Three-dimensional prefabricated fully assembled concrete structure method

Through the three-dimensional prefabricated fully-assembled concrete structure method and the support and top circulation system, the problems of unreliability and low assembly rate of the node core area caused by two-dimensional plane prefabrication are solved, and efficient three-dimensional assembly is achieved, which improves assembly rate and seismic resistance. , ensuring the reliability and construction efficiency of the building.

CN110485570BActive Publication Date: 2024-11-08杨秀敏
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910724476.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-08-07
Publication Date
2024-11-08
Estimated Expiration
2039-08-07

AI Technical Summary

Technical Problem

The existing prefabricated concrete structure adopts two-dimensional planar prefabrication method, which leads to unreliability of the node core area, difficulty in three-dimensional assembly, and low assembly rate, which affects construction efficiency and quality.

Method used

Adopt the three-dimensional prefabricated fully-assembled concrete structure method, and build a supporting top circulation system to prefabricated concrete structure layer by layer in the prefabricated factory building to ensure the integrity of the node core area, and use the liftable supporting top circulation system to achieve smooth dismantling of the upper and lower prefabricated units. Install and connect.

Benefits of technology

Improve the reliability of the node core area and steel bar anchoring, enhance the structure's seismic resistance, significantly improve the assembly rate from 50% to 99%, realize the separation of factory prefabricated and on-site assembly, and ensure the reliability and construction of the building. Convenience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110485570B_ABST
    Figure CN110485570B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for prefabricating a three-dimensional fully assembled concrete structure. When the present invention is used to prefabricate a fully assembled concrete structure, the concrete structure of each layer is divided into a plurality of prefabricated units on the premise of ensuring the integrity of the core area of ​​the concrete structure node. On the basis of ensuring smooth disassembly and assembly between the prefabricated units of each layer, smooth disassembly and assembly between the corresponding prefabricated units of the upper and lower layers can also be ensured. In conjunction with a liftable support top circulation system, prefabrication is carried out in a cycle from bottom to top until the highest level of the design project. The prefabricated units divided according to the core area of ​​the concrete structure node are easy to build, can directly improve the strength of the core area of ​​the node, and can also indirectly improve the anchoring and connection strength of the steel bars. In summary, the present invention can achieve the separation of factory prefabrication and on-site assembly, achieve the purpose of "giving reliability to the factory and convenience to the site", and ultimately ensure the reliability and convenience of the fully assembled concrete structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of buildings, and in particular to a three-dimensional prefabricated fully assembled concrete structure method. Background Art

[0002] Prefabricated concrete structure is the mainstream structure of prefabricated buildings due to its irreplaceable superiority. After decades of efforts by modern humans, prefabricated concrete structure has continued to develop. In order to vigorously develop prefabricated buildings and promote the adjustment and upgrading of industrial structure, the "Guiding Opinions on Vigorously Developing Prefabricated Buildings" was issued in recent years, and prefabricated concrete structure has been greatly developed and improved.

[0003] To date, the prefabrication method of assembled concrete structures has adopted two-dimensional plane prefabrication, which is to split the most important node core area of ​​the concrete structure, destroying the integrity of the node core area. The assembly connection after prefabrication also reduces the reliability of the node core area. At the same time, two-dimensional plane prefabrication will inevitably bring difficulties in the connection of many steel bars in three-dimensional assembly. We believe that: the component products produced by the factory are very good-looking, factory production and on-site installation are very environmentally friendly, and very meaningful in the long run; the production method has made great progress; but most of the production methods are still simple, and the products produced are basically not convenient for construction; the results of the construction are constantly controversial, and the main negative views are that it is unreliable, troublesome, and expensive. This is the inevitable result of two-dimensional plane prefabrication and three-dimensional installation.

