Performance evaluation method during reconstruction or continuous construction of existing foundation pit
Through on-site inspection, rebound test, drill core sampling, indoor test and water pumping test, combined with software analysis, the concrete and steel structure performance of the foundation pit was evaluated, and the performance evaluation gap during foundation pit reconstruction or continued construction was solved, and the foundation was achieved The systematic evaluation of pit components' corrosion and water stop properties is suitable for renovation and continuation projects in underground space development.
Patent Information
- Application Number
- CN202410963467.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-15
AI Technical Summary
The existing technology lacks effective performance evaluation methods when building foundation pits are renovated or continued, especially the detection and evaluation of the corrosion degree of foundation pits and foundation pit components for a long-term shutdown is less, which is difficult to meet the needs of renovation and renewal in underground space development.
Provides a method including on-site inspection, in-situ rebound test, drill core sampling, indoor test and water pumping test to evaluate the strength, corrosion resistance and waterproofing of concrete and steel structures of existing foundation pits, combined with Qimingxing software conducts calculation and analysis to evaluate the working performance and water stop performance of the foundation pit.
This method can systematically evaluate the working performance of the foundation pit, consider the impact of corrosion of the foundation pit component on subsequent construction, and judge the water-stop performance of the foundation pit in high groundwater levels, providing a reliable reference for the renovation and renewal project, with simple operation and indicators Deep in layers.
Smart Images

Figure CN118965497A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of performance evaluation of an already constructed foundation pit during improvement or continued construction, and in particular to a performance evaluation method for an existing foundation pit during reconstruction or continued construction. Background Art
[0002] In the prior art, for example, Chinese patent CN114707225B proposes a foundation pit support performance evaluation method and device that takes into account water level fluctuations and support time effectiveness. By determining a series of rheological properties of soil and groundwater, the groundwater level fluctuation and support time effectiveness evaluation values are derived, and the time effectiveness performance of temporary support of the foundation pit can be evaluated more accurately. Chinese patent CN118133672A proposes a support performance evaluation method based on monitoring data. By collecting displacement, stress, temperature and other data, a series of post-processing is performed to evaluate the performance of the foundation pit support structure and optimize the construction efficiency. Although the above patents can evaluate the service performance of the foundation pit and can consider the influence of foundation pit components and groundwater, the processing involved is relatively complicated and only involves foundation pits in service. At present, there are few patents involving the evaluation of the working performance of long-term shutdown foundation pits and the detection of the degree of corrosion of foundation pit components. Considering the current slowdown in the development of underground space, many new projects also need to be rebuilt on existing structures. It is extremely important to evaluate the existing working performance of the shutdown foundation pit and the rebuilt foundation pit for subsequent construction. This situation was not taken into consideration in the above engineering case. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a performance evaluation method for the reconstruction or continuation of an existing foundation pit.
[0004] In order to solve the above technical problems, the technical solutions provided by the present invention are as follows:
[0005] Performance evaluation methods for reconstruction or continued construction of existing foundation pits include:
[0006] S1) Check the overall structure of the existing foundation pit, the concrete structure and the appearance of the steel structure;
[0007] S2) Carry out in-situ rebound tests to preliminarily test the strength and corrosion resistance of the concrete structure, and conduct core sampling measurements when it meets the requirements;
[0008] S3) On-site core sampling, cutting of steel components, forming core samples and steel component samples for indoor testing;
[0009] S4) obtaining the test parameters of the drill core sample and the steel component sample indoors, and calculating and analyzing the corrosion resistance and strength performance;
[0010] S5) Carry out a simple pumping test in the shutdown area to obtain the water-proof performance of the foundation pit.
[0011] Furthermore, in the step S1), the existing foundation pit is a coastal soft soil foundation pit 8-12m away from the river area, and also includes an inspection of the corrosion and water seepage of the foundation pit.
[0012] Furthermore, the step S2) specifically includes the following steps:
[0013] S21) In the existing foundation pit, components for rebound testing are selected and test areas are randomly set;
[0014] S22) Rebound hammer calibration, including perpendicularity of the hammer axis to the test surface, and reset calibration.
[0015] S23) After obtaining at least 16 rebound values in each measuring area, the average rebound value is calculated to form an initial result of the concrete strength of the measured component to determine whether corrosion causes a decrease in concrete strength.
