Construction technology of steel pipe sleeve installation in reverse drilling and steel pipe sleeve

By using a pneumatic hoist to lift the steel pipe sleeve during raise boring operations, and combining this with the design of bolts and connecting plates, the safety hazards and labor intensity issues during the installation of the steel pipe sleeve were resolved, achieving efficient and safe construction results.

CN109339794BActive Publication Date: 2024-11-12HUAINAN MINING IND GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201811323905.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2018-11-08
Publication Date
2024-11-12
Estimated Expiration
2038-11-08

AI Technical Summary

Technical Problem

In existing reverse drilling operations, the installation of steel pipe sleeves presents problems such as small personnel spacing, significant safety hazards, high labor intensity, and complex and time-consuming construction.

Method used

A pneumatic hoist is used to lift the steel pipe sleeve. Remote operation is achieved by welding bolts and connecting plates onto the sleeve. Combined with the guide plate design, it ensures quick alignment and fixation between sleeves.

Benefits of technology

It reduces safety hazards during construction, alleviates labor intensity, improves construction efficiency, and simplifies the installation process of the sleeve, making it more reliable and easier to operate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109339794B_ABST
    Figure CN109339794B_ABST
Patent Text Reader

Abstract

The present invention provides a construction process for installing a steel pipe sleeve in a reverse borehole and a steel pipe sleeve, which includes the following steps: (i) Sleeve processing: two cross-shaped I-beams are fixed in the first sleeve section with an upper opening, and multiple bolts are evenly welded through the sleeve at a certain distance from the upper and lower edges of each sleeve section, which are used for suturing and connecting the sleeves; (ii) Construction method: 1) Use a starting hoist to lift the steel wire rope connection, 2) Steel sleeve connection: (2) Repeat the operation step (1), and sew in sequence according to the processing number until the last sleeve section; 3) Steel sleeve fixing grouting: The advantages of the present invention are: 1. The pneumatic hoist is used to lift and install the sleeve, and the personnel can operate the pneumatic hoist from a distance, which ensures the safety of the employees, reduces the labor intensity of the employees, and improves the construction efficiency. 2. The steel sleeve processing is novel, which solves the problem of fixing the steel wire rope. The connection design between the sleeves is simple and reliable, and the employees can operate it easily when installing the sleeve.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of reverse drilling in coal mines, in particular to a construction process for installing a steel pipe sleeve in a reverse drilling and a steel pipe sleeve. Background Art

[0002] After the reverse drilling construction is completed, the steel sleeve for drilling and installation is usually lifted or lowered by hand winch or slow twisting. The connection between the sleeves is mainly screwed on the welded flange. Finally, the steel sleeve is fixed by anchor rods or anchor cables from the bottom of the vertical eye and then filled. This process is complicated and has great safety risks. The lifting or lowering installation by hand winch has a high labor intensity. Because the hand winch has a short stroke and the staff is close to the vertical eye and winch, there are safety hazards. The installation of the winch requires the construction of the winch foundation, pouring of concrete, waiting for the concrete to solidify, and the installation of the winch, which is time-consuming and labor-intensive. Summary of the invention

[0003] The technical problem to be solved by the present invention is how to reduce and eliminate the potential safety hazards when installing a steel pipe sleeve due to the personnel standing close to the small eye and the hoist, and how to save construction time and increase construction efficiency.

[0004] The present invention solves the above technical problems through the following technical solutions:

[0005] The construction process of installing steel pipe sleeve by reverse drilling includes the following steps:

[0006] (1) Sleeve processing

[0007] 1) All sleeves are made of steel plates;

[0008] 2) Two cross-shaped I-beams are fixed on the upper opening of the first sleeve to tie the wire rope during lifting;

[0009] 3) Multiple bolts are evenly welded through each sleeve at a certain distance from the upper and lower edges to suture the sleeves;

[0010] (II) Construction method

[0011] 1) Lifting wire rope connection

[0012] Hang the pneumatic hoist on the U-shaped shed beam of the chamber support with an anchor chain, hang the upper end of a wire rope on the pneumatic hoist, lower the other end to the lower mouth of the vertical eye, and use multiple rope clips to fix the wire rope on the cross-shaped I-beam in the first sleeve;

[0013] 2) Steel sleeve connection:

[0014] (1) Start the pneumatic hoist to lift the first sleeve section. Stop when the sleeve is lifted to the set height from the bottom plate. The operator at the lower mouth of the vertical eye moves the second sleeve section to the bottom of the lifted sleeve and confirms that the four M20 bolts welded on the two sleeve sections are aligned up and down. Make a connecting plate with two screw holes. The spacing between the two screw holes is equal to the spacing between the adjacent bolts in the upper and lower sleeves. The bolts of the upper and lower sleeves pass through the two screw holes of the connecting plate respectively and are tightened with nuts;

[0015] (2) Repeat step (1) and sew in sequence according to the processing number until the last sleeve.

