Multi-objective optimization configuration method for energy storage power station containing various controllable loads
By including multiple controllable load-optimized configuration methods in the grid energy storage planning, the problems of high computational complexity and insufficient accuracy in the existing technology are solved, and efficient utilization of energy storage systems and on-site new energy are achieved. Consumption reduces the cost of power grid operation.
Patent Information
- Application Number
- CN202411517006.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-29
- Publication Date
- 2025-02-18
- Estimated Expiration
- 2044-10-29
AI Technical Summary
The existing grid energy storage planning methods are difficult to effectively incorporate controllable loads, resulting in high computational complexity and insufficient accuracy, and the inability to increase the consumption rate of renewable energy and reduce the operating costs of the grid.
A multi-objective optimization configuration method for energy storage power stations containing multiple controllable loads is proposed. By establishing power grid and energy storage power station models, multi-objective optimization goals and constraints are determined, and non-convex optimization problems are transformed into second-order cone planning problems. , POA-GWO-CSO optimization algorithm is used for solution.
The controllable load was implemented into the energy storage power station model, which improved the efficient utilization of energy storage systems and the on-site absorption of new energy, reduced the difficulty of model solving, improved the solution efficiency and accuracy, and optimized the power grid operation cost and energy storage. Power station configuration cost.
Smart Images

Figure CN119482604A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power grid energy storage planning, and in particular to a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads. Background Art
[0002] With the increasingly tense global energy supply situation and the continuous aggravation of environmental pollution problems, energy efficiency has become a core issue in modern society. As a key technology to improve energy efficiency, energy storage power stations have gradually received widespread attention. However, traditional grid energy storage planning often ignores the influencing factors of controllable loads, especially temperature-controlled loads and industrial loads, which poses new challenges to the optimal configuration of energy storage power stations. Controllable loads refer to the types of loads in the power system that can flexibly adjust their power consumption according to the needs of the power grid, market prices or other factors. Reasonable management of controllable loads can effectively improve the flexibility of energy use and reduce fluctuations in power supply demand. In recent years, with the widespread application of renewable energy, such as wind power and solar energy, its intermittent and volatile nature has further increased the instability of the power grid.
[0003] Therefore, how to optimize the configuration of energy storage power stations to improve the absorption rate of renewable energy and ensure the balance between user demand and the power grid has become one of the key research issues. At the same time, for the optimal configuration of power grid energy storage systems, traditional methods such as mixed integer linear programming (MILP) can solve nonlinear problems, but they have problems such as high computational complexity and insufficient accuracy. Convex programming methods, especially second-order cone programming (SOCP), have become a method for solving such problems due to their advantages in solution speed and accuracy.
[0004] Therefore, the present invention proposes a multi-objective optimization configuration method for an energy storage power station including a variety of controllable loads, aiming to achieve efficient utilization of energy storage and local consumption of renewable energy by improving the solution algorithm, and optimize the grid operation cost and energy storage power station configuration cost under the premise of ensuring user demand and grid balance.
[0005] 1. Patent document CN116345507B discloses a method and system for multi-objective optimization configuration of energy storage power station capacity that adapts to variable energy storage cycles. The above patent determines the weights of multi-objective Pareto optimization set elements based on fuzzy set functions, and outputs the multi-objective optimization capacity values of energy storage power stations in an orderly manner, providing an effective method and decision-making support for the multi-objective optimization configuration of energy storage power station capacity. However, the above patent cannot incorporate controllable loads into the energy storage power station model.
[0006] 2. Patent document CN111539086B discloses a method and system for multi-point layout of energy storage power stations. The above patent achieves the goal of maximizing the optimization effect of the energy storage power station layout, comprehensively considers factors such as the constraints of the multi-point layout of energy storage, and meets the different configuration requirements of the power system for energy storage power stations. However, the above patent cannot convert the original problem into a second-order cone programming problem through relaxation and linearization methods.
[0007] 3. Patent document CN113922396B discloses a method and terminal for configuring an energy storage power station to improve the immunity of the power grid to voltage sags. The above patent combines the optimization of the configuration of the energy storage power station with the control of voltage sags to construct an optimal energy storage power station layout and capacity determination plan to improve the immunity of the power grid to voltage sags and improve the voltage quality. However, the above patent cannot propose an algorithm for multi-objective optimization configuration of energy storage power stations.
[0008] 4. Patent document CN113792911B discloses a method and system for double-layer collaborative optimization configuration of energy storage capacity of a photovoltaic storage system. The above patent realizes the reasonable and effective configuration of energy storage capacity of the photovoltaic storage system under the influence of dual uncertainties, but the above patent cannot realize the improvement of optimization strategy and response mechanism.