[0016] Furthermore, in step S3), core drilling sampling is used for concrete structures, and cutting sampling is used for steel structures.
[0017] Furthermore, in the step S4), obtaining the detection parameters of the core samples and the steel structure samples indoors specifically involves performing a concrete compression test and a steel structure thickness test on the core samples indoors.
[0018] Furthermore, the compressive strength test specifically includes the following steps:
[0019] Through the compressive strength test of the concrete support core sample of the dock foundation pit;
[0020] According to the peak pressure obtained from the compressive strength test, the compressive strength of the sample is obtained by substituting it into the cross-sectional area formula (1);
[0021]
[0022] In the formula, α is 1, F is the peak pressure, π is a constant, and d 2 is the cross-sectional area.
[0023] Furthermore, in the analysis and calculation, specifically, the cross section of the foundation pit is calculated, and based on the material parameters obtained from the indoor test, the stress-deformation characteristics of the cross section before and after corrosion are calculated respectively, and the stress-deformation of the cross section before and after corrosion is compared to obtain the influence of corrosion on the performance of the foundation pit.
[0024] Furthermore, in the step S5), the water stopping evaluation effect is obtained based on the water level changes inside and outside the pit.
[0025] Furthermore, in the step S5), water level monitoring points are arranged inside and outside the pit, and the water pumping amount of the water pump is synchronously controlled within the water level drop setting.
[0026] The present invention has the following beneficial effects:
[0027] (1) The present invention fills the gap in the performance evaluation method of long-term shutdown or existing foundation pits, and provides a reference for the evaluation of more future renovation and continued construction foundation pits;
[0028] (2) The techniques and methods involved in the present invention are simple to operate and more suitable for engineering applications. There are standardized methods for reference, and the indicators obtained are in-depth and can consider the impact of corrosion of existing structures in the foundation pit on subsequent construction, and can judge the water-stopping performance of the foundation pit support structure or curtain in areas with high groundwater levels, and can evaluate the working performance of the foundation pit in a relatively systematic manner. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 A flow chart of a performance evaluation method for reconstruction or continued construction of an existing foundation pit provided by the present invention; Figure 2 The Venus calculation diagram and final working condition diagram provided by the present invention;
[0030] Figure 3 The envelope diagram of the maximum horizontal displacement provided by the present invention when it is 43.3 mm;
[0031] Figure 4 The envelope diagram of the bending moment provided by the present invention is -415.9~678.4KN*m / m;
[0032] Figure 5 The envelope diagram of the shear force provided by the present invention when it is -268.1 to 494 kN / m;
[0033] Figure 6 The envelope diagram of the maximum horizontal displacement provided by the present invention when it is 23.1 mm;
[0034] Figure 7 The envelope diagram of the bending moment provided by the present invention is -601.3~1465.4KN*m / m;
[0035] Figure 8 The envelope diagram of the shear force provided by the present invention when it is -377.9 to 574.5 kN / m;
[0036] Fig. 9 This is a comparison diagram of the deformation distribution and moment envelope diagram of the retaining structure before and after corrosion calculated by the Venusstar software in the case of the present invention. DETAILED DESCRIPTION
[0037] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.
[0038] The performance evaluation method of the present invention is applied to the reconstruction of an existing foundation pit in a shipbuilding base. The project is mainly used for the reconstruction of an existing foundation pit in a shipbuilding base. The original dock was suspended in 2012. Before the suspension, temporary cofferdams, dock pit (excavated to the second support) and other structures had been completed. The reconstruction and continuation of the 2# dock project will be carried out on the basis of the above-mentioned construction content. In order to ensure the smooth and safe progress of the subsequent reconstruction and continuation project, it is necessary to evaluate the working performance of the existing foundation pit before starting the construction, including the corrosion degree of the existing concrete structure and steel structure, the overall working performance of the foundation pit and the water-proof performance of the foundation pit.
[0039] See attached Figure 1-9 As shown, this embodiment will take the performance evaluation of the dock foundation pit as an example to introduce the evaluation method of the invention.
