A temporary plugging device and temporary plugging construction method suitable for oil and gas well after pressure relief

By designing a temporary blocking device suitable for the wellbore after oil and gas well pressing, using a sprinkler, a fracturing wellhead, a casing and a temporary blocking packer, combined with a seat sealing tool and a back-inserting docking decapsulator, the existing technology has been solved. The problems of long construction cycle, high costs and serious pollution have achieved efficient and safe oil and gas well construction and dynamic monitoring.

CN110306947BActive Publication Date: 2024-11-05JIANGSU FANGZHENG PETROLEUM MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910627987.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-07-12
Publication Date
2024-11-05
Estimated Expiration
2039-07-12

AI Technical Summary

Technical Problem

The construction methods in the wellbore after the fracturing of the existing oil and gas wells have problems such as long construction cycle, high labor intensity, high costs and serious pollution. The technology of unsealed sealing after temporary blocking and sealing has not been reported, which limits the efficiency of oil and gas mining. and cost control.

Method used

A temporary blocking device suitable for the wellbore after oil and gas well pressing is designed. The device consists of a sprinkler, a fracturing wellhead, a casing and a temporary blocking sealer. The temporary blocking sealer is connected to the seat sealing tool and passed through The back-insert docking unsealer realizes communication with the oil pipe, and uses seat sealing tools and back-insert docking unsealer for sealing and unsealing operations, avoiding the use of high-density liquids.

Benefits of technology

It realizes safe construction in the high-pressure wellbore after fracturing and acidification, reduces labor intensity and cost, simplifies construction processes, ensures dynamic monitoring and production demand of oil and gas wells, and reduces production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110306947B_ABST
    Figure CN110306947B_ABST
Patent Text Reader

Abstract

The present invention relates to a temporary plugging device and a temporary plugging construction method suitable for the wellbore after oil and gas wells are pressurized, and belongs to the field of oilfield equipment. The blowout preventer of the device is connected to the fracturing wellhead, and the fracturing wellhead is connected to the casing; the casing is provided with a temporary plugging packer, and the temporary plugging packer is connected to the sealing tool; the temporary plugging packer in the casing is separated from the sealing tool, and is connected to the back-insertion docking unsealer to achieve communication; the back-insertion docking unsealer is connected to the oil pipe, and the oil pipe is inserted into the casing. The temporary plugging device suitable for the wellbore after oil and gas wells is provided by the present invention, which can be constructed in high-pressure wellbore operations after fracturing and acidizing, without the need for well pressure operations and pressure-carrying equipment operations. The sealing methods are diverse, the structure is reasonable, and the operation is convenient. Electric sealing tools, hydraulic sealing tools, gunpowder sealing tools and other processes can be selected for connection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a temporary plugging device and a temporary plugging construction method suitable for a wellbore after oil and gas well pressure relief, belonging to the field of oilfield equipment. Background Art

[0002] In the process of oil and gas field development, after the oil and gas layers are transformed by fracturing and acidizing, the wellbore is often in a high-pressure state. In order to meet normal production requirements, it is necessary to replace the oil and gas wellheads and put production pipes into the wellbore. To meet the above requirements and ensure safe production, the operation and construction can currently choose well killing or pressure operation equipment. The pressure operation method is to pump high-density liquid into the well and then carry out other operations. The pressure operation equipment operation method is to install pressure operation equipment on the fracturing and acidizing wellhead and then carry out other operations. Both of the above operation methods can achieve the purpose of safe operation, but the construction period is long, the labor intensity is high, and the operation cost is high. During the well killing operation, a large amount of high-density liquid is squeezed into the formation, causing pollution, blocking the oil and gas layer and seriously affecting the production. After the well killing fluid is discharged, funds are needed for water quality treatment. The construction cost of each well with pressure operation equipment is hundreds of thousands of yuan. If the equipment is installed in each well after construction, the production cost will increase significantly, and the oil company will not be able to bear it. The above two operation methods are restricted to varying degrees in actual application. Currently, there is no report on the technology for timely releasing the isolation after temporary plugging.

[0003] Therefore, it is necessary to design a reasonable structure, high-pressure temporary plugging and connection technology in the wellbore after oil and gas fracturing and acidizing on the basis of existing technology to meet the requirements of oil and gas production. Summary of the invention

[0004] In view of the above-mentioned shortcomings, the present invention provides a temporary plugging device and a temporary plugging construction method suitable for the wellbore after oil and gas well pressure relief.

