Public area layout and facility configuration method based on station boarding and alighting amount

Through the classification and classification method based on the station's ride-off volume, the layout and facility configuration of station public areas are refined, and the problems of high vacancy rate and high operating costs of subway station public areas are solved, the matching of facilities and passenger flow is achieved, and the Operating costs.

CN119037510AActive Publication Date: 2024-11-29BEIJING URBAN CONSTRUCTION DESIGN & DEVELOPMENT GROUP CO LIMITED +1

Patent Information

Application Number
CN202411100746.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-11-29
Estimated Expiration
2044-08-12

AI Technical Summary

Technical Problem

The vacancy rate of subway station public areas has high operating and management costs, and the existing extensive development model has failed to effectively match passenger flow, resulting in an increase in construction and operation costs.

Method used

Based on the public area layout and facility configuration method of station ride and landing, the public area layout and facility configuration of stations are determined through hierarchical classification, and the inlet and exit gates, security inspection equipment, building escalators and cameras are coordinated to design the station facilities layout in detail.

Benefits of technology

It reduces the vacancy rate of public areas, reduces the management and maintenance costs during station projects investment and operation periods, and achieves a better matching between facilities and passenger flow.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119037510A_ABST
    Figure CN119037510A_ABST
Patent Text Reader

Abstract

The invention discloses a public area layout and facility configuration method based on station boarding and alighting quantity, which comprises the following steps of: S1, determining station grades according to the number of train marshalling and the station boarding and alighting quantity in peak exceeding hours, and calculating the overall layout and the column span layout of a double-layer island type station public area; s2, determining the width of a station platform; s3, determining the group number of building escalators; s4, determining the number of station entrance and exit gate sets, the number of security inspection equipment and the number of building escalator point position cameras; s5, determining the number of entrance and exit gates; according to the invention, the stations are graded and classified according to the station overpeak hour boarding and descending amount, the overall arrangement, the column span size and the layout of the station public area are determined according to grading, and the refined design of the public area layout is realized; in-out station gates, security inspection equipment, building escalator point position cameras, public area layout and the number of building escalator groups are adjusted in a linkage mode, the public area facility vacancy rate is reduced, and station project investment and management and maintenance cost in the operation period are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of transportation technology, and more specifically, relates to a public area layout and facility configuration method based on the number of passengers and alighters at a station. Background Art

[0002] In recent years, subway development has been dominated by an extensive development model, which focuses on scale expansion rather than efficiency improvement. It can quickly expand the coverage of the subway network and increase capacity. However, with the rapid expansion of the urban rail transit network, the subway, as an important part of urban public transportation, has also seen its construction and operating costs increase year by year.

[0003] According to the economic benefit analysis of subway lines, the original extensive development is no longer suitable for the construction needs of modern subway stations. The cost control and refined design control of the whole life cycle of the station will be the direction of future station construction development. At present, there has been no in-depth research at home and abroad on controlling station investment through refined design during the subway construction period. The platform width of standard subway stations is uniformly 11m or 12m, and the standards of public area service facilities equipped with the same width platform are also the same. This setting leads to a high redundancy in the configuration of equipment terminals, which greatly exceeds the passenger demand; and the calculation method of the same equipment in various places is not unified, and the setting principle does not consider the linkage between the facilities, resulting in the mismatch between the station scale, entry and exit gates, security inspection machines, escalators, etc. and passenger flow, resulting in a high vacancy rate of public area service facilities, which not only increases the engineering investment during the station construction period, but also increases the management and maintenance costs during the operation period. Summary of the invention

[0004] In view of the problems of high vacancy rate of service facilities in the public areas of existing subway stations and high station operation and management costs, the present invention provides a method for public area layout and facility configuration based on the station passenger and alighting volume, classifies the stations according to the station's super peak hour passenger and alighting volume, and determines the overall layout of the station's public areas for different station levels, and determines the column span size and layout to achieve a refined design of the public area layout; and adjusts the linkage between the entry and exit gates, security inspection equipment, escalator point cameras and other facilities and the public area layout form and the number of escalator groups, so as to reduce the vacancy rate of public area facilities, reduce the station project investment and the management and maintenance costs during the operation period.