[0004] In view of the above technical problems, there is an urgent need to develop a completely new three-dimensional prefabricated fully assembled concrete structure method to ensure the reliability of the core area of ​​the node after the assembly and connection of the assembled concrete structure, as well as the reliability of the anchorage and connection of the steel bars in the concrete structure. While ensuring these two, an assembled concrete structure with a stronger seismic performance than the cast-in-place concrete structure can be built. At the same time, the assembly rate of the assembled concrete structure can be greatly increased from less than 50% to 99%, that is, full assembly. Summary of the invention

[0005] The purpose of the present invention is to provide a three-dimensional prefabricated fully assembled concrete structure method to solve the technical problem of unreliable structure after assembly of two-dimensional plane prefabricated concrete structures in the prior art; the purpose of the present invention is also to provide a top support circulation system used in the above method.

[0006] To achieve the above-mentioned purpose, the technical solution adopted by the three-dimensional prefabricated fully assembled concrete structure method of the present invention is:

[0007] The method for prefabricating a three-dimensional fully assembled concrete structure comprises the following steps: the first step is to build a support and top circulation system including a construction platform in a prefabricated plant or on flat ground; the second step is to prefabricate the concrete structure layer by layer on the construction platform; the second step specifically comprises the following steps: step 201, firstly build a first-layer concrete structure on a first-layer construction platform, and build a second-layer concrete structure on a second-layer construction platform, and use the first-layer concrete structure as a reference when building the second-layer concrete structure, and pre-connect the vertical steel bars of the second layer with the vertical steel bars of the first layer; step 202, separate the first-layer concrete structure from under the second-layer concrete structure, that is, lift up the second-layer construction platform through the support and top circulation system, and remove the first-layer concrete structure together with the first-layer construction platform from the support and top circulation system; step 203, The second-layer construction platform including the second-layer concrete structure is lowered to the position of the original first-layer construction platform through the support top circulation system and the support is replaced; step 204, the upper section of the support top circulation system rises one layer again, and a third-layer construction platform is built above the lowered second-layer concrete structure, and a third-layer concrete structure is built on the third-layer construction platform based on the second-layer concrete structure; step 205, the above steps are repeated to dismantle the next-layer concrete structure and the next-layer construction platform, and to lower the previous-layer construction platform including the previous-layer concrete structure and to continue to build a higher-layer construction platform and build a higher-layer concrete structure based on it, until the highest N-th layer of concrete structure is built; in the second step, each layer of concrete structure includes a plurality of prefabricated units split according to the node core area.

[0008] The third step is to transport the prefabricated units to the engineering assembly site and assemble and connect them layer by layer in sequence. The steps are as follows: Step 301, assemble the prefabricated units that form the vertical components of the first-layer concrete structure; Step 302, after all the vertical components of the first-layer concrete structure are assembled, assemble the prefabricated units that form the horizontal components of the first-layer concrete structure; Step 303, pour concrete at the reserved joint position of the first layer to complete the assembly of the first-layer concrete structure; Step 304, assemble layer by layer upwards until the overall assembly of the built house is completed.

[0009] In the second step, before the concrete structure of the corresponding layer is dismantled, the prefabricated units constituting the layer are numbered.

[0010] There is a reserved gap between two adjacent prefabricated units for disassembly and assembly.

[0011] The technical solution adopted by the top support circulation system of the present invention is:

[0012] The support top circulation system for realizing a three-dimensional prefabricated fully assembled concrete structure method comprises a construction platform and a support top assembly for supporting the construction platform, wherein the support top assembly comprises a hollow lower section of a cylinder, in which an movable section of a cylinder that can be raised and lowered is inserted in the air, a movable support is installed at the top of the movable section of the cylinder, a conversion support is installed at the top of the lower section of the cylinder, the conversion support has a through hole through which the movable section of the cylinder extends, a groove is provided at the lower end of the movable support, the cross-sectional shape of the groove is consistent with the cross-sectional shape of the movable section of the cylinder, the movable support is detachably mounted on the top of the movable section of the cylinder through the groove, the through-hole size is smaller than the lower end size of the movable support, a receiving groove for accommodating the movable support and allowing the movable support to be taken out from the side is provided in the middle of the conversion support, the upper end surface of the conversion support has a first supporting surface, the upper end surface of the movable support has a second supporting surface, the first supporting surface is parallel to the second supporting surface, and an avoidance hole is provided on the construction platform for the movable section of the cylinder without the movable support installed to pass through.