[0040] See attached Figure 1 As shown in the figure, in the specific construction, the performance evaluation method for the reconstruction or continuation of the existing foundation pit includes the following steps:
[0041] (1) On-site inspection: Conduct a visual inspection of the foundation pit along the perimeter of the suspended foundation pit, paying attention to whether there is any visible deformation of the retaining structure; after ensuring initial safety, enter the foundation pit to conduct a visual inspection of the existing support system, paying attention to whether the concrete has cracks, looseness, detachment, exposed reinforcement, and steel corrosion, record the location of the cracks and measure the crack width, pay attention to the surface corrosion of the steel structure, and record the obvious rusted areas.
[0042] In this embodiment, considering that the geological environment of the foundation pit is a soft soil foundation pit near the sea, the closest point to the Yangtze River is about 10m, and the foundation pit has abundant groundwater, the foundation pit structure, especially the steel structure, is more susceptible to corrosion. Therefore, in addition to the preliminary inspection of whether the structure is obviously corroded, attention should also be paid to whether there is water seepage in the surrounding structure.
[0043] (2) In-situ testing: In this project, in-situ rebound tests were mainly carried out on concrete components at typical locations. The rebound method was used to comprehensively and continuously test the strength of the structural concrete and to form a preliminary judgment on the corrosion of the foundation pit. On-site rebound tests were carried out on the main support, connecting rod, eight-shaped support and surrounding purlin of the first concrete support of the dock foundation pit, and the on-site rebound compressive strength values of each component were obtained, as shown in Table 1.
[0044]
[0045] In this embodiment, the main purpose of the in-situ detection is to conduct a preliminary test on the strength of the on-site concrete support. The specific operation steps are as follows:
[0046] 1) According to the support arrangement of the foundation pit, select the components for rebound test and randomly set up a certain number of measurement areas; 2) Carry out the test in the selected measurement area. During rebound, the axis of the rebound hammer should be kept perpendicular to the test surface at all times, and the pressure should be applied slowly, the readings should be accurate, and the test should be reset quickly; 3) 16 rebound values should be read in each measurement area, and the rebound values should be accurate to 1; 4) Calculate the average rebound value of the measurement area to obtain the preliminary results of the concrete strength of the measured components, which can be used to preliminarily determine whether there is corrosion that has caused a significant reduction in concrete strength.
[0047] (3) On-site sampling: Sampling of concrete components and steel structure components of typical structures of the foundation pit is carried out. Concrete is sampled by core drilling and steel structure is sampled by cutting. They are used for subsequent indoor material performance tests. The number of on-site samples and the arrangement of measuring points should meet the requirements of the specifications and include the main structures of the foundation pit. In this embodiment, core drilling is carried out on the main support of the first support of the dock pit, and a total of 5 measuring points are selected. According to the test specifications, 3 samples are required for each measuring point, and a total of 15 cylindrical core samples with a diameter of 100 mm are obtained; the main support and the surrounding purlin of the second steel support of the dock pit are selected for cutting sampling. There are 4 sampling points for the main support and 2 sampling points for the surrounding purlin. Three specimens are taken from each measuring point, among which the main support steel pipe is sampled along the thickness direction, and the surrounding purlin H-shaped steel is sampled at the flange.
[0048] In this embodiment, the on-site sampling adopts core drilling sampling for concrete structures and cutting sampling for steel structures. A certain number of concrete sampling positions are selected according to the support arrangement. During the sampling process, internal steel bars should be avoided as much as possible. Similarly, appropriate steel support sampling positions are selected and some components are cut. During the sampling process, it is necessary to avoid causing significant damage to the structure of the foundation pit and affecting the working performance of the foundation pit.
[0049] (4) Indoor testing: Indoor testing is performed on material samples obtained on site to obtain actual material parameters. Compressive strength tests are performed on concrete samples to obtain the actual strength of the concrete after corrosion. Thickness tests are performed on steel structure samples to obtain effective cross-sectional parameters after corrosion, and further determine the degree of corrosion of the material. By conducting compressive strength tests on the concrete support core samples of the dock foundation pit, the peak pressure and cross-sectional area obtained from the test are compared using the formula The compressive strength of the sample was obtained, where α was taken as 1, and the final average strength of the sample was 38.2MPa, while the concrete design value was C35. In order to ensure the quality, a higher strength concrete construction was used; through the thickness test of the steel structure sample, the average thickness of the second support main support was 15.83mm, and the average thickness of the purlin flange was 19.74mm. The design values of the two were 16mm and 20mm, respectively, and the effective thickness was reduced by 2.4% and 1.7%, respectively. In summary, the degree of corrosion of concrete and steel structures is not serious, and the data obtained from indoor testing will be used for subsequent calculations.
