Supporting and positioning device for barrage rubble stepping stone construction
By designing the steel support positioning device, the problem of inconsistent installation positions and difficult installation of the stepping stones on the top of the weir dam was solved, and construction was realized synchronously with concrete pouring, which improved the integrity and stability and simplified the construction process.
Patent Information
- Application Number
- CN202420360836.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-26
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-02-26
AI Technical Summary
When installing paving stones on the top of weirs and dams in water conservancy projects, the existing construction methods of reserved slots or reserved boxes lead to inconsistent positioning of the paving stones, difficult installation, long construction period, weak integrity and stability, and cannot be combined with Concrete pouring takes place simultaneously.
Design a support positioning device made of steel bars, including horizontal fixing frames and longitudinal fixing frames arranged side by side. The length and width of the steel bars are matched with the stepping stone, and the height of the supporting section and the protruding section is set to achieve the stability of the stepping stone. Precise positioning and fixation, and reinforcement through welding and tie bars to ensure synchronization with concrete pouring.
The Tingbu stones are accurately positioned, arranged neatly, have straight axes, are firmly fixed, and have strong integrity with the weir and dam, which reduces construction waiting time and improves construction efficiency and project smoothness.
Smart Images

Figure CN221918843U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of stepping stone construction, in particular to a supporting and positioning device used for the construction of rough stone stepping stone of a dam. Background Art
[0002] Stepping stones are stones arranged in shallow water at a certain interval, allowing people to step across. With the development of society, during the construction of water conservancy projects, stepping stones are often set on the top of the dam to facilitate passage and integrate it with the surrounding landscape.
[0003] At present, when installing stepping stones on the top of the weir of a hydraulic project, the construction method of reserved grooves or reserved boxes is mainly adopted. The principle of these two construction methods is to reserve space in advance according to the size and position of the stepping stones. After waiting for the concrete on the top of the weir to be poured and solidified, the reserved boxes or reserved grooves are processed and then the stepping stones are installed.
[0004] However, the reserved grooves or reserved boxes cannot be fixed in advance or are inconvenient to fix. When the concrete is formed, the reserved grooves or reserved boxes are easily squeezed by the concrete to cause deformation or position movement. Since the deformation and displacement of each reserved groove or reserved box are different, and the amount of connecting materials (concrete, glue) used between the stepping stone and the reserved grooves or reserved boxes is difficult to control when installing the stepping stone, the stepping stones arranged by this method are prone to inconsistent heights and horizontal and vertical positions, making the axis between the stepping stones after installation not straight, the arrangement is not neat, and the ups and downs are not beautiful. In addition, when the reserved grooves or reserved boxes are used for construction, the pouring of the weir top concrete and the installation and fixing of the stepping stones cannot be carried out simultaneously. It is necessary to wait for the weir top concrete to be poured and solidified before installing and fixing the stepping stones. The installation is difficult, the construction period is long, and the integrity and stability are not strong. Utility Model Content
[0005] In order to solve the above technical problems, the utility model provides a support and positioning device for the construction of rough stone stepping stones of dams. The support and positioning device is made of steel bars and can be used to realize the precise positioning, supporting placement and stable fixation of stepping stones, so that the position of the stepping stones is accurate, the arrangement is neat, and the axis is straight. Moreover, the installation and fixation of the stepping stones can be carried out simultaneously with the pouring of concrete on the top of the dam. The stepping stones are more firmly fixed, have a strong integrity with the dam, and are more beautiful and harmonious.
[0006] In order to achieve the above-mentioned purpose, the utility model provides a supporting and positioning device for the construction of rough stone stepping stones of dams, comprising two transverse fixing frames arranged side by side, the middle parts of the two transverse fixing frames are commonly connected with a longitudinal fixing frame perpendicular to them, the transverse fixing frame comprises a first transverse steel bar parallel to the horizontal plane and two first vertical steel bars vertically arranged at both ends of the first transverse steel bar, the length of the first transverse steel bar is equal to the length of the stepping stone, and two vertical supporting steel bars are symmetrically arranged on the first transverse steel bar; the longitudinal fixing frame comprises a second longitudinal steel bar parallel to the horizontal plane and two second vertical steel bars vertically arranged at both ends of the second longitudinal steel bar, the length of the second longitudinal steel bar is equal to the width of the stepping stone.
