A kind of loading device with extended range for foundation pull-out load test and loading method

By adding extended-range parts to the load test equipment based on the transmission pole tower, the jack stroke constraint problem is solved, stable load loading under large deformation conditions is achieved, static load testing requirements are met, and operation safety and efficiency are improved .

CN110042873BActive Publication Date: 2024-11-19CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD +2
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN201910191382.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-03-14
Publication Date
2024-11-19
Estimated Expiration
2039-03-14

AI Technical Summary

Technical Problem

The loading process of the detent loading test equipment based on the existing transmission pole tower is restricted by the jack stroke, which leads to the inability to load to the required deformation amount under large deformation or insufficient foundation stiffness, resulting in the suspension of the test.

Method used

A programmable loading device including a force transmission screw, an upper top plate, a flange, a pressure-bearing force transmission device and a hoisting member is designed. By adding a range-increasing member to the force transmission screw, the stroke of the test foundation is increased, and the The hoisting component drives the flange and test foundation to move upward, overcoming the jack stroke constraints.

Benefits of technology

It realizes the maintenance of load without attenuation under large deformation conditions of foundation, meets the monotonic increase requirements of static load tests, avoids safety hazards for operators to enter the load structure, and saves workload and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110042873B_ABST
    Figure CN110042873B_ABST
Patent Text Reader

Abstract

The present invention provides an extendable loading device for a foundation pull-out load test and a loading method for the device, comprising: a force transmission screw (12), a lower top plate (4), an upper top plate (7), a force transmission crossbeam group (3), a flange (15), a lifting component (B) and a screw nut used in conjunction with the force transmission screw (12); an extender component (C) is added to the force transmission screw (12) to increase the stroke of the test foundation. The technical solution provided by the present invention, by adding an extender component (C) to the force transmission screw (12), the foundation is always in a loading state during the stroke extension operation of the loading device, thereby ensuring the static load test requirements of the foundation being subjected to monotonically increasing pull-out. During the stroke extension operation of the loading device, the loading device allows the operator to only perform the screwing operation of the nut, saving workload and time. It also ensures that the operator only performs operations outside the loading device, thereby avoiding the potential safety hazards of the operator's limbs entering the interior of the traditional loading device.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of transmission line tower foundation pull-out static load test devices, and in particular relates to a foundation pull-out load test with an extended range type loading device and a loading method. Background Art

[0002] The static load test of transmission tower foundation is a direct and reliable method used worldwide to verify the tower foundation design and study the bearing characteristics. The ability and reliability of the pull-out loading structure are key equipment to ensure the reliability of the test results.

[0003] At present, the loading structure types of the in-situ pull-out load test of the transmission tower foundation are diverse and have not been standardized, but their main structural features are that the jack is the power part, the force transmission beam and force transmission screw are the main load-bearing components, and the nut-thread and flange plate (disc) are the main connection methods.

[0004] The existing transmission tower foundation static load test equipment can complete the conventional transmission tower foundation design verification and load-bearing characteristics research work, but there is a problem that the loading process is restricted by the jack stroke. That is, during the loading process, when the foundation deformation or the deformation of the force transmission beam is large, or when it is necessary to study the foundation bearing characteristics under large deformation, the test is forced to be terminated because the jack reaches the maximum stroke when the foundation is not loaded to the required deformation amount. Summary of the invention

[0005] In order to solve the problem of jack stroke restriction, the present invention provides a foundation pull-out load test with an extendable range loading device and a loading method. Through structural measures, the foundation pull-out load is maintained without attenuation during the extended range operation of the pull-out static load test, thereby meeting the pull-out static load test requirements of the foundation being subjected to monotonically increasing pull-out under the condition of large foundation deformation (or insufficient stiffness of the foundation or force transmission structure).