[0009] In summary, the above patents cannot incorporate controllable loads into the energy storage power station model, transform the original problem into a second-order cone programming problem through relaxation and linearization methods, propose algorithms for multi-objective optimization configuration of energy storage power stations, and improve optimization strategies and response mechanisms, resulting in high computational complexity, insufficient accuracy, and failure to improve the absorption rate of renewable energy and high grid operation costs;
[0010] To this end, this application proposes a method for multi-objective optimization configuration of energy storage power stations containing multiple controllable loads that can incorporate controllable loads into the energy storage power station model, transform the original problem into a second-order cone programming problem through relaxation and linearization methods, propose an algorithm for multi-objective optimization configuration of energy storage power stations, and improve the optimization strategy and response mechanism. Summary of the invention
[0011] The purpose of the present invention is to provide a multi-objective optimization configuration method for an energy storage power station including a variety of controllable loads, so as to solve the technical problems proposed in the above background technology that the controllable loads cannot be incorporated into the energy storage power station model, the original problem is converted into a second-order cone programming problem through relaxation and linearization methods, an algorithm for multi-objective optimization configuration of energy storage power stations and improved optimization strategies and response mechanisms are proposed, resulting in high computational complexity, insufficient accuracy, inability to improve the absorption rate of renewable energy and high grid operation costs.
[0012] To achieve the above object, the present invention provides the following technical solution: a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, the configuration method comprising the following steps:
[0013] S1. Establish a power grid model and an energy storage power station model;
[0014] S2. Determine the multi-objective optimization goal: the optimization goal is to minimize the grid operation cost and the energy storage power station configuration cost;
[0015] S3. Set constraints: grid node voltage and line current constraints, power balance constraints, grid branch flow constraints, energy storage battery capacity and energy rate constraints, energy storage battery state of charge constraints and voltage offset constraints;
[0016] S4. Convert the non-convex optimization problem into a second-order cone programming (SOCP) problem;
[0017] S4. Use POA-GWO-CSO optimization algorithm for optimization solution.
[0018] Preferably, the power grid model includes temperature control load and industrial load, wherein the temperature control load model is based on the thermal characteristics of the building, taking into account indoor and outdoor temperature, air conditioning power and wall heat capacity parameters; the industrial load model is based on the importance of the equipment and the user's wishes, and divides the load level according to energy consumption and adjustability;
[0019] The energy storage power station model is based on energy storage equipment. It takes into account the charging and discharging power, charging and discharging efficiency and capacity operating parameters of the energy storage equipment to establish a full life cycle cost model, including the purchase cost, installation cost, operation and maintenance cost and residual value recovery cost of the energy storage power station.
[0020] Preferably, the power grid operation cost includes power purchase cost, network loss cost, power generation cost and load cost; the energy storage power station cost includes purchase cost, installation cost, operation and maintenance cost and residual value recovery.
[0021] Preferably, the power purchase cost in the power grid operation cost is calculated based on the power purchase price and interactive power between the system and the upper-level power grid;
[0022] The network loss cost is calculated based on the voltage difference between the grid nodes and the line conductance;
[0023] The power generation cost is calculated based on the fuel cost and operation and maintenance cost of the micro gas turbine;
[0024] The load cost is dynamically calculated based on the regulation status of the controllable load.
[0025] Preferably, the purchase cost of the energy storage power station is amortized through time value, taking into account the benchmark interest rate and economic life, to optimize the comprehensive configuration cost within the planning period;
[0026] The installation cost and operation and maintenance cost are calculated by the unit capacity installation fee and the operation and maintenance coefficient respectively, and the average annual decline coefficient of the equipment is taken into account.
[0027] Preferably, the second-order cone programming (SOCP) problem uses a second-order cone relaxation method (SOCR) to convert non-convex nonlinear constraints into a second-order cone programming (SOCP) problem, and the calculation accuracy and speed are guaranteed by relaxation processing. The second-order cone programming (SOCP) model is used to optimize the configuration scheme of the energy storage power station, optimize the power balance constraint, power flow constraint and energy storage battery state of charge constraint of the power grid under the premise of ensuring the global optimal solution. The second-order cone relaxation method (SOCR) relaxes the power grid power flow equation and calculates the error gap to ensure that the optimal solution is consistent with the accuracy requirement of the original problem. When the error gap reaches the set accuracy, the optimal solution is considered to be equivalent to the optimal solution of the original problem.
[0028] Preferably, the POA-GWO-CSO optimization algorithm principle is as follows:
[0029] POA simulates the local search behavior of pelicans, updating the population position through the phase of moving toward prey and the phase of skimming over the water surface;
[0030] GWO introduces the gray wolf group strategy to perform global search to avoid falling into local optimality;
[0031] CSO optimizes the population position through horizontal and vertical cross-updates to avoid premature convergence.