[0005] In order to solve the above problems, according to a first aspect of the present invention, a method for public area layout and facility configuration based on the number of passengers and alighting at a station is provided, comprising the following steps:

[0006] S1. Determine the station classification based on the number of train formations and the number of passengers and alighters during the super peak hour at the station, and calculate the overall layout of the public area and the column span layout of the double-deck island station;

[0007] S2. Determine the width of the station platform according to the station classification determined in S1;

[0008] S3. Determine the number of escalator groups in the public area of ​​the station according to the station classification determined in S1;

[0009] S4. According to the number of escalator groups in the public area of ​​the station determined in S3, determine the number of station entry and exit gate groups, the number of security inspection equipment, and the number of escalator point cameras;

[0010] S5. Determine the number of entry and exit gates based on the super peak hour passenger and alighting volume and super peak hour coefficient of the station. The formula for calculating the number of entry gates is:

[0011]

[0012] Where: N e N is the number of entry gates, rounded up; j K is the number of people entering the station during the morning peak or evening peak hour, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V e The capacity of the entry gate, unit: person / hour / channel;

[0013] The formula for calculating the number of exit gates is:

[0014]

[0015] Where: N x N is the number of exit gates, rounded up; c V is the number of people leaving the station during the morning peak or evening peak, taking the maximum value between the two, unit: person-times / hour; x K is the capacity of the exit gate, unit: person / hour / channel; c is the super peak hour coefficient; T j T is the hourly interval between morning and evening peaks, in minutes; c Passenger clearing time, unit: minute.

[0016] Preferably, the S1 specifically comprises the following steps:

[0017] S1-1. Determine the standard station classification based on the number of train sets and the number of passengers and alighting at the station during the super peak hour. The number of train sets is 4A, 6A and 8A, and the station classification is: first-level station, second-level station and third-level station;

[0018] S1-2. Calculate the column span layout of the public area of ​​the double-deck island station under the 4A marshaling vehicle;

[0019] S1-3. Calculate the column span layout of the public area of ​​the double-deck island station under the 6A marshaling vehicle;

[0020] S1-4: Calculate the column span layout of the public area of ​​the double-deck island station under the 8A train formation.

[0021] Preferably, in S1-2, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 4A marshaling vehicle type is:

[0022] (GZK)1=J*ZK1+

(J-2)+(N-1)

[0023] (GZK)2=(J-1)*ZK1+

(J-2)+(N-1)

[0024] Where: J is the level of the station, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 4 for the 4A train set; (GZK)1 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a level 1 station; (GZK)2 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a level 2 or 3 station; ZK1 is the column span value of the non-paid area of ​​the public area, which can be 10 or 12; ZK2 is the column span value of the paid area of ​​the public area, which can be 9 or 10.

[0025] Preferably, in S1-3, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 6A marshaling vehicle type is:

[0026] (GZK)3=2*J*ZK 1-1 +(N / 2-1)*(ZK 2-1 +ZK 2-2 ) (J≦1)

[0027] (GZK)4=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +(N / 2-1)*ZK 2-2 (J>1)

[0028] Where: J is the station level number, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 6 for the 6A train set; (GZK)3 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a first-level station; (GZK)4 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10.

[0029] Preferably, in S1-4, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 8A marshaling vehicle type is:

[0030] (GZK)5=2*J*ZK 1-1 +(N / 2-1)*ZK 2-1 +N / 2*ZK 2-2 (J≦1)

[0031] (GZK)6=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +

N-(J-1)*2

[0032] Where: J is the station level, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 8 for the 8A train set; (GZK)5 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a first-level station; (GZK)6 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10.

[0033] Preferably, S2 specifically includes the following steps:

[0034] S2-1. Determine the standard value of platform width according to station classification;

[0035] S2-2. Revise the platform width according to the influencing factors and determine the actual value of the station platform width. The actual value calculation formula of the station platform width is:

[0036] TKD=KDB+β

[0037] Where: TKD is the actual value of the station platform width; KDB is the standard value of the platform width for different station levels, which is 10.5m for the first-level station, 11m for the second-level station, and 12m for the third-level station; β is the revised value of the standard platform width, and the value range of β is 0.1-0.5.

