A differential pressure sliding sleeve for open hole staged fracturing
By designing the inclined end surface of the inner sliding sleeve and the shear pin connection, the problem of the existing pressure differential sliding sleeve cannot be opened is solved, the success rate of fracturing fluid entering the formation is improved, and the normal progress of fracturing construction is ensured.
Patent Information
- Application Number
- CN201811171960.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-10-09
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2038-10-09
AI Technical Summary
The existing pressure differential sliding sleeves are often unable to be opened in fracturing construction, resulting in failure of fracturing construction and reduced output.
A bare-eye segmented fracturing differential pressure slip sleeve is designed, the top end face of the inner sliding sleeve gradually tilts from outside to inside in the radial direction, and is fixedly connected to the outer cylinder through a shear pin, ensuring that it can be opened more easily under pressure. Improve the success rate of fracturing fluid entering the formation.
The success rate of opening the differential sliding sleeve is improved, ensuring that the fracturing fluid can enter the formation smoothly, and improving the success rate and normal operation of fracturing construction.
Smart Images

Figure CN109138916B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a device used in a horizontal well open hole completion staged fracturing process, in particular to an open hole staged fracturing pressure differential sliding sleeve. Background Art
[0002] In the process of shale gas and other tight oil and gas reservoir exploitation, horizontal well open hole completion combined with horizontal well staged fracturing can significantly save the time required for completion and related construction costs, and can well prevent secondary contamination of the reservoir by cement cementing construction. At the same time, the staged fracturing operation time is short, which can save a lot of fracturing operation time. The horizontal well open hole staged fracturing sliding sleeve packer string plays a key role in the horizontal well open hole completion staged fracturing process technology. It uses a multi-stage packer to mechanically seal the horizontal well open hole section. The string is lowered once, and the differential pressure sleeve is the first stage of the fracturing string, which determines the success or failure of the entire fracturing operation. In addition, the sealing of the packer depends on the pressure in the oil pipe before the differential pressure sleeve is opened, so it is necessary to ensure that the opening pressure of the differential pressure sleeve is greater than the sealing pressure of the packer. However, in current fracturing operations, the existing differential pressure sleeve often fails to open, which adversely affects the normal progress of the entire fracturing operation. In severe cases, it may even directly lead to the failure of the fracturing operation and reduce production.
[0003] Therefore, it is necessary to improve the design of the existing pressure differential sleeve. Summary of the invention
[0004] The object of the present invention is to provide a differential pressure sliding sleeve for open hole staged fracturing, which can effectively improve the opening success rate of the existing differential pressure sliding sleeve.
[0005] To achieve the above-mentioned object, the present invention provides an open hole staged fracturing pressure differential sleeve, wherein the open hole staged fracturing pressure differential sleeve comprises an outer sleeve and an inner sleeve, the outer sleeve and the inner sleeve are both vertically arranged cylindrical bodies that penetrate up and down, the outer sleeve is sleeved outside the inner sleeve and is fixedly connected to the inner sleeve through a shear pin, the inner sleeve comprises a first connecting portion, a sliding portion and a second connecting portion that are sequentially arranged from top to bottom, the first connecting portion and the second connecting portion are respectively sealed with the inner wall of the outer sleeve, the height of the sliding portion is greater than the height of the first connecting portion, the outer diameter of the sliding portion is smaller than the outer diameter of the first connecting portion, and a first step is formed at the bottom end of the first connecting portion, the sliding portion is spaced from the inner wall of the outer sleeve, the sliding portion and the inner wall of the outer sleeve are enclosed to form an annular sliding cavity, the outer wall of the outer sleeve is provided with a fracturing hole that is connected to the sliding cavity, and the end surface of the top end of the inner sleeve is gradually inclined downward from the outside to the inside along the radial direction of the inner sleeve.
[0006] As described above, the open hole staged fracturing differential pressure sleeve, wherein the outer diameter of the second connecting portion is the same as the outer diameter of the sliding portion, and a third connecting portion corresponding to the second connecting portion is provided on the inner wall of the outer cylinder, and the third connecting portion is convex inwardly along the radial direction of the outer cylinder, and the inner wall of the third connecting portion is sealingly matched with the side wall of the second connecting portion.
[0007] As described above, in the open hole staged fracturing differential pressure sleeve, a pressure relief hole communicating with the sliding cavity is provided on the outer wall of the outer cylinder, and the pressure relief hole is located at the bottom end of the sliding cavity.