[0013] The conversion support includes a connecting part and a side supporting part. The conversion support is installed on the top of the lower section of the cylinder through the connecting part. Two side supporting parts are arranged at intervals. The two side supporting parts are symmetrically arranged on the left and right sides of the connecting part. The upper end surfaces of the two side supporting parts form the first supporting surface. The through hole is arranged on the connecting part. The two side supporting parts are completely staggered from the through hole so as not to affect the lifting and lowering of the movable section of the cylinder.

[0014] The second supporting surface is an elongated structure, and the interval between the two side supporting portions is greater than the width of the second supporting surface to form the accommodating groove.

[0015] The connecting portion comprises a cylindrical structure with split grooves symmetrically provided on the front and rear sides, the upper end of the split groove is open, and the width of the split groove is greater than the width of the second supporting surface to form the accommodating groove.

[0016] The lower end of the connecting part is provided with a connecting groove which matches the shape of the top end of the lower section of the oil cylinder and is sleeved on the top end of the lower section of the oil cylinder.

[0017] The lower section of the oil cylinder is the fixed part of the oil cylinder, the movable section of the oil cylinder is the piston rod part of the oil cylinder, and the top support components are arranged in multiple groups.

[0018] The beneficial effects of the present invention are as follows: when the fully assembled concrete structure is prefabricated using the present invention, the division of the concrete structure prefabricated units of each layer is based on the premise of ensuring the integrity of the node core area. By building a construction platform for the complete layer, several concrete structure prefabricated units of the complete layer are prefabricated, and the prefabricated units are smoothly disassembled and assembled. At the same time, the concrete structure of the upper layer is prefabricated based on the concrete structure of the lower layer. By prefabricating the concrete structures of two adjacent layers on the construction platform, the disassembly and assembly of the corresponding prefabricated units of the upper and lower layers can be ensured to be smooth. With the lifting and lowering support top circulation system, the prefabrication is carried out from bottom to top until the highest layer of the design project, and the total number of layers of the highest layer can be exactly the same as the cast-in-place concrete structure. The prefabricated units divided based on the premise of ensuring the integrity of the core area of ​​the concrete structure node are easy to build, can directly improve the strength of the core area of ​​the node, and indirectly improve the anchoring and connection strength of the steel bars, and can build an assembled concrete structure with a stronger structural seismic performance than the cast-in-place concrete structure. At the same time, even complex parts such as elevator shafts and core tubes are prefabricated and assembled according to the same method, which can greatly increase the assembly rate of assembled concrete structures from the current less than 50% to 99%, that is, full assembly. In summary, the present invention can realize the separation of factory prefabrication and on-site assembly, achieve the purpose of "giving reliability to the factory and convenience to the site", and ultimately ensure the reliability and convenience of the fully assembled concrete structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a structural schematic diagram of an embodiment of the support top circulation system of the present invention when the movable section of the oil cylinder is lowered to the bottom;

[0020] Figure 2 yes Figure 1 A top view of

[0021] Figure 3 for Figure 1 The schematic diagram of the structure of the top support circulation system after the construction platform and movable supports are removed;

[0022] Figure 4 yes Figure 1 Schematic diagram of the structure when the movable section of the cylinder is raised to the first state.

[0023] Figure 5 It is a structural schematic diagram of a top supporting circulation system in an embodiment of the present invention when multiple groups of top supporting components are arranged, when the movable section of the cylinder is raised to the second state.

[0024] Figure 6 yes Figure 5 A schematic diagram of the structure when the movable section of the oil cylinder is raised to a level higher than the second state and the first-layer concrete structure and the first-layer construction platform are removed. DETAILED DESCRIPTION

[0025] The present invention will be further described below in conjunction with the accompanying drawings.