[0006] The technical solution to achieve the above purpose is as follows:

[0007] The present invention provides a load device with an extendable range for a pull-out load test on a foundation, wherein the device comprises: a force transmission screw (12), an upper top plate (7), a flange (15), a pressure transmission device (A), a nut on the screw (8) and a lifting component (B); an extender component (C) is added to the force transmission screw (12) to increase the stroke of the test foundation;

[0008] The pressure-bearing force transmission device (A) is placed on the foundation (21), the lifting component (B) is arranged on the pressure-bearing force transmission device (A), and the upper top plate (7) is arranged on the lifting component (B);

[0009] The upper end of the force transmission screw (12) passes through the upper top plate (7) and is fastened to the screw upper nut (8), and then passes through the pressure-bearing force transmission device (A) and is fastened to the flange (15); the flange (15) is also fixedly connected to the pulled-out test foundation (20);

[0010] The range-extending component (C) disposed on the force transmission screw (12) is located between the upper top plate (7) and the pressure-bearing force transmission device (A);

[0011] The lifting component (B) drives the force transmission screw (12) to move upward, thereby driving the flange (15) and the test base (20) fixedly connected to the flange (15) to move upward.

[0012] Preferably, the range-extending component (C) comprises: a range-extending nut (11) and a range-extending thread (10) processed on a force-transmitting screw (12) to cooperate with the range-extending nut (11);

[0013] The length of the extended-range thread (10) is set to match the upward pull-out stroke of the test base (20);

[0014] The range-extending nut (11) is screwed onto the range-extending thread (10) in coordination with the upward pulling stroke of the test base (20).

[0015] Preferably,

[0016] There are two force transmission screws (12), which are symmetrically arranged along the perpendicular midline of the lifting component (B);

[0017] The upper end and the lower end of the force transmission screw (12) are respectively processed with a screw upper thread (9) and a screw lower thread (13);

[0018] The nut (8) on the screw rod is used in conjunction with the thread (9) on the screw rod.

[0019] Preferably,

[0020] The range-extending thread (10) is located between the upper thread (9) of the screw and the lower thread (13) of the screw, and is in close contact with the upper thread (9) of the screw.

[0021] Preferably, it further comprises: a screw lower nut (14) and a screw lower thread (13) arranged on the force transmission screw (12) to cooperate with the screw lower nut (14);

[0022] The screw lower nut (14) cooperates with the screw lower thread (13) to connect the lower end of the force transmission screw (12) to the flange (15).

[0023] Preferably, it further comprises: an anchor bolt (19), an upper anchor nut (16), a lower anchor nut (18), and an anchor thread (17) processed on the anchor bolt (19) to cooperate with the upper anchor nut (16) and the lower anchor nut (18);

[0024] There are two anchor bolts (19), which are symmetrically arranged along the perpendicular line of the flange (15);

[0025] The anchor nut (16) and the anchor nut (18) are screwed onto the anchor thread (17) and are located above the flange (15) and below the flange (15), respectively;

[0026] The lower end of the anchor bolt (19) is cast in advance in the test foundation (20), and the upper end of the anchor bolt (19) passes through the flange (15) and is fixedly connected via an upper anchor nut (16) and a lower anchor nut (18).

[0027] Preferably, the pressure-bearing force transmission device (A) comprises: a pressure-bearing plate (1), a force transmission pier (2) and a force transmission beam group (3);

[0028] The pressure plate (1) is placed on the foundation (21), and the force transmission pier (2) is placed on the pressure plate (1);

[0029] There are two pressure-bearing plates (1) and two force-transmitting piers (2), and the force-transmitting crossbeam group (3) is placed on the two force-transmitting piers (2).

[0030] Preferably, it also includes a lower top plate (4);

[0031] The lower top plate (4) is placed between the lifting component (B) and the force transmission beam group (3), and the lower top plate (4) is used for load transfer between the lifting component (B) and the force transmission beam group (3) as a whole;

[0032] The force transmission screw (12) passes through the lower top plate (4), and the range-extending nut (11) is screwed to fit tightly against the lower top plate (4).