[0007] A further technical solution is that the portion of the supporting steel bar extending below the first transverse steel bar is the supporting section, and the height h of the supporting section is set to be the difference between the pouring height H of the dam top concrete and the height h1 of the portion of the stepping stone buried in the concrete.
[0008] A further technical solution is that the heights of the first vertical steel bar and the second vertical steel bar are both set to 1 / 3-1 / 2 of the height h1 of the portion of the stepping stone embedded in the concrete.
[0009] A further technical solution is that a tensioning bar is fixedly connected between the supporting steel bar and the first transverse steel bar, and a plurality of reinforcing steel bars are fixedly connected between the two first transverse steel bars.
[0010] A further technical solution is that both the transverse fixing frame and the longitudinal fixing frame are made of a single steel bar, and the two ends of the steel bar are bent 90° to the same side by a bending machine, and the transverse fixing frame and the longitudinal fixing frame, and the transverse fixing frame and the supporting steel bar are fixed by welding.
[0011] A further technical solution is that the portion of the supporting steel bar extending above the first transverse steel bar is a protruding section, and the height of the protruding section is set to be greater than 1.75 times the diameter of the steel bar.
[0012] Beneficial effects of the utility model:
[0013] The utility model device is made of a support positioning device through steel bars, wherein the first transverse steel bar and the first longitudinal steel bar are respectively the same as the length and width of the stepping stone, which can control the transverse and longitudinal positions of the stepping stone when it is installed; the height of the support section is the difference between the height of the dam top concrete and the height of the part of the stepping stone buried in the concrete, which can conveniently control the elevation of the stepping stone when it is installed, thereby realizing the precise positioning of the stepping stone. When installing the support positioning device, the position of the support positioning device can be checked by hanging a plumb line to ensure that the installation position of the stepping stone is accurate. In addition, by setting the first vertical steel bar and the second vertical steel bar, not only can the stepping stone be protected and fixed when it is hoisted onto the support positioning device, it plays a limiting role to prevent the stepping stone from falling; it can also be embedded in the concrete as a reinforcing bar when the dam top concrete is poured, thereby increasing the fixing effect of the bottom of the stepping stone and improving the integrity and stability between the stepping stone and the dam.
[0014] The fixing of the stepping stone to the weir dam in the device of the utility model can be carried out simultaneously with the pouring of the weir crest concrete. Compared with the traditional construction using reserved grooves or reserved boxes, the device of the utility model has better stability, is not easy to be damaged or deformed, has more accurate positioning, and realizes the integrated cast-in-place construction of the stepping stone and the weir crest. The bottom of the stepping stone is buried in the weir crest concrete for fixing, so that the connection between the stepping stone and the weir dam is more firm and the integrity is stronger, which prolongs the service life of the stepping stone, reduces the construction waiting time, improves the construction efficiency, and ensures the smooth progress of the engineering project.
[0015] The utility model device can be applicable to the installation and construction of stepping stones of various arrangement types, has a wide application range, good effect, and is economical and practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 is a schematic diagram of the structure of the support positioning device;
[0017] Figure 2 is a schematic side view of the support locating device placed on the bottom panel concrete;
[0018] Figure 3 This is a schematic diagram of the front view position relationship of the stepping stones after the concrete of the dam top is poured;
[0019] Figure 4 is a schematic diagram of Example 1 during lofting;
[0020] Figure 5 is a schematic diagram of Example 2 during lofting;
[0021] Figure 6 is another schematic diagram of Example 2 during lofting;
[0022] Figure 7 It is a schematic diagram of the effect of the completion of the construction of Example 2.