[0026] Embodiments of the three-dimensional prefabricated fully assembled concrete structure method of the present invention:

[0027] The three-dimensional prefabricated fully assembled concrete structure method is used to realize the three-dimensional prefabrication of concrete structures. The three-dimensional prefabricated concrete structure has high strength in the core area of ​​the node and high strength in the steel bar connection. Ideally, an assembled concrete structure with stronger seismic performance than the cast-in-place concrete structure can be built. The overall strength of the assembled building can be stronger than that of the cast-in-place building. Specifically, the following steps are included:

[0028] The first step is to build a roof support circulation system including a construction platform in a prefabricated factory building or on flat ground.

[0029] The second step is to prefabricate the concrete structure layer by layer on the construction platform. The specific steps include:

[0030] Step 201, firstly build a first layer of concrete structure on a first layer construction platform, and build a second layer of concrete structure on a second layer construction platform, the first layer of concrete structure is used as a reference when building the second layer of concrete structure, and the vertical steel bars of the second layer are pre-connected with the vertical steel bars of the first layer;

[0031] Step 202, separating the first layer of concrete structure from under the second layer of concrete structure, that is, lifting up the second layer of construction platform through the supporting and jacking circulation system, and removing the first layer of concrete structure together with the first layer of construction platform from the supporting and jacking circulation system;

[0032] Step 203, lowering the second-layer construction platform including the second-layer concrete structure to the position of the original first-layer construction platform through the support top circulation system and replacing the support;

[0033] Step 204, the upper section of the supporting top circulation system rises one layer again, and a third-layer construction platform is built above the lowered second-layer concrete structure, and a third-layer concrete structure is built on the third-layer construction platform based on the second-layer concrete structure;

[0034] Step 205, the above steps are repeated to dismantle the next layer of concrete structure and the next layer of construction platform, to lower the upper layer of construction platform including the upper layer of concrete structure and to continue to build the upper layer of construction platform and the upper layer of concrete structure upwards based on it, until the highest layer N-th layer of concrete structure is built.

[0035] After step 205, the concrete structures of each layer can be dismantled for curing and storage, and then transported to the engineering assembly site for assembly when needed.

[0036] In the second step, each layer of concrete structure is composed of multiple prefabricated units divided by the node core area, which is divided during the detailed design stage of the construction drawing. The following points should be noted when dividing the prefabricated units: First, the division should be carried out around the node core area on the basis of retaining the integrity of the node core area; second, the hoisting and transportation capacity of the prefabricated unit should be considered, and the weight of the prefabricated unit can be controlled at about 200KN. Third, the size of the reserved seam between two adjacent prefabricated units should be considered, which is generally controlled at 230mm to 260mm.

[0037] In this embodiment, the weight of the prefabricated unit is controlled at about 200KN, mainly because if it is too small, it is not conducive to ensuring that the core area of ​​the node is completely divided, and a certain volume and weight are required, and if it is too small, more connection parts will be added; if it is too large, it is not conducive to hoisting and transportation, and the maximum hoisting capacity of existing large tower cranes is less than 10000KNm, that is, hoisting a weight of 200KN and extending 50m away. With the advancement of hoisting equipment and technical level and better transportation conditions, in other embodiments, the prefabricated unit can be made larger and heavier.

[0038] In this embodiment, the size of the reserved gap between two adjacent prefabricated units is controlled at 230mm to 260mm. First, the movable section of the oil cylinder of the support top circulation system needs to pass through this reserved gap when it rises, and the diameter of the movable section of the oil cylinder needs to be 240mm. This reserved gap can be used as an avoidance gap. Second, each prefabricated unit needs to be pre-connected with a steel sleeve before pouring concrete. After pouring and solidifying the concrete, the steel sleeve needs to be unscrewed to disassemble the prefabricated unit. It also needs to be used as an installation gap to reconnect the steel sleeve during on-site assembly. When pre-connecting the steel sleeve, unscrewing the steel sleeve, and reconnecting the steel sleeve, it is more convenient and quick to use special tools, and the operating spacing of the special tools needs to be about 230mm; third, after the steel bars of each unit block are connected, each unit block needs to be poured by pouring new concrete to form an integral structure. This reserved gap is used as a post-casting strip. If it is too large, it will increase the amount of concrete poured on site and reduce the assembly rate of the fully assembled concrete structure.