[0005] The present invention adopts the following technical solution:

[0006] The temporary plugging device for a wellbore after oil and gas well fracturing of the present invention is composed of a blowout preventer, a fracturing wellhead, and a casing; the blowout preventer is connected to the fracturing wellhead, and the fracturing wellhead is connected to the casing; the casing is provided with a temporary plugging packer, and the temporary plugging packer is connected to a sealing tool;

[0007] The temporary plugging packer in the casing is separated from the sealing tool and connected with the back-insertion docking unsealer to achieve communication; the back-insertion docking unsealer is connected with the oil pipe, and the oil pipe is inserted in the casing.

[0008] The temporary plugging device for oil and gas wells after pressure relief is described in the present invention. The temporary plugging packer comprises a fishing joint, a control joint, a limit joint, a central tube, a locking block sheath, a pressure transmission sleeve, an upper rubber tube seat, a rubber tube, a spacer ring, an outer central tube, a lower rubber tube seat, a sealing ring, a pressure cap, an upper cone, a slip sleeve, a slip, a hoop spring, and a lower cone.

[0009] The center tube has an axially penetrating inner cavity, one end of the center tube is sleeved with a lower cone and blocked by the lower cone; the other end of the center tube is sleeved with a salvage joint, and the salvage joint and the center tube are connected to each other;

[0010] The central tube on the upper part of the lower cone is sleeved with the upper cone, and a slip is arranged between the axial end faces opposite to the upper cone, and the outside of the slip is stabilized by a slip sleeve;

[0011] A limit joint is arranged between one end of the central tube sleeved with the salvage joint and the salvage joint, a control joint is arranged at the top of the limit joint, a pressure transmission sleeve is sleeved on the lower end of the salvage joint along the outer side of the outer circumferential surface of the central tube, a locking block sleeve is sleeved on the lower end of the pressure transmission sleeve along the outer side of the outer circumferential surface of the central tube, and a rubber cylinder seat is sleeved on the lower end of the locking block sleeve along the outer side of the outer circumferential surface of the central tube; a locking block structure is sleeved between the pressure transmission sleeve, the locking block sleeve, the rubber cylinder seat and the outer side of the circumferential surface of the central tube;

[0012] A lower rubber cylinder seat is sleeved on the outer side of the other end of the upper cone relative to the slip, at least two rubber cylinders are arranged between the axial end faces opposite to the lower rubber cylinder seat and the upper rubber cylinder seat, and a spacer ring is provided between the two rubber cylinders;

[0013] A connecting cavity is formed between the lower rubber cylinder seat and the central tube; a side hole is provided on the circumferential surface of the lower rubber cylinder seat, and the side hole is connected to the connecting cavity; an oil supply hole is provided on the circumferential surface of the central tube located at the lower rubber cylinder seat, and the oil supply hole connects the connecting cavity with the inner cavity of the central tube;

[0014] An outer center tube is also arranged between the rubber cylinder and the center tube. The upper end of the outer center tube is fixedly connected to the upper rubber cylinder seat, and the lower end of the outer center tube extends to the connecting cavity of the lower rubber cylinder seat. A movable pressure cap is arranged in the connecting cavity. The lower end of the outer center tube is in contact with the pressure cap and a sealing ring is provided between the two. The outer center tube is driven by the upper rubber cylinder seat to reciprocate along the axial extension direction of the center tube, so that the outer center tube, the pressure cap and the sealing ring cover or open the through hole of the lower rubber cylinder seat and the oil supply hole of the center tube.

[0015] The present invention is suitable for a temporary plugging device in a wellbore after oil and gas well pressure relief, and the locking block structure comprises a locking ring seat, a locking ring, a supporting ring, and a locking block; the locking ring seat is arranged between the pressure transmission sleeve, the locking block sleeve, the rubber tube seat and the center tube, and the locking ring and the supporting ring are arranged between the locking ring seat and the center tube; the locking ring and the supporting ring are both sleeved on the outer circumferential surface of the center tube; the locking block is embedded between the locking ring seat and the supporting ring.