[0008] As described above, the open hole staged fracturing pressure differential sleeve, wherein a thrust piece is further arranged between the outer cylinder and the inner sleeve, the side wall of the first connecting portion is provided with a first mounting groove opened along its circumference, the thrust piece is sleeved in the first mounting groove, the inner wall of the outer cylinder is provided with a limiting groove which can correspond to the thrust piece, the limiting groove is opened along the circumference of the outer cylinder, the limiting groove is located below the fracturing hole, and the distance between the limiting groove and the thrust piece is the same as the height of the sliding cavity.
[0009] In the open hole staged fracturing differential pressure sleeve as described above, the thrust piece is an open ring, the open ring is sleeved in the first mounting groove, and the outer wall of the open ring gradually expands in diameter from bottom to bottom.
[0010] As described above, in the open hole staged fracturing differential pressure sleeve, there is one or more sealing rings disposed between the first connection portion and the outer cylinder, and between the second connection portion and the outer cylinder.
[0011] The open hole staged fracturing pressure differential sleeve as described above, wherein a first sealing ring and a second sealing ring are sleeved between the first connecting portion and the outer cylinder, a first sealing ring groove for installing the first sealing ring and a second sealing ring groove for installing the second sealing ring are opened on the side wall of the first connecting portion, the first sealing ring groove and the second sealing ring groove are both opened along the circumference of the first connecting portion, the first sealing ring groove is arranged above the second sealing ring groove and has a gap with the second sealing ring, and the width of the first sealing ring groove is greater than the width of the second sealing ring groove.
[0012] As described above, the open hole staged fracturing pressure differential sleeve further comprises an upper joint and a lower joint, both of which are vertically arranged cylindrical bodies that penetrate from top to bottom, and the upper joint and the lower joint are respectively fixedly connected to the upper and lower ends of the outer cylinder.
[0013] As described above, the open hole staged fracturing pressure differential sleeve, wherein the top end of the lower joint is sleeved in the outer tube and fixedly connected to the inner wall of the outer tube, the distance between the top end of the lower joint and the bottom end of the inner sleeve is the same as the height of the sliding cavity, and the inner sleeve, after sliding down, abuts against the lower joint.
[0014] As described above, in the open hole staged fracturing differential pressure sleeve, the outer tube and the upper joint, as well as the outer tube and the lower joint are both threadedly connected, and a top screw is also provided between the outer tube and the upper joint, as well as between the outer tube and the lower joint, respectively. The top screw passes through the side wall of the outer tube and is inserted on the upper joint or the lower joint.
[0015] Compared with the prior art, the present invention has the following characteristics and advantages:
[0016] The open hole staged fracturing differential pressure sleeve proposed by the present invention has an inner sleeve whose top end surface is gradually tilted downward from the outside to the inside along the radial direction of the inner sleeve to achieve a better pressure transmission effect, thereby ensuring that the inner sleeve can be opened more easily during fracturing operations, improving the success rate of opening the open hole staged fracturing differential pressure sleeve, allowing the fracturing fluid to smoothly enter the formation, improving the success rate of fracturing operations, and ensuring that the fracturing operation proceeds normally.
[0017] The inner sliding sleeve of the open hole staged fracturing differential pressure sliding sleeve proposed by the present invention is reasonably compact in structural design and easy to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The accompanying drawings described herein are only for explanation purposes and are not intended to limit the scope of the present invention in any way. In addition, the shapes and proportional dimensions of the various components in the figures are only schematic, used to help understand the present invention, and are not specifically limited to the shapes and proportional dimensions of the various components of the present invention. Those skilled in the art can select various possible shapes and proportional dimensions to implement the present invention according to the teachings of the present invention.
[0019] Figure 1 This is a schematic diagram of the structure of the differential pressure sliding sleeve for open hole staged fracturing proposed by the present invention;
[0020] Figure 2 It is a schematic diagram of the structure of the outer cylinder in the present invention;
[0021] Figure 3 It is a schematic diagram of the structure of the inner sliding sleeve in the present invention;
[0022] Figure 4 for Figure 3 A partial enlarged view of point C in the middle;
[0023] Figure 5 It is a partial enlarged view of the first connecting portion of the inner sleeve in the present invention (I);
[0024] Figure 6 This is a partial enlarged view of the first connecting portion of the inner sleeve in the present invention (II).
