Rock slope arch anchor pile composite supporting structure and supporting method

By using the composite support structure of arch anchor piles on the rocky slope and using the force transmission mechanism for support, the problem of failure to consider the distribution form of slope geological layers in the existing technology is solved, and stable support of slopes is achieved and cost savings.

CN118933028AInactive Publication Date: 2024-11-12CHONGQING BASIC ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410991532.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The prior art fails to effectively consider the distribution form of slope geological layers when supporting ultra-high and ultra-steep rock slopes, resulting in high support costs and serious waste.

Method used

The composite support structure of rock slope arch anchor piles is adopted, including side-by-side square piles, arc-distributed round piles, anchor cables and series-connected arch ribs, which are supported through the force transmission mechanism to reduce construction difficulty and Structural area.

Benefits of technology

It realizes stable support of the slope, reduces construction costs and project volume, effectively controls the thrust of ultra-high and steep rock slopes, and reduces the structural cross-sectional area and anchor cable depth.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933028A_ABST
    Figure CN118933028A_ABST
Patent Text Reader

Abstract

The invention relates to the field of slope supporting, and discloses an arch-anchor-pile composite supporting structure which is reasonable in structural design, low in cost and capable of effectively controlling engineering disasters of rock slopes which are ultrahigh, deep and steep by 40 m and large in thrust. And after the arched beam is finished, the anchor cable is locked by the anchor head after prestress is applied to the anchor cable. The arched girders and the surrounding piles can be used as inter-pile interval protection and can also be used as anchor cable supporting points, the construction cost is reduced, meanwhile, force passing through the arched girders is transmitted to the supporting piles and the triangular supporting plates, the section size and the anchoring depth of a traditional pile-anchor supporting structure of the ultrahigh and steep rock slope are reduced, the purpose of reducing the excavation width of a foundation pit is achieved, and the construction efficiency is improved. And the construction risk is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of slope support, and in particular to a rock slope arch anchor pile composite support structure and a support method. Background Art

[0002] Slope support is an engineering project that involves foundation pit engineering, road engineering, and geological disaster control engineering. Among them, super-high and steep rock slopes are a type of complex support engineering. Rock slopes refer to slopes composed of rocks, which are widely found around various engineering projects such as highways, railways, mines, water conservancy and hydropower, and urban construction. Due to the physical and mechanical properties of the rock itself, as well as the influence of natural weathering, rain erosion, earthquakes, and human excavation, rock slopes are prone to deformation and damage, and even geological disasters such as collapse and landslides occur, posing a threat to surrounding facilities and the safety of people's lives and property.

[0003] Rock slopes have discontinuous surfaces such as bedding and joints, are soft and broken, have large thrust, are difficult to support, have high support costs, and have low bonding coefficients between rock layers, which can easily cause large-scale landslide accidents, seriously affecting the safety and construction progress of the project. For ultra-high, ultra-steep rock slopes with huge thrust, the existing technology mostly uses anchor rods and other anchor rod combination support systems for support. Although it can effectively protect the slope, it does not take into account the distribution of the geological layer of the slope, and requires a large amount of steel bars and concrete. The cost is high at the same support strength, resulting in great waste. Based on the above background, it is necessary to develop a rock slope support structure for this type of rock slope that can not only meet the needs of engineering slope protection projects, but also save engineering investment and reduce waste. Therefore, a rock slope arch anchor pile composite support structure came into being. Summary of the invention

[0004] The present invention aims to provide a composite support structure of rock slope arch anchor piles to solve the problem of super-high, super-steep rock slopes with huge thrust. The existing technology mostly uses anchor rods and other anchor rod combination support systems for support. Although it can effectively protect the slope, it does not take into account the distribution of the geological layer of the slope, resulting in great waste.

[0005] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a composite support structure of rock slope arch anchor piles, including two side-by-side stressed square piles, a plurality of stressed circular piles are distributed side by side along an arc between the two stressed square piles, a plurality of anchor cables located outside the arc are vertically arranged on the upper edge of the stressed circular piles, a stressed arch rib with a plurality of stressed circular piles connected in series is connected between the two stressed square piles, a plurality of stressed arch ribs are vertically arranged side by side, and a supporting plate is connected to the side of the stressed square pile away from the stressed arch rib.