[0050] In this embodiment, the parameters obtained by conducting indoor tests are the compressive strength of concrete and the effective thickness of the steel structure, which are also conventional parameters. Specifically, the test parameters of the core samples and steel component samples are obtained indoors, such as conducting compressive strength tests on concrete samples to obtain the actual strength of the concrete after corrosion, and conducting thickness tests on steel structure samples to obtain the effective cross-sectional parameters after corrosion, so as to further determine the degree of corrosion of the material.
[0051] The main steps of the concrete compression test are:
[0052] 1) Process the concrete core sample to obtain a sample of standard size (according to the specification, the sample should be cylindrical or square), and grind the surface to make it uniform and flat;
[0053] 2) Carry out concrete compression test on a universal machine to obtain the stress-deformation curve of each specimen;
[0054] 3) Calculate the compressive strength of the concrete sample based on the peak pressure and take the average value as the strength of the concrete.
[0055] The main steps of steel structure thickness test are:
[0056] 1) Process the steel structure specimens, grind off the surface rust, and obtain a smooth and flat pattern;
[0057] 2) Use a vernier caliper to measure the effective thickness of the sample at this time;
[0058] 3) Take the average value as the effective thickness of the steel structure after corrosion.
[0059] (5) Calculation and analysis: Based on the material parameters and design values obtained from the indoor test, the Venus software was used to carry out calculations, compare and analyze the deformation and stress characteristics of the foundation pit before and after corrosion, analyze the impact of structural corrosion on the working performance of the foundation pit, and determine whether the current working performance of the foundation pit can meet the requirements of subsequent reconstruction and construction. The Venus software was used to calculate the dock pit. According to the support design plan of the dock pit, the calculation diagram of the selected section and the final construction condition diagram are shown in the figure below. Figure 2As shown, soil parameters refer to the engineering geological survey report, structural parameters are selected according to the design plan and indoor test results, and design value calculation and post-corrosion calculation are carried out respectively. The main difference in material parameters is the strength of the first concrete support and the cross-sectional size of the second steel support.
[0060] In this embodiment, the force calculation of the main cross-section of the foundation pit was carried out using Tongji Venus FRWS software. The calculation steps are as follows: (1) According to the design plan of the foundation pit, select a suitable cross-section of the foundation pit for calculation; (2) According to the geological conditions and support plan of the selected cross-section, determine the soil parameters and structural parameters, where the structural parameters use the design values, and calculate the force and deformation characteristics of the cross-section under the ideal condition where no corrosion occurs; (3) According to the material parameters obtained from the indoor test, the calculation is carried out again to obtain the force and deformation characteristics of the cross-section after corrosion; (4) Compare the differences in the force and deformation of the cross-section before and after corrosion to evaluate the impact of material corrosion on the working performance of the foundation pit.
[0061] According to the above, the calculated displacement and force envelope diagram of the foundation pit section are as follows: Figure 3-8 By comparison, it can be found that since the corrosion of the foundation pit mainly occurs in the first two supports, and the corrosion degree of the concrete and steel supports is relatively small, the impact on the subsequent construction is not significant, indicating that the working performance of the foundation pit is relatively good.
