By combining detachable lifting tooling and SPMT module vehicles in the non-slide area of the offshore oil platform, the problems of high construction height, long cycle and high cost are solved, low-level construction and efficient transportation are achieved, and construction costs and work are reduced. quantity.
Patent Information
- Application Number
- CN202411145170.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-22
AI Technical Summary
The existing technology of the construction of offshore oil platforms in non-slide areas has problems such as high height, long construction cycle, large workload, high material consumption and high construction costs.
Design a low-level construction method and device for non-slide areas of marine oil platform. By designing a detachable lifting tool, including columns and flanges, it is directly installed on cement pads and steel pads, and is weighed and installed using SPMT module trucks. Ship transport reduces temporary support and scaffolding occupation, and the flange and column are connected by pins, which have removable characteristics.
It reduces the height of the platform construction, reduces the occupation of temporary support and scaffolding, saves block construction costs, improves work efficiency, simplifies the design and operation of the weighing system, shortens the construction cycle, and reduces construction costs.
Smart Images

Figure CN118997094A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of offshore oil platform construction, and in particular relates to a method and a device for low-position construction of a non-slideway area of an offshore oil platform. Background Art
[0002] Offshore oil platforms are large in size and heavy in tonnage. Considering the later weighing and shipping methods of the platforms, they are usually built on slideways, using a jack-type weighing system for weighing and sliding loading. When the slideway resources are tight and cannot meet the needs of the construction and towing of the jacket and modules in the slideway area, it is necessary to consider building them in non-slideway areas. At present, the traditional construction method of offshore oil platforms in non-slideway areas is high in height, involving more temporary supports and scaffolding, long construction period, large workload, high material consumption and high construction cost.
[0003] Therefore, it is urgent to design a low-level construction method and device for the non-slide area of an offshore oil platform to solve the above-mentioned problems of high construction height, long construction period, large workload, high material consumption and high construction cost of existing offshore oil platforms. Summary of the invention
[0004] In order to solve the technical problems mentioned in the background technology of the existing offshore oil platform, such as high construction height, long construction period, large workload, high material consumption and high construction cost, a method and device for low-level construction of non-slide area of offshore oil platform is provided to solve the above problems.
[0005] To achieve the above-mentioned purpose, the specific technical scheme of the method and device for low-level construction of non-slideway area of an offshore oil platform of the present invention is as follows: A method for low-position construction of a non-slideway area of an offshore oil platform comprises the following steps: S1. Design and prefabricate detachable beam lifting equipment, including columns and side wings; S2. Determine the platform construction area, clean the site, lay the general assembly cement pads, use mortar to level the cement pads, and lay the steel pads on the mortar leveling; S3, install the foot boots and insert the posts into the foot boots; S4. Arrange temporary supports, set up scaffolding, and carry out the final assembly of offshore oil platforms; S5, detachable side wings are installed on the columns; S6, SPMT module truck weighing, loading and transportation.
[0006] Furthermore, the installation of the removable side wings includes placing the transport piers on the SPMT modular vehicle, placing rubber or plywood on the top, and then placing the removable side wings. The levelness of the foot boots and cement pads is measured before entering the vehicle. The SPMT modular vehicle drives into both sides of the cement pads, and the side of the column is connected to the side wings through a pin shaft.
[0007] Furthermore, weighing and shipping of the SPMT modular vehicle include arranging weighing sensors at sensor positions reserved on the transport piers, placing steel plates on the weighing sensors, and during weighing, the SPMT modular vehicle is raised independently using a corresponding hydraulic support system until it contacts the lower surface of the detachable beam lifting fixture, and the hydraulic suspension system is pressurized until the detachable beam lifting fixture is separated from the steel pad. After the SPMT modular vehicle bears all the weight, the pressure data is read after the support pressure of the SPMT modular vehicle reaches the static pressure, and the mass is calculated.