[0032] Preferably, the specific implementation steps of the POA-GWO-CSO optimization algorithm are as follows:
[0033] Step 1, set the population size and maximum number of iterations;
[0034] Step 2: Collect the instantaneous power flow data of the power system, input it into the model, calculate the fitness value of the pelican population, and thus determine the initial value of the objective function;
[0035] Step 3: Randomly generate prey;
[0036] Step 4: Use the improved pelican position formula to update the pelican position in the first stage;
[0037] Step 5: Bring the position in step 4 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0038] Step 6: Update the position of the i-th pelican in the j-th dimension in the second stage;
[0039] Step 7: Bring the position in step 6 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0040] Step 8: Determine whether the maximum number of iterations is met. If yes, jump to the next step; otherwise, jump to step 3.
[0041] Step 9: Determine the position value of the pelican based on the final fitness function value.
[0042] Preferably, the optimization solution steps are as follows:
[0043] a. Initialize the algorithm population size and number of iterations, collect instantaneous power flow data of the power grid, and calculate the fitness;
[0044] b. Update the location of the pelican population, conduct local and global searches, and gradually approach the optimal solution through iteration;
[0045] c. Determine the improvement of the fitness function until the number of iterations is met or the optimal solution is found.
[0046] Preferably, during the execution of the optimization method, the charging and discharging constraints of the energy storage battery are taken into account to ensure that the charge state of the energy storage battery during the scheduling period is not lower than the set lower limit value; the voltage offset constraints of the power grid nodes are taken into account, the deviation of the node voltage is kept within the allowable range, and the average voltage offset degree of the power grid meets the set maximum allowable value.
[0047] Compared with the prior art, the present invention has the following beneficial effects:
[0048] 1. The present invention incorporates controllable loads into the energy storage power station model and fully explores the coordination capabilities of multiple resources to propose an energy storage power station model based on the flexibility of controllable loads and grid balance. While meeting user needs and grid balance, it achieves efficient utilization of the energy storage system and local consumption of new energy.
[0049] 2. The present invention transforms the original problem into a second-order cone programming problem by relaxation and linearization, which significantly reduces the difficulty of solving the model and improves the efficiency and accuracy of the solution;
[0050] 3. The present invention proposes an algorithm for multi-objective optimization configuration of energy storage power stations, which solves the problems of premature convergence, insufficient optimization range, low solution accuracy, slow response speed, etc. in traditional algorithms when processing multi-objective optimization of energy storage power stations;
[0051] 4. The present invention improves the optimization strategy and response mechanism through the POA-GWO-CSO algorithm, and quickly obtains the accurate solution with the lowest power grid operation cost and the lowest energy storage power station configuration cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 It is a schematic diagram of the optimization configuration process of the present invention. DETAILED DESCRIPTION
[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0054] See also Figure 1 , an embodiment provided by the present invention: a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, the configuration method comprising the following steps:
[0055] S1. Establish a power grid model and an energy storage power station model;
[0056] S2. Determine the multi-objective optimization goal: the optimization goal is to minimize the grid operation cost and the energy storage power station configuration cost;
[0057] S3. Set constraints: grid node voltage and line current constraints, power balance constraints, grid branch flow constraints, energy storage battery capacity and energy rate constraints, energy storage battery state of charge constraints and voltage offset constraints;
[0058] S4. Convert the non-convex optimization problem into a second-order cone programming (SOCP) problem;
[0059] S4, using POA-GWO-CSO optimization algorithm for optimization solution;
[0060] The optimization solution steps are as follows:
[0061] a. Initialize the algorithm population size and number of iterations, collect instantaneous power flow data of the power grid, and calculate the fitness;
[0062] b. Update the location of the pelican population, conduct local and global searches, and gradually approach the optimal solution through iteration;
[0063] c. Determine the improvement of the fitness function until the number of iterations is met or the optimal solution is found;
[0064] During the execution of the optimization method, the charging and discharging constraints of the energy storage battery are taken into account to ensure that the state of charge of the energy storage battery during the scheduling period is not lower than the set lower limit value; the voltage offset constraints of the power grid nodes are taken into account, the deviation of the node voltage is kept within the allowable range, and the average voltage offset degree of the power grid meets the set maximum allowable value;
[0065] Furthermore, the following conditions are included when setting constraints:
[0066] (1) Grid node voltage and line current constraints
[0067] When the power grid is operating normally, the voltage at each node cannot exceed the specified upper and lower limits. At the same time, due to the limited cross-section of the line, in order to ensure the safety of the line, its allowable current carrying capacity is subject to certain restrictions:
[0068]
[0069] Where: U max , U min are the upper and lower limits of node voltage respectively; U min It represents the maximum current carrying capacity of the line between node i and node j. The allowable current carrying capacity of the line can be uniformly set to a fixed value.
