Accurate placement construction process for accropode group under large water depth
By using a high-precision positioning system and an underwater visual monitoring system under high water depth conditions, the precise placement of the Twist King block group is solved, and the problems of insufficient accuracy and instability in traditional processes are improved, and construction efficiency and quality are improved.
Patent Information
- Application Number
- CN202411979096.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-31
- Publication Date
- 2025-02-25
AI Technical Summary
Under high water depth conditions, the traditional Twist King block set lifting process leads to insufficient accuracy and instability due to factors such as flow rate, buoyancy and line of sight, and lacks equipment and methods for real-time high-precision monitoring and intelligent position adjustment.
It adopts a high-precision positioning system, including GPS-RTK module, multi-wave speed detector, sonar and gimbal control submodules, and combines the underwater visual monitoring system to realize real-time monitoring and position adjustment to ensure the accurate placement of the Twist King block group.
It significantly improves the lifting accuracy and construction efficiency of the Twist Wangzi block group in deep water environments, reduces position deviation and quality problems, and reduces construction costs and safety risks.
Smart Images

Figure CN119507369A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of submerged dam construction, in particular to a precise construction process for twisted W-shaped block groups under great water depth. Background Art
[0002] Twisted King block groups are often used in submerged dam construction in waterway regulation, which can effectively enhance the stability and anti-scouring ability of the dam body. However, under deep water conditions, the traditional Twisted King block group hanging process faces many challenges, as follows:
[0003] Flow rate influence
[0004] In deep water environment, the water flow velocity has a significant impact on the position accuracy of the twist block group during the hoisting process. The flow velocity changes in deep water are more unpredictable, which can easily cause the twist block group to deviate from the predetermined position, thereby affecting the overall layout of the dam body;
[0005] Buoyancy effect
[0006] The influence of buoyancy in deep water environment is more complicated, which not only produces significant buoyancy interference on the lifting equipment, but also affects the sinking posture and stability of the twisting block group. Traditional lifting equipment is difficult to cope with such variable buoyancy, making it difficult to control the construction accuracy;
[0007] Line of sight restrictions
[0008] As the water depth increases and the turbidity of the water body rises, traditional vision-based positioning methods are limited and it is difficult to achieve high-precision positioning and monitoring in deep water. This situation makes it particularly difficult to accurately place the Twisted King Block Group in a deep water environment;
[0009] Lack of precise equipment
[0010] Existing technologies generally lack equipment and methods that can achieve real-time high-precision monitoring and intelligent position adjustment in deep water environments. The limitations of traditional equipment and methods result in low construction accuracy and long adjustment time, increasing construction costs and safety risks.
[0011] Based on the above technical pain points, the present invention proposes a precise placing construction process for twisting king-shaped block groups in deep water. By comprehensively utilizing high-precision positioning systems, underwater real-time monitoring and intelligent adjustment methods, it aims to significantly improve the placing accuracy and construction efficiency of twisting king-shaped block groups in deep water environments, thereby effectively reducing position deviations and quality problems during the construction process. Summary of the invention
[0012] The purpose of the present invention is to provide a precise construction process for placing twisted king-shaped block groups in deep water, so as to solve the problems of insufficient precision and instability caused by factors such as flow velocity, buoyancy and limited vision when placing twisted king-shaped block groups in deep water environment in the prior art.
[0013] To achieve the above object, the present invention provides the following technical solutions:
[0014] The present invention provides a construction process for precise placement of twisted king-shaped block groups under great water depth, comprising the following steps:
[0015] S1. Construction preparation: prefabricate the twist block group and transport it to the construction site;
[0016] S2. Underwater measurement and positioning: measure underwater terrain, obtain underwater terrain data, and arrange positioning system;
[0017] S3, hoisting and placing: use the underwater visual monitoring system to conduct real-time monitoring and position adjustment, and accurately place the twisted king block group to the predetermined position;
[0018] S4, inspection after sinking: collect the sinking data of the twisted king block group and conduct quality inspection;
[0019] S5. Adjust the sinking position: Make position corrections based on the inspection results to ensure the stability of the twist block.