[0008] A low-position construction device for a non-slideway area of an offshore oil platform comprises a cement pad, a steel pad is laid on the cement pad after mortar is leveled, a foot boot is installed on the steel pad, a column is plugged into the foot boot, an offshore oil platform assembly is overlapped on the column, and also comprises an SPMT module vehicle, a side wing is placed on the module vehicle, the SPMT module vehicle moves to the column, the side wing is connected to the side of the column through a pin shaft, and the SPMT module vehicle transports the offshore oil platform assembly to a designated location via the side wing and the column.
[0009] Furthermore, a cylinder is provided on the boot, and an insert tip is provided at one end of the column, and the insert tip is inserted into the cylinder to connect the column and the boot.
[0010] Furthermore, the foot boot also includes a flat plate, which is arranged on a steel pad, and the cylinder is vertically arranged on the flat plate, and the cylinder and the flat plate are connected by reinforcing ribs.
[0011] Furthermore, the side of the column is symmetrically provided with a first plug-in portion and a second plug-in portion, and two side wings are provided, and the two side wings are respectively provided with a first plug-in slot and a second plug-in slot, the first plug-in portion is plugged into the first plug-in slot, and the second plug-in portion is plugged into the second plug-in slot.
[0012] Furthermore, a first lifting ear and a second lifting ear are symmetrically arranged on the side of the column, and a first connecting groove and a second connecting groove are respectively arranged on the two side wings. The first lifting ear is inserted into the first connecting groove and connected to the first connecting groove through a first pin shaft, and the second lifting ear is inserted into the second connecting groove and connected to the second connecting groove through a second pin shaft.
[0013] Furthermore, a first vertical plate and a second vertical plate are arranged on the side wing, the first vertical plate and the second vertical plate are arranged on the side wing at an interval, and a first plug-in groove is formed between the first vertical plate and the second vertical plate.
[0014] Furthermore, a third vertical plate and a fourth vertical plate are also arranged on the side wing. The third vertical plate and the fourth vertical plate are arranged on the side wing at an interval, and a first connecting groove is formed between the third vertical plate and the fourth vertical plate.
[0015] The method and device for low-position construction of non-slideway areas of an offshore oil platform of the present invention have the following advantages: By designing the column as a part of the lifting beam and directly installing it on the foot boots set above the cement pad and the steel pad, the platform construction height is lowered, the occupation of temporary supports and scaffolding is reduced, and the cost of module construction is saved. The side wings are connected to the columns by pins and have the characteristics of detachability. The SPMT module truck is weighed and shipped for transportation, which reduces the workload of designing, placing and withdrawing the weighing pad of the weighing system, thereby improving work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of a low-position construction device in a non-slideway area of an offshore oil platform in the prior art; Figure 2 It is a structural schematic diagram of the low-position construction device of the non-slideway area of the offshore oil platform and the offshore oil platform of the present invention; Figure 3 It is a structural schematic diagram of a low-position construction device for a non-slideway area of an offshore oil platform according to the present invention; Figure 4 It is a schematic diagram of the structure of the foot boots of the present invention; Figure 5 It is a structural schematic diagram of the column of the present invention; Figure 6 It is a schematic structural diagram of the wing of the present invention.
[0017] Description of the markings in the figure: 100, slide block; 200, lifting beam; 1, offshore oil platform; 2, cement pad; 3, steel pad; 4, foot boot; 41, flat plate; 42, cylinder; 43, reinforcing rib; 5, column; 51, column body; 52, plug tip; 53, first plug-in part; 54, second plug-in part; 55, first lifting ear; 56, second lifting ear; 57, column rib plate; 6, wing; 61, wing vertical plate 61; 62, first vertical plate; 63, second vertical plate; 64, third vertical plate; 65, fourth vertical plate; 66, top plate; 67, bottom plate; 68, wing rib plate; 7, SPMT module car; 8, plywood; 9, transport pier; 10, weighing sensor. DETAILED DESCRIPTION
[0018] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0019] Those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present invention and form different embodiments. For example, in the claims, any one of the claimed embodiments may be used in any combination.
[0020] Please refer to the attached Figure 1 To Attachment Figure 6 The invention describes a method and device for low-position construction of a non-slideway area of an offshore oil platform.
