Deep soft soil covering layer offshore wind turbine installation method and data analysis model

Through pile legs pre-cooling and layered hammering technology, combined with soil curing and data analysis models, the problems of large friction resistance and high risk of pile slipping in deep soft soil cover are solved, and efficient and accurate offshore fan installation is achieved.

CN120401476APending Publication Date: 2025-08-01CHINA RESOURCES OFFSHORE WIND POWER (CANGNAN) CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510448176.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-10
Publication Date
2025-08-01

AI Technical Summary

Technical Problem

In deep soft soil cover, pile legs are subjected to greater frictional resistance during penetration, resulting in low hammering efficiency and low load-bearing capacity of soft soil increases the risk of pile slipping.

Method used

The hardened layer is formed by pre-cooling the pile legs, and the hammer energy is dynamically adjusted by layered hammering method, and the cured material is injected during the hammering process to enhance the bearing capacity of the soil, and the lifting process is optimized based on the data analysis model.

Benefits of technology

It reduces friction resistance during hammering, improves penetration efficiency and installation accuracy, reduces the risk of pile slips, and ensures installation safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120401476A_ABST
    Figure CN120401476A_ABST
Patent Text Reader

Abstract

The invention provides a deep soft soil covering layer offshore wind turbine installation method and a data analysis model, and relates to the field of offshore wind power construction.The method includes the following steps of data collection and preparation, pile leg installation, wind turbine hoisting and later inspection and debugge.The pile leg installation includes the following steps that pile legs are pre-cooled, liquid nitrogen is smeared to the bottoms of the pile legs, and the pile legs are installed; and cooling to a certain low temperature to form a hardened layer, so that the frictional resistance in the hammering process is reduced. Through the pile leg pre-cooling step, rapid formation of a hardened layer on the surface of the pile leg is achieved, the friction resistance between the pile leg and soft soil in the hammering process is reduced, and the mounting efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of offshore wind power construction, and more specifically, to a method for installing an offshore wind turbine in a deep soft soil covering layer and a data analysis model. Background Art

[0002] With the continuous growth of the global demand for renewable energy, offshore wind power, as a clean and efficient form of energy, has received extensive attention and rapid development; in traditional offshore wind turbine installation, the pile legs are usually inserted into the seabed through hydraulic hammering or vibratory pile driving techniques. However, in a deep soft soil covering layer, the high viscosity and low strength of the soft soil result in a large frictional resistance on the pile legs during the penetration process, reducing the hammering efficiency.

[0003] For example: "A pre-tensioned pile-anchor combined foundation for a shallow covering layer seabed and its construction method" disclosed in the Chinese invention patent (application number: 202110055208.3), its specification discloses: including a wind turbine, a tower barrel, and a pile foundation connected in sequence from top to bottom, the bottom of the pile foundation is vertically embedded in the soft soil layer and contacts the rock layer; a plurality of anchor rods are fixedly connected to the side wall of the pile foundation at circumferential intervals through a connecting device, and the other end of each anchor rod passes through the soft soil layer and is embedded in the rock layer and fixedly connected to the rock-embedded anchoring end. In the present invention, the vertical force borne by the pile foundation is mainly borne by the friction force of the surface soil and the rock and soil layer at the bottom of the pile, and the horizontal load is borne by the soil around the pile, the anchor rods, and their rock-embedded anchoring ends. The bearing capacity is stable, facilitating construction and installation, and having a large stiffness, ensuring good stability of the upper structure of the offshore wind turbine; the above patent can prove the defects existing in the prior art.

[0004] Therefore, we make improvements in this regard and propose a method for installing an offshore wind turbine in a deep soft soil covering layer and a data analysis model. Summary of the Invention

[0005] The purpose of the present invention is to solve the problem that the current pile legs are subject to a large frictional resistance during the penetration process, reducing the hammering efficiency. [[ID=2I]]

[0006] In order to achieve the above-mentioned invention purpose, the present invention provides a method for installing an offshore wind turbine in a deep soft soil covering layer and a data analysis model to improve the above problems.