[0016] The temporary plugging device for oil and gas wells after pressure relief is described in the present invention. The outer circumferential surface of the rubber cylinder seat is provided with a radially extending nail hole, and the outer circumferential surface of the central tube is provided with a clamping groove at a position relative to the nail hole of the rubber cylinder seat; the seat seal starting pin passes through the nail hole and its bottom is embedded in the clamping groove;

[0017] The outer circumferential surface of the salvage joint is provided with threads, and the lower part of the threads is provided with control shear nail holes extending radially, and the control shear nail holes penetrate the limit joint sleeved in the salvage joint; the sealing tool is connected to the salvage joint through the control shear nails.

[0018] The temporary plugging device for oil and gas wells after wellbore pressure reduction described in the present invention comprises an upper joint, an upper piston sleeve, an upper center pipe, a lower piston sleeve, a lower center pipe, a sealing core pipe, a sealing ring, a protective sleeve, a fishing claw, and a fishing tube;

[0019] The upper center tube, the lower center tube and the sealing core tube are connected to each other through threads, and the inner cavities of the upper center tube, the lower center tube and the sealing core tube are communicated with each other;

[0020] The top end of the upper center tube is connected to the upper joint through a thread, the outer circumferential surface of the bottom end of the sealing core tube is sleeved with a protective sleeve, the outer circumferential surface of the protective sleeve is sleeved on the salvage claw, the inner wall of the salvage claw is provided with a thread structure, and a gap is provided between the inner wall of the salvage claw and the outer circumferential wall of the protective sleeve;

[0021] The upper piston sleeve, the lower piston sleeve and the salvage tube are connected to each other through threads; the upper piston sleeve, the lower piston sleeve and the salvage tube are sleeved on the outer sides of the upper center tube, the lower center tube and the sealing core tube; the top end of the upper center tube is fixed to the upper joint.

[0022] The temporary plugging construction method of the temporary plugging device in the wellbore after oil and gas well pressure reduction according to the present invention comprises the following temporary plugging construction steps:

[0023] Step 1: The temporary plugging packer is sent into the casing by the sealing tool;

[0024] Step 2: Use the temporary plugging packer to plug the casing and remove the sealing tool;

[0025] Step 3: The temporary plugging packer is connected to the back-insertion docking unsealer, and the back-insertion docking unsealer is connected to the oil pipe;

[0026] Step 4: Reinsert the docking unsealer to supply oil into the oil pipe.

[0027] The temporary plugging construction method of the temporary plugging device in the wellbore after oil and gas well pressure relief described in the present invention comprises the following steps: in step 1, a sealing tool is connected to a cable, and the sealing tool is connected to the temporary plugging packer by controlling shear pins; the temporary plugging packer is sent from the blowout preventer into the casing by the sealing tool.

[0028] The temporary plugging construction method of the temporary plugging device in the wellbore after oil and gas well pressure relief described in the present invention, in step 2, destroys the controlled shear nails to separate the temporary plugging packer of the sealing tool, at which time the temporary plugging packer is retained in the casing to form a plugging state, a low-pressure area is formed on the upper layer of the temporary plugging packer, and a high-pressure area is formed on the lower layer of the temporary plugging packer.

[0029] The temporary plugging construction method of the temporary plugging device in the wellbore after oil and gas well pressure relief is described in the present invention. In step three, the back-inserted docking unsealer is connected with the oil pipe and then extended into the casing to dock with the temporary plugging packer. The inner spacing area of ​​the salvage claw on the back-inserted docking unsealer is threadedly engaged with the salvage joint to form an external closed structure; the inner cavity of the back-inserted docking unsealer and the inner cavity of the temporary plugging packer are connected to each other.

[0030] The temporary plugging construction method of the temporary plugging device in the wellbore after oil and gas well pressure relief of the present invention is as follows: in step 4, the sealing start pin of the temporary plugging packer upper seat is released, and the docking unsealer is pressed down and re-inserted so that the upper rubber cylinder seat pushes the outer central tube to move downward to plug the through hole of the lower rubber cylinder seat and the oil supply hole of the central tube; at the same time, the upper rubber cylinder seat and the lower rubber cylinder seat squeeze the rubber cylinder to make it expand radially;

[0031] Pulling up and plugging back the docking unsealer makes the through hole of the lower rubber cylinder seat and the oil supply hole of the center tube communicate with each other, and the oil in the high-pressure area enters the inner cavity of the center tube and moves to the low-pressure area through pressure.