[0021] like Figure 1 As shown, the offshore oil platform 1 is large in size and heavy in tonnage. Considering the later platform weighing and loading and transportation, it is generally built on a slideway, weighed by a jack-type weighing system, and loaded on board by sliding. When the slideway resources on site are tight and cannot meet the needs of the construction and towing and loading of the jacket and module in the slideway area, it is necessary to consider building it in a non-slideway area. At present, the traditional construction method of offshore oil platforms 1 in non-slideway areas is:
[0022] 1. Level the site with mortar and lay the assembly slide block 100. Clean the site and level and compact the mortar. Stack the assembly slide block 100 at each platform leg position. When laying, align the center line of the slide block 100, level the mortar and pad it.
[0023] 2. Place the transport beam 200 and arrange temporary support. Place the transport beam 200 above the slide block 100 and arrange temporary support for the platform according to the actual situation on site.
[0024] 3. Install the foot boots 4 and the first column under the bottom deck, and the column is provided with a plug tip. Install the foot boots above the lifting beam 200, and then install the first column under the bottom deck upwards.
[0025] 4. Carry out platform assembly according to the principles of modularization and integration. Set up scaffolding according to the actual situation on site, install each deck sheet in turn, and complete the platform assembly work.
[0026] 5. Weighing with jack-type weighing system and SPMT loading. Design and manufacture jack support pads and lifting ring plates that meet the weighing requirements, arrange weighing pads under the lifting beam 200 and level them, and set the specifications, quantity and layout of the jacks according to the weighing report. Place the jacks between the weighing pads and the lifting beam 200, and connect the hydraulic oil circuit. The weighing system jacks synchronously lift the platform until the platform is completely transferred to the jacks. The weight sensors installed on the jacks measure the weight borne by each jack, and calculate the weight of each weighing point, the total weight of the platform and the horizontal center of gravity position. After the platform is weighed, remove the top plate, pads, jacks, and weighing pads for SPMT roll-on / roll-off loading.
[0027] This non-slide construction method has the following disadvantages: 1. The combination of the slide block 100 and the lifting beam 200 raises the entire platform by more than 3 meters, resulting in an increase in temporary supports and scaffolding during site construction, resulting in high construction costs.
[0028] 2. The resources of 200 lifting beams take up a long time throughout the entire platform construction cycle. If new modules are started during the same period, 200 lifting beams will need to be prefabricated, which will increase material costs and prefabrication costs.
[0029] 3. The existing construction method usually adopts a jack-type weighing system for weighing. Before weighing, it is necessary to design and prefabricate jack pads, lifting ring plates, weighing pads for supporting hydraulic jacks, place and level the weighing pads, and arrange and connect the jack hydraulic system. After weighing, the pads, jacks, and pads need to be removed. The entire weighing cycle is long, the workload is large, the material consumption is high, and the construction cost is high.
[0030] Therefore, it is urgent to design a method and device for low-position construction of non-slideway areas of an offshore oil platform 1 to solve the above-mentioned problems.
[0031] like Figures 2 to 6 As shown, a method for low-position construction of a non-slideway area of an offshore oil platform 1 in the present invention comprises the following steps: S1. Design and prefabricate a detachable beam lifting tooling, the beam lifting tooling comprising a column 5 and a side wing 6; The detachable beam lifting tooling is designed according to the platform specifications, weight and other information. The detachable beam lifting tooling mainly includes two parts, namely the column 5 and the wing 6. The column 5 is detachably connected to the wing 6. The interior of the column 5 is reinforced. The first lifting lug 55 and the second lifting lug 56 are symmetrically arranged on the outside of the column 5. The wing 6 is provided with two, and the two wings 6 are respectively provided with a first connecting groove and a second connecting groove. The first lifting lug 55 is inserted in the first connecting groove and connected to the first connecting groove through a first pin shaft. The second lifting lug 56 is inserted in the second connecting groove and connected to the second connecting groove through a second pin shaft. In this embodiment, the wing 6 and the column 5 are assembled when the offshore oil platform 1 is weighed and transported.