[0070] (2) Power balance constraints
[0071] ∑(P ES +P DG +P ESS )=∑(P load +P loss )
[0072] Where: P ES , P DG , P ESS are the grid power, distributed power and energy storage system grid-connected power respectively; P load , P loss They are system load power and system active power loss respectively.
[0073] (3) Power Flow Constraints on Grid Branches
[0074] The data model of the branch power flow model is as follows:
[0075]
[0076]
[0077]
[0078]
[0079] Where: v m,t With v n,t are the squares of the voltage amplitudes at nodes m and n respectively; i mn,t is the square of the current amplitude of line mn; r nm and X mn are the resistance and reactance of line mn respectively; P in,n,t With Q in,n,t are respectively the active / reactive power injected into node n; P mn,t With Q mn,t are the active / reactive power on the node m side respectively; l is the child node of node n.
[0080] (4) Energy storage battery capacity and energy rate constraints
[0081]
[0082] Where: They are the upper and lower limits of the rated capacity of the energy storage battery respectively; are the upper and lower limits of the charging and discharging power of the energy storage battery, respectively, and β is the energy rate of the energy storage battery.
[0083] (5) Energy storage battery state of charge constraints
[0084] First, in order to prevent the deep charge and discharge of the battery from affecting the life of the energy storage battery, the SOC range of the energy storage battery should be constrained; and the charge state of the energy storage battery at the beginning and end of a scheduling cycle should be equal to ensure the regulation ability of the energy storage in the next cycle:
[0085]
[0086] Where: It is the upper and lower limits of the charge and discharge depth of the energy storage battery; They are the charge states at the beginning and end of the energy storage battery operation cycle.
[0087] (6) Voltage offset constraint
[0088] One of the important indicators for measuring grid stability is node voltage fluctuation. In order to ensure grid stability, the node voltage deviation should be kept within a certain range, as shown below:
[0089]
[0090]
[0091] Where: U lev is the average voltage deviation degree during the power grid operation cycle; N is the number of load nodes; T is the statistical duration of the calculation cycle; U i,(t) , are the voltage of the i-th node at time t and the reference voltage; ΔU i,max is the maximum allowable voltage deviation value of the i-th node; It is the maximum value allowed for the average voltage deviation during the grid operation cycle.
[0092] See also Figure 1, an embodiment provided by the present invention: a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, wherein the power grid model includes temperature control load and industrial load, wherein the temperature control load model is based on the thermal characteristics of the building, taking into account indoor and outdoor temperatures, air conditioning power and wall heat capacity parameters; the industrial load model is based on the importance of the equipment and the user's willingness, and divides the load level according to energy consumption and adjustability;
[0093] The energy storage power station model is based on energy storage equipment, taking into account the charging and discharging power, charging and discharging efficiency and capacity operating parameters of the energy storage equipment, and establishing a full life cycle cost model, including the purchase cost, installation cost, operation and maintenance cost and residual value recovery cost of the energy storage power station;
[0094] The grid operation cost includes power purchase cost, network loss cost, power generation cost and load cost; the energy storage power station cost includes purchase cost, installation cost, operation and maintenance cost and residual value recovery;
[0095] The power purchase cost in the power grid operation cost is calculated based on the power purchase price and interactive power between the system and the upper-level power grid;
[0096] The network loss cost is calculated based on the voltage difference between the grid nodes and the line conductance;
[0097] The power generation cost is calculated based on the fuel cost and operation and maintenance cost of the micro gas turbine;
[0098] The load cost is dynamically calculated based on the regulation status of the controllable load;
[0099] The purchase cost of the energy storage power station is amortized through time value, taking into account the benchmark interest rate and economic life, to optimize the comprehensive configuration cost within the planning period;
[0100] The installation cost and operation and maintenance cost are calculated by the installation cost per unit capacity and the operation and maintenance coefficient, respectively, taking into account the average annual decline coefficient of the equipment;
[0101] Furthermore, the power grid temperature control load model is first constructed as shown in the following formula:
[0102] T min ≤T t ≤T max
[0103] 0≤P Tem,t ≤P max
[0104]
[0105] Where, T min and T max Indicates the lower and upper limits of the comfortable temperature; T t represents the indoor temperature; C represents the wall heat capacity; Touut,t Indicates outdoor temperature; C GP Indicates the air conditioning energy efficiency ratio; P TEM,t represents the power consumption of the air conditioner at time t; P max Indicates the rated power of the air conditioner; R wa and R w represents the thermal resistance of the wall and window; k represents the window transmittance; Indicates the intensity of sunlight; Q in Indicates the heating power of the internal heat source; F w Indicates the exterior window area;
