, and use the collected construction area structural feature data to reconstruct the three-dimensional scene, and use computer graphics technology and three-dimensional modeling tools to convert the regional structural features into real-time data. The data is converted into a three-dimensional model. In the three-dimensional model, the elements such as buildings, equipment and roads at the construction site are accurately represented for subsequent scene rendering and visualization. The spatial distribution data of dust concentration is combined with the regional noise intensity map to add dynamic effects to the three-dimensional scene model. According to the dust concentration data, graphics or colors representing dust concentration are added to the corresponding areas in the three-dimensional scene model to reflect the distribution of dust. According to the regional noise intensity map, graphics or colors representing noise intensity are added to the corresponding areas in the three-dimensional scene model to show the noise level. Through dynamic rendering, a three-dimensional environmental parameter scene model is constructed to comprehensively display the structural characteristics of the construction site, dust concentration distribution, noise intensity and other environmental parameters.
[0032] In this embodiment, the dynamic rendering described in step S24 is specifically as follows: Setting concentration levels based on spatial distribution data of dust concentration; Assigning concentration color based on the concentration level to obtain concentration level color data; Perform dust distribution drift simulation on the three-dimensional scene model based on the concentration level color data to obtain a dust distribution scene model; Perform regional noise attenuation change analysis on the regional noise intensity map to obtain regional noise attenuation data; Performing noise attenuation demarcation on the three-dimensional scene model based on the regional noise attenuation data to obtain a noise attenuation demarcation line; Generate dynamic noise rendering parameters based on regional noise intensity map; The noise attenuation boundary line is used to map the boundary line of the dust distribution scene model, and dynamic rendering is performed using dynamic noise rendering parameters to construct a three-dimensional environmental parameter scene model. In this embodiment, refer to Figure 4 , is a flowchart of detailed implementation steps of step S3. In this embodiment, the detailed implementation steps of step S3 include: Step S31: extracting video frames from the construction site monitoring video to obtain a video frame sequence; Step S32: performing time delay visual optimization on the video frame sequence to obtain a time delay optimized video frame sequence; Step S33: performing visual detection of personnel on the delay-optimized video frame sequence to mark personnel position data; Step S34: performing boundary frame segmentation processing on the construction site monitoring video based on the personnel position data to obtain a personnel boundary frame image.
[0033] In this embodiment, different levels of dust concentration are set according to the spatial distribution data of dust concentration. According to actual needs and standard specifications, the dust concentration is divided into multiple levels, such as low, medium and high levels. A corresponding color is assigned to each set dust concentration level, and green is used to represent low concentration, yellow is used to represent medium concentration, and red is used to represent high concentration. The concentration level color data is applied to the dust distribution area in the three-dimensional scene model. According to the dust concentration level and color data, the corresponding area in the three-dimensional scene model is colored or mapped to represent the distribution of dust. A particle system or other simulation technology is used to simulate the drift effect of dust in the model so that dust is dynamically distributed in the scene. The regional noise intensity map is analyzed to understand the noise intensity distribution in different areas. Considering the propagation law and attenuation characteristics of noise, the noise attenuation data of each area is calculated, and the noise attenuation data is obtained. The data is expressed as an attenuation coefficient or attenuation function to describe the attenuation of noise with distance. According to the regional noise attenuation data, the noise attenuation dividing line between different areas is determined, and the noise attenuation dividing line is marked or drawn in the three-dimensional scene model to distinguish different attenuation areas. According to the data of the regional noise intensity map, the parameters required for dynamic noise rendering are generated. The parameters include the intensity, frequency, color, etc. of the noise, which are used to control the rendering and expression of the noise effect. The noise attenuation dividing line is mapped to the dust distribution scene model to mark different attenuation areas. According to the dynamic noise rendering parameters, the dust distribution scene model is dynamically rendered to make the noise and dust effects show realistic dynamic changes in the scene. Combining parameters such as dust distribution, noise attenuation and dynamic rendering, a three-dimensional environmental parameter scene model is constructed. This model is used to simulate and visualize scenes with dust distribution and noise attenuation effects.