[0038] Preferably, in S3, the calculation formula for the number of escalator groups in the public area of ​​the station is:

[0039] LFT=N / 2 -1 (J≦1)

[0040] LFT=N / 2 (J>1)

[0041] Where: LFT is the number of escalator groups in the station building, excluding the number of elevator points; N is the number of train formations, which can be 4, 6 or 8; J is the number of station levels, which can be 1, 2 or 3.

[0042] Preferably, the step S4 specifically includes the following steps:

[0043] S4-1. According to the number of escalator groups in the public area of ​​the station, determine the number and number of entry and exit gates in the station. The formula for calculating the number of entry and exit gates is:

[0044] ZJ=LFT (J≦1)

[0045] ZJ=LFT-1 (J>1)

[0046] Where: ZJ is the number of gates in and out of the station; LFT is the number of escalators in the station building, excluding the number of elevator locations; J is the level of the station, which can be 1, 2, or 3;

[0047] S4-2. Determine the number of security inspection equipment based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of security inspection equipment is:

[0048] AJ=ZJ

[0049] Where: AJ is the number of security inspection equipment for station entry; ZJ is the number of gates for station entry and exit;

[0050] S4-3. Determine the number of cameras at escalator points based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of cameras at escalator points is:

[0051] SXT1=LFT*2

[0052] Where: SXT1 is the number of cameras at the escalator location; LFT is the number of escalator groups in the station, excluding the number of elevator locations.

[0053] Preferably, S5 specifically includes the following steps:

[0054] S5-1. Determine the passenger flow during the morning and evening peak hours and the passenger flow intensity during super peak hours;

[0055] S5-2. Determine the station entry and exit gate capacity, peak hour train intervals and passenger clearance time;

[0056] S5-3. Calculate the number of entry gates and exit gates. The formula for calculating the number of entry gates is:

[0057]

[0058] Where: N e N is the number of entry gates, rounded up;j K is the number of people entering the station during the morning peak or evening peak hour, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V e The capacity of the entry gate, unit: person / hour / channel;

[0059] The formula for calculating the number of exit gates is:

[0060]

[0061] Where: N x N is the number of exit gates, rounded up; c K is the number of people leaving the station during the morning peak or evening peak, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V x T is the capacity of the exit gate, unit: person / hour / channel; j T is the hourly interval between morning and evening peaks, in minutes; c Passenger clearing time, unit: minute.

[0062] Preferably, in S5-3,

[0063] The N j At non-transfer stations, the value is the number of passengers boarding during the morning or evening peak hours, whichever is greater. At transfer stations, the value is the maximum number of passengers boarding during the morning or evening peak hours minus the number of passengers boarding during the corresponding peak hour.

[0064] The N c At non-transfer stations, the value is the number of people getting off during the morning peak or evening peak hour, taking the maximum value between the two. At transfer stations, the value is the maximum number of people getting off during the morning and evening peak hours minus the number of people getting off and transferring during the corresponding peak hour. K c It is the super peak hour coefficient, and its value is 1.1-1.4.

[0065] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0066] 1. The method for public area layout and facility configuration based on the station passenger and alighting volume of the present invention classifies stations according to the station's super peak hour passenger and alighting volume, determines the overall layout of the station's public areas for different station grades, and determines the column span size and layout, thereby realizing a refined design of the public area layout.

[0067] 2. The station facility configuration method based on line passenger flow prediction of the present invention realizes the linkage adjustment of facilities such as entry and exit gates, security inspection equipment, escalator point cameras, etc. with the layout of public areas and the number of escalator groups, thereby reducing the vacancy rate of public area facilities, reducing station project investment and management and maintenance costs during the operation period. BRIEF DESCRIPTION OF THE DRAWINGS

[0068] Figure 1 It is a flow chart of the method for public area layout and facility configuration based on the number of passengers and alighters at a station according to the present invention;

[0069] Figure 2 This is a flow chart of the method for calculating the number of entry and exit gates of the present invention. DETAILED DESCRIPTION

[0070] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0071] The present invention discloses a station facility configuration method based on line passenger flow prediction, comprising: Figure 1 As shown, the following steps are included:

[0072] S1. Determine the station classification based on the number of train formations and the number of passengers and alights during the super peak hour of the station, and calculate the overall layout of the public area and the column span layout of the double-deck island station, which specifically includes the following steps:

[0073] S1-1. Based on the number of train sets, which are 4A, 6A and 8A, and the number of passengers and alighters during super peak hours at the station, the overall layout of the public area is determined according to standard specifications, including: single-end or double-end entry and exit modes of the public area that match the number of passengers and alighters, the number of escalator groups and column span dimensions, etc., to determine the standard station classification, which is divided into first-level station, second-level station and third-level station.

[0074] S1-2. Calculate the column span layout of the public area of ​​a double-deck island station under the 4A marshaling vehicle. The calculation formula for the column span layout of the public area of ​​a double-deck island station under the 4A marshaling vehicle is:

[0075] (GZK)1=J*ZK1+

(J-2)+(N-1)

[0076] (GZK)2=(J-1)*ZK1+

(J-2)+(N-1)

[0077] In the formula: J is the level of the station, and its values ​​are 1, 2, or 3; N is the number of train sets in the station, and N is 4 in the 4A train set; (GZK)1 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a first-level station; (GZK)2 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a second-level or third-level station; ZK1 is the column span value of the non-paid area of ​​the public area, and its values ​​are 10 or 12, in meters; ZK2 is the column span value of the paid area of ​​the public area, and its values ​​are 9 or 10, in meters.

[0078] S1-3. Calculate the column span layout of the public area of ​​a double-deck island station under the 6A train. The calculation formula for the column span layout of the public area of ​​a double-deck island station under the 6A train is:

[0079] (GZK)3=2*J*ZK 1-1 +(N / 2-1)*(ZK 2-1 +ZK 2-2 ) (J≦1)

[0080] (GZK)4=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +(N / 2-1)*ZK 2-2 (J>1)

[0081] Where: J is the station level number, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 6 for the 6A train set; (GZK)3 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a first-level station; (GZK)4 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9, unit: meter; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10, in meters.

[0082] S1-4: Calculate the column span layout of the public area of ​​the double-deck island station under the 8A train. The calculation formula for the column span layout of the public area of ​​the double-deck island station under the 8A train is:

[0083] (GZK)5=2*J*ZK 1-1 +(N / 2-1)*ZK 2-1 +N / 2*ZK 2-2 (J≦1)

[0084] (GZK)6=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +

N-(J-1)*2

[0085] Where: J is the station level, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 8 for the 8A train set; (GZK)5 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a first-level station; (GZK)6 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9, unit: meter; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10, in meters.

[0086] S2. Determine the width of the station platform according to the station classification determined in S1, which specifically includes the following steps:

[0087] S2-1. Determine the standard value of platform width according to station classification;

[0088] S2-2. Revise the platform width according to the influencing factors and determine the actual value of the station platform width. The actual value calculation formula of the station platform width is:

[0089] TKD=KDB+β

[0090] Where: TKD is the actual value of the station platform width; KDB is the standard value of the platform width for different station levels, which is 10.5m for the first-level station, 11m for the second-level station, and 12m for the third-level station; β is the revised value of the standard platform width, that is, various factors that affect the platform width, such as insufficient evacuation capacity or insufficient side platform width and other theoretical calculations. β is calculated and determined according to the relevant formula in the "Metro Design Code"; if the calculation redundancy of the side platform width is greater than 50%, it can be taken in the range of 0.1-0.5.

[0091] S3. According to the station classification determined in S1, determine the number of escalator groups in the public area of ​​the station. The calculation formula for the number of escalator groups is:

[0092] LFT=N / 2 -1 (J≦1)

[0093] LFT=N / 2 (J>1)

[0094] Where: LFT is the number of escalator groups in the station building, excluding the number of elevator points; N is the number of train formations, which can be 4, 6 or 8; J is the number of station levels, which can be 1, 2 or 3.