[0032] Beneficial Effects

[0033] The temporary plugging device provided by the present invention is suitable for the wellbore after fracturing of oil and gas wells. It can be used in high-pressure wellbore operations after fracturing and acidizing, without the need for well killing operations or pressure-carrying equipment. The sealing method is diverse, the structure is reasonable, and the operation is convenient. Electric sealing tools, hydraulic sealing tools, gunpowder sealing tools and other processes can be selected for connection.

[0034] The temporary plugging construction method provided by the present invention is suitable for temporary plugging devices in wellbore after oil and gas well pressure relief. It solves the complex processes of back-insertion, docking, sealing, and unsealing by using a set of pipe strings, and realizes the three-way connection of oil, casing, and production layer at the same time. The temporary plugging packer is unsealed to timely avoid the difficulty of unsealing the packer after long-term operation, which requires major repairs. The three-way connection of oil, casing, and production layer provides feasibility for dynamic monitoring of oil and gas wells and meets production needs. It greatly simplifies the operation construction process, reduces labor intensity, reduces operation risks, and reduces operation construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a structural schematic diagram of the installation of the cable, the sealing tool and the temporary plugging packer of the present invention;

[0036] Figure 2 It is a schematic diagram of the temporary plugging packer of the present invention;

[0037] Figure 3 It is a schematic diagram of the setting tool and the temporary plugging packer of the present invention being released and separated;

[0038] Figure 4 It is a schematic diagram of the docking of the back-insertion docking release device and the temporary plugging packer of the present invention;

[0039] Figure 5 It is a schematic diagram of the connection after the temporary plugging packer of the present invention is unsealed;

[0040] Figure 6 It is a schematic diagram of the structure of the temporary plugging packer of the present invention;

[0041] Figure 7 It is a schematic diagram of the structure of the back-insertion docking unsealer of the present invention.

[0042] In the figure, a blowout preventer 1-1, a fracturing wellhead 1-2, a casing 1-3, a cable 1-4, a sealing tool 1-5, a temporary plugging packer 1-6, a tubing 1-7, and a back-insertion docking unsealer 1-8;

[0043] Salvage joint 1, control joint 2, limit joint 3, control shear nail 4, center pipe 5, lock ring seat 6, lock ring 7, support ring 8, lock block 9, lock block sleeve 10, pressure transmission sleeve 12, upper rubber cylinder seat 13, seat seal start pin 14, rubber cylinder 15, spacer ring 16, outer center pipe 17, lower rubber cylinder seat 18, sealing ring 19, pressure cap 20, upper cone 21, slip sleeve 22, slip 23, hoop spring 24, lower cone 25, side hole 26, connecting cavity 27, oil supply hole 28;

[0044] Upper joint 71, upper piston sleeve 72, upper center tube 73, lower piston sleeve 74, lower center tube 75, sealing core tube 76, sealing ring 77, protective sleeve 78, salvage claw 79, salvage tube 710, impact pin 711, and pressure cap 712. DETAILED DESCRIPTION

[0045] In order to make the purpose and technical solution of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] like Figure 1As shown: a temporary plugging device suitable for a wellbore after oil and gas well pressure, the wellbore after oil and gas well pressure is composed of a blowout preventer 1-1, a fracturing wellhead 1-2, and a casing 1-3; the blowout preventer 1-1 is connected to the fracturing wellhead 1-2, and the fracturing wellhead 1-2 is connected to the casing 1-3; the casing 1-3 is provided with a temporary plugging packer 1-6, and the temporary plugging packer 1-6 is connected to a sealing tool 1-5;

[0047] The temporary plugging packer 1-6 in the casing 1-3 is separated from the sealing tool 1-5 and connected to the back-insertion docking unsealer 1-8 to achieve communication; the back-insertion docking unsealer 1-8 is connected to the oil pipe 1-7, and the oil pipe 1-7 is inserted in the casing 1-3.

[0048] After the temporary plugging packer 6 is seated, the oil and gas channel is closed and sealed, and the high-pressure production layer is sealed; the cable 4 and the sealing tool 5 are separated from the temporary plugging packer 6; the oil pipe 7 is threadedly connected with the back-insertion docking unsealer 8; after the back-insertion docking unsealer 8 is back-inserted and docked with the temporary plugging packer 6, the temporary plugging packer 6 is hydraulically unsealed, so that the oil pressure, casing pressure and high-pressure production layer are all connected to meet the production requirements.