[0007] Specifically, this application is as follows:

[0008] A method for installing an offshore wind turbine in a deep soft soil covering layer includes the following steps:

[0009] Data collection and preparation, collecting the geological data and environmental data of the field area, selecting a lifting ship and equipment, and preparing pile legs, hammering equipment, cooling devices, and solidifying materials;

[0010] Leg installation: Pretreat the leg to reduce frictional resistance, dynamically adjust the hammering energy using the layered hammering method, and inject a solidifying material during hammering to enhance the soil bearing capacity, ensuring that the leg penetrates to the designed depth and maintains verticality;

[0011] Wind turbine hoisting: Hoist the wind turbine tower, nacelle, and blades in sections onto the leg, ensure alignment accuracy and levelness, and monitor environmental parameters in real time during hoisting to ensure operation safety;

[0012] Post-installation inspection and commissioning: Check the installation quality of each component of the wind turbine, commission the electrical and control systems, conduct a trial run, and clean the work site;

[0013] The leg installation includes the following steps:

[0014] Leg pre-cooling: Apply liquid nitrogen to the bottom of the leg, cool it to a certain low temperature to form a hardened layer, reducing frictional resistance during hammering.

[0015] As a preferred technical solution of the present application, the data collection and preparation includes the following steps:

[0016] Data collection: Collect the soil layer distribution, soil hardness, water content of the site geological data, and the wind speed, wave height, and tide of the environmental data;

[0017] Equipment and material preparation: Select a lifting vessel with sufficient lifting capacity, equip it with a dynamic positioning system, and prepare the leg, hydraulic hammering equipment, liquid nitrogen cooling device, and solidifying agent.

[0018] As a preferred technical solution of the present application, the leg installation further includes the following steps:

[0019] Initial hammering: Hoist the leg to the target position, start the hydraulic hammering equipment, set the initial hammering energy to 500 kJ, and in soft soil layers, use low-energy hammering (500 - 800 kJ), and monitor the leg inclination in real time to ensure that the inclination ≤ 1°;

[0020] Layered hammering: When the leg enters the hard soil layer, increase the hammering energy to 1500 kJ to ensure the penetration efficiency. After every certain number of hammerings, check the penetration depth and inclination of the leg to ensure that the penetration speed ≥ 0.5 m / min and the inclination ≤ 1°.

[0021] As a preferred technical solution of the present application, the leg installation further includes the following steps:

[0022] Soil solidification: During hammering, inject cement slurry around the leg to locally harden the soft soil and improve the soil bearing capacity.

[0023] As a preferred technical solution of the present application, the leg installation further includes the following steps:

[0024] Final penetration: When the pile leg approaches the design depth, reduce the hammering energy to 1000 kJ to ensure the penetration accuracy, check the elevation of the pile top, and ensure that the penetration depth error ≤ 10 cm.

[0025] As a preferred technical solution of this application, the installation of the wind turbine includes the following steps:

[0026] Tower installation: Lift the tower to the pile leg and use a hydraulic adjustment device to ensure the alignment accuracy.

[0027] Nacelle and blade installation: Lift the nacelle to the top of the tower, use a level to ensure the levelness of the nacelle, and lift the blades in sequence. During the lifting process, monitor the wind speed and wave height in real time to ensure that the wind speed ≤ 12 m / s and the wave height ≤ 2 m.

[0028] An offshore wind turbine installation data analysis model for thick soft soil cover layer includes:

[0029] Data collection stage: Collect geological information on the structure of the upper and middle part of the foundation soil, soil layer distribution, and soil mechanical properties in the field area. Use meteorological and ocean monitoring equipment to collect environmental parameters such as wind speed, wind direction, wave height, tide, and seawater temperature in real time. Collect the specifications and performance parameters of the lifting ship and lifting equipment, including lifting capacity, stability, and operating range. Record the key parameters during the lifting process, including lifting method, pile sinking method, hammering energy, and number of hammer blows.

[0030] Data preprocessing stage: Integrate data from different sources to form a unified data format and storage method. Standardize the data to eliminate the influence of different dimensions and data ranges on the analysis results. Divide the data set into a training set, a validation set, and a test set, which are used for model training, model tuning, and model performance evaluation respectively.