[0039] In this step, in order to avoid difficulty in identification after splitting, it is necessary to number each prefabricated unit before splitting the concrete structure of the corresponding layer.

[0040] When manufacturing prefabricated units, the corresponding connecting end steel bars of the two interconnected prefabricated units are processed with a threaded big head with a diameter larger than the diameter of the steel bar base material. After one of the prefabricated units is manufactured, the threaded big heads of the two are pre-connected together through a sleeve, and then the concrete of the other prefabricated unit is poured, or the two prefabricated units are poured with concrete at the same time after pre-connection. In this way, when the two disassembled prefabricated units are connected again, there is no need to re-align the threads of the threaded big heads, thereby ensuring the smooth connection of the two adjacent prefabricated units. The above-mentioned steel bar threaded big heads and sleeves were independently developed by the applicant. For details, please see the utility model "Rebar connector with coarse threaded big heads and sleeves" CN201821095637.3.

[0041] The key to whether the seismic performance of concrete structures is reliable is whether the core area of ​​the nodes is reliable, which is mainly reflected in whether the node stirrup densification area is well done. Based on the applicant's experience in engineering quality supervision for more than ten years, it is known that due to the excessive and dense steel bars in the core area of ​​the nodes, and the long main bars and even hooks, it is difficult to install the densified stirrups of the vertical components at the core position of the nodes. These densified stirrups are either put in a pile or simply not put. Even if these densified stirrups are put in place and formed separately in advance, they are cut off later because the main bars with hooks are difficult to insert. Therefore, the situation at the cast-in-place concrete structure is that most of the core areas of the nodes are not well done. Because the stirrups at the core position of the core area of ​​the nodes are not well done, the anchorage strength of the main bars located here is also greatly weakened.

[0042] In the factory, we divide the prefabricated units on the premise of ensuring the integrity of the node core area, and we can professionally make these node core areas. Because the prefabricated units are divided on the premise of ensuring the integrity of the node core area, during manufacturing, the same steel bars are used, but all the main bars that intersect and anchor in the node core area have become shorter. It is easy to make the stirrups at the core position into a cage, and then pass the shorter main bars through the cage. After the concrete of the prefabricated unit is poured, a node core area with integrated columns, beams and slabs or integrated walls, beams and slabs is formed. This naturally solves the problem of making the node core area of ​​the prefabricated concrete structure stronger than that of the cast-in-place concrete structure, thereby solving the key problem of improving the seismic performance of the concrete structure.

[0043] If the stirrups at the core of the node are well anchored, the anchoring of the main reinforcement at this location can be done easily. If the main reinforcement hooks at certain locations are too long, the pier anchor technology can be used to easily solve the problem. The anchoring of the main reinforcement is done better, which also solves another problem of improving the seismic performance of prefabricated concrete structures.

[0044] In summary, the three-dimensional prefabrication method can be used to create an assembled concrete structure with stronger seismic performance than cast-in-place concrete structures, and the overall seismic performance of the assembled building can also be stronger than that of a cast-in-place concrete structure building.

[0045] The third step is to assemble and connect the prefabricated units layer by layer according to the prefabricated unit numbers. This specifically includes the following steps:

[0046] Step 301, first assemble the vertical components of the corresponding layer.

[0047] Step 302: After all vertical components of the layer are assembled, the horizontal components of the layer are assembled.

[0048] Step 303, pouring concrete at the reserved joint position of the layer.

[0049] After the prefabricated units that constitute vertical components such as columns, shear walls and core tubes are assembled, connected, calibrated and verified, concrete can be poured in the reserved joints between the upper and lower layers. Alternatively, concrete may not be poured for the time being and the concrete can be poured simultaneously in the reserved joints between the prefabricated units of the vertical and horizontal components of this layer after the other prefabricated units that constitute the horizontal components of this layer are assembled, connected, calibrated and verified.

[0050] Step 304, assemble layer by layer upwards until the overall assembly is completed.