[0016] 3) Steel sleeve fixing:

[0017] (1) After the lifting and sewing of the multi-section sleeve is completed, two channel steels are fixed at a certain position from the upper edge of the first section sleeve downward from the upper edge of the vertical eye, and the channel steels are supported on the bottom plate;

[0018] (2) After the sleeve is fixed, the gap between the sleeve and the vertical hole wall is reinforced by grouting.

[0019] Preferably, in step (i), the I-beam is fixed to the first sleeve by bolts.

[0020] The present invention also provides a steel pipe sleeve, which is applied to the above steel pipe sleeve construction process to achieve rapid alignment connection. The steel pipe sleeve includes multiple sleeve sections, which are connected end to end to form the steel pipe sleeve.

[0021] Preferably, multiple sections of sleeves are connected end to end through a connecting structure; the connecting structure includes multiple bolts and connecting plates welded at a certain distance from the upper and lower edges of the sleeve; the bolts pass through the sleeve wall; two screw holes are provided on the connecting plate; the spacing between the two screw holes is equal to the spacing between two adjacent bolts of the upper and lower connecting sleeves; the connecting plate passes the bolts of the upper and lower sleeves at the same time through the two screw holes and is fixed by nuts.

[0022] Preferably, four bolts are evenly distributed on the upper and lower edges of each sleeve.

[0023] Preferably, a guide plate is also fixed to the upper edge of the sleeve.

[0024] Preferably, four guide plates are evenly distributed on the upper edge of the sleeve; the four guide plates form a trumpet-shaped guide channel.

[0025] The advantages of the present invention are:

[0026] 1. Use pneumatic hoist to lift the installation sleeve, and personnel can operate the pneumatic hoist from a long distance to ensure the safety of employees.

[0027] 2. Use pneumatic hoist to lift the installation sleeve to reduce the labor intensity of employees and improve construction efficiency.

[0028] 3. The processing of the steel sleeve is novel, which solves the problem of fixing the wire rope. The connection design between the sleeves is simple and reliable, and the workers can easily operate the sleeves during installation. Finally, the fixing method of the steel sleeve is novel, simple to operate, firm and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 This is a schematic diagram of the connection structure of the steel pipe sleeve in Example 2 of the present invention;

[0030] Figure 2 This is a schematic structural diagram of a sleeve connecting plate in Embodiment 2 of the present invention;

[0031] Figure 3 This is a schematic diagram of the structure of installing a cross steel beam in the first sleeve section in Example 2 of the present invention. DETAILED DESCRIPTION

[0032] In order to have a further understanding and recognition of the structural features and the effects achieved by the present invention, a preferred embodiment and accompanying drawings are used for detailed description as follows:

[0033] Example 1

[0034] The construction process of installing steel pipe sleeves in reverse drilling uses a pneumatic hoist as the lifting power, and the sleeves are lifted and assembled from the lower end of the vertical eye upwards. All steel sleeves are lifted to the upper end of the vertical eye and fixed, and finally the hole wall is filled and reinforced with concrete. The specific steps include:

[0035] (1) Sleeve processing

[0036] 1. Sleeve 1 is made of 5mm steel plate, with a diameter of 1000mm. The first section is 1000mm high, and the remaining sleeves 1 are 1500mm high. Each section weighs 183kg. The drilling sleeve has 10 sections of sleeve 1 (14.5m), with a total weight of about 1830kg.

[0037] 2. Use M20 screws to sew two cross-shaped 11# I-beams in the first sleeve 1 to form a cross steel beam 11, which is used to tie the wire rope during lifting. Figure 3 As shown,

[0038] 3. Weld 4 M20 bolts 12 evenly through each sleeve 1 at a position 150mm from the upper and lower edges, and sew them together between the sleeves 1. Figure 1 , Figure 2 shown.

[0039] (II) Construction method

[0040] 1. Lifting wire rope connection: Hang the pneumatic hoist on the U-shaped shed beam of the chamber support with a 40T anchor chain, hang the upper end of a 18.5mm diameter wire rope on the pneumatic hoist, and lower the other end to the lower mouth of the vertical eye. Use 3 pairs of rope clamps to fix the wire rope on the cross-crossed 11# I-beam in the first section of the sleeve 1, and the rope clamp spacing is 200mm.

[0041] 2. Steel sleeve 1 connection:

[0042] (1) Start the pneumatic hoist to lift the first section of the sleeve 1. Stop when the sleeve 1 is 1600 mm above the bottom plate. The operator at the bottom of the vertical eye moves the second section of the sleeve 1 to the bottom of the lifted sleeve 1, and confirms that the four M20 bolts 12 welded on the two sections of the sleeve 1 are aligned vertically, and sews the nuts on the connecting plate 13 made of 10 mm thick steel plate.

[0043] (2) Due to the height limit of the upper chamber of the vertical eye and the travel limit of the hoist, the operator must re-clamp the rope above the small eye every time a section of sleeve 1 is lifted and sewed. When the rope is re-clamped, sleeve 1 falls to the ground, and then the operation is repeated in sequence according to the processing number until the last section of sleeve 1 is sewed.