[0062] (6) Pumping test: For foundation pits in coastal areas, a simple pumping test should be conducted before the reconstruction and continuation of construction work is carried out. Water level monitoring points should be arranged inside and outside the pit to detect the water-proof performance of the suspended foundation pit by observing the water level changes inside and outside the pit. The width of the cofferdam is 32m and the length is 144.4m. The amount of water to be pumped out for every 1m drop in the water level is 5004m3. The commonly used water pump flow is about 250m3 / h. Four water pumps are arranged on site. The water level can be pumped down by 1m in 5 hours. Each pumping is carried out according to the water level drop of 1m. The interval between two pumpings is 4 hours, and a total of 2 pumpings are carried out. 9 groundwater level monitoring points are set outside the pit. The groundwater level monitoring results of the pumping test are shown in Table 2, where the start of the pumping test is defined as t0, the time when the two pumpings end is defined as t1 and t2, and the time 24 hours after the end of the pumping test is defined as t3. From the results, it can be seen that as the pumping test in the pit proceeds, the overall water level outside the pit will show a certain downward trend, but in the absence of leakage in the retaining structure, the groundwater level outside the pit will not drop sharply. In addition, it can be seen that since the SW6~SW8 measuring points are very close to the Yangtze River and can be replenished from a distance to a certain extent, their water levels fluctuate to a certain extent. As the pumping test proceeds, the water level outside the pit continues to drop in a short period of time (24 hours). The water level change did not exceed 0.3m within 24 hours, and the cumulative change did not exceed 1m, indicating that there was no obvious leakage in the retaining structure and the water-stopping performance was good.
[0063] Table 2
[0064]
[0065] In this embodiment, a local pumping test is carried out before the reconstruction and continuation of the construction project. According to the characteristics of the water level changes inside and outside the pit, it is judged whether there is a hydraulic connection between the inside and outside of the pit, and whether the waterproof performance of the retaining structure is good. The main steps of the local pumping test are: (1) setting up a number of pumping wells in the pit (inside the curtain) and a number of observation wells inside and outside the pit; (2) opening the pumping wells to carry out local precipitation in the pit, monitoring the pumping volume and the changes in the water level inside and outside the pit; (3) analyzing the waterproof effect of the retaining structure or the waterproof curtain by comparing the changes in the water level inside and outside the pit.
[0066] In this embodiment, in the entire step, S01 on-site detection and S02 in-situ detection are preliminary qualitative judgments, which can be used to preliminarily evaluate the performance of the foundation pit, such as whether there are wider cracks or obvious water leakage, whether the results of the on-site concrete rebound test are generally small, etc. The results of this step are usually used to preliminarily understand the working performance of the foundation pit.
[0067] If none of the above serious problems exist, sampling can be carried out in the S03 on-site sampling step for further quantitative research.
[0068] After sampling of concrete and steel structures, the S04 indoor test is carried out to further obtain more accurate material performance parameters, including the compressive strength of concrete and the effective thickness of steel structures. After completing this step, an evaluation can be carried out from the perspective of materials alone, such as how much the compressive strength of concrete is reduced compared to the design value after corrosion, and how much the effective thickness of the steel structure is reduced compared to the design value.
[0069] Then, the S05 calculation and analysis step is carried out. The properties of the material after corrosion are substituted into the foundation pit section through the Venus software for calculation, and the stress and deformation characteristics of the foundation pit section after corrosion are obtained. The results are compared with the calculation results using the design value (non-corroded) to evaluate the impact of material corrosion on the overall foundation pit.
[0070] The above steps can be used to determine the overall stress and deformation characteristics of the foundation pit. The S06 pumping test step is mainly aimed at foundation pits with high groundwater levels in coastal soft soil to determine whether the water-stopping performance of its retaining structure or water-stop curtain still meets the construction requirements.
[0071] In this embodiment, the results obtained include: (1) material aspects, including the degree of corrosion of concrete and steel structures, which is determined by the compressive strength of concrete after corrosion and the effective thickness of steel structures; (2) stress and deformation characteristics of foundation pits, which are the results of software calculations, including the maximum deformation and maximum bending moment of the retaining structure before and after corrosion; (3) water-stopping performance, which is mainly the changing characteristics of the water level inside and outside the pit during the pumping test.
[0072] In this embodiment, through 5 steps, logically progressive evaluation indicators are obtained, which are then linked together. The final conclusion should be whether the current working performance of the foundation pit is suitable for the construction of subsequent renovation and construction projects.
[0073] According to the above steps, if there are serious problems in the S01 on-site inspection and S02 in-situ detection steps, the foundation pit must be unsuitable for direct subsequent construction; if there are no obvious problems in the S01 on-site inspection and S02 in-situ detection, further testing is required to quantitatively obtain the performance of the material after corrosion from indoor tests, and the results are mainly reflected in physical and mechanical parameters; after obtaining the material performance, the deformation and stress changes of the foundation pit before and after corrosion are compared by calculation to determine whether the foundation pit is suitable for subsequent construction. For foundation pits with high groundwater levels near the sea, it is also necessary to verify whether its water-stopping performance is good through pumping tests.