[0032] S2. Determine the platform construction area, clean the site, lay the assembly cement pad 2, level the cement pad 2 with mortar, and lay the steel pad 3 on the mortar; As with traditional platform construction, after the platform construction area is determined and before the assembly pads and temporary supports are placed, the site is cleaned and leveled and compacted with mortar. In this embodiment, four columns 5 are provided. According to the weight and the bearing capacity of the foundation, a group of cement pads 2 are placed under each column 5. There are four cement pads 2 in total, which are arranged in an array with the center line of the column 5 as the center. To ensure the horizontality of the upper surface of the cement pad 2, mortar leveling grouting is performed above the cement pad 2, and then a layer of 20 mm thick steel pad 3 is laid.
[0033] S3, installing the foot boot 4, and inserting the column 5 into the foot boot 4; In this embodiment, four foot boots 4 are prefabricated, and the foot boots 4 are welded by a 60mm thick φ1829mm cylinder 42, a 40mm thick rectangular flat plate 41, and four 30mm thick reinforcing ribs 43. The welding is performed in accordance with the welding process specification. The foot boots 4 are placed in the projection area of the column 5 on the steel pad 3. One end of the column 5 is provided with an insert tip 52, which is inserted into the cylinder 42 of the foot boot 4.
[0034] S4, arrange temporary supports, set up scaffolding, and carry out the final assembly of offshore oil platform 1; Arrange temporary supports and set up scaffolding according to the actual needs of the site, and complete the prefabrication, installation and assembly of the offshore oil platform 1 in accordance with the principles of modularization and integration. When assembling the deck plates of each layer, use horse ties to weld and fix the 5 pairs of interfaces of the columns.
[0035] S5, a detachable side wing 6 is installed on the column 5; The wing 6 is assembled by the SPMT module vehicle 7. The transport pier 9 is placed on the SPMT module vehicle 7, and the detachable wing 6 is placed after the rubber or plywood 8 is placed on the top of the transport pier 9 to ensure that there is enough clearance between the upper surface of the wing 6 and the lower surface of the block. The levelness of the boots 4 and the cement pad 2 is measured before entering the vehicle. The SPMT module vehicle 7 includes two vehicles, and the two vehicles drive under the preset block and are placed on both sides of the cement pad 2. Specifically, the column 5 and the wing 6 are connected by a pin shaft, and the SPMT module vehicle 7 uses its own jacking function to lift and adjust the height of the wing 6 to complete the connection and fixation of the wing 6 and the column 5. The pin shaft used in this embodiment is an 800-ton pin shaft.
[0036] S6, SPMT module car 7 is weighed and loaded for transportation.
[0037] After the assembly is completed on land, the SPMT weighing system is used for weighing, and the roll-on / roll-off loading is carried out after the weighing is completed. Specifically, the displacement sensor and hydraulic sensor are arranged and connected, and the weighing sensor 10 is arranged at the reserved sensor position of the transport pier 9. A steel plate is placed on the weighing sensor 10, and a spare pad is prepared to adjust the weighing height. During weighing, the positioning and point arrangement of the SPMT are completely consistent with the point position and point arrangement of the loading plan. Each column of SPMT is raised separately using the corresponding hydraulic support system until they contact the lower surface of the column 5 and the wing 6. The hydraulic support system continues to gradually raise the height to reduce the gap between the contact points and monitor the pressure gauge at the same time. The hydraulic suspension system is gradually pressurized until the offshore oil platform 1 is lifted, the detachable lifting beam tooling and the cement pad 2 are separated, the pressure of each group is checked, and the hydraulic support system is confirmed again. After the entire weight of the offshore oil platform 1, the column 5 and the wing 6 is borne by the SPMT, after the SPMT support pressure reaches the static pressure, the pressure data is read and the average of each data is taken, and the mass calculation is performed. The weighing is repeated 3 times, and the final result is the average of the weighings. After the weighing is completed, the loading operation is carried out.
[0038] By designing the column 5 as a part of the lifting beam and directly installing it on the foot boot 4 set above the cement pad 2 and the steel pad 3, the platform construction height is lowered, the occupation of temporary support and scaffolding is reduced, and the module construction cost is saved. The side wing 6 is connected to the column 5 by a pin shaft and has a detachable feature. The SPMT module vehicle 7 is weighed and shipped for transportation, which reduces the workload of designing, placing and withdrawing the weighing pad of the weighing system, thereby improving work efficiency.