[0044] 3. Steel sleeve 1 fixation:

[0045] (1) After the lifting and sewing of the 10th section of sleeve 1 is completed, two 2000mm long 10# channel steels are fastened with bolts 12 at the upper edge 200mm downward of the first section of sleeve 1, and the channel steels are supported on the bottom plate.

[0046] (2) After the sleeve 1 is fixed, the gap between the sleeve 1 and the vertical hole wall is reinforced by grouting, and the grouting is done manually by the construction personnel at the upper end of the vertical hole.

[0047] (III) Safety precautions

[0048] 1. When the pneumatic hoist is fixed to the U-shaped shed with an anchor chain, it must be firm and reliable, and anti-slip measures must be taken.

[0049] 2. Personnel at the top of the vertical eye must wear a safety rope when entering within 5 meters of the vertical eye to perform work.

[0050] 3. After the vertical eye sleeve 1 is installed, the upper opening of the sleeve wall must be covered with a wooden board to prevent debris from falling into the eye. Workers under the vertical eye are strictly prohibited from standing directly below the vertical eye to perform work.

[0051] 4. During the suturing process, when the sleeve 1 is moved and aligned to the bolt 12, special tools such as a pointed cone should be used for operation. It is strictly forbidden to use hands directly to prevent hands from being squeezed and injured.

[0052] Example 2

[0053] like Figure 1 , Figure 2As shown, a steel pipe sleeve is applied to the steel pipe sleeve construction process described in the above-mentioned embodiment 1, and the steel pipe sleeve 1 includes a plurality of sleeve sections 1, and the plurality of sleeve sections 1 are connected end to end through a connecting structure. The connecting structure includes four bolts 12 and a connecting plate 13 welded at a certain distance from the upper and lower edges of the sleeve 1; the four bolts 12 are evenly distributed around the sleeve 1, and the bolts 12 pass horizontally through the wall of the sleeve 1; two screw holes are provided on the connecting plate 13; the spacing between the two screw holes is equal to the spacing between the two screw rods adjacent to the upper and lower connecting sleeves 1; the connecting plate 13 passes the bolts 12 of the upper and lower sleeve sections 1 through the two screw holes at the same time, and is fixed by nuts.

[0054] Four guide plates 14 are fixed on the upper edge of the sleeve 1, and a trumpet-shaped guide channel is formed by the four guide plates 14. When the upper and lower sleeves 1 are aligned, they are guided by the four guide plates 14, so that quick alignment can be achieved.

[0055] The present invention adopts a pneumatic hoist to lift and install the sleeve, and personnel can operate the pneumatic hoist from a distance, thereby ensuring the safety of workers. The pneumatic hoist is adopted to lift and install the sleeve, thereby reducing the labor intensity of workers and improving the construction efficiency. The processing of the steel sleeve is novel, which solves the problem of fixing the wire rope. The connection design between the sleeves is simple and reliable, and the workers can easily operate when installing the sleeve. Finally, the fixing method of the steel sleeve is novel, simple to operate, and firm and reliable.

[0056] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.

Claims

1. The construction process of installing steel pipe sleeve by reverse drilling is characterized by: The following steps are involved: (1) Sleeve processing 1) All sleeves are made of steel plates; 2) Two cross-shaped I-beams are fixed on the upper opening of the first sleeve to tie the wire rope during lifting; 3) Multiple bolts are evenly welded through each sleeve at a certain distance from the upper and lower edges to suture the sleeves; (II) Construction method 1) Lifting wire rope connection Hang the pneumatic hoist on the U-shaped shed beam of the chamber support with an anchor chain, hang the upper end of a wire rope on the pneumatic hoist, lower the other end to the lower mouth of the vertical eye, and use multiple rope clips to fix the wire rope on the cross-shaped I-beam in the first sleeve; 2) Steel sleeve connection: (1) Start the pneumatic hoist to lift the first sleeve section, and stop when the sleeve is lifted to the set height from the bottom plate. The operator at the lower mouth of the vertical eye moves the second sleeve section to the bottom of the lifted sleeve, and confirms that the multiple bolts welded on the two sleeve sections are aligned up and down. Make a connecting plate with two screw holes. The spacing between the two screw holes is equal to the spacing between the adjacent bolts in the upper and lower sleeves. The bolts of the upper and lower sleeves pass through the two screw holes of the connecting plate respectively and are tightened with nuts; (2) Repeat step (1) and sew in sequence according to the processing number until the last sleeve is completed; 3) Steel sleeve fixing: (1) After the lifting and sewing of the multi-section sleeve is completed, two channel steels are fixed at a certain position from the upper edge of the first section sleeve downward from the upper edge of the vertical eye, and the channel steels are supported on the bottom plate; (2) After the sleeve is fixed, the gap between the sleeve and the vertical hole wall is reinforced by grouting.

2. The construction process for installing a steel pipe sleeve by reverse drilling according to claim 1 is characterized in that: In the step (a), the I-beam is fixed to the first sleeve by bolts.