[0095] S4. According to the number of escalator groups in the public area of ​​the station determined in S3, the number of station entry and exit gate groups, the number of security inspection equipment and the number of escalator point cameras are determined, which specifically includes the following steps:

[0096] S4-1. According to the number of escalator groups in the public area of ​​the station, determine the number and number of entry and exit gates in the station. The formula for calculating the number of entry and exit gates is:

[0097] ZJ=LFT (J≦1)

[0098] ZJ=LFT-1 (J>1)

[0099] Where: ZJ is the number of entry and exit gates; LFT is the number of escalators in the station building, excluding the number of elevator locations; J is the number of levels of the station, with values ​​of 1, 2, or 3.

[0100] S4-2. Determine the number of security inspection equipment based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of security inspection equipment is:

[0101] AJ=ZJ

[0102] Where: AJ is the number of entry security inspection equipment groups, ZJ is the number of entry and exit gate groups.

[0103] S4-3. Determine the number of cameras at escalator points based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of cameras at escalator points is:

[0104] SXT1=LFT*2

[0105] Where: SXT1 is the number of cameras at the escalator location; LFT is the number of escalator groups in the station, excluding the number of elevator locations.

[0106] S5. Determine the number of entry and exit gates based on the super peak hour passenger and alighting volume and super peak hour coefficient of the station. Figure 2 As shown, S5 specifically includes the following steps:

[0107] S5-1. Determine the passenger flow of the morning and evening peak hours and the passenger flow intensity of the super peak hours: the passenger flow of the morning and evening peak hours is the maximum value of the passenger flow of the morning and evening peak hours, and the passenger flow intensity of the super peak hours is calculated by the super peak hour coefficient K. c express.

[0108] S5-2. Determine the capacity of the station entrance and exit gates, the running interval during peak hours, and the passenger clearance time: the capacity of the station entrance and exit gates is the maximum number of passengers passing through the station entrance and exit gates per unit time; the running interval during peak hours is equal to the peak time divided by the number of trains during peak hours; the passenger clearance time value is provided by the specific passenger flow report.

[0109] S5-3. Calculate the number of entry gates and exit gates. The formula for calculating the number of entry gates is:

[0110]

[0111] Where: N e N is the number of entry gates, rounded up; j K is the number of people entering the station during the morning peak or evening peak hour, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V e The capacity of the entry gate, unit: person / hour / channel;

[0112] The formula for calculating the number of exit gates is:

[0113]

[0114] Where: N x N is the number of exit gates, rounded up; c is the number of people leaving the station during the morning peak or evening peak, taking the maximum value between the two, unit: person-times / hour; K c is the super peak hour coefficient; V x T is the capacity of the exit gate, unit: person / hour / channel; j T is the hourly interval between morning and evening peaks, in minutes; c Passenger clearing time, unit: minute.

[0115] Where N j At non-transfer stations, the value is the number of passengers boarding during the morning or evening peak hours, whichever is greater. At transfer stations, the value is the maximum number of passengers boarding during the morning or evening peak hours minus the number of passengers boarding during the corresponding peak hour.

[0116] N c At non-transfer stations, the value is the number of people getting off during the morning peak or evening peak hour, taking the maximum value between the two. At transfer stations, the value is the maximum number of people getting off during the morning and evening peak hours minus the number of people getting off and transferring during the corresponding peak hour. K c As the super peak hour coefficient, it refers to the ratio of the average passenger flow during the super peak period to the average passenger flow during the peak hour per unit time, and the value is 1.1-1.4.

[0117] The present invention is based on the public area layout and facility configuration method of the station passenger and alighting volume. The station is graded and classified according to the station's super peak hour passenger and alighting volume, and the overall layout of the station's public area is determined for different station grades, and the column span size and layout are determined to achieve a refined design of the public area layout; and the station entry and exit gates, security inspection equipment, escalator point cameras and other facilities are linked to the public area layout form and the number of escalator groups to reduce the vacancy rate of public area facilities, reduce the station project investment and the management and maintenance costs during the operation period.