[0039] Furthermore, before weighing and loading the SPMT module vehicle 7 for transportation, the floating rust and welding slag on the sensor placement positions on both sides of the transport pier 9 are cleaned with a steel brush. Before weighing, the operation area should be closed, warning signs should be hung, and no unauthorized personnel are allowed to enter. Any work that may generate a high-frequency electric field in the weighing equipment area must be stopped.
[0040] The present invention also provides a low-position construction device for a non-slide area of an offshore oil platform 1, comprising a cement pad 2, on which a steel pad 3 is laid after mortar is leveled, on which a foot boot 4 is installed, on which a column 5 is inserted, and on which the offshore oil platform 1 assembly is overlapped, and further comprising an SPMT module vehicle 7, on which a side wing 6 is placed, and the SPMT module vehicle 7 is moved to the column 5, so that the side wing 6 is connected to the side of the column 5 through a pin shaft, and the SPMT module vehicle 7 transports the offshore oil platform 1 assembly to a designated location through the side wing 6 and the column 5.
[0041] Compared with the offshore platform construction process in the prior art, the platform construction height is also passively raised due to the height of the slide block 100 and the lifting beam 200. The present invention converts the column 5 into a part of the detachable lifting beam tooling by connecting the side wing 6 through a pin shaft on the column 5, and directly installs it on the foot boot 4 set above the cement pad 2 and the steel pad 3, thereby reducing the platform construction height to an absolute low position, avoiding the dependence on the slideway during the construction of the offshore oil platform 1, improving the construction efficiency, and at the same time, reducing the occupation of temporary supports and scaffolding, saving the cost of module construction.
[0042] Moreover, in the prior art, the lifting beam 200 must be used throughout the entire construction cycle. There are multiple platforms being built at the same time on the construction site, and the demand for the lifting beam 200 is large, and the material procurement cost and prefabrication cost are high. The low-level construction device for the non-slide area of the offshore oil platform 1 provided by the present invention is detachable, and the side wing 6 does not need to be installed during the construction of the platform. After the platform is built, it can be assembled before weighing and loading, and no additional time is taken up by the SPMT module vehicle 7. After the installation of the side wing 6 is completed, weighing, transportation and loading operations can be carried out, shortening the construction period and improving the overall efficiency. At the same time, the side wing 6 can be flexibly arranged and applied to other projects according to the site's loading and weighing requirements, reducing the waste of resources caused by prefabricating multiple lifting beams 200 and long-term occupation of the lifting beams 200.
[0043] The SPMT module vehicle 7 is used for weighing, which avoids the use of weighing systems in the traditional non-slide area construction process, which requires the design of placing weighing piers, designing jack support pads and jacking ring plates, and removing weighing piers and jacks after weighing, thereby improving the platform weighing efficiency.
[0044] Further, if Figure 4 As shown, a cylinder 42 is provided on the boot 4, and a plug tip 52 is provided at one end of the column 5, and the plug tip 52 is inserted into the cylinder 42 to connect the column 5 to the boot 4. The boot 4 also includes a flat plate 41, which is arranged on the steel backing plate 3, and the cylinder 42 is vertically arranged on the flat plate 41, and the cylinder 42 and the flat plate 41 are connected by a reinforcing rib 43.