[0033] Preferably, the force transmission beam group (3) consists of a plurality of force transmission beams.

[0034] Preferably,

[0035] The lifting component (B) comprises: a jack (5), a jack piston (6) and a jack pump station;

[0036] The jack piston (6) is located above the jack (5) and is extended and retracted on the jack (5) under the drive of the jack pump station.

[0037] The present invention provides a loading method of a base pull-out load test with an extended-range loading device, the improvement of which is that the method comprises:

[0038] 1) Filling the stroke of the lifting component (B) and adjusting the position of the range-extending component on the force-transmitting screw (12) so that the range-extending component is in close contact with the pressure-bearing force-transmitting device (A);

[0039] 2) retracting the lifting component (B), causing the upper top plate (7) to naturally fall along with the lifting component (B), and screwing the nut (8) on the screw rod to make it close to the upper top plate (7);

[0040] 3) Continue to fill the stroke of the lifting component (B), drive the force transmission screw (12) to move upward through the lifting component (B), and then drive the flange (15) and the test base (20) fixedly connected to the flange (15) to move upward;

[0041] Then, if you need to continue to increase the foundation uplift displacement, repeat steps 1) to 3).

[0042] Preferably, when the test foundation (20) is cast, the anchor bolts (19) are cast at the same time.

[0043] Preferably, the stroke of the lifting component (B) is filled up, and the position of the range-extending component on the force transmission screw (12) is adjusted so that the range-extending component is closely attached to the pressure-bearing force transmission device (A), and before that, the method further includes:

[0044] The force transmission screw (12) is fixedly connected to the anchor bolt (19) cast in the test foundation (20) via the flange (15).

[0045] Compared with the closest prior art, the technical solution provided by the present invention has the following beneficial effects:

[0046] (1) The technical solution provided by the present invention comprises: a force transmission screw (12), an upper top plate (7), a flange (15), a pressure transmission device (A), a screw upper nut (8) and a lifting component (B); an extension component (C) is added to the force transmission screw (12) to increase the stroke of the test foundation; the pressure transmission device (A) is placed on a foundation (21), the lifting component (B) is arranged on the pressure transmission device (A), and the upper top plate (7) is arranged on the lifting component (B); the upper end of the force transmission screw (12) passes through the upper top plate (7) and is fastened to the screw upper nut (8), and then After passing through the pressure-bearing force transmission device (A), it is fastened to the flange (15); the flange (15) is also fixedly connected to the pulled test foundation (20); the range-extending component (C) arranged on the force transmission screw (12) is located between the upper top plate (7) and the pressure-bearing force transmission device (A); the lifting component (B) drives the force transmission screw (12) to move upward, thereby driving the flange (15) and the test foundation (20) fixedly connected to the flange (15) to move upward. By adding the range-extending component (C) to the force transmission screw (12), during the process of the loading structure's range-extending operation, the range-extending component (C) cooperates with the upward pulling movement of the test foundation (20) to continuously screw downward on the force transmission screw (12), thereby overcoming the jack stroke restriction problem, so that the foundation is always in a loaded state, and ensuring the static load test requirements of the foundation being pulled monotonically and incrementally;

[0047] (2) The technical solution provided by the present invention allows the operator to only screw the nut during the loading structure's extended-range operation, saving workload and time.

[0048] (3) The technical solution provided by the present invention ensures that the operator can only perform operations outside the loading structure, thereby avoiding the potential safety hazard of the operator's limbs entering the interior of the traditional loading structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 A large-scale drawing of the loading structure assembly of the present invention;

[0050] Figure 2 It is a cross-sectional view of the loading structure of the present invention;

[0051] Figure 3 It is a side cross-sectional view of the loading structure of the present invention;