[0031] Data analysis and simulation stage: Based on environmental data, ship and machinery data, and lifting process data, simulate the lifting process. Combine soil layer characteristics, environmental factors, and ship and machinery performance to determine the best installation time and process. Predict the risk of pile slipping according to soil layer characteristics and lifting parameters and propose preventive measures. Automatically adjust the hammering force according to the hardness of different soil layers to ensure the smooth progress of the pile sinking process.

[0032] Scheme generation stage: Generate detailed information on the lifting sequence, lifting point position, and lifting attitude. Recommend the hammering force of the pile leg in soil layers at different depths according to soil layer characteristics and environmental factors, and determine the best installation time window to ensure the safety and efficiency of the lifting operation.

[0033] As a preferred technical solution of this application, in the data preprocessing stage, the data is processed using standardization methods, including Z-score standardization and Min-Max standardization, to eliminate the influence of different dimensions and data ranges on the analysis results.

[0034] As a preferred technical solution of this application, in the data analysis and rehearsal stage, by simulating the hoisting process, comprehensively considering meteorological, oceanic environment, ship and machine performance, and geological conditions, the optimal hoisting time window is determined, and the hammering force is dynamically adjusted according to the soil layer hardness, so as to reduce the risk of pile slipping and improve the hoisting efficiency.

[0035] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0036] In the solution of this application:

[0037] 1. Through the set pile leg pre-cooling step, the rapid formation of the hardened layer on the surface of the pile leg is realized, the frictional resistance between the pile leg and the soft soil during the hammering process is reduced, the installation efficiency is improved, and the problem that the pile leg in the prior art is subject to a large frictional resistance during the penetration process and the hammering efficiency is reduced is solved;

[0038] 2. Through the set layered hammering step, the dynamic adjustment of the hammering energy according to the hardness of different soil layers is realized, and the problem that a single hammering energy in the prior art cannot adapt to complex soil layers, resulting in low penetration efficiency or excessive disturbance of the soil body, is solved;

[0039] 3. Through the set soil solidification step, the injection of cement slurry around the pile leg during the hammering process is realized, the soft soil is locally hardened, and the soil bearing capacity is improved, and the problem of high risk of pile slipping and insufficient installation accuracy caused by the low bearing capacity of the soft soil in the prior art is solved;

[0040] 4. Through the set data analysis and rehearsal stage, the comprehensive analysis of different soil layer characteristics, environmental factors, and ship and machine performance is realized, and the problem of inaccurate risk assessment caused by relying on empirical judgment in the prior art is solved. Description of the Drawings

[0041] Figure 1 It is the method flow chart of the offshore wind turbine installation method with a deep soft soil covering layer provided by this application;

[0042] Figure 2 It is the method flow chart of data collection and preparation in the offshore wind turbine installation method with a deep soft soil covering layer provided by this application;

[0043] Figure 3 It is the method flow chart of pile leg installation in the offshore wind turbine installation method with a deep soft soil covering layer provided by this application;

[0044] Figure 4 It is the method flow chart of wind turbine hoisting in the offshore wind turbine installation method with a deep soft soil covering layer provided by this application;

[0045] Figure 5It is the method flow chart for mid - and late - stage inspection and commissioning in the installation method of an offshore wind turbine with a thick soft soil cover layer provided by this application;

[0046] Figure 6 It is the system flow chart of the data analysis model for the installation of an offshore wind turbine with a thick soft soil cover layer provided by this application. Specific embodiments

[0047] In order to enable those skilled in the art to better understand the solution of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all of the embodiments. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts shall fall within the protection scope of the present invention.

[0048] In order to enable those skilled in the art to better understand the solution of the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings.

[0049] It should be noted that, without conflict, the embodiments in the present invention and the features and technical solutions in the embodiments can be combined with each other.

[0050] It should be noted that similar reference numerals and letters denote similar items in the following drawings. Therefore, once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings.