[0025] Description of reference numerals:
[0026] 10. Outer cylinder; 11. Fracturing hole;
[0027] 12. The third connecting portion; 13. The second step;
[0028] 14. Pressure relief hole; 15. Limiting groove;
[0029] 20. Inner sliding sleeve; 21. First connecting portion;
[0030] 22. Sliding portion; 23. Second connecting portion;
[0031] 24. First step; 25. Sliding cavity;
[0032] 26. end surface; 27. first mounting groove;
[0033] 28. First sealing ring groove; 29. Second sealing ring groove;
[0034] 30. Shear pin; 40. Thrust piece;
[0035] 50. Sealing ring; 60. Upper joint;
[0036] 70. Lower joint; 80. Top screw. DETAILED DESCRIPTION
[0037] The details of the present invention can be more clearly understood with reference to the accompanying drawings and the description of the specific embodiments of the present invention. However, the specific embodiments of the present invention described herein are only used for the purpose of explaining the present invention and cannot be understood as limiting the present invention in any way. Under the guidance of the present invention, technicians can conceive of any possible variations based on the present invention, which should all be considered to belong to the scope of the present invention.
[0038] like Figures 1 to 6As shown, the open hole staged fracturing differential pressure sleeve proposed by the present invention comprises an outer sleeve 10 and an inner sleeve 20, both of which are vertically arranged and vertically penetrated cylindrical bodies, the outer sleeve 10 is sleeved outside the inner sleeve 20 and is fixedly connected to the inner sleeve 20 through a shear pin 30, and the inner sleeve 20 comprises a first connecting portion 21, a sliding portion 22 and a second connecting portion 23 which are sequentially arranged from top to bottom, the first connecting portion 21 and the second connecting portion 23 are respectively sealed with the inner wall of the outer sleeve 10, and the sliding portion 2 ... The height of the sliding portion 22 is greater than the height of the first connecting portion 21, the outer diameter of the sliding portion 22 is smaller than the outer diameter of the first connecting portion 21 and a first step 24 is formed at the bottom end of the first connecting portion 21, the sliding portion 22 is spaced apart from the inner wall of the outer cylinder 10 and is enclosed with the inner wall of the outer cylinder 10 to form an annular sliding cavity 25, a fracturing hole 11 connected to the sliding cavity 25 is opened on the outer wall of the outer cylinder 10, and the end face 26 of the top end of the inner sleeve 20 is gradually inclined downward from the outside to the inside along the radial direction of the inner sleeve 20.
[0039] The open hole staged fracturing pressure differential sleeve proposed in the present invention is installed between the fracturing pipe string and the pressure holding device. When the open hole staged fracturing pressure differential sleeve needs to be opened, fracturing fluid is injected into the fracturing pipe string, and the fracturing fluid enters the outer tube 10 and acts on the end face 26 at the top of the inner sleeve 20, so that the inner sleeve 20 is subjected to a downward thrust (pressure). When the thrust reaches a certain value, the shear pin 30 is sheared off under the action of the thrust (pressure), and the inner sleeve 20 moves downward. When the first connecting portion 21 descends to the corresponding position at the lower part of the fracturing hole 11, the fracturing hole 11 is opened, and the fracturing hole 11 is connected to the formation to establish a fracturing channel. The fracturing fluid enters the formation through the fracturing hole 11, thereby fracturing the formation.
[0040] The end surface 26 at the top of the inner sleeve 20 of the open hole staged fracturing differential pressure sleeve proposed by the present invention is gradually inclined downward from the outside to the inside along the radial direction of the inner sleeve 20 to achieve a better pressure transmission effect, thereby ensuring that the inner sleeve 20 can be opened more easily during the fracturing operation, improving the success rate of opening the open hole staged fracturing differential pressure sleeve, allowing the fracturing fluid to smoothly enter the formation, improving the success rate of the fracturing operation, and ensuring the normal progress of the fracturing operation.
[0041] The inner sleeve 20 of the open hole staged fracturing differential pressure sleeve proposed by the present invention is reasonably compact in structure design and easy to use.
[0042] In an optional example of the present invention, the inclination angle β of the end surface 26 (the angle between the end surface 26 and the horizontal plane) ranges from 3 degrees to 7 degrees.
[0043] In an optional example, the inclination angle β of the end surface 26 is 5 degrees.
[0044] In an optional example of the present invention, a plurality of fracturing holes 11 are opened on the outer wall of the outer cylinder 10 , and the plurality of fracturing holes 11 are evenly distributed along the circumference of the outer cylinder 10 .