[0049] like Figure 6 The temporary plugging device shown is suitable for the wellbore after the oil and gas well is pressurized. The temporary plugging packer 1-6 includes a fishing joint 1, a control joint 2, a limit joint 3, a control shear nail 4, a central tube 5, a lock ring seat 6, a lock ring 7, a support ring 8, a lock block 9, a lock block sleeve 10, a pressure transmission sleeve 12, an upper rubber cylinder seat 13, a seat seal start pin 14, a rubber cylinder 15, a spacer ring 16, an outer central tube 17, a lower rubber cylinder seat 18, a sealing ring 19, a pressure cap 20, an upper cone 21, a slip sleeve 22, a slip 23, a hoop spring 24, a lower cone 25, a through hole 26, a connecting cavity 27, and an oil supply hole 28;

[0050] The center tube 5 has an axially penetrating inner cavity. One end of the center tube 5 is sleeved with a lower cone 25 and blocked by the lower cone 25. The other end of the center tube 5 is sleeved with a salvage joint 1, and the salvage joint 1 and the center tube 5 are connected to each other. The center tube 5 on the upper part of the lower cone 25 is sleeved with an upper cone 21, and a slip 23 is provided between the axial end faces opposite to the upper cone 21 and the lower cone 25, and the slip 23 is stabilized by a slip sleeve 22.

[0051] A limit joint 3 is arranged between one end of the center tube 5 sleeved with the salvage joint 1 and the salvage joint 1, a control joint 2 is arranged at the top of the limit joint 3, a pressure transmission sleeve 12 is sleeved on the lower end of the salvage joint 1 along the outer side of the outer circumference of the center tube 5, a locking block sleeve 10 is sleeved on the lower end of the pressure transmission sleeve 12 along the outer side of the outer circumference of the center tube 5, and a rubber cylinder seat 13 is sleeved on the lower end of the locking block sleeve 10 along the outer side of the outer circumference of the center tube; a locking block structure is sleeved between the pressure transmission sleeve 12, the locking block sleeve 10, the rubber cylinder seat 13 and the outer side of the circumference of the center tube 5;

[0052] A lower rubber cylinder seat 18 is sleeved on the outer side of the other end of the upper cone 21 relative to the slip, at least two rubber cylinders 15 are arranged between the axial end faces of the lower rubber cylinder seat 18 and the upper rubber cylinder seat 13, and a spacer ring 16 is provided between the two rubber cylinders 15; a communication cavity 27 is formed between the lower rubber cylinder seat 18 and the center tube 5; a side hole 26 is provided on the circumferential surface of the lower rubber cylinder seat 18, and the side hole 26 and the communication cavity 27 are communicated with each other, and an oil supply hole 28 is provided on the circumferential surface of the center tube 5 located at the lower rubber cylinder seat 18, and the oil supply hole 28 connects the communication cavity 27 with the inner cavity of the center tube;

[0053] An outer central tube 17 is also arranged between the rubber cylinder 15 and the central tube 5. The upper end of the outer central tube 17 is fixedly connected to the upper rubber cylinder seat 13, and the lower end of the outer central tube 17 extends into the communication cavity 27 of the lower rubber cylinder seat 18. A movable pressure cap 20 is arranged in the communication cavity 27. The lower end of the outer central tube 17 contacts the pressure cap 20 and a sealing ring 19 is arranged between the two. The outer central tube 17 is driven by the upper rubber cylinder seat 18 to reciprocate along the axial extension direction of the central tube 5, so that the outer central tube 17, the pressure cap 20 and the sealing ring 19 cover or open the through hole of the lower rubber cylinder seat and the oil supply hole 28 of the central tube. The side hole is the oil casing switch channel. When the oil casing channel is closed, the seat seal is pushed to move the outer central tube 17 and the sealing ring 19 upward to close the upper side hole 26 of the central tube 5. The oil casing channel is opened: when unsealing, the outer central tube 17 and the sealing ring 19 are pulled downward to expose the upper side hole 26 of the central tube 5.

[0054] The locking block structure of the present invention includes a locking ring seat 6, a locking ring 7, a support ring 8, and a locking block 9; the locking ring seat 6 is arranged between the pressure transmission sleeve 12, the locking block sleeve 10, the rubber cylinder seat 13 and the center tube 5, and the locking ring 7 and the support ring 8 are arranged between the locking ring seat 6 and the center tube 5; the locking ring 7 and the support ring 8 are both sleeved on the outer circumferential surface of the center tube 5; the locking block 9 is embedded between the locking ring seat 6 and the support ring 7.