[0051] Embodiment 1

[0052] Please refer to Figure 1 and Figure 3 , an installation method of an offshore wind turbine with a thick soft soil cover layer, which includes the following steps:

[0053] Data collection and preparation: Collect field geological data and environmental data, select a hoisting ship and equipment, and prepare pile legs, hammering equipment, cooling devices, and solidifying materials;

[0054] Pile leg installation: Pretreat the pile legs to reduce frictional resistance, use the layered hammering method to dynamically adjust the hammering energy, and at the same time inject solidifying materials during the hammering process to enhance the soil bearing capacity, ensuring that the pile legs penetrate to the designed depth and maintain verticality;

[0055] Wind turbine hoisting: Hoist the wind turbine tower, nacelle, and blades in sections onto the pile legs, ensure the alignment accuracy and levelness, and monitor the environmental parameters in real time during the hoisting process to ensure operation safety;

[0056] Late - stage inspection and commissioning: Check the installation quality of each component of the wind turbine, commission the electrical and control systems, conduct a trial run, and clean the operation site.

[0057] Further, as Figure 1 and Figure 2 shown, data collection and preparation include the following steps:

[0058] Data collection: Collect geological data of the site area (soil layer distribution, soil hardness, water content, etc.) to determine the depth and characteristics of the soft soil layer. For example, the depth of the soft soil layer is 20 - 30 meters, the soil hardness is 5 - 10 MPa. Collect environmental data (wind speed, wave height, tide, etc.), and select a time window with a wind speed lower than 10 m / s and a wave height lower than 1.5 meters for operation;

[0059] Prepare equipment and materials: Select a crane ship with a lifting capacity ≥ 1000 tons, equipped with a dynamic positioning system (DP), and prepare pile legs (length ≥ 50 meters), hydraulic hammering equipment (hammering energy ≥ 2000 kJ), liquid nitrogen cooling device, curing agent (cement slurry), etc.

[0060] Further, as Figure 1 and Figure 3 shown, pile leg installation includes the following steps:

[0061] Pile leg pre - cooling: Apply liquid nitrogen to the bottom of the pile leg and cool it to - 50 °C to form a hardened layer, reducing the frictional resistance during the hammering process, which takes about 1 hour; The pre - cooling hardens the surface of the pile leg, significantly reducing the frictional resistance of the soft soil to the pile leg, improving the hammering efficiency. During the penetration process of the pile leg, the disturbance to the soft soil is small, reducing the risk of soil liquefaction and settlement. By reducing the frictional resistance and soil disturbance, the penetration process of the pile leg is more stable, reducing the risk of pile slipping and improving the installation accuracy;

[0062] Initial hammering: Lift the pile leg to the target position, start the hydraulic hammering equipment, set the initial hammering energy to 500 kJ. In the soft soil layer (depth 0 - 20 meters), use low - energy hammering (500 - 800 kJ) to avoid excessive disturbance to the soil, and monitor the inclination of the pile leg in real - time to ensure that the inclination ≤ 1°;

[0063] Layered hammering: When the pile leg enters the hard soil layer (depth 20 - 30 meters), increase the hammering energy to 1500 kJ to ensure the penetration efficiency. Every 10 hammerings, check the penetration depth and inclination of the pile leg to ensure that the penetration speed ≥ 0.5 m / min and the inclination ≤ 1°;

[0064] Soil solidification: During the hammering process, inject cement slurry (water - cement ratio 0.5) around the pile leg to locally harden the soft soil and improve the soil bearing capacity. The solidification range has a diameter of about 5 meters and takes about 2 hours;

[0065] Final penetration: When the pile leg approaches the design depth (about 40 meters), reduce the hammering energy to 1000 kJ to ensure penetration accuracy. Finally, check the elevation of the pile top to ensure that the penetration depth error ≤ 10 cm.

[0066] Further, as Figure 1 and Figure 4 shown, the wind turbine hoisting includes the following steps:

[0067] Tower installation: Hoist the tower onto the pile leg and use a hydraulic adjustment device to ensure the alignment accuracy (deviation ≤ 2 cm). The installation of each section of the tower takes about 1 hour, and the total time is about 4 hours.