[0023] In the figure:
[0024] 1. Support and positioning device, 11. Longitudinal fixing frame, 111. Second longitudinal reinforcement, 112. Second vertical reinforcement, 12. Transverse fixing frame, 121. First transverse reinforcement, 122. First vertical reinforcement, 13. Tension reinforcement, 14. Reinforcement reinforcement, 15. Support reinforcement, 151. Support section, 152. Protruding section, 2. Bottom panel concrete, 3. Weir top concrete, 4. Binding reinforcement, 5. Stepping stone, 51. Part of stepping stone buried in concrete, 52. Part of stepping stone exposed in concrete, 6. Control point, 7. Marking point, 8. Control line, 9. Positioning area. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] Embodiment 1:
[0027] like Figure 1-Figure 4 As shown, a certain weir dam includes bottom panel concrete 2 and weir crest concrete 3, and a row of parallel stepping stones 5 are installed on the top surface of the weir crest concrete 3 of the weir dam. The construction process of this embodiment is: first pour the bottom panel concrete 2 and cure it, then tie the weir dam steel bars 4, and finally construct the stepping stones 5 and pour the weir crest concrete 3 on the bottom panel concrete 2.
[0028] The construction method of rough stone stepping of weir dam is as follows:
[0029] (1) In a processing plant, rough stones are processed into stepping stones 5, and the dimensions of the stepping stones 5 are uniformly 100×40×50 cm (length×width×height). A supporting and positioning device 1 is manufactured according to the construction drawings. The supporting and positioning device 1 includes two transverse fixing frames 12 arranged side by side, and the middle parts of the two transverse fixing frames 12 are commonly connected to a longitudinal fixing frame 11 perpendicular thereto. The transverse fixing frame 12 includes a first transverse steel bar 121 parallel to the horizontal plane and two first vertical steel bars 122 vertically arranged at both ends of the first transverse steel bar 121. The length of the first transverse steel bar 121 is equal to the length of the stepping stone 5, and the length of the first transverse steel bar 121 is 100 cm. Two vertical supporting steel bars 15 are symmetrically arranged on the first transverse steel bar 121; the longitudinal fixing frame 11 includes a second longitudinal steel bar 111 parallel to the horizontal plane and two second vertical steel bars 112 vertically arranged at both ends of the second longitudinal steel bar 111. The length of the second longitudinal steel bar 111 is equal to the width of the stepping stone 5, and the length of the second longitudinal steel bar 111 is 40 cm.
[0030] When manufacturing the support and positioning device 1, the transverse fixing frame 12 and the longitudinal fixing frame 11 are both made of a single steel bar, and the two ends of the steel bar are bent 90 degrees to the same side by a bending machine. The transverse fixing frame 12 and the longitudinal fixing frame 11, and the transverse fixing frame 12 and the supporting steel bar 15 are fixed by welding.
[0031] The portion of the support steel bar 15 extending below the first transverse steel bar 121 is the support section 151. The height h of the support section 151 is set to the difference between the pouring height H of the weir top concrete 3 and the height h1 of the stepping stone embedded in the concrete portion 51. The pouring height H of the weir top concrete and the height h1 of the stepping stone embedded in the concrete portion 51 are both recorded in the construction drawing. By controlling the height of the support section 151, the installation height of the stepping stone 5 is accurately positioned to ensure the correct position of the stepping stone 5.
[0032] The portion of the support steel bar 15 extending above the first transverse steel bar 121 is a protruding section 152, and the height of the protruding section 152 is set to be greater than 1.75 times the diameter of the steel bar to reduce the impact of the steel bar bending.
[0033] The height of the first vertical steel bar 122 and the second vertical steel bar 112 are both set to 1 / 3-1 / 2 of the height h1 of the stepping stone buried in the concrete part 51, which not only allows them to be buried in the concrete together with the bottom of the stepping stone 5, helping to fix the position of the stepping stone 5, but also reserves a sufficient concrete protective layer thickness.
[0034] A tie bar 13 is fixedly connected between the support steel bar 15 and the first transverse steel bar 121, and a reinforcing steel bar 14 is fixedly connected between the two first transverse steel bars 121. Preferably, the support steel bar 15, the reinforcing steel bar 14 and the first transverse steel bar 121 are vertically connected to each other and intersect at one point, and the stability of the support positioning device 1 is improved by providing the tie bar 13 and the reinforcing steel bar 14.