[0034] In this embodiment, the specific steps of step S31 are: Step S311: annotate the video frame sequence with timestamps frame by frame to generate video frame annotation points; Step S312: calculating the average moving time between the video frame annotation points to obtain the average moving time of the annotation points in each frame; Step S313: identifying the video frame annotation points exceeding the standard based on the average moving time of the annotation points in each frame, so as to mark the frame points exceeding the delay standard; Step S314: performing video frame positioning based on the frame point where the delay exceeds the standard, so as to obtain the video frame where the delay exceeds the standard; Step S315: Calculate the time difference of the video frame with excessive delay and the video frame sequence to obtain delay time difference data; Step S316: Perform delay visual optimization on the video frames with excessive delay based on the delay time difference data to generate a delay optimized video frame sequence. In this embodiment, a video frame sequence is read and timestamp information is added to each frame. The timestamp uses the video playback time, frame number or other time representation methods to ensure that each frame has a unique time identifier. The video frame annotation points are traversed to calculate the time difference between each two adjacent frames. The time differences between all frames are added and divided by the total number of frames. The result is subtracted by one to obtain the average movement time. According to a preset threshold, the average movement time is compared with the threshold to determine whether the delay limit is exceeded. The frames that exceed the delay limit are marked to indicate the frame points where the delay exceeds the limit. According to the marking of the frame points where the delay exceeds the limit, the original frame is located. The corresponding frames in the initial video frame sequence are extracted, and the video frames with excessive delay are accurately located according to the frame index or timestamp and other information. The time stamp information of the video frames with excessive delay and their adjacent frames is used to calculate the time difference between them, and the time difference data between each video frame with excessive delay and its previous and subsequent frames are obtained. The video frames with excessive delay are subjected to delay visual optimization processing by using the delay time difference data, and the video frames are interpolated, removed, adjusted and other operations are performed according to the size and direction of the time difference to achieve the optimization effect of delay, and a video frame sequence after delay optimization is generated to display the optimized video content.
[0035] In this embodiment, the specific steps of step S4 are: Step S41: performing multi-frame optical flow tracking on the person boundary frame image to obtain dynamic optical flow tracking data; Step S42: performing optical flow motion characteristic analysis on the dynamic optical flow tracking data to generate motion vector deformation data; Step S43: performing behavior trajectory analysis on the motion vector deformation data to generate dynamic behavior trajectory data; Step S44: spatially map the dynamic behavior trajectory data to construct a behavior trajectory mapping diagram.
[0036] In this embodiment, the person boundary frame image is taken as input, and a time window is set, which includes multiple frames of continuous images. In the time window, the optical flow tracking algorithm is used to calculate the optical flow of each pixel point to obtain the displacement vector of the pixel point between continuous frames, and the optical flow tracking is performed on the pixel points in each person boundary frame, and the optical flow displacement vector of each pixel point is recorded. The above steps are repeated until all the person boundary frame images are processed. For each person boundary frame, the corresponding optical flow displacement vector data is collected, and the optical flow displacement vector is statistically analyzed to calculate the average displacement, displacement direction, displacement speed and other motion characteristics. According to the motion characteristics, motion vector deformation data is generated to represent the motion of the person boundary frame between continuous frames. The motion vector deformation data is represented in the form of a vector, including Displacement vectors, velocity vectors, etc., are connected between consecutive frames according to motion vector deformation data to form the motion trajectory of the person's bounding box. The motion trajectory is processed using an interpolation or smoothing algorithm to remove noise or smooth the motion. According to the motion trajectory, some behavioral features are extracted, such as movement direction, speed change, etc. According to the behavioral features, dynamic behavior trajectory data is generated to represent the motion trajectory of the person in the video sequence. The dynamic behavior trajectory data is mapped onto the video screen to form a behavior trajectory mapping diagram. The trajectory is drawn on the video frame using the position information of the person's bounding box and the motion change information in the dynamic behavior trajectory data. Different colors or line thicknesses are used to represent different behavior trajectories. The behavior trajectory mapping diagram is used to analyze the movement patterns and behavior changes of the person.