[0045] In an optional example of the present invention, the outer diameter of the second connection part 23 is the same as the outer diameter of the sliding part 22, and a third connection part 12 corresponding to the second connection part 23 is provided on the inner wall of the outer cylinder 10. The third connection part 12 protrudes inward along the radial direction of the outer cylinder 10 and forms a second step 13 at the top of the third connection part 12. The inner wall surface of the third connection part 12 is sealed with the side wall surface of the second connection part 23. The distance between the first step 24 and the second step 13 is the height of the sliding cavity 25 (also the height of the sliding part 22). When the shear pin 30 is cut off, the inner sleeve 20 slides downward. When the first step 24 on the inner sleeve 20 abuts against the second step 13 on the inner wall of the outer cylinder 10, the inner sleeve 20 stops descending to prevent the inner sleeve 20 from falling off the outer cylinder 10 and affecting subsequent construction operations.
[0046] In an optional example of the present invention, a pressure relief hole 14 communicating with the sliding cavity 25 is provided on the outer wall of the outer cylinder 10. The pressure relief hole 14 is located at the bottom end of the sliding cavity 25 to facilitate the discharge of the fluid in the sliding cavity 25 when the inner sleeve 20 moves downward.
[0047] In an optional example of the present invention, a pin installation groove is opened on the side wall of the first connecting part 21, and a shear pin hole is correspondingly opened on the outer cylinder 10. The shear pin 30 passes through the corresponding shear pin hole and is inserted into the pin installation groove.
[0048] In an optional example of the present invention, Figure 6 As shown, the pin installation groove formed on the inner sleeve 20 may not be chamfered or rounded to prevent the shear pin 30 from being unable to be cut off.
[0049] In an optional example, a plurality of shear pins 30 are disposed between the first connecting portion 21 and the outer cylinder 10 , and the plurality of shear pins 30 are evenly distributed along the circumference of the outer cylinder 10 .
[0050] Furthermore, the shear pins 30 and the fracturing holes 11 are arranged alternately.
[0051] In an optional example of the present invention, a thrust piece 40 is further provided between the outer cylinder 10 and the inner sleeve 20, a first mounting groove 27 is provided on the side wall of the first connecting portion 21 along the circumference thereof, the thrust piece 40 is sleeved in the first mounting groove 27, a limiting groove 15 which can be matched with the thrust piece 40 is provided on the inner wall of the outer cylinder 10, the limiting groove 15 is provided along the circumference of the outer cylinder 10, the limiting groove 15 is located below the fracturing hole 11, and the distance between the limiting groove 15 and the thrust piece 40 is the same as the height of the sliding cavity 25. In this way, when the first connecting portion 21 of the inner sleeve 20 descends to the second step 13, the thrust piece 40 falls into the limiting groove 15 accordingly, locks the inner sleeve 20, prevents the inner sleeve 20 from ascending, and ensures the normal progress of the fracturing operation.
[0052] In an optional example of the present invention, the thrust member 40 is an open ring, which is sleeved in the first mounting groove 27, and the outer wall of the open ring gradually expands from bottom to top. When the open ring is located in the first mounting groove 27, the open ring is limited by the inner wall of the outer cylinder 10 and is in a tightened state. When the inner sleeve 20 moves downward, the open ring moves downward with the inner sleeve 20. When the open ring moves downward to the limiting groove 15, the limiting effect of the outer cylinder 10 on the open ring disappears, and the open ring expands along its own radial direction and is engaged in the limiting groove 15, thereby locking the inner sleeve 20.
[0053] In another optional example of the present invention, the thrust member 40 may also be designed as a retaining spring, and its working process and principle are similar to those of the open ring, which will not be described in detail here.
[0054] In an optional example of the present invention, Figure 6 As shown, the first mounting groove 27 formed on the inner sleeve 20 may not be subjected to any chamfering or rounding treatment, so as to avoid the fracturing hole 11 being closed due to the resetting of the inner sleeve 20 during the fracturing process.
[0055] In an optional example of the present invention, the inner diameter of the outer cylinder 10 at A above the fracturing hole 11 is larger than the inner diameter at B below the fracturing hole 11, so as to facilitate the drainage of the pressure relief hole 14 during the downward movement of the inner sleeve 20.
[0056] In an optional example, the inner diameter at A is greater than the inner diameter at B by 1 mm.