[0068] Nacelle and blade installation: Hoist the nacelle to the top of the tower and use a level to ensure the levelness of the nacelle (deviation ≤ 0.5°). Then hoist the blades in sequence. The installation of each blade takes about 1 hour, and the total time is about 3 hours. During the hoisting process, monitor the wind speed and wave height in real time to ensure that the wind speed ≤ 12 m / s and the wave height ≤ 2 meters.

[0069] Embodiment 2

[0070] Further optimize the installation method of the offshore wind turbine in the deep soft soil covering layer provided in Embodiment 1. Specifically, as Figure 1 and Figure 5 shown, the later inspection and commissioning include the following steps:

[0071] Structural inspection: Check the installation quality of the pile leg, tower, nacelle and blades to ensure that each component meets the design requirements. Use a laser rangefinder to check the verticality of the tower (deviation ≤ 0.1°).

[0072] System commissioning: Commission the electrical system and control system of the wind turbine to ensure its normal operation. Conduct a trial run and check the power generation performance of the wind turbine (output power ≥ 5 MW).

[0073] Environmental restoration: Clean the operation site and restore the marine environment.

[0074] Embodiment 3

[0075] Further optimize the installation method of the offshore wind turbine in the deep soft soil covering layer provided in Embodiment 1 or 2. Specifically, as Figure 6 shown, the data analysis model for the installation of the offshore wind turbine in the deep soft soil covering layer includes:

[0076] During the data collection stage, detailed geological information such as the structure of the upper-middle foundation soil in the field area, soil layer distribution, and soil mechanical properties is collected to ensure the accuracy and integrity of the data, providing a reliable basis for subsequent analysis. Environmental parameters such as wind speed, wind direction, wave height, tide, and seawater temperature are collected in real-time using meteorological and ocean monitoring equipment. The specifications and performance parameters of the lifting vessel and lifting equipment are collected, including lifting capacity, stability, and operating range. Key parameters during the lifting process are recorded, such as the lifting method, pile driving method, hammering energy, and number of hammer blows.

[0077] During the data preprocessing stage, data from different sources are integrated to form a unified data format and storage method, and the data is standardized.

[0078] Z-score standardization, formula:

[0079] Z = (X - μ) / σ

[0080] Where X is the original data, μ is the mean of the data, and σ is the standard deviation of the data.

[0081] Min-Max standardization, formula:

[0082] X , = (X - X- min ) / (X- max - X- min )

[0083] Where X is the original data, Xmin is the minimum value in the data, and Xmax is the maximum value in the data.

[0084] The influence of different dimensions and data ranges on the analysis results is eliminated, and the data set is divided into a training set, a validation set, and a test set. The training set is used for model training, the validation set is used for model tuning, and the test set is used for evaluating model performance.

[0085] During the data analysis and simulation stage, based on the collected environmental data, ship and machinery data, and lifting process data, the lifting process is simulated. Considering different soil layer characteristics, environmental factors, and ship and machinery performance, the optimal installation time and process are obtained. According to the soil layer characteristics and lifting parameters, the possibility of pile slipping is predicted, and preventive measures are proposed to reduce the risk of pile slipping.

[0086] Logistic regression formula:

[0087] P(Y = 1|X) = 1 / (1 + e ^ (-(β0 + β2 * X2 + … + βn * Xn)))

[0088] Among them, P(Y = 1|X) is the probability that event Y occurs when the input variable X is given, β0, β1,..., βn are coefficients obtained through logistic regression training, and X1, X2,..., Xn are input variables;

[0089] Automatically adjust the hammering force according to the hardness of different soil layers to ensure the smooth progress of the pile driving process and improve the hoisting efficiency;

[0090] Polynomial regression formula:

[0091] F = β0 + β1*H + β2*H^2

[0092] Among them, F is the predicted hammering force, H is the soil hardness, and β0, β1, β2 are coefficients obtained through polynomial regression training; Comprehensively consider meteorological, marine environment, ship and machine performance, and geological conditions to determine the optimal hoisting time window to ensure the safety and efficiency of hoisting operations.