[0052] In the figure, 1-pressure plate, 2-force transmission pier, 3-force transmission beam group, 4-lower top plate, 5-jack, 6-jack piston, 7-upper top plate, 8-nut on screw, 9-screw upper thread, 10-range extension thread, 11-range extension nut, 12-force transmission screw, 13-screw lower thread, 14-screw lower nut, 15-flange, 16-nut on anchor, 17-anchor thread, 18-nut under anchor, 19-anchor bolt, 20-test foundation, 21-foundation. DETAILED DESCRIPTION

[0053] Example 1

[0054] like Figure 1 and Figure 2 As shown, the device includes: a force transmission screw 12, an upper top plate 7, a flange 15, a pressure transmission device A, a screw upper nut 8 and a lifting component B; an extended-range component C is added to the force transmission screw 12 to increase the stroke of the test base; the extended-range component C includes: an extended-range nut 11 and an extended-range thread 10 processed on the force transmission screw 12 to match the extended-range nut 11; the length of the extended-range thread 10 is set to match the pull-up stroke of the test base 20; the extended-range nut 11 is screwed on the extended-range thread 10 to match the pull-up stroke of the test base 20. The extended-range component C arranged on the force transmission screw 12 is located between the upper top plate 7 and the pressure transmission device A; the extended-range thread 10 is located between the upper screw thread 9 and the lower screw thread 13, and is close to the upper screw thread 9. The pressure-bearing force transmission device A is placed on the foundation 21, the lifting component B is arranged on the pressure-bearing force transmission device A, and the upper top plate 7 is arranged on the lifting component B; the pressure-bearing force transmission device A includes: a pressure plate 1, a force transmission pier 2 and a force transmission beam group 3; the pressure plate 1 is placed on the foundation 21, and the force transmission pier 2 is placed on the pressure plate 1; there are two pressure plates 1 and two force transmission piers 2, and the force transmission beam group 3 is placed on two force transmission piers 2. The upper end of the force transmission screw 12 passes through the upper top plate 7 and is fastened to the screw upper nut 8, and then passes through the pressure-bearing force transmission device A and is fastened to the flange 15; the flange 15 is also fixedly connected to the pulled-out test foundation 20; there are two force transmission screws 12, which are symmetrically arranged along the perpendicular midline of the jacking component B; the upper end and the lower end of the force transmission screw 12 are respectively processed with a screw upper thread 9 and a screw lower thread 13; the screw upper nut 8 is used in conjunction with the screw upper thread 9. It also includes: a screw lower nut 14 and a screw lower thread 13 provided on the force transmission screw 12 to cooperate with the screw lower nut 14; the screw lower nut 14 is connected in cooperation with the screw lower thread 13 to fix the lower end of the force transmission screw 12 to the flange 15. It also includes a lower top plate 4; the lower top plate 4 is placed between the jacking component B and the force transmission beam group 3, as shown in FIG. Figure 3As shown, the force transmission beam group 3 is composed of multiple force transmission beams. The lower top plate 4 is used for lifting component B and the load transmission of the force transmission beam group 3 as a whole; and the force transmission screw 12 passes through the lower top plate 4, and the range extender nut 11 is screwed to be close to the lower top plate 4. It also includes: an anchor bolt 19, an upper anchor nut 16, a lower anchor nut 18, and an anchor thread 17 processed on the anchor bolt 19 to match the upper anchor nut 16 and the lower anchor nut 18; there are two anchor bolts 19, which are symmetrically arranged along the mid-vertical line of the flange 15; the upper anchor nut 16 and the lower anchor nut 18 are screwed on the anchor thread 17, and are respectively located above the flange 15 and below the flange 15; the lower end of the anchor bolt 19 is cast in advance in the test foundation 20, and the upper end of the anchor bolt 19 passes through the flange 15 and is fixedly connected by the upper anchor nut 16 and the lower anchor nut 18. The lifting component B drives the force transmission screw 12 to move upward, thereby driving the flange 15 and the test base 20 fixedly connected to the flange 15 to move upward. The lifting component B includes: a jack 5, a jack piston 6 and a jack pump station; the jack piston 6 is located above the jack 5 and is extended and retracted on the jack 5 under the drive of the jack pump station.