[0074] Therefore, the final result is reflected by two indicators: the stress and deformation characteristics of the foundation pit and the water-stopping performance. To evaluate the former, it is necessary to obtain the physical and mechanical parameters of the material through a series of tests, and the latter requires obtaining the water level change characteristics through a pumping test.
[0075] In summary, through on-site monitoring and indoor tests, the concrete and steel structures of the dock pit have minor corrosion after 10 years of suspension. The deformation and stress characteristics of the dock pit excavation to the base were calculated using Venusstar software, and it was found that the corrosion of the first and second supports had little effect on the overall construction of the pit. The pumping test verified that the water-stopping performance of the retaining structure of the dock pit was good. In general, the working performance of the pit is good and can be subsequently expanded and rebuilt.
[0076] In this embodiment, in order to solve the corrosion degree and working performance problems of the existing structure of the renovation and continued foundation pit project, on-site detection, on-site sampling, indoor testing, calculation analysis and on-site pumping test were carried out to effectively evaluate the working performance and water-proof performance of the renovation and continued foundation pit project after long-term suspension. The series of methods used in the present invention form a set of evaluation methods for the working performance of the renovation and continued foundation pit, which can provide guidance and suggestions for such projects.
[0077] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0078] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. Performance evaluation method for reconstruction or continuation of existing foundation pits, It is characterized in that include, S1) Check the overall structure of the existing foundation pit, the concrete structure and the appearance of the steel structure; S2) Carry out in-situ rebound tests to preliminarily test the strength and corrosion resistance of the concrete structure, and conduct core sampling measurements when it meets the requirements; S3) On-site core sampling, cutting of steel components, forming core samples and steel component samples for indoor testing; S4) obtaining the test parameters of the drill core sample and the steel component sample indoors, and calculating and analyzing the corrosion resistance and strength performance; S5) Carry out a simple pumping test in the shutdown area to obtain the water-proof performance of the foundation pit.
2. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 1, It is characterized in that In the step S1), the existing foundation pit is a soft soil foundation pit near the sea 8-12m away from the river area, and also includes an inspection of the corrosion and water seepage of the foundation pit.
3. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 1, It is characterized in that The step S2) specifically comprises the following steps: S21) In the existing foundation pit, components for rebound testing are selected and test areas are randomly set; S22) Rebound hammer calibration, including perpendicularity of the hammer axis to the test surface, and reset calibration. S23) After obtaining at least 16 rebound values in each measuring area, the average rebound value is calculated to form an initial result of the concrete strength of the measured component to determine whether corrosion causes a decrease in concrete strength.
4. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 1, It is characterized in that In the step S3), core drilling is used for concrete structures and cutting is used for steel structures.
5. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 4, It is characterized in that In the step S4), obtaining the test parameters of the core sample and the steel structure sample indoors specifically involves performing a concrete compression test and a steel structure thickness test on the core sample indoors.
6. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 5, It is characterized in that The compressive strength test specifically comprises the following steps: Through the compressive strength test of the concrete support core sample of the dock foundation pit; According to the peak pressure obtained from the compressive strength test, the compressive strength of the sample is obtained by substituting it into the cross-sectional area formula (1); In the formula, α is 1, F is the peak pressure, π is a constant, and d 2 is the cross-sectional area.
7. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 5, It is characterized in that In the analysis and calculation, specifically, the cross section of the foundation pit is calculated, and based on the material parameters obtained from the indoor test, the stress-deformation characteristics of the cross section before and after corrosion are calculated respectively, and the stress-deformation of the cross section before and after corrosion is compared to obtain the influence of corrosion on the performance of the foundation pit.
8. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 1, It is characterized in that In the step S5), the water stopping evaluation effect is obtained based on the water level changes inside and outside the pit.
9. The performance evaluation method for reconstruction or continued construction of an existing foundation pit according to claim 8, It is characterized in that In the step S5), water level monitoring points are arranged inside and outside the pit, and the water pumping amount of the water pump is synchronously controlled within the water level drop setting.