[0037] In this embodiment, the specific steps of step S5 are: Step S51: constructing a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; Step S52: performing abnormal behavior analysis on the digital twin construction scene model based on a preset construction behavior specification database to obtain abnormal behavior data; Step S53: performing abnormal frequency statistics on the abnormal behavior data to obtain abnormal behavior frequency data; Step S54: Evaluate the risk level of abnormal behavior based on the abnormal behavior frequency data to obtain a risk level. In this embodiment, the behavior trajectory mapping diagram is matched and integrated with the three-dimensional environmental parameter scene model. The behavior trajectory mapping diagram provides the movement trajectory information of the personnel, which is matched with the position, scale and other parameters of the three-dimensional environmental parameter scene model. The behavior trajectory in the behavior trajectory mapping diagram is associated with the corresponding area in the scene model to construct a digital twin construction scene model. The digital twin construction scene model will contain the information of the personnel behavior trajectory for subsequent abnormal behavior analysis and risk assessment. A preset construction behavior specification database is prepared, which contains normal construction behavior patterns and specifications. The digital twin construction scene model is compared and matched with the construction behavior specification database, and the personnel behavior trajectory in the digital twin construction scene model is analyzed and compared with the preset construction behavior specifications. Detect whether there are abnormal behaviors that do not conform to the specifications in the behavior trajectory, and record the abnormal behavior data, organize and count the recorded abnormal behavior data, count the frequency of each abnormal behavior within a certain time range, and calculate the frequency data of the abnormal behavior based on indicators such as the number of occurrences or duration of the abnormal behavior. Obtain the frequency data of each abnormal behavior for subsequent abnormal behavior risk assessment, set certain risk level classification standards based on the abnormal behavior frequency data, and determine the risk level of each abnormal behavior by comparing the frequency data of the abnormal behavior with the classification standards. According to indicators such as the frequency and duration of the abnormal behavior, classify the abnormal behavior into different risk levels, and obtain the risk level data of each abnormal behavior for evaluating the abnormal behavior risk in the construction scenario.
[0038] In this embodiment, the specific steps of step S6 are: Step S61: locating the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; Step S62: Predicting potential risks for abnormal area data to generate potential risk data for the construction site; Step S63: Optimize the risk decision of the potential risk data of the construction site to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0039] In this embodiment, the abnormal behavior frequency data and risk level data are used to determine the location and scope of abnormal behavior in the construction site. According to the area with high abnormal behavior frequency and abnormal behavior with high risk level, the area with abnormality is located. The abnormal area is a specific spatial location, such as a certain area of a building or a certain part of the construction site. The abnormal area data is obtained, the location and related information of the abnormal area are recorded, and the abnormal area data is analyzed to understand the potential risks in the abnormal area. Considering the characteristics of the abnormal behavior and the environmental conditions of the construction site, the nature and impact of the potential risks in the abnormal area are predicted. The potential risks include personnel safety risks, equipment damage risks, engineering quality risks, etc. According to the prediction results, the potential risk data of the construction site is generated, and the type and level of the potential risks are recorded. Based on the potential risk data of the construction site, risk decision optimization is performed, and corresponding risk decision strategies are formulated considering the specific conditions and resource constraints of the construction site. Risk decisions are optimized to minimize the probability of occurrence of potential risks and maximize the risk control effect, and regional risk decision optimization data is obtained, including optimized risk decision plans and corresponding execution plans. According to the regional risk decision optimization data, wireless monitoring operations are performed to monitor and control risks on the construction site.
[0040] In this embodiment, a wireless monitoring device for a smart building construction site is provided, which is used to execute the wireless monitoring method for a smart building construction site as described above, including: The regional segmentation module is used to obtain the construction site environmental perception parameters, the construction site monitoring video and the construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain the regional monitoring map; calculate the regional noise intensity of the regional monitoring map based on the construction site environmental perception parameters to construct the regional noise intensity map; Dynamic rendering module, used to generate dust concentration spatial distribution data based on construction site environmental perception parameters; dynamically render the construction site structure diagram based on dust concentration spatial distribution data and regional noise intensity map, and construct a three-dimensional environmental parameter scene model; The delay optimization module is used to perform delay visual optimization on the construction site monitoring video to obtain a delay optimized video frame sequence; based on the delay optimized video frame sequence, a personnel boundary box image is obtained; The behavior trajectory module is used to analyze the optical flow motion characteristics of the person's bounding box image and generate motion vector deformation data; and to construct a behavior trajectory map based on the motion vector deformation data; The abnormal behavior module is used to construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram, and to construct a digital twin construction scene model; the abnormal behavior frequency data and risk level are obtained through the digital twin construction scene model; The risk decision module is used to locate abnormal areas based on abnormal behavior frequency data and risk levels to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
[0041] The present invention provides visual perception and structural information of the entire construction site and specific areas through the regional segmentation module, providing basic data for subsequent monitoring and analysis. The regional noise intensity map helps identify and locate the noise source in the construction site, which is helpful to evaluate the potential impact of noise on workers and equipment. The dynamic rendering module provides a comprehensive simulation and visualization of the environmental parameters of the construction site, so that monitoring personnel can more intuitively understand the environmental conditions of the construction site. The three-dimensional environmental parameter scene model helps predict and evaluate the distribution of dust and noise in the construction site, providing a reference for optimizing construction plans and worker arrangements. The delay optimization module improves the quality and clarity of the monitoring video, reduces the video delay, and enables monitoring personnel to observe and analyze the situation on the construction site more accurately. The personnel boundary box image is used for further motion analysis and behavior recognition, helping monitoring personnel detect and track the construction site. The behavior trajectory module provides quantitative analysis of the movement and behavior of personnel on the construction site, and detects abnormal movement and behavior. The behavior trajectory map intuitively displays the movement paths and activity areas of personnel on the construction site, which helps monitoring personnel to have an overall understanding of the construction site and detect anomalies. The abnormal behavior module provides detection and identification of abnormal behaviors on the construction site, helping monitoring personnel to promptly discover potential safety risks. The digital twin construction scene model simulates and predicts various behaviors and scenarios on the construction site, and provides decision support for risk assessment and preventive measures. The risk decision-making module can conduct more targeted monitoring and intervention on the construction site based on the location and risk level of the abnormal area, improve the safety and efficiency of the construction site, optimize risk decisions, help monitoring personnel to reasonably allocate resources and take appropriate measures, and reduce potential safety risks and work interruptions.