[0057] In an optional example of the present invention, one or more sealing rings 50 are provided between the first connection part 21 and the outer tube 10 and between the second connection part 23 and the outer tube 10 to further ensure the sealing cooperation between the first connection part 21 and the outer tube 10 and between the second connection part 23 and the outer tube 10. Specifically, the sealing ring 50 can be an O-ring.
[0058] In an optional example of the present invention, a first sealing ring and a second sealing ring are sleeved between the first connecting portion 21 and the outer tube 10, and a first sealing ring groove 28 corresponding to the first sealing ring and a second sealing ring groove 29 corresponding to the second sealing ring are opened on the side wall of the first connecting portion 21, and the first sealing ring groove 28 and the second sealing ring groove 29 are both opened along the circumference of the first connecting portion 21, the first sealing ring groove 28 is arranged above the second sealing ring groove 29 and is spaced from the second sealing ring groove 29, and the width HI of the first sealing ring groove 28 is greater than the width H2 of the second sealing ring groove 29.
[0059] In an optional example, the width H1 of the first sealing ring groove 28 is 6 mm, the width H2 of the second sealing ring groove 29 is 4 mm, and the first sealing ring groove 28 is a high-pressure sealing ring groove, thereby ensuring the reliability of the sealing performance between the first connecting portion 21 of the inner sleeve 20 and the outer tube 10.
[0060] In an optional example of the present invention, the open hole staged fracturing differential pressure sleeve also includes an upper joint 60 and a lower joint 70, both of which are vertically arranged cylindrical bodies that penetrate from top to bottom, and the upper joint 60 and the lower joint 70 are respectively fixed to the upper and lower ends of the outer tube 10.
[0061] In an optional example of the present invention, the top end of the lower joint 70 is sleeved in the outer tube 10 and fixedly connected to the inner wall of the outer tube 10. The distance between the top end of the lower joint 70 and the bottom end of the inner sleeve 20 is the same as the height of the sliding cavity 25. After sliding down, the inner sleeve 20 presses against the lower joint 70, thereby preventing the inner sleeve 20 from falling off the outer tube 10 and affecting subsequent construction operations.
[0062] In an optional example of the present invention, the outer tube 10 and the upper joint 60, and the outer tube 10 and the lower joint 70 are all threaded connections, and a top screw 80 is also provided between the outer tube 10 and the upper joint 60, and between the outer tube 10 and the lower joint 70, respectively. The top screw 80 passes through the outer tube 10 and is inserted on the upper joint 60 or the lower joint 70, further improving the firmness of the connection between the upper joint 60, the lower joint 70 and the outer tube 10.
[0063] In an optional example, a top screw groove is formed at the upper end of the outer tube 10, and a top screw 80 passes through the corresponding top screw groove and is inserted into the upper joint 60, thereby fixing the upper joint 60 and the outer tube 10 together; a top screw groove is also formed at the lower end of the outer tube 10, and a top screw 80 passes through the corresponding top screw groove and is inserted into the lower joint 70, thereby fixing the lower joint 70 and the outer tube 10 together.
[0064] In an optional example of the present invention, a sealing ring 50 is also provided between the upper joint 60 and the outer tube 10 to ensure a sealed connection between the upper joint 60 and the outer tube 10 .
[0065] In an optional example of the present invention, the bottom end of the upper joint 60 is connected to the top end of the inner sliding sleeve 20 .
[0066] The installation and use process of the open hole staged fracturing differential pressure sleeve proposed by the present invention is as follows:
[0067] First, the upper part of the upper joint 60 is fixedly installed at the lowest end of the fracturing pipe string, and the lower part of the lower joint 70 is fixedly installed together with the pressure holding device, and then the fracturing fluid is injected into the fracturing pipe string. The fracturing fluid acts on the end face 26 at the top of the inner sleeve 20, so that the inner sleeve 20 is subjected to a downward thrust. When the pressure reaches a certain value, the shear pin 30 is sheared off under the action of the pressure, and the inner sleeve 20 moves downward. When the first connecting part 21 moves downward to the corresponding position at the lower part of the fracturing hole 11, the fracturing hole 11 is opened, and the fracturing fluid enters the formation through the fracturing hole 11, thereby fracturing the formation. When the bottom end of the inner sleeve 20 abuts against the top end of the lower joint 70, the inner sleeve 20 stops descending. At this time, the thrust piece 40 is stuck in the limit groove 15 to achieve the locking of the inner sleeve 20 and prevent the inner sleeve 20 from moving upward.