[0035] (2) After the concrete 2 of the bottom panel of the dam is cast and the reinforcement 4 of the dam is tied, the control points 6 and the marking points 7 are arranged row by row according to the construction drawings. The control points 6 are arranged on both sides of the dam according to the longitudinal position of the outer edge of the row of stepping stones 5. The marking points 7 are arranged in the center of the bottom panel concrete 2 according to the longitudinal and transverse positions of the four vertices of each stepping stone 5.
[0036] Before staking out according to the construction drawings, the surveyors shall set up a total station at a known point and build a coordinate system, with the length of the weir as the horizontal coordinate and the width of the weir as the vertical coordinate. Figure 4 As shown, two groups of control points 6 are arranged according to the minimum and maximum values of the vertical coordinates of the orthographic projection of the row of stepping stones 5 on the dam. The first group of control points is arranged on both sides of the dam according to the maximum value of the vertical coordinate (see Figure 4 Y1 and Y1' in the middle upper row), a set of control points are set on both sides of the weir according to the minimum value of the ordinate (see Figure 4 Y1 and Y1' in the middle and lower rows). According to the horizontal and vertical coordinates of the four vertices of the positive projection of each stepping stone 5 in this row on the dam, mark points 7 are arranged on the bottom panel concrete 2, such as Figure 4 As shown, the four marking points 7 of the first stepping stone 5 are set to A1, B1, C1 and D1 in clockwise order, and the marking points 7 of other stepping stones 5 are arranged in the same way. The control points 6 and marking points 7 made by the total station are marked with a marker or paint.
[0037] (3) Connect the four marking points 7 belonging to the same stepping stone 5 to form a rectangular positioning area 9, which has the same shape and size as the stepping stone 5. Set lines between the control points 6 at the same longitudinal position to form a control line 8, and the elevation of the control line 8 is set within the elevation range of the exposed concrete part 52 of the stepping stone.
[0038] Use paint or marker to connect the marking points A1, B1, C1, and D1 in sequence to form a rectangular positioning area Z1 of the first stepping stone 5, and similarly, lay out the positioning areas Z2, Z3, and Z4 of the other three stepping stones 5 in the row in sequence in the center of the dam.
[0039] Vertical poles perpendicular to the ground are set up at two control points Y1 and Y1' belonging to the same group, and a nylon line is pulled between the two vertical poles as a control line 8 and kept in a straight and tight state. By setting two rows of control lines, it is verified whether the arrangement of the stepping stones is neat.
[0040] (4) Professional measurement personnel use infrared ray meter to check and re-measure steps (2) and (3).
[0041] (5) Place the supporting positioning device 1 on the bottom panel concrete 2 in sequence according to the indication of the positioning area 9.
[0042] When placing the support positioning device 1, plumb lines are hung at the bending points at both ends of the longitudinal fixing frame 11 and the two transverse fixing frames 12 (the bending point of the longitudinal fixing frame 11 is the connection point between the second longitudinal steel bar 111 and the second vertical steel bar 112, and the bending point of the transverse fixing frame 12 is the connection point between the first transverse steel bar 121 and the first vertical steel bar 122). If the positioning area 9 is all located on the inner side of the six plumb lines, the support positioning device 1 is placed correctly, otherwise continue to adjust until the position is correct.
[0043] After the position of the support positioning device 1 is determined, the four support steel bars 15 of the support positioning device 1 are fixedly connected to the non-main structural steel bars of the dam. When fixing, welding, wire binding or fastener clamping can be used.
[0044] (6) A plurality of stepping stones 5 are hoisted onto the supporting and positioning device 1 in sequence; and the control line 8 is used to verify whether the placement of the row of stepping stones is correct. If not, they are readjusted until the position is correct; after the inspection is correct, the next row of stepping stones is laid out and installed until all the stepping stones are placed.
[0045] When stepping stone 5 is hoisted onto supporting positioning device 1 by crane, if control line 8 is always close to the outer edge of the side wall of stepping stone 5 and remains straight, stepping stone 5 is accurately placed. Otherwise, support positioning device 1 or stepping stone 5 is readjusted until the position is correct.