[0093] In the scheme generation stage, generate detailed information such as hoisting sequence, hoisting point position, hoisting attitude, etc., to provide a clear basis for hoisting operations; Recommend the hammering force of the pile leg in soil layers at different depths according to soil layer characteristics and environmental factors; Determine the optimal installation time window to ensure the successful progress of hoisting operations.

[0094] In the present invention, unless otherwise clearly specified and limited, terms such as "installation", "connection", "connection", "fixation", etc. should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or integrated; It can be a mechanical connection, an electrical connection, or communication with each other; It can be directly connected, or indirectly connected through an intermediate medium. It can be the communication inside two components or the interaction relationship between two components, unless otherwise clearly limited. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0095] Obviously, the above-described embodiments are only a part of the embodiments of the present invention, rather than all embodiments. The accompanying drawings show the preferred embodiments of the present invention, but do not limit the patent scope of the present invention. The present invention can be implemented in many different forms. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosed content of the present invention more thorough and comprehensive. Although the present invention has been described in detail with reference to the foregoing embodiments, for those skilled in the art, they can still modify the technical solutions recorded in the foregoing specific embodiments, or perform equivalent replacements for some of the technical features. Any equivalent structures directly or indirectly using the content of the specification and drawings of the present invention in other related technical fields are equally within the scope of the patent protection of the present invention.

Claims

1. An installation method for an offshore wind turbine in a thick soft soil covering layer, characterized in that It includes the following steps: Data collection and preparation: Collect the geological data and environmental data of the site area, select the lifting vessel and equipment, and prepare the jacking legs, hammering equipment, cooling device and solidifying materials. Jacking leg installation: Pretreat the jacking legs to reduce the frictional resistance, dynamically adjust the hammering energy by using the layer-by-layer hammering method, and at the same time inject the solidifying materials during the hammering process to enhance the soil bearing capacity, ensure that the jacking legs penetrate to the designed depth and maintain the verticality. Wind turbine hoisting: Hoist the wind turbine tower, nacelle and blades in sections onto the jacking legs, ensure the centering accuracy and levelness, and monitor the environmental parameters in real time during the hoisting process to ensure the operation safety. Post-inspection and commissioning: Check the installation quality of each component of the wind turbine, commission the electrical and control systems, conduct a trial run and clean up the operation site. The jacking leg installation includes the following steps: Jacking leg pre-cooling: Apply liquid nitrogen to the bottom of the jacking legs, cool them to a certain low temperature to form a hardened layer, and reduce the frictional resistance during the hammering process.

2. The installation method of an offshore wind turbine in a deep soft soil covering layer according to claim 1, wherein, The data collection and preparation includes the following steps: Data collection: Collect the soil layer distribution, soil hardness, water content of the geological data of the site area and the wind speed, wave height and tide of the environmental data. Equipment and material preparation: Select a lifting vessel with sufficient lifting capacity, equip it with a dynamic positioning system, and prepare the jacking legs, hydraulic hammering equipment, liquid nitrogen cooling device and solidifying agent.

3. A method for installing an offshore wind turbine in a thick soft soil covering layer according to claim 2, characterized in that, The jacking leg installation further includes the following steps: Initial hammering: Hoist the jacking legs to the target position, start the hydraulic hammering equipment, in the soft soil layer, use low-energy hammering (500 - 800 kJ), and monitor the inclination of the jacking legs in real time to ensure that the inclination ≤ 1°. Layer-by-layer hammering: When the jacking legs enter the hard soil layer, increase the hammering energy to ensure the penetration efficiency. After hammering a certain number of times, check the penetration depth and inclination of the jacking legs to ensure that the penetration speed ≥ 0.5 m / min and the inclination ≤ 1°.

4. A method for installing an offshore wind turbine in a deep soft soil covering layer according to claim 3, characterized in that, The jacking leg installation further includes the following steps: Soil solidification: During the hammering process, inject cement slurry around the jacking legs to locally harden the soft soil and improve the soil bearing capacity.