[0045] Further, if Figure 5 and Figure 6As shown, the side of the column 5 is symmetrically provided with a first plug-in portion 53 and a second plug-in portion 54. Specifically, the column 5 includes a column body 51, and the outer circumference of the column body 51 is symmetrically provided with the first plug-in portion 53 and the second plug-in portion 54, and the plug tip 52 is provided at one end of the column body 51. Two side wings 6 are provided, and the two side wings 6 are respectively provided with a first plug-in slot and a second plug-in slot, and the first plug-in portion 53 is plugged into the first plug-in slot, and the second plug-in portion 54 is plugged into the second plug-in slot. The side wing 6 is provided with a first vertical plate 62 and a second vertical plate 63, and the first vertical plate 62 and the second vertical plate 63 are arranged on the side wing 6 at intervals, and a first plug-in slot is formed between the first vertical plate 62 and the second vertical plate 63. The side wing 6 is also provided with a fifth vertical plate and a sixth vertical plate, and the fifth vertical plate and the sixth vertical plate are arranged on the side wing 6 at intervals, and a second plug-in slot is formed between the fifth vertical plate and the second sixth vertical plate. By setting the first plugging slot and the second plugging slot, the first plugging portion 53 is plugged into the first plugging slot, and the second plugging portion 54 is plugged into the second plugging slot, so as to achieve positioning of the column 5 and the side wing 6 during installation, and facilitate installation of the side wing 6 on the column 5.
[0046] Further, if Figure 5 and Figure 6 As shown, the side of the column 5 is symmetrically provided with a first lifting ear 55 and a second lifting ear 56, and the two side wings 6 are respectively provided with a first connecting groove and a second connecting groove. The first lifting ear 55 is inserted in the first connecting groove and connected to the first connecting groove through a first pin shaft, and the second lifting ear 56 is inserted in the second connecting groove and connected to the second connecting groove through a second pin shaft. The side wing 6 is also provided with a third vertical plate 64 and a fourth vertical plate 65, which are arranged on the side wing 6 at intervals, and a first connecting groove is formed between the third vertical plate 64 and the fourth vertical plate 65. The side wing 6 is also provided with a seventh vertical plate and an eighth vertical plate, which are arranged on the side wing 6 at intervals, and a second connecting groove is formed between the seventh vertical plate and the eighth vertical plate. The first lifting ear 55 is inserted in the first connecting groove, and through holes are opened on the first lifting ear 55, the third vertical plate 64 and the fourth vertical plate 65, and the first pin shaft hinges the first lifting ear 55 in the first connecting groove by passing through the through holes. The second lifting ear 56 is inserted into the second connecting groove. The second lifting ear 56, the seventh vertical plate and the eighth vertical plate are all provided with through holes. The second pin passes through the through holes to hinge the second lifting ear 56 into the second connecting groove.
[0047] Further, if Figure 5 and Figure 6As shown, the outer circumference of the column body 51 is symmetrically provided with a plurality of column ribs 57, which are arranged horizontally. The plurality of column ribs 57 are used to connect with the first plug-in portion 53, the second plug-in portion 54, the first hanging ear 55 and the second hanging ear 56, so as to increase the strength and limit the position. The side wing 6 includes a side wing vertical plate 61, a top plate 66 is arranged on the top of the side wing vertical plate 61, a bottom plate 67 is arranged on the bottom of the side wing vertical plate 61, and a plurality of side wing ribs 68 are arranged on the side of the side wing vertical plate 61. The top plate 66, the bottom plate 67 and the side wing vertical plate 61 can increase the strength. The side wing vertical plate 61 and the first vertical plate 62 are connected as a whole, that is, they are cut and formed from a piece of steel plate.
[0048] The column 5 is used as a part of the detachable beam lifting tooling, which is inserted and installed in the foot boot 4 arranged on the steel pad 3, so as to achieve the goal of lowering the module to an absolute low position for construction, reduce the cost of temporary support and scaffolding, save construction costs, overcome the dependence of module construction on the slideway and solve the difficulties such as location restrictions of the construction site; and this low-position construction method is also suitable for SPMT weighing, transportation and loading operations, improving the weighing and loading efficiency; the detachable beam lifting tooling can be flexibly disassembled, and only the side wing 6 needs to be installed when the module is weighed, loaded and transported. During the construction period before weighing and loading, the pin shaft can be removed and the side wing 6 can be used for other projects, avoiding the long-term occupation of the beam lifting 200 resources and saving construction costs.