[0106] Secondly, construct the industrial load model as shown below:
[0107] ψ1=(1-a)ζ
[0108] Where: a is the importance of the equipment, which is related to the actual process; ζ is the willingness of the user in the processing plant;
[0109]
[0110]
[0111] Where: L low , L high In order to distinguish the minimum and maximum values of the levels of low, medium and high importance of equipment in the process, the equipment is divided into L1-L according to its importance in the process. 10 There are 10 levels in total, L1 is the device that can be interrupted at any time, L 10 For non-interruptible devices; P low , P high In order to distinguish the minimum and maximum energy consumption of low-energy-consuming equipment, medium-energy-consuming equipment and high-energy-consuming equipment, L con is the monthly energy consumption of the equipment, the data can be obtained from actual questionnaire survey;
[0112] The operating costs of the power grid include power purchase costs, network loss costs, power generation costs and load costs, as follows:
[0113] (1) Electricity purchase cost C grid
[0114]
[0115] Where: It represents the electricity price that the system purchases from the upper power grid during period t; It represents the interactive power between the system and the upper power grid during the period t; Δt represents the length of the segmented scheduling time;
[0116] (2) Network loss cost C loss
[0117]
[0118] Where: N node is the total number of nodes; is the voltage amplitude of nodes j and k during period t; is the tail node set with node j as the head node; G jk is the conductance between node j and node k; is the phase angle difference between the voltages at nodes j and k during period t;
[0119] (3) Power generation cost C DG
[0120]
[0121] Where: Ω MG Assemble for micro gas turbine unit; and Unit fuel for MG
[0122] Cost and unit operation and maintenance cost; is the power generation of micro gas turbine i during period t;
[0123] η i is the conversion efficiency of micro gas turbine i;
[0124] (4) Load cost C L0
[0125]
[0126] Where: P in,t It represents the energy consumption of industrial load at time t;
[0127] Energy storage power station model
[0128] Among the various equipment available for energy storage power stations, battery (SB) energy storage technology is mature and widely used, and is the most common energy storage device in the power grid. The remaining capacity (SOC) of the battery is an important parameter to characterize the operating status of the battery. The remaining capacity SOC of the battery at time t is SB (t) and the remaining power S at time t-1 SB The relationship between (t-1) and (t-1) in the case of charging and discharging is shown below. This relationship needs to be taken into account in the optimization model, and the energy storage output and energy storage capacity are first regarded as control variables;
[0129] When the energy storage power station is in charging state:
[0130] S SB (t) = S SB (t-1)+η ch Pch (t)Δt-λQ SB When the energy storage power station is in the discharging state:
[0131]
[0132] Where: P ch (t) is the charging power of the battery at time t; P dis (t) is the discharge power of the battery at time t; η ch is the charging efficiency of the battery; η dis is the discharge efficiency of the battery; λ is the self-discharge rate of the battery; Q SB is the capacity of the battery; Δt is the time interval;
[0133] (1) Purchase cost of energy storage power station
[0134] The purchase cost of the energy storage power station, as the main part of the comprehensive configuration cost, directly affects the economic efficiency of the optimization configuration model. The full life cycle cost model of the energy storage power station is used to measure the comprehensive configuration cost of the system, so that the cost can be amortized within the planning cycle, making the model more objective. The purchase cost of the energy storage power station is shown in the following formula, which takes into account the time value of the capital cost:
[0135]
[0136] Where: D is the planned life cycle of the energy storage power station; N is the number of energy storage power stations, each of which is connected to a node in the power grid and operated in parallel; r is the benchmark interest rate, which uses the average social investment rate of return to measure the time value of funds; Q i is the configuration capacity of the i-th energy storage power station, c i is the unit capacity investment cost of the i-th energy storage power station, n i is the number of replacements of the i-th energy storage power station within the planned period, represented by n i =floor(D / d), d is the economic life of the energy storage power station.
[0137] (2) Energy storage power station installation cost
[0138] Generally speaking, the manufacturer who purchases the energy storage power station and the manufacturer who installs the equipment may belong to different manufacturers. Even if they belong to the same manufacturer, the installation of the energy storage power station is a huge project, and its installation costs need to be settled separately. Therefore, the equipment installation cost in the comprehensive optimization configuration cost needs to be considered by establishing a model. The equipment installation cost of the energy storage power station during the planning period is shown in the following formula:
[0139]
[0140] Where: j = 0, 1, ..., ni Indicates the number of installations; is the j-th installation cost of the i-th energy storage power station, a i represents the average annual reduction coefficient of the installation cost of the i-th energy storage power station, C rep,i is the installation cost per unit capacity of the i-th energy storage power station.