[0118] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for public area layout and facility configuration based on the number of passengers and alighting at a station, characterized in that: The following steps are involved: S1. Determine the station classification based on the number of train formations and the number of passengers and alighters during the super peak hour of the station, and calculate the overall layout of the public area and the column span layout of the double-deck island station; S2. Determine the width of the station platform according to the station classification determined in S1; S3. Determine the number of escalator groups in the public area of ​​the station according to the station classification determined in S1; S4. According to the number of escalator groups in the public area of ​​the station determined in S3, determine the number of station entry and exit gate groups, the number of security inspection equipment, and the number of escalator point cameras; S5. Determine the number of entry and exit gates based on the super peak hour passenger and alighting volume and super peak hour coefficient of the station. The formula for calculating the number of entry gates is: Where: N e N is the number of entry gates, rounded up; j K is the number of people entering the station during the morning peak or evening peak hour, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V e The capacity of the entry gate, unit: person / hour / channel; The formula for calculating the number of exit gates is: Where: N x N is the number of exit gates, rounded up; c V is the number of people leaving the station during the morning peak or evening peak, taking the maximum value between the two, unit: person-times / hour; x K is the capacity of the exit gate, unit: person / hour / channel; c is the super peak hour coefficient; T j The hourly intervals between morning and evening peaks, in minutes; T c Passenger clearing time, unit: minute.

2. The station facility configuration method based on line passenger flow prediction according to claim 1 is characterized in that: The S1 specifically includes the following steps: S1-1. Determine the standard station classification based on the number of train sets and the number of passengers and alighting at the station during the super peak hour. The number of train sets is 4A, 6A and 8A, and the station classification is: first-level station, second-level station and third-level station; S1-2. Calculate the column span layout of the public area of ​​the double-deck island station under the 4A marshaling vehicle; S1-3. Calculate the column span layout of the public area of ​​the double-deck island station under the 6A marshaling vehicle; S1-4: Calculate the column span layout of the public area of ​​the double-deck island station under the 8A train formation.

3. The station facility configuration method based on line passenger flow prediction according to claim 2 is characterized in that: In S1-2, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 4A marshaling vehicle is: (GZK)1=J*ZK1+【(J-2)+(N-1)】*ZK2(J≦1) (GZK)2=(J-1)*ZK1+【(J-2)+(N-1)】*ZK2(J>1) Where: J is the level of the station, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 4 for the 4A train set; (GZK)1 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a level 1 station; (GZK)2 represents the column span layout of the public area of ​​the station under the 4A train set when the station is a level 2 or 3 station; ZK1 is the column span value of the non-paid area of ​​the public area, which can be 10 or 12; ZK2 is the column span value of the paid area of ​​the public area, which can be 9 or 10.

4. The station facility configuration method based on line passenger flow prediction according to claim 2 is characterized in that: In S1-3, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 6A marshaling vehicle is: (GZK)3=2*J*ZK 1-1 +(N / 2-1)*(ZK 2-1 +ZK 2-2 )(J≦1)(GZK)4=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +(N / 2-1)*ZK 2-2 (J>1) where: J is the station level number, which can be 1, 2, or 3; N is the number of train sets at the station, and N is 6 for the 6A train set; (GZK)3 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a first-level station; (GZK)4 represents the column span layout of the public area of ​​the station under the 6A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10.

5. The station facility configuration method based on line passenger flow prediction according to claim 2, characterized in that: In S1-4, the calculation formula for the column span layout of the public area of ​​the double-deck island station under the 8A marshaling vehicle is: (GZK)5=2*J*ZK 1-1 +(N / 2-1)*ZK 2-1 +N / 2*ZK 2-2 (J≦1)(GZK)6=2*(J-1)*ZK 1-1 +N / 2*ZK 2-1 +【N-(J-1)*2】*ZK 2-2 (J>1) where: J is the station level number, with values ​​of 1, 2, and 3; N is the number of train sets at the station, and N is 8 for the 8A train set; (GZK)5 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a first-level station; (GZK)6 represents the column span layout of the public area of ​​the station under the 8A train set when the station is a second-level or third-level station; ZK 1-1 The column span value of the public area and non-paid area can be 8, 10 or 12; ZK 2-1 The column span value of the staircase section in the public area and the paid area is 9; ZK 2-2 It is the column span value of the stairwell area in the public area and paid area, which can be 8 or 10.