[0006] Preferably, as an improvement, the length of the anchor cable penetrating into the stable rock formation is not less than 0.5 m.

[0007] Preferably, as an improvement, the length of the anchor cable penetrating into the soft and broken layer is not less than 0.5 m.

[0008] Preferably, as an improvement, the embedded section of the stressed circular pile is not less than 1 / 3 of the total length of the whole pile.

[0009] Advantages of the present invention include:

[0010] 1. The present invention uses an ultra-high, ultra-steep and high-thrust rock slope model and uses different principles of force transmission as the basis for engineering design, thereby achieving stable slope support while reducing the construction difficulty and the area and engineering volume of the structural interface. It has significant economic benefits for engineering applications with huge slope thrust and large support engineering volume.

[0011] 2. The action mechanism and connection of anchor cables, load-bearing circular piles and load-bearing arch ribs, through the transmission of force, connect the anchoring area within the length of the anchor cables with the load-bearing circular piles and load-bearing arch ribs after the anchor cables apply prestress, which has the effect of squeezing and reinforcing the rock formations in the action area, thereby improving its integrity.

[0012] 3. The forces of anchor cables and load-bearing circular piles are dispersedly transmitted to the load-bearing square piles at both ends of the supporting structure through the load-bearing arch ribs, so that the thrust transmission is not limited to a certain supporting structure. Under the joint action, the thrust is greatly decomposed, the safety of each structure is guaranteed, the cross-sectional area of ​​the structure is reduced, the construction cost is saved, and the cost waste is reduced.

[0013] 4. Previously, the tensile and shear resistance of steel bars and concrete was mainly used to support the slope. After improvement, this scheme mainly supports it through an integral arch structure. The structural design is reasonable, the cost is low, and it can effectively control engineering disasters of rock slopes that are ultra-high, deep, steep, and have huge thrust.

[0014] 5. The thrust is transmitted to the supporting column through the arch beam, reducing the depth of the surrounding piles and anchor cables.

[0015] The present invention also provides a rock slope arch anchor pile composite support method, which is used to form the above-mentioned rock slope arch anchor pile composite support structure, comprising the following steps:

[0016] A. Before excavating the foundation pit, load-bearing round piles, load-bearing square piles and the first layer of load-bearing arch ribs are installed. Then, the soil is excavated in layers according to the vertical position of the anchor cables and the position of the second layer of load-bearing arch ribs. The soil between the piles is excavated, and then the steel mesh is erected, and the transverse tensioning bars are implanted, and then the protective concrete between the piles is sprayed. At the position of the second layer of load-bearing arch ribs, the soil between the piles is installed according to the cross-sectional size of the second layer of load-bearing arch ribs. The longitudinal reinforcement of the load-bearing arch ribs is welded to the connecting steel bars by implanting reinforcement, and the stirrups of the load-bearing arch ribs are tied. Finally, the load-bearing arch rib concrete is poured;

[0017] B. After the concrete reaches the designed strength, use a drilling machine to drill holes for anchor cables on the stressed circular piles. After the drilling is completed, insert the anchor cables through the holes, then inject the anchor bodies, cast the anchor heads, and after the anchor bodies reach the strength, perform prestressing, and after tensioning to the designed value, use anchors to lock them;

[0018] C. Excavate and pour in layers according to the above sequence to the top elevation of the triangular retaining plate, dig the foundation trench for the triangular retaining plate, dig the foundation trench according to the size of the triangular retaining plate, implant the transverse reinforcement of the triangular retaining plate into the load-bearing square piles, and tie the triangular retaining plate steel bars. Finally, support the formwork and pour the triangular retaining plate concrete. After the concrete reaches the designed strength, construct the last layer of load-bearing arch ribs and anchor cables according to the above construction sequence of the load-bearing arch ribs and anchor cables.

[0019] Preferably, as an improvement, the concrete strength grade of the load-bearing circular piles and the load-bearing arch ribs is C30.