[0055] A radially extending nail hole is provided on the outer circumferential surface of the rubber cylinder seat 13, and a clamping groove is provided on the outer circumferential surface of the central tube at a position corresponding to the nail hole of the rubber cylinder seat 13; the seat seal starting pin 14 passes through the nail hole and its bottom is embedded in the clamping groove;

[0056] The outer circumferential surface of the salvage joint 1 is provided with threads, and the lower part of the threads is provided with control shear nail holes 4 extending in the radial direction, and the control shear nail 4 holes penetrate the limit joint 3 sleeved in the salvage joint; the sealing tool 5 is connected to the salvage joint 1 through the control shear nail 4. The control joint 2 is plug-in connected to the limit joint 3 and fixed by the control shear nail 4. After the temporary plugging packer 6 is sealed, the control shear nail 4 is cut off, and the sealing tool 5 and the temporary plugging packer 6 can be separated.

[0057] The back-insertion docking unsealing device includes an upper joint 71, an upper piston sleeve 72, an upper center tube 73, a lower piston sleeve 74, a lower center tube 75, a sealing core tube 76, a sealing ring 77, a protective sleeve 78, a salvage claw 79, a salvage tube 710, a collision pin 711, and a pressure cap 712;

[0058] The upper center tube 73, the lower center tube 75 and the sealing core tube 76 are connected to each other through threads, and the inner cavities of the upper center tube 73, the lower center tube 75 and the sealing core tube 76 are connected to each other; the top of the upper center tube 73 is connected to the upper joint 71 through threads, and the outer circumferential surface of the bottom end of the sealing core tube 76 is sleeved with a protective sleeve 78, and the outer circumferential surface of the protective sleeve 78 is sleeved on the fishing claw 79, and the inner wall of the fishing claw 79 is provided with a threaded structure, and a certain distance is provided between the inner wall of the fishing claw 79 and the outer circumferential wall of the protective sleeve 78;

[0059] The upper piston sleeve 72, the lower piston sleeve 74 and the overshot tube 710 are connected to each other by threads; the upper piston sleeve 72, the lower piston sleeve 74 and the overshot tube 710 are sleeved on the outside of the upper center tube 73, the lower center tube 75 and the sealing core tube 76; the top end of the upper center tube 73 is fixed to the upper joint 71.

[0060] When the unsealer 7 is inserted back and docked with the temporary plugging packer 6, the sealing core tube 76 is inserted into the central tube 5, and the salvage tube 710 and the salvage claw 79 are engaged with the salvage joint 1 and firmly grasped.

[0061] The temporary plugging packer 6 is unsealed, and the oil in the casing 1-3 enters the back-insertion docking unsealer 7 from the oil pipe 1-7 through the hydraulic pressure, pushing the overshot tube 710 and the overshot claw 79 upward, pulling up the overshot head 1, so that the rubber tube 15 and the slips 23 are restored to their original state, and the closed channel at the side hole 26 of the central pipe 5 is opened.

[0062] like Figure 1 Only Figure 5 As shown: A temporary plugging construction method applicable to a temporary plugging device in a wellbore after oil and gas well pressure relief. The construction steps are as follows:

[0063] Step 1: The temporary plugging packer is sent into the casing by the sealing tool;

[0064] The specific operation is as follows: the sealing tool is connected to the cable, and the sealing tool is connected to the temporary plugging packer through the control shear nails; the temporary plugging packer is sent from the blowout preventer into the casing by the sealing tool.

[0065] Step 2: Use the temporary plugging packer to plug the casing and remove the sealing tool;

[0066] The specific operation is: destroy the control shear nails to separate the temporary plugging packer of the sealing tool. At this time, the temporary plugging packer is retained in the casing to form a plugging state, a low-pressure area is formed on the upper layer of the temporary plugging packer, and a high-pressure area is formed on the lower layer of the temporary plugging packer.

[0067] Step 3: The temporary plugging packer is connected to the back-insertion docking unsealer, and the back-insertion docking unsealer is connected to the oil pipe;

[0068] The specific operation is as follows: after the back-insertion docking unsealer is connected to the oil pipe, it is inserted into the casing to dock with the temporary plugging packer; the inner spacing area of ​​the salvage claw on the back-insertion docking unsealer is threadedly engaged with the salvage joint to form an external closed structure; the inner cavity of the back-insertion docking unsealer and the inner cavity of the temporary plugging packer are connected to each other.