[0042] Therefore, the embodiments should be regarded as illustrative and non-restrictive from all points, and the scope of the present invention is limited by the appended claims rather than the above description, and it is therefore intended that all changes falling within the meaning and range of equivalent elements of the application documents are included in the present invention.
[0043] The above is only a specific embodiment of the present invention, so that those skilled in the art can understand or implement the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but should conform to the widest scope consistent with the principles and novel features invented herein.
Claims
1. A wireless monitoring method for a smart building construction site, characterized in that: The following steps are involved: Step S1: Obtain construction site environmental perception parameters, construction site monitoring video and construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain a regional monitoring map; perform regional noise intensity calculation on the regional monitoring map based on the construction site environmental perception parameters to construct a regional noise intensity map; Step S2: Generate dust concentration spatial distribution data based on the construction site environmental perception parameters; dynamically render the construction site structure diagram based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model; Step S3: performing time-delay visual optimization on the construction site monitoring video to obtain a time-delay optimized video frame sequence; obtaining a personnel boundary frame image based on the time-delay optimized video frame sequence; Step S4: performing optical flow motion characteristic analysis on the person boundary frame image to generate motion vector deformation data; Constructing a behavior trajectory map based on motion vector deformation data; Step S5: construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; obtain abnormal behavior frequency data and risk level through the digital twin construction scene model; Step S6: locating the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; Risk decision optimization is performed on abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
2. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S1 are: Step S11: Obtaining construction site environmental perception parameters, construction site monitoring video and construction site structural diagram; Step S12: performing regional segmentation on the construction site structure diagram to obtain a regional monitoring diagram; Step S13: Calculating the regional noise intensity of the regional monitoring map based on the construction site environment perception parameters to obtain regional noise intensity data; Step S14: Perform intensity map drawing processing on the regional noise intensity data to construct a regional noise intensity map.
3. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S2 are: Step S21: performing dust concentration distribution analysis on the construction site environmental perception parameters to generate dust concentration spatial distribution data; Step S22: performing regional structural feature analysis on the construction site structure diagram to generate construction area structural feature data; Step S23: reconstructing the three-dimensional scene of the construction area structural feature data to construct a three-dimensional scene model; Step S24: dynamically render the three-dimensional scene model based on the dust concentration spatial distribution data and the regional noise intensity map to construct a three-dimensional environmental parameter scene model.
4. The method for wireless monitoring of smart building construction sites according to claim 3 is characterized in that: The dynamic rendering described in step S24 is specifically as follows: Setting concentration levels based on spatial distribution data of dust concentration; Assigning concentration color based on the concentration level to obtain concentration level color data; Perform dust distribution drift simulation on the three-dimensional scene model based on the concentration level color data to obtain a dust distribution scene model; Perform regional noise attenuation change analysis on the regional noise intensity map to obtain regional noise attenuation data; Performing noise attenuation demarcation on the three-dimensional scene model based on the regional noise attenuation data to obtain a noise attenuation demarcation line; Generate dynamic noise rendering parameters based on regional noise intensity map; The noise attenuation boundary line is used to map the boundary line of the dust distribution scene model, and dynamic rendering is performed using dynamic noise rendering parameters to construct a three-dimensional environmental parameter scene model.
5. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S3 are: Step S31: extracting video frames from the construction site monitoring video to obtain a video frame sequence; Step S32: performing time delay visual optimization on the video frame sequence to obtain a time delay optimized video frame sequence; Step S33: performing visual detection of personnel on the delay-optimized video frame sequence to mark personnel position data; Step S34: performing boundary frame segmentation processing on the construction site monitoring video based on the personnel position data to obtain a personnel boundary frame image.
6. The method for wireless monitoring of smart building construction sites according to claim 5, characterized in that: The specific steps of step S31 are: Step S311: annotate the video frame sequence with timestamps frame by frame to generate video frame annotation points; Step S312: calculating the average moving time between the video frame annotation points to obtain the average moving time of the annotation points in each frame; Step S313: identifying the video frame annotation points exceeding the standard based on the average moving time of the annotation points in each frame, so as to mark the frame points exceeding the delay standard; Step S314: performing video frame positioning based on the frame point where the delay exceeds the standard, so as to obtain the video frame where the delay exceeds the standard; Step S315: Calculate the time difference of the video frame with excessive delay and the video frame sequence to obtain delay time difference data; Step S316: Perform delay visual optimization on the video frames with excessive delay based on the delay time difference data to generate a delay optimized video frame sequence.
7. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S4 are: Step S41: performing multi-frame optical flow tracking on the person boundary frame image to obtain dynamic optical flow tracking data; Step S42: performing optical flow motion characteristic analysis on the dynamic optical flow tracking data to generate motion vector deformation data; Step S43: performing behavior trajectory analysis on the motion vector deformation data to generate dynamic behavior trajectory data; Step S44: spatially map the dynamic behavior trajectory data to construct a behavior trajectory mapping diagram.
8. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S5 are: Step S51: constructing a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram to construct a digital twin construction scene model; Step S52: performing abnormal behavior analysis on the digital twin construction scene model based on a preset construction behavior specification database to obtain abnormal behavior data; Step S53: performing abnormal frequency statistics on the abnormal behavior data to obtain abnormal behavior frequency data; Step S54: Evaluate the risk level of abnormal behavior based on the abnormal behavior frequency data to obtain a risk level.
9. The method for wireless monitoring of smart building construction sites according to claim 1, characterized in that: The specific steps of step S6 are: Step S61: locating the abnormal area based on the abnormal behavior frequency data and the risk level to obtain abnormal area data; Step S62: Predicting potential risks for abnormal area data to generate potential risk data for the construction site; Step S63: Optimize the risk decision of the potential risk data of the construction site to obtain regional risk decision optimization data to perform wireless monitoring operations.
10. A wireless monitoring device for a smart building construction site, characterized in that: Used to execute the wireless monitoring method for smart building construction site as claimed in claim 1, comprising: The regional segmentation module is used to obtain the construction site environmental perception parameters, the construction site monitoring video and the construction site structure diagram; perform regional segmentation on the construction site structure diagram to obtain the regional monitoring map; calculate the regional noise intensity of the regional monitoring map based on the construction site environmental perception parameters to construct the regional noise intensity map; Dynamic rendering module, used to generate dust concentration spatial distribution data based on construction site environmental perception parameters; dynamically render the construction site structure diagram based on dust concentration spatial distribution data and regional noise intensity map, and construct a three-dimensional environmental parameter scene model; The delay optimization module is used to perform delay visual optimization on the construction site monitoring video to obtain a delay optimized video frame sequence; based on the delay optimized video frame sequence, a personnel boundary box image is obtained; The behavior trajectory module is used to analyze the optical flow motion characteristics of the person's bounding box image and generate motion vector deformation data; and to construct a behavior trajectory map based on the motion vector deformation data; The abnormal behavior module is used to construct a twin model of the three-dimensional environmental parameter scene model based on the behavior trajectory mapping diagram, and to construct a digital twin construction scene model; the abnormal behavior frequency data and risk level are obtained through the digital twin construction scene model; The risk decision module is used to locate abnormal areas based on abnormal behavior frequency data and risk levels to obtain abnormal area data; optimize the risk decision of the abnormal area data to obtain regional risk decision optimization data to perform wireless monitoring operations.
Citation Information
Cited By
Rapid construction method and system of infrared three-dimensional model
CN119091054A
Safety management system for constructors in dangerous area
CN119418454A
Road construction site all-weather flying dust online monitoring method and system
CN119470183A
Intelligent construction site management method and system based on Internet of Things
CN119728743A
Bridge construction dynamic three-dimensional risk area monitoring method and system based on monocular 3D detection algorithm
CN119832492A