[0020] Preferably, as an improvement, the strength grade of the protective shotcrete between piles is C25, the steel mesh is first-grade steel, with a diameter of 8mm and a spacing of 200mm×200mm; the transverse reinforcement is third-grade steel, with a diameter of 16mm and a vertical spacing of 1500mm. The depth of the reinforcement implanted in the load-bearing circular pile is 300mm and it is implanted inside the spiral reinforcement of the load-bearing circular pile. The single-sided welding length of the transverse reinforcement is 160mm.

[0021] Preferably, as an improvement, the concrete strength grade of the stressed square piles is C30, the longitudinal bars and stirrups are both grade three steel, the diameter of the longitudinal bars is 20 mm, the diameter of the stirrups is 12 mm, the spacing between the stirrups in the core area is 100 mm, the spacing between the stirrups in the non-core area is 200 mm, and the single-sided welding length of the longitudinal bars is 200 mm.

[0022] Preferably, as an improvement, the triangular support plate is an isosceles triangle, the transverse reinforcements are all grade three steel, the transverse reinforcements are embedded in the load-bearing square piles, the transverse reinforcement diameter is 20mm, the stirrup diameter is 12mm, the spacing is 100mm, and the single-sided welding length of the transverse reinforcement is 160mm.

[0023] Preferably, as an improvement, the anchor cable is a prestressed anchor cable. After the stress-bearing arch rib sprayed concrete and the anchor body reach the design strength, the prestressed anchor cable is tensioned and locked according to the design requirements, the barge is connected together, and a number of stress-bearing arch rib longitudinal reinforcements are tied by the stress-bearing arch rib stirrups.

[0024] Compared with the traditional pile-anchor support structure, the arch-anchor pile composite support structure of the rock slope formed by the construction of this scheme does not occupy the internal space of the foundation pit. After the arch rib is completed, it is only necessary to apply prestress to the anchor cable and then lock the anchor cable with the anchor head. The thrust is transmitted to the support column through the arch beam, which can reduce the depth of the surrounding piles and anchor cables. The arch rib and the round pile in the present invention can be used as interval protection between piles and as anchor cable support points, which reduces the construction cost. At the same time, the force of the arch rib is transmitted to the square pile and the triangular support plate, which reduces the cross-sectional size and anchoring depth of the traditional pile-anchor support structure of the super-high and steep rock slope, achieving the purpose of reducing the excavation width of the foundation pit, reducing the construction risk, and is suitable for promotion and use. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a top view of embodiment 1 of the present invention.

[0026] Figure 2 It is a side view of embodiment 1 of the present invention.

[0027] Figure 3 It is a front view of embodiment 1 of the present invention.

[0028] Figure 4 Schematic diagram of the arch rib force and thrust angle changes in Example 3 of the present invention.

[0029] Figure 5 This is a schematic diagram of stress control of a medium-thick arch in Example 3 of the present invention.

[0030] Figure 6 This is a schematic diagram of the K~φ curve in Example 3 of the present invention. DETAILED DESCRIPTION

[0031] The following is further described in detail through specific implementation methods:

[0032] The figure marks in the drawings of the specification include: anchor cable 1, load-bearing square pile 2, support plate 3, load-bearing round pile 4, load-bearing arch rib 5, ground line 6, and embedded section 7.

[0033] Embodiment 1, a rock slope arch anchor pile composite support structure, basically as shown in the attached Figure 1 , Figure 2 and Figure 3As shown: it includes two side-by-side stressed square piles 2, the cross section of the stressed square piles 2 is 3000mm×4000mm, and seven stressed round piles 4 are distributed side by side along the arc between the two stressed square piles 2, the pile diameter of the stressed round piles 4 is 800mm, the pile spacing is 1500mm, the bottom of the stressed round piles 4 is embedded below the ground line 6, and the embedded section 7 of the stressed round piles 4 is not less than 1 / 3 of the total length. Six anchor cables 1 located outside the arc are vertically arranged on the upper edge of the stressed round piles 4, and the anchor cables 1 are prestressed anchor cables 1, and the anchor cables 1 penetrate into the rock layer, and the length of the anchor cables 1 penetrating into the stable rock layer is not less than 0.5m; the length of the anchor cables 1 penetrating into the weak and broken layer is not less than 0.5m. A load-bearing arch rib 5 with a number of load-bearing circular piles 4 connected in series is connected between the two load-bearing square piles 2. The cross-section of the load-bearing arch rib 5 is 800mm×800mm. The load-bearing arch rib 5 is vertically arranged in four layers side by side. A triangular supporting plate 3 is cast and connected on the side of the load-bearing square pile 2 away from the load-bearing arch rib 5. The triangular supporting plate 3 is a 7000mm isosceles triangle with a thickness of 1000mm.