[0055] Example 2

[0056] Figure 1 A large-scale drawing of the loading structure assembly of the present invention; Figure 2 It is a cross-sectional view of the loading structure of the present invention; Figure 1 and Figure 2As shown, the pressure plate 1 is naturally placed on the surface of the foundation 21, and its function is to transfer the compressive load between the force transfer pier 2 and the foundation 21. Since the pressure plate 1 has a large area, it reduces the load of the foundation 21, reduces the foundation settlement, and increases the total resistance of the foundation. The force transfer pier 2 is naturally placed on the pressure plate 1; its function is to transfer the compressive load between the lower top plate 1 and the force transfer beam group 3. The force transfer beam group 3 is naturally placed on the force transfer pier 2; its function is to transfer the compressive load between the lower top plate 4 and the force transfer pier 2. The lower top plate 4 is naturally placed on the force transfer beam group 3, and its function is to transfer the compressive load between the jack 5 and the force transfer beam group 3. The jack 5 is naturally placed on the lower top plate 4; the jack piston 6 is a component of the jack 5; the oil supply and oil return working states of the jack pump station control the extension and retraction of the jack piston 6 respectively. The upper top plate 7 is naturally placed on the jack piston 6, and its function is to transfer the compressive load between the jack piston 6 and the nut on the screw; the nut and the screw are connected by threads, such as the connections between 16-19, 18-19, 8-12, 11-12, and 14-12; the force transmission screw 12 is used to transfer the tensile load between the nut 8 on the screw and the nut 14 on the screw; an extended-range thread 10 and an extended-range nut 11 are added to the force transmission screw 12, and the extended-range thread 10 is processed below the thread 9 on the screw and extends downward for a certain length; the extended-range nut 11 is screwed on the extended-range thread 10 and is located between the upper top plate 7 and the lower top plate 4; as the lifting component (B) drives the force transmission screw 12 to move upward and then drives the flange 15 and the test base 20 fixedly connected to the flange 15 to move upward, the extended-range nut 11 is screwed on the extended-range thread 10 in accordance with the upward pull-out stroke of the test base 20. Figure 3 As shown, the force transmission beam group 3 is composed of multiple force transmission beams, and the existence of the lower top plate 4 ensures the load transmission of the jack 5 and the force transmission beam group 3 as a whole. The anchor bolt 19 is used to transmit the tensile load between the nut 16 on the anchor and the test foundation 20; the force transmission beam group 3, the lower top plate 4, and the upper top plate 7 reserve holes or gaps, and the force transmission screw 12 passes through them; the force transmission beam group 3, the lower top plate 4, the upper top plate 7, and the flange 15 reserve holes or gaps, and the force transmission screw 12 passes through them; the flange 15 reserves holes or gaps, and the anchor bolt 19 passes through them; the anchor bolt 19 is pre-buried in the test foundation 20, and during the foundation pouring process, the anchor bolt 19 is positioned and poured into it. The nut 18 under the foot of the foundation plays a leveling function to ensure that the flange 15 remains level after falling on it.