[0141] (3) Operation and maintenance costs of energy storage power stations
[0142] The daily operation of energy storage power stations requires investment in operation and maintenance costs including personnel, management, parts replacement, etc. The operation and maintenance costs of energy storage power stations over their entire life cycle are shown in the following formula:
[0143]
[0144] Where: P SB,i (t) is the charging and discharging power of the i-th energy storage power station in period t, P SB,i (t)≥0, the energy storage power station is in the discharging state, P SB,i (t) < 0, the energy storage power station is in charging state; k ch,i is the operation and maintenance cost coefficient of the i-th energy storage station when charging, u i,1 (t) is the energy storage charging coefficient, u 2.i (t) is the energy storage discharge coefficient. When the energy storage is charged, u i,1 (t)=1 and u 2,i (t)=0, when the energy storage is discharged, u i,1 (t) = 0 and u 2,i (t) = 1; k dis,i is the operation and maintenance cost coefficient of the i-th energy storage power station during discharge. The specific calculation method of this coefficient is as follows:
[0145]
[0146]
[0147] Where: N(x) is the maximum number of cycles, which is determined by x, where x is the charge and discharge depth; C in it is the initial fixed investment cost of energy storage; S SB,start is the initial charge state of energy storage; S SB,end It is the state of charge at the end of energy storage; is the maximum remaining power, which is 0.9 times the capacity of the energy storage station; c ch and c dis They are charging and discharging influencing factors respectively. Assuming that each energy storage power station in the optimized configuration adopts the same type of energy storage equipment, the above coefficients are all constants.
[0148] (4) Equipment residual value recovery
[0149] When an energy storage power station is completed within its life cycle, the remaining equipment has a certain residual value that can be recovered. This residual value can be accrued as a benefit in the comprehensive optimization configuration cost. The calculation method is as follows:
[0150]
[0151] Where: C 4,i is the residual value of the i-th energy storage power station, which can be considered to be related to the capacity of the energy storage power station, and C 4,i The calculation method of is as follows:
[0152] C 4,i =k val Q i
[0153] Where: k val is the residual value coefficient of the energy storage power station.
[0154] See also Figure 1 , an embodiment provided by the present invention: a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, wherein the second-order cone programming (SOCP) problem is to convert the non-convex nonlinear constraint condition into a second-order cone programming (SOCP) problem by using the second-order cone relaxation method (SOCR), and the calculation accuracy and speed are guaranteed by relaxation processing, and the second-order cone programming (SOCP) model is used to optimize the configuration scheme of the energy storage power station under the premise of ensuring the global optimal solution, and optimize the power balance constraint, power flow constraint and energy storage battery state of charge constraint of the power grid, and the second-order cone relaxation method (SOCR) is used to relax the power grid power flow equation, and calculate the error gap to ensure that the optimal solution is consistent with the accuracy requirement of the original problem. When the error gap reaches the set accuracy, it is considered that the optimal solution is equivalent to the optimal solution of the original problem;
[0155] Furthermore, the solution model with the lowest grid operation cost and the lowest energy storage power station configuration cost is obtained:
[0156]
[0157] The grid-side modeling of the above model is mainly related to the power grid branch flow model. However, there are non-convex nonlinear constraints in the above model. It is difficult to guarantee the global optimal solution for the mathematical optimization model containing such constraints. Therefore, the constraint condition can be processed by the second-order cone relaxation method (SOCR). The second-order cone programming (SOCP) model after SOCR can be used as a further generalization of the linear programming model. It is essentially a convex programming, and its standard form is as follows:
[0158] F socp =min{cT x|Ax=b,x∈H}
[0159] Where: x is the n-dimensional decision variable; b, c, and A refer to coefficient constants; c T x is a linear function about x; H is a second-order cone or a rotated second-order cone, and its specific form is as follows:
[0160] Second-order cone:
[0161] Rotate a second-order cone:
[0162] Among them, R N represents an N-dimensional real number, N represents the dimension, x i represents the i-th dimension variable;
[0163] The SOCP model can obtain better solution results while ensuring the calculation speed and accuracy. Based on the characteristics of the SOCP model, the mathematical model of the branch flow model is transformed into the following form:
[0164] ||[2 Pmn,t 2Q mn,t i mn,t -v m,t ] T ||2≤i mn,t +v m,t
[0165] Before SOCP, C original is the original non-convex feasible domain. After SOCR, C original will be expanded to include the original C original The convex feasible region C SOC , thus transforming the original power flow equation into a convex form. SOC The optimal solution S obtained in is a lower bound solution of the original problem, and if the optimal solution S is also the original feasible domain C original Then, the optimal solution to the original problem can be found by using the branch and bound method or cutting plane method in the algorithm toolboxes such as GUROBI, CPLEX and MOSEK to solve the proposed problem, further ensuring the accuracy and efficiency of the model solution.