[0020] The present invention is further configured as follows: in step S1, the specific process of the construction preparation is as follows:
[0021] Prefabricated components: Prefabricate the twist block group on the shore according to the design standards to ensure the precise control of size and quality. Strictly follow the quality management system during the prefabrication process to ensure the consistency and adaptability of the block specifications;
[0022] Component transportation: The prefabricated twist king block group is transported to the construction site using special transportation tools to ensure that the blocks are not damaged during transportation.
[0023] The present invention is further configured as follows: in the step S2, the underwater topography measurement is to use a multi-beam depth sounder to perform accurate measurement of the surface of the submerged dam.
[0024] The present invention is further configured as follows: the multi-beam echo sounder and sonar are installed on a descent vessel to obtain underwater terrain and real-time environmental data, and the data are transmitted to a central control unit on the vessel via a data line for positioning and monitoring.
[0025] The present invention is further configured as follows: in step S2, the positioning system includes a GPS-RTK module, a multi-beam velocity detector, a sonar and a pan / tilt control submodule, wherein:
[0026] The GPS-RTK module is installed on the floating crane to provide real-time, high-precision position data of the floating crane;
[0027] The multi-wave velocity detector is installed on the hanging ship to measure the underwater topography and assist in obtaining the accurate underwater position data of the twisted king block group;
[0028] The sonar device is used to monitor the final position of the twisting prince block;
[0029] The pan / tilt control submodule is installed on the hoisting vessel and is used to adjust the angle and orientation of the hoisting equipment during the hoisting process.
[0030] The present invention is further configured as follows: in the step S2, the underwater measurement and positioning further includes optimizing the installation position of the positioning system according to the acquired underwater terrain data.
[0031] The present invention is further configured as follows: in step S3, the specific process of the hanging is as follows:
[0032] Lift the twist king block assembly from the transport ship to the floating crane ship;
[0033] The twist king block assembly is hoisted by steel cables and lifting equipment;
[0034] Use underwater visual monitoring system to monitor the hanging position in real time;
[0035] By adjusting the length of the sling and the lifting angle, slowly place the twist king block group to the predetermined position.
[0036] The present invention is further configured as follows: the lifting equipment includes a lifting arm and a supporting assembly, and the lifting arm is installed on a floating crane vessel through the supporting assembly, and a winch is installed on the lifting arm, and the winch is used to control the retraction and extension of the steel cable.
[0037] The present invention is further configured as follows: in step S3, the underwater visual monitoring system includes an underwater sonar and a real-time data analysis module, wherein:
[0038] The underwater sonar is used to transmit image data in real time during the hoisting process;
[0039] The real-time data analysis module is used to monitor and adjust the hoisting operation.
[0040] The present invention is further configured as follows: in the step S3, the lifting process adopts a fixed-point random method so that adjacent blocks are staggered and hooked to each other.
[0041] The present invention is further configured as follows: in the step S4, underwater monitoring equipment and sonar are used to collect the sinking data of the twisted king block group in real time.
[0042] The present invention is further configured as follows: in the step S5, the placement position adjustment includes correcting the area that does not meet the requirements and re-sinking the twisted king block group to the correct position.
[0043] The present invention is further configured as follows: the central control unit is connected to the GPS-RTK module, the sonar and the pan / tilt control submodule.
[0044] Compared with the prior art, the present invention has the following beneficial effects:
[0045] (1) The present invention realizes high-precision positioning of the lifting vessel and the twisting block group by comprehensively using the GPS-RTK module, sonar and pan-tilt control submodule.
[0046] (2) The present invention adopts real-time monitoring and adjustment technology to ensure the stable sinking of the twisted king block group in a complex underwater environment and reduce the impact of flow velocity and buoyancy on construction.