[0069] Step 4: Reinsert the docking unsealer to supply oil into the oil pipe;

[0070] The specific operation is as follows: release the upper seat seal start pin of the temporary plugging packer, press down and insert the docking unsealer to make the upper rubber cylinder seat push the outer central tube to move downward to seal the through hole of the lower rubber cylinder seat and the oil supply hole of the central tube; at the same time, the upper rubber cylinder seat and the lower rubber cylinder seat squeeze the rubber cylinder to make it expand radially;

[0071] Pulling up and plugging back the docking unsealer makes the through hole of the lower rubber cylinder seat and the oil supply hole of the center tube communicate with each other, and the oil in the high-pressure area enters the inner cavity of the center tube and moves to the low-pressure area through pressure.

[0072] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily realized by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A temporary plugging construction method for a temporary plugging device in a wellbore after oil and gas well pressure, wherein the wellbore after oil and gas well pressure is composed of a blowout preventer, a fracturing wellhead, and a casing; the blowout preventer is connected to the fracturing wellhead, and the fracturing wellhead is connected to the casing; characterized in that: The casing is provided with a temporary plugging packer, which is connected to a sealing tool; The temporary plugging packer in the casing is separated from the sealing tool and connected to the back-insertion docking unsealer to achieve communication; the back-insertion docking unsealer is connected to the oil pipe, and the oil pipe is inserted in the casing; The temporary plugging packer includes a salvage joint, a control joint, a limit joint, a central tube, a locking block sheath, a pressure transmission sleeve, an upper rubber tube seat, a rubber tube, a spacer ring, an outer central tube, a lower rubber tube seat, a sealing ring, a pressure cap, an upper cone, a slip sleeve, a slip, a hoop spring, and a lower cone; The center tube has an axially penetrating inner cavity, one end of the center tube is sleeved with a lower cone and blocked by the lower cone; the other end of the center tube is sleeved with a salvage joint, and the salvage joint and the center tube are connected to each other; The central tube on the upper part of the lower cone is sleeved with the upper cone, and a slip is arranged between the axial end faces opposite to the upper cone, and the outside of the slip is stabilized by a slip sleeve; A limit joint is arranged between one end of the central tube sleeved with the salvage joint and the salvage joint, a control joint is arranged at the top of the limit joint, a pressure transmission sleeve is sleeved on the lower end of the salvage joint along the outer side of the outer circumference of the central tube, a locking block sleeve is sleeved on the lower end of the pressure transmission sleeve along the outer side of the outer circumference of the central tube, and a rubber sleeve is sleeved on the lower end of the locking block sleeve along the outer side of the outer circumference of the central tube; a locking block structure is sleeved between the pressure transmission sleeve, the locking block sleeve, the rubber sleeve and the outer side of the outer circumference of the central tube; A lower rubber cylinder seat is sleeved on the outer side of the other end of the upper cone relative to the slip, at least two rubber cylinders are arranged between the axial end faces opposite to the lower rubber cylinder seat and the upper rubber cylinder seat, and a spacer ring is provided between the two rubber cylinders; A connecting cavity is formed between the lower rubber cylinder seat and the central tube; a side hole is provided on the circumferential surface of the lower rubber cylinder seat, and the side hole is connected to the connecting cavity; an oil supply hole is provided on the circumferential surface of the central tube located at the lower rubber cylinder seat, and the oil supply hole connects the connecting cavity with the inner cavity of the central tube; An outer center tube is arranged between the rubber cylinder and the center tube, the upper end of the outer center tube is fixedly connected to the upper rubber cylinder seat, the lower end of the outer center tube extends into the communicating cavity of the lower rubber cylinder seat, a movable pressure cap is arranged in the communicating cavity, the lower end of the outer center tube contacts the pressure cap and a sealing ring is arranged between the two; the outer center tube is driven by the upper rubber cylinder seat to reciprocate along the axial extension direction of the center tube, so that the outer center tube, the pressure cap and the sealing ring cover or open the side hole of the lower rubber cylinder seat and the oil supply hole of the center tube; The back-insertion docking unsealing device comprises an upper joint, an upper piston sleeve, an upper center tube, a lower piston sleeve, a lower center tube, a sealing core tube, a sealing ring, a protective sleeve, a salvage claw, and a salvage tube; The upper center tube, the lower center tube and the sealing core tube are connected to each other through threads, and the inner cavities of the upper center tube, the lower center tube and the sealing core tube are communicated with each other; The top end of the upper center tube is connected to the upper joint through a thread, the outer circumferential surface of the bottom end of the sealing core tube is sleeved with a protective sleeve, the outer circumferential surface of the protective sleeve is sleeved on the salvage claw, the inner wall of the salvage claw is provided with a thread structure, and a gap is provided between the inner wall of the salvage claw and the outer circumferential wall of the protective sleeve; The upper piston sleeve, the lower piston sleeve and the overshot tube are connected to each other through threads; the upper piston sleeve, the lower piston sleeve and the overshot tube are respectively sleeved on the outer sides of the upper center tube, the lower center tube and the sealing core tube; the top end of the upper center tube is fixedly connected to the upper joint; The locking block structure comprises a locking ring seat, a locking ring, a supporting ring, and a locking block; the locking ring seat is arranged between the pressure transmission sleeve, the locking block sleeve, the rubber cylinder seat and the central tube, and the locking ring and the supporting ring are arranged between the locking ring seat and the central tube; the locking ring and the supporting ring are both sleeved on the outer circumference of the central tube; the locking block is embedded between the locking ring seat and the supporting ring; The outer circumferential surface of the rubber cylinder seat is provided with a radially extending nail hole, and the outer circumferential surface of the central tube is provided with a clamping groove at a position corresponding to the nail hole of the rubber cylinder seat; the seat seal starting pin passes through the nail hole, and its bottom is embedded in the clamping groove; The outer circumferential surface of the salvage joint is provided with threads, and the lower part of the threads is provided with control shear pins extending radially, and the control shear pins penetrate the limit joint sleeved in the salvage joint; the sealing tool is connected to the salvage joint through the control shear pins; The temporary plugging construction steps are as follows: Step 1: The temporary plugging packer is sent into the casing by the sealing tool; Step 2: Use the temporary plugging packer to plug the casing and remove the sealing tool; Step 3: The temporary plugging packer is connected to the back-insertion docking unsealer, and the back-insertion docking unsealer is connected to the oil pipe; Step 4: Reinsert the docking unsealer to supply oil into the oil pipe.