6. The station facility configuration method based on line passenger flow prediction according to claim 1, characterized in that: The S2 specifically includes the following steps: S2-1. Determine the standard value of platform width according to station classification; S2-2. Revise the platform width according to the influencing factors and determine the actual value of the station platform width. The actual value calculation formula of the station platform width is: TKD=KDB+β Where: TKD is the actual value of the station platform width; KDB is the standard value of the platform width for different station levels, which is 10.5m for the first-level station, 11m for the second-level station, and 12m for the third-level station; β is the revised value of the standard platform width, and the value range of β is 0.1-0.

5.

7. The station facility configuration method based on line passenger flow prediction according to claim 1, characterized in that: In S3, the calculation formula for the number of escalator groups in the public area of ​​the station is: LFT=N / 2-1(J≦1) LFT=N / 2(J>1) Where: LFT is the number of escalator groups in the station building, excluding the number of elevator points; N is the number of train formations, which can be 4, 6 or 8; J is the number of station levels, which can be 1, 2 or 3.

8. The station facility configuration method based on line passenger flow prediction according to claim 7, characterized in that: The S4 specifically includes the following steps: S4-1. According to the number of escalator groups in the public area of ​​the station, determine the number and number of entry and exit gates in the station. The formula for calculating the number of entry and exit gates is: ZJ=LFT(J≦1) ZJ=LFT-1(J>1) Where: ZJ is the number of gates in and out of the station; LFT is the number of escalators in the station building, excluding the number of elevator locations; J is the level of the station, which can be 1, 2, or 3; S4-2. Determine the number of security inspection equipment based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of security inspection equipment is: AJ=ZJ Where: AJ is the number of security inspection equipment for station entry; ZJ is the number of gates for station entry and exit; S4-3. Determine the number of cameras at escalator points based on the number of escalator groups in the public area of ​​the station. The calculation formula for the number of cameras at escalator points is: SXT1=LFT*2 Where: SXT1 is the number of cameras at the escalator location; LFT is the number of escalator groups in the station, excluding the number of elevator locations.

9. The station facility configuration method based on line passenger flow prediction according to claim 8, characterized in that: The S5 specifically includes the following steps: S5-1. Determine the passenger flow during the morning and evening peak hours and the passenger flow intensity during super peak hours; S5-2. Determine the station entry and exit gate capacity, peak hour train intervals and passenger clearance time; S5-3. Calculate the number of entry gates and exit gates. The formula for calculating the number of entry gates is: Where: N e N is the number of entry gates, rounded up; j K is the number of people entering the station during the morning peak or evening peak hour, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V e The capacity of the entry gate, unit: person / hour / channel; The formula for calculating the number of exit gates is: Where: N x N is the number of exit gates, rounded up; c K is the number of people leaving the station during the morning peak or evening peak, taking the maximum value between the two, unit: person-times / hour; c is the super peak hour coefficient; V x T is the capacity of the exit gate, unit: person / hour / channel; j T is the hourly interval between morning and evening peaks, in minutes; c Passenger clearing time, unit: minute.

10. The station facility configuration method based on line passenger flow prediction according to claim 9, characterized in that: In S5-3, The N j At non-transfer stations, the value is the maximum number of boardings during the morning or evening peak hours; at transfer stations, the value is the maximum number of boardings during the morning or evening peak hours minus the number of boardings during the corresponding peak hour. The N c At non-transfer stations, the value is the number of people getting off during the morning peak or evening peak hour, taking the maximum value between the two. At transfer stations, the value is the maximum number of people getting off during the morning and evening peak hours minus the number of people getting off and transferring during the corresponding peak hour. K c It is the super peak hour coefficient, and its value is 1.1-1.4.

Citation Information

Patent Citations

  • Station passenger flow pressure testing method

    CN109492935A

  • Subway station passenger flow grading alarm method based on regional linkage

    CN110942411A

  • Urban rail transit system transport capacity load assessment method

    CN113496353A

  • Underground first-layer lower pull-in side type station structure

    CN115787708A

  • Underground first-layer flat layer station entering side type station structure

    CN115787709A

Cited By

  • Station layout method, device and equipment based on commuting trip, medium and product

    CN119228100A