[0051] Embodiments of the support top circulation system of the present invention:

[0052] The support and top circulation system of the present invention is used to implement the above-mentioned three-dimensional prefabricated fully assembled concrete structure method, including a construction platform for the three-dimensional prefabricated concrete structure and a support and top assembly for supporting the construction platform. The specific structure of the support and top assembly is as follows: Figures 1 to 4 As shown, it comprises a hollow lower section 1 of the oil cylinder, in which a movable section 2 of the oil cylinder that can be lifted up and down is inserted, a conversion support 3 is installed on the upper end of the lower section 1 of the oil cylinder, a through hole 31 is provided in the middle of the conversion support 3 for the movable section 2 of the oil cylinder to extend out, an active support 4 is sleeved on the upper end of the movable section 2 of the oil cylinder, and a receiving groove 33 is provided in the middle of the conversion support 3 for receiving the movable support 4 and allowing the movable support 4 to be removed from the side of the conversion support 3. The upper end surface of the conversion support 3 has a first supporting surface 32, and the upper end surface of the active support 4 has a second supporting surface 41, and the first supporting surface 32 is parallel to the second supporting surface 41.

[0053] The construction platform 5 is a frame-type steel structure. The construction platform 5 of the frame-type steel structure can be used as a support for the manufacturing stage of each prefabricated unit of the horizontal component, and secondly, it can be used for the extension of the movable section 2 of the cylinder without the movable support 4 installed.

[0054] In this embodiment, the conversion support 3 includes a connection portion 34 and a side support portion 35. The connection portion 34 is made of split grooves with upper openings symmetrically provided at the front and rear ends of the cylinder, and two side support portions 35 are symmetrically arranged on the left and right sides of the connection portion 34, and the upper end surfaces of the two side support portions 35 form the first support surface 32. The lower end of the connection portion 34 is provided with a connection groove that matches the shape of the upper end of the lower section 1 of the oil cylinder and is fitted on the upper end of the lower section 1 of the oil cylinder, and the conversion support 3 is installed on the upper end of the lower section 1 of the oil cylinder through the connection portion 34.

[0055] The lower end of the movable support 4 has a groove, and the cross-sectional shape of the groove matches the cross-sectional shape of the cylinder movable section 2. The movable support 4 is sleeved on the upper end of the cylinder movable section 2 through the groove. The movable support 4 must be removed before the cylinder movable section 2 rises. The size of the through hole 31 is smaller than the size of the lower end of the movable support 4. When the cylinder movable section 2 descends to the bottom of the upper construction platform 5 and contacts the first supporting surface 32 of the conversion support 3, the conversion support 3 supports the lowered upper construction platform 5, and the movable support 4 is separated from the upper construction platform 5; when the cylinder movable section 2 descends again, the lower end of the movable support 4 contacts the top surface of the through hole 31 of the conversion support 3; when the cylinder movable section 2 continues to descend until its top is lower than the top surface of the through hole 31 of the conversion support 3, the movable support 4 is separated from the cylinder movable section 2, and the movable support 4 can be taken out by side translation.

[0056] The second supporting surface 41 is an elongated structure, and its area is larger than the area of ​​the upper end of the oil cylinder movable section 2. The width of the split groove is larger than the width of the second supporting surface 41 to form the accommodating groove 33. The through hole 31 is opened on the connecting portion 34, and the two side supporting portions 35 arranged on the outer side of the connecting portion 34 are completely staggered from the through hole 31 so as not to affect the lifting of the oil cylinder movable section 2.

[0057] In other embodiments, the connecting portion may also be an annular structure, and the side supporting portions are installed at intervals on both sides of the connecting portion. In this case, it is necessary to ensure that the distance between the supporting portions on both sides is greater than the width of the second supporting surface 41 to form the accommodating groove 33, but it is necessary to ensure that the overall conversion support 3 has sufficient bearing capacity.