[0034] The concrete strength grade of the load-bearing round pile 4, the load-bearing square pile 2 and the load-bearing arch rib 5 is C30.

[0035] Embodiment 2, a rock slope arch anchor pile composite support method, used to form a rock slope arch anchor pile composite support structure of embodiment 1, comprising the following steps:

[0036] A. Before excavation of the foundation pit, load-bearing round piles 4, load-bearing square piles 2 and the first layer of load-bearing arch ribs 5 are constructed. The concrete strength grade of load-bearing round piles 4 and load-bearing arch ribs 5 is C30. The diameter of load-bearing round piles 4 is 800mm, the pile spacing is 1500mm, and the cross section of load-bearing arch ribs 5 is 800mm×800mm. The concrete strength grade of load-bearing square piles 2 is C30, the cross section is 3000mm×4000mm, the longitudinal bars and stirrups are both grade 3 steel, the longitudinal bars have a diameter of 20mm, the stirrups have a diameter of 12mm, the stirrups have a core area spacing of 100mm, the non-core area spacing of 200mm, and the longitudinal bars have a single-sided welding length of 200mm.

[0037] B. Then, according to the vertical position of the anchor cable 1 and the position of the second-layer load-bearing arch rib 5, the soil is excavated in layers, 100mm thick soil is excavated between the piles, and then a steel mesh is erected, and transverse reinforcement is implanted before spraying 50mm thick pile protection concrete. The strength grade of the pile protection sprayed concrete is C25, the steel mesh is first-class steel, with a diameter of 8mm and a spacing of 200mm×200mm; the transverse reinforcement is third-class steel, with a diameter of 16mm and a vertical spacing of 1500mm. It is implanted into the load-bearing round pile 4 with a depth of 300mm and inside the spiral reinforcement of the load-bearing round pile 4. The single-sided welding length of the transverse reinforcement is 160mm.

[0038] C. Dig out 800mm thick × 800mm high soil between piles at the position of the second layer of arch rib 5, weld the longitudinal reinforcement of arch rib 5 to the connecting reinforcement by planting reinforcement, tie the stirrups of arch rib 5, and finally pour the concrete of arch rib 5.

[0039] D. After the concrete reaches the design strength, use a drilling machine to drill holes for anchor cables 1 on the stressed circular pile 4. After the drilling is completed, insert the anchor cables 1 through the holes. The anchor cables 1 are prestressed anchor cables 1. Then inject anchor bodies, which are cement slurry or cement mortar. Cast anchor heads. After the stressed arch rib 5 is sprayed with concrete and the anchor bodies reach the design strength, tension the prestressed anchor cables 1 according to the design requirements. After tensioning to the design value, lock them with anchors. The barges are connected together, and a number of stressed arch rib 5 longitudinal bars are tied by the stressed arch rib 5 stirrups.

[0040] E. Excavate and pour in layers according to the above sequence to the top elevation of the triangular retaining plate 3. The triangular retaining plate 3 is a 7000mm isosceles triangle with a thickness of 1000mm. Dig a foundation trench for the triangular retaining plate 3. Dig a foundation trench of 1000mm thick × 7000mm long according to the size of the triangular retaining plate 3. Through planting reinforcement, embed the transverse reinforcement of the triangular retaining plate 3 into the stressed square pile 2. The transverse reinforcement is grade 3 steel. The transverse reinforcement is embedded in the stressed square pile 2. The transverse reinforcement diameter is 20mm, the stirrup diameter is 12mm, the spacing is 100mm, and the single-sided welding length of the transverse reinforcement is 160mm. Tie the triangular retaining plate 3 steel bars, and finally support the formwork to pour the triangular retaining plate 3 concrete. After the concrete reaches the design strength, construct the last layer of stressed arch rib 5 and anchor cable 1 according to the above construction sequence of stressed arch rib 5 and anchor cable 1.