[0047] (3) The precise positioning and real-time monitoring technology of the present invention makes the construction process smoother and reduces the rework and time waste caused by position deviation in traditional methods.
[0048] (4) The process provided by the present invention is suitable for various complex underwater environments, especially dam construction under deep water conditions, and has broad application prospects and adaptability. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] Figure 1 A top view of the overall structure of the present invention;
[0050] Figure 2 It is a front view of the overall structure of the present invention;
[0051] Figure 3 It is a side view of the overall structure of the present invention.
[0052] Description of Figure Numbers:
[0053] 1. Floating crane; 2. Twist-K-shaped block assembly; 3. Crane; 4. Crane arm; 5. Winch; 6. Self-telescopic rod; 7. Steel cable; 8. GPS-RTK module; 9. Sonar; 10. Dam body; 11. Sonar connected to telescopic rod. DETAILED DESCRIPTION
[0054] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0055] The present invention provides a construction process for precise placement of twisted king-shaped block groups under great water depth, comprising the following steps:
[0056] S1. Construction preparation: prefabricate the twisted king block group 2 and transport it to the construction site.
[0057] The specific process of construction preparation is as follows:
[0058] Prefabricated components: Prefabricate the twist block group 2 on shore according to the design standards to ensure accurate control of size and quality, and strictly follow the quality management system during the prefabrication process to ensure the consistency and adaptability of the block specifications;
[0059] Component transportation: The prefabricated twist king block group 2 is transported to the construction site using special transportation tools to ensure that the blocks are not damaged during transportation.
[0060] S2. Underwater measurement and positioning: measure underwater terrain, obtain underwater terrain data, and deploy positioning system.
[0061] Among them, underwater topography measurement is to use multi-beam depth sounder and sonar 9 to accurately measure the surface of the submerged dam 10.
[0062] The multi-beam echo sounder is installed on the dipping vessel to obtain underwater terrain and real-time environmental data. The data is transmitted to the central control unit on the ship via a data line for positioning and monitoring.
[0063] Furthermore, the positioning system includes a GPS-RTK module 8, a multi-beam velocity detector, a sonar 9 and a pan / tilt control submodule, wherein:
[0064] The GPS-RTK module 8 is installed on the floating vessel to provide real-time, high-precision position data of the floating vessel;
[0065] The multi-wave velocity detector is installed on the hanging ship to measure the underwater topography and assist in obtaining the precise underwater position data of the twisted king block group 2;
[0066] Sonar device 9 is used to monitor the final position of the twisting prince block
[0067] The pan / tilt control submodule is installed on the lifting vessel and is used to adjust the angle and direction of the lifting equipment during the lifting process.
[0068] Furthermore, underwater measurement and positioning also includes optimizing the installation position of the positioning system based on the acquired underwater terrain data.
[0069] S3. Lifting and lowering: Use the underwater visual monitoring system to conduct real-time monitoring and position adjustment to accurately lower the twist king block group 2 to the predetermined position.
[0070] The specific process of hoisting is as follows:
[0071] Lift the twist king block set 2 from the transport ship to the floating crane ship;
[0072] The twist block group 2 is hoisted by the steel cable 7 and the lifting equipment;
[0073] Use underwater visual monitoring system to monitor the hanging position in real time;
[0074] By adjusting the length of the steel cable 7 and the hoisting angle, the twist block group 2 is slowly placed to the predetermined position.
[0075] Furthermore, the lifting equipment includes a lifting arm 4 and a supporting assembly, and the lifting arm 4 is installed on the floating crane through the supporting assembly. A winch is installed on the lifting arm 4, and the winch is used to control the retraction and extension of the steel cable 7.
[0076] Furthermore, the underwater visual monitoring system includes underwater sonar and real-time data analysis modules, wherein:
[0077] Underwater sonar is used to transmit image data in real time during the hoisting process;
[0078] Real-time data analysis module is used to monitor and adjust the lifting operation.