[0058] When manufacturing the first layer of concrete structure, the state of the support top circulation system can be as follows: Figure 1As shown, the movable support 4 is not in the receiving groove 33 (it can also be in a state where the cylinder movable section 2 has been raised to any height above the first layer concrete structure floor slab), a first layer construction platform 51 is built on the first supporting surface 32, and a first layer concrete structure is manufactured on the first layer construction platform 51; after the first layer concrete structure is manufactured, the cylinder movable section 2 is raised to the first state (above the first layer concrete structure floor slab), the movable support 4 is installed on the top of the cylinder movable section 2, and the cylinder movable section 2 continues to be raised to the second state (in this state, the distance between the first layer concrete structure slab and the second layer concrete structure slab can be guaranteed to be equal to the second layer height), a second layer construction platform 52 is built on the second supporting surface 41, and a second layer concrete structure is manufactured on the second layer construction platform 52. The structure of the top support circulation system after the second layer construction platform 52 is built is shown in FIG. Figure 4 shown.

[0059] When manufacturing the first-layer concrete structure, the prefabricated units of the vertical components of the first-layer concrete structure, including the vertical steel bars and their threaded heads extending upward from the floor slab, must be completely manufactured according to the requirements of the detailed design of the construction drawings to ensure the integrity of the node core area of ​​the first-layer concrete structure and serve as the basis for the manufacturing of the second-layer concrete structure. The same applies to the above layers.

[0060] After the second layer of concrete structure is manufactured, the first layer of construction platform 51 and the first layer of concrete structure thereon need to be removed. The specific operation steps are as follows: first, disassemble the connecting sleeve between the second-layer concrete structure and the first-layer concrete structure, and stand them up; then continue to raise the cylinder movable section 2 to a higher position above the second state, at which time the second-layer construction platform 52 is completely separated from the first-layer concrete structure; then the first-layer concrete structure and the first-layer construction platform 51 are both removed from the conversion support 3; finally, lower the cylinder movable section 2 until the bottom of the second-layer construction platform 52 contacts the first supporting surface 32 of the conversion support 3, the conversion support 3 supports the lowered second-layer construction platform 52, and the movable support 4 is separated from the second-layer construction platform 52; when the cylinder movable section 2 is lowered again, the lower end of the movable support 4 contacts the top surface of the through hole 31 of the conversion support 3; when the cylinder movable section 2 continues to descend until its top is lower than the top surface of the through hole 31 of the conversion support 3, the movable support 4 is separated from the cylinder movable section 2, and the movable support 4 is translated and taken out, completing a working cycle, and preparing for the construction of the third-layer construction platform.

[0061] There are multiple groups of supporting top components, and the multiple groups of supporting top components jointly support the construction platform 5, such as Figure 5 and Figure 6 shown.

[0062] In a more preferred embodiment, the lower section 1 of the oil cylinder is the fixed seat part of the oil cylinder, the movable section 2 of the oil cylinder is the piston rod part of the oil cylinder, and the oil cylinder used is a two-stage oil cylinder with two stable extension distances.

[0063] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Other modifications or equivalent substitutions made to the technical solution of the present invention by ordinary technicians in this field should be included in the scope of the claims of the present invention as long as they do not depart from the spirit and scope of the technical solution of the present invention.