[0041] Compared with the traditional pile-anchor support structure, the stressed arch rib 5 does not occupy the internal space of the foundation pit. After the stressed arch rib 5 is completed, it is only necessary to apply prestress to the anchor cable 1 and then lock the anchor cable 1 with the anchor head. The stressed arch rib 5 and the stressed round pile 4 in the present invention can be used as the interval protection between piles and as the support point of the anchor cable 1, which reduces the construction cost. At the same time, the force of the stressed arch rib 5 is transmitted to the stressed square pile 2 and the triangular support plate 3, reducing the cross-sectional size and anchoring depth of the traditional pile-anchor support structure of the super-high and steep rock slope, achieving the purpose of reducing the excavation width of the foundation pit, reducing the construction risk, and being suitable for promotion and use.

[0042] Example 3: This example provides a method for determining the arch rib center angle of the arch-anchor pile composite supporting structure, which is used to determine the arch rib center angle of the arch-anchor pile composite supporting structure in Example 1 and Example 2.

[0043] For a rock slope of a given length and height, the active rock pressure or residual sliding force P is determined. Due to the use of an arch structure, a P' force is generated to press on the stable rock mass at both ends of the slope, such as Figure 4As shown in (a), this force varies with the size of the central angle.

[0044] Depend on Figure 4 (a) It can be seen that P' = Rsinα (see the figure for the meaning of the symbols), where R = P / 2cosα. Since P is a constant, it can be seen that R increases as α increases.

[0045] According to calculations, as the center angle gradually increases, the thrust angle α will gradually deviate to the slope at both ends of the slope and reach a certain peak value, that is, the thrust angle αmax corresponding to the maximum P' that can be obtained using the arch rib. Beyond this point, the thrust angle α gradually decreases, and the thrust gradually turns to the slope surface, as shown in Figure 4 (b).

[0046] Depend on Figure 4 (a) shows:

[0047]

[0048] Where HA and VA are the arch end axial force and shear force respectively.

[0049] As the arch gradually bends, the numerator of the first term in the formula gradually increases and the denominator gradually decreases. In this way, the direction of the resultant force is closer to the normal direction of the square pile, and the first term in the formula gradually increases, which makes the α value monotonically increase, that is, the direction of the resultant force gradually turns from the tangent direction to the normal direction and deflects toward the slope; and as the arch gradually bends, the φA value, that is, the absolute value of the second term in the formula, gradually increases and makes the α value monotonically decrease, that is, the normal direction gradually deflects out of the slope. There must be a maximum value of α, and the central angle 2φ corresponding to αmax is the optimal central angle.

[0050] 1. The optimal center angle of the hoop theory

[0051] Assuming that the arch ring is a simple hoop, ignoring the bending moment and only considering the axial force, the stress inside the arch is:

[0052] σ=pr / t

[0053] Where: p is the radial water pressure acting on the arch axis; r is the radius of the arch center axis; t is the thickness of the arch.

[0054] Assume the span of the arch is L, the semi-center angle is φ, then r = L / (2sinφ). If the allowable stress is [σ], let σ = [σ], and the thickness of the arch is t = pr / [σ]. The volume V of the arch per unit height is:

[0055]

[0056] From the above formula, we can see that for different central angles, the arch will have different volumes. According to the extreme value condition:

[0057] The optimal center angle of the arch is 2φ=133.56°, which is obtained based on the simple hoop theory.

[0058] 2. Calculation of the optimal center angle

[0059] In the above derivation, only the axial force is considered in the stress calculation, and the bending moment is ignored. The stress of the arch rib is relatively complex, some parts are controlled by the allowable tensile stress, and some parts are controlled by the allowable compressive stress. It is very difficult to directly calculate the optimal center angle using extreme value conditions.