[0166] To verify the accuracy of the above model, it is necessary to further calculate the error gap of SOCR. The calculation method of the error gap after relaxation is as follows:
[0167]
[0168] When the error gap reaches the set accuracy, the corresponding optimal solution can be considered to be equivalent to the actual optimal solution.
[0169] See also Figure 1 , an embodiment provided by the present invention: a multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, the POA-GWO-CSO optimization algorithm principle is as follows:
[0170] POA simulates the local search behavior of pelicans, updating the population position through the phase of moving toward prey and the phase of skimming over the water surface;
[0171] GWO introduces the gray wolf group strategy to perform global search to avoid falling into local optimality;
[0172] CSO optimizes the population position through horizontal and vertical cross-updates to avoid premature convergence;
[0173] The specific implementation steps of the POA-GWO-CSO optimization algorithm are as follows:
[0174] Step 1, set the population size and maximum number of iterations;
[0175] Step 2: Collect the instantaneous power flow data of the power system, input it into the model, calculate the fitness value of the pelican population, and thus determine the initial value of the objective function;
[0176] Step 3: Randomly generate prey;
[0177] Step 4: Use the improved pelican position formula to update the pelican position in the first stage;
[0178] Step 5: Bring the position in step 4 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0179] Step 6: Update the position of the i-th pelican in the j-th dimension in the second stage;
[0180] Step 7: Bring the position in step 6 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0181] Step 8: Determine whether the maximum number of iterations is met. If yes, jump to the next step; otherwise, jump to step 3.
[0182] Step 9: Determine the position value of the pelican according to the final fitness function value;
[0183] Furthermore, in the algorithm implementation, the pelican population is first initialized, and then the positions of the pelicans are updated in two stages. The first stage uses the POA algorithm and the introduced nonlinear inertia weight factor for updating, and the second stage uses the CSO algorithm for vertical and horizontal cross-updates. Through continuous iteration, the optimal optimization solution is finally found to achieve the premise of satisfying the user's temperature comfort, promoting the efficient use of energy storage and the local consumption of new energy.
[0184] The specific implementation steps based on the POA-GWO-CSO optimization algorithm are as follows:
[0185] Step 1: Set the population size N and the maximum number of iterations L;
[0186] Step 2: Collect the instantaneous power flow data of the power system, input it into the model, calculate the fitness value of the pelican population, and thus determine the initial value of the objective function;
[0187] Step 3: Randomly generate prey;
[0188] Step 4: Use the improved Pelicans position formula to calculate the Pelicans position in the first stage Make updates;
[0189] Step 5: Substitute this position into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0190] Step 6: Update the position of the i-th pelican in the j-th dimension in the second phase
[0191] Step 7: Substitute this position into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved;
[0192] Step 8: Determine whether the maximum number of iterations is met. If yes, jump to the next step, otherwise jump to step 3;
[0193] Step 9: Determine the position value of the pelican based on the final fitness function value.
[0194] Working principle: First, considering the power balance of the power grid, a controllable load model of the power grid is constructed, and a storage power station model that comprehensively considers factors such as the economy of energy storage is established; secondly, a multi-objective optimization strategy for energy storage power stations is proposed with the lowest grid operation cost and the lowest energy storage power station configuration cost as the optimization goals; then, the original problem is transformed into a second-order cone problem through relaxation and linearization methods; finally, the POA-GWO-CSO algorithm is used to complete the solution of the multi-objective optimization configuration method.
[0195] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
Claims
1. A multi-objective optimization configuration method for an energy storage power station including multiple controllable loads, characterized in that: The configuration method comprises the following steps: S1. Establish a power grid model and an energy storage power station model; S2. Determine the multi-objective optimization goal: minimize the grid operation cost and the energy storage power station configuration cost as the optimization goal; S3. Set constraints: grid node voltage and line current constraints, power balance constraints, grid branch flow constraints, energy storage battery capacity and energy rate constraints, energy storage battery state of charge constraints and voltage offset constraints; S4, transform the non-convex optimization problem into a second-order cone programming (SOCP) problem; S4. Use POA-GWO-CSO optimization algorithm for optimization solution.
2. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The power grid model includes temperature control load and industrial load. The temperature control load model is based on the thermal characteristics of the building, taking into account indoor and outdoor temperature, air conditioning power and wall heat capacity parameters; the industrial load model is based on the importance of the equipment and the user's wishes, and divides the load level according to energy consumption and adjustability; The energy storage power station model is based on energy storage equipment. It takes into account the charging and discharging power, charging and discharging efficiency and capacity operating parameters of the energy storage equipment to establish a full life cycle cost model, including the purchase cost, installation cost, operation and maintenance cost and residual value recovery cost of the energy storage power station.
3. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The grid operation costs include electricity purchase costs, network loss costs, power generation costs and load costs; the energy storage power station costs include purchase costs, installation costs, operation and maintenance costs and residual value recovery.
4. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 3 is characterized in that: The power purchase cost in the power grid operation cost is calculated based on the power purchase price and interactive power between the system and the upper-level power grid; The network loss cost is calculated based on the voltage difference between the grid nodes and the line conductance; The power generation cost is calculated based on the fuel cost and operation and maintenance cost of the micro gas turbine; The load cost is dynamically calculated based on the regulation status of the controllable load.
5. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 3 is characterized in that: The purchase cost of the energy storage power station is amortized through time value, taking into account the benchmark interest rate and economic life, to optimize the comprehensive configuration cost within the planning period; The installation cost and operation and maintenance cost are calculated by the unit capacity installation fee and the operation and maintenance coefficient respectively, and the average annual decline coefficient of the equipment is taken into account.
6. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The second-order cone programming (SOCP) problem uses a second-order cone relaxation method (SOCR) to transform non-convex nonlinear constraints into a second-order cone programming (SOCP) problem. The calculation accuracy and speed are guaranteed by relaxation processing. The second-order cone programming (SOCP) model is used to optimize the configuration scheme of the energy storage power station, the power balance constraint, the flow constraint and the state of charge constraint of the energy storage battery under the premise of ensuring the global optimal solution. The second-order cone relaxation method (SOCR) relaxes the power flow equation of the power grid and calculates the error gap to ensure that the optimal solution is consistent with the accuracy requirement of the original problem. When the error gap reaches the set accuracy, it is considered that the optimal solution is equivalent to the optimal solution of the original problem.
7. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The principles of the POA-GWO-CSO optimization algorithm are as follows: POA simulates the local search behavior of pelicans, updating the population position through the phase of moving toward prey and the phase of skimming over the water surface; GWO introduces the gray wolf group strategy to perform global search to avoid falling into local optimality; CSO optimizes the population position through horizontal and vertical cross-updates to avoid premature convergence.
8. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The specific implementation steps of the POA-GWO-CSO optimization algorithm are as follows: Step 1, set the population size and maximum number of iterations; Step 2: Collect the instantaneous power flow data of the power system, input it into the model, calculate the fitness value of the pelican population, and thus determine the initial value of the objective function; Step 3: Randomly generate prey; Step 4: Use the improved pelican position formula to update the pelican position in the first stage; Step 5: Bring the position in step 4 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved; Step 6: Update the position of the i-th pelican in the j-th dimension in the second stage; Step 7: Bring the position in step 6 into the fitness function to determine whether the fitness value is improved at this position, that is, whether the objective function is improved; Step 8: Determine whether the maximum number of iterations is met. If yes, jump to the next step; otherwise, jump to step 3. Step 9: Determine the position value of the pelican based on the final fitness function value.
9. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: The optimization solution steps are as follows: a. Initialize the algorithm population size and iteration times, collect instantaneous power flow data of the power grid, and calculate the fitness; b. Update the location of the pelican population, conduct local and global searches, and gradually approach the optimal solution through iteration; c. Determine the improvement of the fitness function until the number of iterations is met or the optimal solution is found.
10. The multi-objective optimization configuration method of an energy storage power station including multiple controllable loads according to claim 1, characterized in that: During the execution of the optimization method, the charging and discharging constraints of the energy storage battery are taken into account to ensure that the charge state of the energy storage battery during the scheduling period is not lower than the set lower limit value; the voltage offset constraints of the power grid nodes are taken into account, the deviation of the node voltage is kept within the allowable range, and the average voltage offset degree of the power grid meets the set maximum allowable value.
Citation Information
Patent Citations
A method and system for multi-point layout of energy storage power stations
CN111539086B
Double-layer collaborative optimization configuration method and system for energy storage capacity of photovoltaic storage system
CN113792911B
Energy storage power station configuration methods and terminals to enhance grid voltage sag immunity
CN113922396B
Multi-objective optimization configuration method and system for capacity of energy storage power stations adapted to variable energy storage cycles