[0049] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A method for low-level construction of non-slideway areas of an offshore oil platform, characterized in that: The following steps are involved: S1. Design and prefabricate detachable beam lifting equipment, including columns and side wings; S2. Determine the platform construction area, clean the site, lay the general assembly cement pads, use mortar to level the cement pads, and lay the steel pads on the mortar leveling; S3, install the foot boots and insert the posts into the foot boots; S4. Arrange temporary supports, set up scaffolding, and carry out the final assembly of offshore oil platforms; S5, detachable side wings are installed on the columns; S6, SPMT module truck weighing, loading and transportation.
2. The method for low-level construction of non-slideway areas of an offshore oil platform according to claim 1, characterized in that: The installation of the removable side wings includes placing the transport piers on the SPMT modular vehicle, placing rubber or plywood on top, and then placing the removable side wings. The levelness of the foot boots and cement pads is measured before entering the vehicle. The SPMT modular vehicle drives into both sides of the cement pads, and the side of the column is connected to the side wings through a pin shaft.
3. The method for low-level construction of non-slideway areas of an offshore oil platform according to claim 1, characterized in that: The weighing and shipping of the SPMT modular vehicle includes arranging weighing sensors at the sensor positions reserved on the transport piers, placing steel plates on the weighing sensors, and using the corresponding hydraulic support system to raise the SPMT modular vehicle alone during weighing until it contacts the lower surface of the detachable beam lifting fixture. The hydraulic suspension system is pressurized until the detachable beam lifting fixture is separated from the steel pad. After the SPMT modular vehicle bears all the weight, the pressure data is read and the mass calculation is performed after the support pressure of the SPMT modular vehicle reaches the static pressure.
4. A low-level construction device for non-slideway areas of an offshore oil platform, characterized in that: It includes cement pads, on which mortar is leveled and then steel pads are laid, on which foot boots are installed, on which columns are inserted, on which offshore oil platform assemblies are overlapped, and it also includes SPMT module vehicles, on which side wings are placed, the SPMT module vehicle is moved to the columns, so that the side wings are connected to the sides of the columns through pins, and the SPMT module vehicle transports the offshore oil platform assemblies to the designated location through the side wings and the columns.
5. The low-position construction device for non-slideway area of an offshore oil platform according to claim 4 is characterized in that: A cylinder is arranged on the foot boot, and an inserting tip is arranged at one end of the column, and the inserting tip is inserted into the cylinder to connect the column with the foot boot.
6. The low-position construction device for non-slideway areas of an offshore oil platform according to claim 4, characterized in that: The foot boot also includes a flat plate, which is arranged on a steel pad, and a cylinder is vertically arranged on the flat plate, and the cylinder and the flat plate are connected by reinforcing ribs.
7. The low-position construction device for non-slideway areas of an offshore oil platform according to claim 4, characterized in that: The side of the column is symmetrically provided with a first plug-in portion and a second plug-in portion, and two side wings are provided with a first plug-in slot and a second plug-in slot respectively. The first plug-in portion is plugged into the first plug-in slot, and the second plug-in portion is plugged into the second plug-in slot.
8. The low-position construction device for non-slideway areas of an offshore oil platform according to claim 7, characterized in that: The side of the column is symmetrically provided with a first lifting ear and a second lifting ear, and the two side wings are respectively provided with a first connecting groove and a second connecting groove. The first lifting ear is inserted into the first connecting groove and connected to the first connecting groove through a first pin shaft, and the second lifting ear is inserted into the second connecting groove and connected to the second connecting groove through a second pin shaft.
9. The low-level construction device for non-slideway areas of an offshore oil platform according to claim 7, characterized in that: A first vertical plate and a second vertical plate are arranged on the side wing, the first vertical plate and the second vertical plate are arranged on the side wing at an interval, and a first plugging groove is formed between the first vertical plate and the second vertical plate.
10. The low-position construction device for non-slideway areas of an offshore oil platform according to claim 8, characterized in that: A third vertical plate and a fourth vertical plate are also arranged on the side wing. The third vertical plate and the fourth vertical plate are arranged on the side wing at intervals, and a first connecting groove is formed between the third vertical plate and the fourth vertical plate.
Citation Information
Cited By
Split vertical non-slideway construction design method for shallow water jacket
CN120930290A