[0060] The determination method is introduced in two steps: the first step is the calculation of the fully stressed arch rib; the second step is the calculation of the optimal center angle of the elastic arch that takes into account both the arch rib stress and the stability of the loaded square pile.

[0061] (1) Calculation of fully stressed arch ribs

[0062] A fully stressed arch rib is one in which the stress at at least one point in the arch rib reaches the allowable stress.

[0063] For Figure 5 The equal thickness arch shown in the figure generally has 6 stress control points, namely points 1 to 6. The so-called fully stressed arch rib means that the stress at at least one control point reaches the allowable stress.

[0064] Assume that the central angle of the arch is 2φ, the radius is r, the thickness is t, the active rock pressure is p, and the elastic moduli of the arch rib and the slope rock mass are E and Ef respectively. The steps for calculating the thickness of the fully stressed arch rib are as follows:

[0065] ① Calculate the initial arch thickness by the following formula:

[0066] t=βpr / [σ] (2-2)

[0067] In the formula: [σ] is the allowable compressive stress; β = 1.1~1.4, which is an empirical coefficient, usually β = 1.3.

[0068] ② Calculate the axial force N and bending moment M of the arch rib according to the elastic arch calculation.

[0069] ③ Let the stress of each control point 1 to 6 in the arch be equal to the corresponding allowable compressive stress or allowable tensile stress. According to the plane section assumption, we get:

[0070]

[0071] In the formula, the allowable stress [σ] is positive for tensile stress and negative for compressive stress. The critical thickness of the arch rib is obtained from the above formula:

[0072]

[0073] Where a = [σ], b = N, c = 6M (slope surface), or c = -6M (free surface), there are two solutions for t, take the larger one. Corresponding to the six control points 1 to 6 of the arch, the above formula can be used to calculate the six critical thicknesses, and the largest one is taken as the allowable thickness of the arch, so that at least one control point in the arch reaches the allowable stress, and the stress of other points does not exceed the allowable stress.

[0074] After the thickness changes, the internal force of the arch rib also changes to a certain extent. For this reason, an iterative algorithm is used. According to the thickness of the arch rib obtained above, the above steps ② to ③ are repeated and the iterative calculation is performed until convergence.

[0075] Given n center angles 2φi (i=1~n), corresponding to each center angle, the thickness ti of the fully stressed arch and the corresponding arch volume Vi=2rφiti are calculated using the above method. From the V~φ curve, the center angle 2φ with the smallest volume can be obtained, which is the optimal center angle of the elastic arch determined by the stress conditions.

[0076] (2) Calculation of the optimal center angle of the elastic arch taking into account both the arch rib stress and the stability of the square pile

[0077] In actual engineering, in addition to stress conditions, the stability condition of the loaded square pile is also an important factor. Therefore, the optimal center angle of the arch should satisfy the stability coefficient K of the loaded square pile not less than the allowable value [K].

[0078] According to the process of step (1), after drawing the V~φ curve of the fully stressed arch, for each central angle 2φi, calculate the stability coefficient Ki of the arch anchor pile composite support structure and draw the K~φ curve. Figure 6 As shown in the figure, the intersection of the K~φ curve and the horizontal straight line K=[K] is the optimal central angle of the elastic arch that satisfies both the arch rib stress condition and the stability condition of the loaded square pile.

[0079] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A rock slope arch anchor pile composite support structure, characterized by: It includes two side-by-side stressed square piles, between which a plurality of stressed circular piles are distributed side by side along an arc, a plurality of anchor cables located outside the arc are vertically arranged on the stressed circular piles, a stressed arch rib with a plurality of stressed circular piles connected in series is connected between the two stressed square piles, a plurality of stressed arch ribs are vertically arranged side by side, and a triangular supporting plate is connected to the side of the stressed square pile away from the stressed arch rib.

2. The rock slope arch anchor pile composite support structure according to claim 1, characterized in that: The length of the anchor cable penetrating into the stable rock formation shall not be less than 0.5m.