Claims

1. A three-dimensional prefabricated fully assembled concrete structure method, characterized in that: The method comprises the following steps: the first step is to build a support and top circulation system including a construction platform in a prefabricated plant or on flat ground; the second step is to prefabricate a concrete structure layer by layer on the construction platform; the second step specifically comprises the following steps: step 201, firstly build a first-layer concrete structure on a first-layer construction platform, and then build a second-layer concrete structure on a second-layer construction platform, and when building the second-layer concrete structure, the first-layer concrete structure is used as a reference, and the vertical steel bars of the second layer are pre-connected with the vertical steel bars of the first layer; step 202, the first-layer concrete structure is separated from the second-layer concrete structure, that is, the first-layer concrete structure is lifted up by the support and top circulation system. The second-layer construction platform is constructed, and the first-layer concrete structure together with the first-layer construction platform is removed from the support top circulation system; step 203, the second-layer construction platform including the second-layer concrete structure is lowered to the position of the original first-layer construction platform through the support top circulation system and the support is replaced; step 204, the upper section of the support top circulation system rises one layer again, and the third-layer construction platform is built above the lowered second-layer concrete structure, and the third-layer concrete structure is built on the third-layer construction platform based on the second-layer concrete structure; step 205, the above steps are repeated to remove the next-layer concrete structure and the next-layer construction platform, and lower The process of building a higher construction platform and a higher concrete structure upwards based on the upper construction platform including the upper concrete structure, until the highest N-th concrete structure is built; in the second step, each layer of concrete structure includes a plurality of prefabricated units split according to the core area of ​​the node; wherein, the support top circulation system includes a construction platform and a support top assembly for supporting the construction platform, the support top assembly includes a hollow lower section of the oil cylinder, in which a movable section of the oil cylinder that can be raised and lowered is inserted in the air, a movable support is installed on the top of the movable section of the oil cylinder, and a conversion support is installed on the top of the lower section of the oil cylinder, and the conversion support has an oil supply The through hole through which the cylinder movable section extends out, the lower end of the movable support has a groove, the cross-sectional shape of the groove is consistent with the cross-sectional shape of the cylinder movable section, the movable support can be detachably mounted on the top of the cylinder movable section through the groove, the through hole size is smaller than the lower end size of the movable support, the middle part of the conversion support is provided with a accommodating groove for accommodating the movable support and the movable support can be taken out from the side, the upper end surface of the conversion support has a first supporting surface, the upper end surface of the movable support has a second supporting surface, the first supporting surface is parallel to the second supporting surface, and an avoidance hole is provided on the construction platform for the cylinder movable section without the movable support installed to pass through.

2. The three-dimensional prefabricated fully assembled concrete structure method according to claim 1, characterized in that: The method further includes a third step of transporting the prefabricated units to the engineering assembly site and assembling and connecting them layer by layer in sequence, specifically including the following steps: Step 301, assembling the prefabricated units constituting the vertical components of the first-layer concrete structure; Step 302, after all the vertical components of the first-layer concrete structure are assembled, assembling the prefabricated units constituting the horizontal components of the first-layer concrete structure; Step 303, pouring concrete at the reserved joint position of the first layer to complete the assembly of the first-layer concrete structure; Step 304, assembling layer by layer upwards until the overall assembly of the constructed house is completed.

3. The three-dimensional prefabricated fully assembled concrete structure method according to claim 1, characterized in that: In the second step, before the concrete structure of the corresponding layer is dismantled, the prefabricated units constituting the layer are numbered.

4. The three-dimensional prefabricated fully assembled concrete structure method according to claim 1, characterized in that: There is a reserved gap between two adjacent prefabricated units for disassembly and assembly.

5. The three-dimensional prefabricated fully assembled concrete structure method according to claim 1, characterized in that: The conversion support includes a connecting part and a side supporting part. The conversion support is installed on the top of the lower section of the cylinder through the connecting part. Two side supporting parts are arranged at intervals. The two side supporting parts are symmetrically arranged on the left and right sides of the connecting part. The upper end surfaces of the two side supporting parts form the first supporting surface. The through hole is arranged on the connecting part. The two side supporting parts are completely staggered from the through hole so as not to affect the lifting and lowering of the movable section of the cylinder.

6. The three-dimensional prefabricated fully assembled concrete structure method according to claim 1, characterized in that: The second supporting surface is an elongated structure, and the interval between the two side supporting portions is greater than the width of the second supporting surface to form the accommodating groove.

7. The three-dimensional prefabricated fully assembled concrete structure method according to claim 5, characterized in that: The connecting portion comprises a cylindrical structure with split grooves symmetrically provided on the front and rear sides, the upper end of the split groove is open, and the width of the split groove is greater than the width of the second supporting surface to form the accommodating groove.

8. The three-dimensional prefabricated fully assembled concrete structure method according to claim 5, characterized in that: The lower end of the connecting part is provided with a connecting groove which matches the shape of the top end of the lower section of the oil cylinder and is sleeved on the top end of the lower section of the oil cylinder.

9. The three-dimensional prefabricated fully assembled concrete structure method according to any one of claims 5 to 8, characterized in that: The lower section of the oil cylinder is the fixed part of the oil cylinder, the movable section of the oil cylinder is the piston rod part of the oil cylinder, and the top support components are arranged in multiple groups.