2. The temporary plugging construction method for a temporary plugging device in a wellbore after pressure reduction of an oil and gas well according to claim 1, characterized in that: In the step 1, the sealing tool is connected to the cable, and the sealing tool is connected to the temporary plugging packer through the control shear nail; the temporary plugging packer is sent from the blowout preventer into the casing by the sealing tool.

3. The temporary plugging construction method for a temporary plugging device in a wellbore after pressure reduction of an oil and gas well according to claim 1, characterized in that: In step 2, the control shear pins are destroyed to separate the sealing tool and the temporary plugging packer. At this time, the temporary plugging packer is retained in the casing to form a plugging state, a low-pressure area is formed on the upper layer of the temporary plugging packer, and a high-pressure area is formed on the lower layer of the temporary plugging packer.

4. The temporary plugging construction method for a temporary plugging device in a wellbore after pressure reduction of an oil and gas well according to claim 1, characterized in that: In step three, the back-insertion docking unsealer is connected to the oil pipe and then inserted into the casing to dock with the temporary plugging packer. The inner spacing area of ​​the salvage claw on the back-insertion docking unsealer is threadedly engaged with the salvage joint to form an external closed structure; the inner cavity of the back-insertion docking unsealer is connected to the inner cavity of the temporary plugging packer.

5. The temporary plugging construction method for a temporary plugging device in a wellbore after pressure relief of an oil and gas well according to claim 1, characterized in that: In step 4, the sealing start pin of the temporary plugging packer is released, and the docking unsealer is pressed down and re-inserted so that the upper rubber cylinder seat pushes the outer center tube downward to seal the side hole of the lower rubber cylinder seat and the oil supply hole of the center tube; at the same time, the upper rubber cylinder seat and the lower rubber cylinder seat squeeze the rubber cylinder to cause radial expansion and deformation; the docking unsealer is pulled up and re-inserted so that the side hole of the lower rubber cylinder seat and the oil supply hole of the center tube are connected, and the oil in the high-pressure area enters the inner cavity of the center tube and moves to the low-pressure area through pressure.