[0057] Example 3

[0058] The method includes: 1) filling the stroke of the jacking component B, and adjusting the position of the range-extending component on the force transmission screw 12 so that the range-extending component is close to the pressure-bearing force transmission device A; 2) retracting the jacking component B, the upper top plate 7 naturally falls with the jacking component B, and the nut 8 on the screw is screwed close to the upper top plate 7; 3) continuing to fill the stroke of the jacking component B, driving the force transmission screw 12 to move upward through the jacking component B, and then driving the flange 15 and the test foundation 20 fixedly connected to the flange 15 to move upward. In step 3), continue to fill the stroke of the jacking component B, drive the force transmission screw 12 to move upward through the jacking component B, and then drive the flange 15 and the test foundation 20 fixedly connected to the flange 15 to move upward. Afterwards, if it is necessary to continue to increase the displacement of the foundation, repeat steps 1) to 3). When the test foundation 20 is cast, the anchor bolts 19 are cast at the same time. The stroke of the lifting component B is filled up, and the position of the range-extending component on the force transmission screw 12 is adjusted so that the range-extending component is close to the pressure-bearing force transmission device A. It also includes: the force transmission screw 12 is fixedly connected to the anchor bolt 19 cast in the test foundation 20 through the flange 15, and the anchor bolt 19 is fixedly connected to the flange 15 by screwing the upper anchor nut 16 and the lower anchor nut 18 on the anchor thread 17, and the lower screw nut 14 is matched with the lower screw thread 13 to fix the lower end of the force transmission screw 12 to the flange 15.

[0059] Example 4

[0060] 1) Carry out the pull-up loading test according to the standard process. For the pull-up loading test process, refer to Appendix K / p.150-154 of the Technical Code for Foundation Design of Overhead Power Transmission Lines DL / T 5219-2014; when the jack stroke is full, close the jack oil supply pump station;

[0061] 2) Screw down the range extender nut 11 until it contacts the lower top plate 4;

[0062] 3) Adjust the jack oil supply pump station to the oil return working state and start it. After the jack piston 6 is fully retracted, close the pump station; at this time, the upper top plate 7 falls naturally along with the jack piston 6, forming a gap between the screw nut 8 and the upper top plate 7;

[0063] 4) Screw down the nut 8 on the screw until it contacts the upper top plate 7;

[0064] 5) Adjust the jack oil supply pump station to the oil supply working state, and then continue the loading test according to the standard process;

[0065] 6) When the jack reaches full travel again, if you need to continue increasing the displacement of the foundation, repeat steps 1) to 5).

[0066] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents, and any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention should be included in the scope of the claims of the present invention.

Claims

1. A load device with an extended range for foundation pull-out load test, It is characterized in that The device comprises: a force transmission screw (12), an upper top plate (7), a flange (15), a pressure transmission device (A), a nut (8) on the screw and a lifting component (B); a stroke extension component (C) is added to the force transmission screw (12) to increase the stroke of the test foundation; The pressure-bearing force transmission device (A) is placed on the foundation (21), the lifting component (B) is arranged on the pressure-bearing force transmission device (A), and the upper top plate (7) is arranged on the lifting component (B); The upper end of the force transmission screw (12) passes through the upper top plate (7) and is fastened to the screw upper nut (8), and then passes through the pressure-bearing force transmission device (A) and is fastened to the flange (15); the flange (15) is also fixedly connected to the pulled-out test foundation (20); The range-extending component (C) disposed on the force transmission screw (12) is located between the upper top plate (7) and the pressure-bearing force transmission device (A); The lifting component (B) drives the force transmission screw (12) to move upward, thereby driving the flange (15) and the test base (20) fixedly connected to the flange (15) to move upward; The range-extending component (C) comprises: a range-extending nut (11) and a range-extending thread (10) processed on a force-transmitting screw (12) to cooperate with the range-extending nut (11); The length of the extended-range thread (10) is set to match the upward pull-out stroke of the test base (20); The range-extending nut (11) is screwed onto the range-extending thread (10) in coordination with the upward pulling stroke of the test base (20); There are two force transmission screws (12), which are symmetrically arranged along the perpendicular midline of the lifting component (B); The upper end and the lower end of the force transmission screw (12) are respectively processed with a screw upper thread (9) and a screw lower thread (13); The nut (8) on the screw rod is used in conjunction with the thread (9) on the screw rod; The range-extending thread (10) is located between the upper thread (9) of the screw and the lower thread (13) of the screw, and is in close contact with the upper thread (9) of the screw; The pressure-bearing force transmission device (A) comprises: a pressure-bearing plate (1), a force transmission pier (2) and a force transmission crossbeam group (3); The pressure plate (1) is placed on the foundation (21), and the force transmission pier (2) is placed on the pressure plate (1); The pressure plate (1) and the force transfer pier (2) are each two, and the force transfer beam group (3) is placed on the two force transfer piers (2); Also includes a lower top plate (4); The lower top plate (4) is placed between the lifting component (B) and the force transmission beam group (3), and the lower top plate (4) is used for load transfer between the lifting component (B) and the force transmission beam group (3) as a whole; The force transmission screw (12) passes through the lower top plate (4), and the range-extending nut (11) is screwed to fit tightly against the lower top plate (4); The lifting component (B) comprises: a jack (5), a jack piston (6) and a jack pump station; The jack piston (6) is located above the jack (5) and is extended and retracted on the jack (5) under the drive of the jack pump station.