5. The installation method of an offshore wind turbine in a deep soft soil covering layer according to claim 4, characterized in that, The jacking leg installation further includes the following steps: Final penetration: When the jacking legs are close to the designed depth, reduce the hammering energy to ensure the penetration accuracy, check the pile top elevation to ensure that the penetration depth error ≤ 10 cm.

6. The installation method of an offshore wind turbine in a deep soft soil covering layer according to claim 5, characterized in that, The wind turbine hoisting includes the following steps: Tower installation: Hoist the tower onto the jacking legs and use the hydraulic adjustment device to ensure the centering accuracy. Nacelle and blade installation: Hoist the nacelle to the top of the tower, use a level to ensure the levelness of the nacelle, and hoist the blades in sequence. During the hoisting process, monitor the wind speed and wave height in real time to ensure that the wind speed ≤ 12 m / s and the wave height ≤ 2 m.

7. The installation method of an offshore wind turbine in a deep soft soil cover layer according to claim 6, characterized in that, The post-inspection and commissioning includes the following steps: Structural inspection: Check the installation quality of the jacking legs, tower, nacelle and blades to ensure that each component meets the design requirements, and check the verticality of the tower through a laser rangefinder. System commissioning: Commission the electrical system and control system of the wind turbine to ensure its normal operation, conduct a trial run, and check the power generation performance of the wind turbine. Environmental restoration: Clean up the operation site and restore the marine environment.

8. An analysis data model for the installation of an offshore wind turbine in a thick soft soil cover layer, using the installation method of an offshore wind turbine in a thick soft soil cover layer as described in claim 7, characterized in that, It includes: In the data collection stage, geological information on the structure of the upper-middle foundation soil, soil layer distribution, and soil mechanical properties in the field area is collected. Environmental parameters such as wind speed, wind direction, wave height, tide, and seawater temperature are collected in real time using meteorological and ocean monitoring equipment. The specifications and performance parameters of the lifting vessel and lifting equipment are collected, including lifting capacity, stability, and operating range. Key parameters during the lifting process are recorded, including lifting methods, pile driving methods, hammering energy, and number of hammer blows. In the data preprocessing stage, data from different sources are integrated to form a unified data format and storage method. The data is standardized to eliminate the influence of different dimensions and data ranges on the analysis results. The dataset is divided into a training set, a validation set, and a test set, which are used for model training, model tuning, and model performance evaluation respectively. In the data analysis and simulation stage, based on environmental data, vessel and machinery data, and lifting process data, the lifting process is simulated. Considering soil layer characteristics, environmental factors, and vessel and machinery performance, the optimal installation time and process are determined. According to soil layer characteristics and lifting parameters, the risk of pile slipping is predicted and preventive measures are proposed. According to the hardness of different soil layers, the hammering force is automatically adjusted to ensure the smooth progress of the pile driving process. In the plan generation stage, detailed information on the lifting sequence, lifting point position, and lifting attitude is generated. According to soil layer characteristics and environmental factors, the hammering force of the pile legs in soil layers at different depths is recommended, and the optimal installation time window is determined to ensure the safety and efficiency of the lifting operation.

9. The data analysis model for the installation of an offshore wind turbine with a thick soft soil cover layer according to claim 8, characterized in that, In the data preprocessing stage, the data is processed using standardization methods, including Z-score standardization and Min-Max standardization, to eliminate the influence of different dimensions and data ranges on the analysis results.

10. The data analysis model for the installation of an offshore wind turbine in a thick soft soil cover layer according to claim 9, characterized in that, In the data analysis and simulation stage, by simulating the lifting process, considering meteorological, oceanic environment, vessel and machinery performance, and geological conditions comprehensively, the optimal lifting time window is determined, and the hammering force is dynamically adjusted according to the soil layer hardness to reduce the risk of pile slipping and improve the lifting efficiency.

Citation Information

Patent Citations

  • Pre-tensioning pile-anchor combined foundation for shallow covering layer seabed and construction method of pre-tensioning pile-anchor combined foundation

    CN114763698A