[0079] Furthermore, the process of hoisting adopts a fixed-point random method so that adjacent blocks are staggered and hooked to each other.
[0080] S4. Inspection after sinking: collect sinking data of twisted king block group 2 and conduct quality inspection.
[0081] Among them, underwater monitoring equipment and sonar 9 are used to collect the sinking data of the twisted king block group 2 in real time.
[0082] S5. Adjust the sinking position: Make position corrections based on the inspection results to ensure the stability of the twist block.
[0083] The adjustment of the placement position includes correcting the areas that do not meet the requirements and re-sinking the twisted king block group 2 to the correct position.
[0084] In addition, the central control unit is connected to the GPS-RTK module 8, the sonar 9 and the gimbal control submodule.
[0085] Embodiment 1:
[0086] like Figure 1-Figure 3 As shown, this embodiment provides a twisted king block group lifting and placing device, which includes a floating crane 1 as an overall construction platform, a longitudinal traction system and a transverse traction system, the longitudinal traction system is composed of a crane 3, a steel cable 7, a pulley and a hook, and the transverse traction system is composed of a winch 5 and a self-retractable rod 6, and the transverse traction system is also provided with a steel cable 7, a pulley and a hook. Based on the twisted king block group lifting and placing device, this embodiment provides an implementation method for accurately lifting the twisted king block group, and the specific process is as follows:
[0087] Preparation before construction: (1) Train construction personnel to ensure equipment operation and safe construction; (2) Determine the installation location and quantity of the twist block group 2 according to the construction design drawing; (3) Install the winch 5, self-retractable rod 6, pulley, hook and steel cable 7, and debug the equipment to ensure the normal operation of each part.
[0088] Pre-construction work: Floating crane 1 goes to the construction area and determines the construction site through GPS positioning; then the crew binds the twist king block group 2 with hooks and steel cables to ensure the stability of the twist king block group 2 during the lifting process. After the binding is completed, the surveyor determines the sinking position of the twist king block group 2.
[0089] Lifting operation: The crane operator lifts the twist king block group 2 and makes it reach the front end of the self-telescopic rod 6 through the crane arm 4. Then the crew connects the twist king block group 2 with the lateral traction system through the hook and the steel cable 7. After the binding is completed, the twist king block group 2 is moved to the top of the installation position through the coordinated operation of the crane arm 4 and the lateral traction system. After confirming that the placement position is correct, it is lowered.
[0090] Precise placement: During the lowering of the twist block group 2, the position and posture of the twist block group 2 shall be monitored in real time through the GPS-RTK module 8 and the sonar device 9 to avoid the influence of water flow and flow field on the placement of the twist block group 2. When the GPS-RTK module 8 and the sonar 9 convey abnormal information, the length and angle of the steel cable shall be adjusted in time according to the data fed back by the sonar 9 using the winch 5 and the self-retractable rod 6 to ensure that the twist block group 2 is stably placed in the designed position.
[0091] Acceptance and adjustment: After sinking, carry out installation position and quality acceptance. If deviations are found, adjust the equipment in time and re-hang it.
[0092] Embodiment 2:
[0093] like Figure 1-Figure 3 As shown, this embodiment provides a specific process for accurately placing the twist block group under deep water conditions. This process achieves accurate positioning and placement of the twist block group through the synergy of multiple high-precision equipment and technical means, thereby improving construction efficiency and quality. As an implementation method, the specific process is as follows:
[0094] First, the construction preparation stage includes prefabricating the twist king block group 2 on shore according to the design standards to ensure precise control of its size and quality. After prefabrication, the twist king block group 2 is transported to the construction site using special transportation tools to ensure that the blocks are not damaged during transportation.