2. A basic pull-out load test range-extending loading device as claimed in claim 1, It is characterized in that Also includes: A screw lower nut (14) and a screw lower thread (13) provided on the force transmission screw (12) to cooperate with the screw lower nut (14); The screw lower nut (14) cooperates with the screw lower thread (13) to connect the lower end of the force transmission screw (12) to the flange (15).

3. A basic pull-out load test with an extended range loading device as claimed in claim 1, It is characterized in that Also includes: An anchor bolt (19), an upper anchor nut (16), a lower anchor nut (18), and an anchor thread (17) processed on the anchor bolt (19) to cooperate with the upper anchor nut (16) and the lower anchor nut (18); There are two anchor bolts (19), which are symmetrically arranged along the perpendicular line of the flange (15); The anchor nut (16) and the anchor nut (18) are screwed onto the anchor thread (17) and are located above the flange (15) and below the flange (15), respectively; The lower end of the anchor bolt (19) is cast in advance in the test foundation (20), and the upper end of the anchor bolt (19) passes through the flange (15) and is fixedly connected via an upper anchor nut (16) and a lower anchor nut (18).

4. A basic pull-out load test range-extending loading device as claimed in claim 1, It is characterized in that The force transmission crossbeam group (3) consists of a plurality of force transmission crossbeams.

5. A loading method for the extended-range loading device for pull-out load testing according to claim 1, It is characterized in that The method comprises: 1) Filling the stroke of the lifting component (B) and adjusting the position of the range-extending component on the force-transmitting screw (12) so that the range-extending component is in close contact with the pressure-bearing force-transmitting device (A); 2) retracting the lifting component (B), causing the upper top plate (7) to naturally fall along with the lifting component (B), and screwing the nut (8) on the screw rod to make it close to the upper top plate (7); 3) Continue to fill the stroke of the lifting component (B), drive the force transmission screw (12) to move upward through the lifting component (B), and then drive the flange (15) and the test base (20) fixedly connected to the flange (15) to move upward; Then, if you need to continue to increase the foundation uplift displacement, repeat steps 1) to 3).

6. A loading method for a basic pull-out load test with an extended-range loading device as claimed in claim 5, It is characterized in that When the test foundation (20) is cast, the anchor bolts (19) are cast at the same time.

7. A loading method for a basic pull-out load test with an extended-range loading device as claimed in claim 6, It is characterized in that The stroke of the lifting component (B) is filled up, and the position of the range-extending component on the force transmission screw (12) is adjusted so that the range-extending component is closely attached to the pressure-bearing force transmission device (A), and the method also includes: The force transmission screw (12) is fixedly connected to the anchor bolt (19) cast in the test foundation (20) via the flange (15).

Citation Information

Patent Citations

  • Anti-lift load testing device for rock anchorage bar foundation

    CN104480977A

  • Range-extendable loading device for foundation uplift load test

    CN210395464U

  • Seal device of the lubrication unit

    RU112934U1

  • Telescopic cylinder

    SU1041775A1

  • Device for determining strength of ground in monolith

    SU1747596A1