[0046] (7) After all the stepping stones 5 are placed, pour the dam top concrete 3 to the designed elevation, vibrate it sufficiently, cover the concrete surface with insulation cotton, and sprinkle water to maintain the concrete in shape.
[0047] Before pouring concrete, the exposed concrete portion 52 of the stepping stone is covered with EVA plastic film for protection, leaving only the exposed concrete portion 51 of the stepping stone unprotected, to ensure that when pouring concrete, the outer surface of the stepping stone 5 will not be contaminated and its appearance will not be affected.
[0048] When pouring concrete, a concrete mixer truck is used to transport the concrete to the pouring area at the top of the dam, and the concrete is transported vertically into the warehouse through a car pump. A high-frequency vibrator is used for concrete vibrating, and the holes of the vibrator are arranged in a plum blossom shape. The vibration time at each position is about 20-30 seconds, until the concrete no longer sinks significantly, no bubbles appear, and begins to overflow. The vibration operation is strictly carried out in accordance with the requirements of the operating procedures. During vibration, the vibrator shall not touch the dam binding steel bars 4 and embedded parts, especially the stepping stones 5. The vertical distance between the vibrator and the dam concrete formwork shall not be less than 1 / 2 of the effective action radius of the vibrator, and the displacement spacing of the vibrator shall not exceed 1.5 times the effective action radius of the vibrator.
[0049] Embodiment 2:
[0050] like Figure 5-Figure 7 As shown, in Example 2, two rows of staggered stepping stones 5 are installed on the top of the same weir as in Example 1. The specific steps of stepping stone construction are as follows:
[0051] (1) In a processing plant, rough stones are processed into stepping stones 5 of uniform size, and a supporting and positioning device 1 is manufactured according to the size of the stepping stones 5 and the construction drawings. The structure of the supporting and positioning device 1 of this embodiment is the same as that of the embodiment 1, and will not be described in detail.
[0052] When manufacturing the support and positioning device 1, the transverse fixing frame 12 and the longitudinal fixing frame 11 are both made of three steel bars, and two short steel bars are vertically welded and fixed to the same side of the two ends of the long steel bars during processing. The transverse fixing frame 12 and the longitudinal fixing frame 11, and the transverse fixing frame 12 and the supporting steel bars 15 are fixed by welding.
[0053] (2) After the concrete 2 of the bottom panel of the dam is cast and the reinforcement 4 of the dam is tied, the stepping stones are laid out row by row (those arranged on the same straight line are the same row) according to the construction drawings. Control points 6 are arranged on both sides of the dam according to the longitudinal position of the outer edge of the row of stepping stones 5. Marking points 7 are arranged at the center of the bottom panel concrete 2 according to the longitudinal and transverse positions of the four vertices of each stepping stone 5 in the row.
[0054] Before staking out, surveyors set up total stations at known points and build a coordinate system, with the length of the weir as the horizontal coordinate and the width of the weir as the vertical coordinate. Figure 6 As shown, firstly, the first row of stepping stones 5 is laid out, and a group of control points is arranged according to the maximum value of the vertical coordinate of the orthographic projection of the first row of stepping stones 5 on the dam. The two control points 6 set on both sides of the dam are Y1 and Y1', and the control points 6 are marked with a marker or paint. Then, four marking points 7 are arranged on the bottom panel concrete 2 in order from left to right according to the horizontal and vertical coordinates of the four vertices of the orthographic projection of each stepping stone 5 in the first row on the dam, and the marking points 7 are marked with a marker or paint.
[0055] (3) Use paint or a marker to sequentially connect the four marking points 7 of the first stepping stone 5 in the first row to form a positioning zone Z1, and similarly, continue to lay out the positioning zone Z2 of the second stepping stone 5 in the first row.
[0056] An infrared ray meter is set up at the control point Y1, and it emits infrared rays to the control point Y1' as the control line 8, and the elevation of the infrared rays is set within the elevation range of the exposed concrete part 52 of the stepping stone. A black baffle is placed on the control point Y1', and a marking line is drawn on the black baffle, so that the marking line is perpendicular to the ground and the extension direction passes through the control point Y1'.