[0095] Next, underwater measurement and positioning are carried out, and the underwater terrain of the construction area is measured in detail using a multi-beam depth sounder and sonar 9 to obtain accurate terrain data. These data are used to install a GPS-RTK module 8, a multi-beam velocity detector, sonar 9 and a pan / tilt control submodule on the drop ship, and high-precision positioning is achieved through real-time data feedback, wherein the sonar 9 is connected to the GPS-RTK module through a sonar connection telescopic rod 11.
[0096] During the lifting process, firstly, the lifting preparation is carried out, the twist king block group 2 is lifted from the transport ship to the floating crane ship 1, and then lifted by the steel cable 7 and the lifting equipment. The lifting position is monitored and adjusted in real time by the underwater visual monitoring system to ensure that the block is accurately sunk to the predetermined position.
[0097] After sinking, data collection and quality inspection are required. Use underwater monitoring equipment and sonar 9 to collect the sinking data of the twisted king block group 2 in real time to obtain the precise position and status information of the block after sinking. Subsequently, key indicators such as the sinking density and position deviation of the twisted king block group 2 are checked to ensure that the block position meets the design requirements.
[0098] Finally, based on the quality inspection results, position corrections are made to areas that do not meet the requirements to ensure that the blocks are accurately sunk to the correct position.
[0099] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0100] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. The precise construction technology of twisting Wang-shaped block group under great water depth is characterized by: The following steps are involved: S1. Construction preparation: prefabricate the twist block group and transport it to the construction site; S2. Underwater measurement and positioning: measure underwater terrain, obtain underwater terrain data, and arrange positioning system; S3, hoisting and placing: use the underwater visual monitoring system to conduct real-time monitoring and position adjustment, and accurately place the twisted king block group to the predetermined position; S4, inspection after sinking: collect the sinking data of the twisted king block group and conduct quality inspection; S5. Adjust the sinking position: Make position corrections based on the inspection results to ensure the stability of the twist block.
2. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In step S2, the underwater topography measurement is to use a multi-beam echo sounder to accurately measure the surface of the submerged dam.
3. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In step S2, the positioning system includes a GPS-RTK module, a multi-beam velocity detector, a sonar and a pan / tilt control submodule, wherein: The GPS-RTK module is installed on the floating crane to provide real-time, high-precision position data of the floating crane; The multi-wave velocity detector is installed on the hanging ship to measure the underwater topography and assist in obtaining the accurate underwater position data of the twisted king block group; The sonar device is used to monitor the final position of the twisting prince block; The pan / tilt control submodule is installed on the hoisting vessel and is used to adjust the angle and orientation of the hoisting equipment during the hoisting process.
4. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In the step S2, the underwater measurement and positioning further includes optimizing the installation position of the positioning system according to the acquired underwater terrain data.
5. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In step S3, the specific process of the hanging is as follows: Lift the twist king block assembly from the transport ship to the floating crane ship; The twist king block assembly is hoisted by steel cables and lifting equipment; Use underwater visual monitoring system to monitor the hanging position in real time; By adjusting the length of the sling and the lifting angle, slowly place the twist king block group to the predetermined position.
6. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In step S3, the underwater visual monitoring system includes an underwater sonar and a real-time data analysis module, wherein: The underwater sonar is used to transmit image data in real time during the hoisting process; The real-time data analysis module is used to monitor and adjust the hoisting operation.
7. The precise construction process for twisting W-shaped blocks under great water depth according to claim 1 is characterized in that: In step S3, the hoisting process adopts a fixed-point random method so that adjacent blocks are arranged in a staggered manner and hooked to each other.
8. The precise construction process for the twisting block group under great water depth according to claim 1 is characterized in that: In the step S4, underwater monitoring equipment and sonar are used to collect the sinking data of the twisted king block group in real time.
9. The precise construction process for twisting W-shaped blocks under great water depth according to claim 1 is characterized in that: In step S5, the adjustment of the placement position includes correcting the area that does not meet the requirements and re-settling the twisted king block group to the correct position.