[0068] The detailed explanation of the above-mentioned embodiments is only intended to explain the present invention so as to facilitate a better understanding of the present invention. However, these descriptions cannot be interpreted as limitations on the present invention for any reason. In particular, the various features described in different embodiments may also be arbitrarily combined with each other to form other embodiments. Unless there is a clear description to the contrary, these features should be understood to be applicable to any embodiment and are not limited to the described embodiments.
Claims
1. An open hole staged fracturing differential pressure sleeve, characterized in that: The open hole staged fracturing differential pressure sleeve comprises an outer sleeve and an inner sleeve, the outer sleeve and the inner sleeve are both cylindrical bodies arranged vertically and penetrating from top to bottom, the outer sleeve is sleeved outside the inner sleeve and fixedly connected to the inner sleeve through a shear pin, the inner sleeve comprises a first connecting portion, a sliding portion and a second connecting portion arranged in sequence from top to bottom, the first connecting portion and the second connecting portion are respectively sealed with the inner wall of the outer sleeve, the height of the sliding portion is greater than the height of the first connecting portion, the outer diameter of the sliding portion is smaller than the outer diameter of the first connecting portion, and a first step is formed at the bottom end of the first connecting portion, the sliding portion and the inner wall of the outer sleeve are spaced apart, the sliding portion and the inner wall of the outer sleeve are enclosed to form an annular sliding cavity, the outer wall of the outer sleeve is provided with a fracturing hole connected to the sliding cavity, and the end face of the top end of the inner sleeve is gradually inclined downward from the outside to the inside along the radial direction of the inner sleeve; The outer diameter of the second connection part is the same as the outer diameter of the sliding part, and a third connection part corresponding to the second connection part is provided on the inner wall of the outer tube, the third connection part is convex inwardly along the radial direction of the outer tube, and the inner wall of the third connection part is sealed with the side wall of the second connection part; A pressure relief hole communicating with the sliding cavity is provided on the outer wall of the outer cylinder, and the pressure relief hole is located at the bottom end of the sliding cavity; A thrust piece is also provided between the outer cylinder and the inner sleeve, a first mounting groove is provided on the side wall of the first connecting portion along its circumference, the thrust piece is sleeved in the first mounting groove, a limiting groove which can be matched with the thrust piece is provided on the inner wall of the outer cylinder, the limiting groove is provided along the circumference of the outer cylinder, the limiting groove is located below the fracturing hole, and the distance between the limiting groove and the thrust piece is the same as the height of the sliding cavity; The thrust member is an open ring, which is sleeved in the first mounting groove, and the outer wall of the open ring gradually expands in diameter from bottom to bottom.
2. The open hole staged fracturing differential pressure sleeve according to claim 1, characterized in that: One or more sealing rings are arranged between the first connecting portion and the outer tube, and between the second connecting portion and the outer tube.
3. The open hole staged fracturing differential pressure sleeve according to claim 2, characterized in that: A first sealing ring and a second sealing ring are sleeved between the first connecting portion and the outer tube, a first sealing ring groove for installing the first sealing ring and a second sealing ring groove for installing the second sealing ring are provided on the side wall of the first connecting portion, the first sealing ring groove and the second sealing ring groove are both provided along the circumference of the first connecting portion, the first sealing ring groove is provided above the second sealing ring groove and is spaced apart from the second sealing ring, and the width of the first sealing ring groove is greater than the width of the second sealing ring groove.
4. The open hole staged fracturing differential pressure sleeve according to claim 1, characterized in that: The open hole staged fracturing differential pressure sleeve also includes an upper joint and a lower joint, both of which are vertically arranged cylindrical bodies that penetrate from top to bottom, and the upper joint and the lower joint are respectively fixed to the upper and lower ends of the outer cylinder.
5. The open hole staged fracturing differential pressure sleeve according to claim 4, characterized in that: The top end of the lower joint is sleeved in the outer tube and fixedly connected to the inner wall of the outer tube, the distance between the top end of the lower joint and the bottom end of the inner sleeve is the same as the height of the sliding cavity, and the inner sleeve, after sliding down, abuts against the lower joint.
6. The open hole staged fracturing differential pressure sleeve according to claim 4, characterized in that: The outer tube and the upper joint, as well as the outer tube and the lower joint are all threadedly connected, and a top screw is also provided between the outer tube and the upper joint, as well as between the outer tube and the lower joint. The top screw passes through the side wall of the outer tube and is inserted on the upper joint or the lower joint.