3. The rock slope arch anchor pile composite support structure according to claim 2 is characterized by: The length of the anchor cable penetrating into the soft and broken layer shall not be less than 0.5m.

4. The rock slope arch anchor pile composite support structure according to claim 3 is characterized by: The embedded section of the loaded circular pile shall not be less than 1 / 3 of the total length.

5. A rock slope arch anchor pile composite support method, used to form a rock slope arch anchor pile composite support structure as claimed in any one of claims 1 to 4, characterized in that: The following steps are involved: A. Before excavating the foundation pit, load-bearing round piles, load-bearing square piles and the first layer of load-bearing arch ribs are installed. Then, the soil is excavated in layers according to the vertical position of the anchor cables and the position of the second layer of load-bearing arch ribs. The soil between the piles is excavated, and then the steel mesh is erected, and the transverse tensioning bars are implanted, and then the protective concrete between the piles is sprayed. At the position of the second layer of load-bearing arch ribs, the soil between the piles is installed according to the cross-sectional size of the second layer of load-bearing arch ribs. The longitudinal reinforcement of the load-bearing arch ribs is welded to the connecting steel bars by implanting reinforcement, and the stirrups of the load-bearing arch ribs are tied. Finally, the load-bearing arch rib concrete is poured; B. After the concrete reaches the designed strength, use a drilling machine to drill holes for anchor cables on the stressed circular piles. After the drilling is completed, insert the anchor cables through the holes, then inject the anchor bodies, cast the anchor heads, and after the anchor bodies reach the strength, perform prestressing, and after tensioning to the designed value, use anchors to lock them; C. Excavate and pour in layers according to the above sequence to the top elevation of the triangular retaining plate, dig the foundation trench for the triangular retaining plate, dig the foundation trench according to the size of the triangular retaining plate, implant the transverse reinforcement of the triangular retaining plate into the load-bearing square piles, and tie the triangular retaining plate steel bars. Finally, support the formwork and pour the triangular retaining plate concrete. After the concrete reaches the designed strength, construct the last layer of load-bearing arch ribs and anchor cables according to the above construction sequence of the load-bearing arch ribs and anchor cables.

6. A rock slope arch anchor pile composite support method according to claim 5, characterized in that: The concrete strength grade of the load-bearing circular piles and load-bearing arch ribs is C30.

7. A rock slope arch anchor pile composite support method according to claim 6, characterized in that: The strength grade of the protective shotcrete between piles is C25, the steel mesh is first-grade steel with a diameter of 8mm and a spacing of 200mm×200mm; the transverse reinforcement is third-grade steel with a diameter of 16mm and a vertical spacing of 1500mm. It is implanted 300mm deep into the load-bearing circular pile and is implanted inside the spiral reinforcement of the load-bearing circular pile. The single-sided welding length of the transverse reinforcement is 160mm.

8. A rock slope arch anchor pile composite support method according to claim 7, characterized in that: The concrete strength grade of the loaded square piles is C30. The longitudinal bars and stirrups are both grade three steel. The diameter of the longitudinal bars is 20mm, the diameter of the stirrups is 12mm, the spacing between the stirrups in the core area is 100mm, the spacing in the non-core area is 200mm, and the single-sided welding length of the longitudinal bars is 200mm.

9. A rock slope arch anchor pile composite support method according to claim 8, characterized in that: The triangular support plate is an isosceles triangle. The transverse reinforcement is made of grade 3 steel. The transverse reinforcement is embedded in the load-bearing square piles. The diameter of the transverse reinforcement is 20mm, the diameter of the stirrup is 12mm, the spacing is 100mm, and the single-sided welding length of the transverse reinforcement is 160mm.

10. A rock slope arch anchor pile composite support method according to claim 9, characterized in that: The anchor cable is a prestressed anchor cable. After the arch rib sprayed concrete and anchor body reach the design strength, the prestressed anchor cable is tensioned and locked according to the design requirements, the barge is connected together, and several arch rib longitudinal reinforcements are tied through the arch rib stirrups.