[0057] (4) After the first row of stepping stones are laid out, they will be inspected and re-measured by professional surveying personnel.
[0058] (5) Then, the support positioning device 1 is placed on the bottom panel concrete 2 according to the indication of the positioning area 9, and a plumb line is hung to determine whether the placement position of the support positioning device 1 is correct. After confirming that the position is correct, the support steel bar 15 is fixedly connected to the non-main structure steel bar of the dam.
[0059] (6) Hoist multiple stepping stones 5 onto the support and positioning device 1 in sequence. During the installation process, if a red dot always appears on the marking line on the baffle, the position is correct. Otherwise, readjust the stepping stone 5 or the support and positioning device 1 until the position is correct. After verification, the second row of stepping stones 5 is laid out. Figure 7 As shown, a group of two control points Y2 and Y2' are arranged on both sides of the dam according to the maximum value of the vertical coordinate of the orthographic projection of the second row of stepping stones on the dam, and then the marking points 7 of each stepping stone 5 in the row are arranged in sequence from left to right. The steps of arranging the positioning area 9 and the control line 8 are the same as the arrangement method of the first row of stepping stones 5, which will not be repeated here. In this embodiment, each row of stepping stones is arranged with a group of control points 6 by an infrared ray meter. Since the stepping stones are regular rectangles, at least one group of control lines 8 can be arranged to complete the verification of the position of the stepping stones 5. And the infrared rays arranged by the infrared ray meter are used as control lines, which are not affected by wind force, deadweight, etc., and the verification is more accurate.
[0060] (7) Pour the dam top concrete 3 to the designed elevation, and after sufficient vibration, cover the concrete surface with insulation cotton and sprinkle water to maintain the shape. Before pouring concrete, cover the exposed concrete part 52 of the stepping stone with EVA plastic film for protection.
[0061] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
Claims
1. A support and positioning device for rough stone stepping construction of weirs and dams, characterized in that: It includes two transverse fixing frames arranged side by side, and the middle parts of the two transverse fixing frames are commonly connected to a longitudinal fixing frame perpendicular to them. The transverse fixing frames include a first transverse steel bar parallel to the horizontal plane and two first vertical steel bars vertically arranged at both ends of the first transverse steel bar, the length of the first transverse steel bar is equal to the length of the stepping stone, and two vertical supporting steel bars are symmetrically arranged on the first transverse steel bar; the longitudinal fixing frame includes a second longitudinal steel bar parallel to the horizontal plane and two second vertical steel bars vertically arranged at both ends of the second longitudinal steel bar, and the length of the second longitudinal steel bar is equal to the width of the stepping stone.
2. A supporting and positioning device for rough stone stepping construction of dams according to claim 1, characterized in that: The portion of the support steel bar extending below the first transverse steel bar is the support section, and the height h of the support section is set to the difference between the pouring height H of the dam top concrete and the height h1 of the portion of the stepping stone buried in the concrete.
3. A support and positioning device for rough stone stepping construction of dams according to claim 2, characterized in that: The heights of the first vertical steel bar and the second vertical steel bar are both set to 1 / 3-1 / 2 of the height h1 of the portion of the stepping stone embedded in the concrete.
4. A supporting and positioning device for rough stone stepping construction of dams according to claim 1, characterized in that: A tensioning bar is fixedly connected between the supporting steel bar and the first transverse steel bar, and a plurality of reinforcing steel bars are fixedly connected between the two first transverse steel bars.
5. A supporting and positioning device for rough stone stepping construction of dams according to claim 1, characterized in that: The transverse fixing frame and the longitudinal fixing frame are both made of a single steel bar, and the two ends of the steel bar are bent 90° to the same side by a bending machine. The transverse fixing frame and the longitudinal fixing frame, and the transverse fixing frame and the supporting steel bar are fixed by welding.
6. A supporting and positioning device for rough stone stepping construction of dams according to claim 5, characterized in that: The portion of the supporting steel bar extending above the first transverse steel bar is a protruding section, and the height of the protruding section is set to be greater than 1.75 times the diameter of the steel bar.